When Working Near An Energized Switchgear Do Not Wear Nylon, Polyester, Polypropylene And Acetate
-
Upload
nirmala-last -
Category
Business
-
view
1.692 -
download
1
description
Transcript of When Working Near An Energized Switchgear Do Not Wear Nylon, Polyester, Polypropylene And Acetate
Arc Flash ExposureNESC Rules related to Arc Flash
NFPA 70E Rulesand other Standards
Overview• Basic discussion about the ARC FLASH
• Hazard Risk
• Questions
• Standards and Regulations
• NESC,NFPA 70E, IEEE Standard 1584
• Questions
• Arc Flash Study
• Calculations
• Relay Coordination
• Questions
Megaway, Inc.Consulting Engineers
Arc Flash
•What is it?
•What is the Source?
•Hazard Risk Categories
Arc Flash
•Arc flash is an explosion with extremely high temperature, toxic and vaporized metals
•The worst case is when a bolted fault occurs.
•Hazard risk exists at all times, when working near the exposed and energized equipment
ARC FLASH
•When the normal flow of current in a conductor is disrupted, it takes a short cut to release its energy
•The short path could be between the conductors, at the equipment or to ground, etc.
•The released energy flashes an arc at the point of contact which is extremely hot and toxic
Arcing Fault• Electrical shorts occurs due to:
– Accidents
– Touching the energized bus or conductors
– Insulation breakdown of the equipment, bus conductors, etc.
– Once the accident happens more events will follow:
Arc blast due to expanding gases
Arc plasma or Heat
Arc Flash Characteristics•Amount of heat from an arc depends
on the Voltage across it and the arc current
•Power in arc ( V arc x I arc) which is radiated out and multiplied by time as incident Energy
•The arc produces expanding gases by heat transfer such as radiant and convection
•Gasses heat up the contact surfaces
•Burn, melt and vaporizes the contacts
Arc Resistance
Arc resistance is highly variable and changes non-linearly with the arc current duration each cycle.
Arc plasma at higher impedance conducts current.
Electromagnetic Radiation
• Produced by arc flash, is highly variable
• The bandwidth Includes:
• Radio waves
• Microwave
– Infrared( IR )
– Visible, UV and X-Ray
Arc Energy• Measured in Calories
• 1 cal. = 4.1868 Joules
• 1Joule = 1 watt-second
• 1Kilowat-hour= 3600000 Joules
• Exposure > 2Cal/cm-squ require PPE, NESC
• Arc energy ( I squared) x t, calculated based on the fault current magnitude and its duration in cycles
Hazard Risk
• Risk exists during the fault
• When it takes a longer time to clear the fault
• When the prohibited areas are violated
• Boundaries
• Insulations defects
• Old equipment
• Equipment designed for lower SC withstand capability than the actual system faults
Approach Boundaries
• NFPA 70E annex C Sketch
FLASH PROTECTION BOUNDARY
LIMITED APPROACH BOUNDARY
LIMITED SPACE
RESTRICTED APPROACH BOUNDARY
RESTRICTED SPACE
PROHIBITED APPROACH BOUNDARY
PROHIBITED SPACE
EXPOSED CONDUCTOR
Phase to phase
voltage
Exposed Movable
Conductor
Exposed fixed circuit part
Restricted approach boundary
Prohibited approach boundary
<50 Not specified Not specified Not specified Not specified
50-300 10’ 3’ - 6” Avoid contact Avoid contact
301-750 10’ 3’ - 6” 1’ 1”
751-15kV 10’ 5’ 2’ - 2” 7”
15.1-36kV 10’ 6’ 2’ - 7” 10”
36.1- 46kV 10’ 8’ 2’ - 9” 1’ - 5”
46.1- 72.5kV 10’ 8’ 3’ - 2” 2’ - 1”
72.6-121kV 10’ – 8” 8’ 3’ - 3” 2’ - 8”
138 – 145kV 11’ 10’ 3’ - 7” 3’ - 1”
161 – 169kV 11’ – 8” 11’ – 8” 4’ 3’ - 6”
230 – 242kV 13’ 13’ 5’ - 3” 4’ - 9”
Table 130.2(C) Limited, restricted, and prohibited approach boundary
Key Concepts• Open Arc
• Non Enclosed areas, energy is radiated equally
• Overhead lines
• Directed Arc
• Arc in a box, energy is radiated and reflected
• Switchgear enclosure with the door open
• Radiant Arc
• Light released by an arc ( radiant Energy)
• Blast Energy
• Energy of moving objects due to the arcing faults, 100s of MPH speed , penetrate human body
RISK ANALYSIS GOAL
•To determine the Incident Energy for Electrical path to the equipment
•To examine boundaries and distances
•To determine level of Personal Protective Equipment
•To provide Labeling, training & guidelines
• To minimize injury and death
•To minimize insurance cost & legal issues
Hazard Risk Categories
Flash Hazard Risk Category
Range of Calculated
Incident Energy
Min. PPE Rating
Clothing Required
0 0-1.2 cal/cm2 N/A 4.5-14 oz/yd2 untreated cotton
1 1.2- 4 cal/cm2 4 cal/cm2 FR shirt and pants
2 4- 8 cal/cm2 8 cal/cm2 Cotton underclothing plus FR shirt and pants
3 8- 25 cal/cm2 25 cal/cm2 Cotton underclothing plus FR shirt, pants, overalls or equivalent
4 25- 40 cal/cm2 40 cal/cm2
Cotton underclothing plus FR shirt, pants, plus double layer switching
coat and pants or equiv
FR=Fire resistance fabric
Standards & Regulations
•Five separate industry standards focus on preventing arc flash incidents:
•NESC (National Electric Safety Code)
•NFPA70-2005
•NFPA70E-2004
• IEEE Standard 1584
•OSHA 29 code of Federal Regulations
NESC (National Electric Safety Code)
• Section 41 Supply & Communications systems
• Rule 410 A3, employees to wear clothing with a correct arc rating
• Tables 410-1 and 410-2 to be used for quick reference to use PPE
• Arc hazard Analysis must be performed
• When working near an energized switchgear do not wear Nylon, Polyester, polypropylene and Acetate
NESC Section 41Supply & Communication Rules for Employers
• General duties of Employers
1. Inform employees about all communication equipments or electrical supply equipment
2. Training has to be provided to all employees who work on or near the energized facilities.
3. Ensure that potential exposure has been assessed to an electric arc
4. (Effective as of Jan. 1, 2009)
– Exposure > 2 cal/cm2
PPE required .
NESC Section 41Supply & Communication Rules for Employers
• Rule410A, general requirements
• Employer shall perform an assessment on exposure to electric arc
• Rule 410B Emergency procedures and first aid rules
• Rule 410c responsibility
• A designated person shall be in charge
NESC RULE 410 A3• Applicable work rules and engineering
controls for secondary systems below 1000 V is required to limit exposure.
– Clothing system with Min. effective arc rating of 4 cal/cm2 can be used instead of performing of an arc hazard analysis.
• Using multiple layers clothing instead of one layer can be used. The outer layer should have flame resistant material and inner layer of normal wear.
Table 410-1 NESC • Calculations for Energy levels based on Fault
currents and Max. clearing time for voltages 1-46KV
•Based on open air phase–ground arcs
•Based on 15” separation distance from the arc
• Arc Gaps used for this Table calculations:
– 2” for 1-15KV, 4” for 15.1- 25KV
– 6” for 25.1-36KV, 9” for 36.1-46KV
Clothing Systems
Phase- to Phase voltage (kV)
Fault current (KA)
4-cal systemMaximum
clearing time(cycles)
8-cal systemMaximum
clearing time (cycles)
12- cal systemMaximum
Clearing time (cycles)
1 to 15 5 46.5 93.0 139.5
10 18.0 36.1 54.1
15 10.0 20.1 30.1
20 6.5 13.0 19.5
15.1 to 25 5 27.6 55.2 82.8
10 11.4 22.7 34.1
15 6.6 13.2 19.8
20 4.4 8.8 13.2
25.1 to 36 5 20.9 41.7 62.6
Table 410-1
Clothing Systems
Phase- to Phase voltage (kV)
Fault current (KA)
4-cal systemMaximum
clearing time(cycles)
8-cal systemMaximum
clearing time (cycles)
12- cal systemMaximum
Clearing time (cycles)
10 8.8 17.6 26.5
15 5.2 10.4 15.7
20 3.5 7.1 10.6
36.1 to 46 5 16.2 32.4 48.6
10 7.0 13.9 20.9
15 4.3 8.5 12.8
20 3.0 6.1 0.1
Table 410-1
Table 410-2 NESCLive –Line Tool Work
Clothing•Calculations for Energy levels based on
Fault currents and Max. clearing time for voltages 46.1-up to 800KV
– Arc gap is calculated by using Phase – Ground Voltage of system divided by 10
•Dielectric of air is taken at 10 KV per inch
•Distance from arc is calculated based on minimum approach distance in table 441-2
• Refer to table 441-2
Live – Line Tool Work Clothing
Phase- to Phase voltage
(kV)
Fault current
(KA)
4-cal systemMaximum
clearing time(cycles)
8-cal system
Maximum clearing
time (cycles)
12- cal system
MaximumClearing time
(cycles)
46.1 to 72.5 20 8.5 17.0 25.5
30 5.3 10.5 15.8
40 3.7 7.3 11.0
50 2.8 5.5 8.3
72.6 to 121 20 8.2 16.5 24.7
30 4.7 9.4 14.1
40 3.1 6.2 9.3
Table 410-2
Phase- to Phase voltage
(kV)
Fault current
(KA)
4-cal systemMaximum
clearing time(cycles)
8-cal system
Maximum clearing
time (cycles)
12- cal system
MaximumClearing time
(cycles)
50 2.6 5.3 7.9
161 to 169 20 9.3 18.6 27.9
30 5.7 11.5 17.2
40 4.0 8.0 12.0
50 3.0 6.0 9.0
230 to 242 20 10.4 20.9 31.3
30 6.4 12.9 19.3
Table 410-2
Live – Line Tool Work Clothing
Phase- to Phase voltage
(kV)
Fault current
(KA)
4-cal systemMaximum
clearing time(cycles)
8-cal system
Maximum clearing
time (cycles)
12- cal system
MaximumClearing time
(cycles)
30 6.4 12.9 19.3
40 4.5 9.0 13.5
50 3.4 6.8 10.1
345 to 362 20 22.6 45.3 67.9
30 14.0 28.1 42.1
40 9.8 19.6 29.4
50 7.4 14.7 22.1
Table 410-2
Live – Line Tool Work Clothing
Phase- to Phase voltage (kV)
Fault current (KA)
4-cal systemMaximum
clearing time(cycles)
8-cal systemMaximum
clearing time (cycles)
12- cal systemMaximum
Clearing time (cycles)
500 to 550 20 18.9 37.8 56.7
30 11.7 23.3 35.0
40 8.1 16.3 24.4
50 6.1 12.2 18.3
765 t0 800 20 43.6 87.3 130.9
30 27.0 53.9 80.9
40 18.9 37.8 57.7
50 14.2 28.4 42.6
Table 410-2
Live – Line Tool Work Clothing
Protective Methods and Devices
• Rule411A methods :
• Access for authorized personnel only
• Diagrams and documents
• Instructions and guide lines for employees
NESC Rules continued
• Rule411B Devices & equipment
• Adequate supply
• First aid
• All protective devices shall conform with applicable standards
• Grounding materials & devices
•Devices and equipment
• Voltage detection devices/meters & more
•Signs and tags for employee safety
• With the provisions of ANSI Z535.1-2006 through ANSI Z535.5-2006, the safety signs and tags are required.
Protective Methods and Devices
NESC Rules continued
• Rule411C Inspection and testing of protective devices
• All PPE and tools etc
• shall be tested, inspected regularly prior to any usage
• Rule 411F Fall Protection
• Employers shall maintain an effective program for training
NESC SECTION 42 General Rules for Employees
• Rule420B qualification of Employees
• Rule420C Safeguarding oneself & others
• Rule420I Clothing ,suitable for the assigned work
• Rule420Q Communication Antennas
• Range 3KHZ-300GHZ
• Workers shall not be exposed to radiation levels set by regulatory authority Jurisdiction.
– Refer to FCC Bulletin #65, IEEE C95.1, OSHA29
NESC SECTION 43 Additional Rules for Communications
Employees
• Approach to energized conductors or parts:
• conductive object should not be brought within any distance of an energized part (see table 431-1)
• Supply lines should be de-energized and grounded when voltage is involved.
NESC SECTION 43 Additional Rules for Communications
Employees
• Joint-use structures:
• Certain safe distances should be taken into consideration according to table 431-1 while working on poles or structures.
– This rule does not apply on voltages of 140 kV and below, when installing a rigid fixed barriers between the supply and communication facilities, when attached above electric supply conductors.
NESC SECTION 43 Additional Rules for Communications
Employees
• Joint –use manhole, Metallic or semi conductive sheath should be used when working on buried cable or on cable in manholes.
• While working in a manhole a member of the personnel should be on hand at the surface to render any assistance required.
NESC SECTION 44 Additional Rules for Supply
Employees
• Minimum approach distances should be followed on chart 441-1 when voltages of 301 V to 72.5 kV is involved.
• Rubber insulated gloves must be worn when personnel are within reach or minimum approach distances of the above voltages.
NFPA 70E
• All protective equipment must meet the requirements as shown in the latest edition of NFPA 70E.
• Protective equipment, sufficient for protection against the potential electrical flash, required for every part of the body.
• Selection of the required thermal rated PPE depends on the incident energy level at the point of work.
NFPA 70E PPE
Employees should be trained in the use of proper protective equipment as well as using proper wearing cloths.
•Employees must wear and be trained in the use of appropriate protective equipment for the possible electrical hazards they may face.
•PPE include hard hat, face shield, flame resistant neck protection, ear protectors, insulated rubber gloves with leather protectors, and insulated leather footwear.
NFPA70E Hazard Risk Categories
Flash Hazard Risk Category
Range of Calculated
Incident Energy
Min. PPE Rating
Clothing Required
0 0-1.2 cal/cm2 N/A 4.5-14 oz/yd2 untreated cotton
1 1.2+ to 4 cal/cm2 4 cal/cm2 FR shirt and pants
2 4+ to 8 cal/cm2 8 cal/cm2 Cotton underclothing plus FR shirt and pants
3 8+ to 25 cal/cm2 25 cal/cm2 Cotton underclothing plus FR shirt, pants, overalls or equivalent
4 25+ to 40 cal/cm2 40 cal/cm2
Cotton underclothing plus FR shirt, pants, plus double layer switching
coat and pants or equivFR=Fire resistance fabric
PPE StandardsHead Protection ANSI Z89.1,1997
Eye and Face ANSI Z87.1,1989Gloves ASTM D 120-95Sleeves ASTM D 1051-95
Gloves and Sleeves
ASTM F 496-97
Leather Protectors ASTM 696-97Footwear ASTM 1117-93
Visual Inspection ASTM F 1236-96Apparel ASTM F 1506-00
Rainwear ASTM F 1891-01
Standards for Other Protective Equipment
LaddersANSI AA14.1, A14.3, A14.4,
A14,5Safety signs & tags ANSI Z535
Blankets ASTM D 1048 & F 479Covers ASTM D 1049
Line Hoses & covers ASTM D 1050 & F478Fiber Glass tools ASTM F711Plastic Guards ASTM F712
Temporary Grounding
ASTM F 855
Insulated Hand Tools ASTM F 1505
Signs
Safety Video
• This is a graphic video. Viewer discretion is advised.
QuickTime™ and a decompressor
are needed to see this picture.
Break
Arc Flash Study• Involves four Major Tasks
•Existing System & Data Gathering
•Engineering analysis of Data
•Personal Protection Equipment procurement and labeling
•Training program
Existing System & Data Gathering
•Final set of drawings
•Field verify all drawings and system configurations
•Check all equipment name plates
•Prepare an accurate data ready for modeling and software inputs
Engineering Analysis of Data
•Perform Short Circuit Analysis and calculations for each bus and equipment
•Calculate for maximum fault
•Perform arc flash energy calculations using two approaches, IEEE 1584 & NFPA70E
• Incident Energy
• Flash Boundary
• Determine Working Distance
Relay Setting and Coordination
•Perform relay settings and coordination to include all protective devices for different system configurations
• Normal configuration settings
• Alternate settings for temporary or emergency configurations
Data Collection
• Fault Current Limits
• Information of Physical Structure
• Bus Isolation
• Grounding
• Collect all System Impedance data
Calculations
• One line diagram of a switchgear
• Use computer, typical software for fault current calc.
• Most programs provide a complete and comprehensive calculations for all variable items ( SC, Arcing Current , Incident Energy, boundaries PPE materials etc.)
System Fault Currents
IEEE 1584• Incident Energy :
• lg En = K1 + K2 + 1.081lgIa + 0.0011G (1)
• En = J/cm2
• Distance from the arc = 610 mm.
• Arcing time = 0.2 sec.K1 = -0.792 for open configurations, -0.555 for box configurations / enclosed
• K2 = 0 for ungrounded and high resistance grounded systems, -0.113 for grounded G = gap between conductors in mm.Ia = Arcing current in kA.
IEEE STANDARD 1584
• Incident Energy Calculation
System K1open K1box
K2open K2box
Ia
1000 V or lover -0.792 -0.555 0 -0.113Arcing current
1kV up 15 kV -0.153 -0.097 0 0Arcing current
IEEE 1584• For 1000V and lower systems:
lgIa = K + 0.662lgIbf + 0.0966V + 0.000526 G + 0.5588VlgIbf - 0.00304GlgIbf (2a)
• lg - is logarithm base 10 (log10).Ia - arcing current in kA.En - normalized incident energy in J/cm2
• K – is -0.153 for open arc, -0.097 for box configurations.Ibf - bolted fault current in kA symmetrical rms.V - system voltage in kV.G - gap between conductors in millimeters.
IEEE 1584• voltage ranging from 1 up to 15kV:
• lgIa = 0.00402 + 0.983lgIbf (2b)
• E = 4.184CfEn(t / 0.2)(610x/Dx) (3)
• E - incident energy exposure in J/cm2.
• Cf - calculation factor equal to 1.0 for voltages >1 kV, 1.5 for voltages <1 kV.
• En - normalized incident energy in J/cm2 t - arcing time in seconds.D - distance from possible arcing point to workers in mmx - distance exponent.
IEEE 1584• Flash Protection Boundary equation :
DB = [4.184 * Cf * En * (t / 0.2) * (610x/EB)]1/x (4)
• DB - distance of the boundary from the arc point in mm.Cf - calculation factor equal to 1.0 for voltages >1 kV, 1.5 for voltages <1 kV.En - normalized incident energy in J/cm2
• EB - incident energy in J/cm2 at the boundary distance.Ibf - bolted fault current for three phase faults in kA symmetrical rms.t - arcing time in seconds.x - Distance exponent.
• EB is usually set at 5 J/cm2 (1.2 cal/cm2 ) for bare skin, or at the rating of proposed PPE.
IEEE1584 Bus Gaps • Typical bus gaps are shown below:
•Open Air 10 – 40 mm
•Low-voltage switchgear 32mm
•15kV switchgear 152mm
•5kV switchgear 104mm
•Low-voltage MCC,PNL 25 mm
•Cable 13 mm
Working Distance
• Typical working distance is the sum of the distances between the worker standing in front of the equipment, and from the front of the equipment to the potential arc source inside the equipment.
IEEE1584 Working Distances• Classes of equipment:
• LV Switchgear 610 mm
• 15KV/5KV switchgear 910 mm
• LV MCC & PNL B 455 mm
• Cable 455 mm
1”=25.4mm
Personal Protective Equipment (PPE)
•Use the calculations results to apply on the given tables to assign type of clothing for the given example
•Gloves
•Tools
•Face Protection
•Glasses
•Clothing
Show photos of PPE
Grounding Type
• Two grounding classes are applied in the IEEE 1584 procedure, as follows:
• Ungrounded systems, which includes, high-resistance grounding.
• Solidly grounded systems.
Solidly Grounded System
• X0/X1< 3 and R0/X1 <1
• Low impedance return path for Fault current during a L-G fault.
• Protective devices will clear the fault faster
• Stabilizes the line to ground voltage during the normal and abnormal (lightning) conditions
• Higher ground faults, higher incident energy due to arc flash
Ungrounded System
• Incident Energy is usually higher
• During the fault large over voltage occurs between the un-faulted phases and ground which can cause high transients
• Increases L-L and L-G voltages.
High Resistance Grounding Systems
• Intentional resistance between neutral and ground.
• R is usually 1/3 of coupling capacitive reactance between the phases and ground
• Same advantages as ungrounded systems
Training
• According to Rule 410 A 2
• Training shall include applicable work rules to section 41 NESC
• Re-training until the employee demonstrated complete proficiency
Relay Settings & Coordination
• Protection Engineers have a main objective to reduce the effects of electrical disturbances
• This obviously includes protecting the safety of personnel.
• Lately there has been more emphasis on arc flash events.
• The need to protect against fatal levels of heat, radiation, blasts producing shrapnel and deafening sound waves.
• The energy produced is proportional to voltage, current and time. ( V*I*t )
• To reduce energy then reduce one of V,I or t.
• Voltage is fixed
• Current can be reduced by the use of current limiting fuses and to some extent good grounding practices.
• It would seem that time should be the easiest one to change by shortening the clearing time.
• Looking at shortening the clearing time it also gives us less coordination time.
• Let us look at the way we produce a coordination study.
• Working along the system from the source, we add up all the impedances and produce the bolted short circuit currents.
• This current is the highest expected.
• Then the times are used to produce the coordination.
SOURCE
S
RELAY
Fault Level13,000 A
1 RELAY
Fault Level2,300 A
2 RELAY
Fault Level1,100 A
3
Inst. Set at 3,000 AP.U. 350
Inst. Set at 1,400 AP.U. 40
Inst. Set at 500 AP.U. 20
• The arc fault will have some extra impedance from the arc so less current and therefore
SOURCE
S
RELAY
Fault LevelArcing
12,560 A
1 RELAY
Fault LevelArcing
2,289 A
2 RELAY
Fault Level Arcing
1,066 A
3
100%
85% 10,676 A 1,946 A 906 A
• Longer times to trip if using an inverse time overcurrent relay or fuse.
• This extra time increases the arc energy.
• Now it is normal to do two studies using 100 % and 85 % of the arc fault current.
• Working down the system we can add new times for, the new currents, and from these new times and current (the breaker operating times need to be added to the TOC times.) Try to improve the coordination.
• We can then document the incident energy from information already given.
• Once this is accomplished a tabulation will help to show the flash boundaries due to these energy levels.
• Other than cutting down the tripping times we can
• use some form of differential scheme
• use a communication scheme to tell quickly where the fault has occurred
• put settings in relay with lower instantaneous times for maintenance
• Other than cutting down the tripping times we can
• use some form of differential scheme
• use a communication scheme to tell quickly where the fault has occurred
• put settings in relay with lower instantaneous times for maintenance
• Other than cutting down the tripping times we can
• use some form of differential scheme
• use a communication scheme to tell quickly where the fault has occurred
• put settings in relay with lower instantaneous times for maintenance