Water Street Hydrologic and Hydraulic (H&H) Analysis (Drainage Study) City of Platteville Common Council Presented by: Caroline Burger, P.E. Theran Jacobson, E.I.T. AECOM Madison, WI

description

Existing Conditions

Transcript of Water Street Hydrologic and Hydraulic (H&H) Analysis (Drainage Study) Water Street Hydrologic and...

Page 1: Water Street Hydrologic and Hydraulic (H&H) Analysis (Drainage Study) Water Street Hydrologic and Hydraulic (H&H) Analysis (Drainage Study) City of Platteville.

Water Street Hydrologic and Hydraulic (H&H) Analysis

(Drainage Study)

City of PlattevilleCommon Council

Presented by:Caroline Burger, P.E.

Theran Jacobson, E.I.T.AECOM

Madison, WI

Page 2: Water Street Hydrologic and Hydraulic (H&H) Analysis (Drainage Study) Water Street Hydrologic and Hydraulic (H&H) Analysis (Drainage Study) City of Platteville.

Outline Existing Conditions Fire Station Impacts Alternatives Cost Estimates Conclusions Recommendations

Page 3: Water Street Hydrologic and Hydraulic (H&H) Analysis (Drainage Study) Water Street Hydrologic and Hydraulic (H&H) Analysis (Drainage Study) City of Platteville.

Existing Conditions

Page 4: Water Street Hydrologic and Hydraulic (H&H) Analysis (Drainage Study) Water Street Hydrologic and Hydraulic (H&H) Analysis (Drainage Study) City of Platteville.

Fire Station Location #1 and #2 were modeled separately

Purpose was to determine the individual impact from each

Modeling indicates neither location will “adversely impact” the Water Street Basin

“Adversely impact” means increasing water surface elevations

Fire Station Impacts

Location #1

Location #2

Page 5: Water Street Hydrologic and Hydraulic (H&H) Analysis (Drainage Study) Water Street Hydrologic and Hydraulic (H&H) Analysis (Drainage Study) City of Platteville.

1. Regrade Open Channel

2. Replace Open Channel with Box Culvert

3. Construct Stormwater Pond

4. Combination of 1 - 3

Alternatives

Page 6: Water Street Hydrologic and Hydraulic (H&H) Analysis (Drainage Study) Water Street Hydrologic and Hydraulic (H&H) Analysis (Drainage Study) City of Platteville.

Regrade open channel

Reconstruct junction Results in no adverse

impacts

Location #1

Alternatives - Scenario 1

Page 7: Water Street Hydrologic and Hydraulic (H&H) Analysis (Drainage Study) Water Street Hydrologic and Hydraulic (H&H) Analysis (Drainage Study) City of Platteville.

Replace open channel with box culvert

Reconstruct junction Results in no adverse

impacts

Location #1

Alternatives - Scenario 2

Page 8: Water Street Hydrologic and Hydraulic (H&H) Analysis (Drainage Study) Water Street Hydrologic and Hydraulic (H&H) Analysis (Drainage Study) City of Platteville.

Alternatives – Scenario 3

Location #2

Replace open channel with box culvert

Results in adverse impacts

Page 9: Water Street Hydrologic and Hydraulic (H&H) Analysis (Drainage Study) Water Street Hydrologic and Hydraulic (H&H) Analysis (Drainage Study) City of Platteville.

Alternatives – Scenario 4

Location #1

Location #2

Construct stormwater pond by high school

Results in no adverse impacts

Page 10: Water Street Hydrologic and Hydraulic (H&H) Analysis (Drainage Study) Water Street Hydrologic and Hydraulic (H&H) Analysis (Drainage Study) City of Platteville.

Alternatives – Scenarios 5-7

Location #1

Location #2

Scenario 5: Combination of Open Channel at Location 1 and pond

Scenario 6: Combination of Box Culvert at Location 1 and pond

Scenario 7: Combination of Box Culvert at Location 2 and pond

All result in no adverse impacts

Page 11: Water Street Hydrologic and Hydraulic (H&H) Analysis (Drainage Study) Water Street Hydrologic and Hydraulic (H&H) Analysis (Drainage Study) City of Platteville.

Cost Estimates

Location #1

Location #2

Scenario Capital Cost ($)

1 $174,000

2 $311,000

3 $300,000

4 $203,000

5 $377,000

6 $514,000

7 $503,000

Page 12: Water Street Hydrologic and Hydraulic (H&H) Analysis (Drainage Study) Water Street Hydrologic and Hydraulic (H&H) Analysis (Drainage Study) City of Platteville.

A Fire Station at either location will not adversely impact the basin

Improvements to Location 1 will not adversely impact the basin

Improvements to Location 2 will adversely impact the basin

If Location 2 is chosen, the stormwater pond must also be constructed

The stormwater pond will reduce water surface elevations in the basin

Conclusions

Location #1

Location #2

Page 13: Water Street Hydrologic and Hydraulic (H&H) Analysis (Drainage Study) Water Street Hydrologic and Hydraulic (H&H) Analysis (Drainage Study) City of Platteville.

Proceed with the selection of the Fire Station location

The junction box downstream of location 1 and the sanitary main adjacent to location 1 should be addressed

Conveyance improvements will likely require permitting – meet with WDNR staff early during design

Recommendations

Location #1

Location #2

Page 14: Water Street Hydrologic and Hydraulic (H&H) Analysis (Drainage Study) Water Street Hydrologic and Hydraulic (H&H) Analysis (Drainage Study) City of Platteville.

Questions?