Water InfrastructureSeptember 2015
EXECUTIVE SUMMARY FOR TREASURY APPROVAL: I AND FOR PUBLIC PARTICIPATION
![Page 2: Water Infrastructure - polokwane.gov.za · water (currently estimated ... –No extensions are being made to the existing reticulation networks, ... bids for PPP tender Project fails](https://reader031.fdocuments.in/reader031/viewer/2022020413/5b5ddd0b7f8b9aa3048be933/html5/thumbnails/2.jpg)
Study Area and Project Objectives
• Study Area
– The study area includes Seshego B, Seshego C, Annadale and the Central Business District (CBD) of Polokwane City
• Project Objective
– The primary objective of the project is the reduction of un-accounted for water (currently estimated at 43%) in the three areas to acceptable levels
Replacement and upgrading of water pipes in the Seshego, Annadale and Polokwane CBD area
![Page 3: Water Infrastructure - polokwane.gov.za · water (currently estimated ... –No extensions are being made to the existing reticulation networks, ... bids for PPP tender Project fails](https://reader031.fdocuments.in/reader031/viewer/2022020413/5b5ddd0b7f8b9aa3048be933/html5/thumbnails/3.jpg)
Study Area and Project Objectives
![Page 4: Water Infrastructure - polokwane.gov.za · water (currently estimated ... –No extensions are being made to the existing reticulation networks, ... bids for PPP tender Project fails](https://reader031.fdocuments.in/reader031/viewer/2022020413/5b5ddd0b7f8b9aa3048be933/html5/thumbnails/4.jpg)
Needs Assessment
• Needs Assessment
– Asbestos Cement (AC) are 50 to 60 years old, reached end of design life
Frequent pipe bursts (this will increase)
High levels of water losses (this will increase)
High repair and maintenance costs (this will increase)
Existing pipe sizes may no longer be adequate to meet LoS requirements
Most water reticulation pipes in Seshego are mid-block - access for operation & maintenance crews is restricted
![Page 5: Water Infrastructure - polokwane.gov.za · water (currently estimated ... –No extensions are being made to the existing reticulation networks, ... bids for PPP tender Project fails](https://reader031.fdocuments.in/reader031/viewer/2022020413/5b5ddd0b7f8b9aa3048be933/html5/thumbnails/5.jpg)
Option Analysis
• Pipe Laying Options
– Conventional open trench pipe laying techniques
Hand excavation
Machine excavation
– Trenchless pipe-laying techniques
Moling
Pipe bursting / pipe cracking
Slip-lining
Pipe jacking
• Pipe Material Options
– Most suitable pipe materials for replacing the AC pipes are:
unPlasticized Polyvinyl Chloride (uPVC) pipes (open trench pipe-laying techniques)
High-Density Polyethylene (HDPE) pipes (open trench pipe-laying and trenchless techniques)
![Page 6: Water Infrastructure - polokwane.gov.za · water (currently estimated ... –No extensions are being made to the existing reticulation networks, ... bids for PPP tender Project fails](https://reader031.fdocuments.in/reader031/viewer/2022020413/5b5ddd0b7f8b9aa3048be933/html5/thumbnails/6.jpg)
Option Analysis
• Seshego B & C
– Residential area, and conventional open trench pipe-laying will be most suitable, and EPWP can be used
– unPlasticized Polyvinyl Chloride (uPVC) pipes will be most suitable
• Annadale
– Annadale (mostly residential area) conventional open trench pipe-laying will be most suitable, and EPWP can be used
– unPlasticized Polyvinyl Chloride (uPVC) pipes will be most suitable
• Central Business District (CBD)
– High density developments and limited working space, a combination of conventional open trench and trenchless pipe-laying techniques is considered most suitable for the CBD
![Page 7: Water Infrastructure - polokwane.gov.za · water (currently estimated ... –No extensions are being made to the existing reticulation networks, ... bids for PPP tender Project fails](https://reader031.fdocuments.in/reader031/viewer/2022020413/5b5ddd0b7f8b9aa3048be933/html5/thumbnails/7.jpg)
Due Diligence
• Staffing Requirements
– No extensions are being made to the existing reticulation networks, therefore no additional staff will be required as a result of this project
– Training will be required for personnel in handling HDPE pipe repairs
• Environmental Issues
– Asbestos is a hazardous substance which poses a serious health hazard to people if it is not handled properly and is allowed to become air-borne
– Handling and disposal of materials which contain asbestos should be carried out in accordance with the Asbestos Regulations, 2001 (Regulation 155 of the OHS)
– Asbestos pipes buried in the ground are unlikely to cause a health hazard as long as they remain buried
– Where possible the replacement of AC should be done without exposing or removing the old pipes (This has been done in several towns e.g. Rustenburg)
![Page 8: Water Infrastructure - polokwane.gov.za · water (currently estimated ... –No extensions are being made to the existing reticulation networks, ... bids for PPP tender Project fails](https://reader031.fdocuments.in/reader031/viewer/2022020413/5b5ddd0b7f8b9aa3048be933/html5/thumbnails/8.jpg)
Due Diligence
• Land Ownership
– Not likely to present any challenges as space is specifically provided for utility services
– Property owners must be consulted and notified in time in order to obtain access to their properties when replacing mid-block pipes in Seshego
• Geotechnical Issues
– Geotechnical assessments: determine excavation quantities, bedding requirements and inform selection of pipe materials
– Geotechnical investigations: undertaken during the project planning (before detailed design)
• Hydraulic Modelling of Networks
– Optimisation of pipe diameters for current and future water requirements
– Determine baseline for reduction of water losses and un-accounted for water
![Page 9: Water Infrastructure - polokwane.gov.za · water (currently estimated ... –No extensions are being made to the existing reticulation networks, ... bids for PPP tender Project fails](https://reader031.fdocuments.in/reader031/viewer/2022020413/5b5ddd0b7f8b9aa3048be933/html5/thumbnails/9.jpg)
Due Diligence
• Selection of Pipe Replacement Technique
– Selection of replacement technique will be crucial in respect of:
project implementation timeframes
project costs
Involvement of local companies and labour
– Estimates of lengths for trenchless and open trench methods
Area Trenchless (m) Open Trench (m)
CBD 15 667 51 914
Annandale 0 17 425
Seshego 0 45 544
![Page 10: Water Infrastructure - polokwane.gov.za · water (currently estimated ... –No extensions are being made to the existing reticulation networks, ... bids for PPP tender Project fails](https://reader031.fdocuments.in/reader031/viewer/2022020413/5b5ddd0b7f8b9aa3048be933/html5/thumbnails/10.jpg)
Due Diligence
• Integration with current & future projects
– Coordination with current and planned projects, i.e. ongoing meter replacement (part of a broader WC/WDM strategy) of the Polokwane Municipality
– Retro-fitting of water and sanitary fixtures in Seshego and other low income residential areas should also be prioritised
– Replacement of old water pipe networks should be extended to other areas in future phases
• Site Issues
– Project to be implemented in built-up areas:
• Limited working space
• Strategies required to maintain LoS to water consumers
• Minimise disruptions to other services during construction
• Traffic management
• Community liaison
![Page 11: Water Infrastructure - polokwane.gov.za · water (currently estimated ... –No extensions are being made to the existing reticulation networks, ... bids for PPP tender Project fails](https://reader031.fdocuments.in/reader031/viewer/2022020413/5b5ddd0b7f8b9aa3048be933/html5/thumbnails/11.jpg)
Project RisksDesign Stage Risks
Risk Consequence Mitigation
Delay in completion of designs Delayed implementationIncreased costsContinued discharge of poor effluent
Clear realistic deadlines Penalty clause
Available information is inaccurate or incomplete
Incorrect conclusions and decisions Budget to verify information & further investigations
Inaccurate sizing of pipelines Pre-mature upgrading costsNon-cost effective designHigh maintenance costs
Detailed consumer profilingInvestigate current & future water useHydraulic modelling
Design errors and omissions Infrastructure fails to performAdditional funds to rectify Over-design: wasteful expenditure.
Experienced PSP +Adequate PI insurance cover
Costing errors Insufficient to complete project Appoint experienced PSP + expert review
![Page 12: Water Infrastructure - polokwane.gov.za · water (currently estimated ... –No extensions are being made to the existing reticulation networks, ... bids for PPP tender Project fails](https://reader031.fdocuments.in/reader031/viewer/2022020413/5b5ddd0b7f8b9aa3048be933/html5/thumbnails/12.jpg)
Project Risks
Procurement Stage Risks
Risk Consequence Mitigation
Delays due to prolonged procurement processes
Delayed project completionIncreased costs
Detailed planning of procurement process
Lack of market interest to submit bids for PPP tender
Project fails to take off Advertise widely
Tender Loopholes - selection of Contractor with no capacity
Delayed project completionFailure to completeRe-tendering costs
Governed by SCM requirements
High prices - lack of clarity on project risks
Budget not sufficient Detailed investigations Workshops to clarify risks
Below cost tender price Contractor fails to complete project Rigorous evaluation - Rejection of below cost tenders
![Page 13: Water Infrastructure - polokwane.gov.za · water (currently estimated ... –No extensions are being made to the existing reticulation networks, ... bids for PPP tender Project fails](https://reader031.fdocuments.in/reader031/viewer/2022020413/5b5ddd0b7f8b9aa3048be933/html5/thumbnails/13.jpg)
Project Risks
Construction Stage Risks
Risk Consequence Mitigation
Delays Delayed completionIncreased costs
Realistic deadlinesPenalty clause in contract
Cost overruns Increased costs Possibly higher tariffs
Detailed work plan
Poor quality of work High maintenance costs Sufficient specification, construction monitoring + rigorous acceptance testing
Contractual disputes Delayed completionIncreased costs
Minimise vague clauses in contractClear dispute resolution procedures
Exposure to asbestos Persons contracting diseasesPossible financial claims
Authorised contractorCompliance with Asbestos Regulations
![Page 14: Water Infrastructure - polokwane.gov.za · water (currently estimated ... –No extensions are being made to the existing reticulation networks, ... bids for PPP tender Project fails](https://reader031.fdocuments.in/reader031/viewer/2022020413/5b5ddd0b7f8b9aa3048be933/html5/thumbnails/14.jpg)
Project Risks
Construction Stage Risks
Risk Consequence Mitigation
Injury to persons Injuries or fatalities Financial claims
Compliance with OHS rulesCompetent OHS personnel
Damage to adjacent services Loss of servicesInconveniencePossibility of claims
Identify exact locations of existing servicesCareful planning and execution of work
Damage to environment Environmental degradation Monitoring and controlRehabilitation measures
Industrial action by workers Delays and cost implications Appropriate insurance cover
Prolonged disruption of services Public inconveniencePossible financial losses
Alternative services provision