Webinar: Making the Right Choices in - Public Contracting Institute · 2018-03-21 · Officer has a...

24
Making the Right Choices Part 2- Copyright 2017 Richard D. Lieberman 1 Webinar: Making the Right Choices in Government Contracting™ – Part 2 Presented by Richard D. Lieberman, FAR Consultant, Website: www.richarddlieberman.com , Email [email protected]. Mr. Lieberman is a procurement consultant and retired government contracts attorney. He is the author of eight books including The 100 Worst Government Mistakes in Government Contracting,; The 100 Worst Mistakes in Government Contracting (with Jason D. Morgan), and Elements of Government Contracting. His published articles include “10 Big Mistakes in Government Contract Bidding, “10 Big Mistakes in Government Contract Administration,” Incorrect Government Advice – Whom Should You Heed” and “The Ten Big Mistakes Made by Small Businesses and New Government Contractors.” Mr. Lieberman is a former Deputy Inspector General and Assistant Inspector General of the Department of Defense. He served as a Professional Staff Member of the Senate Appropriations Committee. He has taught government contracts courses for the Public Contracting Institute, Federal Publications Seminars, LLC, the George Washington University Law School, the University of Maryland and numerous military, aerospace and information technology contractors. Public Contracting Institute LLC

Transcript of Webinar: Making the Right Choices in - Public Contracting Institute · 2018-03-21 · Officer has a...

Page 1: Webinar: Making the Right Choices in - Public Contracting Institute · 2018-03-21 · Officer has a right to obtain that data Not required for actions under $750,000 Not required

Making the Right Choices Part 2-Copyright 2017 Richard D.

Lieberman 1

Webinar: Making the Right Choices in

Government Contracting™ – Part 2

Presented by Richard D. Lieberman, FAR Consultant, Website: www.richarddlieberman.com, Email [email protected].

Mr. Lieberman is a procurement consultant and retired government contracts attorney. He is the author of eight books including The 100 Worst Government Mistakes in Government Contracting,; The 100 Worst Mistakes in Government Contracting (with Jason D. Morgan), and Elements of Government Contracting. His published articles include “10 Big Mistakes in Government Contract Bidding, “10 Big Mistakes in Government Contract Administration,” “Incorrect Government Advice – Whom Should You Heed” and “The Ten Big Mistakes Made by Small Businesses and New Government Contractors.” Mr. Lieberman is a former Deputy Inspector General and Assistant Inspector General of the Department of Defense. He served as a Professional Staff Member of the Senate Appropriations Committee. He has taught government contracts courses for the Public Contracting Institute, Federal Publications Seminars, LLC, the George Washington University Law School, the University of Maryland and numerous military, aerospace and information technology contractors.

Public Contracting Institute LLC

Page 2: Webinar: Making the Right Choices in - Public Contracting Institute · 2018-03-21 · Officer has a right to obtain that data Not required for actions under $750,000 Not required

Polling Question

You submitted a proposal that was noncompliant in one small material way. Can you resubmit a late, compliant proposal?

a. Yes

b. No

Also, is there any other way to make the proposal compliant?

Making the Right Choices Part 2-Copyright 2017 Richard D.

Lieberman 2

Page 3: Webinar: Making the Right Choices in - Public Contracting Institute · 2018-03-21 · Officer has a right to obtain that data Not required for actions under $750,000 Not required

Answer to Polling Question

Making the Right Choices Part 2-Copyright 2017 Richard D.

Lieberman 3

Page 4: Webinar: Making the Right Choices in - Public Contracting Institute · 2018-03-21 · Officer has a right to obtain that data Not required for actions under $750,000 Not required

Making the Right Choices Part 2-Copyright 2017 Richard D.

Lieberman 4

Award of Contract-Reading

Always read your entire contract again, including all of the

amendments and clauses incorporated by reference,

and always plan your contract execution.

Retain every contractual document for reference (Solicitation,

Contract, Modification, Correspondence, Audits etc.)

Develop a plan for full contract implementation from the outset of

the contract that implements the requirements of every clause and

every part of the contract.

Page 5: Webinar: Making the Right Choices in - Public Contracting Institute · 2018-03-21 · Officer has a right to obtain that data Not required for actions under $750,000 Not required

Making the Right Choices Part 2-Copyright 2017 Richard D.

Lieberman 5

Protests

Always consider the implications of a bid protest on your future relationship with a particular contracting office

May chill relationship with a CO or a contracting office

A special problem with CO’s use of schedule contracts, where CO has discretion to use GSA Advantage! or get price lists of 3 contractors. FAR 8.405-1(c).

Protesting may not hurt you if you do not expect to do business with this contracting office in the future.

Always be civil and professional in a bid protest; criticize actions not people.

Page 6: Webinar: Making the Right Choices in - Public Contracting Institute · 2018-03-21 · Officer has a right to obtain that data Not required for actions under $750,000 Not required

Making the Right Choices Part 2-Copyright 2017 Richard D.

Lieberman 6

Protests - 2

Always ensure that any protest you submit contains all the required elements, particularly a statement of how you were prejudiced by the improper agency action

1. In writing, addressed to GAO Gen. Counsel

2. Name, address, email, phone & fax of protester

3. Signed by protester or representative (counsel)

4. Identify Agency and solicitation or contract no.

5. Include detailed statement of legal and factual grounds & documents

6. State what law or regulation was violated

7. State how protester was prejudiced by agency actions

8. State why protester is an interested party

9. State why the protest is timely

10. Specifically request a ruling by the Comptroller General (GAO).

11. State the form of relief requested

12. State that a copy of the protest was provided to the CO

13. Request specific documents

14. Request a protective order, if required.

Page 7: Webinar: Making the Right Choices in - Public Contracting Institute · 2018-03-21 · Officer has a right to obtain that data Not required for actions under $750,000 Not required

Polling Question

You submit a protest of an LPTA award to the GAO 11 days after you received notice of award, explaining the basis of the award. Your protest says you think the award is unlawful because the agency evaluation was wrong. Your offer was technically acceptable but 3rd

lowest in price. GAO dismisses your protest because:

1)Your protest is untimely

2) You are not an interested party

3) GAO frequently dismisses protests of agency evaluations

4) Both 1 & 2 above

Making the Right Choices Part 2-Copyright 2017 Richard D.

Lieberman 7

Page 8: Webinar: Making the Right Choices in - Public Contracting Institute · 2018-03-21 · Officer has a right to obtain that data Not required for actions under $750,000 Not required

Answer to Polling Question

Making the Right Choices Part 2-Copyright 2017 Richard D.

Lieberman 8

Page 9: Webinar: Making the Right Choices in - Public Contracting Institute · 2018-03-21 · Officer has a right to obtain that data Not required for actions under $750,000 Not required

Truth in Negotiations Act

If requested to provide certified cost or pricing data, always ensure that the Contracting Officer has a right to obtain that data

Not required for actions under $750,000

Not required for commercial items

Not required where there is adequate price competition

Not required where prices are set by law or regulation

Not required where head of contracting activity waives the requirement

Making the Right Choices Part 2-Copyright 2017 Richard D.

Lieberman 9

Page 10: Webinar: Making the Right Choices in - Public Contracting Institute · 2018-03-21 · Officer has a right to obtain that data Not required for actions under $750,000 Not required

Polling Question

What would you do if a solicitation stated that all offerors must provide certified cost or pricing data, but you believe there is an exception and such data isn’t lawfully required?a) Be quiet and provide the data

b) Wait till after offers are submitted to complain or protest

c) Submit a protest prior to the RFP closing date

Making the Right Choices Part 2-Copyright 2017 Richard D.

Lieberman 10

Page 11: Webinar: Making the Right Choices in - Public Contracting Institute · 2018-03-21 · Officer has a right to obtain that data Not required for actions under $750,000 Not required

Answer to Polling Question

Making the Right Choices Part 2-Copyright 2017 Richard D.

Lieberman 11

Page 12: Webinar: Making the Right Choices in - Public Contracting Institute · 2018-03-21 · Officer has a right to obtain that data Not required for actions under $750,000 Not required

Making the Right Choices Part 2-Copyright 2017 Richard D.

Lieberman 12

Truth In Negotiations Act

Always provide accurate, current and complete certified cost or pricing data to the government when cost or pricing data is required

Cost or pricing data are all facts (not estimates) that prudent buyer or seller would reasonably expect to affect price negotiation

They are used to determine price reasonableness

Includes vendor quotes, nonrecurring costs, unit cost trends, make/buy decisions, changes in production methods, other things that are factual.

Must certify data are “accurate, current and complete”

If “defective pricing,” you are subject to price reductions, e.g. FAR 52.215-11

Page 13: Webinar: Making the Right Choices in - Public Contracting Institute · 2018-03-21 · Officer has a right to obtain that data Not required for actions under $750,000 Not required

Contract Types

Never abuse micropurchase or simplified acquisition programs (“SAT”) or be complicit in such abuse

Micropurchases (under $3,500 for goods, under $2,500 for services and under $2,000 for construction)

Simplified acquisitions (under $150,000)

Abuses:

Must solicit three sources for SAT buys

Cannot break down requirements to evade any of the thresholds

Do not buy improper things such as: Alcohol

Internet pornography

Six months of personal long distance and cell phone calls

Brand name items at high prices (Coach briefcase, Oakley sunglasses)

GAO-02-1041

Making the Right Choices Part 2-Copyright 2017 Richard D.

Lieberman 13

Page 14: Webinar: Making the Right Choices in - Public Contracting Institute · 2018-03-21 · Officer has a right to obtain that data Not required for actions under $750,000 Not required

Contract Types

Whenever the government is buying commercial items, insist that it use the procedures in FAR Part 12, commercial item procurements

Preference in law & FAR for use of commercial items when they are available to meet agency needs. 41 USC 1907-7, 10 USC 2375-77, FAR 12.101

Definition of “commercial items” and “commercially available off the shelf items” in FAR 2.101 is very broad.

Fixed price type contracts only

Include, to maximum extent practicable, only clauses specified in FAR 12.301, use commercial quality control procedures

Do not allow an agency to use a “standard” government contract, with all of its burdensome terms and conditions, for a commercial item.

“Tailoring” is allowed only based on market research showing what is consistent with commercial practice

Making the Right Choices Part 2-Copyright 2017 Richard D.

Lieberman 14

Page 15: Webinar: Making the Right Choices in - Public Contracting Institute · 2018-03-21 · Officer has a right to obtain that data Not required for actions under $750,000 Not required

Contract Types

Be certain you understand economic price adjustment factors in fixed price, economic price adjustment contract.

FAR 16.203 authorizes fixed price contracts with economic price adjustment (“EPA”), upward or downward:

Based on established prices in the contract

Based on actual costs of labor or material

Based on cost indices of labor or material (most common)

Request price increases whenever contract allows it

In Multiple Award Schedule contracts (up to 20 years) use the “price adjustment” clause (GSAR 552.216-70)

Initially possible after 12 months, then up to 3 increases per year

At least 30 days between price increases

Gov’t may accept, negotiate price increase or remove item

Making the Right Choices Part 2-Copyright 2017 Richard D.

Lieberman 15

Page 16: Webinar: Making the Right Choices in - Public Contracting Institute · 2018-03-21 · Officer has a right to obtain that data Not required for actions under $750,000 Not required

Contract Types

Be certain you understand the rights that a contractor has in a cost-plus-incentive-fee (CPIF) contract A cost-plus-incentive-fee contract

is a cost-reimbursement contract that provides for the initially negotiated fee to be adjusted later by a formula based on the relationship of total allowable costs to total target costs. This contract type specifies a target cost, a target fee, minimum and maximum fees, and a fee adjustment formula. After contract performance, the fee payable to the contractor is determined in accordance with the formula. The formula provides, within limits, for increases in fee above target fee when total allowable costs are less than target costs, and decreases in fee below target fee when total allowable costs exceed target costs. FAR 16.405-1

A cost-reimbursement contract incentivizes the contractor to control costs.

Contractor must devote managerial attention to maintaining costs at or belowtarget cost in order maximize fee (profit).

Making the Right Choices Part 2-Copyright 2017 Richard D.

Lieberman 16

Page 17: Webinar: Making the Right Choices in - Public Contracting Institute · 2018-03-21 · Officer has a right to obtain that data Not required for actions under $750,000 Not required

Contract Types

Be sure you understand the award fee formula and evaluation criteria in your cost-plus-award-fee (CPAF) contract.

A CPAF contract is

a cost-reimbursement contract that provides for a fee consisting of (1) a base amount fixed at inception of the contract, … and (2) an award amount that the contractor may earn in whole or in part during performance and that is sufficient to provide motivation for excellence in the areas of cost, schedule, and technical performance. [] The amount of award fee earned shall be commensurate with the contractor's overall cost, schedule, and technical performance as measured against contract requirements in accordance with the criteria stated in the award-fee plan. Award fee shall not be earned if the contractor's overall cost, schedule, and technical performance in the aggregate is below satisfactory. FAR 16.405-2, FAR 16.401(e)

Example: Contractor and government estimate total annual cost to be incurred, then allocate 9% of it to an award fee pool, which is the maximum fee (profit) available. Gov’t makes evaluations every 6 months, and awards a percentage of pool to contractor based on performance.

Making the Right Choices Part 2-Copyright 2017 Richard D.

Lieberman 17

Page 18: Webinar: Making the Right Choices in - Public Contracting Institute · 2018-03-21 · Officer has a right to obtain that data Not required for actions under $750,000 Not required

Contract Types

Always keep in mind the government’s wide range of options in requirements and Indef. Deliv. Indef. Quantity (IDIQ) contracts

Requirements contract: government buys specified goods or services from ONE contractor for all its needs during a specified period by issuing orders

Government can’t buy goods from any contractor other than the requirements contractor.

Government must inform contractor during formation of its realistic estimates of requirements (including past requirements)

IDIQ contract: used to acquire goods or services when exact times or quantities of deliveries are not known as contract award.

IDIQ contract must contain minimum quantity or dollar amount and may contain a maximum quantity or dollar value.

Orders may only be issued during the contract period, but performance of

orders may extend beyond the contract period.

Making the Right Choices Part 2-Copyright 2017 Richard D.

Lieberman 18

Page 19: Webinar: Making the Right Choices in - Public Contracting Institute · 2018-03-21 · Officer has a right to obtain that data Not required for actions under $750,000 Not required

Making the Right Choices Part 2-Copyright 2017 Richard D.

Lieberman 19

Multiple Award Schedules-part A

When required, always properly disclose your commercial sales practices on the General Services Administration (“GSA”) Commercial Sales Practice (“CSP”) form

Requirement to disclose contractor’s actual practices

Failure to make full and complete disclosure can result in defective pricing

Requires disclosure of all “discounts” which are very broadly defined Reduction to catalog prices, published or unpublished

Rebates, quantity discounts, purchase option credits

Anything that reduces the amount of money a customer ultimately pays

Any price lower than list price is considered a discount

Requires disclosure of all “concessions, which are very broadly defined Benefit, enhancement or privilege, other than discount, which reduces cost

Includes freight allowance, extended warranty, extended price guarantee, free installation and bonus goods

Requires disclosure prior to award of Multiple Award Schedule (“MAS”) contract. GSBCA No. 4878

Page 20: Webinar: Making the Right Choices in - Public Contracting Institute · 2018-03-21 · Officer has a right to obtain that data Not required for actions under $750,000 Not required

Making the Right Choices Part 2-Copyright 2017 Richard D.

Lieberman 20

Multiple Award Schedules-part A

When required, always give most-favored customer pricing to the Government throughout the entire life of the contract.

(a) Before award of a contract, the [parties] will agree upon (1) the customer (or category of customers) which will be the basis of award, and (2) the Government's price or discount relationship to the identified customer (or category of customers). This relationship shall be maintained through out the contract period. Any change in the Contractor's commercial pricing or discount arrangement applicable to the identified customer (or category of customers) which disturbs this relationship shall constitute a price reduction….

(c) (1) A price reduction shall apply to purchases under this contract if, after the date negotiations conclude, the Contractor--(i) Revises the commercial catalog, pricelist, schedule or other document upon which contract award was predicated to reduce prices; (ii) Grants more favorable discounts or terms and conditions than those contained in the commercial catalog, pricelist, schedule or other documents upon which contract award was predicated; or (iii) Grants special discounts to the customer (or category of customers) that formed the basis of award, and the change disturbs the price/discount relationship of the Government to the customer (or category of customers) that was the basis of award.

(2) The Contractor shall offer the price reduction to the Government with the same effective date, and for the same time period, as extended to the commercial customer (or category of customers)…

(d) (1)There shall be no price reduction for sales[](1) To commercial customers under firm, fixed-price definite quantity contracts with specified delivery in excess of the maximum order threshold specified in this contract;[or]

(2) To Federal agencies….

GSAM 552.238-75, Price Reductions.

Page 21: Webinar: Making the Right Choices in - Public Contracting Institute · 2018-03-21 · Officer has a right to obtain that data Not required for actions under $750,000 Not required

Multiple Award Schedules-Part B –(Excludes

Dep’t of Veterans Affairs Schedule)

New Multiple Award Schedule Approach by GSA known as “Transactional Data Reporting (“TDR”)-result unknown. 81 Fed. Reg 41104

This is a pilot program involving 30% of GSA MAS line items, about 45% of GSA MAS dollars

GSA evaluates MAS proposals without requiring a CSP form, uses TDR data to determine reasonableness, or asks for more information “other than cost or pricing data”

Contractor must agree to provide monthly detailed transactional data to GSA

Alternate Price Reductions clause in these contracts merely states that gov’t may request a temporary or permanent price reduction and the contractor may offer a voluntary price reduction at any time. GSAR 552.238-75 (No mandatory price reductions, but remains to be seen)

Making the Right Choices Part 2-Copyright 2017 Richard D.

Lieberman 21

Page 22: Webinar: Making the Right Choices in - Public Contracting Institute · 2018-03-21 · Officer has a right to obtain that data Not required for actions under $750,000 Not required

Polling Question

You have a GSA Multiple Award Schedule contract that includes the clause requiring you to grant “most favored customer pricing” to the government. Your local office in Troy, Ohio sells 15 electronic slide projectors to a local customer, at a 22 percent discount from list. Your contract states that the Government is entitled to a 15 percent discount from list. GSA auditors find this sale 18 months later. During that 18 months, you have sold 100 projectors on the GSA contract at the 15% discount. What is the government entitled to?

1) A refund for the amount that equals a 37% discount off list on all 100 projectors (22 % + 15 %)

2) A refund for the amount that equals the regular 22 % discount on all 100 projectors.

3) A refund for 7% off on all 100 projectors (22% minus 15%)

4) Nothing

Making the Right Choices Part 2-Copyright 2017 Richard D.

Lieberman 22

Page 23: Webinar: Making the Right Choices in - Public Contracting Institute · 2018-03-21 · Officer has a right to obtain that data Not required for actions under $750,000 Not required

Answer to Polling Question

Making the Right Choices Part 2-Copyright 2017 Richard D.

Lieberman 23

Page 24: Webinar: Making the Right Choices in - Public Contracting Institute · 2018-03-21 · Officer has a right to obtain that data Not required for actions under $750,000 Not required

Making the Right Choices Part 2-Copyright 2017 Richard D.

Lieberman 24

Lessons Learned Today

Contract Administration issues can be even more complex than formation issues

Learn from the good/bad choices of others — don’t repeat them.

It is important to read the regulations and clauses—always.

It is impossible to tell you about every bad choice, but as you experience government contracting, you will undoubtedly spot them.