Week 10-Safety Design Philosophy

21
OSE571 Ocean Plant Design Safety Design Philosophy Korea Advanced Institute of Science and Technology Daejun CHANG ([email protected] ) Division of Ocean System Engineering

description

design

Transcript of Week 10-Safety Design Philosophy

  • OSE571 Ocean Plant Design

    Safety Design Philosophy

    Korea Advanced Institute ofScience and Technology

    Daejun CHANG ([email protected])

    Division of Ocean System Engineering

  • Design Procedure and Key deliverablesDesign Procedure and Key deliverables

    Design Basis (Philosophy)

    Concept Consolidation

    Process Flow DiagramProcess Simulation

    Equipment SpecificationEquipment Design

    System Description

    Production Availability ?

    -1- Ocean Systems EngineeringOcean Systems Engineering

    Process Operation and Control Philosophy

    P&ID

    Layout

    HAZOPRisk AssessmentSafety Studies

    Caution: Not universally applicable

  • Hazards and Safety SystemsHazards and Safety Systems

    Accident Controlling Protection(F&G Detection, ESD, Depressurization, Alarm)

    Accident Mitigating Protection(Active/Passive Fire Protection, Fire/Blast Walls)

    Emergency Response(Escape Route, TR, Evacuation Means, Rescue Equipment, Emergency Power)

    Potential Accident:

    Accident:Fire/Explosion

    -2- Ocean Systems EngineeringOcean Systems Engineering

    Inherent Safety Design(Layout, Inventory, Leak, Ignition)

    Basic Process Control(P, T, F, Surge, Back Pressure)

    Preventive Protection(Structural & Machinery Integrity, Relief, PSV)

    Potential Accident:Gas Leak

    Layered Structure of Safety Systems against Fire and Explosion

  • Principles of Safety DesignPrinciples of Safety Design

    Segmentation

    Depressurization (Blowdown)

    Pressure Protection

    Preventive Measures

    -3- Ocean Systems EngineeringOcean Systems Engineering

    Preventive Measures

    Mitigating Measures

    Shutdown Logic

  • Segmentation Segmentation

    What if there is a leak? All the inventory (gas) will get out of the process! Segmentation

    - Divide the whole plant into several segments(Divide and defeat!)

    -4- Ocean Systems EngineeringOcean Systems Engineering

    (Divide and defeat!)- Boundary of the segments: block valves- The valves are closed if there is a leak. The inventory within the segment will get out.

  • Depressurization (Depressurization (BlowdownBlowdown))

    Do we have to wait until all the inventory gets out. Venting of the inventory into a safe area. How? Depressurization (Blowdown)

    - Install a vent line from each segment.- The vent line is normally blocked by blowdown valves.

    -5- Ocean Systems EngineeringOcean Systems Engineering

    - The vent line is normally blocked by blowdown valves.- In case of fire, the valve is open to guide the inventory to the

    flare stack. Reduce the leaked inventory by the amount vented to flare

  • Pressure ProtectionPressure Protection

    What if the internal pressure of a segment increases? Cause

    - Too much incoming feed flow- Outlets blocked- Fire thermal explosion

    -6- Ocean Systems EngineeringOcean Systems Engineering

    - Fire thermal explosion- Leak due to internal rupture (tube rupture of exchanger)

    Double-layer pressure protection- Layer 1: PSV, rupture disc- Layer 2: depressurization

  • Pressure ProtectionPressure Protection

    Flare Open

    BDV

    PSV

    -7- Ocean Systems EngineeringOcean Systems Engineering

    Closed

    Closed Drain

    Closed

    Open

    ESDV ESDV

    PSDVPSV: Pressure Safety ValveBDV: Blowdown ValveESDV: Emergency Shutdown ValvePSDV: Pressure Shutdown Valve

  • Preventive MeasuresPreventive Measures

    Prevent an accident from happening (or to decrease the frequency) Detection: Fire and Gas (F&G System) Ventilation

    -8- Ocean Systems EngineeringOcean Systems Engineering

  • Mitigating MeasuresMitigating Measures

    Once an accident happens, mitigate the consequence. Water spray (deluge) Fire and blast walls

    -9- Ocean Systems EngineeringOcean Systems Engineering

  • Overview of Safety SystemsOverview of Safety Systems

    -10- Ocean Systems EngineeringOcean Systems Engineering

  • An Real Example: ESDV & PSDVAn Real Example: ESDV & PSDV

    -11- Ocean Systems Engineering

  • An Real Example: PSV and BDVAn Real Example: PSV and BDV

    -12- Ocean Systems Engineering

  • Shutdown LogicShutdown Logic

    Shut down the system partially or entirely. To what degree depending on the seriousness

    Low seriousness partial shutdown High seriousness total shutdown Extreme seriousness Just escape and abandon the facility

    -13- Ocean Systems EngineeringOcean Systems Engineering

    Extreme seriousness Just escape and abandon the facility

  • Level 1 APS Abandon platform

    Level 2 ESD I Emergency shutdown (total)

    Level 3 ESD II Emergency shutdown (partial)

    Shutdown LogicShutdown Logic

    -14- Ocean Systems Engineering

    Level 3 ESD II Emergency shutdown (partial)

    Level 4 PSD Process shutdown (total)

    Level 5 PSD Process shutdown (partial)

  • Shut DHSVAuto Depressurisation

    Timer-based disconnectionFire&gas detectionPA, ESD/PSD, radioEmergency generator/UPS

    DisconnectionMain generatorNon-critical non-EXequipment

    APS

    ESD I

    Manual

    Manual

    Input

    Gas detection Non hazardous area

    Fire&gas detectionHazardous area

    Standardizing

    -15- Ocean Systems Engineering

    Start Emergency generator

    equipment

    Shut fuel gas supply

    Activation of DHSV (fire in riser/ well area)Riser ESDVDepressurisation

    ESD II

    PSD

    Manual

    Low pressurehydraulic system

    Low pressure Instrument air

    High lev flare k.o drum

    Tube rupture in cooler

    Hazardous area

  • Cause

    Effect

    Cause and Effect ChartCause and Effect Chart

    -16- Ocean Systems Engineering

    X

  • -17- Ocean Systems Engineering

  • Design and Maximum Operating PressureDesign and Maximum Operating Pressure

    Design Pressure The maximum allowable pressure for equipment and piping

    under pressure Used for equipment design (with some margin)

    Maximum Operating Pressure (or Maximum Allowable Working Pressure)

    -18- Ocean Systems EngineeringOcean Systems Engineering

    (or Maximum Allowable Working Pressure) The maximum of all the pressure fluctuations over the all the

    conceivable operation mode. start-up/shutdown, process flexibility, control requirements and

    process upsets Shut-off (discharge blocked) cases for rotating machineries For unknown cases, the rules of thumbs are

    - Pump: 1.25 times the discharge pressure- Compressor: 1.3 times the discharge pressure

  • Design PressureDesign Pressure

    PSV (pressure safety valve) to vent out the internal gas Segment with a PSV

    Maximum operating pressure (MOP), barg

    Design pressure, barg

    0 23 MOP + 3.5 bar

    -19- Ocean Systems EngineeringOcean Systems Engineering

    0 23 MOP + 3.5 bar

    35 70 1.1 MOP

    70 200 Max (1.085 MOP, MOP + 7 bar)

    200 + 1.05 MOP

  • Design TemperatureDesign Temperature

    Maximum design temperature When the maximum operating temperature is clear, take it for the

    design temperature Otherwise, design temperature = MOT + 30 oC

    Minimum design temperature Material selection may be affected.

    -20- Ocean Systems EngineeringOcean Systems Engineering

    Material selection may be affected. The minimum operating temperature 5 oC Operating conditions considered

    - Air temperature (winter condition)- Normal- start-up, shutdown, process upsets- Cooldown due to depressuriization