Wastewater Treatment Plant Facility Plan Update
Transcript of Wastewater Treatment Plant Facility Plan Update
Wastewater Treatment PlantFacility Plan Update
City Project #11-013City of Liberty, Missouri
May 6, 2013
2
Oct‐2011 ‐HDR Begins Feasibility Study to Evaluate Construction of a New Wastewater Treatment Plan versus Remaining with KCMO
‐‐
Jan‐2012 ‐ Council Approves Feasibility Study‐‐‐
May‐2012 ‐ City Authorizes Antidegradation Report and Facility Plan‐‐
Aug‐2012 ‐ Antidegradation Report Approved by MDNR‐
Oct‐2012 ‐ October 2012 Draft Operating Permit issued for public comment‐
Dec‐2012 ‐ Comment Period Closed without Public Comment‐
Jan‐March2013 ‐ Workshops and Site Visits
‐Apr‐2013 ‐ Draft Facility Plan Complete
Background
3
Feasibility Study Results
Feasibility Study Estimate Anaerobic AerobicConveyance $22,327,100 $22,327,100WWTP $53,398,200 $40,513,000TOTAL $75,725,000 $62,840,000
Feasibility Study Debt Service Cost Which Was Inflated to 2014 $78,130,000 $65,027,000
Adjustment for a Delayed Start from 2014 to 2015 $1,563,000 $1,301,000
Adjusted Debt Service Feasibility Cost (2015, 4.6 MGD) $79,693,000 $66,328,000
4
Facility Plan ResultsFacility Plan Estimate CostBase Cost $66,880,000
The Base Case Wastewater Treatment Facility will provide functionally reliable, consistenttreatment, with capacity for the next 20 years. It will meet the Missouri River discharge limitsapproved by the Missouri Department of Natural Resources, plus provide biological nutrientremoval reducing effluent nitrogen and phosphorus. The estimated construction costs arebased on costs for similar facilities constructed in the last 5 years and include inflation to aconstruction period beginning in 2015.Enhancements Recommended by Budget Committee
• Increase in Capacity – 30 years $5,280,000
• Modify Headworks for Future Expansion $980,000
• Dry Pit versus Submersible Pump Stations $1,240,000
• Access road from Highway 210 $340,000
Total Recommended Capital Cost ($2015) $74,720,000
5
Advantages of Liberty Wastewater Treatment Facility
• Lower present value• Predictable future rate increases• Nutrient removal capacity now; KCMO will need to
add later• Not dependent on KCMO schedule for upgrades to
Birmingham Pump Station• Capacity for 30 or more years• Liberty controls its wastewater and economic
development future
6
Public Workshop• Public Workshop
held November 11, 2012 at the Liberty Community Center
• Residents heard information about the options and gave feedback on preferences
30%
48%
22%
7
Workshops with City Staff
• January 7, 2013Collection System Improvements and Plant Flow
• January 22, 2013Process Evaluation and Hydraulic Review
• January 28, 2013Equipment Selection Review
• February 4, 2013Biosolids Disposal Options
• February 19, 2013Architectural Theme and Building Design
8
Workshop Results
• Wastewater Treatment Facility– $74.7 Million Capital Cost– 5.1 Million Gallon per Day Capacity– Dry Pit Pump Stations– Aerobic Digestion of Solids– UV Disinfection– Class B Biosolids– Solids Storage– Laboratory– Offices– Plant Maintenance Facility
9
Workshop Results
• Collection System– KCMO 42” Interceptor– West Pump Station
• Force Main Pumps• Excess Flow Pumps
– West Excess Flow Holding Basin– East Pump Station
• Influent Plant Pumps• Excess Flow Pumps
– East Excess Flow Holding Basin
11
Facility Plan Recommended Facilities (2015$)
CONVEYANCEINTERCEPTOR ‐ LIBERTY $230,000INTERCEPTOR ‐ KANSAS CITY $5,500,000CITY OF KANSAS CITY INTERCEPTOR CREDIT ‐$1,920,000WEST PUMP STATION $4,356,000PS BAR SCREENWEST EFHB $2,490,000WEST FORCE MAIN $2,320,000EAST EFHB $3,010,000CONVEYANCE TOTAL $15,986,000
WWTPINFLUENT PUMP STATION $6,445,000HEADWORKS $4,488,000AERATION BASINS $9,545,000RAS PS AND BLOWERS $5,260,000SECONDARY CLARIFIERS $7,787,000DEWATERING BUILDING $8,959,000DIGESTERS $4,520,000SOLIDS STORAGE $1,100,000INTERMEDIATE PUMP STATION $2,520,000UV DISINFECTION $2,440,000LAB/OFFICE (OPTION 5) $1,700,000SUBTOTAL $54,764,000
OUTFALL $3,300,000ACCESS ROAD $670,000PLANT TOTAL $58,734,000
PROJECT TOTAL $74,720,000
CAPITALIZED INTEREST $10,718,750DEBT SERVICE RESERVE FUND $8,227,268COST OF ISSUANCE $1,286,250BOND AMOUNT $94,952,268
12
Site Plan
12. INFLUENT PUMP STATION16. HEADWORKS20. AERATION BASIN SPLITTER22. BLOWER PAD24. AERATION BASIN30. SECONDARY CLARIFIER FLOW SPLITTER32. SECONDARY CLARIFIER34. INTERMEDIATE PUMP STATION36. FILTRATION (FUTURE)
38. UV DISINFECTION40. RAS/WAS LIFT STATION42. ELECTRICAL ROOM44. DEWATERING/THICKENING45. DIGESTION BLOWER PAD46. AEROBIC DIGESTERS48. CLASS B SOLIDS STORAGE60. LAB/OFFICE62. PLANT MAINTENANCE
13
Facility Plan EnhancementsNot Funded
Description EnhancementsExpanded Lab/Maintenance/C&D $6,217,000Biosolids Drying $6,400,0003 Clarifiers in lieu of 2 Clarifiers $2,070,000Blowers Inside a Building $1,020,000Alternate Biological Nutrient Removal $4,131,000Rush Creek Pump Station Screen $467,000
14
Net Present Value
Facility Plan
Feasibility Study
$‐ $50 $100 $150 $200 $250
Option 4 ‐ KCMO Projected Rates
Option 5‐ KCMO, Negotiated Rates
Alternative 1 ‐ Missouri River Discharge
Alternative 3 ‐ Missouri River Discharge
Alternative 2 ‐ Missouri River Discharge
Millions
$‐ $50 $100 $150 $200 $250
KCMO Direct to Plant Rates
KCMO Direct to Plant Rates (6.3% through 2020)
Liberty Recommended Facilities ‐ Scenario 2 Financing
Millions
10%/8% Increases through 2020
15
$‐
$5
$10
$15
$20
$25
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
2030
2031
2032
2033
2034
2035
2036
2037
2038
2039
Millions
Liberty WWTP ‐ Scenario 2 Financing KCMO Direct to Plant
KCMO 6.3% Through 2020 Liberty WWTP ‐ Level Payment Financing
Comparison of Total Annual Revenue Requirements
16
Average Annual Revenue Requirement Increase for Liberty
2014‐2018 2019‐2023 2024‐2039
Liberty Recommended Facility (Level Debt Payments)
9.7% 1.8% 0.7%
Liberty Recommended Facility (Scenario 2 Financing)
7.2% 4.5% 1.6%
KCMO Direct to Plant Rates (10%/8% KCMO Increases through 2020)
9.9% 5.4% 2.3%
KCMO Retail Rates(6.3% KCMO Increases through 2020) 7.6% 4.7% 2.2%
17
Cost per Average HouseholdBased on 4,165 gallons per month
Alternative $/Month
Current – 2013 $43.40
KCMO Direct to Plant (10%/8% KCMO Increases)
2019 $75.84
2024 $92.08
KCMO Direct to Plant (6.3% KCMO Increases)
2019 $67.92
2024 $80.55
Construct Liberty Plant (Level Payment Financing)
2019 $72.74
2024 $76.07
Construct Liberty Plant (Scenario 2 Financing)
2019 $64.19
2024 $79.22
18
Advantages of Liberty Wastewater Treatment Facility
• Lower present value• Predictable future rate increases• Nutrient removal capacity now; KCMO will need to
add later• Not dependent on KCMO schedule for upgrades to
Birmingham Pump Station• Capacity for up to 30 years• Liberty controls its wastewater and economic
development future
20
South Liberty Parkway DevelopmentDescription Cost Cumulative Total Enhancement/Benefit
West Liberty Interceptor with Capacity for South Liberty ParkwayArea
$5,949,000 $5,949,000
The base cost includes use of the shared interceptor currently used by KCMO and Liberty which has limited long‐term capacity. Construction of a new West Liberty Interceptor will provide capacity for the full West service area.
Scenario 2 City Extensions and Increased Capacity
$7,915,000 $13,864,000 This provides for the infill sewers in the area around the South Liberty Parkway.
2013 Adjusted Capital/Debt Costs (in 2015 dollars) $13,864,000
Description Additional Cost per Month (2019)
West Liberty Interceptor with Capacity for South Liberty Parkway $3.10Scenario 2 City Extensions and Increased Capacity for Ultimate Buildout $4.13
21
Next Steps
• May 6, 2013 – 1st Council Meeting Presentation of Facility Plan
• May – 2nd Council Meeting on August Bond Election• June/July 2013 – Public Meetings on Facility Plan• August 6, 2013 - Bond Election