ArcelorMittal Dofasco currently has Site Specific Standards (SSS) under Ontario Regulation 419/05. In this meeting we are sharing information on the 2015-2020 SSS Application. Feel free to review information presented: The display panels share information about ArcelorMittal Dofasco’s application and the Ministry of the Environment and Climate Change’s (MOECC’s) process. Please ask questions: Staff are available to respond to your questions. Please provide feedback: Comment forms are available so you can provide us with your feedback. Welcome

Transcript of Welcome...

Page 1: Welcome [dofasco.arcelormittal.com]dofasco.arcelormittal.com/~/media/Files/A/Arcelormittal-Canada... · Standards (SSS) under Ontario ... • Acquired by ArcelorMittal in 2006-2007.

ArcelorMittal Dofasco currently has Site SpecificStandards (SSS) under Ontario Regulation419/05. In this meeting we are sharinginformation on the 2015-2020 SSS Application.

• Feel free to review information presented:The display panels share information aboutArcelorMittal Dofasco’s application and the Ministry ofthe Environment and Climate Change’s (MOECC’s)process.

• Please ask questions:Staff are available to respond to your questions.

• Please provide feedback:Comment forms are available so you can provide uswith your feedback.

Welcome

Page 2: Welcome [dofasco.arcelormittal.com]dofasco.arcelormittal.com/~/media/Files/A/Arcelormittal-Canada... · Standards (SSS) under Ontario ... • Acquired by ArcelorMittal in 2006-2007.

• Established in 1912 as Dominion Steel Castings Co. Ltd.• Acquired by ArcelorMittal in 2006-2007.• Canada’s largest integrated steel producer.• 5,400 employees / more than 20,000 indirect jobs in region.• Key player in North American supply chain, working with top

auto, energy and construction companies.

ArcelorMittalDofasco

Page 3: Welcome [dofasco.arcelormittal.com]dofasco.arcelormittal.com/~/media/Files/A/Arcelormittal-Canada... · Standards (SSS) under Ontario ... • Acquired by ArcelorMittal in 2006-2007.

• $700 million in facility investments from 2011-2016including significant enhancements to air emissions.controls.

• Member of Hamilton Industrial EnvironmentalAssociation and Clean Air Hamilton.

• Quarterly Community Liaison Committee meetings,open to the public.

• 24/7 reporting hotline for inquiries related tooperations.

• History of community support and partnerships.

ArcelorMittalDofasco and theCommunity

Page 4: Welcome [dofasco.arcelormittal.com]dofasco.arcelormittal.com/~/media/Files/A/Arcelormittal-Canada... · Standards (SSS) under Ontario ... • Acquired by ArcelorMittal in 2006-2007.

How isSteel Made?1. RAW MATERIALS

4. STEEL MAKING

3. IRON PRODUCTION

5. FINISHING

2. COKE PRODUCTION

Raw materials (coal,iron ore, recycledsteel) arrive by ship,truck and train toDofasco’s facility.

Rail cars take molten ironto steel making furnaces.Dofasco has 2 furnaces –the KOBM Furnace andthe Electric Arc Furnace.

Dofasco has 3 BlastFurnaces thatconvert iron oreand coke into iron.

Dofasco has 3coke plants onsite that convertcoal into coke.

Coke Plant

Blast Furnace (BF)

Continuous Castingmakes solid slabs ofsteel.

Heat treating, galvanizingand other finishingprocesses produce finalsteel products that are usedby manufacturers. Flat Rolled Steel

6. CONSUMER PRODUCTS

Steel Making Furnace

Page 5: Welcome [dofasco.arcelormittal.com]dofasco.arcelormittal.com/~/media/Files/A/Arcelormittal-Canada... · Standards (SSS) under Ontario ... • Acquired by ArcelorMittal in 2006-2007.

Site Specific Standards are designed to improveenvironmental performance over time. Regulation419/05, under the Environmental Protection Act,phases in updated air quality standards developedby the MOECC.

MOECC has three compliance options:

MOECC’s goal of the Site Specific Standard processis “continuous improvement of emissions as newtechnologies become available”.

What is anMOECC SiteSpecific Standard?

Demonstrate emission levelswithin prescribed limits

Request Site Specific Standards(SSS) focused on the reduction of

emissions over time

Register under a TechnicalStandard

Page 6: Welcome [dofasco.arcelormittal.com]dofasco.arcelormittal.com/~/media/Files/A/Arcelormittal-Canada... · Standards (SSS) under Ontario ... • Acquired by ArcelorMittal in 2006-2007.

ArcelorMittal Dofasco currently meets MOECC-approved emission limits for the followingcompounds:

Total Suspended Particulate (TSP)Total Reduced Sulphur (TRS)Benzo(a)pyrene (BaP)Benzene

What’s Next (2015-2020)

ArcelorMittal Dofasco is applying for Site SpecificStandards for the compounds listed above aswell as Manganese (Mn).

New MOECC Standards for Benzo(a)pyrene,Benzene and Mn will be coming into effect in2016.

Site SpecificStandards atArcelorMittal Dofasco

Page 7: Welcome [dofasco.arcelormittal.com]dofasco.arcelormittal.com/~/media/Files/A/Arcelormittal-Canada... · Standards (SSS) under Ontario ... • Acquired by ArcelorMittal in 2006-2007.

SSS ProcessTo Date

2008

•ArcelorMittal Dofasco applies for SSS for TSP, TRS,Benzene and Benzo(a)pyrene.

•Public meetings held on July 31 and October 16,2008.

•Application is supported by: Emissions Summary andDispersion Modeling Report (ESDM), TechnologyBenchmarking Report and Action Plan.

2009

•2008 SSS Application final Public Meeting onSeptember 17, 2009.

•MOECC public meeting & the Environmental Bill ofRights Registry Process further engaged the public.

2010

•SSS for ArcelorMittal Dofasco (2010 – 2015) wereapproved by the MOECC.

•ArcelorMittal Dofasco implements Action Plan.

2014

•ArcelorMittal Dofasco complies with SSS andapproved levels.

•ArcelorMittal Dofasco begins another SSS applicationprocess for 2015 to 2020.

•Public meeting, September 9, 2014.

Page 8: Welcome [dofasco.arcelormittal.com]dofasco.arcelormittal.com/~/media/Files/A/Arcelormittal-Canada... · Standards (SSS) under Ontario ... • Acquired by ArcelorMittal in 2006-2007.

What is thecompound and its

sources?

What has been doneto reduce emissions?

(2010-2014)

What is planned tofurther reduce

emissions?(2015-2020)

The following panels provide information oneach of the compounds that are being addressedthrough this Site Specific Standard process.Information is shown in the following order:

1

2

3

Page 9: Welcome [dofasco.arcelormittal.com]dofasco.arcelormittal.com/~/media/Files/A/Arcelormittal-Canada... · Standards (SSS) under Ontario ... • Acquired by ArcelorMittal in 2006-2007.

• TSP is particulate matter with a diameter lessthan 44 micrometres (µm) (e.g., smoke, dust,aerosols) suspended in the air

• MOECC Standard: 120 micrograms per cubicmetre (µg/m³) (24-hr basis)

Total SuspendedParticulate

ArcelorMittalDofasco Source

RelativeContribution to

Emissions

Included in2015 – 2020Action Plan

Coffining of HotMetal High Yes

Material Storage &Roads (Fugitives) High Yes

Pelletizers(Fugitives) High Yes

Coke Plants(Fugitives) High Yes

KOBM Furnace(Fugitives) Medium Yes

1 2 3 What is the compound and its sources?

Page 10: Welcome [dofasco.arcelormittal.com]dofasco.arcelormittal.com/~/media/Files/A/Arcelormittal-Canada... · Standards (SSS) under Ontario ... • Acquired by ArcelorMittal in 2006-2007.

2010-2014 Action Plan resulted in ~30%reduction in maximum TSP concentration

Total SuspendedParticulate

Source Actions Completed

Coffining of HotMetal

• Analysis & Preliminary Engineering ofCapture & Control Systems

• Coffining Volume Reduction PlanMaterial Storage &Roads (Fugitives)

• Enhanced Road Silt Management &Auditing Program

Pelletizers(Fugitives)

• Installation of No. 3 BF Pelletizer Hoodand Stack

• Analysis & Preliminary Engineering onNo. 4 BF Pelletizer Hood and Stack

Coke Plants(Fugitives)

• #1 Coke Plant – New Door Machine• #2 Coke Plant – Installation of Pusher

Side Jamb Cleaner & New Coke SideDoor + Jamb Cleaner

• #3 Coke Plant – Replacement of DoorJambs & Off-gas TemperatureMonitoring

• Electronic Off-Gas Controllers

Predicted maximum concentration after2010-2014 Action Plan: 177 µg/m³ (24-hr basis)

1 2 3 What has been done to reduce emissions? (2010-2014)

Page 11: Welcome [dofasco.arcelormittal.com]dofasco.arcelormittal.com/~/media/Files/A/Arcelormittal-Canada... · Standards (SSS) under Ontario ... • Acquired by ArcelorMittal in 2006-2007.

2015-2020 Action Plan will result in a further~20% reduction in maximum TSP concentration

Total SuspendedParticulate

Source Actions Planned

Coffining of HotMetal

• Blast Furnace Running Reline Strategy toReduce Excess Hot Metal

Material Storage &Roads (Fugitives)

• Road Silt Management & AuditingProgram (ongoing)

Pelletizers(Fugitives)

• No. 4 Blast Furnace Pelletizer Hood andStack

Coke Plants(Fugitives)

• Shutdown of #1 Coke Plant• Application of US EPA NESHAP Rules

• Monitoring using US EPA Method 303• Improved collector main pressure control• Revised maintenance program – door,

oven and door & jamb cleaning practices• Supplemental door sealing

• Coke Plant Restoration Program (#2 and#3 Coke Plants)

KOBM Furnace(Fugitives)

• Investigation of KOBM Charge EnclosureCanopy

Predicted maximum concentration after2015-2020 Action Plan: 143 µg/m³ (24-hr basis)

1 2 3 What is planned to further reduce emissions? (2015-2020)

Page 12: Welcome [dofasco.arcelormittal.com]dofasco.arcelormittal.com/~/media/Files/A/Arcelormittal-Canada... · Standards (SSS) under Ontario ... • Acquired by ArcelorMittal in 2006-2007.

• Total Reduced Sulphur (TRS) refers to thecombination of all reduced sulphur compounds,expressed as hydrogen sulphide equivalents

• MOECC Standards: 7 µg/m³ (24-hr basis)and 13 µg/m³ (10-min basis)

Total ReducedSulphur

ArcelorMittalDofasco Source

RelativeContribution to

Emissions

Included in2015 – 2020Action Plan

Pelletizers(Fugitives) High Yes

By-Products Plants(Fugitives) Low Yes

Coke Plants(Fugitives) Low Yes

1 2 3 What is the compound and its sources?

Page 13: Welcome [dofasco.arcelormittal.com]dofasco.arcelormittal.com/~/media/Files/A/Arcelormittal-Canada... · Standards (SSS) under Ontario ... • Acquired by ArcelorMittal in 2006-2007.

Total ReducedSulphur

Source Actions Completed

Pelletizers(Fugitives)

• Installation of No. 3 BF Pelletizer Hood andStack

• Analysis & Preliminary Engineering on No. 4BF Pelletizer Hood and Stack

By-ProductsPlants (Fugitives)

• #1 By-Products - Installation of ThermalOxidizer

• Leak Detection and Repair Program• #1 By-Products – Excess Liquor Sump

Coke Plants(Fugitives)

• #1 Coke Plant – New Door Machine• #2 Coke Plant – Installation of Pusher Side

Jamb Cleaner & New Coke Side Door +Jamb Cleaner

• #3 Coke Plant – Replacement of DoorJambs & Off-gas Temperature Monitoring

• Electronic Off-Gas Controllers

2010-2014 Action Plan resulted in ~10%reduction in maximum TRS concentrations

Predicted maximum concentration after2010-2014 Action Plan: 17 µg/m³ (24-hr basis)and 40 µg/m³ (10-min basis)

1 2 3 What has been done to reduce emissions? (2010-2014)

Page 14: Welcome [dofasco.arcelormittal.com]dofasco.arcelormittal.com/~/media/Files/A/Arcelormittal-Canada... · Standards (SSS) under Ontario ... • Acquired by ArcelorMittal in 2006-2007.

2015-2020 Action Plan will result in compliancewith MOECC Reg 419/05 Standards for TRS

Total ReducedSulphur

Source Actions Planned

Pelletizers (Fugitives) • No. 4 Blast Furnace Pelletizer Hoodand Stack

By-Products Plants(Fugitives)

• #1 By-Products: Shutdown of #1 By-Products Plant

• #2 By-Products: COG CoolingImprovement Project

• #2, #3 By-Products: Leak Detection andRepair Program

Coke Plants(Fugitives)

• Shutdown of #1 Coke Plant• Application of US EPA NESHAP Rules

• Monitoring using US EPA Method 303• Improved collector main pressure

control• Revised maintenance program – door,

oven and door & jamb cleaning practices• Supplemental door sealing

• Coke Plant Restoration Program (#2and #3 Coke Plants)

Predicted maximum concentration after2015-2020 Action Plan: 6.7 µg/m³ (24-hr basis)and 12 µg/m³ (10-min basis)

1 2 3 What is planned to further reduce emissions? (2015-2020)

Page 15: Welcome [dofasco.arcelormittal.com]dofasco.arcelormittal.com/~/media/Files/A/Arcelormittal-Canada... · Standards (SSS) under Ontario ... • Acquired by ArcelorMittal in 2006-2007.

• Benzo(a)pyrene is a polycyclic aromatichydrocarbon (PAH) formed during incompleteburning of organic substances (e.g., coal, oil,gas)

• MOECC Standard (effective in 2016) :0.01 ng/m³ (annual basis)

Benzo(a)pyrene

ArcelorMittalDofasco Source

RelativeContribution to

Emissions

Included in2015 - 2020Action Plan

Coke Plants(Fugitives) - Leaks High Yes

Coke Plants(Fugitives) - Pushing

EmissionsMedium Yes

1 2 3 What is the compound and its sources?

Page 16: Welcome [dofasco.arcelormittal.com]dofasco.arcelormittal.com/~/media/Files/A/Arcelormittal-Canada... · Standards (SSS) under Ontario ... • Acquired by ArcelorMittal in 2006-2007.

Benzo(a)pyrene

Source Actions Completed

Coke Plants(Fugitives)

• #1 Coke Plant – New Door Machine• #2 Coke Plant – Installation of Pusher Side

Jamb Cleaner & New Coke Side Door +Jamb Cleaner

• #3 Coke Plant – Replacement of DoorJambs & Off-gas Temperature Monitoring

• Electronic Off-Gas Controllers

Predicted maximum concentration after2010-2014 Action Plan: ~17 ng/m³ (annual basis)

2010-2014 Action Plan resulted in ~20%reduction in maximum B(a)P concentration

1 2 3 What has been done to reduce emissions? (2010-2014)

Page 17: Welcome [dofasco.arcelormittal.com]dofasco.arcelormittal.com/~/media/Files/A/Arcelormittal-Canada... · Standards (SSS) under Ontario ... • Acquired by ArcelorMittal in 2006-2007.

Benzo(a)pyrene

Source Actions Planned

Coke Plants(Fugitives)

• Shutdown of #1 Coke Plant• Application of US EPA NESHAP Rules

• Monitoring using US EPA Method 303• Improved collector main pressure control• Revised maintenance program – door, oven

and door & jamb cleaning practices• Supplemental door sealing

• Coke Plant Restoration Program (#2 and#3 Coke Plants)

2015-2020 Action Plan will result in a further~30% reduction in maximum B(a)Pconcentration

Predicted maximum concentration after2015-2020 Action Plan: ~11 ng/m³ (annual basis)

1 2 3 What is planned to further reduce emissions? (2015-2020)

Page 18: Welcome [dofasco.arcelormittal.com]dofasco.arcelormittal.com/~/media/Files/A/Arcelormittal-Canada... · Standards (SSS) under Ontario ... • Acquired by ArcelorMittal in 2006-2007.

• Benzene is an organic compound (aromatichydrocarbon). Emissions come mainly fromwood burning, transportation, and industry

• MOECC Standard (effective in 2016):0.45 µg/m³ (annual basis)

Benzene

ArcelorMittalDofasco Source

RelativeContribution to

Emissions

Included in2015 - 2020Action Plan

Coke Plants(Fugitives) High Yes

By-Products Plants(Fugitives) High Yes

#1 By-Products PlantOxidizing Tower Medium Yes

1 2 3 What is the compound and its sources?

Page 19: Welcome [dofasco.arcelormittal.com]dofasco.arcelormittal.com/~/media/Files/A/Arcelormittal-Canada... · Standards (SSS) under Ontario ... • Acquired by ArcelorMittal in 2006-2007.

Benzene

Source Actions Completed

Coke Plants(Fugitives)

• #1 Coke Plant – New Door Machine• #2 Coke Plant – Installation of Pusher Side

Jamb Cleaner & New Coke Side Door +Jamb Cleaner

• #3 Coke Plant – Replacement of DoorJambs & Off-gas Temperature Monitoring

• Electronic Off-Gas ControllersBy-Products

Plants (Fugitives)• Leak Detection and Repair Program• #1 By-Products – Excess Liquor Sump

#1 By-ProductsPlant Oxidizing

Tower

• #1 By-Products - Installation of ThermalOxidizer

2010-2014 Action Plan resulted in >20%reduction in maximum Benzene concentration

Predicted maximum concentration after2010-2014 Action Plan: ~10.8 µg/m³ (annualbasis)

1 2 3 What has been done to reduce emissions? (2010-2014)

Page 20: Welcome [dofasco.arcelormittal.com]dofasco.arcelormittal.com/~/media/Files/A/Arcelormittal-Canada... · Standards (SSS) under Ontario ... • Acquired by ArcelorMittal in 2006-2007.

Source Actions Planned

Coke Plants(Fugitives)

• Shutdown of #1 Coke Plant• Application of US EPA NESHAP Rules

• Monitoring using US EPA Method 303• Improved collector main pressure control• Revised maintenance program – door, oven

and door & jamb cleaning practices• Supplemental door sealing

• Coke Plant Restoration Program (#2 and #3Coke Plants)

By-ProductsPlants (Fugitives)

• #1 By-Products: Shutdown of #1 By-Products Plant

• # 2 By-Products: Coke Oven Gas CoolingImprovement Project

• #2, #3 By-Products: Leak Detection andRepair

2015-2020 Action Plan will result in a further~6% reduction in maximum Benzeneconcentration

Predicted maximum concentration after2015-2020 Action Plan: 10.1 µg/m³ (annual basis)

Benzene

1 2 3 What is planned to further reduce emissions? (2015-2020)

Page 21: Welcome [dofasco.arcelormittal.com]dofasco.arcelormittal.com/~/media/Files/A/Arcelormittal-Canada... · Standards (SSS) under Ontario ... • Acquired by ArcelorMittal in 2006-2007.

• Manganese is a metallic compound foundnaturally in ores. It is used to improve steelstrength and hardness.

• MOECC Standard (effective in 2016):0.4 µg/m³ (24-hr basis) (2016)

Manganese

ArcelorMittal DofascoSource

RelativeContribution to

Emissions

Included in2015 - 2020Action Plan

Slag Processing High Yes

Ore Handling High YesCoffining of Hot Metal Medium Yes

Material Storage &Roads (Fugitives) Medium Yes

KOBM Furnace(Fugitives) Medium Yes

1 2 3 What is the compound and its sources?

Page 22: Welcome [dofasco.arcelormittal.com]dofasco.arcelormittal.com/~/media/Files/A/Arcelormittal-Canada... · Standards (SSS) under Ontario ... • Acquired by ArcelorMittal in 2006-2007.

Manganese

Source Actions Planned

Slag Processing • Reduction of Mn content of oreOre Handling • Reduction of Mn content of ore

Coffining of Hot Metal • Blast Furnace Running RelineStrategy to Reduce Excess Hot Metal

Material Storage &Roads (Fugitives)

• Road Silt Management & AuditingProgram (ongoing)

KOBM Furnace(Fugitives)

• Investigation of KOBM ChargeEnclosure Canopy

2015-2020 Action Plan will result in ~3%reduction in maximum Mn concentration

Predicted maximum concentration after2015-2020 Action Plan: 1.45 µg/m³ (24-hr basis)

~3% reduction in concentration does not include“Reduction of Mn content of ore”. The benefit ofthis action is still being assessed.

1 2 3 What is planned to further reduce emissions? (2015-2020)

Page 23: Welcome [dofasco.arcelormittal.com]dofasco.arcelormittal.com/~/media/Files/A/Arcelormittal-Canada... · Standards (SSS) under Ontario ... • Acquired by ArcelorMittal in 2006-2007.

Hamilton AirQuality is Improving

0

10

20

30

40

50

60

70

80

90

96 97 98 99 00 01 02 03 04 05 06 07 08 09 10 11 12 13

Geo

met

ricAv

erag

e(

g/m

³)

Year

Total Suspended Particulate (TSP) Trend

2 City Sites 2 Industry Sites

Annual Objective

0

50

100

150

200

250

300

350

400

450

500

96 97 98 99 00 01 02 03 04 05 06 07 08 09 10 11 12 13

Num

bero

fHou

rsO

ver1

0pp

b

Year

Total Reduced Sulphur Trend

Industry 1 Downtown (City) Industry 2

Hours Over 10 ppb Odour Threshold

0.0

0.5

1.0

1.5

2.0

2.5

3.0

3.5

96 97 98 99 00 01 02 03 04 05 06 07 08 09 10 11 12 13

Annu

alAv

erag

e(n

g/m

³)

Year

Benzo(a)pyrene Trend

Industry 1 Downtown (City) Industry 3 Industry 2

*2011 & 2012 Downtown data is interim

0

1

2

3

4

5

6

7

8

9

10

96 97 98 99 00 01 02 03 04 05 06 07 08 09 10 11 12 13

Annu

alAv

erag

e(

g/m

³)

Year

Benzene Trend

Industry 1 Industry 2 Downtown (City)

*2011 & 2012 Downtown data is interim

Data provided by Clean Air Hamilton (2014)

Page 24: Welcome [dofasco.arcelormittal.com]dofasco.arcelormittal.com/~/media/Files/A/Arcelormittal-Canada... · Standards (SSS) under Ontario ... • Acquired by ArcelorMittal in 2006-2007.

2015 – 2020 Action Plan:$135 Million Dollars

Project Compoundof Interest

Approximate Investment

EarlyAction:2014

2015 2016 2017 2018 2019 2020

COKE: Coke PlantRestoration Program

B(a)P, Benzene,TSP, TRS

$16.6 M $22.7 M $27.5 M $16.5 M $3.7 M

COKE: Shutdown of #1Coke Plant & By-Products $4.3 M

COKE: Application of USEPA NESHAP Rules:• Collector Main Pressure

Control• ProActive Maintenance

Program• Supplemental Door

Sealing

$2.8 M $9.1 M $2.8 M $2.8 M $2.8 M $2.8 M $2.8 M

BP 2: COG CoolingImprovement Project Benzene $6 M

BP 2,3: LDAR Benzene $50 K $50 K $50 K $50 K $50 K $50 K $50 KIRON: #4 BF Slag PelletizerStack TRS,TSP $3.6 M

CTS: Increased RoadSweeping/Flushing TSP, Mn $1 M $1 M $1 M $1 M $1 M $1 M $1 M

INVESTIGATION -STEEL:KOBM Charge EnclosureCanopy

TSP, Mn $1.5 M

ACTION PLAN TOTAL $135 M

ArcelorMittal Dofasco spends an additional$15 million on repairs, maintenance andimprovements to coke plants annually.

Page 25: Welcome [dofasco.arcelormittal.com]dofasco.arcelormittal.com/~/media/Files/A/Arcelormittal-Canada... · Standards (SSS) under Ontario ... • Acquired by ArcelorMittal in 2006-2007.

Next Steps

Gather Stakeholder Input:

• Submit Comments in Writing

• Review Environmental Bill of Rights (EBR) –MOECC will post summary of application on EBRwebsite for public review and comment. Expectedin Fall 2014 http://www.ebr.gov.on.ca/ERS-WEB-External/

Submission of Application to the MOECC:

• Application for Site Specific Standards andEnvironmental Compliance Approval expected inOctober 2014

Page 26: Welcome [dofasco.arcelormittal.com]dofasco.arcelormittal.com/~/media/Files/A/Arcelormittal-Canada... · Standards (SSS) under Ontario ... • Acquired by ArcelorMittal in 2006-2007.

Please take the time to fill out a comment sheetwith your comments and concerns.

You may also contact us directly:

Jim Stirling,General Manager, Environment

ArcelorMittal DofascoBox 2460

Hamilton, Ontario L8N 3J5Phone: (905) 548-7200 ext. 2284

[email protected]/dofasco/hamilton

Thank You