EFFECTIVE EFFECTIVE WORK BREAKDOWN WORK BREAKDOWN STRUCTURES STRUCTURES Gregory T. Haugan, PhD, PMP GLH, Incorporated Heathsville, Virginia

Transcript of Wbs Pmi Presentation

Page 1: Wbs Pmi Presentation

EFFECTIVEEFFECTIVE WORK BREAKDOWN WORK BREAKDOWN

STRUCTURESSTRUCTURES

Gregory T. Haugan, PhD, PMPGLH, Incorporated

Heathsville, Virginia

Page 2: Wbs Pmi Presentation

GLH, Incorporated 2

Anatomy of Work Breakdown Anatomy of Work Breakdown StructuresStructures

1. What is a WBS?

2. The 100% Rule

3. Three Types of WBS Structures

4. Four Types of WBS Elements

5. Two Types of Programs

6. Use of WBS to Define Activities

Page 3: Wbs Pmi Presentation

GLH, Incorporated 3

Anatomy of Work Breakdown Anatomy of Work Breakdown StructuresStructures

1. What is a WBS?

2. The 100% Rule

3. Three Types of WBS Structures

4. Four Types of WBS Elements

5. Two Types of Programs

6. Use of WBS to Define Activities

Page 4: Wbs Pmi Presentation

GLH, Incorporated 4

Work Breakdown StructureWork Breakdown StructureFormal Definition per the PMBOK®

Guide:A Deliverable - Oriented Grouping of Project Elements that Organizes and Defines the Total Scope of the Project.Each Descending Level Represents an Increasingly Detailed Definition of the Project Work.

Page 5: Wbs Pmi Presentation

GLH, Incorporated 5

ELEPHANT BREAKDOWN STRUCTURE

Tail Legs Body Head

Page 6: Wbs Pmi Presentation

GLH, Incorporated 6

WBS CONCEPTWBS CONCEPT

Outline of the Work to be PerformedProvides a Framework for Defining the

Work on the Project - SOWProvides a Framework for Planning(Work Not in the WBS is Work Not in

the Project)

Page 7: Wbs Pmi Presentation

GLH, Incorporated 7

DefinitionsDefinitions

A WBS Consists of ElementsThe Lowest Level Element in the WBS

is Often Referred to as a Work PackageA Work Package Consists of Tasks or

ActivitiesElements are Described by NounsActivities Contain Verbs

Page 8: Wbs Pmi Presentation

GLH, Incorporated 8

USERDOCUMENTS

Sample Partial WBSSample Partial WBSSOFTWAREPROJECT

SOFTWARESYSTEM

TRAININGMATERIALS

SYSTEMANALYSIS

PROJECTMGT

MODULE 1 MODULE 2 MODULE 3SYSTEM

TEST

CODING TEST

Level 1

Level 3

Page 9: Wbs Pmi Presentation

GLH, Incorporated 9

Anatomy of Work Breakdown Anatomy of Work Breakdown StructuresStructures

1. What is a WBS?

2. The 100% Rule

3. Three Types of WBS Structures

4. Three Types of WBS Elements

5. Two Types of Programs

6. Use of WBS to Define Activities

Page 10: Wbs Pmi Presentation

GLH, Incorporated 10

100 % Rule100 % Rule

The next level decomposition of a WBS element (child level) must represent 100% of the work applicable to the next higher (parent) element.

Page 11: Wbs Pmi Presentation

GLH, Incorporated 11

PERMITS/INSPECTIONS

SAMPLE WBS - GARAGESAMPLE WBS - GARAGE

GARAGEPROJECT

GARAGEGROUNDS CONSTR.PLANS

PROJECTMGT

WALLSFOUNDATION ROOFUTILITIES

FRAME DOORS/WINDOWS

Level 1

Level 4DOORS/WINDOWS

DRY WALL/

PANELINGASSEMBLY

ASSEMBLY

Page 12: Wbs Pmi Presentation

GLH, Incorporated 12

100 % Rule Importance100 % Rule Importance

If you follow the 100% rule, and define the WBS elements as nouns, you have won the battle to get an effective WBS.

Page 13: Wbs Pmi Presentation

GLH, Incorporated 13

Anatomy of Work Breakdown Anatomy of Work Breakdown StructuresStructures

1. What is a WBS?

2. The 100% Rule

3. Three Types of WBS Structures

4. Four Types of WBS Elements

5. Two Types of Programs

6. Use of WBS to Define Activities

Page 14: Wbs Pmi Presentation

GLH, Incorporated 14

Three Types of WBS Three Types of WBS StructuresStructures

PMBOK® Guide Definition of a Project:

“A temporary endeavor undertaken to create a unique product, product, serviceservice or or resultresult.”.”

Page 15: Wbs Pmi Presentation

GLH, Incorporated 15

Product BreakdownProduct Breakdown

Decomposition of the Natural, Physical Structure of the Deliverable

Follows a BOM FrameworkThe Deliverable is a Tangible ProductMost Common Example Used

Page 16: Wbs Pmi Presentation

GLH, Incorporated 16

PERMITS/INSPECTIONS

SAMPLE WBS - GARAGESAMPLE WBS - GARAGE

GARAGEPROJECT

GARAGEGROUNDS CONSTR.PLANS

PROJECTMGT

WALLSFOUNDATION ROOFUTILITIES

FRAME DOORS/WINDOWS

Level 1

Level 4DOORS/WINDOWS

DRY WALL/

PANELINGASSEMBLY

ASSEMBLY

Page 17: Wbs Pmi Presentation

GLH, Incorporated 17

ServiceService Breakdown BreakdownNo Tangible Output ProductMain Event or “Service”Decomposition Based on a Logical

Grouping (not Physical Structure)Often Developed Bottom-upDetailed Activities May be ChecklistsLend Themselves to Templates

Page 18: Wbs Pmi Presentation

GLH, Incorporated 18

Service Project BreakdownService Project BreakdownInternationalConference

Project

Project Management

DisplaysProgramFacilitiesTransport-

ationAttendees

ToursPresentationsSpouse

ActivitiesReceptions

TranslatorsSpeakersPapers

Level 1

Level 3

Level 4

Page 19: Wbs Pmi Presentation

GLH, Incorporated 19

ResultsResults Project Breakdown Project BreakdownProject Does not have a Well-Structured

Primary Product as a DeliverableMay Have Several Products that

Collectively Achieve the Planned “Result”

The Projects are Process-Based

Page 20: Wbs Pmi Presentation

GLH, Incorporated 20

Results Project WBSResults Project WBS

HACCPPROJECT

1. Work Plan2. Product &

ProcessAnalyses

3. HazardAnalysis

4. Q.A.Process

5. HACCPPlan

Process

6. HACCPImplement-

ation

7. ProjectManagement

Level 1

Page 21: Wbs Pmi Presentation

GLH, Incorporated 21

Anatomy of Work Breakdown Anatomy of Work Breakdown StructuresStructures

1. What is a WBS?

2. The 100% Rule

3. Three Types of WBS Structures

4. Four Types of WBS Elements

5. Two Types of Programs

6. Use of WBS to Define Activities

Page 22: Wbs Pmi Presentation

GLH, Incorporated 22

Four Types of WBS Four Types of WBS Crosscutting ElementsCrosscutting Elements

1. Integrative

2. Analytical

3. Process

4. Project Management

Page 23: Wbs Pmi Presentation

GLH, Incorporated 23

Four Types of WBS Crosscutting Four Types of WBS Crosscutting ElementsElements

1. Integrative1. IntegrativeNew TechnologyBicycle Project

ProjectManagement

BicyclePreliminaryDesign

FrameSeat

AssemblyPedals &

GearsHandlebars Assembly

Level 1

Level 2

Page 24: Wbs Pmi Presentation

GLH, Incorporated 24

Four Types of WBS Crosscutting Four Types of WBS Crosscutting ElementsElements

2. Analytical2. AnalyticalNew PC

Development

ProjectManagement

PersonalComputerDocumentation

StructureCircuitBoards

HardDisk

PowerSupply

Assembly

System TestSystem Analyses

Level 1

Page 25: Wbs Pmi Presentation

GLH, Incorporated 25

Four Types of WBS Crosscutting Four Types of WBS Crosscutting ElementsElements

3. Process3. Process

ProjectManagement

AircraftSystem

Manuals &Data

SupportEquipment

AirVehicle

FacilitiesTest &

Evaluation

Level 1

Page 26: Wbs Pmi Presentation

GLH, Incorporated 26

Four Types of WBS Crosscutting Four Types of WBS Crosscutting ElementsElements

3. Process3. ProcessNew PC

Development

ProjectManagement

PersonalComputerDocumentation

StructureCircuitBoards

HardDisk

PowerSupply

Assembly

System TestSystem Analyses

DesignProcure-

mentFabrication

SubsystemTest

Level 1

Level 2

Page 27: Wbs Pmi Presentation

GLH, Incorporated 27

Four Types of WBS Crosscutting Four Types of WBS Crosscutting ElementsElements

4. Project Management4. Project Management

A Special Type of WBS ElementAll Projects have a PM ElementMay be Looked-at Conceptually as an

“Overhead” Element

Page 28: Wbs Pmi Presentation

GLH, Incorporated 28

Four Types of WBS Crosscutting ElementsFour Types of WBS Crosscutting Elements

4. Project Management4. Project Management

PROJECT START AND FINISH Contract Award

Complete Project

MEETINGS AND REVIEWS Kick-off Meeting

Monthly/Quarterly Project Reviews

Corporate Reviews

In-Process Reviews

Close-out Meeting

Action Item Tracking System

REPORTS Monthly Progress Report

Annual Report

Budget/Financial Status Report

PLANS Project Charter

Master Schedule

Project Plan (Current and Future Phases

Risk Management & etc

Level 3 Level 4 Work Packages

PROJECT MANAGEMENT (Level 2)

Page 29: Wbs Pmi Presentation

GLH, Incorporated 29

Four Types of WBS Crosscutting ElementsFour Types of WBS Crosscutting Elements

4. Project Management4. Project Management

CONTROL Schedule Tracking

Cost Tracking

Earned Value Management Analysis

Variance Analysis

Corrective Action

Work-Arounds

ADMINISTRATIVE Project Management Office

Space/Relocation

Correspondence Control System

PROJECT SUPPORT Procurement/Purchasing

Subcontract Management

Contract Management

Level 3 Level 4 Work Packages

PROJECT MANAGEMENT (Level 2)

Page 30: Wbs Pmi Presentation

GLH, Incorporated 30

Anatomy of Work Breakdown Anatomy of Work Breakdown StructuresStructures

1. What is a WBS?

2. The 100% Rule

3. Three Types of WBS Structures

4. Four Types of WBS Elements

5. Two Types of Programs

6. Use of WBS to Define Activities

Page 31: Wbs Pmi Presentation

GLH, Incorporated 31

Two Types of ProgramsTwo Types of Programs

Life Cycle Phases – Process ProjectsProgram Areas – Series of Projects

PMBOK® GUIDE:A group of related projects managed in a coordinated way. Programs usually include an element of ongoing work.

Page 32: Wbs Pmi Presentation

GLH, Incorporated 32

A Program Life Cycle PhasesA Program Life Cycle Phases

I. Feasibility, Conceptual or Initiation

II. Planning

III. Execution or Implementation

IV. Close-Out

V. Operations and Maintenance

VI. (Program Management)

Page 33: Wbs Pmi Presentation

GLH, Incorporated 33

Example Program AreasExample Program AreasNanotechnologyAlcohol and Drug AbuseCancer ResearchAnti-Terrorism

Page 34: Wbs Pmi Presentation

GLH, Incorporated 34

PM WBS Elements in a PM WBS Elements in a ProgramProgram

Traditional PM Elements at Level 1Level 2 PM Elements for each

Phase/ProjectLevel 2 PM Elements that Relate to

Subsequent Phases– Cross-cutting Analytical Elements– Outputs for Future Phases

Page 35: Wbs Pmi Presentation

GLH, Incorporated 35

Program/Project Management WBSProgram/Project Management WBS

Project Definition Phase

Planning Phase

Closeout Phase

Operation and Maintenance Phase

Program Management

Generic Museum Program

Development and Production Phase

Space Plan

Planning Phase PM

Project Management Office

Development & Production Phase Plans

Closeout And O & M Phase Plans

Planning Project Management

Exhibit Plan-Design Package

Script Package

A B

C D E F

Formative Evaluation & Prototyping

Only Total Program Elements

B.1 B.2 B.3 B.5-6 B.7

1. Schedule & budget tracking

2. Reports 3. Risk management 4. Project reviews

B.7.1

1. Project Plan 2. Project Plan

review and approval

1. Initial WBS and scope

2. Initial resource, schedule & budget

1. Core & extended team

2. Project support office

B.7.2 B.7.3 B.7.4

Education & PR Plans

B.4

Level 0

Level 1

Page 36: Wbs Pmi Presentation

GLH, Incorporated 36

Level 1 PM DecompositionLevel 1 PM Decomposition

ProgramManagement

Etc.Administration

& BudgetCommunications

ProgramSupport

ProgramControl

Level 1

Page 37: Wbs Pmi Presentation

GLH, Incorporated 37

Anatomy of Work Breakdown Anatomy of Work Breakdown StructuresStructures

1. What is a WBS?

2. The 100% Rule

3. Three Types of WBS Structures

4. Four Types of WBS Elements

5. Two Types of Programs

6. Use of WBS to Define Activities

Page 38: Wbs Pmi Presentation

GLH, Incorporated 38

Time Sharing System (TSS) Time Sharing System (TSS) Project WBSProject WBS

TSS PROJECT

TSSSoftware

DesignSpecification

RequirementsSpecification

ProjectManagement

•Project Start•Project Meetings•Project Reports

•Initial Specification•Final Specification

•Initial Specification•Final Specification

•Module 1•Module 2•Integrate Modules

Level 1

Page 39: Wbs Pmi Presentation

GLH, Incorporated 39

WBS in MS Project 98WBS in MS Project 98

Page 40: Wbs Pmi Presentation

GLH, Incorporated 40

WBS and Activities in MS ProjectWBS and Activities in MS Project

Page 41: Wbs Pmi Presentation

GLH, Incorporated 41

SummarySummaryGeneric WBS ElementsGeneric WBS Elements

PROGRAM

ProgramManagement

ProjectA

Phase/Project

1. ProductBreakdownElements

2. ServiceBreakdownElements

3. ResultsBreakdownElements

4. CrosscuttingElements

5. ProjectManagement

Elements

Phase/Project

OngoingWork

Level 0

ProductStructure

Groupings Steps Integrative, Analytical, orProcess

SupportandManagement

Level 1

Level 2

Page 42: Wbs Pmi Presentation

GLH, Incorporated 42

Effective Work Breakdown Effective Work Breakdown StructuresStructures

This presentation is based on the book titled: Effective Work Breakdown Structures authored by Dr. Gregory T. Haugan. It was published in 2002 by Management ConceptsInc. of Vienna, Virginia.

Other books by Dr. Haugan and also published by Management Concepts include:

Project Planning and Scheduling, 2002 and

The Work Breakdown Structure in Government Contracting, 2003

Books may be purchased through Management Concepts at:

www.managementconcepts.com or from Amazon and other on-line stores.

Page 43: Wbs Pmi Presentation

GLH, Incorporated 43

Effective Work Breakdown Structures

Thank You