Water Management in Angra 2 NPP
Brazil
José Victor Jardim Sampaio [email protected]
Nuclear Energy in Brazil
1
![Page 2: Water Management in Angra 2 NPP Brazil · PDF fileNuclear Energy in Brazil 1 . BRAZIL Supplied by an electrical system of continental dimensions. ... return to FW tank (2 Kg/s) or](https://reader031.fdocuments.in/reader031/viewer/2022030506/5ab550d27f8b9adc638ce000/html5/thumbnails/2.jpg)
BRAZIL Supplied by an electrical system of continental
dimensions
Manaus
Brasília
São Paulo Itaipu
Porto Alegre
Fortaleza
Salvador
Rio de Janeiro
Belo Horizonte
Recife
Angra
4.0
00
km
→ Generation sources concentrated (most part hydraulic) far from consumers centers → High degree of interconnection with big interregional energy exchanges 2
![Page 3: Water Management in Angra 2 NPP Brazil · PDF fileNuclear Energy in Brazil 1 . BRAZIL Supplied by an electrical system of continental dimensions. ... return to FW tank (2 Kg/s) or](https://reader031.fdocuments.in/reader031/viewer/2022030506/5ab550d27f8b9adc638ce000/html5/thumbnails/3.jpg)
ANGRA DOS REIS / PARATY
3
![Page 4: Water Management in Angra 2 NPP Brazil · PDF fileNuclear Energy in Brazil 1 . BRAZIL Supplied by an electrical system of continental dimensions. ... return to FW tank (2 Kg/s) or](https://reader031.fdocuments.in/reader031/viewer/2022030506/5ab550d27f8b9adc638ce000/html5/thumbnails/4.jpg)
Central Nuclear Almirante Álvaro Alberto
Nuclear Energy in Brazil
4
![Page 5: Water Management in Angra 2 NPP Brazil · PDF fileNuclear Energy in Brazil 1 . BRAZIL Supplied by an electrical system of continental dimensions. ... return to FW tank (2 Kg/s) or](https://reader031.fdocuments.in/reader031/viewer/2022030506/5ab550d27f8b9adc638ce000/html5/thumbnails/5.jpg)
Nuclear Energy in Brazil
5
Before and after...
![Page 6: Water Management in Angra 2 NPP Brazil · PDF fileNuclear Energy in Brazil 1 . BRAZIL Supplied by an electrical system of continental dimensions. ... return to FW tank (2 Kg/s) or](https://reader031.fdocuments.in/reader031/viewer/2022030506/5ab550d27f8b9adc638ce000/html5/thumbnails/6.jpg)
Nuclear Energy in Brazil
6
Present and future...
![Page 7: Water Management in Angra 2 NPP Brazil · PDF fileNuclear Energy in Brazil 1 . BRAZIL Supplied by an electrical system of continental dimensions. ... return to FW tank (2 Kg/s) or](https://reader031.fdocuments.in/reader031/viewer/2022030506/5ab550d27f8b9adc638ce000/html5/thumbnails/7.jpg)
Hydrographic Basin Nuclear Energy in Brazil
7
![Page 8: Water Management in Angra 2 NPP Brazil · PDF fileNuclear Energy in Brazil 1 . BRAZIL Supplied by an electrical system of continental dimensions. ... return to FW tank (2 Kg/s) or](https://reader031.fdocuments.in/reader031/viewer/2022030506/5ab550d27f8b9adc638ce000/html5/thumbnails/8.jpg)
Water Concession Agreement Nuclear Energy in Brazil
8
River Water Concession Annual Cost (2015)
Frade 100 m³/h
USD 18,600 Sacher 48 m³/h
![Page 9: Water Management in Angra 2 NPP Brazil · PDF fileNuclear Energy in Brazil 1 . BRAZIL Supplied by an electrical system of continental dimensions. ... return to FW tank (2 Kg/s) or](https://reader031.fdocuments.in/reader031/viewer/2022030506/5ab550d27f8b9adc638ce000/html5/thumbnails/9.jpg)
Nuclear Energy in Brazil
9
Qmáx = 120 m³/h Conductivity : ~70µS;cm pH : 6-7 Cl2 < 1,0 ppm Turbidity: 0.5 NTU
![Page 10: Water Management in Angra 2 NPP Brazil · PDF fileNuclear Energy in Brazil 1 . BRAZIL Supplied by an electrical system of continental dimensions. ... return to FW tank (2 Kg/s) or](https://reader031.fdocuments.in/reader031/viewer/2022030506/5ab550d27f8b9adc638ce000/html5/thumbnails/10.jpg)
Demineralized Water System Nuclear Energy in Brazil
10
![Page 11: Water Management in Angra 2 NPP Brazil · PDF fileNuclear Energy in Brazil 1 . BRAZIL Supplied by an electrical system of continental dimensions. ... return to FW tank (2 Kg/s) or](https://reader031.fdocuments.in/reader031/viewer/2022030506/5ab550d27f8b9adc638ce000/html5/thumbnails/11.jpg)
Improvement Planned in the Demineralized Water System Nuclear Energy in Brazil
11
- Reduction of 9000 m³/year - Reduced from 45 to 5 min to start production
![Page 12: Water Management in Angra 2 NPP Brazil · PDF fileNuclear Energy in Brazil 1 . BRAZIL Supplied by an electrical system of continental dimensions. ... return to FW tank (2 Kg/s) or](https://reader031.fdocuments.in/reader031/viewer/2022030506/5ab550d27f8b9adc638ce000/html5/thumbnails/12.jpg)
Consumption of Demineralized Water Nuclear Energy in Brazil
12
![Page 13: Water Management in Angra 2 NPP Brazil · PDF fileNuclear Energy in Brazil 1 . BRAZIL Supplied by an electrical system of continental dimensions. ... return to FW tank (2 Kg/s) or](https://reader031.fdocuments.in/reader031/viewer/2022030506/5ab550d27f8b9adc638ce000/html5/thumbnails/13.jpg)
Blowdown Treatment System Nuclear Energy in Brazil
13
![Page 14: Water Management in Angra 2 NPP Brazil · PDF fileNuclear Energy in Brazil 1 . BRAZIL Supplied by an electrical system of continental dimensions. ... return to FW tank (2 Kg/s) or](https://reader031.fdocuments.in/reader031/viewer/2022030506/5ab550d27f8b9adc638ce000/html5/thumbnails/14.jpg)
Blowdown Treatment System Nuclear Energy in Brazil
14
Blowdown Flow= 0,5 % of Feedwater (10 Kg/s) or (158.2 gpm)
20 % evaporate and return to FW tank
(2 Kg/s) or (31.7 gpm)
80 % demineralized (8 Kg/s) or (126.8
gpm)
![Page 15: Water Management in Angra 2 NPP Brazil · PDF fileNuclear Energy in Brazil 1 . BRAZIL Supplied by an electrical system of continental dimensions. ... return to FW tank (2 Kg/s) or](https://reader031.fdocuments.in/reader031/viewer/2022030506/5ab550d27f8b9adc638ce000/html5/thumbnails/15.jpg)
Reuse of Drains During Outages Nuclear Energy in Brazil
15
![Page 16: Water Management in Angra 2 NPP Brazil · PDF fileNuclear Energy in Brazil 1 . BRAZIL Supplied by an electrical system of continental dimensions. ... return to FW tank (2 Kg/s) or](https://reader031.fdocuments.in/reader031/viewer/2022030506/5ab550d27f8b9adc638ce000/html5/thumbnails/16.jpg)
Leakage Identification Nuclear Energy in Brazil
16
![Page 17: Water Management in Angra 2 NPP Brazil · PDF fileNuclear Energy in Brazil 1 . BRAZIL Supplied by an electrical system of continental dimensions. ... return to FW tank (2 Kg/s) or](https://reader031.fdocuments.in/reader031/viewer/2022030506/5ab550d27f8b9adc638ce000/html5/thumbnails/17.jpg)
Primary Water Management During Outages Nuclear Energy in Brazil
17
![Page 18: Water Management in Angra 2 NPP Brazil · PDF fileNuclear Energy in Brazil 1 . BRAZIL Supplied by an electrical system of continental dimensions. ... return to FW tank (2 Kg/s) or](https://reader031.fdocuments.in/reader031/viewer/2022030506/5ab550d27f8b9adc638ce000/html5/thumbnails/18.jpg)
Primary and Auxiliary Systens Effluent Releases Nuclear Energy in Brazil
18
OUTAGE
![Page 19: Water Management in Angra 2 NPP Brazil · PDF fileNuclear Energy in Brazil 1 . BRAZIL Supplied by an electrical system of continental dimensions. ... return to FW tank (2 Kg/s) or](https://reader031.fdocuments.in/reader031/viewer/2022030506/5ab550d27f8b9adc638ce000/html5/thumbnails/19.jpg)
Secondary and Auxiliary Systens Effluent Releases Nuclear Energy in Brazil
19
OUTAGE