Water Services National Training Group

27
Water Services National Training Group 12th Annual Conference 11 th September, 2008

description

Water Services National Training Group. 12th Annual Conference 11 th September, 2008. Water Services National Training Group. Delivery. New Conditions of Engagement and Forms of Contract from a Consultant's Perspective. Michael Hand Managing Director WYG Engineering Ireland Ltd. - PowerPoint PPT Presentation

Transcript of Water Services National Training Group

Page 1: Water Services National Training Group

Water Services National Training Group

12th Annual Conference

11th September, 2008

Page 2: Water Services National Training Group

Water Services National Training Group

Delivery

Page 3: Water Services National Training Group

Michael Hand

Managing Director

WYG Engineering Ireland Ltd

New Conditions of Engagement and Forms of Contract

from a Consultant's Perspective

Page 4: Water Services National Training Group

Content

Introduction

New Conditions of Engagement

New Conditions of Contract

Conclusions

Page 5: Water Services National Training Group

Introduction

Page 6: Water Services National Training Group

Project Execution - Aims

Time Cost

Performance

Project

Time

Cost

Quality/Performance

Page 7: Water Services National Training Group

Strategic Choices

ManagementAll-in

Conventional

CompetitiveTwo – StageNegotiatedContinuity

Lump SumAdmeasurement

Cost Reimbursable Target

Organisational Method

Tender ProcedureType of Contract

Page 8: Water Services National Training Group

Historical Development of New Conditions

2004/05 Development of New Conditions of Contract & Conditions of Engagement

2005/06 Consultation with the Industry

2007 Public & Private Sector Training

2008 Effective Launch of New Conditions

2010 Review and Modifications ?

Page 9: Water Services National Training Group

Change Process Model

Page 10: Water Services National Training Group

New Conditions of Engagement

Page 11: Water Services National Training Group

Consultancy in ContextTypically 7-10 year project relationship

Design critical to project cost efficiency

Consultants’ fees represent 4-6% of Project Capital Cost

Consultants’ fees represent 1-2% of Project Whole Life Costs

Service or Commodity ?

Page 12: Water Services National Training Group

Guide Quality/Price Ratios

Feasibility Report and Investigations

Innovative and Imaginative Design ProjectsMajor Conservation & Restoration Projects

Most Construction Projects

Repeat & Straightforward Projects

Straightforward Repairs & Maintenance

RatioQuality/Price

80%

80%

70%

40%

20%

20%

20%

30%

60%

80%

Page 13: Water Services National Training Group

Risks of Price-Biased Selection

THE COMMON LAW OF BUSINESS PROHIBITS PAYING A LITTLE AND GETTING A LOT – John Ruskin (1860)

Drop in Quality of Service

Less Time for Innovation

Less Time for Value Engineering

More Errors and Consequential Costs

More Claims for Extras and Disputes

Conflict/Adversarial Relationships

Loss of Quality Personnel from the Industry

Page 14: Water Services National Training Group

Value EngineeringProject 1 – RC Basement

Initial Design 130t Rebar

Revised Design 80t Rebar

Works Cost Saving €60k

Audit Fee €5k

Project 2 – 3 storey RC Building

Initial Design 150t Rebar

Revised Design 110t Rebar

Works Cost Saving €150k

Job Fee €250k

Page 15: Water Services National Training Group

Fee CorrectionWhere approved construction contract tender price >10% higher or lower than pre-tender estimate

Design Stage Fee reduced by % variation in excess of + 10%

Sliding Scale 10% for projects up to €50m 1% for projects above €600m

Applies only to Consultant at fault

Client discretion to waive fee correction

Page 16: Water Services National Training Group

Procurement - Lianakis

Prequalification – Qualitative Selection Criteria

Tender – Award Criteria

Can Assess Quality of Team Once Only

Award Sub-criteria to be Brought to Tenderers’ Attention

Transparency and Equal Treatment

Page 17: Water Services National Training Group

Some Suggestions on ConsultantsBrief at EOI Stage

“Eurovision” Scoring on Quality

Reality Check on Prices and Eliminate Outliers

Health & Safety is a Key Ingredient

Select on Value for Money – Not Price

Timely Appointments and Approvals

Page 18: Water Services National Training Group

New Conditions of Contract

Page 19: Water Services National Training Group

Historical Contracts – Employer Issues

Overspends & VFM

Health & Safety

Public Relations

Services Disruption

Landowner Issues

Prompt Reinstatement

Page 20: Water Services National Training Group

Historical Contracts - Contractual Claims

Unforeseeable Conditions

Legislative Enactments

Delay & Disruption

Method of Measurement

Method Statement

Extensions of Time

Page 21: Water Services National Training Group

DoF Public Works Contract Objectives

Short listing of tenderers

Tender price = Final cost

Transparent risk allocation

Non adversarial / partnering

Value engineering incentivised

Speedy appointments

New Inflation Index

Page 22: Water Services National Training Group

New Conditions of Contract Experience

Early Days

Launch Coincided with Market Decline

Burden of Notices

Value Engineering

Partnering

SI Inadequacies / Errors

Award Delays

Page 23: Water Services National Training Group

Ground Condition RisksAll Risk may be transferred to Contractor

Comprehensive Site Investigation

Factual Report Only

Tender Period SI Facilitated

Archaeology Fully Investigated

Utility Services Identified

Page 24: Water Services National Training Group

Measurements IssuesBOQ Accuracy – Contractors Risk

Compensation Events

Delay Events

Claims - Notice within 20 days- Valuation within 20 additional days- Monthly updates for continuing effect

Delay costs - Cost per day Quote

Provisional Sums Out

Prime Cost Sums Out

Price Variation (New Index) after 36Mts

Page 25: Water Services National Training Group

Conclusions

Page 26: Water Services National Training Group

Conclusions

Engineers Adaptable & Flexible

Industry Cooperation Essential for Efficiency

Vital to Attract and Retain the Best

Competition on Price Wrong for Design – Not VFM

Still Time to Stave off Lawyer-ridden Industry

Enlightened Review Essential

Page 27: Water Services National Training Group