Transcript of Welcome to SNOLAB David Sinclair. Welcome to our new Building Note – Building is still under...
![Page 1: Welcome to SNOLAB David Sinclair. Welcome to our new Building Note – Building is still under construction Note – Building is still under construction.](https://reader035.fdocuments.in/reader035/viewer/2022062314/56649e175503460f94b01f5b/html5/thumbnails/1.jpg)
Welcome to SNOLAB
David Sinclair
![Page 2: Welcome to SNOLAB David Sinclair. Welcome to our new Building Note – Building is still under construction Note – Building is still under construction.](https://reader035.fdocuments.in/reader035/viewer/2022062314/56649e175503460f94b01f5b/html5/thumbnails/2.jpg)
Welcome to our new Welcome to our new BuildingBuilding
Note – Building is still under Note – Building is still under constructionconstruction
Please stay out of lab spacePlease stay out of lab space Elevator is currently freight onlyElevator is currently freight only Fire alarm is slow bell – evacuate Fire alarm is slow bell – evacuate
buildingbuilding
![Page 3: Welcome to SNOLAB David Sinclair. Welcome to our new Building Note – Building is still under construction Note – Building is still under construction.](https://reader035.fdocuments.in/reader035/viewer/2022062314/56649e175503460f94b01f5b/html5/thumbnails/3.jpg)
![Page 4: Welcome to SNOLAB David Sinclair. Welcome to our new Building Note – Building is still under construction Note – Building is still under construction.](https://reader035.fdocuments.in/reader035/viewer/2022062314/56649e175503460f94b01f5b/html5/thumbnails/4.jpg)
![Page 5: Welcome to SNOLAB David Sinclair. Welcome to our new Building Note – Building is still under construction Note – Building is still under construction.](https://reader035.fdocuments.in/reader035/viewer/2022062314/56649e175503460f94b01f5b/html5/thumbnails/5.jpg)
![Page 6: Welcome to SNOLAB David Sinclair. Welcome to our new Building Note – Building is still under construction Note – Building is still under construction.](https://reader035.fdocuments.in/reader035/viewer/2022062314/56649e175503460f94b01f5b/html5/thumbnails/6.jpg)
Underground ProgressUnderground Progress
Excavation progressing well ~50% of Excavation progressing well ~50% of Phase I completePhase I complete
Raise bore to 6700/6600 completeRaise bore to 6700/6600 complete
![Page 7: Welcome to SNOLAB David Sinclair. Welcome to our new Building Note – Building is still under construction Note – Building is still under construction.](https://reader035.fdocuments.in/reader035/viewer/2022062314/56649e175503460f94b01f5b/html5/thumbnails/7.jpg)
Underground FacilitiesUnderground Facilities
![Page 8: Welcome to SNOLAB David Sinclair. Welcome to our new Building Note – Building is still under construction Note – Building is still under construction.](https://reader035.fdocuments.in/reader035/viewer/2022062314/56649e175503460f94b01f5b/html5/thumbnails/8.jpg)
![Page 9: Welcome to SNOLAB David Sinclair. Welcome to our new Building Note – Building is still under construction Note – Building is still under construction.](https://reader035.fdocuments.in/reader035/viewer/2022062314/56649e175503460f94b01f5b/html5/thumbnails/9.jpg)
Features of underground Features of underground spacespace
All space within a common clean boundary All space within a common clean boundary (~class 2000)(~class 2000)
Common infrastructure includes dirty-Common infrastructure includes dirty-clean transition and materials handling, clean transition and materials handling, power (~1.5 MW), cooling (300 T), water, power (~1.5 MW), cooling (300 T), water, UPW, networking (Gb/s off site, high speed UPW, networking (Gb/s off site, high speed internal) and clean ventilation systeminternal) and clean ventilation system
Design allows for future expansion but Design allows for future expansion but scale is limitedscale is limited
![Page 10: Welcome to SNOLAB David Sinclair. Welcome to our new Building Note – Building is still under construction Note – Building is still under construction.](https://reader035.fdocuments.in/reader035/viewer/2022062314/56649e175503460f94b01f5b/html5/thumbnails/10.jpg)
![Page 11: Welcome to SNOLAB David Sinclair. Welcome to our new Building Note – Building is still under construction Note – Building is still under construction.](https://reader035.fdocuments.in/reader035/viewer/2022062314/56649e175503460f94b01f5b/html5/thumbnails/11.jpg)
![Page 12: Welcome to SNOLAB David Sinclair. Welcome to our new Building Note – Building is still under construction Note – Building is still under construction.](https://reader035.fdocuments.in/reader035/viewer/2022062314/56649e175503460f94b01f5b/html5/thumbnails/12.jpg)
![Page 13: Welcome to SNOLAB David Sinclair. Welcome to our new Building Note – Building is still under construction Note – Building is still under construction.](https://reader035.fdocuments.in/reader035/viewer/2022062314/56649e175503460f94b01f5b/html5/thumbnails/13.jpg)
![Page 14: Welcome to SNOLAB David Sinclair. Welcome to our new Building Note – Building is still under construction Note – Building is still under construction.](https://reader035.fdocuments.in/reader035/viewer/2022062314/56649e175503460f94b01f5b/html5/thumbnails/14.jpg)
![Page 15: Welcome to SNOLAB David Sinclair. Welcome to our new Building Note – Building is still under construction Note – Building is still under construction.](https://reader035.fdocuments.in/reader035/viewer/2022062314/56649e175503460f94b01f5b/html5/thumbnails/15.jpg)
![Page 16: Welcome to SNOLAB David Sinclair. Welcome to our new Building Note – Building is still under construction Note – Building is still under construction.](https://reader035.fdocuments.in/reader035/viewer/2022062314/56649e175503460f94b01f5b/html5/thumbnails/16.jpg)
![Page 17: Welcome to SNOLAB David Sinclair. Welcome to our new Building Note – Building is still under construction Note – Building is still under construction.](https://reader035.fdocuments.in/reader035/viewer/2022062314/56649e175503460f94b01f5b/html5/thumbnails/17.jpg)
Underground ScheduleUnderground Schedule
ExcavationExcavation Entry – now – 1 NovemberEntry – now – 1 November Ladder – now – 1 NovemberLadder – now – 1 November Rectangular hall – 1 November – 9 MayRectangular hall – 1 November – 9 May Cryopit – 10 May – 1 December/06Cryopit – 10 May – 1 December/06
![Page 18: Welcome to SNOLAB David Sinclair. Welcome to our new Building Note – Building is still under construction Note – Building is still under construction.](https://reader035.fdocuments.in/reader035/viewer/2022062314/56649e175503460f94b01f5b/html5/thumbnails/18.jpg)
Underground ScheduleUnderground Schedule
OutfittingOutfitting Finalize contract package – 30 Finalize contract package – 30
SeptemberSeptember Award contract – 14 JanuaryAward contract – 14 January Entry 14Feb/06 – 13 JuneEntry 14Feb/06 – 13 June Ladder 14 June – 11 OctLadder 14 June – 11 Oct Rectangular hall 12 Oct – 8 February 07Rectangular hall 12 Oct – 8 February 07
![Page 19: Welcome to SNOLAB David Sinclair. Welcome to our new Building Note – Building is still under construction Note – Building is still under construction.](https://reader035.fdocuments.in/reader035/viewer/2022062314/56649e175503460f94b01f5b/html5/thumbnails/19.jpg)
Science ProgrammeScience Programme
Scientific programme established Scientific programme established through series of workshopsthrough series of workshops
This marks the 4This marks the 4thth in the series in the series Try to define likely first experiments Try to define likely first experiments
and the long term roadmapand the long term roadmap
![Page 20: Welcome to SNOLAB David Sinclair. Welcome to our new Building Note – Building is still under construction Note – Building is still under construction.](https://reader035.fdocuments.in/reader035/viewer/2022062314/56649e175503460f94b01f5b/html5/thumbnails/20.jpg)
External CommitteesExternal Committees
Experiments Advisory Experiments Advisory CommitteeCommittee
B. Barish/A HimeB. Barish/A Hime B. BalantenkinB. Balantenkin C. BurgessC. Burgess T. KajitaT. Kajita J. MartinJ. Martin K. RaganK. Ragan K. ScholbergK. Scholberg D. WarkD. Wark
Science and Technical Science and Technical CommitteeCommittee
G. OakhamG. Oakham E. BlackmoreE. Blackmore G. Greer (Inco)G. Greer (Inco) J. MartinJ. Martin
![Page 21: Welcome to SNOLAB David Sinclair. Welcome to our new Building Note – Building is still under construction Note – Building is still under construction.](https://reader035.fdocuments.in/reader035/viewer/2022062314/56649e175503460f94b01f5b/html5/thumbnails/21.jpg)
The Selection ProcessThe Selection Process
Proponents submit LOIProponents submit LOI EEC reviews LOI, requests additional EEC reviews LOI, requests additional
inputinput Proponents provide input, make Proponents provide input, make
presentationpresentation EEC makes recommendation based on EEC makes recommendation based on
science/technical feasibility/fit to science/technical feasibility/fit to facility etc. Conditional approval!facility etc. Conditional approval!
Proponents obtain fundingProponents obtain funding
![Page 22: Welcome to SNOLAB David Sinclair. Welcome to our new Building Note – Building is still under construction Note – Building is still under construction.](https://reader035.fdocuments.in/reader035/viewer/2022062314/56649e175503460f94b01f5b/html5/thumbnails/22.jpg)
Selection ProcessSelection Process
Proponents do detailed designProponents do detailed design SNOLAB participates in design review SNOLAB participates in design review
process – Aim is to find solutionsprocess – Aim is to find solutions Experiment is carried outExperiment is carried out
![Page 23: Welcome to SNOLAB David Sinclair. Welcome to our new Building Note – Building is still under construction Note – Building is still under construction.](https://reader035.fdocuments.in/reader035/viewer/2022062314/56649e175503460f94b01f5b/html5/thumbnails/23.jpg)