WATER AND SANITATION SERVICES IMPROVEMENT PROJECT
ADDITIONAL FINANCING (WaSSIP-AF)
SUMMARY PROCUREMENT PLAN
I. General
The following procurement plan has been developed for project implementation during the period October
2014 to September 2015 and provides the basis for the procurement methods and Bank prior/post review
thresholds. The plan will be updated when need arises to reflect the actual project implementation needs.
1. Project information:
a. Country: KENYA
b. Borrower: Government of Kenya
c. Project Name: Water and Sanitation Service Improvement Project Additional Financing
d. Loan/Credit No., IDA51030-KE (P096367) (P126637)
e. Project Implementing Agencies:
i. Athi Water Services Board (AWSB)
ii. Coast Water Services Board (CWSB)
iii. Lake Victoria North Water Services Board (LVNWSB)
2. Bank’s approval Date of the Procurement Plan: February 29, 2012 (during negotiations)
3. Bank’s approval Date of the Updated Procurement Plan: October 15, 2014
4. Date of General Procurement Notice. March 26, 2012
5. Period covered by this Procurement Plan: October 2014 to September 2015
91879 P
ublic
Dis
clos
ure
Aut
horiz
edP
ublic
Dis
clos
ure
Aut
horiz
edP
ublic
Dis
clos
ure
Aut
horiz
edP
ublic
Dis
clos
ure
Aut
horiz
edP
ublic
Dis
clos
ure
Aut
horiz
edP
ublic
Dis
clos
ure
Aut
horiz
edP
ublic
Dis
clos
ure
Aut
horiz
edP
ublic
Dis
clos
ure
Aut
horiz
ed
Page 2 of 19
II. Goods, Works, Consultancies and non-consulting services
1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated
in Appendix 1 to the Guidelines for Procurement:
(i) Works and Goods
Procurement Method Threshold (USD) Prior/ Post/
Review
Comments
1. ICB
Goods
Works
≥ 3,000,000
≥ 15,000,000
Prior Review
Prior Review
2. LIB (Goods) ≥ 3,000,000 Prior Review
3. NCB
Goods
Works
< 3,000,000
<15,000,000
Above 1.0 million
Prior Review
Above 10 million
Prior Review
4. Shopping
Goods
Works
< 100,000
< 200,000
Post Review
Post Review
5. Direct
Contracting
≥100,000 Prior Review Below 0.1 million
Post Review
(ii) Selection of Consultant Services
Selection Method Prior Review
Threshold (USD)
Comments
1. Competitive Methods (Firms)
(QCBS,QBS, FBS, LCS)
≥ 500,000
Single Source (Firms) ≥ 100,000
2. Individual Consultant Selection
(ICS)
≥ 200,000
3. Consultant Qualification Selection ≥ 200,000 The threshold for CQS is USD
300,000 as per the Guidelines.
4. Single Source (ICS) ≥ 100,000
Note: All ToRs will require Bank clearance.
Page 3 of 19
ATHI WATER SERVICES BOARD
A: WORKS
No
R.
No.
Works Description Status
Estimated
Cost in
USD
Procureme
nt Method
Review
by
Bank
(Prior/
Post)
Bid
submission
& Opening
Date
Remarks
1 77
Bulk Water Supply to
Nairobi : Construction of
Northern Collector Phase 1
(River abstruction/intake
structures and 12km tunnels)
Planned 85,000,000 ICB Prior 10-Nov-13
Actual 80,301,643 ICB Prior 29-Apr-14
2
Construction of Raw Water
and Treated water (Thika-
Ngorongo TW-Kabete)
pipeline for NCT Phase 1
Planned 62,600,000 ICB Prior 30-Oct-14
Actual
3 N/A
Development of 4 deep
(600m) and 4 shallower
(250m) Exploratory/pilot
Wells at Ruiru and Kiunyu
Planned 3,000,000 NCB Post 18-Dec-13
Actual 3,614,258 NCB Post 24-Oct-12
3a N/A
Addendum No. 1:
Geotechnical Investigations
for Karimenu 2 Dam
Planned 400,000 Variation Post N/A
Actual 363,957 Variation Post N/A
4
Development of Energy
Generation Innovations at
Dandora Wastewater
Treatment Plant
Planned 9,080,000 NCB Post 14-Nov-14
Actual
5 61
Construction of Independent
Community Water Supply
along the Northern Collector
Tunnel Phase 1 to Thika
Dam - Muranga W/S
Planned 9,800,000 ICB Prior 11-Dec-13
Actual 8,822,148 ICB Prior 24-Jan-14
6a N/A
Improvement of Sanitation in
informal settlements in
Nairobi:
Matopeni/Springvalley
Sewerage Works - Lot 3
Planned 3,000,000
NCB Post 12-Apr-13
Actual 3,316,571 NCB Post 23-Apr-13
6b N/A
Improvement of Sanitation in
informal settlements in
Nairobi: Embakasi
Riverbank Sewerage Works -
Lot 4B
Planned 1,000,000 NCB Post 12-Apr-13
Actual 750,347 NCB Post 23-Apr-13
6c N/A
Improvement of Sanitation in
informal settlements in
Nairobi: Huruma 3 Villages
(Ghetto, Mahiira &
Redeemed) Sewerage Works
- Lot 5A
Planned 1,000,000 NCB Post 12-Apr-13
Actual 711,709 NCB Post 23-Apr-13
7 N/A
Hydropower generation
scheme at Chania Outfall and
Thika Dam
Planned 3,000,000 NCB Post 17-Sep-14
Actual
8 60 Construction of Kiambu
Water Supply Works
Planned 8,500,000 ICB Prior 9-Dec-13
Actual 6,129,598 ICB Prior 29-Jan-14
9 N/A
Construction of Community
water supply downstream of
Thika Dam (Gatanga Water
Supply)
Planned 3,400,000 NCB Post 20-Jan-13
Actual 3,109,828 NCB Post 3-Jun-14
Page 4 of 19
No
R.
No.
Works Description Status
Estimated
Cost in
USD
Procureme
nt Method
Review
by
Bank
(Prior/
Post)
Bid
submission
& Opening
Date
Remarks
10 N/A
Construction of the Water
Reticulation System for
Ruiru and Juja towns
Planned 1,700,000 NCB Post 15-Oct-14
Actual
11 N/A
Independent Water Supply
around Ruiru II dam
(Mukuyu Water Supply)
Planned 1,000,000 NCB Post 22-Oct-14
Actual
12 N/A
Development of Kikuyu
springs water source for
Kikuyu town
Planned 500,000 NCB Post 20-Jul-13
Actual 610,331 NCB Post 18-Jun-13
13 N/A
Renovation and Construction
of 5 Water Appeals Board's
offices/courts (Narok,
Kisumu, Eldoret, Kitui,
Kakamega)
Planned 350,000 NCB Post 16-Feb-15
Actual
14a N/A
Drilling and Equipping of 7
Boreholes and Civil Works
in Athi WSB Area - Phase 1
Planned 1,260,000 NCB Post 14-Sep-13
Actual 1,337,352 NCB Post 5-Sep-13
14b N/A
Drilling and Equipping of 7
Boreholes and Civil Works
in Athi WSB Area - Phase 2
Planned 1,390,000 NCB Post 14-Jan-15
Actual
15 N/A
Drilling and Equipping of 5
Boreholes and Civil Works
in Tana WSB Area
Planned 930,000 NCB Post 8-Feb-14
Actual 856,658 NCB Post 17-Jun-14
16 N/A
Drilling and Equipping of 20
Boreholes and Civil Works
in Tanathi WSB Area in 3
Lots: Lot 1: Kajiado County,
Lot 2: Kitui County, Lot 3:
Machakos & Makueni
County
Planned 3,820,000 NCB Post 14-Feb-14
Actual NCB Post 16-Jun-14
17 N/A
Rehabilitation and expansion
of Wote in Tanathi WSB
area
Planned 1,140,000 NCB Post 14-Dec-14
Actual
18 N/A
Rehabilitation and expansion
of Mwala Water Supply in
Tanathi WSB Area
Planned 520,000 NCB Post 14-Feb-15
Actual
19 N/A
Rehabilitation of Amboseli
Pastrolist Water Supply in
Kajiado in County Tanathi
WSB Area
Planned 520,000 NCB Post 26-Jan-15
Actual
20 N/A
Construction of Mwea-
Makima Water Supply in
Tana WSB area
Planned 825,000 NCB Post 17-Mar-14
Actual 1,051,174 20-Jun-14
21 N/A
Installation of water tanks,
construction of tank-base and
guttering for rainwater
harvesting in AWSB area in
4 Packages - Lot 1
Planned 190,000
NCB
Post 9-Feb-15
Each Lot
is a
separate
Contract
Actual
22 N/A Installation of water tanks,
construction of tank-base and Planned 195,000 Post 9-Feb-15
Page 5 of 19
No
R.
No.
Works Description Status
Estimated
Cost in
USD
Procureme
nt Method
Review
by
Bank
(Prior/
Post)
Bid
submission
& Opening
Date
Remarks
guttering for rainwater
harvesting in Tanathi WSB
area in 4 Packages Lot 2
Actual
23 N/A
Installation of water tanks,
construction of tank-base and
guttering for rainwater
harvesting in Tana WSB
area- Lot 3
Planned 50,000 Post 9-Feb-15
Actual
24 N/A Utilities retrofit to reduce
energy costs
Planned 500,000 NCB Post 11-Feb-15
Actual
25 N/A Construction of AWSB
Operations Building
Planned 900,000 NCB Post 5-Feb-15
Actual
26 N/A Sewer extensions and
connections in Nairobi City
Planned 1,000,000 NCB Post 15-Nov-14
Actual
27 N/A
Rehabilitation of Boreholes
in Kajiado, Machakos,
Makueni and Kitui Counties
Planned 600,000 NCB Post 15-Oct-14
Actual
28 N/A Augmentation of Tigoni
Water Supply
Planned 1,000,000 NCB Post 14-Dec-14
Actual
29 N/A
Independent Water Supply
along NCT 1 dam (Gatango
Water Supply)
Planned 2,000,000 NCB Post 20-Nov-14
Actual
B: GOODS
No R.
No.
Goods Description Status Estimated
Cost in
USD
Procurement
Method Review
by
Bank
(Prior/
Post)
Submission
of bids &
Bid
opening
Remarks
1a Water Metering Programme for
WSPs (in Lots) Lot 1: Ordinary
and Bulk Meters, Lot 2:
Automatic Remote Read
Meters and Pressure Data
Loggers, and Lot 3: Leak
detection equipment and
Repair Tool Kits for WSPs
Planned 1,900,000 NCB Prior 29-Oct-14
Actual
2 2 Supply of 1,150 Plastic Tanks
in 3 Lots. (Capacity
10,000litres)
Planned 1,620,000 ICB Prior 1-Jul-12
Actual 820,361 ICB Prior 19-Jul-12
3 Supply of water pipes and
fittings for Water Services
Providers
Planned 1,000,000 ICB Prior 22-Nov-13
Actual 1,076,989 ICB Prior 16-Dec-13
Page 6 of 19
No R.
No.
Goods Description Status Estimated
Cost in
USD
Procurement
Method Review
by
Bank
(Prior/
Post)
Submission
of bids &
Bid
opening
Remarks
4 N/A Project Communication
materials - Lot 1: T-Shirts
1000, Umbrellas 1000, caps
1000, carrier bags 1000, Lot 2:
Annual Report 500, Bomba
Newsletter 8,000, and Best
practices Handbook - 1000,
Lot 3 Brochures 6000, pens
8000, paper folders 6000,
Fliers 10000, Lot 4: Banners
30, Billboards 5, Lot 5: media
campaigns 1, documentaries 3,
Lot 6: Diaries 1000, Calendars
5000 and seasons cards 1000
Planned 300,000 NCB Post 1-Nov-14
Actual
5a N/A Supply and Installation of ICT
Equipment and Software for
AWSB, WSPs and WAB in
Lots: , Lot 1 - Computers and
accessories, Lot 2 - Computer
Engineering Softwares, Lot 3 -
Publications Software, Lot 4 -
Communication equipments
Planned 420,000 NCB Post 21-Dec-13
Actual 340,392 NCB Post 21-Mar-14
5b N/A Athi Water Exchange Server:
Lot 1: Upgrading AWSB
Exchange Server Lot 2:
Installation of Audit Software
Planned 180,000 NCB Post 21-Dec-13
Actual 252,683 NCB Post 16-May-14
6 21 Supply of Lot1: Nine (9)
Lorries, Lot 2: Five (5) Water
tankers , and Lot 3: Single &
Double Cab Pick ups and
Twelve (12) operational
vehicles; and Lot 4: Twelve 12
Motor Cycles
Planned 1,930,000 ICB Prior 27-Aug-12
Actual 1,110,265 ICB Prior 14-Dec-12
7 Provision of 16 mobile
treatments units for Athi and
Tanathi WSBs
Planned 450,000 NCB Post 30-Dec-14
Actual 543,057 27-Jan-14
8a N/A Supply of 65 collapsible
(potable) water tanks: 5,000 to
10,000 litres Athi and Tanathi
WSBs
Planned 140,000 NCB Post 30-Dec-14
Actual
8b N/A Supply of five (5) sample
collapsible water tank and
accessories: 5,000 and 10,000
litres
Planned 20,000 Shopping Post 30-Oct-14
Actual
9 N/A Water Services Regulatory
Board: (i) Supply of
Promotional materials; and (ii)
Supply of Information
Education and Communication
materials
Planned 90,000 shopping Post 29-Nov-14
Actual
Actual
11 N/A Water Services Regulatory
Board: Supply of Computer
Hardware, Software and
Accessories
Planned 200,000 NCB Post 9-Nov-14
Actual
12 N/A Water Services Regulatory
Board: Storage Areas Network
Hardware
Planned 50,000 Shopping Post 9-Nov-14
Actual
Page 7 of 19
C: CONSULTANCY SERVICES
No R.
No.
Consultancy Description Status Cost
Estimate
USD
Selection
Method
Review
by Bank
(Prior/
Post)
RFP
submission
&
Opening
Remarks
1 3 Design, supervision and
coordination of Works of
Northern Collector Tunnel
Phase 1 (River intake
structures and tunnels)
Planned 6,610,000 QCBS Prior 4-Oct-12
Actual 3,893,875 QCBS Prior 21-Dec-12
2 66 Design Review and
Supervision of Construction
of Independent Community
Water Supply along the
Northern Collector Tunnel
Phase 1 to Thika Dam
Planned 300,000 QCBS Prior 7-Jan-14
Actual QCBS Prior 7-Oct-14
3 30 Environmental Impact
Assessment (EIA) and
Resettlement Action Plan
(RAP) for Raw Water and
Treated Water Pipelines
(Thika Dam - Ngorongo-
Kabete) and EIA for Northern
Collector Tunnel Phase 1
Planned 250,000 QCBS Prior 13-Mar-13
Actual 244,278 QCBS Prior 5-Jul-13
4 15 Design Review, Supervision
and Co-ordination of Northern
Collector System Raw Water
and Treated Water Pipelines
(Thika Dam - Ngorongo-
Kabete)
Planned 2,300,000 QCBS Prior 2-Mar-13
Actual 2,041,403 QCBS Prior 10-Apr-13
5 34 Project Monitoring &
Evaluation and Preparation of
Project Completion Report
Planned 180,000 IC Prior 11-Dec-13
Actual 91,800 IC Prior 28-Nov-13
7 Supervision of the
construction of Boreholes and
Elevated Steel Water Tanks
Athi Water Services Board
area (Phase 2)
Planned 250,000 QCBS Post 11-Mar-15
Actual
8 Energy Audits for Water
Service Providers in AWSB
Area
Planned 120,000 QCBS Post 15-Jan-15
Actual
9 Customer Identification
Survey and Infrastructure
Mapping for Water Service
Providers
Planned 250,000 QCBS Post 12-Jan-15
Actual
10 6 Environmental Impact
Assessment for Development
of Energy Generation at
Dandora Wastewater
Treatment Plant
Planned 150,000 QCBS Post 7-Feb-14
Actual
11 83 Detailed desing and
Supervision of Works for
Development of Energy
Generation at Dandora
Wastewater Treatment Plants
Planned 1,500,000 QCBS Prior 15-Aug-14
Actual
12 Review of Environmental
Impact Assessment Reports
Planned 250,000 QCBS Post 16-Oct-14
Page 8 of 19
No R.
No.
Consultancy Description Status Cost
Estimate
USD
Selection
Method
Review
by Bank
(Prior/
Post)
RFP
submission
&
Opening
Remarks
and Resettlement Action Plan
Reports and preparation of
Final Reports
Actual
13 Implementation of
Resettlement Action Plan
(RAP) and Environment and
Social Management
Frameworks (ESMF)
including Legal services for
Establishing and Registering
water and sewer Wayleaves
Planned 180,000 QCBS Post 5-Feb-15
Actual
14 41 AWSB WaSSIP
communication, Brand Roll-
out and Customer Satisfaction
surveys
Planned 200,000 QCBS Prior 15-Dec-13
Actual 178,245 2-Apr-14
15 Integration of Nairobi City
Water & Sewerage Company’s
Customer Management
System to Geographical
Information Systems (GIS).
Planned 150,000 QCBS Post 26-Jan-15
Actual
16 Updating of Nairobi City
Water Sewerage Company’s
GIS Maps, Water Network
Model and Training of Staff
Planned 170,000 QCBS Post 24-Jan-15
Actual
17a Water Services Regulatory
Board (WASREB):
Preparation of guidelines on
investment planning and
financial strategy for water
services
Planned 120,000 QCBS Post 8-Apr-13
Actual 158,110 4-Jun-13
17b Water Services Regulatory
Board (WASREB): Value for
Money study
Planned 75,000 QCBS Post 8-Apr-13
Actual 82,765 4-Jun-13
17c 37 Water Services Regulatory
Board (WASREB): Mid Term
Review of the performance of
5 Licensed Water Services
Boards
Planned 100,000 QCBS Post 8-Apr-13
Actual 43,471 4-Jun-13
17d 39 Water Services Regulatory
Board (WASREB): Feasibility
Study on Sewer Levy for
urban areas
Planned 120,000 QCBS Post 8-Mar-13
Actual 187,750 4-Jun-13
17e Water Services Regulatory
Board (WASREB): Technical
Assistance for Implementing
the Communication Strategy
Planned 190,000 QCBS Post 21-Feb-14
Actual 5-Sep-14
17f Water Services Regulatory
Board (WASREB): Technical
Assistance for Implementing
compliance and enforcement
strategy
Planned 125,000 QCBS Post 24-Dec-14
Actual
17g Water Services Regulatory
Board (WASREB): Updating
of regulatory tools and
guidelines and aligning them
to the constitution
Planned 50,000 QCBS Post 28-Jan-15
Actual
Page 9 of 19
No R.
No.
Consultancy Description Status Cost
Estimate
USD
Selection
Method
Review
by Bank
(Prior/
Post)
RFP
submission
&
Opening
Remarks
17h Water Services Regulatory
Board (WASREB): Employee
satisfaction and corruption
perception surveys
Planned 50,000 QCBS Post 5-Jan-15
Actual
17i
Water Services Regulatory
Board (WASREB): Customer
satisfaction Survey
Planned 50,000 QCBS Post 6-Dec-14
Actual
17j Water Services Regulatory
Board (WASREB): Audits and
inspections
Planned 150,000 QCBS Post 9-Jan-15
Actual
18a Water Appeals Board: Review
of Water Appeals Board rules
Planned 50,000 QCBS Post 5-Feb-15
Actual
18b Water Appeals Board:
Development of Human
Resources Management
Systems
Planned 50,000 QCBS Post 30-Jan-15
Actual
19 40 Updating the Nairobi City
Sewerage Masterplan and
Preparation of Masterplan for
Selected Satellite towns
Planned 455,000 QCBS Post 4-Mar-14
Actual Post
20 50 Design and Supervision of the
Construction of Hydropower
Power Generation Station at
Chania Outfall/Thika Dam
Planned 450,000 QCBS Prior 16-Jan-14
Actual 22-Apr-14
21 Environmental Impact
Assessment for Hydropower
generation station at Chania
outfall/Thika Dam
Planned 100,000 ICS Post 1-Jan-15
Actual
22 22 Review of Design and
supervision of Kiambu Water
Supply System
Planned 400,000 QCBS Prior 31-Dec-12
Actual QCBS Prior 15-Aug-13
23 23 Supervision of Independent
Community water supply
downstream of Thika Dam
(Intakes on Kimakia and
Kiama Rivers for Gatanga
WSP and treatment plant at
Gatura Mkt)
Planned 250,000 QCBS Prior 29-Nov-13
Actual QCBS Prior 14-Nov-13
24 27 Supervision of Water
Reticulation System for Ruiru
and Juja towns
Planned 160,000 QCBS Post 15-Jul-13
Actual 76,182 QCBS Post 28-May-13
25 Design of Automatic Meter
Reading and Review of
Prepaid Services system by
MPesa in Nairobi
Planned 50,000 ICS Post 25-Feb-15
Actual
26 29 Design and supervision of
water treatment works for
Theta Dam
Planned 240,000 QCBS Prior 31-Dec-12
Actual QCBS Prior 19-Feb-14
27 26 Review of Design and
Supervision of Kikuyu springs
water source for Kikuyu town
Planned 150,000 QCBS Post 18-Dec-12
Actual 60,033 QCBS Post 28-Feb-13
28 5 Review of the Environmental
Impact Assessment and
Planned 160,000 QCBS Post 22-Jul-12
Page 10 of 19
No R.
No.
Consultancy Description Status Cost
Estimate
USD
Selection
Method
Review
by Bank
(Prior/
Post)
RFP
submission
&
Opening
Remarks
Preparation of Resettlement
Action Plan for Ruiru
sewerage works
Actual QCBS Post 12-Nov-12
29 1 Updating Ruiru Sewerage
Design, detailed design for
Juja and Thika Municipality
and Supervision of Ruiru
Sewerage Works
Planned 610,000 QCBS Prior 17-Aug-12
Actual 584,558 QCBS Prior 31-Aug-12
30 13 Carry out strategic drought
Mitigation studies/Plan for
Athi Water Services Board,
Tana and Tanathi Water
Service Board areas
Planned 600,000 QCBS Prior 7-Mar-13
Actual 594,910 QCBS Prior 11-Apr-13
31 16 Design of Wote water supply,
Design of Amboseli Pastoralist
and Mwala water Supply and
Supervision of works in
Tanathi WSB Area
Planned 380,000 QCBS Prior 10-Aug-13
Actual 383,745 QCBS Prior 30-Sep-13
32 Design and Supervision of
Sewer Extensions and
connections in Nairobi
Planned 250,000 QCBS Post 12-Jun-15
Actual
33 25 Design and supervision of
Mwea-Makima Water Supply
works in Tana Water Services
Board area
Planned 180,000 QCBS Post 1-Mar-13
Actual 139,841 QCBS Post 25-Feb-13
34 Forensic Audit of NCWSC
and tax advisory services for
AWSB
Planned 150,000 QCBS Post 8-Jan-14
Actual 139,144 QCBS Post 9/27/2013
35 33 Hydrogeological studies,
design, Bid document
preparation and supervision of
construction of Boreholes and
elevated water tanks in Athi
Water Services Board area
Planned 150,000 QCBS Post 12-Nov-12
Actual 88,879 QCBS Post 12-Apr-13
36 17 Hydrogeological studies,
design, Bid document
preparation and supervision of
construction of boreholes and
elevated steel water tanks in
Tanathi Water Services Board
area
Planned 180,000 QCBS Post 13-Mar-13
Actual 89,433 QCBS Post 26-Feb-13
37 28 Hydrogeological studies,
design, Bid document
preparation and supervision of
construction of boreholes and
elevated steel water tanks in
Tana Water Services Board
area
Planned 170,000 QCBS Post 10-Mar-13
Actual 105,335 QCBS Post 4-Apr-13
38 63 Environmental Impact
Assessment and Resettlement
Action Plan for Rwaka dam
and Ruiru II Dam
Planned 300,000 QCBS Prior 2-Feb-14
Actual QCBS Prior
39 64 Environmental Impact
Assessment and Resettlement
Action Plan for Karimenu 2
dam
Planned 300,000 QCBS Prior 2-Feb-14
Actual QCBS Prior
40 Financial and Technical Audits Planned 150,000 QCBS Post 16-May-14
Page 11 of 19
No R.
No.
Consultancy Description Status Cost
Estimate
USD
Selection
Method
Review
by Bank
(Prior/
Post)
RFP
submission
&
Opening
Remarks
of WaSSIP AF Projects under
AWSB
Actual QCBS Post 24-Oct-14
41 Technical Assistance for
Implementation of the
Business Continuity Plan for
AWSB and NCWSC
Planned 50,000 ICS Post 18-Jan-15
Actual
42 Design and supervision of
Construction of AWSB
Operations Building and Water
Appeals Board Regional
offices refurbishment works
Planned 400,000 QCBS Post 3-Oct-14
Actual QCBS Post
43 Supervision of the
Construction of Mukuyu and
Tigoni Water Supplies
Planned 300,000 QCBS Post 3-Nov-14
Actual
44 Supervision of the
Construction of Gatango
Water Supply
Planned 300,000 QCBS Post 4-Dec-14
Actual
45 Supervision of Rehabilitation
of Boreholes in Kajiado,
Machakos, Makueni and Kitui
Counties
Planned 200,000 QCBS Post 2-Feb-15
Actual
46 N/A Supervision of the Installation
of Water Tanks and Gutters in
Schools in Tanathi WSB
Planned 200,000 ICS Post 3-Dec-14
Actual
COAST WATER SERVICES BOARD
A: WORKS
No Contract Description Status Contract
Cost USD
Procurement
Method
Review
by
Bank
(Prior/
Post)
Bid
submission
&
Opening
Remarks
1(a)
Emergency Immediate Works-Lot
1: Agumentation of the
BarichoWellfield,
Electromechanical Works and
10km RibeNguuTatu pipeline
Planned 6,800,000 NCB Post 31-Dec-14
Actual
1(b)
Emergency Immediate Works-Lot
2: Water Treatment/Manganese
Removal & Swabbing of Pipelines
Planned 8,000,000 NCB Post 27-Dec-14
Actual
1(c)
Emergency Immediate Works-Lot
3:
Malindi/Gongoni&Kakuyuni/Kilifi
Interconnection Pipelines Works
Planned 18,000,000 ICB Prior 31-Aug-15
Procurement by
Prequalification Actual
Actual
5 Rehabilitation of the Bulk Water
Pipeline System
Planned 3,600,000 NCB Post 18-Sep-12
Actual 3,465,028 NCB Post 12-Oct-12
8 Construction of office block for
CWSB
Planned 1,100,000 NCB Post 16-Nov-14
Actual
Page 12 of 19
No Contract Description Status Contract
Cost USD
Procurement
Method
Review
by
Bank
(Prior/
Post)
Bid
submission
&
Opening
Remarks
9 Construction of office blocks for
Tavevo and Lamu WSPs
Planned 200,000 NCB Post 28-Sep-12
Actual 174,767 NCB Post 15-Aug-12
10 Rehabilitation of Kizingo WWTP Planned 4,450,000 NCB Post 19-Jul-15
Actual
12
Rehabilitation of the Mombasa
WSP Water Reticulation Network-
Part of Lot 2
Planned 6,000,000 NCB Post 29-Jun-14
Actual 11,490,323 NCB Post 16-Jul-14
14
Construction of Water Supplies in
Drought Areas Lot 1: Equipping of
Existing Boreholes
Lot 2: Development &Equipping
of New Boreholes Lot 3:
Construction of Elevated Tanks at
Existing Borehole Locations
Planned 3,000,000 NCB Post 29-Mar-14
Actual 3,475,230 NCB Post 2-Apr-14
15
Construction of underground rain
water harvesting tanks (Djabias),
150m3 in Lamu county
Planned 1,000,000 NCB Post 12-Nov-14
Actual
16
Construction of Surface Modular
Pressed Steel Water Tanks for
CWSB
Planned 700,000 NCB Post 28-Dec-13
Actual 841,428 NCB Post 17-Dec-13
17 Construction of earth dam in
NWSB (Bute Dam)
Planned 3,350,000 NCB Post 31-Jan-15
Actual
18(a)
Extension/Construction of Water
Supply pipelines (Nyalani Water
Supply) for Kwale County and
Taveta Lumi W/Suppy for
T/Taveta County
Planned 2,000,000 NCB Post 14-Nov-14
Actual
18(b)
Extension/Construction of Water
Supply pipelines in
Maralal,Rumuruti & Laisamis in
NWSB
Planned 1,500,000 NCB Post 22-Nov-14
Actual
19(a)
Installation of Plastics Tanks &
gutters and Fittings at Various
Sites in CWSB
Planned 200,000 NCB Post 25-Mar-14
Actual 489,280 NCB Post 9-Apr-14
19(b)
Installation of Plastics Tanks &
gutters and Fittings at Various
Sites in Wajir, Garissa & Mandera
Counties in NWSB
Planned 200,000 NCB Post 27-Mar-14
Actual 404,958 NCB Post 10-Apr-14
19(c)
Installation of Plastics Tanks &
gutters and Fittings at Various
Sites Marsabit, Isiolo Counties in
NWSB
Planned 200,000 NCB Post 28-Mar-14
Actual 408,596 NCB Post 11-Apr-14
20(a)
Extending services to informal
settlements- Mombasa Works-Lot
1
Planned 1,000,000 NCB Post 31-May-14
Actual 1,458,602 NCB Post 29-May-14
20(b)
Extending services to informal
settlements- Mombasa Works-Lot
2
Planned 1,000,000 NCB Post 30-Nov-14
Actual
21 Extending services to informal
settlements- Malindi Works
Planned 783,900 NCB Post 22-Nov-12
Actual 1,205,970 NCB Post 18-Jan-13
22 Rehabilitation & Partitioning of
Bulk Water Company offices
Planned 200,000 Shopping Post 9-Sep-12
Actual 204,997 Shopping Post 30-Jan-13
23 Rehabilitation/Extension of Water Planned 1,000,000 NCB Post 22-Oct-14
Page 13 of 19
No Contract Description Status Contract
Cost USD
Procurement
Method
Review
by
Bank
(Prior/
Post)
Bid
submission
&
Opening
Remarks
Services in Tana River County
(Rehab of Hola W/Supply) Actual
24 Construction of Kilifi and Malindi
Sludge Drying Beds
Planned 500,000 NCB Post 23-Jan-15
Actual
25 Kilifi NRW Works Contract Planned 620,000 NCB Post 23-Jan-16
Actual
B: GOODS
No Contract Description Status Contract
Cost USD
Procurement
Method
Bank
Review
(Prior/
Post)
Submission
of bids &
Bid
opening
Remarks
1 Supply of Bulk water equipments and
tools
Planned 350,000 NCB Post 6-Oct-12
Actual 1,175,527 NCB Post 14-Dec-12
2 Supply of 30,000 ordinary consumer
and bulk water meters for WSPs
Planned 1,400,000 ICB Prior 27-Sep-12
Actual
1,624,640 ICB Prior 17-Jan-13
3
Supply of 30 motorcycles for meter
reading and general operations of the
WSPs
Planned 220,000 NCB Post 11-Oct-12
Actual 210,988 NCB Post 24-Sep-12
5(a) Supply of 4No. Sets of Leak detection
equipments and associated hand tools
Planned 300,000 NCB Post 10-Dec-13
Actual 460,967 NCB Post 2-Apr-14
5(b)
Supply of 4No. Sets of Leak detection
equipments and associated hand tools-
rebidding
Planned 300,000 NCB Post 9-Aug-14
Actual NCB Post 10-Sep-14
7
Supply, Installation and Maintenance of
Billing Systems for 6WSPs (Malindi,
Kilifi, Kwale, Tavevo, Lamu and Tana
River)
Planned 600,000 ICB Prior 10-Jan-14
Actual ICB Prior 21-Jan-14
8
Supply, Installation and Maintenance of
GIS Systems for 6WSPs (Malindi,
Kilifi, Kwale, Tavevo, Lamu and Tana
River)
Planned 480,000 NCB Post 27-Nov-13
Actual 520,255 NCB Post 4-Feb-14
9 Office Equipment for CWSB, Bulk
Company and WSPs
Planned 400,000 NCB Post 17-Apr-13
Actual 250,478 NCB Post 17-Apr-13
10 Supply and Delivery of Dewatering
Pumping Units
Planned 230,000 NCB Post 27-Nov-13
Actual NCB Post 12-Sep-14
11
Supply of 500No. 10m3 plastic water
tanks to public schools and institutions
in drought prone areas for rain water
harvesting
Planned 562,500 ICB Prior 6-Oct-12
Actual 522,367 ICB Prior 17-Oct-12
12(a)
Supply & Delivery of Utility Mini-
lorries for CWSB, Water Bowsers and
4WD drought Monitoring vehicles for
CWSB &NWSB
Planned 1,310,000 ICB Prior 8-Jan-14
Actual 902,228 ICB Prior 17-Jan-14
12(b)
Supply & Delivery of Portable Steel
Tanks, Collapsible Tanks and
Dewatering Pumps for CWSB
Planned 450,000 NCB Post 11-Jan-14
Actual 163,781 NCB Post 16-Dec-13
13 Supply of 9No. mobile water treatment
units for both silty river water and saline Planned 578,500 ICB Prior 18-Oct-12
Page 14 of 19
No Contract Description Status Contract
Cost USD
Procurement
Method
Bank
Review
(Prior/
Post)
Submission
of bids &
Bid
opening
Remarks
water from boreholes (to be pulled by
pickup) to all counties within Coast and
Northern WSBs Actual 586,620 ICB Prior 27-Sep-12
14
Supply of 2No.water trucking boats
(with engine power) for Lamu and
Wasini Islands
Planned 450,000 NCB Post 10-Dec-13
Actual NCB Post 6-Jun-14
15 Supply and Delivery of Standby
Generating Sets
Planned 130,000 NCB Post 5-Aug-14
Actual NCB Post 10-Sep-14
16 Supply of submersible pumps Planned 150,000 NCB Post 11-Sep-14
Actual 11-Sep-14
17 Supply & Delivery of Bulk Water
Machinery & Vehicles
Planned 500,000 ICB Prior 18-Nov-13
Actual 617,417 ICB Prior 7-Jan-14
18 Supply & Delivery of Bulk Water
Company Office Furnishings
Planned 100,000 Shopping Post 9-Jul-14
Actual Shopping Post 25-Jun-14
19 Printing of Communication Materials
(Calendars, Diaries, bags etc.)
Planned 175,000 NCB Post 7-Nov-14
Actual
20 Supply & Delivery of MOWASCO
Repair Kit (Pipes & Fittings)
Planned 650,000 NCB Post 13-Dec-14
Actual
C: CONSULTANCY SERVICES
No Contract Description Status Contract
Cost USD
Procurement
method
Bank
Review
(Prior/
Post)
Submission
of
proposals
Remarks
1(b)
Review and updating of previous studies,
conceptual and detailed design, tender
documents preparation and construction
supervision for the emergency
immediate works for lot 1,2&3
Planned 3,000,000 QCBS Prior 16-Oct-13
Actual 3,611,316 QCBS Prior 24-Sep-13
4
Supervision Services for the
Rehabilitation of the Bulk Pipeline
System Works
Planned 850,000 SSS Prior 29-Mar-13
Actual 985,243 SSS Prior 14-Nov-12
5 Energy audits in water utilities (WSPs) Planned 110,000 CQS Post 4-Feb-15
Actual -
6 Customer identification survey and
infrastructure mapping for all WSPs
Planned 150,000 QCBS Post 13-Jan-13
Actual 182,319 QCBS Post 18-Feb-13
7
UFW/NRW Reduction Consultancy
Services for Bulk and all WSPs (Kilifi,
Malindi, Lamu, Tavevo, Kwale and Tana
River)
Planned 610,000 QCBS Prior 13-Dec-14
Actual -
9 Study on incentive based performance for
Mowasco and 6WSPs Staff
Planned 75,000 CQS Post 23-Oct-14
Actual - CQS Post
10 Development of Waste water master plan
for Mombasa and other selected towns
Planned 560,000 QCBS Prior 11-Dec-13
Actual - QCBS Prior 30-Jan-14
11
Feasibility Studies, Detailed Design,
Tender Document Preparation for the
new Lamu Water Supply (for LAPSSET
Project)
Planned 600,000 QCBS Prior 21-Feb-15
Actual -
12 Identification and mapping of catchment
areas of Mzima, Tiwi, Marere and Planned 450,000 QCBS Post 13-Jan-15
Page 15 of 19
No Contract Description Status Contract
Cost USD
Procurement
method
Bank
Review
(Prior/
Post)
Submission
of
proposals
Remarks
Baricho Systems
Actual -
13 Preparation/Review of strategic plans for
CWSB and all the WSPs
Planned 25,000 QCBS Post 7-Nov-12
Actual 24,800 QCBS Post 7-Feb-13
14
Establishment and registration of
wayleaves for water facilities for various
works
Planned 100,000 QCBS Post 13-Dec-14
Actual -
18
Design Review & Supervision of
Mombasa WSP Water Reticulation
System-lot 2
Planned 600,000 QCBS Prior 6-Sep-14
Actual - QCBS Prior 2-Oct-14
19
Detailed Design, Tender Document
Preparation and Supervision of Kizingo
WWTP
Planned 360,000 QCBS Prior 30-May-14
Actual - QCBS Prior 7-May-14
21 Drought Mitigation Study (Plan) for
CWSB region
Planned 500,000 QCBS Prior 19-Oct-12
Actual 475,983 QCBS Prior 22-Feb-13
22 Ground Water Study for the
MertiAcquifer in Wajir
Planned 600,000 QCBS Prior 15-Dec-14
Actual
23 Supervision of Drought Response Civil
works
Planned 650,000 QCBS Prior 13- Oct-14
Actual
24 Design Review and Supervision of Bute
Dam
Planned 685,000 QCBS Prior 14-Apr-14
Actual
Prior 24-Jul-14
25 Consultancy Services for Preparation of
EIA& RAP Reports for all Works
Planned 400,000 QCBS Prior 26-May-14
Actual - QCBS Prior 27-Jun-14
26
Consultancy Services for Mombasa &
Malindi Informal Settlements Works
Supervision
Planned 200,000 CQS Prior 13-Dec-14
Actual -
27 Consultancy Services for Preparation of
Investment Plan for all WSPs
Planned 550,000 QCBS Prior 13-Nov-14
Actual -
28 Consultancy Services for Communication
Strategy Contract 2
Planned 200,000 QCBS Post 9-Nov-14
Actual
29 Consultancy for Bulk Water Services
Contract 2
Planned 500,000 QCBS Prior 15-Dec-14
Actual - QCBS Prior
30 Consultancy for Implementation of the
Recievables/Reconcilliation Report
Planned 200,000 SSS Prior 8-Nov-14
Actual
SSS Prior
31 Consultancy Services for Bute Dam
Safety Inspection/Review
Planned 300,000 QCBS Post 9-Nov-14
Actual QCBS Post
LAKE VICTORIA NORTH WATER SERVICES BOARD
A: WORKS
No Project Description Status Estimated
Cost USD
Procurement
Method
Review
by
Bank
(Prior/
Post)
Bid
submission
& Opening
Remarks
1 Construction of Elligirini Pipeline and
and expansion of Kapsoya Treatment
works.
Planned 3,500,000 NCB Post 10-Apr-15
Actual
Page 16 of 19
No Project Description Status Estimated
Cost USD
Procurement
Method
Review
by
Bank
(Prior/
Post)
Bid
submission
& Opening
Remarks
2 Construction of Kipkarren Dam
Treatment works and Distribution. Planned 6,500,000 NCB Post 26-Apr-15
Actual
3 Construction of Power Generation
Works at Waste Water Treat Plant
Eldoret
Planned 2,000,000 NCB Post 21-Nov-14
Actual
4 Construction of Water and Sanitation
facilities for Informal Settlements in
Mumias
Planned 800,000 NCB Post 20-Jul-14
Actual
NCB Post 16-Jul-14
5 Construction of Upstream Water
Treatment Works and Distribution
Lines, (Additional investment in
Kapcherop)
Planned 1,300,000 NCB Post 18-Oct-14
Actual
NCB Post 7-Oct-14
7a Drilling and capping of Drought
Boreholes LVNWSB
Planned 500,000 NCB Post 17-Dec-13
Actual 376,470.59 NCB POST 11-Nov-13
7b Drilling and capping of Drought
Boreholes RVWSB Planned 1,175,000 NCB POST 17-Dec-13
Actual 621,834 NCB POST 11-Nov-13
7c Drilling and capping of Drought
Boreholes LVSWSB Planned 550,000 NCB Post 17-Dec-13
Actual 232,000 NCB POST 11-Nov-13
8a Equipping of Drought Boreholes and
Civil Works LVNWSB
Planned 1,190,000 NCB Post 27-Oct-14
Actual
8b
Equipping of Drought Boreholes and
Civil Works RVWSB
Planned 3,250,000 NCB Post 27-Oct-14
Actual
8c
Equipping of Drought Boreholes and
Civil Works LVSWSB Planned 1,200,000 NCB Post 27-Oct-14
9a Rehabilitation/Expansion of Water
Supplies for LVNWSB - Kwanza
Water Supply
Planned 920,000 NCB Post 1-Apr-15
Actual
9b Rehabilitation/Expansion of Water
Supplies for RVWSB-Suswa Water
Supply
Planned 550,000 NCB Post 20-Feb-15
Actual
9c Rehabilitation/Expansion of Water
Supplies for RVWSB-Kapenguria
Water Supply
Planned 350,000 NCB Post 20-Feb-15
Actual
9d Rehabilitation/Expansion of Water
Supplies for RVWSB-Kapindaram Planned 550,000 NCB Post 20-Feb-15
Actual
10 Construction of plinths/gutters for
plastic water tanks 10,000lts for LVN,
LVS AND RV WSBs
Planned 575,000 NCB Post 26-Feb-14
Actual
NCB Post 16-Jun-14
B: GOODS
No Contract Description Status Estimated
Cost USD
Procurement
Method
Review
by
Bank
(Prior/
Post)
Bid
submission
& Opening
Remarks
1 Water Metering Programme for WSPs (in
Lots) Lot 1: Ordinary Meters; Lot 2:
Zonal/Bulk meters
Planned 700,000.00 ICB Prior 11-Nov-13
Actual 903,995.57 ICB Prior 8-Jan-14
2 Supply and Installation for LVNWSB and
WSPs -[ Office equipment & Specialized
software]
Planned 275,000.00 NCB Post 6-Nov-13
Actual 185,263.35 NCB Post 30-Apr-14
Page 17 of 19
No Contract Description Status Estimated
Cost USD
Procurement
Method
Review
by
Bank
(Prior/
Post)
Bid
submission
& Opening
Remarks
3 Procurement of communication materials
and services as per communication
strategy
Planned 280,000.00 Shopping Post 10-Nov-13
Actual 58,000.00 Shopping Post
4 Procurement of intranet system for the
Board, VOIP software, MIS for the Board
Planned 50,000.00 Shopping Post 29-Nov-13
Actual 49,020.24 NCB Post 27-May-14
5 Procure/Upgrade billing/accounting
software for WSPs/WSB
Planned 150,000.00 NCB Post 21-Oct-14
Actual
6 Leak detection and GIS Equipments for
WSP
Planned 130,000.00 NCB Post 27-Nov-14
Actual
7 Procurement of 18m3 Water Bowsers/10
tonnes Lorry Planned 2,970,000.00 NCB Prior 8-Aug-13
Actual 2,141,176.00 NCB Prior 25/02/2014
8 Purchase of Operational Vehicles Planned 240,000.00 NCB Post 7-Feb-13
Actual 356,961.00 NCB Post 12-Mar-13
9 Purchase of Plastic Tanks (400 No) Planned 600,000.00 NCB Prior 13-Jul-12
Actual 311,058.00 NCB Prior 21-Aug-12
10 Procurement of collapsible Tanks:
10,000 to 15,000 litres
Planned 184,000.00 NCB Post 23-Feb-15
Actual
11 Procurement of Stand-by generating sets:
various ratings
Planned 299,000.00 NCB Post 23-Feb-15
Actual
12 Procurement of Stand-by submersible
pumps Planned 115,000.00 NCB Post 23-Feb-15
Actual
13 Provision of Mobile treatment units Planned 489,500.00 NCB Post 23-Feb-15
Actual
C: CONSULTANCY SERVICES
S/No. Project Description Status
Cost
Estimate
USD
Selection
Method
Review
by
Bank
(Prior/
Post)
RFP
submission
& Opening
Remarks
1 Supervision of Project in Informal
Settlements in Eldoret (Gap
financing original WaSSIP)1
Planned 294,118 QCBS Post 25-Jan-15
Actual
2 Supervision Informal Settlements in
Mumias2
Planned 120,000 QCBS Prior 10-Aug-14
Actual 394,942 QCBS Prior
3 FS, Design and supervision of Energy
Generation from WWTP in Eldoret Planned 250,000 QCBS Prior 16-Aug-14
Actual
QCBS Prior 22-Oct-14
4 FS study review, design and
Supervision of Kapsoya Treatment
Works and Supervision of Elligirini
Pipeline
Planned 350,000 QCBS Prior 27-Sep-13
Actual 389,971 QCBS Prior 15-Jan-14
5a FS and Final Design for Kipkarren
Dam T Works and Associated
Distribution lines
Planned 650,000 QCBS Prior 4-Oct-13
Actual
QCBS Prior 9-Apr-14
5b Design Review and construction
supervision for Kipkarren Dam T
Works and Associated Distribution
lines
Planned 411,765 QCBS Post 25-Jan-/15
Actual
6 Consultancy services for
communication Planned 82,353 ICS Post 15-Aug-13
Actual 82,353 ICS Post 25-Aug-13
Page 18 of 19
S/No. Project Description Status
Cost
Estimate
USD
Selection
Method
Review
by
Bank
(Prior/
Post)
RFP
submission
& Opening
Remarks
7 Integration of customer management
systems to GIS and updating of GIS
maps and network model for WSPS
Planned 97,839 ICS Post 5-Nov-14
Actual
10 Carry out Staffing Needs Assessment
for the Board (Human Resources
Department)
Planned 22,588 ICS Post 15-May-14
Actual 21,176 ICS POST 15-May-14
12 Carry out Water and Sanitation
Service Levels Survey in the Board
Area
Planned 150,000 QCBS POST 19-Mar-14
Actual
QCBS POST 11-July-14
13 TA for Environmental and Quality
Management Systems
implementation
Planned 94,118 ICS Post 15-Feb-14
Actual 91,765 ICS POST 20-Feb-14
14a Consultancy for Energy Audit for
Eldowas Planned 47,435 ICS Post 19-Jan-15
Actual
ICS Post
14b Consultancy for Eldoret Water
Master plan Planned 1,400,000 QCBS Prior 25-Jan-15
Actual
QCBS Prior
15 TA for Performance Based NRW
Reduction for ELDOWAS Planned 90,353 ICS Post 2-Feb-14 At EOIs
evaluation
stage Actual
QCBS Post
16 TA for Customer Identification
Survey for ELDOWAS Planned 45,176 ICS Post 30-Dec-14
Actual
ICS POST
17A TA for Resettlement Action
Plan(RAP) for Kipkarren dam Water
Supply,Ellegirini/Kapsoya Project,
Additional Works for Kapcherop
Projects
Planned 97,882 ICS Post 14-Nov-14
Actual
ICS POST
17B TA for EIA for Kipkarren dam Water
Supply, Ellegirini/Kapsoya Project,
Additional Works for Kapcherop
Projects
Planned 50,000 ICS Post 28-Feb-15
Actual
ICS POST
18a Conditional Survey for Ellegirini &
Kipkarren Dams (Dam Safety
Inspection)
Planned 99,388 ICS Post 13-Feb-14
Actual 100,164 ICS POST 30-Nov-13
18b Condition Survey for Chebara -
Kapsoya Transmission main Planned 100,000 ICS Post 6-Aug-14
Actual 95,402 ICS Post 17-May-14
19 Customer/Employee Satisfaction
Survey Planned 90,000 ICS Post 1-Jun-14
Actual 84,706 ICS Post 7-Aug-13
20 Feasibility Study ,Detailed design
and supervision for a gravity Scheme
for Indigenous People (Kapcherop)
Planned 91,782 ICS Post 11-Oct-13
Actual 115,253 ICS POST 11-Aug-13
21
TA for Assessment of FMIS for
WSPs and WSB
Planned 23,824 ICS Post 7-Feb-14
Actual 21,182 ICS POST 7-Feb-14
22 Carry out strategic drought mitigation
studies/plan Planned 600,000 QCBS Prior 28-Oct-12
Actual
QCBS Prior 16-Apr-14
23 Preparation of EIA & RAP for
drought boreholes-LVNWSB
Planned 22,588 ICS Post 19-Sep-13
Actual
ICS POST
24 Design for civil works and Planned 90,353 ICS Post 20-Jan-15
Page 19 of 19
S/No. Project Description Status
Cost
Estimate
USD
Selection
Method
Review
by
Bank
(Prior/
Post)
RFP
submission
& Opening
Remarks
supervision of drought boreholes-
LVNWSB Actual
25 Preparation of EIA & RAP for
drought boreholes-RVWSB Planned 45,176 ICS Post 20-Jan-15
Actual
ICS POST
26 Design for civil works and
supervision of drought boreholes-
RVWSB
Planned 180,706 QCBS Post 14-Aug-15
Actual
27 Preparation of EIA & RAP for
drought boreholes-LVSWSB Planned 22,588 ICS Post 23-Nov-14
Actual
ICS POST
28 Design for civil works and
supervision of drought boreholes-
LVSWSB
Planned 88,588 ICS Post 26-Jan-15
Actual
29 Design and Supervision for Kwanza
Water Supply Project Planned 176,000 ICS Post 21-Nov-14
Actual
ICS Post
30a Design and construction supervision
for Suswa, Water Supply Projects in
RVWSB
Planned 150,000 ICS Post 7-Dec-14
Actual
ICS Post
30b Design and construction supervision
for Kapindaram Water Supply
Projects in RVWSB
Planned 120,000 ICS Post 21-Nov-14
Actual
ICS Post
30c Design and construction supervision
for Kapenguria Water Supply
Projects in RVWSB
Planned 130,000 ICS Post 21-Nov-14
Actual
ICS Post
31 TA for ESIA and RAP for Kwanza
and Kapenguria water supply Planned 90,000 ICS POST 21-Nov-14
Actual
32 TA for ESIA and RAP for Suswa
and Kapindarum Planned 100,000 ICS post 21-Nov-14
Actual