Week 1 (2) 2008IS33 IS Failure Cases 1 COMP3470 IS33 People-Centred Information Systems Development...
-
Upload
amber-barrett -
Category
Documents
-
view
212 -
download
0
Transcript of Week 1 (2) 2008IS33 IS Failure Cases 1 COMP3470 IS33 People-Centred Information Systems Development...
Week 1 (2) 2008 IS33 IS Failure Cases 1
COMP3470 IS33 People-Centred Information Systems Development
Week 1 : Lecture 2IS Failure Case Studies
School of ComputingFACULTY OF Engineering
IS33 IS Failure Cases 2Week 1 (2) 2008
Is this you?
A Software Engineer’s approach to correcting systems failure ? http://www.sei.cmu.edu/cbs/monographs/case.study.correcting.pdf
Good! But can you do more?
IS33 IS Failure Cases 3Week 1 (2) 2008
Categories of IS failure Process Failure: no workable solution
produced &/or cost of the delivered IS over run
Correspondence Failure: design objectives not met
Interaction Failure: poor levels of user satisfaction or acceptance
Expectation Failure: the inability of an IS to meet a specific stakeholder group’s expectations
Source: Lyytinen & Hirschheim (1987), IS Failures - A Survey and Classification of the Empirical Literature, Oxford Surveys in IT, Vol 4, pp.257-309
IS33 IS Failure Cases 4Week 1 (2) 2008
Different degree of failures
Total Failure – system not operational Partial Failure Type 1 – Goal Failure (main
stated goals not attained) Partial Failure Type 2 – Sustainability Failure
(succeeds initially but then fails after a year or so)
Partial Failure Type 3 – Zero-Sum Failure (succeeds for one stakeholder group but fails for another)
Richard Heeks, IDPM, University of Manchester
IS33 IS Failure Cases 5Week 1 (2) 2008
A classic case – LASCAD project
LASCAD = London Ambulance Service’s Computer Aided Despatch
How to conduct a case study?- get the facts on what happened
(primary & secondary sources? others?)- investigate context, cause & effect- analyse using some kind of ‘framework’- lessons learned (recommendations)
IS33 IS Failure Cases 6Week 1 (2) 2008
Sources of information
Beynon-Davies P (1995), “ Information systems ‘failure’: the case of the London Ambulance Service’s Computer Aided Despatch project”, European Journal of Information Systems, Vol. 4 pp.171-184
Report of the Inquiry into the London Ambulance Service (Feb 1993), access via http://www.cs.ucl.ac.uk/staff/A.Finkelstein/las.html
IS33 IS Failure Cases 7Week 1 (2) 2008
The old way …
Read pp.176/177 of Beynon-Davies’ paper on the manual ambulance despatch system
Error-prone and inefficient ….need computerisation!
IS33 IS Failure Cases 8Week 1 (2) 2008
LASCAD project – what happened
Key dates Late 1990 – Feb 1991 : writing system
requirement spec 7 Feb 1991 : invitation to tender June – July 1991 : systems design spec Aug – Sept 1991 : contracts (2 suppliers) signed Jan 1992 : original planned implementation 26 Oct 1992 : full implementation (problems
started - a flood of 999 calls swamping operators’ screens – some went missing – lots of automatic alerts generated …etc.)
4 Nov 1992 : system crashed!
From the Inquiry Report
IS33 IS Failure Cases 9Week 1 (2) 2008
How LASCAD should work
Read Beynon-Davies’ paper p.177
(p.178 has a cause-&-effect diagram too)
So what went wrong? – p.179
IS33 IS Failure Cases 10Week 1 (2) 2008
Context NHS was under reform and there was
already ‘a climate of mistrust and obstructiveness’
LAS management was under pressure to improve performance and to meet standards set
Staff was alienated to the changes rather than brought on board
2 earlier unsuccessful attempts with CAD (early 80s and 1989/90)
IS33 IS Failure Cases 11Week 1 (2) 2008
People issues as the framework for analysis Individual – inadequate training; system assume
perfect condition at coal face; Group – change of layout in control room (the usual
peer-support lost); no fall back position; management’s hope to use the system to bring about the desired change of working practice automatically;
Organisation – both systems and users were not ready for full implementation; poor fit between system and organisational structure and operational procedure; over-ambitious scoping and timetable; the process of awarding CAD contract dubious; poor project management
IS33 IS Failure Cases 12Week 1 (2) 2008
Recommendations by the Inquiry Team Continue to implement a CAD Better IT procurement guidelines (more than financial
aspects) CAD should be follow these imperatives
Reliable/resilient Total ownership by management and staff Timescale which allows consultation, QA, testing and
training Staged delivery with maximum benefits first
Re-training of control room staff Establish a project subcommittee of the LAS Board
and recruit an IT Director who will have direct access to LAS Board
IS33 IS Failure Cases 13Week 1 (2) 2008
For next week!
Write down on a piece of paper a list of ‘people issues’ raised in this article:Dennis A R, Carte T A and Kelly G G, “Breaking the rules: success and failure in groupware-supported business process reengineering”, in Decision Support Systems, Volume 36, Issue 1 (Sept 2003), pp.31-47, Elsevier Science Publishers B.V.
Go to http://www.leeds.ac.uk/library/
IS33 IS Failure Cases 14Week 1 (2) 2008
Need some help in speed reading?
Workshops by Skills Centre
Effective Reading (in Oct / Nov)
Develop your writing skills
(and others….?)
More info from
http://www.skillscentre.leeds.ac.uk/workshops.php