Welcome
CONSULTANT : DDF CONSULTANT PVT. LTD
CONTRACTOR : AHLUWALIA CONTRACTS (I) LTD
CLIENT : BUILDING CONSTRUCTION
DEPT. , BIHAR
Project Synopsis Nature of Work : CONSTRUCTION OF BIHAR POLICE BHAWAN, PATNA BIHAR (Includes the composite work for Civil, Plumbing, Electrical, Lift works and Misc. Work)
Client : BUILDING CONSTRUCTION DEPARTMENT ( GOVT. OF BIHAR ) Contractor : AHLUWALIA CONTRACTS INDIA LIMITED , NEW DELHI-110020 Consultant : DDF CONSULTANT PVT. LTD. , NEW DELHI - 110034 Environmental Clearance Certificate : Received from SEIAA, Bihar on 29 Sept 2014 Contract Agreement No. with Date : SBD No. 09-14/15 on 17 Oct 2014 Type of Contract : ITEM RATE ( BOQ ) Uniqueness of Project : Bihar’s First Building based on Base Isolation Technology (Mitigation of Earthquake loads) Griha 4 Star (Green Rating for Integrated Habitat Assessment) and LEED Platinum Rating
(Quality and Standard Method of Execution) Proposed Campus Area : 28, 322 SQM ( Approx. 7 Acres ) Proposed Built Up Area : 54, 716 SQM Approximate Height of Building : 40 Meter Original Contract Value : INR 335,00,98,113 Commencement Date : 29 Sept 2014 Project Duration : 24 Months Date of Completion : 28 Sept 2016 Defect Liability Period : 3 Years Performance Guarantee : 2 % of the Contract Value Mobilizations Advance : 5 % of the Contract Value Security Deposit : 10 % of the Contract Value
Main Building (B+S+6)
Pile Work - 100 % Completed
Pile Cap - 100 % Completed
LRB – 100% Completed
Stilt Floor Casting – 100%
First Floor Casting – 100%
Second Floor Casting-100%
Third Floor Casting-100%
Fourth Floor – 60%
Fifth Floor – 50 %
Brickwork : In Progress
Plastering : In Progress
Main Building (B+S+6)
Pile Work - 100 % Completed
Pile Cap - 100 % Completed
LRB – 100% Completed
Stilt Floor Casting – 100%
First Floor – 100%
Brickwork : In Progress
Main Building (B+S+6)
Pile Work - 100 % Completed
Pile Cap - 100 % Completed
LRB – 100% Completed
Stilt Floor Casting – 100% Completed
First Floor – 50% Completed
Main Building (B+S+6)
Pile Work - 100 % Completed
Pile Cap - 100 % Completed
LRB – 100% Completed
Stilt Floor Casting – 100%
First Floor – 100%
Brickwork in Progress
Main Building (B+S+6)
Pile Work - 100 % Completed
Pile Cap - 100 % Completed
LRB – 100% Completed
Stilt Floor Casting – 100%
First Floor Casting – 100%
Second Floor Casting- 100%
Third Floor – 60%
Fourth Floor – 50 %
Brickwork : In Progress
OFFICER ACCOMODATION(DORMITORY) O F F I C E R A C C O M O D A T I O N
50
50
5000
G+4 Building ( For 30 Persons )
No. of beds on each floor : 10
UP
UP
Dormitory Block (S+4)
Piling work - 100%
completed
Structure Work upto
Terrace Floor – 100%
Completed
Finishing Work in Progress
AUDITORIUM F L O O R A C T I V I T I E S
Auditorium will composed of following :
1.Auditorium – 400capacity (approx. ) 2.Seminar Hall (2 nos. – 150 each) 3.Exhibition Area 4.Lounge 5.Artists’ Area 6. Simulation area
Special Features •Audio/Visual system •PA system •Stage Lighting •Non-conventional Energy – Solar •Landscaping & Horticulture •Signage
Auditorium Building
Pile Work - 100 %
Completed
Structural Work – 90
% Completed
Finishing Work in
Progress
Plinth Area - 2400
SQM
Transit Block
Pile Work - 100 %
Completed
Structural Work – 100 %
Completed
Finishing Work in Progress
MOCK UP FLAT COMPLETED
Electrical Sub-Station and Services
Pile Work - 100 %
Completed
Structural Work – 100 %
Completed
Finishing Work in
Progress