Stephen Anthony U.S. Geological Survey Pacific Islands Water Science Center Honolulu, Hawaii
WATER SURVEY RESEARCH CENTER #2
Transcript of WATER SURVEY RESEARCH CENTER #2
POOR ($)(1-5 YEARS)
FAIR ($)(5-10 YEARS)
GOOD ($)(10-20 YEARS)
EXCELLENT ($)(20+ YEARS)
E X P E C T E D R E M A I N I N G S E R V I C E L I F E
TOTAL ($) $/GSF
PERCENT OF BUILDING TOTAL (%)
TRADE
B U I L D I N G D I S C I P L I N E R E P L A C E M E N T C O S T S U M M A R Y
MECHANICAL 239,700 256,100 495,800 9.08 18.8
PLUMBING 23,400 37,300 29,400 162,600 252,600 4.63 9.6
FIRE PROTECTION 115,000 115,000 2.11 4.4
ELECTRICAL 510,900 162,400 628,400 1,301,600 23.85 49.5
COMMUNICATIONS 466,100 466,100 8.54 17.7
889,000 37,300 913,900 791,000 2,631,200 48.2233.8 1.4 34.7 30.1
TOTAL% OF TOTAL
NO CRITICAL ITEMS IDENTIFIED FOR THIS BUILDING
NOTE: Cost Estimates are Construction Costs are in 2013 dollars to Replace in Kind unless otherwise noted.
WATER SURVEY RESEARCH CENTER #2
4/10/2013
2204 SOUTH GRIFFITH DRIVECHAMPAIGN , ILLINOIS 61820
.338
SYSTEMCONDITION
INDEX
0289
$ 2,631,200
BUILDING SYSTEMREPLACEMENT
COST
54,571
BUILDINGGROSS
SQUARE FEET
1
NUMBEROF BUILDING
STORIES
1964
ORIGINALYEAR OF
CONSTRUCTION
BUILDING SURVEY DATEOFFICEPRIMARY BUILDING USE
CCJM: Josh Polasky (M), Stanley Panek (E)BUILDING SURVEY TEAM
NOTE: THIS REPORT INCLUDES BUILDING NUMBERS 1104, 1107, 1108 & 1109
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 1
POOR(1-5 YEARS)
FAIR(5-10 YEARS)
GOOD(10-20 YEARS)
EXCELLENT(20+ YEARS)
E X P E C T E D R E M A I N I N G S E R V I C E L I F E
TOTALSYSTEM/COMPONENT
Text106M E C H A N I C A L D I S C I P L I N E R E P L A C E M E N T C O S T S U M M A R Y
CHILLED WATER SYSTEM
113,200 113,200Cooling System
HEATING HOT WATER SYSTEM
105,900 105,900Heating Hot Water System
SUPPLY AIR SYSTEM
239,700 239,700Air Handling System
LABORATORY EXHAUST SYSTEM
4,500 4,500Air Handling System
HVAC CONTROLS SYSTEM
32,400 32,400HVAC Controls
239,700 256,100 495,800
48.3 51.7% OF TOTAL
MECHANICAL TOTAL
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 2
Text6 C O O L I N G S Y S T E M A S S E S S M E N T D A T A
Comments Buildings 1, 2, and 4-6 total 54.000 sq/ft.
The chilled water pumps have VFDs installed but the system is run at a constant speed. The cooling tower fans are cycled on and off to maintain a condenser water temp of 78F.
Date Installed 1/1/2005
Description The entire Water Survey Research Center Complex is connected to a 429 ton York chiller located in Building #2, which provides all cooling. The chiller is centrifugal and located in room #226B. There are two cooling towers located on the South side of Building #2. The BAS gives the chiller a run enable, controls the two chilled water pumps, the condenser pump, and the two cooling tower fans.
Chiller = 429 ton York MaxE Centrifugal Chiller (Unit Model YK CH CF P5 – CN FS)3 pumps = 60 HP each2 Cooling Towers = Baltimore Aircoil Company (Model #94600421)
Overall Condition Good
Replacement Cost $113,200
Remaining Useful Life 20+ Years Nominal Useful Life: 30 Years
Item ID 301726
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 3
Text6 C O O L I N G S Y S T E M S U R V E Y P H O T O G R A P H S
Chiller Chilled water pumps (60 hp) Cooling towers
Single cooling tower
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 4
Text6 H E A T I N G H O T W A T E R S Y S T E M A S S E S S M E N T D A T A
Comments 54,000 sq/ft is the combined square footage of buildings 1, 2, 4, 5, and 6.
Date Installed 1/1/2005
Description (4) 2,000 MBH Aerco condensing boilers serve preheat, reheat, and perimeter radiation throughout the complex. There are 2 hot water pumps (1 is 100% standby) with a flow capacity of 850 gpm each.
Equipment Tag Boiler #1 - #4
Manufacturer Aerco – Benchmark 2.0
Overall Condition Good
Replacement Cost $105,900
Size/Capacity 2,000 MBH
Remaining Useful Life 20 Years Nominal Useful Life: 30 Years
Item ID 301739
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 5
Text6 H E A T I N G H O T W A T E R S Y S T E M S U R V E Y P H O T O G R A P H S
Row of boilers Boiler front control panel Hot water pumps (40 hp, 850 gmp)
Hot water piping to other buildings
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 6
Text6 A I R H A N D L I N G S Y S T E M A S S E S S M E N T D A T A
Comments Units are all functional and were visited by a retro commissioning team in 2012.buildings.
Date Installed 1/1/1984
Description There are 11 AHUs total between the 5 buildings surveyed, all are constant volume. Buildings 1, 4, 5, and 6 each have 2 AHUs. For these buildings, one of the units is on the roof and serves the center of the building; the other unit is located in the mech. room and serves the perimeter rooms.Building 2 has 3 rooftop units and one unit above the ceiling in room 224. Roof top unit size -3000CFM to 4000 CFM. For estimation purposes, here are the spaces that need service:Building 1 = 10,404 sq/ftBuilding 2 = 10,923 sq/ftBuilding 4, 5, and 6 (almost identical) = 11.040 sq/ft
Overall Condition Poor
Replacement Cost $239,700
Remaining Useful Life Exceeded Nominal Useful Life: 30 Years
Item ID 301725
Text6 A I R H A N D L I N G S Y S T E M S U R V E Y P H O T O G R A P H S
AHU on roof (in background) AHU on roof of building #4
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 7
Text6 A I R H A N D L I N G S Y S T E M A S S E S S M E N T D A T A
Date Installed 1/1/1997
Description Building #4 has 1 hood which failed University inspection. Building #6 has 1 functional hood and 1 hood listed as “restricted” by the University.
Overall Condition Good
Recommendation Remove 2 nonfunctional hoods. Assess whether replacements are necessary given very limited use.
Replacement Cost $4,500
Remaining Useful Life 14 Years Nominal Useful Life: 30 Years
Item ID 301738
Text6 A I R H A N D L I N G S Y S T E M S U R V E Y P H O T O G R A P H S
Nonfunctional fume hood (building #6) Functional fume hood (building #6)
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 8
Text6 H V A C C O N T R O L S A S S E S S M E N T D A T A
Comments The controls are either new (2012) or were maximized by the retro commissioning team, which repaired many existing problems.
Date Installed 1/1/2012
Description Existing pneumatic controls on AHUs were replaced with a Siemens DDC system in 2012. Humidity sensors were installed in the return air on a majority of the AHUs.
The majority of the reheats and perimeter radiation are pneumatically controlled by space thermostats. Building 2 is an exception; it’s controlled digitally through a thermostat and Terminal Equipment Controller (TEC).
The York chillers are monitored by a BAS through Modbus communication. The BAC also controls the Aerco boiler management system and pumps through Modbus communication.
A Quincy/Pneumatech pneumatic compressor system serves pneumatic controls (dual 5-hp motors).
Manufacturer Siemens and others
Overall Condition Good
Recommendation The AHU system is soon due for replacement – update and/or integrate controls at that time.
Replacement Cost $32,400
Remaining Useful Life 17 Years Nominal Useful Life: 18 Years
Item ID 301740
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 9
Text6 H V A C C O N T R O L S S U R V E Y P H O T O G R A P H S
Thermostat Quincy/Pneumatech pneumatic compressor system Pneumatic piping
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 10
POOR(1-5 YEARS)
FAIR(5-10 YEARS)
GOOD(10-20 YEARS)
EXCELLENT(20+ YEARS)
E X P E C T E D R E M A I N I N G S E R V I C E L I F E
TOTALSYSTEM/COMPONENT
Text106P L U M B I N G D I S C I P L I N E R E P L A C E M E N T C O S T S U M M A R Y
DOMESTIC HOT WATER SYSTEM
37,300 37,300Domestic Hot and Cold Water
PLUMBING FIXTURES SYSTEM
29,400 29,400Plumbing Fixtures
SUB-SOIL DRAINAGE SYSTEM
23,400 23,400Storm and Subsoil Drainage
PROCESS WATER SYSTEM
162,600 162,600Lab Processes
23,400 37,300 29,400 162,600 252,600
9.2 14.8 11.6 64.4% OF TOTAL
PLUMBING TOTAL
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 11
Text6 D O M E S T I C H O T A N D C O L D W A T E R A S S E S S M E N T D A T A
Date Installed 1984 and 2005
Description PVI Turbopower gas water heater (installed 2005, 125 gal, 339,000 Btu/h) serves building 1 and 2 and is in excellent condition.
Buildings 4-6 are almost identical and are each served by an electric, 80 gal, residential-type water heater. 2 of these are from the 80s and one is from 2005. 2 additional 80 gal heaters are used for water storage only.
Overall Condition Fair
Recommendation Replace 2 of the 3 electric water heaters in buildings 4-6.
Replacement Cost $37,300
Remaining Useful Life 0 – 20 Years Nominal Useful Life: 50 Years
Item ID 301727
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 12
Text6 D O M E S T I C H O T A N D C O L D W A T E R S U R V E Y P H O T O G R A P H S
Water heater for buildings 1 and 2 Domestic cold water pipes in building #4 Water heaters in building #4 (one is water storage only, poor condition due to age)
Single water heater in building #6 (excellent condition)
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 13
Text6 P L U M B I N G F I X T U R E S A S S E S S M E N T D A T A
Comments Approximately 20-25 toilets, 25 sinks, 6-7 urinals, 5-6 kitchenette sinks, and 5-6 janitor sinks. No problems reported.
Date Installed 1/1/1984
Description Bathroom and kitchenette fixtures are of various ages and in mostly fair condition.
Overall Condition Good
Replacement Cost $29,400
Remaining Useful Life 20 Years Nominal Useful Life: 50 Years
Item ID 301748
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 14
Text6 P L U M B I N G F I X T U R E S S U R V E Y P H O T O G R A P H S
Toilet and sink Standard sinks Kitchenette sink
Fountain
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 15
Text6 S T O R M A N D S U B S O I L D R A I N A G E A S S E S S M E N T D A T A
Comments Failed sump pump has been replaced with temporary one.
Date Installed 1/1/1964
Description Roofs drain internally. There are no basements in any of the assessed buildings. The only sub-grade room is the main mechanical room #226B in Building #2. That room has a pit with a sump pump.
Despite poor rating, this system functions normally with no problems reported.
Overall Condition Poor
Recommendation Replace temporary sump pump with permanent one.
Replacement Cost $23,400
Remaining Useful Life Exceeded Nominal Useful Life: 50 Years
Item ID 301750
Text6 S T O R M A N D S U B S O I L D R A I N A G E S U R V E Y P H O T O G R A P H S
Roof showing drains Sump pump pit
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 16
Text6 L A B P R O C E S S E S A S S E S S M E N T D A T A
Date Installed 1/1/2007
Description Building #6 has lab air, lab vacuum, and deionized water systems, all in good condition.
Lab air compressor = Speedair, 1 HP Lab vacuum = Speedair, ¾ HPDI Water System = M2 Innovative Solutions
Overall Condition Excellent
Replacement Cost $162,600
Remaining Useful Life 24 Years Nominal Useful Life: 30 Years
Item ID 301745
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 17
Text6 L A B P R O C E S S E S S U R V E Y P H O T O G R A P H S
Lab compressor Lab vacuum Deionized water system
Deionized water system different angle
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 18
POOR(1-5 YEARS)
FAIR(5-10 YEARS)
GOOD(10-20 YEARS)
EXCELLENT(20+ YEARS)
E X P E C T E D R E M A I N I N G S E R V I C E L I F E
TOTALSYSTEM/COMPONENT
Text106F I R E P R O T E C T I O N D I S C I P L I N E R E P L A C E M E N T C O S T S U M M A R Y
FIRE ALARM SYSTEM
41,600 41,600Fire Alarm System
64,600 64,600Fire Alarm System – 1107, 1108 and 1109
STANDPIPE SYSTEM
8,800 8,800Standpipe
115,000 115,000
100.0% OF TOTAL
FIRE PROTECTION TOTAL
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 19
Text6 F I R E A L A R M S Y S T E M A S S E S S M E N T D A T A
Date Installed 1989 and 2005
Description Fire alarm system includes pull stations, horns, strobes, smoke detectors and heat detectors. Main panel was replaced in 2005.
Equipment Tag -
HP/kW -
Manufacturer Pyrotronics
Material -
Model Number MXL
Overall Condition Poor
Recommendation Upgrade to new system
Replacement Cost $41,600
Serial Number -
Size/Capacity -
Remaining Useful Life Exceeded Nominal Useful Life: 20 Years
Voltage -
Item ID 301737
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 20
Text6 F I R E A L A R M S Y S T E M S U R V E Y P H O T O G R A P H S
Fire alarm interconnection box Typical pull station Strobe/horn
Fire Alarm Panel
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 21
Text6 F I R E A L A R M S Y S T E M – 1 1 0 7 , 1 1 0 8 A N D 1 1 0 9 A S S E S S M E N T D A T A
Date Installed 1/1/1989
Description Fire alarm system includes pull stations, horns, strobes, smoke detectors and heat detectors. Main panel is located in bldg.#2
Equipment Tag -
HP/kW -
Manufacturer Pyrotronics
Material -
Model Number MXL
Overall Condition Poor
Recommendation Upgrade to new system
Replacement Cost $64,600
Serial Number -
Size/Capacity -
Remaining Useful Life Exceeded Nominal Useful Life: 20 Years
Voltage -
Item ID 301736
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 22
Text6 F I R E A L A R M S Y S T E M – 1 1 0 7 , 1 1 0 8 A N D 1 1 0 9 S U R V E Y P H O T O G R A P H S
Horn/strobe and pull station Smoke detector and strobe Strobe/horn at exit door
Pull station
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 23
Text6 S T A N D P I P E A S S E S S M E N T D A T A
Comments No sprinklers.
Date Installed 1/1/1964
Description Standpipes serve buildings 1, 2, and 4-6 and are original to building (1964).
Overall Condition Poor
Replacement Cost $8,800
Size/Capacity 2” pipe
Remaining Useful Life 0-5 Years Nominal Useful Life: 50 Years
Item ID 301749
Text6 S T A N D P I P E S U R V E Y P H O T O G R A P H S
Typical standpipe cabinet Another standpipe cabinet
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 24
POOR(1-5 YEARS)
FAIR(5-10 YEARS)
GOOD(10-20 YEARS)
EXCELLENT(20+ YEARS)
E X P E C T E D R E M A I N I N G S E R V I C E L I F E
TOTALSYSTEM/COMPONENT
Text106E L E C T R I C A L D I S C I P L I N E R E P L A C E M E N T C O S T S U M M A R Y
LOW VOLTAGE SYSTEM
162,400 162,400Low Voltage Distribution
253,100 253,100Low Voltage Distribution – 1107, 1108 and 1109
SWITCHGEAR
304,600 304,600Switchboard
EMERGENCY POWER SYSTEM
68,200 68,200Emergency Power System
106,300 106,300Emergency Power System – 1107, 1108 and 1109
INTERIOR LIGHTING
126,500 126,500Interior Lighting
197,200 197,200Interior Lighting – 1107, 1108 and 1109
EMERGENCY LIGHTING SYSTEM
15,300 15,300Emergency Lighting System
23,000 23,000Emergency Lighting System – 1107, 1108 and 1109
EXIT LIGHTING SYSTEM
11,800 11,800Exit lighting System
17,600 17,600Exit lighting System – 1107, 1108 and 1109
EXTERIOR LIGHTING SYSTEM
6,200 6,200Exterior Lighting
9,400 9,400Exterior Lighting – 1107, 1108 and 1109
510,900 162,400 628,400 1,301,600
39.3 12.5 48.3% OF TOTAL
ELECTRICAL TOTAL
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 25
Text6 L O W V O L T A G E D I S T R I B U T I O N A S S E S S M E N T D A T A
Date Installed 1964 ,1984 and 2004
Description Buildings were installed in1964. In 2004 new 2000 KVA transformer and 2500 A switchboard was installed to provide service to existing distribution panelboards located within (6) buildings.
Equipment Tag -
HP/kW -
Manufacturer Federal Pacific and Cutler Hammer
Material -
Model Number -
Overall Condition Good
Recommendation .
Replacement Cost $162,400
Serial Number -
Size/Capacity -
Remaining Useful Life 15 Years Nominal Useful Life: 40 Years
Voltage 277/480V and 120/208 V
Item ID 301747
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 26
Text6 L O W V O L T A G E D I S T R I B U T I O N S U R V E Y P H O T O G R A P H S
Typical panelboard in mech room Typical panelboard in office area 2000KVA transformer
Distribution Panelboard
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 27
Text6 L O W V O L T A G E D I S T R I B U T I O N – 1 1 0 7 , 1 1 0 8 A N D 1 1 0 9 A S S E S S M E N T D A T A
Date Installed 1/1/1964
Description Each building receives 480 V power from switchboard located in building #2. Local transformers provide 120/208 V for lighting and receptacles.
Equipment Tag -
HP/kW -
Manufacturer Federal Pacific
Material -
Model Number -
Overall Condition Poor
Recommendation .
Replacement Cost $253,100
Serial Number -
Size/Capacity -
Remaining Useful Life Exceeded Nominal Useful Life: 40 Years
Voltage 277/480V and 120/208 V
Item ID 301746
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 28
Text6 L O W V O L T A G E D I S T R I B U T I O N – 1 1 0 7 , 1 1 0 8 A N D 1 1 0 9 S U R V E Y P H O T O G R A P H S
Typical panelboard –bldg #4 Emergency panelboard –bldg #4 112.5 KVA transformer
Panelboard-bldg #5
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 29
Text6 S W I T C H B O A R D A S S E S S M E N T D A T A
Date Installed 1/1/2005
Description 2500 A main switch (located in separate enclosure) and switchboard with (12) feeder breakers serving (6) buildings. 2500 A main switch is located in separate enclosure.
Equipment Tag MDSB
HP/kW -
Manufacturer Cutler -Hammer
Material Copper bus
Model Number SDC47675
Overall Condition Excellent
Recommendation -
Replacement Cost $304,600
Serial Number -
Size/Capacity 2500 A
Remaining Useful Life 35 Years Nominal Useful Life: 40 Years
Voltage 277/480 V
Item ID 301751
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 30
Text6 S W I T C H B O A R D S U R V E Y P H O T O G R A P H S
Switchboard Switchboard data Distribution section
Main Switch
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 31
Text6 E M E R G E N C Y P O W E R S Y S T E M A S S E S S M E N T D A T A
Comments Existing system is not recognized as emergency power.
Critical Issues Installation of emergency lighting and exit signs with battery back up
Date Installed 1/1/1984
Description 100 A breaker located at main switchboard is designated as “emergency power” and provide protection for emergency panelboard EMD. From EMD located in building #2 power is distributed to five buildings.
Equipment Tag -
HP/kW -
Manufacturer -
Material -
Model Number -
Overall Condition Poor
Replacement Cost $68,200
Serial Number -
Size/Capacity -
Remaining Useful Life Exceeded Nominal Useful Life: 25 Years
Voltage 120 V
Item ID 301731
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 32
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 33
Text6 E M E R G E N C Y P O W E R S Y S T E M – 1 1 0 7 , 1 1 0 8 A N D 1 1 0 9 A S S E S S M E N T D A T A
Comments Existing system is not recognized as emergency power.
Critical Issues Installation of emergency lighting and exit signs with battery back up
Date Installed 1/1/1984
Description 100 A breaker located at main switchboard is designated as “emergency power” and provide protection for emergency panelboard EMD. From EMD located in building #2 power is distributed to five buildings.
Equipment Tag -
HP/kW -
Manufacturer -
Material -
Model Number -
Overall Condition Poor
Replacement Cost $106,300
Serial Number -
Size/Capacity -
Remaining Useful Life Exceeded Nominal Useful Life: 25 Years
Voltage 120 V
Item ID 301730
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 34
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 35
Text6 I N T E R I O R L I G H T I N G A S S E S S M E N T D A T A
Date Installed 3/28/2011
Description Offices, corridors and labs have been illuminated with two lamp type fluorescent fixtures. Lamps and ballasts were replaced in 2011.Fixtures were installed in 1985
Equipment Tag -
HP/kW -
Manufacturer -
Material -
Model Number -
Overall Condition Excellent
Recommendation -
Replacement Cost $126,500
Serial Number -
Size/Capacity -
Remaining Useful Life 23 Years Nominal Useful Life: 25 Years
Voltage 277 V
Item ID 301744
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 36
Text6 I N T E R I O R L I G H T I N G S U R V E Y P H O T O G R A P H S
Lab lighting Conference room lighting Office lighting
Storage lighting
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 37
Text6 I N T E R I O R L I G H T I N G – 1 1 0 7 , 1 1 0 8 A N D 1 1 0 9 A S S E S S M E N T D A T A
Date Installed 3/28/2011
Description Offices, corridors and labs have been illuminated with two lamp type fluorescent fixtures. Lamps and ballasts were replaced in 2011.Fixtures were installed in 1985
Equipment Tag -
HP/kW -
Manufacturer -
Material -
Model Number -
Overall Condition Excellent
Recommendation -
Replacement Cost $197,200
Serial Number -
Size/Capacity -
Remaining Useful Life 23 Years Nominal Useful Life: 25 Years
Voltage 120 V and 277V
Item ID 301743
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 38
Text6 I N T E R I O R L I G H T I N G – 1 1 0 7 , 1 1 0 8 A N D 1 1 0 9 S U R V E Y P H O T O G R A P H S
Office lighting-bldg #4 Office lighting-bldg #5 Office lighting-bldg #6
Corridor lighting
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 39
Text6 E M E R G E N C Y L I G H T I N G S Y S T E M A S S E S S M E N T D A T A
Critical Issues Installation of emergency lighting with battery back up
Date Installed 1/1/1984
Description Emergency circuits originated from emergency panelboard provide power to selected light fixtures located in corridors.
Equipment Tag -
HP/kW -
Manufacturer -
Material -
Model Number -
Overall Condition Poor
Recommendation -
Replacement Cost $15,300
Serial Number -
Size/Capacity -
Remaining Useful Life Exceeded Nominal Useful Life: 25 Years
Voltage 120 V
Item ID 301729
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 40
Text6 E M E R G E N C Y L I G H T I N G S Y S T E M S U R V E Y P H O T O G R A P H S
Corridor lighting includes emergency fixtures Emergency light in corridor
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 41
Text6 E M E R G E N C Y L I G H T I N G S Y S T E M – 1 1 0 7 , 1 1 0 8 A N D 1 1 0 9 A S S E S S M E N T D A T A
Critical Issues Installation of emergency lighting with battery back up
Date Installed 1/1/1984
Description Emergency circuits originated from emergency panelboard provide power to selected light fixtures located in corridors.
Equipment Tag -
HP/kW -
Manufacturer -
Material -
Model Number -
Overall Condition Poor
Recommendation -
Replacement Cost $23,000
Serial Number -
Size/Capacity -
Remaining Useful Life Exceeded Nominal Useful Life: 25 Years
Voltage 120 V
Item ID 301728
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 42
Text6 E M E R G E N C Y L I G H T I N G S Y S T E M – 1 1 0 7 , 1 1 0 8 A N D 1 1 0 9 S U R V E Y P H O T O G R A P H S
Corridor lighting- includes emergency fixtures Emergency light in corridor
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 43
Text6 E X I T L I G H T I N G S Y S T E M A S S E S S M E N T D A T A
Date Installed 1/1/1964
Description Box type exit sign with (2) incandescent lamps
Equipment Tag -
HP/kW -
Manufacturer -
Material -
Model Number -
Overall Condition Poor
Recommendation Replacement with LED type battery back up signs
Replacement Cost $11,800
Serial Number -
Size/Capacity -
Remaining Useful Life Exceeded Nominal Useful Life: 25 Years
Voltage 120 V
Item ID 301733
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 44
Text6 E X I T L I G H T I N G S Y S T E M S U R V E Y P H O T O G R A P H S
Typical exit sign-pic 1 Typical exit sign-pic2 Typical exit sign -pic3
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 45
Text6 E X I T L I G H T I N G S Y S T E M – 1 1 0 7 , 1 1 0 8 A N D 1 1 0 9 A S S E S S M E N T D A T A
Date Installed 1/1/1964
Description Box type exit sign with (2) incandescent lamps
Equipment Tag -
HP/kW -
Manufacturer -
Material -
Model Number -
Overall Condition Poor
Recommendation Replacement with LED type battery back up signs
Replacement Cost $17,600
Serial Number -
Size/Capacity -
Remaining Useful Life Exceeded Nominal Useful Life: 25 Years
Voltage 120 V
Item ID 301732
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 46
Text6 E X I T L I G H T I N G S Y S T E M – 1 1 0 7 , 1 1 0 8 A N D 1 1 0 9 S U R V E Y P H O T O G R A P H S
Typical exit sign-pic 1 Typical exit sign-pic2 Typical exit sign –pic3
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 47
Text6 E X T E R I O R L I G H T I N G A S S E S S M E N T D A T A
Date Installed 1/1/1984
Description Wall pack or recessed canopy lighting
Equipment Tag -
HP/kW -
Manufacturer -
Material -
Model Number -
Overall Condition Poor
Recommendation Replace with high efficiency fixtures at the end of remaining fixture life.
Replacement Cost $6,200
Serial Number -
Size/Capacity -
Remaining Useful Life Exceeded Nominal Useful Life: 25 Years
Voltage 277 V
Item ID 301735
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 48
Text6 E X T E R I O R L I G H T I N G S U R V E Y P H O T O G R A P H S
Main entry-no exterior lighting Fixture at west side Canopy Light fixture
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 49
Text6 E X T E R I O R L I G H T I N G – 1 1 0 7 , 1 1 0 8 A N D 1 1 0 9 A S S E S S M E N T D A T A
Date Installed 1/1/1984
Description Wall pack or recessed canopy lighting
Equipment Tag -
HP/kW -
Manufacturer -
Material -
Model Number -
Overall Condition Poor
Recommendation Replace with high efficiency fixtures at the end of remaining fixture life add site walkway lights
Replacement Cost $9,400
Serial Number -
Size/Capacity -
Remaining Useful Life Exceeded Nominal Useful Life: 25 Years
Voltage 277 V
Item ID 301734
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 50
Text6 E X T E R I O R L I G H T I N G – 1 1 0 7 , 1 1 0 8 A N D 1 1 0 9 S U R V E Y P H O T O G R A P H S
Overhang lighting Site lighting Overhang lighting close up
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 51
POOR(1-5 YEARS)
FAIR(5-10 YEARS)
GOOD(10-20 YEARS)
EXCELLENT(20+ YEARS)
E X P E C T E D R E M A I N I N G S E R V I C E L I F E
TOTALSYSTEM/COMPONENT
Text106C O M M U N I C A T I O N S D I S C I P L I N E R E P L A C E M E N T C O S T S U M M A R Y
DATA SYSTEM
37,800 37,800Communication Infrastructure System - 1104
40,600 40,600Communication Infrastructure System - 1107
40,100 40,100Communication Infrastructure System - 1108
40,200 40,200Communication Infrastructure System - 1109
39,700 39,700Communication Infrastructure System - 289
77,600 77,600Voice/Data System
120,900 120,900Voice/Data System – 1107, 1108 and 1109
SECURITY ACCESS CONTROL SYSTEM
27,700 27,700Access Control
41,500 41,500Access Control – 1107, 1108 and 1109
466,100 466,100
100.0% OF TOTAL
COMMUNICATIONS TOTAL
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 52
Text6 C O M M U N I C A T I O N I N F R A S T R U C T U R E S Y S T E M - 1 1 0 4 A S S E S S M E N T D A T A
Date Installed UIUC network upgrade complete (date range 2006 to 2012)
Description Water Survey Research Centers (WSRC) 1, 2, 4, 5 and 6 are all fed from one IDF located in WSRC 2 (building 289). The IDF is fed with 36 strands of single mode fiber and 1000 copper pairs with each pair grounded and individually protected by a fuse/surge arrestor. The IDF is located in room 206 on the first floor. Fiber distributes radially from the building IDF to hub rooms (telecommunication rooms) to within 100 meters of end-use equipment and lands at rack mounted fiber switch(es) within the hub room.
In WSRC 1 (building 1104) there is one hub room located in room 151 to feed the entire building (Hub A). The hub room is equipped with one free standing rack and wire management. Cables appear to be routed loose above the ceiling. The hub room has a technology ground bar tied into the building grounding system. The hub room has a dedicated electrical panel. The hub room also has a dedicated Liebert Data Mate split system AC unit and remote condensing unit.
Outlet standards typically have 1"C stubbed to cable management. Standard outlet consists of two network cables and two data jacks. Station cable consists of Cat 6. The building is typically equipped with WIFI throughout (coverage not noted)
Overall Condition Good
Replacement Cost $37,800
Remaining Useful Life 20 Years Nominal Useful Life: 20 Years
Item ID 301830
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 53
Text6 C O M M U N I C A T I O N I N F R A S T R U C T U R E S Y S T E M - 1 1 0 4 S U R V E Y P H O T O G R A P H S
WSRC 1, Building 1104 Hub Room Rack WSRC 1, Building 1104 Hub Room AC unit WSRC 1, Building 1104 Hub Room
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 54
Text6 C O M M U N I C A T I O N I N F R A S T R U C T U R E S Y S T E M - 1 1 0 7 A S S E S S M E N T D A T A
Date Installed UIUC network upgrade complete (date range 2006 to 2012)
Description Water Survey Research Centers (WSRC) 1, 2, 4, 5 and 6 are all fed from one IDF located in WSRC 2 (building 289). The IDF is fed with 36 strands of single mode fiber and 1000 copper pairs with each pair grounded and individually protected by a fuse/surge arrestor. Fiber distributes radially from the building IDF to hub rooms (telecommunication rooms) to within 100 meters of end-use equipment and lands at rack mounted fiber switch(es) within the hub room.
In WSRC 4 (building 1107) there is one hub room located within a fenced area in computer room 405 to feed the entire building (Hub F). The room has raised floor and a dedicated chilled water computer room cooling unit (Pomona Air). The hub room is equipped with one free standing rack and wire management. The hub room has a technology ground bar tied into the building grounding system. The hub room has smoke detector protection.
Outlet standards typically have 1"C stubbed to cable management. Standard outlet consists of two network cables and two data jacks. Station cable consists of Cat 6 (Mohawk Advancenet). The building is typically equipped with WIFI throughout (coverage not noted)
Overall Condition Good
Replacement Cost $40,600
Remaining Useful Life 20 Years Nominal Useful Life: 20 Years
Item ID 301831
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 55
Text6 C O M M U N I C A T I O N I N F R A S T R U C T U R E S Y S T E M - 1 1 0 7 S U R V E Y P H O T O G R A P H S
Rack Mounted Patch Panel Data Rack Receptacles and Ground Bar Computer Room Cooling Unit
WSRC 4, Building 1107 Hub Room
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 56
Text6 C O M M U N I C A T I O N I N F R A S T R U C T U R E S Y S T E M - 1 1 0 8 A S S E S S M E N T D A T A
Date Installed UIUC network upgrade complete (date range 2006 to 2012)
Description Water Survey Research Centers (WSRC) 1, 2, 4, 5 and 6 are all fed from one IDF located in WSRC 2 (building 289). The IDF is fed with 36 strands of single mode fiber and 1000 copper pairs with each pair grounded and individually protected by a fuse/surge arrestor. Fiber distributes radially from the building IDF to hub rooms (telecommunication rooms) to within 100 meters of end-use equipment and lands at rack mounted fiber switch(es) within the hub room.
In WSRC 5 (building 1108) there is one hub room located within a fenced area in computer room 505 to feed the entire building (Hub G). The room has a ceiling mounted computer room cooling unit. The hub room is equipped with one free standing rack and wire management. The hub room has a dedicated electrical panel and a technology ground bar tied into the building grounding system. The hub room has smoke detector protection.
Outlet standards typically have 1"C stubbed to cable management. Standard outlet consists of two network cables and two data jacks. Station cable consists of Cat 6 (Mohawk Advancenet). The building is typically equipped with WIFI throughout (coverage not noted)
Overall Condition Good
Replacement Cost $40,100
Remaining Useful Life 20 Years Nominal Useful Life: 20 Years
Item ID 301832
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 57
Text6 C O M M U N I C A T I O N I N F R A S T R U C T U R E S Y S T E M - 1 1 0 8 S U R V E Y P H O T O G R A P H S
Data Rack Receptacles Computer Room Ceiling Mounted AC Unit WSRC 5, Building 1108 Hub Room
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 58
Text6 C O M M U N I C A T I O N I N F R A S T R U C T U R E S Y S T E M - 1 1 0 9 A S S E S S M E N T D A T A
Date Installed UIUC network upgrade complete (date range 2006 to 2012)
Description Water Survey Research Centers (WSRC) 1, 2, 4, 5 and 6 are all fed from one IDF located in WSRC 2 (building 289). The IDF is fed with 36 strands of single mode fiber and 1000 copper pairs with each pair grounded and individually protected by a fuse/surge arrestor. Fiber distributes radially from the building IDF to hub rooms (telecommunication rooms) to within 100 meters of end-use equipment and lands at rack mounted fiber switch(es) within the hub room.
In WSRC 6 (building 1109) there is one hub room located within a fenced area in room 622A to feed the entire building (Hub C). The hub room is equipped with one free standing rack and wire management. The hub room has a technology ground bar tied into the building grounding system. The hub room has smoke detector protection. The hub room does not have dedicated cooling systems-conditioned/exhausted by the base building system.
Outlet standards typically have 1"C stubbed to cable management. Standard outlet consists of two network cables and two data jacks. Station cable consists of Cat 6. The building is typically equipped with WIFI throughout (coverage not noted)
Overall Condition Good
Replacement Cost $40,200
Remaining Useful Life 20 Years Nominal Useful Life: 20 Years
Item ID 301833
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 59
Text6 C O M M U N I C A T I O N I N F R A S T R U C T U R E S Y S T E M - 1 1 0 9 S U R V E Y P H O T O G R A P H S
WSRC 6, Building 1109 Hub Room
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 60
Text6 C O M M U N I C A T I O N I N F R A S T R U C T U R E S Y S T E M - 2 8 9 A S S E S S M E N T D A T A
Date Installed UIUC network upgrade complete (date range 2006 to 2012)
Description Water Survey Research Centers (WSRC) 1, 2, 4, 5 and 6 are all fed from one IDF located in WSRC 2 (building 289). The IDF is fed with 36 strands of single mode fiber and 1000 copper pairs with each pair grounded and individually protected by a fuse/surge arrestor. The IDF is located in room 206 on the first floor. Fiber distributes radially from the building IDF to hub rooms (telecommunication rooms) to within 100 meters of end-use equipment and lands at rack mounted fiber switch(es) within the hub room.
In WSRC 2 (building 289) there is one hub room located within a fenced area in room 208B to feed the entire building (Hub D). The hub room is equipped with one free standing rack and wire management. The hub room has a technology ground bar tied into the building grounding system. The hub room has smoke detector protection. The hub room does not have dedicated cooling systems-conditioned/exhausted by the base building system.
Outlet standards typically have 1"C stubbed to cable management. Standard outlet consists of two network cables and two data jacks. Station cable consists of Cat 6. The building is typically equipped with WIFI throughout (coverage not noted)
Overall Condition Good
Replacement Cost $39,700
Remaining Useful Life 20 Years Nominal Useful Life: 20 Years
Item ID 301834
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 61
Text6 C O M M U N I C A T I O N I N F R A S T R U C T U R E S Y S T E M - 2 8 9 S U R V E Y P H O T O G R A P H S
Water Survey Research Buildings IDF WSRC 2, Building 289 Hub Room WSRC 2, Building 289 Data Rack Receptacles and Ground
Water Survey Research Buildings IDF
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 62
Text6 V O I C E / D A T A S Y S T E M A S S E S S M E N T D A T A
Comments MDF room was not accessible.
Date Installed 1/1/2002
Description Voice/data outlets are installed at offices and labs.
Equipment Tag -
HP/kW -
Manufacturer -
Material -
Model Number -
Overall Condition Good
Recommendation -
Replacement Cost $77,600
Serial Number -
Size/Capacity -
Remaining Useful Life 10 Years Nominal Useful Life: 20 Years
Voltage -
Item ID 301742
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 63
Text6 V O I C E / D A T A S Y S T E M S U R V E Y P H O T O G R A P H S
Fiber service for voice and data Typical data outlet Wi Fi antenna
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 64
Text6 V O I C E / D A T A S Y S T E M – 1 1 0 7 , 1 1 0 8 A N D 1 1 0 9 A S S E S S M E N T D A T A
Comments MDF room was not accessible.
Date Installed 1/1/2002
Description Voice/data outlets are installed at offices and labs.
Equipment Tag -
HP/kW -
Manufacturer -
Material -
Model Number -
Overall Condition Good
Recommendation -
Replacement Cost $120,900
Serial Number -
Size/Capacity -
Remaining Useful Life 10 Years Nominal Useful Life: 20 Years
Voltage -
Item ID 301741
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 65
Text6 V O I C E / D A T A S Y S T E M – 1 1 0 7 , 1 1 0 8 A N D 1 1 0 9 S U R V E Y P H O T O G R A P H S
Typical data outlet Typical data outlet Wi Fi antenna
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 66
Text6 A C C E S S C O N T R O L A S S E S S M E N T D A T A
Date Installed 1/1/2004
Description Card access system. Utilizes Andover program to activate employee ID card to allow entry. Computer with Andover program is located in Room #116
Equipment Tag -
HP/kW -
Manufacturer Best
Material -
Model Number -
Overall Condition Good
Recommendation -
Replacement Cost $27,700
Serial Number --
Size/Capacity -
Remaining Useful Life 10 Years Nominal Useful Life: 20 Years
Voltage -
Item ID 301724
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 67
Text6 A C C E S S C O N T R O L S U R V E Y P H O T O G R A P H S
Card reader
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 68
Text6 A C C E S S C O N T R O L – 1 1 0 7 , 1 1 0 8 A N D 1 1 0 9 A S S E S S M E N T D A T A
Date Installed 1/1/2004
Description Card access system. Utilizes Andover program to activate employee ID card to allow entry. Computer with Andover program is located in building #2 Room#116
Equipment Tag -
HP/kW -
Manufacturer Best
Material -
Model Number -
Overall Condition Good
Recommendation -
Replacement Cost $41,500
Serial Number --
Size/Capacity -
Remaining Useful Life 10 Years Nominal Useful Life: 20 Years
Voltage -
Item ID 301723
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 69
Text6 A C C E S S C O N T R O L – 1 1 0 7 , 1 1 0 8 A N D 1 1 0 9 S U R V E Y P H O T O G R A P H S
Card reader-bldg #4 Card reader-bldg #5
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 70
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 71
Item ID
W A T E R S U R V E Y R E S E A R C H C E N T E R # 2 L E G A C Y A S S E S S M E N T S U M M A R Y
CODEPOOR FAIRIDENTIFIED ISSUEREQUIREMENT
NUMBERINSPECTION
DATE TOTALLEGACYVALUE
PERCENTCOMPLETE
GENERAL LEGACY ITEMS ITEMS
12,500REQ-51373 ADA: Install Auto Opener on Front Door10/8/2002 12,50012,500 0.0305641
5,400REQ-51447 ADA: Non-Compliant Kitchenette10/8/2002 5,4005,400 0.0305649
800REQ-52337 Flooring: Replace VAT10/8/2002 800800 0.0305646
6,200REQ-51293 Glazing: Install Compliant Glazing10/8/2002 6,2006,200 0.0305645
REQ-51448 Concrete: Repair Sidewalk & Loading Dock10/8/2002 5,100 100.0305650
24,200REQ-52403 Exterior Wall: Re-point Brick10/8/2002 24,20024,200 0.0305642
6,500REQ-52405 Window: Replace Aluminum Framed Window10/8/2002 6,5006,500 0.0305643
2,200REQ-57411 Fire Barrier: Unprotected Penetrations10/7/2005 2,2002,200 0.0305644
32,900 12,500 12,400GENERAL LEGACY ITEMS TOTALS 57,80062,900 8.1
MEP LEGACY ITEMS ITEMS
30,900REQ-52404 ADA: Restrooms ADA Non-Compliant10/8/2002 30,90030,900 0.0305647
133,900REQ-56037 Data: Upgrade Network Infrastructure10/8/2002 133,900133,900 0.0305648
133,900 30,900MEP LEGACY ITEMS TOTALS 164,700164,700 0.0
32,900 146,400 43,300TOTALS 222,500
19.014.5 64.3% OF LEGACY VALUE
227,600
97.8
2.2
Poor = VFA Priorities 1,2, and 3; Fair – VFA Priority 4; and Code – VFA Priority 5
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 72
Text6 L E G A C Y A S S E S S M E N T D A T A : R E Q - 5 1 3 7 3
Date Inspected 10/8/2002
Description The door needs an ADA auto opener and door hardware in accordance with UIUC guidelines (Accessibility / Universal Design Section B)
Requirement Category Accessibility
Requirement Name ADA: Install Auto Opener on Front Door (Legacy)
Condition Fair
Percent Complete 0.0
Recommendation Install auto door opener on front door.A difficulty factor of 20% has been applied to represent typical costs associated with working in older buildings or confined areas, such as higher staging costs, additional demolition, addition physical and equipment resources and may not account for project specific items such as timing requirements, hidden conditions, and the organizing of multiple deficiencies corrections where issues other than costs are the prime considerations.
Estimated Cost 12,496.00 Estimated Remaining Cost: 12,496.00
Text6 L E G A C Y A S S E S S M E N T D A T A : R E Q - 5 1 4 4 7
Date Inspected 10/8/2002
Description The kitchenette in 226 B is not handicap accessible in accordance with UFAS 4.1.4 (5).
Requirement Category Accessibility
Requirement Name ADA: Non-Compliant Kitchenette (Legacy)
Condition Critical
Percent Complete 0.0
Recommendation Modify kitchennette for ADAAG compliance.A difficulty factor of 40% has been applied to this deficiency to account for known historical data on campus mechanical installations and may not account for project specific items such as timing requirements, hidden conditions, and the organizing of multiple deficiencies corrections where issues other than costs are the prime considerations.A difficulty factor of 20% has been applied to represent typical costs associated with working in older buildings or confined areas, such as higher staging costs, additional demolition, addition physical and equipment resources and may not account for project specific items such as timing requirements, hidden conditions, and the organizing of multiple deficiencies corrections where issues other than costs are the prime considerations.
Estimated Cost 5,446.00 Estimated Remaining Cost: 5,446.00
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 73
Text6 L E G A C Y A S S E S S M E N T D A T A : R E Q - 5 2 4 0 4
Date Inspected 10/8/2002
Description ADAAG 4.1.3 (11) requires that if toilet facilities are provided then each common use toilet shall be wheelchair handicapped accessible. The common restrooms are not all handicapped accessible per UFAS, ADAAG, and State of Illinois Accessibility requirements. They must be in compliance with ADA Section 4 and 9 - 9.1.1. and Illinois Accessibility Codes. Although work has been done to provide for some handicap accessibility there is some remaining work to be done
Requirement Category Accessibility
Requirement Name ADA: Restrooms ADA Non-Compliant (Legacy)
Condition Critical
Percent Complete 0.0
Recommendation Existing fixtures in these restrooms should be replaced with UFAS, ADAAG compliant fixtures.
A difficulty factor of 40% has been applied to this deficiency to account for known historical data on campus mechanical installations and may not account for project specific items such as timing requirements, hidden conditions, and the organizing of multiple deficiencies corrections where issues other than costs are the prime considerations.A difficulty factor of 20% has been applied to represent typical costs associated with working in older buildings or confined areas, such as higher staging costs, additional demolition, addition physical and equipment resources and may not account for project specific items such as timing requirements, hidden conditions, and the organizing of multiple deficiencies corrections where issues other than costs are the prime considerations.
Estimated Cost 30,855.00 Estimated Remaining Cost: 30,855.00
Text6 L E G A C Y A S S E S S M E N T D A T A : R E Q - 5 2 3 3 7
Date Inspected 10/8/2002
Description Rooms 216 was noted as having floor tiles that may contain asbestos. This flooring should be removed and replaced with UIUC approved floor covering (VCT).
Requirement Category Asbestos
Requirement Name Flooring: Replace VAT (Legacy)
Condition Critical
Percent Complete 0.0
Recommendation Replace flooring as indicated. Approximately $2 / square foot as provided by Operations and MaintenanceA difficulty factor of 20% has been applied to represent typical costs associated with working in older buildings or confined areas, such as higher staging costs, additional demolition, addition physical and equipment resources and may not account for project specific items such as timing requirements, hidden conditions, and the organizing of multiple deficiencies corrections where issues other than costs are the prime considerations.
Estimated Cost 783.00 Estimated Remaining Cost: 783.00
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 74
Text6 L E G A C Y A S S E S S M E N T D A T A : R E Q - 5 1 2 9 3
Date Inspected 10/8/2002
Description The wire glass at the front entrance does not conform to BOCA requirements. Wire glazing used as an opening protective must pass the acceptance criteria of NFPA 257 for a fire protective rating of 45 minutes (three-quarter hour) and shall bear the label of the approving agency. No label was noted. Exterior doors are three-quarter hour fire assemblies as they are opening protectives if they have wire glass (See 720.1). BOCA Table 720.1 allows in three-quarter hour assemblies, a maximum area of 1296 square inches with a maximum height of 54 inches and a maximum width of 54 inches. BOCA 1015.6 and Table 717.1 requires vestible doors to be of a one hour fire resistive construction. In addition, the doors need to be identified in accordance with BOCA 2406.1and NFPA 80, Standard for Fire Doors and Fire Windows, sections 1-6 and 2-3.
Requirement Category Building Code
Requirement Name Glazing: Install Compliant Glazing (Legacy)
Condition Critical
Percent Complete 0.0
Recommendation Install complaint glazing as required at north vestible entrances and single south entrance door. A difficulty factor of 20% has been applied to represent typical costs associated with working in older buildings or confined areas, such as higher staging costs, additional demolition, addition physical and equipment resources and may not account for project specific items such as timing requirements, hidden conditions, and the organizing of multiple deficiencies corrections where issues other than costs are the prime considerations.
Estimated Cost 6,178.00 Estimated Remaining Cost: 6,178.00
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 75
Text6 L E G A C Y A S S E S S M E N T D A T A : R E Q - 5 1 4 4 8
Date Inspected 10/8/2002
Description There are signs of deteriorated, cracked or damaged sidewalks at the rear and front of the building as well as deteriorated parge coatings at the rear loading dock. The damage needs to be addressed by having the sections routed out, reformed, and/or replacement of all damaged areas with like material.
*UIUC Comments: Percent Complete Information_4458649 – Small Projects - Cops Excess Earnings___100% Complete
Total Complete to Date: 100%
Requirement Category Integrity
Requirement Name Concrete: Repair Sidewalk & Loading Dock (Legacy)
Condition Poor
Percent Complete 100.0
Recommendation Provide routing and filling work as required to exterior sidewalk surfaceand reparge wall at rear loading dockA difficulty factor of 20% has been applied to represent typical costs associated with working in older buildings or confined areas, such as higher staging costs, additional demolition, addition physical and equipment resources and may not account for project specific items such as timing requirements, hidden conditions, and the organizing of multiple deficiencies corrections where issues other than costs are the prime considerations.
Estimated Cost 5,110.00 Estimated Remaining Cost: 0.00
Action Date 10/8/2003
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 76
Text6 L E G A C Y A S S E S S M E N T D A T A : R E Q - 5 2 4 0 3
Date Inspected 10/8/2002
Description The exterior walls in areas shows signs of failing mortar joints that need to be routed and filled.
Requirement Category Integrity
Requirement Name Exterior Wall: Re-point Brick (Legacy)
Condition Poor
Percent Complete 0.0
Recommendation Repoint east elevation 800 SFRepoint south elevation 950 SFRepoint west elevation 750 SFA difficulty factor of 20% has been applied to represent typical costs associated with working in older buildings or confined areas, such as higher staging costs, additional demolition, addition physical and equipment resources and may not account for project specific items such as timing requirements, hidden conditions, and the organizing of multiple deficiencies corrections where issues other than costs are the prime considerations.
Estimated Cost 24,192.00 Estimated Remaining Cost: 24,192.00
Action Date 10/8/2003
Text6 L E G A C Y A S S E S S M E N T D A T A : R E Q - 5 2 4 0 5
Date Inspected 10/8/2002
Description The present unit is a single glazed original aluminum window that has reached the end of its expected useful life and should be replaced with a new more energy efficient model.
Requirement Category Integrity
Requirement Name Window: Replace Aluminum Framed Window (Legacy)
Condition Poor
Percent Complete 0.0
Recommendation Remove existing aluminum frame, single glazed window. Install double glazed, insulated window. A difficulty factor of 20% has been applied to represent typical costs associated with working in older buildings or confined areas, such as higher staging costs, additional demolition, addition physical and equipment resources and may not account for project specific items such as timing requirements, hidden conditions, and the organizing of multiple deficiencies corrections where issues other than costs are the prime considerations.
Estimated Cost 6,517.00 Estimated Remaining Cost: 6,517.00
Action Date 10/8/2007
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 77
Text6 L E G A C Y A S S E S S M E N T D A T A : R E Q - 5 7 4 1 1
Date Inspected 10/7/2005
Description There exists ductwork, conduit, pipes, and similar building service equipment, without fire protection, penetrating a fire barrier. This occurs in the following areas: Room 206, 226C, 226, and 226B. This is not compliant with NFPA 101 Section 8.2.3.2.4.2
Requirement Category Life Safety
Requirement Name Fire Barrier: Unprotected Penetrations (Legacy)
Condition Poor
Percent Complete 0.0
Recommendation Seal openings with approved through-penetration firestopping system.
Adjustment factor of 1.2 used to account for additional costs typically associated with retrofit work, and/or working with existing construction.
Estimated Cost 2,207.00 Estimated Remaining Cost: 2,207.00
Action Date 10/7/2006
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 78
Text6 L E G A C Y A S S E S S M E N T D A T A : R E Q - 5 6 0 3 7
Date Inspected 10/8/2002
Description Upgrade existing voice/data system to Cat 5 or Cat 6 to meet occupant requirements.
Requirement Category Voice/Data System
Requirement Name Data: Upgrade Network Infrastructure (Legacy)
Condition Fair
Percent Complete 0.0
Recommendation (Cont. from Deficiency)The dollar estimates are based on a combination of average costs drawn from completed building upgrade projects, the existence of partial network upgrades, and physical challenges a building may pose.
The estimates DO NOT include costs for constructing Communication Equipment Rooms, additional power, or additional cooling needed for network equipment. CITES has typically never borne these costs and has no tracking history for them.
There may be a several week delay between the completion of a project and the updating of CITES wiring/jack database; thus, the number of jacks most recently added may not be reflected in this list.
Only campus buildings for which CITES has a record of data jacks are included on this list.
Housing buildings and campus-leased buildings are not included on this list.
Estimated Cost 133,855.00 Estimated Remaining Cost: 133,855.00
UIUC/UIS MEP CONDITION ASSESSMENTUIUC PROJECT NUMBER U12151CANNON DESIGN PROJECT NUMBER 4009.01
WATER SURVEY RESEARCH CENTER #20289 - PAGE 79