Where next? Gordon Shearer BWEA Board Member for Offshore Wind.
-
Upload
imogene-boone -
Category
Documents
-
view
212 -
download
0
Transcript of Where next? Gordon Shearer BWEA Board Member for Offshore Wind.
Where next?
Gordon Shearer
BWEA Board Member for Offshore Wind
4
Where are we now?4 MW existing
18 developments
Each 60-108MW
70% success rate
Construction 2003-6
1000 MW by 2006
Moving forward?
D.T.I.CrownEstate
North Pole South Pole
Industry Wish List
To be awarded additional sites
To spread development risks
To select partners with complementary skills
To optimise site locations
To co-operate as an industry in reducing unit costs
The Issues
New sites must not adversely affect existing proposals
There is a need for an overview of developments
The award of sites must be fair and equitable
The awarded sites should be economically efficient
The Renewables’ Obligation creates an imperative for action
The Possibilities (Wind)
The Possibilities (Grid)
Copyright NGC
A Vision?
Round 1=1000MW
A 3000MW wind farmOff Lincolnshire/ Norfolk
• Site only 30km by 10km
• 20 participating companies?
• Radar impact – MOD/NATs
• Substantial grid reinforcement
• HVDC line to Walpole
• Less than 20m waterdepth
• 20 km offshore
• No portfolio spread
The Probable?
Round 1
>500MW
• 3 or 4 company JV Within 30 kms to shore• Less than 25m waterdepth• HVDC or AC line to grid transmission system
Characteristics
<200MW
• Single company, small JV• Within 15kms to shore• Less than 20m waterdepth• 33/132kV to distribution network
A Timescale2007 200920082006500-1000MW construction
2005 Contract negotiations & procurement
2004 Contract tendering
2002
Now OctSite security
Contractpreparations
2003
12 month wind data
Seismic acquisitionSite investigationConceptual designPublic consultationPreparation of EIA
2004 ES submission and determination
The Target
4000 MW by 2010
4 million people, 1.4 million households
An early startA manageable process