West Onslow Beach/ Topsail Beach Coastal Storm Damage Reduction Project

11
US Army Corps of Engineers BUILDING STRONG ® West Onslow Beach/ Topsail Beach Coastal Storm Damage Reduction Project Town of Topsail Beach Board of Commissioners Brief July 9, 2014 Presented by U.S. Army Corps of Engineers Wilmington District

description

West Onslow Beach/ Topsail Beach Coastal Storm Damage Reduction Project. Town of Topsail Beach Board of Commissioners Brief July 9, 2014. Presented by U.S. Army Corps of Engineers Wilmington District. OVERVIEW. Project Update: Current Status Process to get to a Federal Project: Steps - PowerPoint PPT Presentation

Transcript of West Onslow Beach/ Topsail Beach Coastal Storm Damage Reduction Project

US Army Corps of Engineers

BUILDING STRONG®

West Onslow Beach/Topsail BeachCoastal Storm Damage Reduction Project

Town of Topsail BeachBoard of Commissioners BriefJuly 9, 2014

Presented by U.S. Army Corps of EngineersWilmington District

BUILDING STRONG®

OVERVIEW Project Update: Current Status Process to get to a Federal Project: Steps Project History: How did we get where we are? Project Description and Cost: What will the

Federal Project achieve? Fiscal Overview: How much have we spent and

on what? Project Authorization – FINALLY! The Path to Construction

2

BUILDING STRONG®

PROJECT UPDATE

General Reevaluation Report defining the project was approved in final form in 2009

Preconstruction, Engineering and Design Phase of Work: preliminary design documentation completed

Project is ready for preparation of construction documents once real estate acquisition has been completed

Project authorization received in 2014

3

BUILDING STRONG®

PROCESS TO GET TO A FEDERAL PROJECT

Request from a local entity and, in most cases, Congressional study authority

Cost-shared study completion to identify Federal interest in a potential project

Cost-shared preconstruction, engineering and design for preparation of project plans and specifications

Project authorization (can occur at any time after study completion) Construction appropriation/Project Partnership Agreement

Execution Real Estate Acquisition Construction Contract Award

4

BUILDING STRONG®

WOB/TOPSAIL BEACH PROJECT HISTORY

5

4 Congressional study resolutions were used to undertake the original Feasibility Study that recommended a project at Topsail Beach. Feasibility Report was completed in 1990.

Project was authorized in Water Resources Development Act of 1992

Design activities were completed in 1992; Town decided not to sign the Project Cooperation Agreement

Request was received to re-look at a Federal project in late 1990s, and General Reevaluation Report (GRR) was completed between 2001-2009

Design activities for modified project were initiated in 2010 and preliminary design was completed in 2014

Locally Preferred project was authorized in WRRDA 2014

BUILDING STRONG®

UPDATEDAUTHORIZED PROJECT

6

BUILDING STRONG®

UPDATEDAUTHORIZED PROJECT

7

Project life: 50 yearsInitial construction cost: $39.4M ($25.6M Fed/$13.8M Non-Fed)Renourishment cost/life: $265.5M ($132.8M Fed/$132.8M non-Fed)

23,200 feet longDune and Berm

BUILDING STRONG®

FINANCIAL SUMMARYPROJECT PHASE FEDERAL NON-FEDERAL TOTAL

COST

Feasibility Report (1990) $963,000 $963,000

Project Design $346,200 $115,400 $461,600

GRR (2001-2009)

75/25 cost share $2,025,750 $675,250 $2,701,000

50/50 cost share $ 499,000 $499,000 $ 998,000

$2,524,750 $1,174,250 $3,699,000

Project Design $685,500 $228,500 $914,000

TOTALS: $4,519,450 $1,518,150 $6,037,600

Available funds remaining: $25k (coordination, budget process, PPA dev)

Additional funds required for Econ Update: $60k ($45 Fed/$15 non-Fed)

8

BUILDING STRONG®

PROJECT AUTHORIZATION

AT LAST:

Water Resources Reform and

Development Act of 2014

9

BUILDING STRONG®

THE PATH TO CONSTRUCTION

10

Complete economic/project cost update

Request and receive construction funds

Develop and execute a Project Partnership Agreement

Obtain Real Estate

Finalize construction bid documents

Award construction contract and initiate construction

BUILDING STRONG®

QUESTIONS?

BOTTOM LINE:13 years to study, design and authorize a projectOver $4.5M Fed and $1.5 Non-Fed funds invested to dateOver $150M Fed funding share once construction has initiatedProject authorization allows us finally to request funds for construction

Federal Project life: 50 yearsFederal Non-Fed Total

Initial construction cost: $25.6M $13.8M $39.4MRenourishment cost/life: $132.8M $132.8M $265.6M

TOTAL: $158.4M $146.6M $305M

11