Water steam Circuit in Supercritical Boiler for 660MW Power Plant
-
Upload
hareesh-vs -
Category
Technology
-
view
11.508 -
download
14
description
Transcript of Water steam Circuit in Supercritical Boiler for 660MW Power Plant
WATER-STEAM CIRCUIT inSUPER CRITICAL BOILER
Prepared By: Hareesh VSJr.ManagerIOTEP BARH
BOILER PARAMETERS
Main Boiler TypeOnce Through, Single Reheat, Coal Fired, Balanced draft, Side Fired, Tower type & Symmetrical to Both Axis
Boiler AreaFurnace :- 14.9 X 23.04 MSecond Pass :- 6.07 X 23.04 M X 2( Both side of Furnace)Roof :- 44.35 X 23.04 M
Design FuelGuarantee Bituminous CoalLCV :- 3026 kcal/kgHCV :- 3300 kcal/kg
Material of Construction 12X1MФ and 15X1MФ
Main Steam Flow 2225 T/Hr
Main Steam Pressure 256 Kg/cm2
Main Steam Temp 540 OC
RH Steam Flow 1746 T/Hr
RH Steam Pressure 46.13 Kg/cm2
RH Steam Temp 568 OC
Feed Water Temp 290 OC
Economizer
Suspension Tube
Tubes to furnace ww first run
Furnace ww 1st Run
Furnace ww 2st Run
Attemperator 1st
Furnace ww 3rd run
Horizontal gas duct ww
Hanger tube 1
Roof ww
Hanger tube 2
Convection ww
Steam to steam heat exchanger
Separator
Platen super heater Stage 1,2,3 & 4
Boiler Feed pump
Final Super heater
Economizer
Suspension Tube
Tubes to furnace ww first run
Boiler Feed pump
HP Turbine IP & LP Turbine
Reheat system
Economizer Lower Block
Economizer Upper Block
Suspension Tubes
Collecting Header3320C, 299kg/cm2
Steam to steam heat exchanger Hot suspension
Tubes to furnace ww first run
Intermediate Header
Distribution Header of Furnace WW First run
Inlet Header of Furnace WW First run
Boiler Feed Pump
FRH & HP Heaters2900C, 304kg/cm2
Line From Deaerator
Line From BFP
Economizer
Suspension Tube
Tubes to furnace ww first run
Furnace ww 1st Run
Furnace ww 2st Run
Attemperator 1st
Furnace ww 3rd run
Horizontal gas duct ww
Hanger tube 1
Roof ww
Hanger tube 2
Convection ww
Steam to steam heat exchanger
Separator
Platen super heater Stage 1,2,3 & 4
Recirculation pump
Final Super heater
Economizer
Suspension Tube
Tubes to furnace ww first run
Furnace ww 1st Run
Recirculation pump
HP Turbine IP & LP Turbine
Reheat system
Collecting Header Furnace WW first run
Furnace Side Hot suspension Lower Part
Furnace Front & Rear Hot suspension Lower part
Tubes to Furnace Side Hot suspension Lower part
Furnace WW First RunFurnace Front & Rear Water Wall
Lower panels And Extreme End
panels of Side water Wall Lower
part
Furnace WW first run panels
Furnace Hot suspension Lower Part collecting Header (3770C, 301kg/cm2)
First Run WW Outlet Headers (Intermediate Headers)
Economizer
Suspension Tube
Tubes to furnace ww first run
Furnace ww 1st Run
Furnace ww 2st Run
Attemperator 1st
Furnace ww 3rd run
Horizontal gas duct ww
Hanger tube 1
Roof ww
Hanger tube 2
Convection ww
Steam to steam heat exchanger
Separator
Platen super heater Stage 1,2,3 & 4
Recirculation pump
Final Super heater
Economizer
Suspension Tube
Tubes to furnace ww first run
Furnace ww 1st Run
Recirculation pump
HP Turbine IP & LP Turbine
Reheat system
Side View of Boiler
Collecting Header Furnace WW first run
Furnace Front & Rear Hot suspension Lower Part
Furnace Side Hot suspension Lower part
Furnace Hot suspension Lower Part collecting Header
Inlet Header of Furnace Second Run
Extreme Panels of Side WW
Economizer
Suspension Tube
Tubes to furnace ww first run
Furnace ww 1st Run
Furnace ww 2st Run
Attemperator 1st
Furnace ww 3rd run
Horizontal gas duct ww
Hanger tube 1
Roof ww
Hanger tube 2
Convection ww
Steam to steam heat exchanger
Separator
Platen super heater Stage 1,2,3 & 4
Recirculation pump
Final Super heater
Economizer
Suspension Tube
Tubes to furnace ww first run
Furnace ww 1st Run
Furnace ww 2st Run
Attemperator 1st
Recirculation pump
HP Turbine IP & LP Turbine
Reheat system
Furnace WW second run panels
Outlet Headers of Furnace Second run WW panels
(4010C, 296kg/cm2)
Mixing Headers of Furnace Second run WW panels
Tubes to Furnace Hot suspension Middle part
Furnace Hot Suspension Middle Part
Collecting Headers of Middle Part of Hot Suspension
HP Spraying Attemperator-1
Distribution Header to Furnace 3rd Run
Furnace WW Second RunFurnace Side Water walls Lower Part
Side View of Boiler
Economizer
Suspension Tube
Tubes to furnace ww first run
Furnace ww 1st Run
Furnace ww 2st Run
Attemperator 1st
Furnace ww 3rd run
Horizontal gas duct ww
Hanger tube 1
Roof ww
Hanger tube 2
Convection ww
Steam to steam heat exchanger
Separator
Platen super heater Stage 1,2,3 & 4
Recirculation pump
Final Super heater
Economizer
Suspension Tube
Tubes to furnace ww first run
Furnace ww 1st Run
Furnace ww 2st Run
Attemperator 1st
Furnace ww 3rd run
Recirculation pump
HP Turbine IP & LP Turbine
Reheat system
Inlet Headers Furnace WW 3rd run panels
Furnace WW 3rd run panels
Outlet Headers of Furnace WW 3rd run panels at Horizontal Gas duct Bottom Area (Arch Area)
(4330C, 291kg/cm2)
Tubes to Intermediate Headers of 3rd Run WW
Distribution Header to Furnace 3rd Run
Tubes to Inlet Headers of 3rd Run WW
Side View of Boiler
Furnace WW Third RunAll Upper Panels of Furnace Front,
Rear & Side Water walls
`
Economizer
Suspension Tube
Tubes to furnace ww first run
Furnace ww 1st Run
Furnace ww 2st Run
Attemperator 1st
Furnace ww 3rd run
Horizontal gas duct ww
Hanger tube 1
Roof ww
Hanger tube 2
Convection ww
Steam to steam heat exchanger
Separator
Platen super heater Stage 1,2,3 & 4
Recirculation pump
Final Super heater
Economizer
Suspension Tube
Tubes to furnace ww first run
Furnace ww 1st Run
Furnace ww 2st Run
Attemperator 1st
Furnace ww 3rd run
Horizontal gas duct ww
Hanger tube 1
Recirculation pump
HP Turbine IP & LP Turbine
Reheat system
Tubes to Inlet Headers of 3rd Run WWInlet Headers Furnace WW 3rd
run panels
Furnace WW 3rd run panels
Intermediate Headers of 3rd Run WW
Inlet Headers of Horizontal Gas Duct WW
Horizontal Gas Duct WW
Collecting Header ofFurnace 3rd Run
Inlet Header of Hanger Tube 1
Hanger Tube 1(4410C, 288kg/cm2)
Outlet headers of 3rd run panels(4430C, 291kg/cm2)
`
Economizer
Suspension Tube
Tubes to furnace ww first run
Furnace ww 1st Run
Furnace ww 2st Run
Attemperator 1st
Furnace ww 3rd run
Horizontal gas duct ww
Hanger tube 1
Roof ww
Hanger tube 2
Convection ww
Steam to steam heat exchanger
Separator
Platen super heater Stage 1,2,3 & 4
Recirculation pump
Final Super heater
Economizer
Suspension Tube
Tubes to furnace ww first run
Furnace ww 1st Run
Furnace ww 2st Run
Attemperator 1st
Furnace ww 3rd run
Horizontal gas duct ww
Hanger tube 1
Roof ww
Hanger tube 2
Recirculation pump
HP Turbine IP & LP Turbine
Reheat system
Inlet Header of Hanger tube 2
Roof WW Inlet Header
Roof Water Wall
Roof Water Wall CollectingHeader (4480C, 284kg/cm2)
Distribution Header of Hanger Tube 2
Hanger Tube 2
``̀` `̀ `
Economizer
Suspension Tube
Tubes to furnace ww first run
Furnace ww 1st Run
Furnace ww 2st Run
Attemperator 1st
Furnace ww 3rd run
Horizontal gas duct ww
Hanger tube 1
Roof ww
Hanger tube 2
Convection ww
Steam to steam heat exchanger
Separator
Platen super heater Stage 1,2,3 & 4
Recirculation pump
Final Super heater
Economizer
Suspension Tube
Tubes to furnace ww first run
Furnace ww 1st Run
Furnace ww 2st Run
Attemperator 1st
Furnace ww 3rd run
Horizontal gas duct ww
Hanger tube 1
Roof ww
Hanger tube 2
Convection ww
Recirculation pump
HP Turbine IP & LP Turbine
Reheat system
Distribution Header Of Upper Hot suspension Convection Shaft & Furnace Area
Tubes to FurnaceHot Suspension
Tubes to Convection Hot Suspension
Convection ShaftHot Suspension
Tubes to Hot Suspension Collecting Header
Distribution Header of Convection Shaft WW
Convection ShaftWater Walls
Hanger Tube-3
Collecting Header Of Hanger Tube-2(4520C, 281kg/cm2)
``̀` `̀ `
Economizer
Suspension Tube
Tubes to furnace ww first run
Furnace ww 1st Run
Furnace ww 2st Run
Attemperator 1st
Furnace ww 3rd run
Horizontal gas duct ww
Hanger tube 1
Roof ww
Hanger tube 2
Convection ww
Steam to steam heat exchanger
Separator
Platen super heater Stage 1,2,3 & 4
Recirculation pump
Final Super heater
Economizer
Suspension Tube
Tubes to furnace ww first run
Furnace ww 1st Run
Furnace ww 2st Run
Attemperator 1st
Furnace ww 3rd run
Horizontal gas duct ww
Hanger tube 1
Roof ww
Hanger tube 2
Convection ww
Steam to steam heat exchanger
Separator
Recirculation pump
HP Turbine IP & LP Turbine
Reheat system
Collecting Header of Convection Shaft WWs & Hanger Tube – 3(4650C, 278kg/cm2)
Steam To Steam HeatExchanger
High Pressure Tubes toCollecting Header of SSHE(4570C, 274kg/cm2)
High Pressure SprayAttemperator – 2(4390C, 273kg/cm2)
Separator
Drain Header
Wet Steam
Moisture Content in Steam After Separation
Tubes to Steam To Steam HeatExchanger
`
``̀` `̀
Economizer
Suspension Tube
Tubes to furnace ww first run
Furnace ww 1st Run
Furnace ww 2st Run
Attemperator 1st
Furnace ww 3rd run
Horizontal gas duct ww
Hanger tube 1
Roof ww
Hanger tube 2
Convection ww
Steam to steam heat exchanger
Separator
Platen super heater Stage 1,2,3 & 4
Recirculation pump
Final Super heater
Economizer
Suspension Tube
Tubes to furnace ww first run
Furnace ww 1st Run
Furnace ww 2st Run
Attemperator 1st
Furnace ww 3rd run
Horizontal gas duct ww
Hanger tube 1
Roof ww
Hanger tube 2
Convection ww
Steam to steam heat exchanger
Separator
Platen super heater Stage 1,2,3 & 4
Recirculation pump
Final Super heater
HP Turbine IP & LP Turbine
Reheat system
Tubes to Platen SuperHeater (4390C, 273kg/cm2)
Rear
Front
Righ
t
Left
I/L
O/L
O/L
Steam Flow in 4 Stages of Platen Super Heater
I/L
Platen Super Heaters Stage 1, 2, 3 & 4.
Tubes to Final Super Heater(5000C, 258kg/cm2)
Convection Super Heater(Final Super Heater)
Main Steam Out Let Header(5400C, 256kg/cm2)
Spray Type Attemperator -3(5110C, 259kg/cm2)
`
``̀` `̀
Economizer
Suspension Tube
Tubes to furnace ww first run
Furnace ww 1st Run
Furnace ww 2st Run
Attemperator 1st
Furnace ww 3rd run
Horizontal gas duct ww
Hanger tube 1
Roof ww
Hanger tube 2
Convection ww
Steam to steam heat exchanger
Separator
Platen super heater Stage 1,2,3 & 4
Recirculation pump
Final Super heater
Economizer
Suspension Tube
Tubes to furnace ww first run
Furnace ww 1st Run
Furnace ww 2st Run
Attemperator 1st
Furnace ww 3rd run
Horizontal gas duct ww
Hanger tube 1
Roof ww
Hanger tube 2
Convection ww
Steam to steam heat exchanger
Separator
Platen super heater Stage 1,2,3 & 4
Recirculation pump
Final Super heater
HP Turbine IP & LP Turbine
LPR Stage - II
LPR Stage - I
HP Turbine
LPR Stage - I
LPR Stage - II
IP & LP Turbine
Cool
ed R
e H
eat L
ine
(297
0 C, 4
8kg/
cm2 )
Hot
Re
Hea
t Lin
e (5
680 C
, 46k
g/cm
2 )
HP Turbine LP TurbineIP Turbine Generator
CouplingGenerator
Mai
n St
eam
Lin
e to
TG
(540
0 C, 2
56kg
/cm
2 )
Steam to Steam Heat Exchanger
Suspension Tubes of LPR
LPR Middle
LPR Upper
Collecting Header of LPR(4840C, 47kg/cm2)
LP Spray Atemperator
LPR Stage – 2(Final)
LPR Lower
HRH
Lin
e
CRH Line from HP Turbine
Condenser
Deaerator
Water Line To Boiler Feed Pump
Cooling Water
Hot Water to Cooling Tower
Make Up Water Line From DM Plant
Tube to Low Pressure Reheater(4490C, 28kg/cm2)