Westinghouse AP1000 Program Status

16
Westinghouse AP1000 Program Status Bernd Döhnert Westinghouse Electric Company LLC June 2002

Transcript of Westinghouse AP1000 Program Status

Page 1: Westinghouse AP1000 Program Status

Westinghouse AP1000 Program Status

Bernd Döhnert

Westinghouse Electric Company LLC

June 2002

Page 2: Westinghouse AP1000 Program Status

AP600 Investment in Technology

V E S S E L S U P P O R T

I N S U L A T I O N

SUPPORT

R E M O V A B L EI N S U L A T I O NSUPPORT

P E R M A N E N TCAVITY

SEAL RING

SHIELD BLOCK

O U T L E T V E N TD A M P E R

I N S U L A T I O N

T/C

INLET FLOATBALLS

C O L D L E G

H O T L E G

WATER IN

S T E A M / W A T E R O U T

Passive Safety Systems

US Licensing Approval

Reduced Components & Commodity Components

Severe Accidents Mitigation Features Short Engineering and

Construction Schedule

Advanced Design Features

Modular Construction

Page 3: Westinghouse AP1000 Program Status

AP600 is Mature Design

• Design Maturity

– 1300 man-year / $400 million design and testing effort

– More than 12,000 design documents completed

– 3D computer model developed

• Includes structures, equipment, small / large pipe, cable trays, ducts ...

• Licensing Maturity

– Very thorough / complete NRC review of AP600

• 110 man-year effort (NRC) over 6 years, $30 million

• Independent, confirmatory plant analysis

• Independent, confirmatory plant testing (ROSA, OSU)

• 7400+ questions answered, no open items

• 380+ meeting with NRC, 43 meetings with ACRS

– NRC Design Certification issued 12/99

Page 4: Westinghouse AP1000 Program Status

Why Develop AP1000?

• AP600 meets industry objectives defined in EPRI ALWR Utility Requirements Document (<4.3 ¢/kwh)

• Electric generation environment has significantly changed due to deregulation

– New target generation cost < 3 ¢/kwh

• AP600 cannot achieve this new target through incremental improvements

• This motivated Westinghouse to consider major uprate alternative

Page 5: Westinghouse AP1000 Program Status

AP600 to AP1000 Design Changes

• Increase Core Length & Number of Assemblies

• Increase Size of Key NSSS Components

– Increased height of Reactor Vessel

– Larger Steam Generators

– Larger canned Reactor Coolant Pumps

– Larger Pressurizer

• Increase Containment Height

• Some Capacity Increases in Passive Safety System Components

• Turbine Island Capacity Increased for Power Rating

Retained AP600 Nuclear Island Footprint

Page 6: Westinghouse AP1000 Program Status

AP1000 General ArrangementPlan at Elevation 135’

AP600 AP1000

Page 7: Westinghouse AP1000 Program Status

AP1000 General ArrangementContainment Section View

AP600 AP1000

Page 8: Westinghouse AP1000 Program Status

Comparison of Selected Parameters

Net Electric Output, MWe(2.5”HgA)

Reactor Power, MWt

Hot Leg Temperature, oF

Number of Fuel Assemblies

Type of Fuel Assembly

Active Fuel Length, ft

Linear Heat Rating, kW/ft

R/V I.D., inches

Vessel Thermal Design Flow, gpm

Steam Generator Surface Area, ft2

Reactor Coolant Pump Flow, gpm

Pressurizer Volume, ft3

610

1933

600

145

17x17

12

4.10

157

194,200

75,000

51,000

1600

AP600 AP1000

1117

3400

610

157

17x17

14

5.71

157

299,880

125,000

78,750

2100

PARAMETER

985

2988

626

157

17x17

14

5.02

157

295,500

68,000

103,400

1400

Doel 4 / Tihange 3

Page 9: Westinghouse AP1000 Program Status

AP1000 Design Certification Application

• Formal Application was submitted March 28, 2002– Complete Safety Analysis Report for AP1000 Standard Plant

– Full Probabilistic Risk Assessment (PRA) Report

– Technical Specifications

– Supporting topical reports

• NRC Pre- Certification Review has already established that AP600 testing and safety analysis codes are sufficient for AP1000 design certification.

Page 10: Westinghouse AP1000 Program Status

Capital Cost is Critical Issue for New Plants in U.S.

•Nuclear likely to compete head-to-head against coal plants and natural gas plants

•Nuclear production costs (Fuel plus O&M) already low -- approaching 1 cent/KW-hr.

• Investors will expect payback of capital costs within 20 years of operation

•Overnight capital cost will need to be in the $1000-1300/KWe range for long-term competitiveness with natural gas

Page 11: Westinghouse AP1000 Program Status

Electricity Price Required to Cover Investment Cost - US Conditions

500600700800900

1,0001,1001,2001,3001,4001,500

2.0 2.5 3.0 3.5 4.0 4.5 5.0

Electricity Price To Cover Investment (cents/kwh)

Overn

igh

t C

ost

($/K

We) 12% 14% 16%Nominal After-Tax Equity IRR

Includes 1.1 cents/kwh for O,M&F, Cap Adds, and Decomm.

18%

3% Inflation

15% 17%13%

Page 12: Westinghouse AP1000 Program Status

Impact of Technology Innovation on Plant Price

0

0 200 400 600 800 1000 1200 1400

Power Level, (MWe)

Ove

rnig

ht C

apit

al C

ost

($/K

We)

Passive ALWR

Evolutionary ALWR

* AP1000

Page 13: Westinghouse AP1000 Program Status

Earliest New Plant Order in US - 2005ID Task Name

1 AP1000 Design Certification2 Engineering Design3 NRC Pre-Certification Review4 Prepare Safety Analysis Report5 NRC Review (Issue FDA)6 Hearings / Rule (Issue DC)7

8

9 U.S. Utilities Early Site Permit10 Decide on Plan and Select Site11 Prepare Application12 NRC Review13 Hearings (Issue ESP)14

15

16 U.S. Utility Combined Op License17 Prepare Application18 NRC Review (Issue SER)19 Hearings (Issue COL)

SUBMIT DC APPLICATION

SUBMIT ESP APPLICATION

SUBMIT COL APPLICATION

Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4

2000 2001 2002 2003 2004 2005

Page 14: Westinghouse AP1000 Program Status

AP1000 Business Plan Development

• Developed with US Power Companies to:

– Assess the Economic Competitiveness of AP1000

– Validate the Cost/Price Estimate with Independent (Bechtel) Review

– Develop a Sample Project Implementation Model

• Financial Evaluation Based on a Series of 4 Twin Standard Plants

– Provide a Plan for the Next Steps for Commercialization

– Determine Government Support for Commercialization and Risk Management

Page 15: Westinghouse AP1000 Program Status

AP1000/AP600 Role in U.S. Energy Market• Electricity Demand in the United States is Projected

to Increase

• Westinghouse Supports Industry Goals to Maintain the Nuclear Generation Share of the Market (Maintain 20%)

• Environmental Benefits of Emission Free Nuclear Power - A Future Strength that will be Increasingly Valued

• A Family of Standard AP1000 Plants is Competitive with Current Projected Generation Prices

• DOE and Administration are Providing Increased Support for Near-Term Start of Additional Nuclear Capacity

Page 16: Westinghouse AP1000 Program Status

AP1000 Overview

• Technical Feasibility of AP1000 Established

• Retains AP600 Design Detail

• Retains Credibility of Cost Estimateand Construction Schedule

• Established Regulatory Framework

• AP1000 provides 75% power upratefor 15% increment in capital cost

• AP1000 Meets New Plant Economic Targets in the Near Term