Westfield Washington Schools
Transcript of Westfield Washington Schools
D e c e m b e r m e e t i n g
b o a r D o f t r u s t e e s
c o n s t r u c t i o n u p D at e
D e c e m b e r 11, 2018
Westfield Washington Schools
WESTFIELD INTERMEDIATE SCHOOL
PROGRESS TO DATE Completed structural steel erection (MPIF addition)
Started structural steel erection (classroom addition)
Completed new parking lot lighting
WESTFIELD INTERMEDIATE SCHOOL
PLANNED NEXT 30 DAYS:
Complete structural steel erection (Classroom addition)
Complete steel detailing & install decking (both additions)
Start masonry walls (MPIF addition)
Start exterior stud walls
Prepare grade for remaining concrete slabs (MPIF addition)
WESTFIELD INTERMEDIATE SCHOOL
$2,057,822WORK IN PLACE
$10,702,682TOTAL CONTRACTS
7/21 MONTHSCONSTRUCTION
WESTFIELD MIDDLE SCHOOL
PROGRESS TO DATE - LAST 30 DAYS
MPIF ADDITION
Continue exterior masonry walls (85% complete)
Completed concrete floor slab in gym
Completed concrete floor topping for mezzanine
Started PVC roofing over gym
Started above slab plumbing rough-in at locker rooms
Started duct work at mezzanine
Started sprinkler piping in gym and mezzanine level
WESTFIELD MIDDLE SCHOOL
PROGRESS TO DATE - LAST 30 DAYS
MUSIC RENOVATIONS (OLD POOL)
Completed removal existing exterior precast wall panels
and masonry walls at north & east elevations
NEW OFFICE RENOVATION
Completed interior paint primer and 1st coat
Completed interior ceiling grid
EXISTING MECHANICAL ROOM
Started demolition of existing chiller and piping
SITE
Completed relocation of existing gas main and meters
WESTFIELD MIDDLE SCHOOL
PLANNED WORK - NEXT 30 DAYS
MPIF ADDITION
Complete exterior masonry (block) walls at gym
Set AHU units (3) and start HVAC piping at mezzanine
Continue duct work at gym and mezzanine
Start installing interior masonry walls at locker rooms
Complete roof installation
Continue MEP overhead RIs at gym
WESTFIELD MIDDLE SCHOOL
PLANNED WORK - NEXT 30 DAYS
MUSIC RENOVATIONS (OLD POOL)
Place interior foundations
Backfill existing pool
Start exterior wall framing at south and north walls
NEW OFFICE RENOVATION
Complete interior finishes (doors, flooring, ceiling tile, etc.)
Available for Occupancy
EXISTING MECHANICAL ROOM
Complete demolition and removal of existing piping,
boilers and chiller at existing mechanical rooms
WESTFIELD MIDDLE SCHOOL
PLANNED WORK - NEXT 30 DAYS
CLASSROOM ADDITION
Continue underground plumbing
Continue foundations (pending sanitary lateral permit)
WESTFIELD HIGH SCHOOL
PROGRESS TO DATE Completed new gas main reroute and connection
Completed layout of Phase 1 site utilities
Continued tree protection and removal
Received storm and sanitary piping and structures
Started 36” storm pipe and structures
Started new water main reroute
Completed stripping of topsoil
Completed first proof roll of building pad
Completed removal of 8 existing light poles
Completed temporary power connections
WESTFIELD HIGH SCHOOL
PLANNED NEXT 30 DAYS: Complete water main reroute
Complete 36” storm piping and structures
Start 15” storm piping and structures
Start new sanitary main reroute
Continue building pad (weather permiiting)
Remove remaining two existing phase 1 light poles