Building the Future Current Activities this Week : Mass Excavation : Grading is ongoing in Area 3. Backfilling of on-grade is ongoing in Area 1. Site Utilities : Installation of the new electrical ductbank is complete. Storm Sewer installation (Line 6000) is ongoing on east side of France Family Drive. Foundations : Area 3 Field Level – Footing installation is ongoing and is Complete to Column Line 6. Area 4 Mezzanine Level – Installation of Drilled Piers are ongoing. Structural Steel Erection : Area 1 – Steel Erection in sequence 1-2 is nearly complete to Column Line 23 Decking is nearly complete in sequence 1-1 on Mezzanine and Concourse Levels. Installation of studs and edge plates have started. Decking on Suite Level has started. To: David Ficklin - OnGoal Rory O’Connor – OnGoal Lee Turner – OnGoal Andy Heitmann – Turner Dave Dudzik - Turner From: Brandon Valdez Office: Kansas City Date: 5.19.2010 Re: Wizards Stadium Project Update – Week of 5.17.2010 Field Level Area 1 – Wizards Team Bench concrete is placed. Area 2 – Electrical Ductbank relocation is complete. Field Level Area 1 – South Field Wall installation is ongoing.

description

KC Soccer Stadium construction update from Turner Construction.

Transcript of Weekly Construction Update 05-19-2010

Page 1: Weekly Construction Update 05-19-2010

Building the Future

Current Activities this Week:

Mass Excavation:

Grading is ongoing in Area 3. Backfilling of on-grade

is ongoing in Area 1.

Site Utilities:

Installation of the new electrical ductbank is complete.

Storm Sewer installation (Line 6000) is ongoing on

east side of France Family Drive.

Foundations:

Area 3 Field Level – Footing installation is ongoing and is

Complete to Column Line 6.

Area 4 Mezzanine Level – Installation of Drilled Piers

are ongoing.

Structural Steel Erection:

Area 1 – Steel Erection in sequence 1-2 is nearly

complete to Column Line 23

Decking is nearly complete in sequence 1-1 on

Mezzanine and Concourse Levels. Installation of studs

and edge plates have started. Decking on Suite Level

has started.

To: David Ficklin - OnGoal

Rory O’Connor – OnGoal

Lee Turner – OnGoal

Andy Heitmann – Turner

Dave Dudzik - Turner

From: Brandon Valdez

Office: Kansas City

Date: 5.19.2010

Re: Wizards Stadium Project

Update – Week of

5.17.2010

Field Level Area 1 – Wizards Team Bench

concrete is placed.

Area 2 – Electrical Ductbank relocation is

complete.

Field Level Area 1 – South Field Wall

installation is ongoing.

Page 2: Weekly Construction Update 05-19-2010

Building the Future

Underground Electrical:

Secondary service ducts is complete from Electrical Room

01.34.04 south past Column Line 25.

Installation of secondary service ducts at Column Line D

Is installed to Column Line 24.

Projected Activities occurring next Week:

Mass Excavation:

Grading at Truck Dock Area will continue.

Site Utilities:

Installation of the Storm Line 6000 on the East Side (France

Family Drive) of the site will continue.

Deep Underground Plumbing:

Sanitary in Area 3 will continue.

Foundations:

Area 2 Field Level – Placement of foundation walls east of

Stage will continue.

Area 3 Field Level – Footing placement will continue and

wall installation will begin.

Structural Steel Erection:

Erection of Structural Steel in Sequence 1-4 will begin.

Decking installation on Suite Level of Sequence 1-1 will

continue.

Area 1 – Structural Steel Erection at West

Building to Suite Level 1 Floor is nearly

complete to 23-Line.

Field Level Area 1 – Shot looking north from

Concourse Level.

Concourse Level Area 1 – Decking, studs and

edge plating installed at Main Club.

Page 3: Weekly Construction Update 05-19-2010

Building the Future

Additional Photos:

Field Level Area 3 – Wall reinforcing mats

installed at SE vomitory and A-Line wall.

Field Level Area 1 – Concrete encasement of

Structural Steel columns.

Field Level Area 2 – A-Line reinforcing in

place from Column Lines 14-12.

Field Level Area 1 – Hydrotherapy pit base

concrete being installed.

Mezzanine Level Area 1 – Decking, studs and

edge plating nearly complete at VIP

Entrance.

Field Level Area 1 – Shot looking NW at

Wizards Team Bench Area.