Wastewater Alternative Technology Acceptance in Colorado€¦ · Alternative Technology Process...

20
Wastewater Alternative Technology Acceptance in Colorado David Kurz, P.E. Lead Wastewater Engineer Engineering Section CDPHE Water Quality Control Division July 15, 2015

Transcript of Wastewater Alternative Technology Acceptance in Colorado€¦ · Alternative Technology Process...

  • Wastewater Alternative

    Technology Acceptance

    in Colorado

    David Kurz, P.E.

    Lead Wastewater Engineer

    Engineering Section

    CDPHE Water Quality Control Division

    July 15, 2015

  • Objectives

    Provide information to facilitate:

    • Use of proven technologies in Colorado

    • More efficient interactions between manufacturers, owners,

    engineers, and the WQCD for design reviews.

    • Better understanding of the process for alternative

    technology acceptance

    • Clarification of the role of pilot tests at domestic

    wastewater treatment works

  • Clarifications

    Domestic wastewater treatment = state design review

    Industrial wastewater treatment = no state design review

    Both require discharge permit

  • Regulatory Framework

    Legislature – Colorado Water Quality Control Act

    (Title 25, Article 8, C.R.S.) (25-8-702 – Site location and design review required for domestic wastewater treatment works)

    WQCC – Regulation No. 22 (5 CCR 1002-22, revised 2009) (Site application, design review, in-kind replacement, pilot tests)

    WQCD - Policies • Reg 22 Guidance document (August 2010)

    • Policy 6 (WQSA-6 Multiple OWTS)

    • Wastewater design criteria (Policy WPC-DR-1)

  • Steps in Review Process (WWTP Steps 1-4, Lift Station/Interceptor Steps 2-3)

    1. Preliminary Effluent Limits (PELs) (WWTPs changing discharge, Permits Section, informs site location review)

    2. Site Location Application (*local agency review first*, Engineering Section, informs CDPS permit)

    3. Design Review (Engineering Section)

    • Lift Station or Interceptor = Basis of Design Report (BDR) together with

    Final Design

    • WWTP = Process Design Report (PDR) then Final Design (possibly

    streamlined final design review certified by design engineer §22.11)

    4. Discharge Permit (Permits Section)

  • Site Application Review

    • Review ability of proposed treatment process(es) to meet

    the PELs or effluent limitations [§22.9(1)(g)]

    • What criteria to be used for the design review phase?

    • Already included in the adopted wastewater

    design criteria (WPC-DR-1)

    or

    • Developed through an alternative technology

    acceptance

  • Alternative Technology Acceptance

    • New or non-conforming technologies not represented in the

    wastewater design criteria (reconfiguration, combinations,

    packages)

    • Established or innovative technology with existing

    compliance record

    • Not for emerging treatment techniques without compliance

    history

    • Described in section 1.8.0 of the wastewater design criteria

  • Alternative Technology Process

    • Manufacturer submittal of information in §1.8.0 of the

    wastewater design criteria (e.g., engineering basis,

    operating history)

    • Timing = submit for alternative technology review as soon as

    practical before a site application

    • Alternative technology submittal checklist (see website)

    • Alternative technology recognition statement for a specific

    project (if for a specific project)

  • Alternative Technology Review

    • Review history of successful operations

    • Evaluate efficacy of technology in providing reliable

    wastewater treatment under a range of operating

    conditions throughout Colorado (elevations,

    temperatures)

    • Not just pass/fail or averages

    • Develop appropriate criteria for technology design

    review

  • Data!

    • Document assumptions, calculations, process modeling

    • Actual full-scale operating experience

    • Pilot test work results (long periods, seasons)

    • Limiting conditions (temperature, elevation)

    • Reliability, sensitivity (influent variations, conditions)

  • Acceptance ≠ Design Approval

    • Site location and design approval still required for

    each location where use of accepted technology is

    proposed (just as for other technologies in design

    criteria)

  • Pilot Testing Authority

    • Site location approval requirements in Amendment section

    [§22.8(2)(vii)] provide for conducting pilot projects.

    • Regulation 22 Guidance Document provides additional

    descriptive information. [Page 62, line 2954]

    • Pilot Test Plan is required.

    • Limited period of up to 12 months, with possibility for one

    extension of additional 12 months.

    Note: “Pilot testing” in the wastewater regulatory realm is not the same as in the drinking water regulatory realm.

  • Pilot Testing Goals

    • Goals and scale of pilot tests vary:

    • Sidestream test of established technology to evaluate appropriateness

    for a particular WWTF

    • Testing of emerging technology without compliance track record

    • For alternative technology evaluations where a compliance

    history is not available:

    • Much higher requirement for information to be provided by the pilot test

    • Pilot test must provide adequate level of data to establish alternative

    technology compliance record and design requirements

    • Pilot test plan must be more robust

    • Note: “pilot test completed = alternative technology

    acceptance” is NOT an automatic conclusion

  • Tips to Avoid Pitfalls

    • Use Reg. 22 Guidance and Wastewater Design Criteria

    • Provide complete submittals with documentation

    • Consider pre-meeting with Engineering Section

    • Alternative technology identified early to David Kurz:

    [email protected] or 303-692-3552

    mailto:[email protected]

  • Website Tips

    • http://www.colorado.gov/CDPHE/WQCD

    • Facility Design and Approval

    • Forms

    • Domestic wastewater alternative technologies

    = list with accepted technology letters

    • Guidance (Regulation 22 guidance)

    • Policies (design criteria)

    • Regulations (WQCC – Regulation 22)

  • Innovation Ideas

    • Retrofit: Anoxic Basin on RAS line with carbon source

    diverted from influent wastewater stream; benefit is higher

    MLSS, smaller basin and available carbon source

    • Zero liquid discharge at East Cherry Creek reverse osmosis

    drinking water plant. Distillation of waste stream.

  • Highest Potential Needs

    • Larger facilities:

    sulfate, selenium, dewatering for biological phosphorus

    • Medium facilities:

    assistance for lagoons with ammonia and beyond

    • Small facilities (discharge to groundwater):

    low cost/high treatment/easy operations options to meet

    effluent limit of 10 mg/L TIN

    TDS

  • Barriers and Hurdles

    • Poor testing prior to bringing to the state.

    • Come with defensible evidence of operations

    for all conditions

  • Suggestions to Help Innovation Needs

    • Collaboration on innovation and pilot tests

    • Various entities request pilot tests and sometimes we see

    the same for different facilities. May or may not need

    separate pilot tests.

    • An operating WWTF willing to pilot different ideas that

    could possibly coordinate with other facilities to test viable

    technologies for all to see and possibly use (publish results).

    • Example - Test a technology at one representative facility

    where entities can contribute $ and ideas about how the

    work will be completed.

  • Questions?