Water Treatment Plant Project Ppt

16
WATER TREATMENT PLANT

Transcript of Water Treatment Plant Project Ppt

Page 1: Water Treatment Plant Project Ppt

WATER TREATMENT PLANT

Page 2: Water Treatment Plant Project Ppt

INTRODUCTION

• The objective of designing this water treatment plant for ALDEL campus is to provide clean water for the entire campus.

• The Water treatment plant is being designed for water that has been drawn from the ground.

Page 3: Water Treatment Plant Project Ppt

POPULATION ESTIMATE

No. of students 1469

Teaching & non teaching staffs 108

Hostel and staff population 95

Canteen staff 20

Page 4: Water Treatment Plant Project Ppt

PER CAPITA PER DAY WATER REQUIREMENT - CPHEEO NORMS

1. Domestic 140 to 172 lpcd

2. Industrial, Commercial and Community requirementbased on 45000 litres per hect. per day

47 lpcd

3. Fire protection based on 1% of the total demand

3 lpcd

3. Floating population and special uses like hotels and Embassies

52 lpcd

Page 5: Water Treatment Plant Project Ppt

WATER REQUIREMENT ESTIMATE FROM GUIDELINES

Heads litersWater required for 1469 students @ 47 liters per day 69043

Water required for 108 teaching & non teaching staff @47 liters per day

5047

Water required for 95 hostel and staff population @ 140 liters per day

13440

Water required for 20 canteen staff @ 47 liters per day

940

Water required for Gardening purpose @ 3 liters per person per day for 1692

5076

Total Required 93596

Design requirement 1,00,000

Page 6: Water Treatment Plant Project Ppt

TESTS PERFORMED

Page 7: Water Treatment Plant Project Ppt

Removing Hardness

• SOFTENING • The two basic methods of softening public water

supplies are – chemical precipitation (Lime and Soda ash) and – ion exchange.

• Other methods can also be used to soften water, such as electrodialysis, distillation, freezing, and reverse osmosis.

• These processes are complex and expensive .

Page 8: Water Treatment Plant Project Ppt

Lime and Soda Ash• The chemicals normally used are lime (calcium hydroxide, Ca(OH)2)

and soda ash (sodium carbonate, Na2CO3). – Lime is used to remove the chemicals that cause the carbonate

hardness. – Soda ash is used to remove the chemicals that cause the non-

carbonate hardness.

• In this process Calcium and Magnesium ions are precipitated by the addition of lime (Ca(OH)2) and soda ash (Na2CO3).

Page 9: Water Treatment Plant Project Ppt

ReactionsLIME ADDITION:-

LIME AND SODA ADDITION:-

Page 10: Water Treatment Plant Project Ppt

Lime and Soda dosageTheoritical Quantity Actual Quantity

Lime Required 229.13 mg/L Lime Required 330 mg/L

Soda ash Required 70.25 mg/L Soda ash Required 130 mg/L

Page 11: Water Treatment Plant Project Ppt

Experiments performed

• Total hardness test• Jar test• pH meter test• Titration for chlorine content test

Page 12: Water Treatment Plant Project Ppt
Page 13: Water Treatment Plant Project Ppt

Components and flow Chart of water treatment plant

Page 14: Water Treatment Plant Project Ppt

Aeration Tank

Design Criteria For Cascade Aerators• Number of trays = 4 to 9

• Spacing of trays = 0.3 to 0.75 m c/c

• Height of the structure = 2 m

• Space requirement = 0.015-0.045 m2/m3/hr

Design CalculationQmax = 0.1543 m3/sec.

Provide area at tray = 17 m2

Diameter of bottom most tray = 5 m

Rise of each tray = 0.4 m

Tread of each tray = 50 cm

Page 15: Water Treatment Plant Project Ppt

Aeration (cascade type)

Page 16: Water Treatment Plant Project Ppt

THANKS for Your Patience