WATER SURVEY RESEARCH CENTER #2

79
POOR ($) (1-5 YEARS) FAIR ($) (5-10 YEARS) GOOD ($) (10-20 YEARS) EXCELLENT ($) (20+ YEARS) EXPECTED REMAINING SERVICE LIFE TOTAL ($) $/GSF PERCENT OF BUILDING TOTAL (%) TRADE B U I L D I N G D I S C I P L I N E R E P L A C E M E N T C O S T S U M M A R Y MECHANICAL 239,700 256,100 495,800 9.08 18.8 PLUMBING 23,400 37,300 29,400 162,600 252,600 4.63 9.6 FIRE PROTECTION 115,000 115,000 2.11 4.4 ELECTRICAL 510,900 162,400 628,400 1,301,600 23.85 49.5 COMMUNICATIONS 466,100 466,100 8.54 17.7 889,000 37,300 913,900 791,000 2,631,200 48.22 33.8 1.4 34.7 30.1 TOTAL % OF TOTAL NO CRITICAL ITEMS IDENTIFIED FOR THIS BUILDING NOTE: Cost Estimates are Construction Costs are in 2013 dollars to Replace in Kind unless otherwise noted. WATER SURVEY RESEARCH CENTER #2 4/10/2013 2204 SOUTH GRIFFITH DRIVE CHAMPAIGN , ILLINOIS 61820 .338 SYSTEM CONDITION INDEX 0289 $ 2,631,200 BUILDING SYSTEM REPLACEMENT COST 54,571 BUILDING GROSS SQUARE FEET 1 NUMBER OF BUILDING STORIES 1964 ORIGINAL YEAR OF CONSTRUCTION BUILDING SURVEY DATE OFFICE PRIMARY BUILDING USE CCJM: Josh Polasky (M), Stanley Panek (E) BUILDING SURVEY TEAM NOTE: THIS REPORT INCLUDES BUILDING NUMBERS 1104, 1107, 1108 & 1109 UIUC/UIS MEP CONDITION ASSESSMENT UIUC PROJECT NUMBER U12151 CANNON DESIGN PROJECT NUMBER 4009.01 WATER SURVEY RESEARCH CENTER #2 0289 - PAGE 1

Transcript of WATER SURVEY RESEARCH CENTER #2

Page 1: WATER SURVEY RESEARCH CENTER #2

POOR ($)(1-5 YEARS)

FAIR ($)(5-10 YEARS)

GOOD ($)(10-20 YEARS)

EXCELLENT ($)(20+ YEARS)

E X P E C T E D R E M A I N I N G S E R V I C E L I F E

TOTAL ($) $/GSF

PERCENT OF BUILDING TOTAL (%)

TRADE

B U I L D I N G D I S C I P L I N E R E P L A C E M E N T C O S T S U M M A R Y

MECHANICAL 239,700 256,100 495,800 9.08 18.8

PLUMBING 23,400 37,300 29,400 162,600 252,600 4.63 9.6

FIRE PROTECTION 115,000 115,000 2.11 4.4

ELECTRICAL 510,900 162,400 628,400 1,301,600 23.85 49.5

COMMUNICATIONS 466,100 466,100 8.54 17.7

889,000 37,300 913,900 791,000 2,631,200 48.2233.8 1.4 34.7 30.1

TOTAL% OF TOTAL

NO CRITICAL ITEMS IDENTIFIED FOR THIS BUILDING

NOTE: Cost Estimates are Construction Costs are in 2013 dollars to Replace in Kind unless otherwise noted.

WATER SURVEY RESEARCH CENTER #2

4/10/2013

2204 SOUTH GRIFFITH DRIVECHAMPAIGN , ILLINOIS 61820

.338

SYSTEMCONDITION

INDEX

0289

$ 2,631,200

BUILDING SYSTEMREPLACEMENT

COST

54,571

BUILDINGGROSS

SQUARE FEET

1

NUMBEROF BUILDING

STORIES

1964

ORIGINALYEAR OF

CONSTRUCTION

BUILDING SURVEY DATEOFFICEPRIMARY BUILDING USE

CCJM: Josh Polasky (M), Stanley Panek (E)BUILDING SURVEY TEAM

NOTE: THIS REPORT INCLUDES BUILDING NUMBERS 1104, 1107, 1108 & 1109

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 1

Page 2: WATER SURVEY RESEARCH CENTER #2

POOR(1-5 YEARS)

FAIR(5-10 YEARS)

GOOD(10-20 YEARS)

EXCELLENT(20+ YEARS)

E X P E C T E D R E M A I N I N G S E R V I C E L I F E

TOTALSYSTEM/COMPONENT

Text106M E C H A N I C A L D I S C I P L I N E R E P L A C E M E N T C O S T S U M M A R Y

CHILLED WATER SYSTEM

113,200 113,200Cooling System

HEATING HOT WATER SYSTEM

105,900 105,900Heating Hot Water System

SUPPLY AIR SYSTEM

239,700 239,700Air Handling System

LABORATORY EXHAUST SYSTEM

4,500 4,500Air Handling System

HVAC CONTROLS SYSTEM

32,400 32,400HVAC Controls

239,700 256,100 495,800

48.3 51.7% OF TOTAL

MECHANICAL TOTAL

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 2

Page 3: WATER SURVEY RESEARCH CENTER #2

Text6 C O O L I N G S Y S T E M A S S E S S M E N T D A T A

Comments Buildings 1, 2, and 4-6 total 54.000 sq/ft.

The chilled water pumps have VFDs installed but the system is run at a constant speed. The cooling tower fans are cycled on and off to maintain a condenser water temp of 78F.

Date Installed 1/1/2005

Description The entire Water Survey Research Center Complex is connected to a 429 ton York chiller located in Building #2, which provides all cooling. The chiller is centrifugal and located in room #226B. There are two cooling towers located on the South side of Building #2. The BAS gives the chiller a run enable, controls the two chilled water pumps, the condenser pump, and the two cooling tower fans.

Chiller = 429 ton York MaxE Centrifugal Chiller (Unit Model YK CH CF P5 – CN FS)3 pumps = 60 HP each2 Cooling Towers = Baltimore Aircoil Company (Model #94600421)

Overall Condition Good

Replacement Cost $113,200

Remaining Useful Life 20+ Years Nominal Useful Life: 30 Years

Item ID 301726

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 3

Page 4: WATER SURVEY RESEARCH CENTER #2

Text6 C O O L I N G S Y S T E M S U R V E Y P H O T O G R A P H S

Chiller Chilled water pumps (60 hp) Cooling towers

Single cooling tower

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 4

Page 5: WATER SURVEY RESEARCH CENTER #2

Text6 H E A T I N G H O T W A T E R S Y S T E M A S S E S S M E N T D A T A

Comments 54,000 sq/ft is the combined square footage of buildings 1, 2, 4, 5, and 6.

Date Installed 1/1/2005

Description (4) 2,000 MBH Aerco condensing boilers serve preheat, reheat, and perimeter radiation throughout the complex. There are 2 hot water pumps (1 is 100% standby) with a flow capacity of 850 gpm each.

Equipment Tag Boiler #1 - #4

Manufacturer Aerco – Benchmark 2.0

Overall Condition Good

Replacement Cost $105,900

Size/Capacity 2,000 MBH

Remaining Useful Life 20 Years Nominal Useful Life: 30 Years

Item ID 301739

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 5

Page 6: WATER SURVEY RESEARCH CENTER #2

Text6 H E A T I N G H O T W A T E R S Y S T E M S U R V E Y P H O T O G R A P H S

Row of boilers Boiler front control panel Hot water pumps (40 hp, 850 gmp)

Hot water piping to other buildings

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 6

Page 7: WATER SURVEY RESEARCH CENTER #2

Text6 A I R H A N D L I N G S Y S T E M A S S E S S M E N T D A T A

Comments Units are all functional and were visited by a retro commissioning team in 2012.buildings.

Date Installed 1/1/1984

Description There are 11 AHUs total between the 5 buildings surveyed, all are constant volume. Buildings 1, 4, 5, and 6 each have 2 AHUs. For these buildings, one of the units is on the roof and serves the center of the building; the other unit is located in the mech. room and serves the perimeter rooms.Building 2 has 3 rooftop units and one unit above the ceiling in room 224. Roof top unit size -3000CFM to 4000 CFM. For estimation purposes, here are the spaces that need service:Building 1 = 10,404 sq/ftBuilding 2 = 10,923 sq/ftBuilding 4, 5, and 6 (almost identical) = 11.040 sq/ft

Overall Condition Poor

Replacement Cost $239,700

Remaining Useful Life Exceeded Nominal Useful Life: 30 Years

Item ID 301725

Text6 A I R H A N D L I N G S Y S T E M S U R V E Y P H O T O G R A P H S

AHU on roof (in background) AHU on roof of building #4

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 7

Page 8: WATER SURVEY RESEARCH CENTER #2

Text6 A I R H A N D L I N G S Y S T E M A S S E S S M E N T D A T A

Date Installed 1/1/1997

Description Building #4 has 1 hood which failed University inspection. Building #6 has 1 functional hood and 1 hood listed as “restricted” by the University.

Overall Condition Good

Recommendation Remove 2 nonfunctional hoods. Assess whether replacements are necessary given very limited use.

Replacement Cost $4,500

Remaining Useful Life 14 Years Nominal Useful Life: 30 Years

Item ID 301738

Text6 A I R H A N D L I N G S Y S T E M S U R V E Y P H O T O G R A P H S

Nonfunctional fume hood (building #6) Functional fume hood (building #6)

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 8

Page 9: WATER SURVEY RESEARCH CENTER #2

Text6 H V A C C O N T R O L S A S S E S S M E N T D A T A

Comments The controls are either new (2012) or were maximized by the retro commissioning team, which repaired many existing problems.

Date Installed 1/1/2012

Description Existing pneumatic controls on AHUs were replaced with a Siemens DDC system in 2012. Humidity sensors were installed in the return air on a majority of the AHUs.

The majority of the reheats and perimeter radiation are pneumatically controlled by space thermostats. Building 2 is an exception; it’s controlled digitally through a thermostat and Terminal Equipment Controller (TEC).

The York chillers are monitored by a BAS through Modbus communication. The BAC also controls the Aerco boiler management system and pumps through Modbus communication.

A Quincy/Pneumatech pneumatic compressor system serves pneumatic controls (dual 5-hp motors).

Manufacturer Siemens and others

Overall Condition Good

Recommendation The AHU system is soon due for replacement – update and/or integrate controls at that time.

Replacement Cost $32,400

Remaining Useful Life 17 Years Nominal Useful Life: 18 Years

Item ID 301740

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 9

Page 10: WATER SURVEY RESEARCH CENTER #2

Text6 H V A C C O N T R O L S S U R V E Y P H O T O G R A P H S

Thermostat Quincy/Pneumatech pneumatic compressor system Pneumatic piping

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 10

Page 11: WATER SURVEY RESEARCH CENTER #2

POOR(1-5 YEARS)

FAIR(5-10 YEARS)

GOOD(10-20 YEARS)

EXCELLENT(20+ YEARS)

E X P E C T E D R E M A I N I N G S E R V I C E L I F E

TOTALSYSTEM/COMPONENT

Text106P L U M B I N G D I S C I P L I N E R E P L A C E M E N T C O S T S U M M A R Y

DOMESTIC HOT WATER SYSTEM

37,300 37,300Domestic Hot and Cold Water

PLUMBING FIXTURES SYSTEM

29,400 29,400Plumbing Fixtures

SUB-SOIL DRAINAGE SYSTEM

23,400 23,400Storm and Subsoil Drainage

PROCESS WATER SYSTEM

162,600 162,600Lab Processes

23,400 37,300 29,400 162,600 252,600

9.2 14.8 11.6 64.4% OF TOTAL

PLUMBING TOTAL

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 11

Page 12: WATER SURVEY RESEARCH CENTER #2

Text6 D O M E S T I C H O T A N D C O L D W A T E R A S S E S S M E N T D A T A

Date Installed 1984 and 2005

Description PVI Turbopower gas water heater (installed 2005, 125 gal, 339,000 Btu/h) serves building 1 and 2 and is in excellent condition.

Buildings 4-6 are almost identical and are each served by an electric, 80 gal, residential-type water heater. 2 of these are from the 80s and one is from 2005. 2 additional 80 gal heaters are used for water storage only.

Overall Condition Fair

Recommendation Replace 2 of the 3 electric water heaters in buildings 4-6.

Replacement Cost $37,300

Remaining Useful Life 0 – 20 Years Nominal Useful Life: 50 Years

Item ID 301727

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 12

Page 13: WATER SURVEY RESEARCH CENTER #2

Text6 D O M E S T I C H O T A N D C O L D W A T E R S U R V E Y P H O T O G R A P H S

Water heater for buildings 1 and 2 Domestic cold water pipes in building #4 Water heaters in building #4 (one is water storage only, poor condition due to age)

Single water heater in building #6 (excellent condition)

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 13

Page 14: WATER SURVEY RESEARCH CENTER #2

Text6 P L U M B I N G F I X T U R E S A S S E S S M E N T D A T A

Comments Approximately 20-25 toilets, 25 sinks, 6-7 urinals, 5-6 kitchenette sinks, and 5-6 janitor sinks. No problems reported.

Date Installed 1/1/1984

Description Bathroom and kitchenette fixtures are of various ages and in mostly fair condition.

Overall Condition Good

Replacement Cost $29,400

Remaining Useful Life 20 Years Nominal Useful Life: 50 Years

Item ID 301748

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 14

Page 15: WATER SURVEY RESEARCH CENTER #2

Text6 P L U M B I N G F I X T U R E S S U R V E Y P H O T O G R A P H S

Toilet and sink Standard sinks Kitchenette sink

Fountain

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 15

Page 16: WATER SURVEY RESEARCH CENTER #2

Text6 S T O R M A N D S U B S O I L D R A I N A G E A S S E S S M E N T D A T A

Comments Failed sump pump has been replaced with temporary one.

Date Installed 1/1/1964

Description Roofs drain internally. There are no basements in any of the assessed buildings. The only sub-grade room is the main mechanical room #226B in Building #2. That room has a pit with a sump pump.

Despite poor rating, this system functions normally with no problems reported.

Overall Condition Poor

Recommendation Replace temporary sump pump with permanent one.

Replacement Cost $23,400

Remaining Useful Life Exceeded Nominal Useful Life: 50 Years

Item ID 301750

Text6 S T O R M A N D S U B S O I L D R A I N A G E S U R V E Y P H O T O G R A P H S

Roof showing drains Sump pump pit

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 16

Page 17: WATER SURVEY RESEARCH CENTER #2

Text6 L A B P R O C E S S E S A S S E S S M E N T D A T A

Date Installed 1/1/2007

Description Building #6 has lab air, lab vacuum, and deionized water systems, all in good condition.

Lab air compressor = Speedair, 1 HP Lab vacuum = Speedair, ¾ HPDI Water System = M2 Innovative Solutions

Overall Condition Excellent

Replacement Cost $162,600

Remaining Useful Life 24 Years Nominal Useful Life: 30 Years

Item ID 301745

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 17

Page 18: WATER SURVEY RESEARCH CENTER #2

Text6 L A B P R O C E S S E S S U R V E Y P H O T O G R A P H S

Lab compressor Lab vacuum Deionized water system

Deionized water system different angle

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 18

Page 19: WATER SURVEY RESEARCH CENTER #2

POOR(1-5 YEARS)

FAIR(5-10 YEARS)

GOOD(10-20 YEARS)

EXCELLENT(20+ YEARS)

E X P E C T E D R E M A I N I N G S E R V I C E L I F E

TOTALSYSTEM/COMPONENT

Text106F I R E P R O T E C T I O N D I S C I P L I N E R E P L A C E M E N T C O S T S U M M A R Y

FIRE ALARM SYSTEM

41,600 41,600Fire Alarm System

64,600 64,600Fire Alarm System – 1107, 1108 and 1109

STANDPIPE SYSTEM

8,800 8,800Standpipe

115,000 115,000

100.0% OF TOTAL

FIRE PROTECTION TOTAL

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 19

Page 20: WATER SURVEY RESEARCH CENTER #2

Text6 F I R E A L A R M S Y S T E M A S S E S S M E N T D A T A

Date Installed 1989 and 2005

Description Fire alarm system includes pull stations, horns, strobes, smoke detectors and heat detectors. Main panel was replaced in 2005.

Equipment Tag -

HP/kW -

Manufacturer Pyrotronics

Material -

Model Number MXL

Overall Condition Poor

Recommendation Upgrade to new system

Replacement Cost $41,600

Serial Number -

Size/Capacity -

Remaining Useful Life Exceeded Nominal Useful Life: 20 Years

Voltage -

Item ID 301737

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 20

Page 21: WATER SURVEY RESEARCH CENTER #2

Text6 F I R E A L A R M S Y S T E M S U R V E Y P H O T O G R A P H S

Fire alarm interconnection box Typical pull station Strobe/horn

Fire Alarm Panel

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 21

Page 22: WATER SURVEY RESEARCH CENTER #2

Text6 F I R E A L A R M S Y S T E M – 1 1 0 7 , 1 1 0 8 A N D 1 1 0 9 A S S E S S M E N T D A T A

Date Installed 1/1/1989

Description Fire alarm system includes pull stations, horns, strobes, smoke detectors and heat detectors. Main panel is located in bldg.#2

Equipment Tag -

HP/kW -

Manufacturer Pyrotronics

Material -

Model Number MXL

Overall Condition Poor

Recommendation Upgrade to new system

Replacement Cost $64,600

Serial Number -

Size/Capacity -

Remaining Useful Life Exceeded Nominal Useful Life: 20 Years

Voltage -

Item ID 301736

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 22

Page 23: WATER SURVEY RESEARCH CENTER #2

Text6 F I R E A L A R M S Y S T E M – 1 1 0 7 , 1 1 0 8 A N D 1 1 0 9 S U R V E Y P H O T O G R A P H S

Horn/strobe and pull station Smoke detector and strobe Strobe/horn at exit door

Pull station

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 23

Page 24: WATER SURVEY RESEARCH CENTER #2

Text6 S T A N D P I P E A S S E S S M E N T D A T A

Comments No sprinklers.

Date Installed 1/1/1964

Description Standpipes serve buildings 1, 2, and 4-6 and are original to building (1964).

Overall Condition Poor

Replacement Cost $8,800

Size/Capacity 2” pipe

Remaining Useful Life 0-5 Years Nominal Useful Life: 50 Years

Item ID 301749

Text6 S T A N D P I P E S U R V E Y P H O T O G R A P H S

Typical standpipe cabinet Another standpipe cabinet

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 24

Page 25: WATER SURVEY RESEARCH CENTER #2

POOR(1-5 YEARS)

FAIR(5-10 YEARS)

GOOD(10-20 YEARS)

EXCELLENT(20+ YEARS)

E X P E C T E D R E M A I N I N G S E R V I C E L I F E

TOTALSYSTEM/COMPONENT

Text106E L E C T R I C A L D I S C I P L I N E R E P L A C E M E N T C O S T S U M M A R Y

LOW VOLTAGE SYSTEM

162,400 162,400Low Voltage Distribution

253,100 253,100Low Voltage Distribution – 1107, 1108 and 1109

SWITCHGEAR

304,600 304,600Switchboard

EMERGENCY POWER SYSTEM

68,200 68,200Emergency Power System

106,300 106,300Emergency Power System – 1107, 1108 and 1109

INTERIOR LIGHTING

126,500 126,500Interior Lighting

197,200 197,200Interior Lighting – 1107, 1108 and 1109

EMERGENCY LIGHTING SYSTEM

15,300 15,300Emergency Lighting System

23,000 23,000Emergency Lighting System – 1107, 1108 and 1109

EXIT LIGHTING SYSTEM

11,800 11,800Exit lighting System

17,600 17,600Exit lighting System – 1107, 1108 and 1109

EXTERIOR LIGHTING SYSTEM

6,200 6,200Exterior Lighting

9,400 9,400Exterior Lighting – 1107, 1108 and 1109

510,900 162,400 628,400 1,301,600

39.3 12.5 48.3% OF TOTAL

ELECTRICAL TOTAL

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 25

Page 26: WATER SURVEY RESEARCH CENTER #2

Text6 L O W V O L T A G E D I S T R I B U T I O N A S S E S S M E N T D A T A

Date Installed 1964 ,1984 and 2004

Description Buildings were installed in1964. In 2004 new 2000 KVA transformer and 2500 A switchboard was installed to provide service to existing distribution panelboards located within (6) buildings.

Equipment Tag -

HP/kW -

Manufacturer Federal Pacific and Cutler Hammer

Material -

Model Number -

Overall Condition Good

Recommendation .

Replacement Cost $162,400

Serial Number -

Size/Capacity -

Remaining Useful Life 15 Years Nominal Useful Life: 40 Years

Voltage 277/480V and 120/208 V

Item ID 301747

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 26

Page 27: WATER SURVEY RESEARCH CENTER #2

Text6 L O W V O L T A G E D I S T R I B U T I O N S U R V E Y P H O T O G R A P H S

Typical panelboard in mech room Typical panelboard in office area 2000KVA transformer

Distribution Panelboard

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 27

Page 28: WATER SURVEY RESEARCH CENTER #2

Text6 L O W V O L T A G E D I S T R I B U T I O N – 1 1 0 7 , 1 1 0 8 A N D 1 1 0 9 A S S E S S M E N T D A T A

Date Installed 1/1/1964

Description Each building receives 480 V power from switchboard located in building #2. Local transformers provide 120/208 V for lighting and receptacles.

Equipment Tag -

HP/kW -

Manufacturer Federal Pacific

Material -

Model Number -

Overall Condition Poor

Recommendation .

Replacement Cost $253,100

Serial Number -

Size/Capacity -

Remaining Useful Life Exceeded Nominal Useful Life: 40 Years

Voltage 277/480V and 120/208 V

Item ID 301746

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 28

Page 29: WATER SURVEY RESEARCH CENTER #2

Text6 L O W V O L T A G E D I S T R I B U T I O N – 1 1 0 7 , 1 1 0 8 A N D 1 1 0 9 S U R V E Y P H O T O G R A P H S

Typical panelboard –bldg #4 Emergency panelboard –bldg #4 112.5 KVA transformer

Panelboard-bldg #5

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 29

Page 30: WATER SURVEY RESEARCH CENTER #2

Text6 S W I T C H B O A R D A S S E S S M E N T D A T A

Date Installed 1/1/2005

Description 2500 A main switch (located in separate enclosure) and switchboard with (12) feeder breakers serving (6) buildings. 2500 A main switch is located in separate enclosure.

Equipment Tag MDSB

HP/kW -

Manufacturer Cutler -Hammer

Material Copper bus

Model Number SDC47675

Overall Condition Excellent

Recommendation -

Replacement Cost $304,600

Serial Number -

Size/Capacity 2500 A

Remaining Useful Life 35 Years Nominal Useful Life: 40 Years

Voltage 277/480 V

Item ID 301751

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 30

Page 31: WATER SURVEY RESEARCH CENTER #2

Text6 S W I T C H B O A R D S U R V E Y P H O T O G R A P H S

Switchboard Switchboard data Distribution section

Main Switch

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 31

Page 32: WATER SURVEY RESEARCH CENTER #2

Text6 E M E R G E N C Y P O W E R S Y S T E M A S S E S S M E N T D A T A

Comments Existing system is not recognized as emergency power.

Critical Issues Installation of emergency lighting and exit signs with battery back up

Date Installed 1/1/1984

Description 100 A breaker located at main switchboard is designated as “emergency power” and provide protection for emergency panelboard EMD. From EMD located in building #2 power is distributed to five buildings.

Equipment Tag -

HP/kW -

Manufacturer -

Material -

Model Number -

Overall Condition Poor

Replacement Cost $68,200

Serial Number -

Size/Capacity -

Remaining Useful Life Exceeded Nominal Useful Life: 25 Years

Voltage 120 V

Item ID 301731

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 32

Page 33: WATER SURVEY RESEARCH CENTER #2

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 33

Page 34: WATER SURVEY RESEARCH CENTER #2

Text6 E M E R G E N C Y P O W E R S Y S T E M – 1 1 0 7 , 1 1 0 8 A N D 1 1 0 9 A S S E S S M E N T D A T A

Comments Existing system is not recognized as emergency power.

Critical Issues Installation of emergency lighting and exit signs with battery back up

Date Installed 1/1/1984

Description 100 A breaker located at main switchboard is designated as “emergency power” and provide protection for emergency panelboard EMD. From EMD located in building #2 power is distributed to five buildings.

Equipment Tag -

HP/kW -

Manufacturer -

Material -

Model Number -

Overall Condition Poor

Replacement Cost $106,300

Serial Number -

Size/Capacity -

Remaining Useful Life Exceeded Nominal Useful Life: 25 Years

Voltage 120 V

Item ID 301730

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 34

Page 35: WATER SURVEY RESEARCH CENTER #2

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 35

Page 36: WATER SURVEY RESEARCH CENTER #2

Text6 I N T E R I O R L I G H T I N G A S S E S S M E N T D A T A

Date Installed 3/28/2011

Description Offices, corridors and labs have been illuminated with two lamp type fluorescent fixtures. Lamps and ballasts were replaced in 2011.Fixtures were installed in 1985

Equipment Tag -

HP/kW -

Manufacturer -

Material -

Model Number -

Overall Condition Excellent

Recommendation -

Replacement Cost $126,500

Serial Number -

Size/Capacity -

Remaining Useful Life 23 Years Nominal Useful Life: 25 Years

Voltage 277 V

Item ID 301744

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 36

Page 37: WATER SURVEY RESEARCH CENTER #2

Text6 I N T E R I O R L I G H T I N G S U R V E Y P H O T O G R A P H S

Lab lighting Conference room lighting Office lighting

Storage lighting

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 37

Page 38: WATER SURVEY RESEARCH CENTER #2

Text6 I N T E R I O R L I G H T I N G – 1 1 0 7 , 1 1 0 8 A N D 1 1 0 9 A S S E S S M E N T D A T A

Date Installed 3/28/2011

Description Offices, corridors and labs have been illuminated with two lamp type fluorescent fixtures. Lamps and ballasts were replaced in 2011.Fixtures were installed in 1985

Equipment Tag -

HP/kW -

Manufacturer -

Material -

Model Number -

Overall Condition Excellent

Recommendation -

Replacement Cost $197,200

Serial Number -

Size/Capacity -

Remaining Useful Life 23 Years Nominal Useful Life: 25 Years

Voltage 120 V and 277V

Item ID 301743

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 38

Page 39: WATER SURVEY RESEARCH CENTER #2

Text6 I N T E R I O R L I G H T I N G – 1 1 0 7 , 1 1 0 8 A N D 1 1 0 9 S U R V E Y P H O T O G R A P H S

Office lighting-bldg #4 Office lighting-bldg #5 Office lighting-bldg #6

Corridor lighting

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 39

Page 40: WATER SURVEY RESEARCH CENTER #2

Text6 E M E R G E N C Y L I G H T I N G S Y S T E M A S S E S S M E N T D A T A

Critical Issues Installation of emergency lighting with battery back up

Date Installed 1/1/1984

Description Emergency circuits originated from emergency panelboard provide power to selected light fixtures located in corridors.

Equipment Tag -

HP/kW -

Manufacturer -

Material -

Model Number -

Overall Condition Poor

Recommendation -

Replacement Cost $15,300

Serial Number -

Size/Capacity -

Remaining Useful Life Exceeded Nominal Useful Life: 25 Years

Voltage 120 V

Item ID 301729

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 40

Page 41: WATER SURVEY RESEARCH CENTER #2

Text6 E M E R G E N C Y L I G H T I N G S Y S T E M S U R V E Y P H O T O G R A P H S

Corridor lighting includes emergency fixtures Emergency light in corridor

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 41

Page 42: WATER SURVEY RESEARCH CENTER #2

Text6 E M E R G E N C Y L I G H T I N G S Y S T E M – 1 1 0 7 , 1 1 0 8 A N D 1 1 0 9 A S S E S S M E N T D A T A

Critical Issues Installation of emergency lighting with battery back up

Date Installed 1/1/1984

Description Emergency circuits originated from emergency panelboard provide power to selected light fixtures located in corridors.

Equipment Tag -

HP/kW -

Manufacturer -

Material -

Model Number -

Overall Condition Poor

Recommendation -

Replacement Cost $23,000

Serial Number -

Size/Capacity -

Remaining Useful Life Exceeded Nominal Useful Life: 25 Years

Voltage 120 V

Item ID 301728

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 42

Page 43: WATER SURVEY RESEARCH CENTER #2

Text6 E M E R G E N C Y L I G H T I N G S Y S T E M – 1 1 0 7 , 1 1 0 8 A N D 1 1 0 9 S U R V E Y P H O T O G R A P H S

Corridor lighting- includes emergency fixtures Emergency light in corridor

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 43

Page 44: WATER SURVEY RESEARCH CENTER #2

Text6 E X I T L I G H T I N G S Y S T E M A S S E S S M E N T D A T A

Date Installed 1/1/1964

Description Box type exit sign with (2) incandescent lamps

Equipment Tag -

HP/kW -

Manufacturer -

Material -

Model Number -

Overall Condition Poor

Recommendation Replacement with LED type battery back up signs

Replacement Cost $11,800

Serial Number -

Size/Capacity -

Remaining Useful Life Exceeded Nominal Useful Life: 25 Years

Voltage 120 V

Item ID 301733

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 44

Page 45: WATER SURVEY RESEARCH CENTER #2

Text6 E X I T L I G H T I N G S Y S T E M S U R V E Y P H O T O G R A P H S

Typical exit sign-pic 1 Typical exit sign-pic2 Typical exit sign -pic3

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 45

Page 46: WATER SURVEY RESEARCH CENTER #2

Text6 E X I T L I G H T I N G S Y S T E M – 1 1 0 7 , 1 1 0 8 A N D 1 1 0 9 A S S E S S M E N T D A T A

Date Installed 1/1/1964

Description Box type exit sign with (2) incandescent lamps

Equipment Tag -

HP/kW -

Manufacturer -

Material -

Model Number -

Overall Condition Poor

Recommendation Replacement with LED type battery back up signs

Replacement Cost $17,600

Serial Number -

Size/Capacity -

Remaining Useful Life Exceeded Nominal Useful Life: 25 Years

Voltage 120 V

Item ID 301732

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 46

Page 47: WATER SURVEY RESEARCH CENTER #2

Text6 E X I T L I G H T I N G S Y S T E M – 1 1 0 7 , 1 1 0 8 A N D 1 1 0 9 S U R V E Y P H O T O G R A P H S

Typical exit sign-pic 1 Typical exit sign-pic2 Typical exit sign –pic3

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 47

Page 48: WATER SURVEY RESEARCH CENTER #2

Text6 E X T E R I O R L I G H T I N G A S S E S S M E N T D A T A

Date Installed 1/1/1984

Description Wall pack or recessed canopy lighting

Equipment Tag -

HP/kW -

Manufacturer -

Material -

Model Number -

Overall Condition Poor

Recommendation Replace with high efficiency fixtures at the end of remaining fixture life.

Replacement Cost $6,200

Serial Number -

Size/Capacity -

Remaining Useful Life Exceeded Nominal Useful Life: 25 Years

Voltage 277 V

Item ID 301735

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 48

Page 49: WATER SURVEY RESEARCH CENTER #2

Text6 E X T E R I O R L I G H T I N G S U R V E Y P H O T O G R A P H S

Main entry-no exterior lighting Fixture at west side Canopy Light fixture

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 49

Page 50: WATER SURVEY RESEARCH CENTER #2

Text6 E X T E R I O R L I G H T I N G – 1 1 0 7 , 1 1 0 8 A N D 1 1 0 9 A S S E S S M E N T D A T A

Date Installed 1/1/1984

Description Wall pack or recessed canopy lighting

Equipment Tag -

HP/kW -

Manufacturer -

Material -

Model Number -

Overall Condition Poor

Recommendation Replace with high efficiency fixtures at the end of remaining fixture life add site walkway lights

Replacement Cost $9,400

Serial Number -

Size/Capacity -

Remaining Useful Life Exceeded Nominal Useful Life: 25 Years

Voltage 277 V

Item ID 301734

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 50

Page 51: WATER SURVEY RESEARCH CENTER #2

Text6 E X T E R I O R L I G H T I N G – 1 1 0 7 , 1 1 0 8 A N D 1 1 0 9 S U R V E Y P H O T O G R A P H S

Overhang lighting Site lighting Overhang lighting close up

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 51

Page 52: WATER SURVEY RESEARCH CENTER #2

POOR(1-5 YEARS)

FAIR(5-10 YEARS)

GOOD(10-20 YEARS)

EXCELLENT(20+ YEARS)

E X P E C T E D R E M A I N I N G S E R V I C E L I F E

TOTALSYSTEM/COMPONENT

Text106C O M M U N I C A T I O N S D I S C I P L I N E R E P L A C E M E N T C O S T S U M M A R Y

DATA SYSTEM

37,800 37,800Communication Infrastructure System - 1104

40,600 40,600Communication Infrastructure System - 1107

40,100 40,100Communication Infrastructure System - 1108

40,200 40,200Communication Infrastructure System - 1109

39,700 39,700Communication Infrastructure System - 289

77,600 77,600Voice/Data System

120,900 120,900Voice/Data System – 1107, 1108 and 1109

SECURITY ACCESS CONTROL SYSTEM

27,700 27,700Access Control

41,500 41,500Access Control – 1107, 1108 and 1109

466,100 466,100

100.0% OF TOTAL

COMMUNICATIONS TOTAL

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 52

Page 53: WATER SURVEY RESEARCH CENTER #2

Text6 C O M M U N I C A T I O N I N F R A S T R U C T U R E S Y S T E M - 1 1 0 4 A S S E S S M E N T D A T A

Date Installed UIUC network upgrade complete (date range 2006 to 2012)

Description Water Survey Research Centers (WSRC) 1, 2, 4, 5 and 6 are all fed from one IDF located in WSRC 2 (building 289). The IDF is fed with 36 strands of single mode fiber and 1000 copper pairs with each pair grounded and individually protected by a fuse/surge arrestor. The IDF is located in room 206 on the first floor. Fiber distributes radially from the building IDF to hub rooms (telecommunication rooms) to within 100 meters of end-use equipment and lands at rack mounted fiber switch(es) within the hub room.

In WSRC 1 (building 1104) there is one hub room located in room 151 to feed the entire building (Hub A). The hub room is equipped with one free standing rack and wire management. Cables appear to be routed loose above the ceiling. The hub room has a technology ground bar tied into the building grounding system. The hub room has a dedicated electrical panel. The hub room also has a dedicated Liebert Data Mate split system AC unit and remote condensing unit.

Outlet standards typically have 1"C stubbed to cable management. Standard outlet consists of two network cables and two data jacks. Station cable consists of Cat 6. The building is typically equipped with WIFI throughout (coverage not noted)

Overall Condition Good

Replacement Cost $37,800

Remaining Useful Life 20 Years Nominal Useful Life: 20 Years

Item ID 301830

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 53

Page 54: WATER SURVEY RESEARCH CENTER #2

Text6 C O M M U N I C A T I O N I N F R A S T R U C T U R E S Y S T E M - 1 1 0 4 S U R V E Y P H O T O G R A P H S

WSRC 1, Building 1104 Hub Room Rack WSRC 1, Building 1104 Hub Room AC unit WSRC 1, Building 1104 Hub Room

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 54

Page 55: WATER SURVEY RESEARCH CENTER #2

Text6 C O M M U N I C A T I O N I N F R A S T R U C T U R E S Y S T E M - 1 1 0 7 A S S E S S M E N T D A T A

Date Installed UIUC network upgrade complete (date range 2006 to 2012)

Description Water Survey Research Centers (WSRC) 1, 2, 4, 5 and 6 are all fed from one IDF located in WSRC 2 (building 289). The IDF is fed with 36 strands of single mode fiber and 1000 copper pairs with each pair grounded and individually protected by a fuse/surge arrestor. Fiber distributes radially from the building IDF to hub rooms (telecommunication rooms) to within 100 meters of end-use equipment and lands at rack mounted fiber switch(es) within the hub room.

In WSRC 4 (building 1107) there is one hub room located within a fenced area in computer room 405 to feed the entire building (Hub F). The room has raised floor and a dedicated chilled water computer room cooling unit (Pomona Air). The hub room is equipped with one free standing rack and wire management. The hub room has a technology ground bar tied into the building grounding system. The hub room has smoke detector protection.

Outlet standards typically have 1"C stubbed to cable management. Standard outlet consists of two network cables and two data jacks. Station cable consists of Cat 6 (Mohawk Advancenet). The building is typically equipped with WIFI throughout (coverage not noted)

Overall Condition Good

Replacement Cost $40,600

Remaining Useful Life 20 Years Nominal Useful Life: 20 Years

Item ID 301831

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 55

Page 56: WATER SURVEY RESEARCH CENTER #2

Text6 C O M M U N I C A T I O N I N F R A S T R U C T U R E S Y S T E M - 1 1 0 7 S U R V E Y P H O T O G R A P H S

Rack Mounted Patch Panel Data Rack Receptacles and Ground Bar Computer Room Cooling Unit

WSRC 4, Building 1107 Hub Room

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 56

Page 57: WATER SURVEY RESEARCH CENTER #2

Text6 C O M M U N I C A T I O N I N F R A S T R U C T U R E S Y S T E M - 1 1 0 8 A S S E S S M E N T D A T A

Date Installed UIUC network upgrade complete (date range 2006 to 2012)

Description Water Survey Research Centers (WSRC) 1, 2, 4, 5 and 6 are all fed from one IDF located in WSRC 2 (building 289). The IDF is fed with 36 strands of single mode fiber and 1000 copper pairs with each pair grounded and individually protected by a fuse/surge arrestor. Fiber distributes radially from the building IDF to hub rooms (telecommunication rooms) to within 100 meters of end-use equipment and lands at rack mounted fiber switch(es) within the hub room.

In WSRC 5 (building 1108) there is one hub room located within a fenced area in computer room 505 to feed the entire building (Hub G). The room has a ceiling mounted computer room cooling unit. The hub room is equipped with one free standing rack and wire management. The hub room has a dedicated electrical panel and a technology ground bar tied into the building grounding system. The hub room has smoke detector protection.

Outlet standards typically have 1"C stubbed to cable management. Standard outlet consists of two network cables and two data jacks. Station cable consists of Cat 6 (Mohawk Advancenet). The building is typically equipped with WIFI throughout (coverage not noted)

Overall Condition Good

Replacement Cost $40,100

Remaining Useful Life 20 Years Nominal Useful Life: 20 Years

Item ID 301832

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 57

Page 58: WATER SURVEY RESEARCH CENTER #2

Text6 C O M M U N I C A T I O N I N F R A S T R U C T U R E S Y S T E M - 1 1 0 8 S U R V E Y P H O T O G R A P H S

Data Rack Receptacles Computer Room Ceiling Mounted AC Unit WSRC 5, Building 1108 Hub Room

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 58

Page 59: WATER SURVEY RESEARCH CENTER #2

Text6 C O M M U N I C A T I O N I N F R A S T R U C T U R E S Y S T E M - 1 1 0 9 A S S E S S M E N T D A T A

Date Installed UIUC network upgrade complete (date range 2006 to 2012)

Description Water Survey Research Centers (WSRC) 1, 2, 4, 5 and 6 are all fed from one IDF located in WSRC 2 (building 289). The IDF is fed with 36 strands of single mode fiber and 1000 copper pairs with each pair grounded and individually protected by a fuse/surge arrestor. Fiber distributes radially from the building IDF to hub rooms (telecommunication rooms) to within 100 meters of end-use equipment and lands at rack mounted fiber switch(es) within the hub room.

In WSRC 6 (building 1109) there is one hub room located within a fenced area in room 622A to feed the entire building (Hub C). The hub room is equipped with one free standing rack and wire management. The hub room has a technology ground bar tied into the building grounding system. The hub room has smoke detector protection. The hub room does not have dedicated cooling systems-conditioned/exhausted by the base building system.

Outlet standards typically have 1"C stubbed to cable management. Standard outlet consists of two network cables and two data jacks. Station cable consists of Cat 6. The building is typically equipped with WIFI throughout (coverage not noted)

Overall Condition Good

Replacement Cost $40,200

Remaining Useful Life 20 Years Nominal Useful Life: 20 Years

Item ID 301833

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 59

Page 60: WATER SURVEY RESEARCH CENTER #2

Text6 C O M M U N I C A T I O N I N F R A S T R U C T U R E S Y S T E M - 1 1 0 9 S U R V E Y P H O T O G R A P H S

WSRC 6, Building 1109 Hub Room

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 60

Page 61: WATER SURVEY RESEARCH CENTER #2

Text6 C O M M U N I C A T I O N I N F R A S T R U C T U R E S Y S T E M - 2 8 9 A S S E S S M E N T D A T A

Date Installed UIUC network upgrade complete (date range 2006 to 2012)

Description Water Survey Research Centers (WSRC) 1, 2, 4, 5 and 6 are all fed from one IDF located in WSRC 2 (building 289). The IDF is fed with 36 strands of single mode fiber and 1000 copper pairs with each pair grounded and individually protected by a fuse/surge arrestor. The IDF is located in room 206 on the first floor. Fiber distributes radially from the building IDF to hub rooms (telecommunication rooms) to within 100 meters of end-use equipment and lands at rack mounted fiber switch(es) within the hub room.

In WSRC 2 (building 289) there is one hub room located within a fenced area in room 208B to feed the entire building (Hub D). The hub room is equipped with one free standing rack and wire management. The hub room has a technology ground bar tied into the building grounding system. The hub room has smoke detector protection. The hub room does not have dedicated cooling systems-conditioned/exhausted by the base building system.

Outlet standards typically have 1"C stubbed to cable management. Standard outlet consists of two network cables and two data jacks. Station cable consists of Cat 6. The building is typically equipped with WIFI throughout (coverage not noted)

Overall Condition Good

Replacement Cost $39,700

Remaining Useful Life 20 Years Nominal Useful Life: 20 Years

Item ID 301834

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 61

Page 62: WATER SURVEY RESEARCH CENTER #2

Text6 C O M M U N I C A T I O N I N F R A S T R U C T U R E S Y S T E M - 2 8 9 S U R V E Y P H O T O G R A P H S

Water Survey Research Buildings IDF WSRC 2, Building 289 Hub Room WSRC 2, Building 289 Data Rack Receptacles and Ground

Water Survey Research Buildings IDF

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 62

Page 63: WATER SURVEY RESEARCH CENTER #2

Text6 V O I C E / D A T A S Y S T E M A S S E S S M E N T D A T A

Comments MDF room was not accessible.

Date Installed 1/1/2002

Description Voice/data outlets are installed at offices and labs.

Equipment Tag -

HP/kW -

Manufacturer -

Material -

Model Number -

Overall Condition Good

Recommendation -

Replacement Cost $77,600

Serial Number -

Size/Capacity -

Remaining Useful Life 10 Years Nominal Useful Life: 20 Years

Voltage -

Item ID 301742

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 63

Page 64: WATER SURVEY RESEARCH CENTER #2

Text6 V O I C E / D A T A S Y S T E M S U R V E Y P H O T O G R A P H S

Fiber service for voice and data Typical data outlet Wi Fi antenna

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 64

Page 65: WATER SURVEY RESEARCH CENTER #2

Text6 V O I C E / D A T A S Y S T E M – 1 1 0 7 , 1 1 0 8 A N D 1 1 0 9 A S S E S S M E N T D A T A

Comments MDF room was not accessible.

Date Installed 1/1/2002

Description Voice/data outlets are installed at offices and labs.

Equipment Tag -

HP/kW -

Manufacturer -

Material -

Model Number -

Overall Condition Good

Recommendation -

Replacement Cost $120,900

Serial Number -

Size/Capacity -

Remaining Useful Life 10 Years Nominal Useful Life: 20 Years

Voltage -

Item ID 301741

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 65

Page 66: WATER SURVEY RESEARCH CENTER #2

Text6 V O I C E / D A T A S Y S T E M – 1 1 0 7 , 1 1 0 8 A N D 1 1 0 9 S U R V E Y P H O T O G R A P H S

Typical data outlet Typical data outlet Wi Fi antenna

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 66

Page 67: WATER SURVEY RESEARCH CENTER #2

Text6 A C C E S S C O N T R O L A S S E S S M E N T D A T A

Date Installed 1/1/2004

Description Card access system. Utilizes Andover program to activate employee ID card to allow entry. Computer with Andover program is located in Room #116

Equipment Tag -

HP/kW -

Manufacturer Best

Material -

Model Number -

Overall Condition Good

Recommendation -

Replacement Cost $27,700

Serial Number --

Size/Capacity -

Remaining Useful Life 10 Years Nominal Useful Life: 20 Years

Voltage -

Item ID 301724

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 67

Page 68: WATER SURVEY RESEARCH CENTER #2

Text6 A C C E S S C O N T R O L S U R V E Y P H O T O G R A P H S

Card reader

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 68

Page 69: WATER SURVEY RESEARCH CENTER #2

Text6 A C C E S S C O N T R O L – 1 1 0 7 , 1 1 0 8 A N D 1 1 0 9 A S S E S S M E N T D A T A

Date Installed 1/1/2004

Description Card access system. Utilizes Andover program to activate employee ID card to allow entry. Computer with Andover program is located in building #2 Room#116

Equipment Tag -

HP/kW -

Manufacturer Best

Material -

Model Number -

Overall Condition Good

Recommendation -

Replacement Cost $41,500

Serial Number --

Size/Capacity -

Remaining Useful Life 10 Years Nominal Useful Life: 20 Years

Voltage -

Item ID 301723

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 69

Page 70: WATER SURVEY RESEARCH CENTER #2

Text6 A C C E S S C O N T R O L – 1 1 0 7 , 1 1 0 8 A N D 1 1 0 9 S U R V E Y P H O T O G R A P H S

Card reader-bldg #4 Card reader-bldg #5

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 70

Page 71: WATER SURVEY RESEARCH CENTER #2

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 71

Page 72: WATER SURVEY RESEARCH CENTER #2

Item ID

W A T E R S U R V E Y R E S E A R C H C E N T E R # 2 L E G A C Y A S S E S S M E N T S U M M A R Y

CODEPOOR FAIRIDENTIFIED ISSUEREQUIREMENT

NUMBERINSPECTION

DATE TOTALLEGACYVALUE

PERCENTCOMPLETE

GENERAL LEGACY ITEMS ITEMS

12,500REQ-51373 ADA: Install Auto Opener on Front Door10/8/2002 12,50012,500 0.0305641

5,400REQ-51447 ADA: Non-Compliant Kitchenette10/8/2002 5,4005,400 0.0305649

800REQ-52337 Flooring: Replace VAT10/8/2002 800800 0.0305646

6,200REQ-51293 Glazing: Install Compliant Glazing10/8/2002 6,2006,200 0.0305645

REQ-51448 Concrete: Repair Sidewalk & Loading Dock10/8/2002 5,100 100.0305650

24,200REQ-52403 Exterior Wall: Re-point Brick10/8/2002 24,20024,200 0.0305642

6,500REQ-52405 Window: Replace Aluminum Framed Window10/8/2002 6,5006,500 0.0305643

2,200REQ-57411 Fire Barrier: Unprotected Penetrations10/7/2005 2,2002,200 0.0305644

32,900 12,500 12,400GENERAL LEGACY ITEMS TOTALS 57,80062,900 8.1

MEP LEGACY ITEMS ITEMS

30,900REQ-52404 ADA: Restrooms ADA Non-Compliant10/8/2002 30,90030,900 0.0305647

133,900REQ-56037 Data: Upgrade Network Infrastructure10/8/2002 133,900133,900 0.0305648

133,900 30,900MEP LEGACY ITEMS TOTALS 164,700164,700 0.0

32,900 146,400 43,300TOTALS 222,500

19.014.5 64.3% OF LEGACY VALUE

227,600

97.8

2.2

Poor = VFA Priorities 1,2, and 3; Fair – VFA Priority 4; and Code – VFA Priority 5

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 72

Page 73: WATER SURVEY RESEARCH CENTER #2

Text6 L E G A C Y A S S E S S M E N T D A T A : R E Q - 5 1 3 7 3

Date Inspected 10/8/2002

Description The door needs an ADA auto opener and door hardware in accordance with UIUC guidelines (Accessibility / Universal Design Section B)

Requirement Category Accessibility

Requirement Name ADA: Install Auto Opener on Front Door (Legacy)

Condition Fair

Percent Complete 0.0

Recommendation Install auto door opener on front door.A difficulty factor of 20% has been applied to represent typical costs associated with working in older buildings or confined areas, such as higher staging costs, additional demolition, addition physical and equipment resources and may not account for project specific items such as timing requirements, hidden conditions, and the organizing of multiple deficiencies corrections where issues other than costs are the prime considerations.

Estimated Cost 12,496.00 Estimated Remaining Cost: 12,496.00

Text6 L E G A C Y A S S E S S M E N T D A T A : R E Q - 5 1 4 4 7

Date Inspected 10/8/2002

Description The kitchenette in 226 B is not handicap accessible in accordance with UFAS 4.1.4 (5).

Requirement Category Accessibility

Requirement Name ADA: Non-Compliant Kitchenette (Legacy)

Condition Critical

Percent Complete 0.0

Recommendation Modify kitchennette for ADAAG compliance.A difficulty factor of 40% has been applied to this deficiency to account for known historical data on campus mechanical installations and may not account for project specific items such as timing requirements, hidden conditions, and the organizing of multiple deficiencies corrections where issues other than costs are the prime considerations.A difficulty factor of 20% has been applied to represent typical costs associated with working in older buildings or confined areas, such as higher staging costs, additional demolition, addition physical and equipment resources and may not account for project specific items such as timing requirements, hidden conditions, and the organizing of multiple deficiencies corrections where issues other than costs are the prime considerations.

Estimated Cost 5,446.00 Estimated Remaining Cost: 5,446.00

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 73

Page 74: WATER SURVEY RESEARCH CENTER #2

Text6 L E G A C Y A S S E S S M E N T D A T A : R E Q - 5 2 4 0 4

Date Inspected 10/8/2002

Description ADAAG 4.1.3 (11) requires that if toilet facilities are provided then each common use toilet shall be wheelchair handicapped accessible. The common restrooms are not all handicapped accessible per UFAS, ADAAG, and State of Illinois Accessibility requirements. They must be in compliance with ADA Section 4 and 9 - 9.1.1. and Illinois Accessibility Codes. Although work has been done to provide for some handicap accessibility there is some remaining work to be done

Requirement Category Accessibility

Requirement Name ADA: Restrooms ADA Non-Compliant (Legacy)

Condition Critical

Percent Complete 0.0

Recommendation Existing fixtures in these restrooms should be replaced with UFAS, ADAAG compliant fixtures.

A difficulty factor of 40% has been applied to this deficiency to account for known historical data on campus mechanical installations and may not account for project specific items such as timing requirements, hidden conditions, and the organizing of multiple deficiencies corrections where issues other than costs are the prime considerations.A difficulty factor of 20% has been applied to represent typical costs associated with working in older buildings or confined areas, such as higher staging costs, additional demolition, addition physical and equipment resources and may not account for project specific items such as timing requirements, hidden conditions, and the organizing of multiple deficiencies corrections where issues other than costs are the prime considerations.

Estimated Cost 30,855.00 Estimated Remaining Cost: 30,855.00

Text6 L E G A C Y A S S E S S M E N T D A T A : R E Q - 5 2 3 3 7

Date Inspected 10/8/2002

Description Rooms 216 was noted as having floor tiles that may contain asbestos. This flooring should be removed and replaced with UIUC approved floor covering (VCT).

Requirement Category Asbestos

Requirement Name Flooring: Replace VAT (Legacy)

Condition Critical

Percent Complete 0.0

Recommendation Replace flooring as indicated. Approximately $2 / square foot as provided by Operations and MaintenanceA difficulty factor of 20% has been applied to represent typical costs associated with working in older buildings or confined areas, such as higher staging costs, additional demolition, addition physical and equipment resources and may not account for project specific items such as timing requirements, hidden conditions, and the organizing of multiple deficiencies corrections where issues other than costs are the prime considerations.

Estimated Cost 783.00 Estimated Remaining Cost: 783.00

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 74

Page 75: WATER SURVEY RESEARCH CENTER #2

Text6 L E G A C Y A S S E S S M E N T D A T A : R E Q - 5 1 2 9 3

Date Inspected 10/8/2002

Description The wire glass at the front entrance does not conform to BOCA requirements. Wire glazing used as an opening protective must pass the acceptance criteria of NFPA 257 for a fire protective rating of 45 minutes (three-quarter hour) and shall bear the label of the approving agency. No label was noted. Exterior doors are three-quarter hour fire assemblies as they are opening protectives if they have wire glass (See 720.1). BOCA Table 720.1 allows in three-quarter hour assemblies, a maximum area of 1296 square inches with a maximum height of 54 inches and a maximum width of 54 inches. BOCA 1015.6 and Table 717.1 requires vestible doors to be of a one hour fire resistive construction. In addition, the doors need to be identified in accordance with BOCA 2406.1and NFPA 80, Standard for Fire Doors and Fire Windows, sections 1-6 and 2-3.

Requirement Category Building Code

Requirement Name Glazing: Install Compliant Glazing (Legacy)

Condition Critical

Percent Complete 0.0

Recommendation Install complaint glazing as required at north vestible entrances and single south entrance door. A difficulty factor of 20% has been applied to represent typical costs associated with working in older buildings or confined areas, such as higher staging costs, additional demolition, addition physical and equipment resources and may not account for project specific items such as timing requirements, hidden conditions, and the organizing of multiple deficiencies corrections where issues other than costs are the prime considerations.

Estimated Cost 6,178.00 Estimated Remaining Cost: 6,178.00

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 75

Page 76: WATER SURVEY RESEARCH CENTER #2

Text6 L E G A C Y A S S E S S M E N T D A T A : R E Q - 5 1 4 4 8

Date Inspected 10/8/2002

Description There are signs of deteriorated, cracked or damaged sidewalks at the rear and front of the building as well as deteriorated parge coatings at the rear loading dock. The damage needs to be addressed by having the sections routed out, reformed, and/or replacement of all damaged areas with like material.

*UIUC Comments: Percent Complete Information_4458649 – Small Projects - Cops Excess Earnings___100% Complete

Total Complete to Date: 100%

Requirement Category Integrity

Requirement Name Concrete: Repair Sidewalk & Loading Dock (Legacy)

Condition Poor

Percent Complete 100.0

Recommendation Provide routing and filling work as required to exterior sidewalk surfaceand reparge wall at rear loading dockA difficulty factor of 20% has been applied to represent typical costs associated with working in older buildings or confined areas, such as higher staging costs, additional demolition, addition physical and equipment resources and may not account for project specific items such as timing requirements, hidden conditions, and the organizing of multiple deficiencies corrections where issues other than costs are the prime considerations.

Estimated Cost 5,110.00 Estimated Remaining Cost: 0.00

Action Date 10/8/2003

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 76

Page 77: WATER SURVEY RESEARCH CENTER #2

Text6 L E G A C Y A S S E S S M E N T D A T A : R E Q - 5 2 4 0 3

Date Inspected 10/8/2002

Description The exterior walls in areas shows signs of failing mortar joints that need to be routed and filled.

Requirement Category Integrity

Requirement Name Exterior Wall: Re-point Brick (Legacy)

Condition Poor

Percent Complete 0.0

Recommendation Repoint east elevation 800 SFRepoint south elevation 950 SFRepoint west elevation 750 SFA difficulty factor of 20% has been applied to represent typical costs associated with working in older buildings or confined areas, such as higher staging costs, additional demolition, addition physical and equipment resources and may not account for project specific items such as timing requirements, hidden conditions, and the organizing of multiple deficiencies corrections where issues other than costs are the prime considerations.

Estimated Cost 24,192.00 Estimated Remaining Cost: 24,192.00

Action Date 10/8/2003

Text6 L E G A C Y A S S E S S M E N T D A T A : R E Q - 5 2 4 0 5

Date Inspected 10/8/2002

Description The present unit is a single glazed original aluminum window that has reached the end of its expected useful life and should be replaced with a new more energy efficient model.

Requirement Category Integrity

Requirement Name Window: Replace Aluminum Framed Window (Legacy)

Condition Poor

Percent Complete 0.0

Recommendation Remove existing aluminum frame, single glazed window. Install double glazed, insulated window. A difficulty factor of 20% has been applied to represent typical costs associated with working in older buildings or confined areas, such as higher staging costs, additional demolition, addition physical and equipment resources and may not account for project specific items such as timing requirements, hidden conditions, and the organizing of multiple deficiencies corrections where issues other than costs are the prime considerations.

Estimated Cost 6,517.00 Estimated Remaining Cost: 6,517.00

Action Date 10/8/2007

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 77

Page 78: WATER SURVEY RESEARCH CENTER #2

Text6 L E G A C Y A S S E S S M E N T D A T A : R E Q - 5 7 4 1 1

Date Inspected 10/7/2005

Description There exists ductwork, conduit, pipes, and similar building service equipment, without fire protection, penetrating a fire barrier. This occurs in the following areas: Room 206, 226C, 226, and 226B. This is not compliant with NFPA 101 Section 8.2.3.2.4.2

Requirement Category Life Safety

Requirement Name Fire Barrier: Unprotected Penetrations (Legacy)

Condition Poor

Percent Complete 0.0

Recommendation Seal openings with approved through-penetration firestopping system.

Adjustment factor of 1.2 used to account for additional costs typically associated with retrofit work, and/or working with existing construction.

Estimated Cost 2,207.00 Estimated Remaining Cost: 2,207.00

Action Date 10/7/2006

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 78

Page 79: WATER SURVEY RESEARCH CENTER #2

Text6 L E G A C Y A S S E S S M E N T D A T A : R E Q - 5 6 0 3 7

Date Inspected 10/8/2002

Description Upgrade existing voice/data system to Cat 5 or Cat 6 to meet occupant requirements.

Requirement Category Voice/Data System

Requirement Name Data: Upgrade Network Infrastructure (Legacy)

Condition Fair

Percent Complete 0.0

Recommendation (Cont. from Deficiency)The dollar estimates are based on a combination of average costs drawn from completed building upgrade projects, the existence of partial network upgrades, and physical challenges a building may pose.

The estimates DO NOT include costs for constructing Communication Equipment Rooms, additional power, or additional cooling needed for network equipment. CITES has typically never borne these costs and has no tracking history for them.

There may be a several week delay between the completion of a project and the updating of CITES wiring/jack database; thus, the number of jacks most recently added may not be reflected in this list.

Only campus buildings for which CITES has a record of data jacks are included on this list.

Housing buildings and campus-leased buildings are not included on this list.

Estimated Cost 133,855.00 Estimated Remaining Cost: 133,855.00

UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01

WATER SURVEY RESEARCH CENTER #20289 - PAGE 79