D ECEMBER M EETING B OARD OF T RUSTEES C ONSTRUCTION U PDATE D ECEMBER 11, 2018 W ESTFIELD W ASHINGTON S CHOOLS

Transcript of Westfield Washington Schools

D e c e m b e r m e e t i n g

b o a r D o f t r u s t e e s

c o n s t r u c t i o n u p D at e

D e c e m b e r 11, 2018

Westfield Washington Schools

Westfield Intermediate School

WESTFIELD INTERMEDIATE SCHOOL

WESTFIELD INTERMEDIATE SCHOOL

PROGRESS TO DATE Completed structural steel erection (MPIF addition)

Started structural steel erection (classroom addition)

Completed new parking lot lighting

WESTFIELD INTERMEDIATE SCHOOL

MPIF ADDITION - STRUCTURAL STEEL

WESTFIELD INTERMEDIATE SCHOOL

MPIF ADDITION - STRUCTURAL STEEL

WESTFIELD INTERMEDIATE SCHOOL

CLASSROOM ADDITION - STRUCTURAL STEEL

WESTFIELD INTERMEDIATE SCHOOL

PLANNED NEXT 30 DAYS:

Complete structural steel erection (Classroom addition)

Complete steel detailing & install decking (both additions)

Start masonry walls (MPIF addition)

Start exterior stud walls

Prepare grade for remaining concrete slabs (MPIF addition)

WESTFIELD INTERMEDIATE SCHOOL

$2,057,822WORK IN PLACE

$10,702,682TOTAL CONTRACTS

7/21 MONTHSCONSTRUCTION

Westfield Middle School

WESTFIELD MIDDLE SCHOOL

WESTFIELD MIDDLE SCHOOL

PROGRESS TO DATE - LAST 30 DAYS

MPIF ADDITION

Continue exterior masonry walls (85% complete)

Completed concrete floor slab in gym

Completed concrete floor topping for mezzanine

Started PVC roofing over gym

Started above slab plumbing rough-in at locker rooms

Started duct work at mezzanine

Started sprinkler piping in gym and mezzanine level

WESTFIELD MIDDLE SCHOOL

MPIF ADDITION - EXTERIOR MASONRY WALLS

WESTFIELD MIDDLE SCHOOL

MPIF ADDITION - GYM & MEZZANINE PROGRESS

WESTFIELD MIDDLE SCHOOL

MPIF ADDITION - MEZZANINE PROGRESS

WESTFIELD MIDDLE SCHOOL

PROGRESS TO DATE - LAST 30 DAYS

MUSIC RENOVATIONS (OLD POOL)

Completed removal existing exterior precast wall panels

and masonry walls at north & east elevations

NEW OFFICE RENOVATION

Completed interior paint primer and 1st coat

Completed interior ceiling grid

EXISTING MECHANICAL ROOM

Started demolition of existing chiller and piping

SITE

Completed relocation of existing gas main and meters

WESTFIELD MIDDLE SCHOOL

NEW OFFICE AREA - WALL AND CEILING FINISH PROGRESS

WESTFIELD MIDDLE SCHOOL

NEW MUSIC AREA - SOUTH EXTERIOR WALL DEMOLITION

WESTFIELD MIDDLE SCHOOL

NEW MUSIC AREA - EAST EXTERIOR WALL DEMOLITION

WESTFIELD MIDDLE SCHOOL

PLANNED WORK - NEXT 30 DAYS

MPIF ADDITION

Complete exterior masonry (block) walls at gym

Set AHU units (3) and start HVAC piping at mezzanine

Continue duct work at gym and mezzanine

Start installing interior masonry walls at locker rooms

Complete roof installation

Continue MEP overhead RIs at gym

WESTFIELD MIDDLE SCHOOL

PLANNED WORK - NEXT 30 DAYS

MUSIC RENOVATIONS (OLD POOL)

Place interior foundations

Backfill existing pool

Start exterior wall framing at south and north walls

NEW OFFICE RENOVATION

Complete interior finishes (doors, flooring, ceiling tile, etc.)

Available for Occupancy

EXISTING MECHANICAL ROOM

Complete demolition and removal of existing piping,

boilers and chiller at existing mechanical rooms

WESTFIELD MIDDLE SCHOOL

PLANNED WORK - NEXT 30 DAYS

CLASSROOM ADDITION

Continue underground plumbing

Continue foundations (pending sanitary lateral permit)

WESTFIELD MIDDLE SCHOOL

$4,388,140WORK IN PLACE

$15,434,645TOTAL CONTRACTS

7/21 MONTHSCONSTRUCTION

Westfield High School

WESTFIELD HIGH SCHOOL

CONSTRUCTION PHASING PLANS - PHASE 1

1ST FLOOR 2ND FLOOR

WESTFIELD HIGH SCHOOL

PROGRESS TO DATE Completed new gas main reroute and connection

Completed layout of Phase 1 site utilities

Continued tree protection and removal

Received storm and sanitary piping and structures

Started 36” storm pipe and structures

Started new water main reroute

Completed stripping of topsoil

Completed first proof roll of building pad

Completed removal of 8 existing light poles

Completed temporary power connections

WESTFIELD HIGH SCHOOL

NEW CLASSROOM ADDITION - STORM DRAINAGE SITEWORK

WESTFIELD HIGH SCHOOL

NEW CLASSROOM ADDITION - SITE UTILITY MATERIALS

WESTFIELD HIGH SCHOOL

NEW CLASSROOM ADDITION - NEW WATER LINE

WESTFIELD HIGH SCHOOL

PLANNED NEXT 30 DAYS: Complete water main reroute

Complete 36” storm piping and structures

Start 15” storm piping and structures

Start new sanitary main reroute

Continue building pad (weather permiiting)

Remove remaining two existing phase 1 light poles

WESTFIELD HIGH SCHOOL

$1,007,535WORK IN PLACE

$30,538,917TOTAL CONTRACTS

2/28 MONTHSCONSTRUCTION