Week 10-Safety Design Philosophy
-
Upload
jennifer-scott -
Category
Documents
-
view
12 -
download
3
description
Transcript of Week 10-Safety Design Philosophy
-
OSE571 Ocean Plant Design
Safety Design Philosophy
Korea Advanced Institute ofScience and Technology
Daejun CHANG ([email protected])
Division of Ocean System Engineering
-
Design Procedure and Key deliverablesDesign Procedure and Key deliverables
Design Basis (Philosophy)
Concept Consolidation
Process Flow DiagramProcess Simulation
Equipment SpecificationEquipment Design
System Description
Production Availability ?
-1- Ocean Systems EngineeringOcean Systems Engineering
Process Operation and Control Philosophy
P&ID
Layout
HAZOPRisk AssessmentSafety Studies
Caution: Not universally applicable
-
Hazards and Safety SystemsHazards and Safety Systems
Accident Controlling Protection(F&G Detection, ESD, Depressurization, Alarm)
Accident Mitigating Protection(Active/Passive Fire Protection, Fire/Blast Walls)
Emergency Response(Escape Route, TR, Evacuation Means, Rescue Equipment, Emergency Power)
Potential Accident:
Accident:Fire/Explosion
-2- Ocean Systems EngineeringOcean Systems Engineering
Inherent Safety Design(Layout, Inventory, Leak, Ignition)
Basic Process Control(P, T, F, Surge, Back Pressure)
Preventive Protection(Structural & Machinery Integrity, Relief, PSV)
Potential Accident:Gas Leak
Layered Structure of Safety Systems against Fire and Explosion
-
Principles of Safety DesignPrinciples of Safety Design
Segmentation
Depressurization (Blowdown)
Pressure Protection
Preventive Measures
-3- Ocean Systems EngineeringOcean Systems Engineering
Preventive Measures
Mitigating Measures
Shutdown Logic
-
Segmentation Segmentation
What if there is a leak? All the inventory (gas) will get out of the process! Segmentation
- Divide the whole plant into several segments(Divide and defeat!)
-4- Ocean Systems EngineeringOcean Systems Engineering
(Divide and defeat!)- Boundary of the segments: block valves- The valves are closed if there is a leak. The inventory within the segment will get out.
-
Depressurization (Depressurization (BlowdownBlowdown))
Do we have to wait until all the inventory gets out. Venting of the inventory into a safe area. How? Depressurization (Blowdown)
- Install a vent line from each segment.- The vent line is normally blocked by blowdown valves.
-5- Ocean Systems EngineeringOcean Systems Engineering
- The vent line is normally blocked by blowdown valves.- In case of fire, the valve is open to guide the inventory to the
flare stack. Reduce the leaked inventory by the amount vented to flare
-
Pressure ProtectionPressure Protection
What if the internal pressure of a segment increases? Cause
- Too much incoming feed flow- Outlets blocked- Fire thermal explosion
-6- Ocean Systems EngineeringOcean Systems Engineering
- Fire thermal explosion- Leak due to internal rupture (tube rupture of exchanger)
Double-layer pressure protection- Layer 1: PSV, rupture disc- Layer 2: depressurization
-
Pressure ProtectionPressure Protection
Flare Open
BDV
PSV
-7- Ocean Systems EngineeringOcean Systems Engineering
Closed
Closed Drain
Closed
Open
ESDV ESDV
PSDVPSV: Pressure Safety ValveBDV: Blowdown ValveESDV: Emergency Shutdown ValvePSDV: Pressure Shutdown Valve
-
Preventive MeasuresPreventive Measures
Prevent an accident from happening (or to decrease the frequency) Detection: Fire and Gas (F&G System) Ventilation
-8- Ocean Systems EngineeringOcean Systems Engineering
-
Mitigating MeasuresMitigating Measures
Once an accident happens, mitigate the consequence. Water spray (deluge) Fire and blast walls
-9- Ocean Systems EngineeringOcean Systems Engineering
-
Overview of Safety SystemsOverview of Safety Systems
-10- Ocean Systems EngineeringOcean Systems Engineering
-
An Real Example: ESDV & PSDVAn Real Example: ESDV & PSDV
-11- Ocean Systems Engineering
-
An Real Example: PSV and BDVAn Real Example: PSV and BDV
-12- Ocean Systems Engineering
-
Shutdown LogicShutdown Logic
Shut down the system partially or entirely. To what degree depending on the seriousness
Low seriousness partial shutdown High seriousness total shutdown Extreme seriousness Just escape and abandon the facility
-13- Ocean Systems EngineeringOcean Systems Engineering
Extreme seriousness Just escape and abandon the facility
-
Level 1 APS Abandon platform
Level 2 ESD I Emergency shutdown (total)
Level 3 ESD II Emergency shutdown (partial)
Shutdown LogicShutdown Logic
-14- Ocean Systems Engineering
Level 3 ESD II Emergency shutdown (partial)
Level 4 PSD Process shutdown (total)
Level 5 PSD Process shutdown (partial)
-
Shut DHSVAuto Depressurisation
Timer-based disconnectionFire&gas detectionPA, ESD/PSD, radioEmergency generator/UPS
DisconnectionMain generatorNon-critical non-EXequipment
APS
ESD I
Manual
Manual
Input
Gas detection Non hazardous area
Fire&gas detectionHazardous area
Standardizing
-15- Ocean Systems Engineering
Start Emergency generator
equipment
Shut fuel gas supply
Activation of DHSV (fire in riser/ well area)Riser ESDVDepressurisation
ESD II
PSD
Manual
Low pressurehydraulic system
Low pressure Instrument air
High lev flare k.o drum
Tube rupture in cooler
Hazardous area
-
Cause
Effect
Cause and Effect ChartCause and Effect Chart
-16- Ocean Systems Engineering
X
-
-17- Ocean Systems Engineering
-
Design and Maximum Operating PressureDesign and Maximum Operating Pressure
Design Pressure The maximum allowable pressure for equipment and piping
under pressure Used for equipment design (with some margin)
Maximum Operating Pressure (or Maximum Allowable Working Pressure)
-18- Ocean Systems EngineeringOcean Systems Engineering
(or Maximum Allowable Working Pressure) The maximum of all the pressure fluctuations over the all the
conceivable operation mode. start-up/shutdown, process flexibility, control requirements and
process upsets Shut-off (discharge blocked) cases for rotating machineries For unknown cases, the rules of thumbs are
- Pump: 1.25 times the discharge pressure- Compressor: 1.3 times the discharge pressure
-
Design PressureDesign Pressure
PSV (pressure safety valve) to vent out the internal gas Segment with a PSV
Maximum operating pressure (MOP), barg
Design pressure, barg
0 23 MOP + 3.5 bar
-19- Ocean Systems EngineeringOcean Systems Engineering
0 23 MOP + 3.5 bar
35 70 1.1 MOP
70 200 Max (1.085 MOP, MOP + 7 bar)
200 + 1.05 MOP
-
Design TemperatureDesign Temperature
Maximum design temperature When the maximum operating temperature is clear, take it for the
design temperature Otherwise, design temperature = MOT + 30 oC
Minimum design temperature Material selection may be affected.
-20- Ocean Systems EngineeringOcean Systems Engineering
Material selection may be affected. The minimum operating temperature 5 oC Operating conditions considered
- Air temperature (winter condition)- Normal- start-up, shutdown, process upsets- Cooldown due to depressuriization