WBS-diag
description
Transcript of WBS-diag
Task Name Duration Start Finish
Warehouse construction 122 days Mon 2/2/15 Tue 7/21/15
Initiation 5 days Mon 2/2/15 Fri 2/6/15
Confirming Scope 2 days Mon 2/2/15 Tue 2/3/15
Developing Charter 3 days Wed 2/4/15 Fri 2/6/15
Planning 11 days Mon 2/9/15 Mon 2/23/15
Project Team 3 days Mon 2/9/15 Wed 2/11/15
Construction plan approval 5 days Thu 2/12/15 Wed 2/18/15
Project Plan 6 days Mon 2/9/15 Mon 2/16/15
Select vendors 5 days Tue 2/17/15 Mon 2/23/15
Execution 81 days Tue 2/24/15 Tue 6/16/15
Construction of building 74 days Tue 2/24/15 Fri 6/5/15
Electrical work 5 days Tue 2/24/15 Mon 3/2/15
Plumbing 15 days Tue 3/3/15 Mon 3/23/15
Flooring 10 days Wed 4/15/15 Tue 4/28/15
Painting 10 days Wed 4/29/15 Tue 5/12/15
Fixtures & Furniture 7 days Wed 5/13/15 Thu 5/21/15
Security systems 8 days Fri 5/22/15 Tue 6/2/15
IT Systems 10 days Wed 6/3/15 Tue 6/16/15
Closeout 25 days Wed 6/17/15 Tue 7/21/15
Testing of systems 8 days Wed 6/17/15 Fri 6/26/15
Handover 3 days Mon 6/29/15 Wed 7/1/15
Documentation 8 days Wed 7/1/15 Fri 7/10/15
Official close out of project 7 days Mon 7/13/15 Tue 7/21/15