West Elementary School May 16, 2006 - 100% Construction Documents.
-
Upload
maci-stevers -
Category
Documents
-
view
213 -
download
0
Transcript of West Elementary School May 16, 2006 - 100% Construction Documents.
PRIME CONSTRUCTION CONTRACTS
1. General Construction
2. SItework
3. Food Facilities Equipment
4. Mechanical Construction
5. Electrical Construction
6. Temperature Controls
ALTERNATE BIDS
1A. Schlage Locks
1B. Sargent Locks
2. Terrazzo Flooring in Main Lobby & Main Corridor
3. Terrazzo Flooring in Cafeteria
4. Wood Flooring in Gymnasium
5. Vinyl Wall Covering in Admin. Areas
6. Blue Glass & Blue Storefront frames
7. Additional Storage Cabinets Above Cubbies in Classrooms
8. Two Additional Classrooms on 2-4 Classroom Wing
9. Altro Sheet Vinyl Floor in Kitchen (Deduct)
10. Perforated, Wavy Ceiling Panels in Corridors
11. Ceramic Wall Tile in Staff Toilets 115 & 116 on wet walls
12. FRP Exterior Doors
13. Baseball & Soccer/Football Fields
COST ESTIMATECLARK PLEASANT - WEST ELEMENTARY SCHOOL DRAFT FOR DESIGN TEAMClark Pleasant, Indiana SCOPE REVIEW
95% Construction Document Cost Projection - Revision 2
System System
% Cost/GSF CostSubstructure 5.05% 7.18$ 750,634
Structural Frame 8.50% 12.09$ 1,263,959
Roofing 5.38% 7.65$ 800,210
Exterior Walls 12.21% 17.37$ 1,815,841
Interior Subdivision 7.88% 11.21$ 1,171,937
Vertical Circulation 0.12% 0.17$ 17,422
Wall Finishes 1.69% 2.41$ 251,548
Floor Finishes 2.27% 3.23$ 337,242
Ceiling Finishes 2.35% 3.34$ 349,302
Millwork & Specialties 0.40% 0.57$ 59,329
Casework 1.70% 2.41$ 252,380
Equipment (Excluding Food Service) 1.16% 1.65$ 173,004
48.68% 69.27$ 7,242,808 General Conditions 2.69% 3.83$ 400,000 General Contractor's Overhead & Profit 6.00% 3.08% 4.39$ 458,569 Contractor's Performance/Payment Bonds 1.00% 0.54% 0.77$ 81,014
TOTAL GENERAL CONSTRUCTION 55.00% 78.26$ 8,182,391
SITE DEVELOPMENT 14.40% 20.48$ 2,141,745
FOOD SERVICE EQUIPMENT 2.27% 3.23$ 338,100
MECHANICAL - Fire Protection 1.09% 1.55$ 162,408 - Plumbing 4.73% 6.72$ 703,010 - HVAC 12.11% 17.23$ 1,801,388
ELECTRICAL (Excluding Technology) 10.41% 14.81$ 1,548,228
TECHNOLOGY SYSTEMS (Wiring & Racks) By Owner
100.00% 142.29$ 14,877,270 Design/Escalation Contingency 2.84% 4.04$ 422,730 -$
TOTAL CONSTRUCTION COST 146.33$ 15,300,000$
PROJECT SCHEDULE
April 25, 2006 – May 9, 2006 Cost Estimate Prepared for Bid Package #2 – 95% Construction Documents
May 15, 2005 Construction Documents are complete
May 16, 2006 Board Approval of Bid Package #2 Construction Documents
May 22, 2006 Construction Documents available to Contractors
May 31, 2006 Pre-bid Meeting
June 16, 2006 Bids Due
June 20, 2006 Board Approval of Bids
June 26, 2006 – July 27, 2007 Construction
July 30, 2007 – August 10, 2007 Owner Move In