West Park Hospital
Transcript of West Park Hospital
West Park Hospital Phase III (Dietary Build-out/Cedar
Mountain/Med
Records/Connector/Education)
Monthly Project Report July 2015
West Park Hospital Phase III (2nd Floor patient build�out)
Section 01 – Project Update
1
WEST PARK HOSPITAL PHASE III Weekly Progress Report 022
Period ending July 19, 2015
Weather
Average Daily High Temp 74 F
Min Low Temp 56 F
Average Wind Speed 9 mph
Man Power
Number or Workers on Site: 42
Subcontractors on Site
• Basin Mechanical/NorPac Sheet Metal, Cowan Construction, Yellowstone Electric, Delta United
Specialties, MKM Construction, Spray on Solutions and Sure Steel
Schedule
•••• Upcoming Meetings – local time
o Sub Coordination Meeting, 9am MST July 21 – Conference Office
o Safety Orientation Meeting, 7am MST Daily – Conference Office
2
Work Progress Ground Floor Dietary Buildout
General:
• Layout and Framing – 95%
• In-wall Rough-in – 80%
• Overhead Rough-In – 70%
Concrete:
•
Electrical:
• Overhead rough In - ongoing
• In wall R.I. ongoing
HVAC:
• Overhead duct installation ongoing
Plumbing
• Overhead R.I. - ongoing
• In-wall R.I. – ongoing
Drywall
• Framing Area D ongoing – 90%
• Framing Area A – 95%
• Top-out in Area A and B
• Drywall ongoing – 40%
Work Progress First Floor Medical Records
General:
• Fab and deliver door frames/Doors per revisions
Electrical:
• In wall R.I. ongoing
• Overhead R.I. ongoing
HVAC:
• Overhead ductwork install ongoing
• VAV install ongoing
Plumbing
• Overhead R.I. ongoing
• Hydronic piping install ongoing
Drywall/Stud Framing
• Framing of walls complete
3
Work Progress Connector
General:
• Exterior framing started
• Fireproofing steel complete
Sitework/Concrete
• Backfill around columns ongoing
• Begin form sitework Concrete
Electrical:
• .
HVAC:
• Procurement of duct ongoing
• Equipment deliveries ongoing
Plumbing
• Procurement of materials ongoing
Drywall/Stud Framing
• Layout of walls ongoing – 20%
• Fab truss on-site ongoing
• Exterior framing started
Steel
• Column and beam fireproofing complete
Work Progress Cedar Mountain Center
General:
• Received final CD’s per state revisions on 6/11
• Layout and framing ongoing complete
• Overhead Rough-in – 60%
• In-wall Rough ongoing – 85%
Electrical:
• Overhead rough in ongoing – 80%
• In wall rough in ongoing – 85%
HVAC:
• Overhead rough in ongoing – 35%
• Procurement of materials per revised drawings ongoing
4
Plumbing
• Overhead rough in ongoing – 50%
• Begin in-wall rough-in – 70%
Drywall/Stud Framing
• Layout and framing per final CD’s
• Topout ongoing
• Patching existing walls second floor ongoing
Work Progress Education
General:
• Layout complete
• Duct Installation ongoing
Electrical:
• Overhead rough in ongoing
• In wall rough in ongoing
HVAC:
• Overhead rough in ongoing
Plumbing
• Overhead rough in ongoing
• In wall R.I. complete
Drywall/Stud Framing
• Layout and framing ongoing
• Top-out ongoing
Work Progress Parking Lot
Sitework:
• SWPPP ongoing
• Utility pole relocated June 6th – Secondary service ongoing
• Infiltration system backfill complete
• Underground utility install ongoing
West Park Hospital Phase III (2nd Floor patient build�out)
Section 02 � Project Schedule
Activity ID Activity Name Original
Duration
Remaining
Duration
Duration
%
Complete
Start Finish
Cedar Mountain Renovation 01.20.15Cedar Mountain Renovation 01.20.15 158 135 14.58% 06-Apr-15 A 30-Nov-15
Project Overview and MilestonesProject Overview and Milestones 158 135 14.58% 06-Apr-15 A 30-Nov-15
A1560 Asbestos Remediation 10 0 100% 23-Apr-15 A 22-May-15 A
A1580 Start Cedar Mountain 0 0 0% 26-May-15*
A1620 State Review 30 8 75% 06-Apr-15 A 03-Jun-15
A1000 Overall Construction Duration 111 130 0% 27-Apr-15 A 23-Nov-15
A1510 Notice to Proceed 0 0 0% 26-May-15
A1640 Reissue Drawings State Review 0 0 0% 10-Jun-15
A1600 OFE Install 5 5 0% 30-Oct-15 06-Nov-15
A1590 LCC Document Close-Out to Owner 1 1 0% 18-Nov-15 19-Nov-15
A1010 Substantial Completion 0 0 0% 20-Nov-15
A1540 State Health Insection 0 0 0% 23-Nov-15
A1530 Finish Cedar Mountain 0 0 0% 23-Nov-15
A1610 Owner Prep/Owner Move-In 5 5 0% 23-Nov-15 30-Nov-15
Interior FinishInterior Finish 156 135 13.48% 06-Apr-15 A 30-Nov-15
A1550 State Review 30 8 75% 06-Apr-15 A 03-Jun-15
A1020 Build Temporary Walls/ICRA Setup 2 0 100% 27-Apr-15 A 28-Apr-15 A
A1030 Make Safe - MEP 5 0 100% 27-Apr-15 A 01-May-15 A
A1040 Demolition 20 2 90% 13-Apr-15 A 27-May-15
A1050 Layout 2 2 25% 04-May-15 A 29-May-15
A1570 Reissue Drawings State Review 1 1 0% 10-Jun-15* 10-Jun-15
A1630 Fab and Deliver Duct 30 30 0% 10-Jun-15 22-Jul-15
A1660 Door Frame Fab and Deliver 15 15 0% 10-Jun-15 01-Jul-15
A1060 Frame/Top-out Priority Walls 5 5 0% 01-Jul-15 08-Jul-15
A1100 Frame/Top-Out All Walls 5 5 0% 08-Jul-15 15-Jul-15
A1110 In Wall R.I. MEP 20 20 0% 14-Jul-15 11-Aug-15
A1170 Overhead Fire Protection R.I. 3 3 0% 15-Jul-15 20-Jul-15
A1180 Set Roof Curbs 1 1 0% 15-Jul-15 16-Jul-15
0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 2 2 0 1 1 2 0 0 1 2 30
J J A S O N D J F M A M J
Asbestos Remediation
Start Cedar Mountain
State Review
Overall Construction Duration
Notice to Proceed
Reissue Drawings State Review
OFE Install
LCC Document Close-Out to Owner
Substantial Completion
State Health Insection
Finish Cedar Mountain
Owner Prep/Owner Move-In
State Review
Build Temporary Walls/ICRA Setup
Make Safe - MEP
Demolition
Layout
Reissue Drawings State Review
Fab and Deliver Duct
Door Frame Fab and Deliver
Frame/Top-out Priority Walls
Frame/Top-Out All Walls
In Wall R.I. MEP
Overhead Fire Protection R.I.
Set Roof Curbs
Page 1 of 3
Early Bar
Critical Bar
Actual Bar
Level of Effort
Actual Level of Effort
Project Baseli...
Milestone
Run Date: 27-May-15
Data Date: 26-May-15
Project ID: 15HCG0120
Layton Construction Co., Inc.
27-May-15 Schedule
Activity ID Activity Name Original
Duration
Remaining
Duration
Duration
%
Complete
Start Finish
A1190 Patch Roof 2 2 0% 16-Jul-15 20-Jul-15
A1070 Overhead R.I. Mechanical 20 20 0% 22-Jul-15 19-Aug-15
A1080 Overhead R.I. Electrical 20 20 0% 29-Jul-15 26-Aug-15
A1090 Overhead R.I. Plumbing 20 20 0% 29-Jul-15 26-Aug-15
A1120 In-Wall/Framing Inspection 1 1 0% 11-Aug-15 12-Aug-15
A1130 Prep/Form/Pour Concrete Bathroom Curbs 2 2 0% 12-Aug-15 14-Aug-15
A1140 Insulate/Hang Drywall 5 5 0% 12-Aug-15 19-Aug-15
A1160 Tape/Finish Walls 5 5 0% 17-Aug-15 24-Aug-15
A1210 Frame Hard Ceilings/Soffits 5 5 0% 20-Aug-15 27-Aug-15
A1150 Equipment/FCU Install 3 3 0% 26-Aug-15 31-Aug-15
A1200 Above Ceiling Inspection 1 1 0% 31-Aug-15 01-Sep-15
A1220 Hang Hard Ceilings/Soffits 3 3 0% 01-Sep-15 04-Sep-15
A1230 Tape/Finish Hard Ceilings/Soffits 5 5 0% 04-Sep-15 11-Sep-15
A1240 Prime/1st Coat Walls and Ceilings/Soffits 5 5 0% 11-Sep-15 18-Sep-15
A1250 Ceramic Tile Bathrooms 15 15 0% 18-Sep-15 09-Oct-15
A1270 Ceiling Grid 3 3 0% 18-Sep-15 23-Sep-15
A1280 Sprinkler Drops 3 3 0% 22-Sep-15 25-Sep-15
A1290 Millwork 10 10 0% 23-Sep-15 07-Oct-15
A1310 MEP Trim-Out Ceilings 4 4 0% 23-Sep-15 29-Sep-15
A1320 Above Ceiling Punch 1 1 0% 29-Sep-15 30-Sep-15
A1430 Equimpent Startup 2 2 0% 29-Sep-15 01-Oct-15
A1330 Above Ceiling Inspection 1 1 0% 30-Sep-15 01-Oct-15
A1340 Drop Ceiling Tile 3 3 0% 01-Oct-15 06-Oct-15
A1440 Pre-Cx/PFC Equipment 5 5 0% 01-Oct-15 08-Oct-15
A1350 Resilient Flooring/Carpet/Base 15 15 0% 02-Oct-15 23-Oct-15
A1300 MEP Trim-Out 5 5 0% 07-Oct-15 14-Oct-15
A1470 Equipment ID/Panel Schedules 1 1 0% 08-Oct-15 09-Oct-15
A1260 MEP Trim-Out Bathrooms 3 3 0% 09-Oct-15 14-Oct-15
A1360 Final Paint 5 5 0% 23-Oct-15 30-Oct-15
A1370 Install Accessories/OFE 5 5 0% 30-Oct-15 06-Nov-15
A1650 Install Doors and Hardware 3 3 0% 02-Nov-15 04-Nov-15
A1460 TAB 4 4 0% 04-Nov-15 10-Nov-15
A1380 Construction Clean 2 2 0% 06-Nov-15 10-Nov-15
0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 2 2 0 1 1 2 0 0 1 2 30
J J A S O N D J F M A M J
Patch Roof
Overhead R.I. Mechanical
Overhead R.I. Electrical
Overhead R.I. Plumbing
In-Wall/Framing Inspection
Prep/Form/Pour Concrete Bathroom Curbs
Insulate/Hang Drywall
Tape/Finish Walls
Frame Hard Ceilings/Soffits
Equipment/FCU Install
Above Ceiling Inspection
Hang Hard Ceilings/Soffits
Tape/Finish Hard Ceilings/Soffits
Prime/1st Coat Walls and Ceilings/Soffits
Ceramic Tile Bathrooms
Ceiling Grid
Sprinkler Drops
Millwork
MEP Trim-Out Ceilings
Above Ceiling Punch
Equimpent Startup
Above Ceiling Inspection
Drop Ceiling Tile
Pre-Cx/PFC Equipment
Resilient Flooring/Carpet/Base
MEP Trim-Out
Equipment ID/Panel Schedules
MEP Trim-Out Bathrooms
Final Paint
Install Accessories/OFE
Install Doors and Hardware
TAB
Construction Clean
Page 2 of 3
Activity ID Activity Name Original
Duration
Remaining
Duration
Duration
%
Complete
Start Finish
A1450 Commissioning 1 1 0% 10-Nov-15 11-Nov-15
A1390 LCC/AOE Punch 1 1 0% 10-Nov-15 11-Nov-15
A1480 Owner Training 2 2 0% 11-Nov-15 13-Nov-15
A1400 Final Clean 3 3 0% 11-Nov-15 16-Nov-15
A1410 Fire Marshall/Local Final Inspections 2 2 0% 16-Nov-15 18-Nov-15
A1490 LCC Document Close-Out to Owner 1 1 0% 18-Nov-15 19-Nov-15
A1520 Substatial Completion 1 1 0% 19-Nov-15 20-Nov-15
A1420 State Health Inspection 1 1 0% 20-Nov-15 23-Nov-15
A1500 Owner Prep/Owner Move-In 5 5 0% 23-Nov-15 30-Nov-15
0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 2 2 0 1 1 2 0 0 1 2 30
J J A S O N D J F M A M J
Commissioning
LCC/AOE Punch
Owner Training
Final Clean
Fire Marshall/Local Final Inspections
LCC Document Close-Out to Owner
Substatial Completion
State Health Inspection
Owner Prep/Owner Move-In
Page 3 of 3
Activity ID Activity Name Original
Duration
Remaining
Duration
Duration
%
Complete
Start Finish
WPH Connector and RenovationWPH Connector and Renovation 137 106 22.63% 31-Mar-15 A 20-Oct-15
Project OverviewProject Overview 137 106 22.63% 31-Mar-15 A 20-Oct-15
A1520 Notice to Proceed 0 0 100% 31-Mar-15 A
A1590 Start Connector and Renovation 0 0 100% 31-Mar-15 A
A1000 Overall Construction Duration 124 97 21.77% 31-Mar-15 A 07-Oct-15
A1010 Reissue Drawings State Review 0 0 0% 19-Jun-15*
A1490 OFE Install 3 3 0% 29-Sep-15 01-Oct-15
A1510 LCC Paperwork to Owner 1 1 0% 12-Oct-15 12-Oct-15
A1610 Substantial Completion 0 0 0% 12-Oct-15
A1620 State Health Inspection 0 0 0% 13-Oct-15
A1600 Finish Connector and Renovation 0 0 0% 13-Oct-15
A1500 Owner Prep/Move-In 5 5 0% 14-Oct-15 20-Oct-15
ConstructionConstruction 137 95 30.66% 31-Mar-15 A 20-Oct-15
A1060 Notice to Proceed 1 0 100% 31-Mar-15 A 13-Apr-15 A
A1070 Working Control for Layout 1 0 100% 08-Apr-15 A 09-Apr-15 A
A1080 Demo as needed for Control/Layout/Canopy5 0 100% 20-Apr-15 A 20-Apr-15 A
A1090 Field Verify Steel 1 0 100% 14-Apr-15 A 14-Apr-15 A
A1100 Excavate for Footings/Foundation 5 0 100% 13-Apr-15 A 14-Apr-15 A
A1110 Form/Prep/Rebar/Anchor Bolts 5 0 100% 15-Apr-15 A 08-May-15 A
A1120 City Inspection 1 0 100% 15-Apr-15 A 08-May-15 A
A1130 Pour Foundations 2 0 100% 15-Apr-15 A 08-May-15 A
A1140 Erect Steel 5 5 0% 10-Jun-15* 16-Jun-15
A1150 Install Decking/Detailing 5 5 0% 17-Jun-15 23-Jun-15
A1550 Reissue Drawings State Review 1 1 0% 19-Jun-15 19-Jun-15
A1160 Steel Inspection 1 1 0% 24-Jun-15 24-Jun-15
A1170 Form/Prep SOD 2 2 0% 25-Jun-15 26-Jun-15
A1180 City Inspection SOD 1 1 0% 29-Jun-15 29-Jun-15
A1190 Pour SOD 1 1 0% 30-Jun-15 30-Jun-15
A1200 Exterior Layout North and South Elevations 1 1 0% 01-Jul-15 01-Jul-15
A1450 Fireproofing 3 3 0% 01-Jul-15 03-Jul-15
A1210 Roofing System 10 10 0% 02-Jul-15 15-Jul-15
A1220 Exterior Sheathing and Dry In 5 5 0% 06-Jul-15 10-Jul-15
A1230 Interior MEP Overhead R.I. 5 5 0% 13-Jul-15 17-Jul-15
A1240 Exterior Finishes 20 20 0% 20-Jul-15 14-Aug-15
A1530 Install Window Systems 5 5 0% 20-Jul-15 24-Jul-15
A1250 Interior Framing 5 5 0% 17-Aug-15 21-Aug-15
A1260 Interior MEP In-Wall R.I. 5 5 0% 24-Aug-15 28-Aug-15
A1270 Site Work/Exterior Landscape 8 8 0% 31-Aug-15 09-Sep-15
A1280 Interior City Inspection 1 1 0% 31-Aug-15 31-Aug-15
A1290 Hang Drywall 3 3 0% 01-Sep-15 03-Sep-15
A1300 Tape/Float Walls 4 4 0% 04-Sep-15 09-Sep-15
25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 07 14 21 28 04 11 18 25 02 09 16 2330
June 2015 July 2015 August 2015 S October 2015 N December 2015 January 2016 February 2016 March 2016 April 2016 May 2016June 2016
Start Connector and Renovation
Overall Construction Duration
Reissue Drawings State Review
OFE Install
LCC Paperwork to Owner
Substantial Completion
State Health Inspection
Finish Connector and Renovation
Owner Prep/Move-In
Working Control for Layout
Demo as needed for Control/Layout/Canopy
Field Verify Steel
Excavate for Footings/Foundation
Form/Prep/Rebar/Anchor Bolts
City Inspection
Pour Foundations
Erect Steel
Install Decking/Detailing
Reissue Drawings State Review
Steel Inspection
Form/Prep SOD
City Inspection SOD
Pour SOD
Exterior Layout North and South Elevations
Fireproofing
Roofing System
Exterior Sheathing and Dry In
Interior MEP Overhead R.I.
Exterior Finishes
Install Window Systems
Interior Framing
Interior MEP In-Wall R.I.
Site Work/Exterior Landscape
Interior City Inspection
Hang Drywall
Tape/Float Walls
Page 1 of 2
Early Bar
Critical Bar
Actual Bar
Level of Effort
Actual Level of Effort
Project Baseline Bar
Milestone
Run Date: 02-Jun-15
Data Date: 26-May-15
Project ID: 15HCG0126
Layton Construction Co., Inc.
02-Jun-15 Schedule
Activity ID Activity Name Original
Duration
Remaining
Duration
Duration
%
Complete
Start Finish
A1310 Prime/1st Coat Paint 3 3 0% 10-Sep-15 14-Sep-15
A1320 MEP Trim-Out 3 3 0% 15-Sep-15 17-Sep-15
A1410 Ceiling Grid Install 2 2 0% 15-Sep-15 16-Sep-15
A1430 MEP Trim-Out Ceilings 2 2 0% 17-Sep-15 18-Sep-15
A1440 Above Ceiling Inspection 1 1 0% 21-Sep-15 21-Sep-15
A1420 Drop Ceiling Tile 2 2 0% 22-Sep-15 23-Sep-15
A1330 2nd/Final Coat Paint 3 3 0% 24-Sep-15 28-Sep-15
A1470 Install Flooring 5 5 0% 24-Sep-15 30-Sep-15
A1460 OFE Install 3 3 0% 29-Sep-15 01-Oct-15
A1540 Construction Clean 2 2 0% 01-Oct-15 02-Oct-15
A1340 TAB 0 0 0% 02-Oct-15
A1350 LCC/Owner/Design Punch 2 2 0% 05-Oct-15 06-Oct-15
A1360 Final Clean 2 2 0% 07-Oct-15 08-Oct-15
A1480 Substantial Completion 1 1 0% 07-Oct-15 07-Oct-15
A1370 City Inspection 1 1 0% 09-Oct-15 09-Oct-15
A1380 LCC Paperwork to Owner 1 1 0% 12-Oct-15 12-Oct-15
A1390 State Health Inspection 1 1 0% 13-Oct-15 13-Oct-15
A1400 Owner Prep/Move-In 5 5 0% 14-Oct-15 20-Oct-15
25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 07 14 21 28 04 11 18 25 02 09 16 2330
June 2015 July 2015 August 2015 S October 2015 N December 2015 January 2016 February 2016 March 2016 April 2016 May 2016June 2016
Prime/1st Coat Paint
MEP Trim-Out
Ceiling Grid Install
MEP Trim-Out Ceilings
Above Ceiling Inspection
Drop Ceiling Tile
2nd/Final Coat Paint
Install Flooring
OFE Install
Construction Clean
TAB
LCC/Owner/Design Punch
Final Clean
Substantial Completion
City Inspection
LCC Paperwork to Owner
State Health Inspection
Owner Prep/Move-In
Page 2 of 2
Activity ID Activity Name Original
Duration
Remaining
Duration
Duration
%
Complete
Start Finish
West Park Hospital Build out and RenovationWest Park Hospital Build out and Renovation435 147 66.21% 17-Apr-14 A 16-Dec-15
Project OverviewProject Overview 435 147 66.21% 17-Apr-14 A 16-Dec-15
Phase 2; Cedar Mountain RenovationPhase 2; Cedar Mountain Renovation 124 124 0% 26-May-15 13-Nov-15
Phase 3; Dietary / Dinning RenovationPhase 3; Dietary / Dinning Renovation 176 125 28.98% 26-Jan-15 A 16-Nov-15
A4520 Start Dietary 0 0 100% 26-Jan-15 A
A4700 Education Release MEP Underslab 0 0 100% 27-Feb-15 A
A4710 Education GMP 0 0 100% 13-Apr-15 A
A4540 Overall Construction Duration 162 114 29.63% 26-Jan-15 A 03-Nov-15
A4720 Reissue Drawings State Review 0 0 0% 01-Jun-15*
A4670 OFE Install/Kitchen Equipment 15 15 0% 21-Sep-15 09-Oct-15
A4640 LCC Paperwork to Owner 5 5 0% 15-Oct-15 21-Oct-15*
A4630 Substantial Completion 0 0 0% 21-Oct-15*
A4530 Finish Dietary 0 0 0% 03-Nov-15
A4650 Owner/Prep Move-in 5 5 0% 04-Nov-15 10-Nov-15
A4660 State Health Inspection 0 0 0% 04-Nov-15
Area DArea D 141 90 36.3% 26-Jan-15 A 28-Sep-15
A3360 Excavation for new ductwork 5 0 100% 16-Mar-15 A 14-Apr-15 A
A3370 Demo Concrete wall and slabs for ductwork 3 0 100% 10-Mar-15 A 11-Mar-15 A
A3380 Sand bedding for new ductwork 3 0 100% 19-Mar-15 A 13-Apr-15 A
A3720 Build ICRA Walls 3 0 100% 26-Jan-15 A 29-Jan-15 A
A3730 Locate underground MEP 1 0 100% 26-Jan-15 A 30-Jan-15 A
A3740 Layout All new Underground MEP 2 0 100% 02-Feb-15 A 04-Feb-15 A
A3750 Demo above ceiling MEP in excavating area2 0 100% 10-Feb-15 A 13-Feb-15 A
A4390 Make Ready/Equipment/ICRA 5 0 100% 26-Jan-15 A 30-Jan-15 A
A4680 Education Release MEP Underslab 1 0 100% 27-Feb-15 A 27-Feb-15 A
A4690 Education GMP 1 0 100% 26-Mar-15 A 27-Mar-15 A
A3390 Underground ductwork 5 0 100% 19-Mar-15 A 17-Apr-15 A
A3400 Prep and pour flowable fill around ductwork 1 0 100% 24-Mar-15 A 22-Apr-15 A
A3410 underground plumbing 5 0 100% 31-Mar-15 A 06-Apr-15 A
A3420 Underground Electrical 5 0 100% 31-Mar-15 A 06-Apr-15 A
A3430 MEP underground inspection 1 0 100% 17-Apr-15 A 20-Apr-15 A
A3440 Backfill compaction 1 0 100% 20-Apr-15 A 21-Apr-15 A
A3450 Termite Treatment 0 0 100% 20-Apr-15 A 20-Apr-15 A
A3460 Vapor Barrier/SOG prep/Form work 2 0 100% 06-May-15 A 07-May-15 A
A3470 Pre Slab Inspection 1 0 100% 07-May-15 A 07-May-15 A
A3480 Pour Slab on Grade 1 0 100% 08-May-15 A 08-May-15 A
A3490 Wet Cure Slab 5 0 100% 09-May-15 A 14-May-15 A
A3500 Framing Layout 1 0 100% 13-May-15 A 13-May-15 A
A3510 Frame Priority Walls 1 0 100% 15-May-15 A 18-May-15 A
A3520 Overhead MEP/Sprinkler 10 10 0% 26-May-15 08-Jun-15
A3530 Frame all walls 1 0 100% 15-May-15 A 18-May-15 A
25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 07 14 21 28 04 11 18 25 02 09 16 2330
June 2015 July 2015 August 2015 S October 2015 N December 2015 January 2016 February 2016 March 2016 April 2016 May 2016June 2016
LCC Final Paperwork to Ownwe for StatePhase 1 Final CompletePhase 1 Substantial Completion Phase 2; Substantial CompletionPhase 3 Substantial CompletionFinal Completion of the ProjectPhase 3 Final Complete
Overall Construction Duration
Reissue Drawings State Review
OFE Install/Kitchen Equipment
LCC Paperwork to Owner
Substantial Completion
Finish Dietary
Owner/Prep Move-in
State Health Inspection
Excavation for new ductwork
Demo Concrete wall and slabs for ductwork
Sand bedding for new ductwork
Underground ductwork
Prep and pour flowable fill around ductwork
Underground Electrical
MEP underground inspection
Backfill compaction
Termite Treatment
Vapor Barrier/SOG prep/Form work
Pre Slab Inspection
Pour Slab on Grade
Wet Cure Slab
Framing Layout
Frame Priority Walls
Overhead MEP/Sprinkler
Frame all walls
Page 1 of 4
Early Bar
Critical Bar
Actual Bar
Level of Effort
Actual Level of Effort
Project Baseline Bar
Milestone
Run Date: 02-Jun-15
Data Date: 26-May-15
Project ID: 14213-1
Layton Construction Co., Inc.
02-Jun-15 Schedule
Activity ID Activity Name Original
Duration
Remaining
Duration
Duration
%
Complete
Start Finish
A3540 In wall rough in MEP 5 10 0% 18-May-15 A 08-Jun-15
A3550 In wall inspection LCC/City 1 1 0% 09-Jun-15 09-Jun-15
A3560 Insulate/Hang drywall 3 3 0% 10-Jun-15 12-Jun-15
A3570 Frame Hardlids and Soffits 3 3 0% 12-Jun-15 16-Jun-15
A3580 Tape/Finish walls 3 3 0% 17-Jun-15 19-Jun-15
A3590 Above Ceiling Inspection 1 1 0% 19-Jun-15 22-Jun-15
A3600 Tape/Finish soffits/hard lids 3 3 0% 22-Jun-15 25-Jun-15
A3610 Prime/Paint 1st Coat walls and ceilings 3 3 0% 25-Jun-15 30-Jun-15
A3620 Ceramic Tile in Bathrooms 8 8 0% 30-Jun-15 13-Jul-15
A3630 MEP trim out bathrooms 3 3 0% 13-Jul-15 16-Jul-15
A3640 Ceiling Grid 3 3 0% 16-Jul-15 21-Jul-15
A3650 Sprinkler Drop 1 1 0% 20-Jul-15 21-Jul-15
A3660 Above ceiling punch 1 1 0% 21-Jul-15 22-Jul-15
A3670 Millwork 1 1 0% 22-Jul-15 23-Jul-15
A3680 Drop Ceiling Tile 2 2 0% 23-Jul-15 27-Jul-15
A3690 MEP Trim out ceilings 4 4 0% 27-Jul-15 31-Jul-15
A3700 Final Coat Paint 2 2 0% 31-Jul-15 04-Aug-15
A3710 LCC/AOE Punch 2 2 0% 04-Aug-15 06-Aug-15
A4610 VCT Flooring 2 2 0% 24-Sep-15 28-Sep-15
Area AArea A 129 98 24.12% 14-Apr-15 A 08-Oct-15
A3760 Excavation for new ductwork 5 0 100% 15-Apr-15 A 08-May-15 A
A3770 Demo Concrete wall and slabs for ductwork 1 1 0% 26-May-15 26-May-15
A3780 Sand bedding for new ductwork 19 0 100% 14-Apr-15 A 08-May-15 A
A3790 Underground ductwork 5 0 100% 15-Apr-15 A 18-May-15 A
A3800 Prep and pour flowable fill around ductwork 1 0 100% 13-May-15 A 14-May-15 A
A3810 underground plumbing 5 1 80% 13-May-15 A 26-May-15
A3820 Underground Electrical 2 2 0% 26-May-15 27-May-15
A3830 MEP underground inspection 1 1 0% 28-May-15 28-May-15
A3840 Backfill compaction 1 0 100% 26-May-15 A 27-May-15 A
A3850 Termite Treatment 0 0 100% 14-May-15 A 14-May-15 A
A3860 Vapor Barrier/SOG prep/Form work 3 3 0% 29-May-15 02-Jun-15
A4730 Reissue Drawings State Review 1 1 0% 01-Jun-15* 01-Jun-15
A4740 Fab and Deliver FSD/FD 20 20 0% 02-Jun-15 29-Jun-15
A3870 Pre Slab Inspection 1 1 0% 03-Jun-15 03-Jun-15
A3880 Pour Slab on Grade 1 1 0% 04-Jun-15 04-Jun-15
A3890 Wet Cure Slab 5 5 0% 05-Jun-15 09-Jun-15
A3900 Framing Layout 1 1 0% 08-Jun-15 09-Jun-15
A3910 Frame Priority Walls 2 2 0% 09-Jun-15 11-Jun-15
A4810 Install Coiling Door Steel Support 3 3 0% 09-Jun-15 12-Jun-15
A3920 Overhead MEP/Sprinkler 10 10 0% 30-Jun-15 14-Jul-15
A3930 Frame all walls 3 3 0% 14-Jul-15 16-Jul-15
A4820 Install Coiling Doors 3 3 0% 17-Jul-15 21-Jul-15
A3940 In wall rough in MEP 10 10 0% 21-Jul-15 03-Aug-15
A3950 In wall inspection LCC/City 2 2 0% 31-Jul-15 04-Aug-15
A3960 Insulate/Hang drywall 10 10 0% 04-Aug-15 18-Aug-15
25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 07 14 21 28 04 11 18 25 02 09 16 2330
June 2015 July 2015 August 2015 S October 2015 N December 2015 January 2016 February 2016 March 2016 April 2016 May 2016June 2016
In wall rough in MEP
In wall inspection LCC/City
Insulate/Hang drywall
Frame Hardlids and Soffits
Tape/Finish walls
Above Ceiling Inspection
Tape/Finish soffits/hard lids
Prime/Paint 1st Coat walls and ceilings
Ceramic Tile in Bathrooms
MEP trim out bathrooms
Ceiling Grid
Sprinkler Drop
Above ceiling punch
Millwork
Drop Ceiling Tile
MEP Trim out ceilings
Final Coat Paint
LCC/AOE Punch
VCT Flooring
Excavation for new ductwork
Demo Concrete wall and slabs for ductwork
Sand bedding for new ductwork
Underground ductwork
Prep and pour flowable fill around ductwork
underground plumbing
Underground Electrical
MEP underground inspection
Backfill compaction
Termite Treatment
Vapor Barrier/SOG prep/Form work
Reissue Drawings State Review
Fab and Deliver FSD/FD
Pre Slab Inspection
Pour Slab on Grade
Wet Cure Slab
Framing Layout
Frame Priority Walls
Install Coiling Door Steel Support
Overhead MEP/Sprinkler
Frame all walls
Install Coiling Doors
In wall rough in MEP
In wall inspection LCC/City
Insulate/Hang drywall
Page 2 of 4
Activity ID Activity Name Original
Duration
Remaining
Duration
Duration
%
Complete
Start Finish
A3970 Frame Hardlids and Soffits 5 5 0% 14-Aug-15 21-Aug-15
A3980 Tape/Finish walls 5 5 0% 21-Aug-15 28-Aug-15
A3990 Above Ceiling Inspection 1 1 0% 28-Aug-15 31-Aug-15
A4000 Tape/Finish soffits/hard lids 3 3 0% 31-Aug-15 03-Sep-15
A4010 Prime/Paint 1st Coat walls and ceilings 4 4 0% 04-Sep-15 11-Sep-15
A4040 Ceiling Grid 5 5 0% 11-Sep-15 18-Sep-15
A4050 Sprinkler Drop 3 3 0% 17-Sep-15 22-Sep-15
A4070 Millwork 5 5 0% 17-Sep-15 24-Sep-15
A4060 Above ceiling punch 2 2 0% 22-Sep-15 24-Sep-15
A4080 Drop Ceiling Tile 3 3 0% 24-Sep-15 29-Sep-15
A4090 MEP Trim out ceilings 5 5 0% 24-Sep-15 01-Oct-15
A4100 Final Coat Paint 5 5 0% 25-Sep-15 02-Oct-15
A4020 VCT Flooring 8 8 0% 28-Sep-15 08-Oct-15
A4110 LCC/AOE Punch 3 3 0% 02-Oct-15 07-Oct-15
Area BArea B 138 105 23.91% 13-Apr-15 A 21-Oct-15
A4120 Excavation for new ductwork 5 0 100% 13-Apr-15 A 08-May-15 A
A4130 Demo Concrete wall and slabs for ductwork 1 0 100% 11-May-15 A 11-May-15 A
A4140 Sand bedding for new ductwork 3 0 100% 11-May-15 A 13-May-15 A
A4150 Underground ductwork 5 0 100% 06-May-15 A 14-May-15 A
A4160 Prep and pour flowable fill around ductwork 1 0 100% 11-May-15 A 11-May-15 A
A4170 Underground plumbing 5 0 100% 29-Apr-15 A 20-May-15 A
A4180 Underground Electrical 2 0 100% 13-May-15 A 14-May-15 A
A4190 MEP underground inspection 1 0 100% 13-May-15 A 13-May-15 A
A4200 Backfill compaction 1 0 100% 13-May-15 A 13-May-15 A
A4210 Termite Treatment 0 0 100% 13-May-15 A 13-May-15 A
A4220 Vapor Barrier/SOG prep 3 3 0% 28-May-15 01-Jun-15
A4750 Reissue Drawings State Review 1 1 0% 01-Jun-15* 01-Jun-15
A4230 Pre Slab Inspection 1 1 0% 02-Jun-15 02-Jun-15
A4760 Fab and Deliver FSD/FD 20 20 0% 02-Jun-15 29-Jun-15
A4240 Pour Slab on Grade 1 1 0% 03-Jun-15 03-Jun-15
A4250 Wet Cure Slab 7 7 0% 04-Jun-15 10-Jun-15
A4770 Demo Roof for Doghouse 2 2 0% 08-Jun-15 09-Jun-15
A4780 Erect steel supports at doghouse 2 2 0% 10-Jun-15 11-Jun-15
A4260 Framing Layout 1 1 0% 10-Jun-15 11-Jun-15
A4270 Frame Priority Walls 2 2 0% 11-Jun-15 15-Jun-15
A4790 Frame/Hang/Exterior Finish Doghouse 10 10 0% 12-Jun-15 25-Jun-15
A4800 Install MEP/ Louvers at Doghouse 5 5 0% 12-Jun-15 18-Jun-15
A4280 Overhead MEP/Sprinkler 10 10 0% 30-Jun-15 14-Jul-15
A4290 Frame all walls 3 3 0% 10-Jul-15 14-Jul-15
A4300 In wall rough in MEP 10 10 0% 23-Jul-15 05-Aug-15
A4310 In wall inspection LCC/City 1 1 0% 06-Aug-15 06-Aug-15
A4320 Insulate/Hang drywall 5 5 0% 07-Aug-15 13-Aug-15
A4330 Frame Hardlids and Soffits 2 2 0% 14-Aug-15 17-Aug-15
A4340 Tape/Finish walls 3 3 0% 18-Aug-15 20-Aug-15
A4350 Above Ceiling Inspection 1 1 0% 20-Aug-15 20-Aug-15
25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 07 14 21 28 04 11 18 25 02 09 16 2330
June 2015 July 2015 August 2015 S October 2015 N December 2015 January 2016 February 2016 March 2016 April 2016 May 2016June 2016
Frame Hardlids and Soffits
Tape/Finish walls
Above Ceiling Inspection
Tape/Finish soffits/hard lids
Prime/Paint 1st Coat walls and ceilings
Ceiling Grid
Sprinkler Drop
Millwork
Above ceiling punch
Drop Ceiling Tile
MEP Trim out ceilings
Final Coat Paint
VCT Flooring
LCC/AOE Punch
Excavation for new ductwork
Demo Concrete wall and slabs for ductwork
Sand bedding for new ductwork
Underground ductwork
Prep and pour flowable fill around ductwork
Underground plumbing
Underground Electrical
MEP underground inspection
Backfill compaction
Termite Treatment
Vapor Barrier/SOG prep
Reissue Drawings State Review
Pre Slab Inspection
Fab and Deliver FSD/FD
Pour Slab on Grade
Wet Cure Slab
Demo Roof for Doghouse
Erect steel supports at doghouse
Framing Layout
Frame Priority Walls
Frame/Hang/Exterior Finish Doghouse
Install MEP/ Louvers at Doghouse
Overhead MEP/Sprinkler
Frame all walls
In wall rough in MEP
In wall inspection LCC/City
Insulate/Hang drywall
Frame Hardlids and Soffits
Tape/Finish walls
Above Ceiling Inspection
Page 3 of 4
Activity ID Activity Name Original
Duration
Remaining
Duration
Duration
%
Complete
Start Finish
A4360 Tape/Finish soffits/hard lids 3 3 0% 21-Aug-15 25-Aug-15
A4370 Prime/Paint 1st Coat walls and ceilings 5 5 0% 26-Aug-15 01-Sep-15
A4380 Ceramic Tile in Bathrooms 3 3 0% 02-Sep-15 04-Sep-15
A4480 Stonehard Flooring Kitchen 12 12 0% 02-Sep-15 18-Sep-15
A4500 MEP trim out Bathrooms 1 1 0% 02-Sep-15 02-Sep-15
A4400 Ceiling Grid 5 5 0% 03-Sep-15 10-Sep-15
A4510 Toilet Accessories / Div. 10 Specialties/ Doors and Hardware20 20 0% 03-Sep-15 01-Oct-15
A4410 Sprinkler Drop 5 5 0% 11-Sep-15 17-Sep-15
A4420 Above ceiling punch 2 2 0% 18-Sep-15 21-Sep-15
A4490 OFE Install/Kitchen Equipment 10 10 0% 21-Sep-15 02-Oct-15
A4430 Millwork 3 3 0% 22-Sep-15 24-Sep-15
A4440 Drop Ceiling Tile 3 3 0% 25-Sep-15 29-Sep-15
A4450 MEP Trim out ceilings 3 3 0% 30-Sep-15 02-Oct-15
A4620 VCT Flooring 6 6 0% 08-Oct-15 16-Oct-15
A4460 Final Coat Paint 5 5 0% 12-Oct-15 16-Oct-15
A4470 LCC/AOE Punch 3 3 0% 19-Oct-15 21-Oct-15*
CommissioningCommissioning 37 37 0% 25-Sep-15 16-Nov-15
C7640 O & M Info 10 10 0% 25-Sep-15 08-Oct-15
C7550 Point to Point Checks 2 2 0% 05-Oct-15 06-Oct-15
C7560 Pre-Commissioning, Checks / Start Up / Test 1 1 0% 07-Oct-15 07-Oct-15
C7680 Final Commissioning, Control System 1 1 0% 08-Oct-15 08-Oct-15
C7570 Startup Documentation 5 5 0% 12-Oct-15 16-Oct-15
C7580 Air Balance 2 2 0% 16-Oct-15 19-Oct-15
C7590 Water Balance 1 1 0% 16-Oct-15 16-Oct-15
C7600 Equipment Identification 2 2 0% 16-Oct-15 19-Oct-15
C7630 Owner Training 2 2 0% 16-Oct-15 19-Oct-15
C7610 Performance / Endurance Testing 4 4 0% 19-Oct-15 22-Oct-15
C7650 Final Commissioning, Electrical System 1 1 0% 20-Oct-15 20-Oct-15
C7660 Final Commissioning, Heating / Cooling and Fan System1 1 0% 20-Oct-15 20-Oct-15
C7620 Consultant/Owner Verification 2 2 0% 22-Oct-15 23-Oct-15
C7670 Final Commissioning, Fireprotection Equipment1 1 0% 26-Oct-15 26-Oct-15
C7700 Attic Stock, Keys & Certification to Owner 3 3 0% 26-Oct-15 28-Oct-15
C7690 Demonstrations 2 2 0% 27-Oct-15 28-Oct-15
C7710 Issues Test & Balance Report / Flame Spread Lab Report3 3 0% 27-Oct-15 29-Oct-15
Close OutClose Out 30 30 0% 06-Oct-15 16-Nov-15
C7760Produce As-Built Drawing 10 10 0% 06-Oct-15 19-Oct-15
C7740Fire Marshall Inspection 1 1 0% 02-Nov-15 02-Nov-15
C7770Final Clean 10 10 0% 03-Nov-15 16-Nov-15
C7800LCC Document Close-Out Submitted to Owner1 1 0% 03-Nov-15 03-Nov-15
C7750State Health Inspector / Inspection 0 0 0% 03-Nov-15
C7730State Certification 1 1 0% 16-Nov-15 16-Nov-15
25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 07 14 21 28 04 11 18 25 02 09 16 2330
June 2015 July 2015 August 2015 S October 2015 N December 2015 January 2016 February 2016 March 2016 April 2016 May 2016June 2016
Tape/Finish soffits/hard lids
Prime/Paint 1st Coat walls and ceilings
Ceramic Tile in Bathrooms
Stonehard Flooring Kitchen
MEP trim out Bathrooms
Ceiling Grid
Toilet Accessories / Div. 10 Specialties/ Doors and Hardware
Sprinkler Drop
Above ceiling punch
OFE Install/Kitchen Equipment
Millwork
Drop Ceiling Tile
MEP Trim out ceilings
VCT Flooring
Final Coat Paint
LCC/AOE Punch
O & M Info
Point to Point Checks
Pre-Commissioning, Checks / Start Up / Test
Final Commissioning, Control System
Startup Documentation
Air Balance
Water Balance
Equipment Identification
Owner Training
Performance / Endurance Testing
Final Commissioning, Electrical System
Final Commissioning, Heating / Cooling and Fan System
Consultant/Owner Verification
Final Commissioning, Fireprotection Equipment
Attic Stock, Keys & Certification to Owner
Demonstrations
Issues Test & Balance Report / Flame Spread Lab Report
Produce As-Built Drawing
Fire Marshall Inspection
Final Clean
LCC Document Close-Out Submitted to Owner
State Health Inspector / Inspection
State Certification
Page 4 of 4
Activity ID Activity Name Original
Duration
Remaining
Duration
Duration
%
Complete
Start Finish
Medical RecordsMedical Records 132 59 55.3% 16-Mar-15 A 15-Sep-15
Project Overview and MilestonesProject Overview and Milestones 131 58 55.73% 04-May-15 A 14-Sep-15
A1000 Start Medical Records 0 0 100% 04-May-15 A
A1020 Notice to Proceed 0 0 100% 04-May-15 A
A1010 Overall Construction Duration 94 53 43.62% 04-May-15 A 07-Sep-15
A1040 OFE Install 5 5 0% 25-Aug-15 31-Aug-15
A1030 LCC Document Close-Out to Owner 1 1 0% 07-Sep-15 07-Sep-15
A1050 Substantial Completion 0 0 0% 07-Sep-15
A1060 State Health Inspection 0 0 0% 08-Sep-15
A1080 OwnerPrep/Owner Move-In 5 5 0% 08-Sep-15 14-Sep-15
A1070 Finish Medical Records 0 0 0% 08-Sep-15
Interior FinishInterior Finish 132 59 55.3% 16-Mar-15 A 15-Sep-15
A1090 ICRA Setup 2 0 100% 16-Mar-15 A 04-May-15 A
A1100 Make Safe - MEP 5 0 100% 18-Mar-15 A 24-Mar-15 A
A1110 Demolition 15 0 100% 25-Mar-15 A 14-Apr-15 A
A1120 Layout 3 0 100% 15-Apr-15 A 17-Apr-15 A
A1130 Frame/Top Out Priority Walls 3 0 100% 20-Apr-15 A 29-May-15 A
A1150 Frame/Top Out All Walls 5 0 100% 23-Apr-15 A 08-May-15 A
A1140 Overhead R.I. MEP 25 3 90% 23-Apr-15 A 29-Jun-15
A1160 In-Wall R.I. MEP 10 1 90% 11-May-15 A 25-Jun-15
A1170 Overhead Fire Protection R.I. 5 5 0% 25-Jun-15 01-Jul-15
A1180 In-Wall Framing Inspection 1 1 0% 29-Jun-15 29-Jun-15
A1190 Insulate/Hang Drywall 8 8 0% 30-Jun-15 09-Jul-15
A1200 Tape/Finish Walls 5 5 0% 10-Jul-15 16-Jul-15
A1230 Prime/First Coat Walls 3 3 0% 17-Jul-15 21-Jul-15
A1240 Ceiling Grid 3 3 0% 22-Jul-15 24-Jul-15
A1260 MEP Trim-Out Walls 5 5 0% 22-Jul-15 28-Jul-15
A1250 MEP Trim-Out Ceilngs 5 5 0% 27-Jul-15 31-Jul-15
A1270 Sprinkler Head Drops 2 2 0% 27-Jul-15 28-Jul-15
A1290 Millwork 5 5 0% 27-Jul-15 31-Jul-15
A1300 Above Ceiling Punch 1 1 0% 03-Aug-15 03-Aug-15
A1310 Equipment Startup 2 2 0% 03-Aug-15 04-Aug-15
A1220 Above Ceiling Inspection 1 1 0% 04-Aug-15 04-Aug-15
A1280 Drop Ceiling Tile 3 3 0% 05-Aug-15 07-Aug-15
A1340 Pre Cx/PFC Equipment 5 5 0% 05-Aug-15 11-Aug-15
A1320 VCT-Base 8 8 0% 10-Aug-15 19-Aug-15
A1350 TAB 3 3 0% 19-Aug-15 21-Aug-15
A1330 Final Paint 3 3 0% 20-Aug-15 24-Aug-15
A1360 Commissioning 3 3 0% 24-Aug-15 26-Aug-15
A1370 Install Accessories/OFE 3 3 0% 25-Aug-15 27-Aug-15
A1380 Owner Training 2 2 0% 27-Aug-15 28-Aug-15
22 29 06 13 20 27 03 10 17 24 31 07 14 21 28
July 2015 August 2015 September 2015 October 2015
Overall Construction Duration
OFE Install
LCC Document Close-Out to Owner
Substantial Completion
State Health Inspection
OwnerPrep/Owner Move-In
Finish Medical Records
Overhead R.I. MEP
In-Wall R.I. MEP
Overhead Fire Protection R.I.
In-Wall Framing Inspection
Insulate/Hang Drywall
Tape/Finish Walls
Prime/First Coat Walls
Ceiling Grid
MEP Trim-Out Walls
MEP Trim-Out Ceilngs
Sprinkler Head Drops
Millwork
Above Ceiling Punch
Equipment Startup
Above Ceiling Inspection
Drop Ceiling Tile
Pre Cx/PFC Equipment
VCT-Base
TAB
Final Paint
Commissioning
Install Accessories/OFE
Owner Training
Page 1 of 2
Early Bar
Critical Bar
Actual Bar
Level of Effort
Actual Level of Effort
Project Baseline Bar
Milestone
Run Date: 15-Jul-15
Data Date: 25-Jun-15
Project ID: 14213.02102015
Layton Construction Co., Inc.
15-Jul-15 Schedule
Activity ID Activity Name Original
Duration
Remaining
Duration
Duration
%
Complete
Start Finish
A1390 Construction Clean 1 1 0% 28-Aug-15 28-Aug-15
A1400 LCC/AOE Punch 2 2 0% 31-Aug-15 01-Sep-15
A1410 Final Clean 2 2 0% 02-Sep-15 03-Sep-15
A1420 Fire Marshall/Local Final Inspections 1 1 0% 04-Sep-15 04-Sep-15
A1430 LCC Document Close-Out to Owner 1 1 0% 07-Sep-15 07-Sep-15
A1440 Substantial Completion 1 1 0% 07-Sep-15 07-Sep-15
A1450 State Health Inspection 1 1 0% 08-Sep-15 08-Sep-15
A1460 Owner Prep/Owner Move-In 5 5 0% 09-Sep-15 15-Sep-15
22 29 06 13 20 27 03 10 17 24 31 07 14 21 28
July 2015 August 2015 September 2015 October 2015
Construction Clean
LCC/AOE Punch
Final Clean
Fire Marshall/Local Final Inspections
LCC Document Close-Out to Owner
Substantial Completion
State Health Inspection
Owner Prep/Owner Move-In
Page 2 of 2
West Park Hospital Phase III (2nd Floor patient build�out)
Section 03 – Change Order Log
West Park Hospital Phase III (2nd Floor patient build�out)
Section 04 – Submittal Log
Layton Construction Co., Inc.
Project 14213 - West Park Hospital Ph 3 - CodySUBMITTAL LOG
107/29/2015
07:22 AMTime:Date:Page: of 1
03
05
07
09
21
PL030353-01
C051200-04
E051200-01
C073113-01
C096519-01
CM096800-02
C211000-03
Submittal Id
Miscellaneous Cast in Place Concrete
Connector - Revised Erection DrawingsEducation Erection and Shop Drawings
Connector Asphalt Shingles
Connector Resilient Tile Flooring
Cedar Mountain - Flooring Finishes Shop Drawings ASI 03
Connector - New Dry Valve Location
Title
Out For Approval
Out For ApprovalOut For Approval
Out For Approval
Out For ApprovalOut For Approval
Out For Approval
Status From Sub From Architect
1
1
1
1
1
1
1
LastRev.
06/29/2015
06/22/2015
06/09/2015
07/08/2015
07/27/2015
From Sub
06/29/2015
06/08/2015
06/09/2015
06/22/2015
06/09/2015
07/08/2015
07/27/2015
To Architect From Architect To Sub
Johnson, Johnson, Crabtree Architects P.C.
Johnson, Johnson, Crabtree Architects P.C.Johnson, Johnson, Crabtree Architects P.C.
Johnson, Johnson, Crabtree Architects P.C.
Johnson, Johnson, Crabtree Architects P.C.Johnson, Johnson, Crabtree Architects P.C.
Johnson, Johnson, Crabtree Architects P.C.
ResponsibilityRequired Forwarded
Project: 14213
Operator:Run Time:Run Date:
Report Code:
07/29/201507:22 AMGBALDWIN
Report ParametersEND OF REPORT
Package:
Responsibility Partner:
Status: OTFRAPP
Spec Section:
Spec Section:
Spec Section:
Spec Section:
Spec Section:
From Specification Section: To Specification Section:
Break By: Spec. Section (S)
Responsibility Partner Type:Received From Partner:Received From Partner Type:Sent To Partner:Sent To Partner Type:Returned By Partner:Returned By Partner Type:Forwarded To Partner:Forwarded To Partner Type:
Sort By: Submittal Sort Order
ReturnedSentReceived
TLCPM3041
West Park Hospital Phase III (2nd Floor patient build�out)
Section 05 – RFI Log
14213 - West Park Hospital Ph 3 - Cody
REQUEST FOR INFORMATION LOG
Layton Construction Co., Inc. 07/29/201507:21 AM
Page: of1
14213
RFINumber Cost Subject From Company To Company
Date Created
DateRequired
DateAnswered Status Answered By
Date:Time:Job:
1
RFI-0127
RFI-0134
RFI-0140
Education - Skyfold Door Existing Beam Clash
Dietary - Wall Rating/Duct Clarification
Cedar Mountain - Hydronic System Clarifications
Layton Construction Co., Inc.
Layton Construction Co., Inc.
Layton Construction Co., Inc.
Johnson, Johnson, Crabtree Architects P.C.
Johnson, Johnson, Crabtree Architects P.C.
Johnson, Johnson, Crabtree Architects P.C.
06/25/2015
07/06/2015
07/28/2015
07/02/2015
07/13/2015
08/04/2015
Open
Open
Open
Project:Sent To:
14213
Operator:Run Time:Run Date:
Report Code:
07/29/201507:21 AMGBALDWINPM3011
Report Parameters
END OF REPORT
Restrict Value of: From Date:To Date:
Status Class:
Create Date
Status:
Basin Mechanical, Inc. WILL POINDEXTER
Co-Author:
Co-Author:
Co-Author:
Potentially
Potentially
Potentially
Co-Author RFI #:
Co-Author RFI #:
Co-Author RFI #:
West Park Hospital Phase III (2nd Floor patient build�out)
Section 06 – Progress Photos
Building Connector
Parking Lot
5
Progress Photos
Dietary Area A Dry Wall
Connector Slab on Deck
6
Connector Exterior Framing
Connector Fireproofing
7
Cedar Mountain Top-out and Fireproofing
Dietary Area B Dry Wall