Weylon Malek AMPEAK 2014 Presentation - Process Reliability
-
Upload
arms-reliability -
Category
Engineering
-
view
133 -
download
1
Transcript of Weylon Malek AMPEAK 2014 Presentation - Process Reliability
www.armsreliability.com
Process Reliability
Weylon Malek
Lead Engineer - Western Australia
www.armsreliability.com
Your Organisation
• What triggers your organisation to perform an RCA?
• Easy… These typically cause significant production losses
• Shutdown Extensions
• Explosions or other event that may cause injury
• What triggers your organisation to perform an RCM study?
• Typically smaller losses that add up or Reliability issues on
bottleneck assets
• Poor Maintenance Strategy
• Poor Spares Management and/or Resource Levelling
• How often does your organisation review its’ maintenance
strategies?
• Answers I’ve heard in the past…
• Never
• Every 24 months
www.armsreliability.com
Why Use Process Reliability
• The Weibull process reliability techniques help define a strategic course of action for making improvements.
• The look down technique provides opportunities for developing a strategy to solve problems.
• The method tells the nature of
problems and quantifying the
losses.
www.armsreliability.com
Analysing a PR Chart
The reliability of the process is defined at the point where the trend line, in the upper reaches of the production, began their losses at a cusp.
A portion of the losses appear as cutbacks.
Another portion of the losses appear as very severe problems characterized by a zone labeled crash and burn---both zones are associated with reliability problems.
www.armsreliability.com
Process Reliability Chart
www.armsreliability.com
Nameplate Values
• NAMEPLATE Eta
– The maximum plant capacity under assumed ideal operating and control conditions. This
value can be however obtained by taking an average of the best 15 production results.
• NAMEPLATE Beta
– Manually set to 75 (or other pre-determined value). Beta of 100 is seen to be “world class”
production, achieving highly consistent results.
– Improvement in Nameplate Values will occur as the consistency of throughput is increased
as a result of focussing on both Production and Reliability losses
www.armsreliability.com
Production Values • PRODUCTION Eta
– Production Line tonnes are based on the Weibull analysis performed using the daily production data,
returning a value where the production data line (best of fit) intersects with the Eta estimator (63.2% of
production results are below)
• PRODUCTION Beta
– The Characteristic Shape, or slope of the Weibull Distribution.
In Process analysis, this represents the consistency in the plant’s outputs. The lower the number, the
lower the consistency or increase in variability within the process.
– Production Losses are typically related to;
• Utilisation
• Efficiency
• Process variability
• Equipment Operating Characteristics
• Systemic issues
www.armsreliability.com
Reliability Losses • Total Reliability & Loss
– Reliability point is where there is a cusp in the production points plotted on the Weibull chart. This
represents the point where production becomes inconsistent or unreliable. The loss value is the
difference between demonstrated capacity and are the points at which the production values lie to
the left of that capacity line
– The cusp for the point of reliability represents probability the capacity (tonnes) is likely to be
achieved or greater.
– i.e at this point a 90.34% probability of achieving 382.3 tonnes or greater
– Losses here equate to “Given” tonnes lost per day through reliability plant issues
such as breakdowns
– Reliability losses should be targeted with a formailised RCA Defect Elimination Process with
defined trigger points to reduce variability in plant throughput. This will result in higher eta and
beta Production values which represents increased throughput consistency
www.armsreliability.com
12 Month Analysis Profile
Profile
ProductionLosses
ReliabilityLosses 1
Dec 11 Jan 12 Feb Mar Apr May Jun Jul Aug Sep
Month
0
25
50
75
100
125
150
175
200
225
Lo
st C
ap
acity to
nnes
www.armsreliability.com
How To Improve?
• What is the issue?
• Reliability or Process?
• How to deal with those issues?
• Do those issues change over time?
• How to quantify improvements?
www.armsreliability.com
Using a Reliability Block Diagram (RBD)
to Help Make Decisions
• An RBD is a logic diagram that describes a system behaviour
and easily allows different scenarios to be analysed.
1.1Prim ary Crushing
System
(97.45) %
1.240,000 tonne Live Coars e Ore Pile
System
(95.46) %
1.3Sec ondary
Crus her Feed Conveyor
621-CVR-0-02M TTF=100.6M TTR=0.92
100 %
1.4Sec ondary
Crus hing System
(99.71) %
1.5Coars e Screen
Feed Conveyor 622-CRV-0-03
M TTF=144.2M TTR=1.65
100 %
1.7HRGR Feed
Conveyor623-CVR-0-04
M TTF=173.5M TTR=1.15
100 %
1.8HPGR Sy stem
(87.63) %
1.2.1Coars e Ore Pile
TTE=96TFL=12
100 %
1.11Fine Sc reening
and Ball Mill System 1
(24.48) %
1.12Fine Sc reening
and Ball Mill System 2
(24.45) %
1.13Fine Sc reening
and Ball Mill
System 3
(24.52) %
1.14Fine Sc reening
and Ball Mill
System 4
(24.44) %
1.26
Coars e Screen Feeder
623-FDV-1-01
M TTF=64.8M TTR=0.45
35 %
1.27
Coars e Screen623-SCR-1-01
35 %
1.28Coars e Screen
Feeder623-FDV-2-01
M TTF=64.8M TTR=0.45
35 %
1.29Coars e Screen
623-SCR-2-01
35 %
1.30Coars e Screen
Feeder623-FDV-3-01
M TTF=64.8M TTR=0.45
35 %
1.31Coars e Screen623-SCR-3-01
35 %
1.32
Coars e Screen Feeder
623-FDV-4-01
M TTF=64.8M TTR=0.45
35 %
1.33
Coars e Screen623-SCR-4-01
35 %
1.3412W Shutdown
TTF=1000000M TTR=0100 %
1.351 YR Shutdown
TTF=1000000M TTR=0100 %
1.366W Shutdown
TTF=1000000M TTR=0
100 %
Copy Of1.8.17
Fine Ore Bin625-BIN
TTE=2.27TFL=1.19
100 %
System 1
Example of a crushing circuit
www.armsreliability.com
Which System is the Bottleneck?
www.armsreliability.com
Is there something in that system we can
target?
• Lets take a look at the problem system in detail
Example of the Secondary Crushing System
BN-003Secondary Screen
Feed Bin 1
FE-002Secondary Screen
Belt Feeder 1
BN-004Secondary Screen
Feed Bin 2
FE-003Secondary Screen
Belt Feeder 2
SC-002Secondary Screen
1
SC-003Secondary Screen
2
CV-003Conveyor CV03
BN-006Secondary
Crusher Feed Bin 1
BN-007Secondary
Crusher Feed Bin 2
FE-005Secondary
Crusher Feeder 1
FE-006Secondary
Crusher Feeder 2
CV-004
Conveyor CV04
CR-002Secondary Crusher 1
CR-003Secondary Crusher 2
PP-004
Dust Scrubber Slurry Pump
PP-010
Sump Pump
PP-011
Sump Pump
DC-003
Secondary Screening Dust
Scrubber
AU10-PPP-CRU-BLDNG-BD002
BUILDING, SECONDARY SCREENING
AU10-PPP-CRU-BLDNG-BD003
BUILDING, SECONDARY CRUSHING
F-004.1No Capacity Consequence
Sub-system F-004
www.armsreliability.com
What to do in the Problem System to
Improve Production?
In this example CV04 and CV03 have the biggest impact on production.
0 200 400 600 800 1000 1200 1400 1600 1800
Conveyor CV04
Conveyor CV03
Secondary Crusher 1
Secondary Crusher 2
Secondary Screening Dust Scrubber
Secondary Crusher Feeder 1
Secondary Crusher Feeder 2
Contribution to Capacity Loss (Thousand $)
Co
mp
on
en
t
Contribution to Capacity Loss over 10 YRS
www.armsreliability.com
Implementing The Strategy
• Reliability Block Diagrams (RBD)
– Utilise an Availability Simulation to predict production
increases with different scenarios.
How does a redundancy
scenario change production?
www.armsreliability.com
Implementing Your Strategy
• Reliability Block Diagrams (RBD)
– Utilise an Availability Simulation to predict production
increases with different scenarios.
What predicted impact will a
RCM have on our production?
MTTF goes from 8760
to 4860 through RCM
www.armsreliability.com
What is the Best Solution?
www.armsreliability.com
Comparing Results
www.armsreliability.com
Conclusions
• Step One
– Identify room for improvement
• Step Two
– Identify the best improvement that can be made.
• Step Three
– Quantify the cost benefit in the options available for
improvement through statistical methods.
• Step Four
– Analyse the data to see what impact decisions have on the
business.