CROSSTOWN LRTConstruction Liaison CommitteeWestern WorksSeptember 26, 2017
![Page 2: Western Works Construction Liaison Committee Meeting - September 2017](https://reader033.fdocuments.in/reader033/viewer/2022061307/5a64e5177f8b9a2c5d8b4c7b/html5/thumbnails/2.jpg)
Agenda
• Eglinton Maintenance & Storage Facility
• Mount Dennis Station
• Railway Corridor
• West Portal & Elevated Guideway
• Keelesdale Station
• Caledonia Station
2
![Page 3: Western Works Construction Liaison Committee Meeting - September 2017](https://reader033.fdocuments.in/reader033/viewer/2022061307/5a64e5177f8b9a2c5d8b4c7b/html5/thumbnails/3.jpg)
3
Maintenance & Storage Facility : ongoing works
• Site services – dry/wet utilities (ongoing)
• Steel erection for Maintenance Building (ongoing)
• Concrete placing, formwork and rebar – maintenance building pours (ongoing)
• OCS Foundation Installation
![Page 4: Western Works Construction Liaison Committee Meeting - September 2017](https://reader033.fdocuments.in/reader033/viewer/2022061307/5a64e5177f8b9a2c5d8b4c7b/html5/thumbnails/4.jpg)
Mount Dennis Station: ongoing works
• Foundations – Mount Dennis station box concrete structure & main entrance (ongoing)
• Driven Piles for Photography Drive Bridge Abutment – Week of Sept 25 7:00 AM to 11:00 PM
• Keelesdale Road and sidewalk north of Eglinton closed commencing October 2, 2017
• Building 9 foundations
4
![Page 5: Western Works Construction Liaison Committee Meeting - September 2017](https://reader033.fdocuments.in/reader033/viewer/2022061307/5a64e5177f8b9a2c5d8b4c7b/html5/thumbnails/5.jpg)
Railway Corridor: ongoing work
5
Phase 2 – started April 2017
• CP Track diversion Track Grading & Track Construction – started September 5, 2017
Phase 3 – started May 2017
• Center Temporary Shoring Wall (excavation & tie-backs) – Fall 2017
• LRT and Pedestrian Tunnel construction (excavation) – Fall 2017
• Work within the rail corridor will occur during the hours of 7:00 AM to 11:00 PM
• Anticipated night work will occur over the span of 2 to 3 nights to complete borehole drilling. This work is expected to begin at the end of September 2017. A notice will be canvassed to the affected residents on Hollis Street within the next week
![Page 6: Western Works Construction Liaison Committee Meeting - September 2017](https://reader033.fdocuments.in/reader033/viewer/2022061307/5a64e5177f8b9a2c5d8b4c7b/html5/thumbnails/6.jpg)
West Portal & Elevated Guideway
*90% rendering6
![Page 7: Western Works Construction Liaison Committee Meeting - September 2017](https://reader033.fdocuments.in/reader033/viewer/2022061307/5a64e5177f8b9a2c5d8b4c7b/html5/thumbnails/7.jpg)
West Portal & Elevated Guideway
7
![Page 8: Western Works Construction Liaison Committee Meeting - September 2017](https://reader033.fdocuments.in/reader033/viewer/2022061307/5a64e5177f8b9a2c5d8b4c7b/html5/thumbnails/8.jpg)
8
West Portal & Elevated Guideway
*60% rendering
![Page 9: Western Works Construction Liaison Committee Meeting - September 2017](https://reader033.fdocuments.in/reader033/viewer/2022061307/5a64e5177f8b9a2c5d8b4c7b/html5/thumbnails/9.jpg)
9
West Portal: ongoing work
• Box tunnel construction tiebacks and struts de-stressed and removals. Backfill (ongoing)
• Utility relocation works for Elevated Guideway – Manhole 27 is completed• To follow: Retaining wall and backfilling for Eglinton Avenue West realignment –
shaft walls demolition started. Utilities relocation at south Eglinton Avenue West (No-Frills entrance) to start foundations of the Elevated Guideway by end of September 2017.
![Page 10: Western Works Construction Liaison Committee Meeting - September 2017](https://reader033.fdocuments.in/reader033/viewer/2022061307/5a64e5177f8b9a2c5d8b4c7b/html5/thumbnails/10.jpg)
10
West Portal: current traffic
![Page 11: Western Works Construction Liaison Committee Meeting - September 2017](https://reader033.fdocuments.in/reader033/viewer/2022061307/5a64e5177f8b9a2c5d8b4c7b/html5/thumbnails/11.jpg)
LRT Tunnel Fit Out
11
![Page 12: Western Works Construction Liaison Committee Meeting - September 2017](https://reader033.fdocuments.in/reader033/viewer/2022061307/5a64e5177f8b9a2c5d8b4c7b/html5/thumbnails/12.jpg)
Tunnel Invert Pour: Key Milestones
12
![Page 13: Western Works Construction Liaison Committee Meeting - September 2017](https://reader033.fdocuments.in/reader033/viewer/2022061307/5a64e5177f8b9a2c5d8b4c7b/html5/thumbnails/13.jpg)
Concrete Invert Pour: Concrete Delivery
13
• Mini concrete trucks delivering concrete into tunnel.
![Page 14: Western Works Construction Liaison Committee Meeting - September 2017](https://reader033.fdocuments.in/reader033/viewer/2022061307/5a64e5177f8b9a2c5d8b4c7b/html5/thumbnails/14.jpg)
Concrete Invert Pour: Stage 1
14
• Concrete trucks deliver loose concrete to the work area• Loose concrete mix is used to fill the bottom of the tunnel• Tunnel Fit Out Crew flatten and smooth it
![Page 15: Western Works Construction Liaison Committee Meeting - September 2017](https://reader033.fdocuments.in/reader033/viewer/2022061307/5a64e5177f8b9a2c5d8b4c7b/html5/thumbnails/15.jpg)
Concrete Invert Pour: Stage 2
15
• Workers install welded mesh which functions like rebar to help reinforce the next layer of concrete
• Higher strength concrete is poured to provide the flat track slab for the rail tracks• Workers spread the concrete, and a truss screed machine vibrates it into a perfectly level
surface
![Page 16: Western Works Construction Liaison Committee Meeting - September 2017](https://reader033.fdocuments.in/reader033/viewer/2022061307/5a64e5177f8b9a2c5d8b4c7b/html5/thumbnails/16.jpg)
Keelesdale Station: ongoing works
Ongoing
• Excavation under the deck, Main Entrance, 2nd Entrance, 3rd Entrance and TPSS • Tieback installation level B complete. Level C starts Sepbember 25th• Utility support 95% complete• Second shift is working from 5:00 p.m. to 2:00 a.m. daily.
16
![Page 17: Western Works Construction Liaison Committee Meeting - September 2017](https://reader033.fdocuments.in/reader033/viewer/2022061307/5a64e5177f8b9a2c5d8b4c7b/html5/thumbnails/17.jpg)
17
Caledonia Station Update
Fall 2017
• Dewatering (ongoing through construction period)
• Continue deep excavation and hauling (starting at 6:00 a.m.)
• Continue installation of tie-backs
![Page 18: Western Works Construction Liaison Committee Meeting - September 2017](https://reader033.fdocuments.in/reader033/viewer/2022061307/5a64e5177f8b9a2c5d8b4c7b/html5/thumbnails/18.jpg)
18
Long-term Construction Staging
Late June 2017 until 2021