Watts Bar Unit 2
Transcript of Watts Bar Unit 2
Watts Bar Unit 2Tritium Production License Amendment
Pre-Application Meeting
Mark BurzynskiSeptember 26, 2017
Agenda
Purpose Introduction and Background Project Scope Licensing Amendment Request Technical Specification Changes Interface Items with New Analyses Licensing Schedule Closing
| 2Tritium Production License Amendment Pre-Application Meeting | September 26, 2017
Purpose
Pre-submittal meeting to describe the Unit 2 license amendment request (LAR) to authorize tritium production
Summarize LAR content and key results Explain where the Unit 2 LAR differs from the
Unit 1 precedents Identify key schedule milestones to support
Department of Energy (DOE) National Nuclear Security Administration (NNSA) production requirements
PLACE THE TITLE OF THE PRESENTATION HERE | 3
Introduction and Background (1/3)
Tritium Production Program Watts Bar Unit 1 tritium production began in
October 2003DOE-NNSA identified need to expand
production, which requires a second reactor In December 2015, DOE-NNSA notified TVA of
future tritium needs In June 2016, TVA agreed to assess potential
for tritium production for Watts Bar Unit 2
| 4Tritium Production License Amendment Pre-Application Meeting | September 26, 2017
Introduction and Background (2/3)
Watts Bar tritium production target Steady ramp-up of tritium production to
approximately 2800 grams every 18 months by December 2025
July 2016 Unit 1 license amendment authorized 1792 TPBAR production
September 13, 2016 planning meeting held with NRC to discuss Unit 2 TPBAR production
| 5Tritium Production License Amendment Pre-Application Meeting | September 26, 2017
Introduction and Background (3/3)
Unit 2 LAR to be submitted in December 2017 with requested approval by May 31, 2019
Approval needed to support tritium production beginning in Unit 2 Cycle 4 (currently scheduled for November 2020)
| 6Tritium Production License Amendment Pre-Application Meeting | September 26, 2017
Project Scope (1/2)
Plant Modifications Replacing seven CCS and ERCW relief valves to
address post-LOCA subcriticality margin Increasing the required minimum dilution flowrate
setpoint during radioactive effluent releases from 20,000 gpm to 30,000 gpm
Reverse osmosis unit Impact on liquid radioactive effluents determined not to be
required for 10 CFR Part 20 compliance Adding to Liquid Radwaste System to provide additional
operational capabilities for effluent management
| 7Tritium Production License Amendment Pre-Application Meeting | September 26, 2017
Project Scope (2/2)
TVA Engineering Documentation Westinghouse analyses PNNL engineering documentation Holtec analyses S&L revisions to affected dose calculations, FSAR,
and System Descriptions LAR to operate with 1792 TPBARs at Watts Bar
Unit 2
| 8Tritium Production License Amendment Pre-Application Meeting | September 26, 2017
License Amendment Request (1/3)
Watts Bar Unit 2 LAR for tritium production based on Watts Bar Unit 1 precedents Addresses 17 plant-specific interface items from
NUREG 1672 Safety Evaluation Report for DOE Tritium Production Core Topical Report
Addresses post-LOCA subcriticality for lithium leaching effects
Updates information for two-unit tritium production for environmental assessment
Effect on thermal conductivity degradation would be treated in same manner as for Unit 1 PAD4TCD licensing issue for Unit 2 License Condition would not
be coupled with Unit 2 TPBAR LAR
| 9Tritium Production License Amendment Pre-Application Meeting | September 26, 2017
License Amendment Request (2/3)
Watts Bar Unit 2 LAR for tritium production addresses lessons learned from emergent industry issues Interface Item #4 includes new reactor vessel fluence
evaluations that address issues documented in RIS 2014-11
Interface Item #10 includes results of new spent fuel rack criticality analyses that uses the latest version of NEI 12-16
| 10Tritium Production License Amendment Pre-Application Meeting | September 26, 2017
License Amendment Request (3/3)
Watts Bar Unit 2 LAR for tritium production addresses lessons learned from the NRC review of the Unit 1 application and the Unit 2 LAR preparation Interface Item #5 includes results of new accident
analyses updated to bound the use of original and replacement steam generators and updated primary and secondary radionuclide concentrations
Interface Item #14 includes results of new radioactive effluent assessments that address effects of two unit tritium production on radioactive effluent management
| 11Tritium Production License Amendment Pre-Application Meeting | September 26, 2017
Technical Specification Changes (1/3)
Proposed change revises the Unit 2 Technical Specification (TS) 4.2.1, "Fuel Assemblies," to add a limit on the number of Tritium Producing Burnable Absorber Rods (TPBARs) that can be irradiated Change is analogous to changes implemented in
Watts Bar Unit 1
| 12Tritium Production License Amendment Pre-Application Meeting | September 26, 2017
Technical Specification Changes (2/3)
Proposed change revises the Units 1 and 2 TSs affected by the new spent fuel rack criticality analysis TS 3.7.15, “Spent Fuel Assembly Storage,” revised to
simplify the fuel storage limitations on fuel assemblies by eliminating burnup–related criteria
TS 3.7.18, “Fuel Storage Pool Boron Concentration,” added to specify minimum fuel storage pool boron concentration when fuel is stored in the pool
TS 3.9.9, “Spent Fuel Pool Boron Concentration,” revised to modify the minimum fuel storage pool boron concentration during refueling operations when fuel is stored in the pool
| 13Tritium Production License Amendment Pre-Application Meeting | September 26, 2017
Technical Specification Changes (3/3)
Proposed change revises the Units 1 and 2 TSs affected by the new spent fuel rack criticality analysis (continued) TS 4.3, “Fuel Storage,” revised to replace the storage
limitations on fuel assembly initial enrichment, burnup, and storage location limitations with a single requirement to maintain a specified boron concentration in the spent fuel pool
TS 5.7.2.21, “Spent Fuel Storage Rack Neutron Absorber Monitoring Program,” added to incorporate the NRC-approved NEI 16-03-A guidance
| 14Tritium Production License Amendment Pre-Application Meeting | September 26, 2017
Interface Item #4 – Reactor Vessel Integrity
New heatup and cooldown P-T limit curves generated using limiting Adjusted Reference Temperature values for WBN Unit 2
P-T limit curves generated for 32 effective full-power years using the KIc methodology detailed in the 1998 through the 2000 Addenda Edition of the ASME Code, Section XI, Appendix G Methodology is consistent with the NRC-approved
methodology documented in WCAP-14040-A, Revision 4.
| 15Tritium Production License Amendment Pre-Application Meeting | September 26, 2017
Interface Item #5 – Control Room Dose Analyses
Main steam line break and steam generator tube rupture analyses updated Bounds use of original and replacement steam
generators Correct some errors affecting primary and secondary
radionuclide concentrations Tritium assumptions remain the same as for Watts
Bar Unit 1 Dose results remain well within 10 CFR Part 100 and
10 CFR Part 50 Appendix A GDC 19 dose limits.
| 16Tritium Production License Amendment Pre-Application Meeting | September 26, 2017
Interface Item #10 – Fuel Rack Criticality Analyses (1/2)
Watts Bar spent fuel pool contains a single type of BORALTM racks with flux traps designed for storage of pressurized water reactor fuel.
Criticality control in the BORALTM storage racks rely on the following: Fixed neutron absorbers: BORALTM panels Storage cell spacing, i.e., flux traps between storage
cells Soluble boron
| 17Tritium Production License Amendment Pre-Application Meeting | September 26, 2017
Interface Item #10 – Fuel Rack Criticality Analyses (2/2)
Criticality calculations qualify the BORALTM
storage racks uniformly loaded with fresh fuel assemblies with an initial enrichment up to 5 weight percent 235U Bounding fuel density of all types of fuel assemblies is
considered Bounding approach provides analysis simplicity and
adequate margin Neutron absorber monitoring program, will be
implemented following the NRC-approved guidance in NEI 16-03-A
| 18Tritium Production License Amendment Pre-Application Meeting | September 26, 2017
Interface Item #14 – Radioactive Liquid Effluents (1/4)
New analysis of liquid and gaseous radioactive effluents performed: Included effects of tritium production in Watts Bar
Units 1 and 2 Updated primary and secondary radionuclide
concentrations Minimum dilution flow required for discharge of
radioactivity into the Cooling Tower Blowdown lines increased from 20,000 gpm to 30,000 gpm
Results demonstrate that both 10 CFR Part 20 effluent concentration limit values and 10 CFR Part 50 Appendix I dose limits are met
| 19Tritium Production License Amendment Pre-Application Meeting | September 26, 2017
Interface Item #14 – Radioactive Liquid Effluents (2/4)
| 20
Liquid Release, Mobile Demineralizer ProcessingDual Unit Operation
Design C/ECLTotal (no TPC) 5.65E-01
Total (with TPC) 8.35E-01Liquid Release, Direct SGBD Release at Maximum Appendix I
Dual Unit OperationDesign C/ECL
Total (no TPC) 5.79E-01Total (with TPC) 8.47E-01
Tritium Production License Amendment Pre-Application Meeting | September 26, 2017
Interface Item #14 – Radioactive Liquid Effluents (3/4)
| 21
Annual Radioactive Liquid Emissions
Non-TPC Dose
TPCDose
Incremental Increase from
TPC
NRC Annual Effluent
Exposure Guideline
Maximally Exposed Individual (mrem) Total Body
0.34 0.37 0.03 3.00Total Body
Maximally Exposed Individual (mrem) Organ
0.47(Liver)
0.49(Liver) 0.02 10.00
Any Organ50-mile Population Dose (person-rem)
6.9(Thyroid)
11.0(Thyroid) 4.1 NA
Tritium Production License Amendment Pre-Application Meeting | September 26, 2017
Interface Item #14 – Radioactive Liquid Effluents (4/4)
| 22
Annual Radioactive Gaseous Emissions
Non-TPC Dose
TPCDose
Incremental Increase from
TPC
NRC Annual Effluent
Exposure Guideline
Maximally Exposed Individual (mrem) Total Body
0.63 0.63 0 5.00Total Body
Maximally Exposed Individual (mrem) Organ
11.9(Bone)
12.7(Bone) 0.8 15.00
Any Organ50-mile Population Dose (person-rem)
16.0(Thyroid)
21.4(Thyroid) 5.4 NA
Tritium Production License Amendment Pre-Application Meeting | September 26, 2017
Licensing Schedule
| 23Tritium Production License Amendment Pre-Application Meeting | September 26, 2017
Closing
LAR is scheduled to be submitted in December 2017 requesting approval to operate with 1792 TPBARs at Watts Bar Unit 2 Based on DOE need to expand tritium production
Watts Bar Unit 2 LAR for tritium production based on Watts Bar Unit 1 precedents Includes new analyses to address lessons learned
from emergent industry issues and NRC review of the Unit 1 application to simplify NRC review
TVA requests approval of the proposed License Amendment by May 31, 2019, to support TPBAR irradiation starting in Watts Bar Unit 2 Cycle 4
| 24Tritium Production License Amendment Pre-Application Meeting | September 26, 2017