Who does what and when?
description
Transcript of Who does what and when?
Who does what and Who does what and when?when?
Mary RowlattMary Rowlatt
MDR PartnersMDR Partners
EDLocal – How are we going to do EDLocal – How are we going to do this?this?
Get all our stuff into Europeana?Get all our stuff into Europeana?
You might be feeling a little lostYou might be feeling a little lost
confused, or even a bit worried ..confused, or even a bit worried ..
But don’t worryBut don’t worry
Because we have, what every good project needs ….
a cunning plan!a cunning plan!
Project structure & phasesProject structure & phases
2 x operation of the project2 x operation of the project Project management & co-ordination (WP1)Project management & co-ordination (WP1) Evaluation & progress monitoring (WP6)Evaluation & progress monitoring (WP6)
1 x publicity & operating/business model1 x publicity & operating/business model Dissemination and awareness raising (WP5)Dissemination and awareness raising (WP5)
1 x preparatory1 x preparatory Metadata survey & content analysis (WP1)Metadata survey & content analysis (WP1)
2 x doing stuff with content2 x doing stuff with content Content harvesting & aggregation (WP3)Content harvesting & aggregation (WP3) Implementing Europeana standards & tools (WP4)Implementing Europeana standards & tools (WP4)
WP/task M
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
WP1 Project managemen and co-ordination
M1 M2 M3 M4 M5 M6
T1 Activity planning/ mgmnt
T2 Management of the GA
T3 Quality Assurance delivb
WP 2 Metadata survey and content analysis
M1 M2/3
T1 Partner survey metadata/voc use
T2 Optimising repositories nwork
T3 Identifying thematic content
WP 3 Content harvesting and aggregation
M1 M2 M3 M4 M5
T1 Implementing central environmt
T2 Test harvesting
T3 Building and testing services
T4 Moving to integrated access
WP/task M 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
WP 4 ImplementingEuropeana standards and tools
M1 M2 M3 M4
T1 Briefing the technical partners
T2 Support mechanisms
T3 Multi-regional training wkshops
T4 Implementation
WP 5 Dissemination and awareness raising
M1 M2 M3 M4 M5
T1 EDLocal web environment
T2 Framework for joining Europeana
T3 National meetings
T4 Digitisation best practice
WP 6 Evaluation and progress monitoring
M1 M2 M3 M4 M5 M6
T1 Performance monitoring
T2 Impact study
Doing stuff: planning & analysisDoing stuff: planning & analysis
CT to plan + instigate survey of metadata schema / vocabulariesWP2 Task 1.1Jul – Sept 08
||Jun 08 Jan 09 May 09 ||
Content partners to completeWP2 Task 1.2Oct 08 – Jan 09
CT to lead on analysis + recommendations on metadata + terminology WP2 Task 1.3Feb 09
EDL, MDR to plan work to set up repositories in each countryWP2 Task 2.1Sep – Oct 08
EDL, MDR to assess suitable approaches to aggregation in each countryWP2 Task 2.2Sept 08 – May 09
CT to form working group >6 content partners for thematic analysis of content WP2 Task 3.1Nov 08 – Mar 09
Working group to use + add to content list in proposal to prioritise themes or topics where content neededWP2 Task 3.2Nov 08 – May 09
M1 Nov M2 M3 D21. D2.2 D2.3 D2.4 May
KO PMB PMG Programme Conference Nov
Tech Workshop WP4 Jan
Training Feb, Apr, Jun PMB, PMG, TR, Concertation May
Doing stuff: training & supportDoing stuff: training & support
Content partners + Asplan, EEA draw up local implementation plansWP4 Task 4.1Jan 09 – Jan 10
|| Jan 09 Nov 10 ||
Asplan, EEA produce online technical support + helpdeskWP4 Task 2.2, 2.3Jan 09 – May 09 ->
Asplan, EEA,MDR to provide set of 4 multi-regional training workshops (harvesting, repositories, metadata mapping etc)WP4 Tasks 3.1 Feb 09 – Aug 09
Asplan, EEA,MDR to provide set of 4 multi-regional training workshops (refresher, vocabularies, SKOS, Europeana developments etc)WP4 Tasks 3.2Jan 10 – May 10
Asplan, EEA make up to 10 problem solving visits WP4 Task 2.4Jun 09 – Nov 10
Doing stuff: set-up repositoriesDoing stuff: set-up repositories
Asplan, EEA provide guidance on selection repository software & toolsWP3 Task 2.1Nov 08 – Feb 09
||Nov 08 Jan 09 Jan 11 ||
Asplan, EEA review tools for repository installation & metadata conversionWP4 Task 2.1Jan 09 – Feb 09
EDL, Asplan, EEA Knowledge transfer workshop + regular EDL technical info updates startWP4 Tasks 1.1, 1.2Jan 09
Content partners to plan & install repositories. MDR maintain registry Jan 10 onwardsWP3 Task 2.3, 2.4 Mar 09 – Jan 10
EDL to carry out interoperability tests on each repository or aggregation. Asplan, EEA to analyse results and report back to EDL on action neededWP4 Task 4.5 Nov 10 - Jan 11
Doing stuff: harvesting + metadataDoing stuff: harvesting + metadata
Selected content partners test the Europeana ingestion tool + roll out to partnersWP3 Task 2.2Nov 08 – Mar 09
EDL + 3 content partners with existing repositories will test harvesting of metadataWP3 Task 1.2June 09 – Nov 09
Content partners to map their metadata schemas to Europeana schema + import converted metadata to their repository using Europeana toolsWP4 Task 4.2, 4.3Sept 09 – Nov 10
EDL implement initial test environment WP3 Task 1.1May 09
||Nov 08 Jan 09 Nov 10 ||
Content providers + Asplan, EEA, EDL to prepare local vocabularies for SKOS magicWP4 Task 4.4Jan 10 – Oct 10
Doing stuff: EDL to EuropeanaDoing stuff: EDL to Europeana
EDL to produce and test with content providers technical guidance for contribution of content to EuropeanaWP3 Task 2.6 Aug 09 - Dec 09
|| Jun 09 Mar 11 ||
CT, Asplan, EEA + EDL to identify, adapt & document best practice in usability testingWP3 Task 3.2Nov 09- Mar 10
EDL to implement services in test environment to enable end-users to access EDLocal contentWP3 Task 3.1June 09 – Dec 09
CT, Asplan, EEA + EDL to test Europeana interface + tools identified for the projectWP3 Task 3.2Sept 10 – Jan 11
EDL to modify Europeana services following testingWP3 Task 3.2Feb 11 – Mar 11
EDL to test + migrate EDLocal content to Europeana WP3 Task 4.1Feb 11 – Mar 11
Publicity and developing Publicity and developing operation/business model: WP5operation/business model: WP5
Content partners + MDR to organise National Meetings (1 each Content partners + MDR to organise National Meetings (1 each country) between May 10 and April 11country) between May 10 and April 11
MDR to collate and synthesise the outcomes of these meetings to MDR to collate and synthesise the outcomes of these meetings to asses the situation and identify any barriers to continued expansion asses the situation and identify any barriers to continued expansion of content providers to Europeana by May 11of content providers to Europeana by May 11
MDR to maintain a register of content providers and aggregators MDR to maintain a register of content providers and aggregators who want to join Europeana and assist EDL in prioritising and who want to join Europeana and assist EDL in prioritising and managing applicationsmanaging applications
EDLocal website and newsletter to advocate further digitisation and EDLocal website and newsletter to advocate further digitisation and point to best practicepoint to best practice
MDR to monitor best practice and produce guidance by April 10 in MDR to monitor best practice and produce guidance by April 10 in time for 1time for 1stst National Meeting National Meeting
Publicity and developing Publicity and developing operation/business model: WP5operation/business model: WP5
MDR to set up EDLocal website, news, distribution MDR to set up EDLocal website, news, distribution facilities and content management system by Jul 08facilities and content management system by Jul 08
MDR to lead development of very wide stakeholder MDR to lead development of very wide stakeholder database (1000 people by Jul 08, 5000+ by May 11)database (1000 people by Jul 08, 5000+ by May 11)
MDR to produce EDLocal Newsletter 3 times a yearMDR to produce EDLocal Newsletter 3 times a year MDR to lead discussions with EDL Foundation to MDR to lead discussions with EDL Foundation to
establish easy procedures for new content providers to establish easy procedures for new content providers to joinjoin
EDL consortium to agree ongoing basis for participation EDL consortium to agree ongoing basis for participation in Europeana governance proceduresin Europeana governance procedures
Content partners + MDR to agree framework and Content partners + MDR to agree framework and processes for aggregation in their countryprocesses for aggregation in their country
Evaluation & progress monitoringEvaluation & progress monitoring(Operation of the project: WP6)(Operation of the project: WP6)
ABM to convene and lead a Performance Monitoring ABM to convene and lead a Performance Monitoring Working Group (Sogn og Fjordane, MDR, EDL, technical Working Group (Sogn og Fjordane, MDR, EDL, technical partner, 3+ content partners). Sept 09 –partner, 3+ content partners). Sept 09 –
Working group to design a schema of targets and Working group to design a schema of targets and measurement mechanisms by Oct 09. measurement mechanisms by Oct 09.
Working Group to establish procedures for monitoring Working Group to establish procedures for monitoring number of content items harvested from EDLocal number of content items harvested from EDLocal sources – to assist in meeting our targetssources – to assist in meeting our targets
MDR to monitor and report on overall progress and MDR to monitor and report on overall progress and initiate remedial actions as requiredinitiate remedial actions as required
ABM, MDR to design and conduct impact survey of ABM, MDR to design and conduct impact survey of 50%+ of content providers/aggregators (Dec 10 – Mar 50%+ of content providers/aggregators (Dec 10 – Mar 11)11)
Project managementProject management(Operation of the project: WP1)(Operation of the project: WP1)
MDR + Sogn og Fjordane MDR + Sogn og Fjordane Set up communication + distribution channelsSet up communication + distribution channels Organise regular Project Management Board MeetingsOrganise regular Project Management Board Meetings Organise kick-off and mid-term meetingsOrganise kick-off and mid-term meetings Provide periodic management and progress reports to Provide periodic management and progress reports to
the Commissionthe Commission Manage the budget, submit cost claims, pay partnersManage the budget, submit cost claims, pay partners Compile final public reportCompile final public report Quality assure deliverablesQuality assure deliverables Monitor and chase to keep to deadlinesMonitor and chase to keep to deadlines
Next 6 months: content partnersNext 6 months: content partners CT to plan + instigate survey of metadata schema / vocabularies Jul – Sept
08 Content partners to complete, Oct 08 – Jan 09 CT to lead on analysis + recommendations on metadata + terminology. Feb
09 EDL, MDR to plan work to set up repositories in each country Sept – Oct 08 EDL, MDR to assess suitable approaches to aggregation in each country.
Sept 08 – May 09 CT to form working group >6 content partners for thematic analysis of
content Nov 08 – Mar 09 Working group to use + add to content list in proposal to prioritise themes
or topics where content needed. Nov 08 – May 09 Selected content partners test the Europeana ingestion tool + roll out to
partners. Nov 08 – Mar 09 Asplan, EEA,MDR to provide set of 4 multi-regional training workshops
(harvesting, repositories, metadata mapping etc). Feb 09 – Aug 09 Content partners + Asplan, EEA draw up local implementation plans. Jan
09 – Jan 10