Welcome [] · Welcome CONSULTANT : DDF CONSULTANT PVT. ... Finishing Work in Progress . AUDITORIUM...

23
Welcome CONSULTANT : DDF CONSULTANT PVT. LTD CONTRACTOR : AHLUWALIA CONTRACTS (I) LTD CLIENT : BUILDING CONSTRUCTION DEPT. , BIHAR

Transcript of Welcome [] · Welcome CONSULTANT : DDF CONSULTANT PVT. ... Finishing Work in Progress . AUDITORIUM...

Welcome

CONSULTANT : DDF CONSULTANT PVT. LTD

CONTRACTOR : AHLUWALIA CONTRACTS (I) LTD

CLIENT : BUILDING CONSTRUCTION

DEPT. , BIHAR

Project Synopsis Nature of Work : CONSTRUCTION OF BIHAR POLICE BHAWAN, PATNA BIHAR (Includes the composite work for Civil, Plumbing, Electrical, Lift works and Misc. Work)

Client : BUILDING CONSTRUCTION DEPARTMENT ( GOVT. OF BIHAR ) Contractor : AHLUWALIA CONTRACTS INDIA LIMITED , NEW DELHI-110020 Consultant : DDF CONSULTANT PVT. LTD. , NEW DELHI - 110034 Environmental Clearance Certificate : Received from SEIAA, Bihar on 29 Sept 2014 Contract Agreement No. with Date : SBD No. 09-14/15 on 17 Oct 2014 Type of Contract : ITEM RATE ( BOQ ) Uniqueness of Project : Bihar’s First Building based on Base Isolation Technology (Mitigation of Earthquake loads) Griha 4 Star (Green Rating for Integrated Habitat Assessment) and LEED Platinum Rating

(Quality and Standard Method of Execution) Proposed Campus Area : 28, 322 SQM ( Approx. 7 Acres ) Proposed Built Up Area : 54, 716 SQM Approximate Height of Building : 40 Meter Original Contract Value : INR 335,00,98,113 Commencement Date : 29 Sept 2014 Project Duration : 24 Months Date of Completion : 28 Sept 2016 Defect Liability Period : 3 Years Performance Guarantee : 2 % of the Contract Value Mobilizations Advance : 5 % of the Contract Value Security Deposit : 10 % of the Contract Value

Wing-V

Wing-IV

Wing-III

Wing-II Wing-I

P E R S P E C T I V E V I E W N I G H T V I E W

Main Building (B+S+6)

Pile Work - 100 % Completed

Pile Cap - 100 % Completed

LRB – 100% Completed

Stilt Floor Casting – 100%

First Floor Casting – 100%

Second Floor Casting-100%

Third Floor Casting-100%

Fourth Floor – 60%

Fifth Floor – 50 %

Brickwork : In Progress

Plastering : In Progress

Main Building (B+S+6)

Pile Work - 100 % Completed

Pile Cap - 100 % Completed

LRB – 100% Completed

Stilt Floor Casting – 100%

First Floor – 100%

Brickwork : In Progress

Main Building (B+S+6)

Pile Work - 100 % Completed

Pile Cap - 100 % Completed

LRB – 100% Completed

Stilt Floor Casting – 100% Completed

First Floor – 50% Completed

Main Building (B+S+6)

Pile Work - 100 % Completed

Pile Cap - 100 % Completed

LRB – 100% Completed

Stilt Floor Casting – 100%

First Floor – 100%

Brickwork in Progress

Main Building (B+S+6)

Pile Work - 100 % Completed

Pile Cap - 100 % Completed

LRB – 100% Completed

Stilt Floor Casting – 100%

First Floor Casting – 100%

Second Floor Casting- 100%

Third Floor – 60%

Fourth Floor – 50 %

Brickwork : In Progress

OFFICER ACCOMODATION(DORMITORY) O F F I C E R A C C O M O D A T I O N

50

50

5000

G+4 Building ( For 30 Persons )

No. of beds on each floor : 10

UP

UP

Dormitory Block (S+4)

Piling work - 100%

completed

Structure Work upto

Terrace Floor – 100%

Completed

Finishing Work in Progress

AUDITORIUM F L O O R A C T I V I T I E S

Auditorium will composed of following :

1.Auditorium – 400capacity (approx. ) 2.Seminar Hall (2 nos. – 150 each) 3.Exhibition Area 4.Lounge 5.Artists’ Area 6. Simulation area

Special Features •Audio/Visual system •PA system •Stage Lighting •Non-conventional Energy – Solar •Landscaping & Horticulture •Signage

Auditorium Building

Pile Work - 100 %

Completed

Structural Work – 90

% Completed

Finishing Work in

Progress

Plinth Area - 2400

SQM

Transit Block

Pile Work - 100 %

Completed

Structural Work – 100 %

Completed

Finishing Work in Progress

MOCK UP FLAT COMPLETED

Electrical Sub-Station and Services

Pile Work - 100 %

Completed

Structural Work – 100 %

Completed

Finishing Work in

Progress

Wing-1

Wing-2

Dormitory

ESS Stockyard