Waste Management Handbook

59
1

description

good

Transcript of Waste Management Handbook

  • 1

  • 2

    Rev. No. : 0

    Waste Management Handbook for Building Division Date : March 2013

    REVISION STATUS SHEET

    Review Approval Rev. No.

    Date Summary of Revision

    By Date By Date

    0 Mar 2013 First Version

    selinachinRectangle

  • 3

    CONTENTS

    1 BACKGROUND ...........................................................................................................1

    2 PURPOSE OF THE HANDBOOK................................................................................2

    3 BENEFIT FROM BETTER WASTE MANAGEMENT ...................................................2

    4 WASTE MANAGEMENT STRATEGIES ......................................................................3

    5 ORGANISATION STRUCTURE AND INDIVIDUAL RESPONSIBILITIES ...................4

    6 ANALYSIS OF WASTE GENERATION AT DIFFERENT STAGE ...............................5

    7 MANAGEMENT OF LANDFILL WASTE ON SITE ......................................................6

    8 WASTE REDUCTION MEASURES .............................................................................8

    9 MONITORING AND REVIEWING ..............................................................................11

    10 TRAINING AND PROMOTION...................................................................................12

    Appendix A Appendix B Appendix C Appendix D Appendix E Appendix F Appendix G Appendix H Appendix I

    Cost saving from waste minimization Figures of Different Projects Waste generated at different construction stage Project Specific Waste Management Plan Template Waste Recycling Companies / Charities Detailed Waste Reduction Measures Building Waste Baseline Audit Scorecard Project-base Waste Management Kick-off and Audit Schedule Waste Management Key Performance Index (WMKPI) Template

    Figure 1 Figure 2

    Total tonnage disposed by division Landfill Waste Intensity of Building Division

    Figure 1 Temporary on Site Sorting Facilities

  • Waste Management Handbook for Building Division Rev. 0

    1

    1 BACKGROUND

    Waste to municipal landfill is a pressing and critical issue in Hong Kong and construction waste is a sensitive topic that raises much attention. About 25% of the waste to Hong Kong landfills is construction waste. In simple terms, the generation and management of waste for Gammon impacts profitability, productivity and is an added logistical burden; it is also associated with housekeeping and safety.

    Gammons quantity (tonnes) of landfill waste has increased from 26,000 tonnes in 2007 to 35,800 tonnes in 2012 (+37.7%) and the majority of waste disposed of in municipal landfill representing 2.5% of Hong Kong total.

    Figure 1: Total tonnage disposed by division

    Landfill Disposal

    0

    5000

    10000

    15000

    20000

    25000

    30000

    2007 2008 2009 2010 2011 2012

    BDG CVL E&M FDN SGP

    As the majority comes from building type works, a workgroup comprised of Building, Environment and Procurement has developed actions towards achieving significant reductions.

    GCL % 2.3% 1.5% 2.5% 2.3% 3.7%

    Total HK

  • Waste Management Handbook for Building Division Rev. 0

    2

    2 PURPOSE OF THE HANDBOOK

    With the baseline of 2007, building division aimed to achieve 30% reduction* in landfill intensity by end 2018, we must: 1) exercise better planning and design 2) reduce the waste generated and 3) reduce sent to landfill by increasing reuse and recycle arrangements. There are sub-reduction targets in 2014 (by 10%) and 2016 (by 20%) for achieving our ultimate target step by step. * Rebar or steel waste is not counted in the target figure

    Figure 2: Landfill Waste Intensity of Building Division

    This Waste Management Handbook (WMH) aims to provide each project team with practical and achievable guidelines for achieving waste reduction target of the Sustainability Vision of gammon Building Home. The Handbook includes:

    Project organisation structure setting out the roles and responsibilities of the respective project team member responsible for waste management and appropriate mitigation measures;

    An analysis of timing and types of C&D materials to be generated in the course of the execution of the Works;

    The steps required to implement a site waste management plan; Suggestion of waste reduction measures; A monitoring and reviewing proposal to ensure that the requirements of the

    site waste management plan are properly implemented; and Contact details for waste recyclers in Hong Kong.

    3 BENEFIT FROM BETTER WASTE MANAGEMENT

    Reduce waste disposal costs Enjoy lower disposal costs for separated wastes, the cost-saving calculation

    shown in Appendix A. Receive payment for some wastes (especially metals)

    Landfill Waste Intensity

    30.03

    4.13 5.3 2.893.313.72

    0

    5

    10

    15

    20

    25

    30

    35

    2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018

    Ton

    nes

    /HK$

    1M Tu

    rno

    ver

    Ban of inert waste to landfill

    Baseline Target

  • Waste Management Handbook for Building Division Rev. 0

    3

    Cut back purchasing cost by re-using existing materials/equipment onsite instead of disposed as waste

    Reduce onsite risk Decrease the chance of worker injuries due to better housekeeping Improve the visual impact of project on the surrounding community

    Meet contractual obligations and rating requirements Achieve higher green ratings for the development

    4 WASTE MANAGEMENT STRATEGIES

    4.1 Hierarchy

    The various waste management options shall be categorised in terms of preference from an environmental viewpoint. The options considered to be more preferable have the least impacts and are more sustainable in the longer term. Hence, the hierarchy of waste management is as follows:

    Planning and Design

    Recycling & Reprocessing material

    Avoidance and Minimization

    Zero conservation of recourses

    Reuse of materials

    Planning and Design

    Recycling & Reprocessing material

    Avoidance and Minimization

    Zero conservation of recourses

    Reuse of materials

    This hierarchy shall be used to evaluate waste management options, thus allowing maximum waste reduction. Rethink is careful planning at the design and drawing stages. It is at this stage that the greatest reductions in waste can be achieved. Reduce waste by eliminating over-ordering of construction materials, waste is avoided and costs are reduced both in terms of purchasing of raw materials and in disposing of waste. On site, the Reuse and Recycle of materials should be maximized to avoid Disposal.

    4.2 Waste Management

    The proposed strategy is not limited to collection & disposal system. Instead, it proposes to employ a multi-pronged approach that revolves round the waste hierarchy participatory principle. Procurement strategy Manage at source - Proposing a task force team Education Incentives to subcontractors

  • Waste Management Handbook for Building Division Rev. 0

    4

    5 ORGANISATION STRUCTURE AND INDIVIDUAL RESPONSIBILITIES

    An execution team should be established. The team members should be those who directly involved with the project and can collective influence all aspects of waste management. The project organisation with respect to waste management works is outlined in the following sections.

    5.1 Project Manager

    The Project Manager is responsible to the Contract Manager for overall planning, site operations, appointment of committee members for waste management, staff supervision control co-ordination and external liaison. He is ultimately responsible for all aspects of waste management issues within the Project, which they achieve by implementation of the WMH. He is also responsible for provision of necessary support to the environmental engineer for the preparation and review of waste management and arrangement of site staff to attend environmental training with regard to waste management organised by other bodies or the environmental engineer.

    The Project Manager has the following responsibilities in relation to waste management:

    i. Keep abreast of the requirements of the statutory regulations in relation to waste management;

    ii. Ensure works are executed in accordance with the WMH; iii. Arrange routine joint site inspection with environmental engineer and review

    environmental inspection report submitted by the environmental engineer; iv. Ensure appropriate waste management mitigation measures are properly

    implemented; v. Ensure follow up actions are properly undertaken in the event of non-

    compliance of the waste management plan; vi. Review method statement to ensure appropriate mitigation measures are

    implemented prior to execution of work; and vii. Monitor the following documents.

    any statutory required waste management permits/licenses including dumping licence, chemical waste producer, admission ticket and etc;

    C&D material disposal delivery record; and, waste reuse / recycle / disposal summary.

    5.2 Site Agent

    He shall have the following duties in relation to environmental control:

    i. Assist the Project Manager in implementing the waste management plan; ii. Monitor and control the works including those of subcontractors to ensure

    compliance of WMH; iii. Report to the Project Manager regarding non-compliance of any waste

    management issues; iv. Ensure the remedial actions or mitigation measures are carried out as

    planned; and v. Supervise and arrange the maintenance of waste management facilities.

  • Waste Management Handbook for Building Division Rev. 0

    5

    5.3 Foremen

    Foremen are responsible for the following duties in relation to environmental control:

    i. Assist the Site Agent in implementing the WMH; ii. Control the works including those of subcontractors to fulfil the requirement of

    waste management issues; iii. Report to the Site Agent any non-compliance of any waste management

    issues; iv. Maintain the on-site waste management facilities including sorting area,

    temporary storage area, general refuse bins, recycling bins and etc; v. Leading task force to do sorting and separation at source, housekeeping,

    waste collection, disposal management in site vi. Carry out remedial actions or mitigation measures to rectify the non-

    compliance; vii. They shall carry out routine maintenance of waste management facilities.

    Maintenance records shall be kept in site office.

    5.4 Environmental Engineer

    The Environmental Engineer shall oversee the implementation and the performance of the WMH and shall also be responsible for:

    i. Reviewing works programmes, method statements, licence application and other relevant documentation so as to ensure the best practice would be implemented to generate no unacceptable impacts with respect to waste management to the established guidelines/standards;

    ii. Identifying any potential unanticipated or greater than expected waste impacts;

    iii. Formulating any necessary preventative or remedial measures to be taken for these potential impacts;

    iv. Liaising and consulting with all relevant parties during implementing WMH; v. Preparing training material for environmental toolbox talks with regard to

    waste management and disseminating guidance notes to operatives.

    5.5 Task Force for Waste Management

    Depending on the size of individual project, task force led by a project coordinator/supervisor provided with direct labours and technically supported by the project environmental team shall implement waste management on site (planning, waste identification of each construction stage, sorting and separation at source, housekeeping, waste collection, disposal management and reporting).

    6 ANALYSIS OF WASTE GENERATION AT DIFFERENT STAGE

    To give a brief idea on the amount of waste generated in different stages, the landfill waste of various building projects were shown in Appendix B. The scope of projects, contract sum and landfill waste intensity are stated for easy comparison.

    Different types of waste will be generated throughout the construction period of the Project from various construction activities and daily operation of the construction site. The major construction activities and the associated waste generation are identified in Appendix C.

  • Waste Management Handbook for Building Division Rev. 0

    6

    7 MANAGEMENT OF LANDFILL WASTE ON SITE

    All Construction and Demolition (C&D) materials arising from or in connection with the Works will be sorted on site to recover reusable and/or recyclable materials. All sorted and processed surplus materials arising from or in connection with the Works from the Site will be promptly removed to minimise temporary stockpiling on the Site.

    A system will be devised for on-site sorting of C&D materials. The system will include the identification of the source of generation, estimated quantity, arrangement for on-site sorting and/or collection, temporary storage areas, frequency of collection by recycling contractors or frequency of removal off the Site, etc. Each project should prepare their project specific Waste Management Plan and a template was attached in Appendix D.

    7.1 Prediction of construction activities and Estimation of waste generation

    Identify the materials likely to be discarded and at what stage of the project. This should be carried out prior to the commencement of the site works. This involves looking at the construction program and the project design and identifying materials in-flows and outflows. Estimate the quantities by using normal ordering margins and packaging mode. Moreover, using landfill waste intensity target of building home to calculate the total waste generation of project. These will give the information to team for scheduling bin numbers, sizes and likely changeovers

    7.2 Set waste diversion target

    Setting waste diversion target can be based on green building guidelines, BEAM Plus and LEED. These guidelines do not only focus on recycling, instead they focus on the diverting waste from landfills by finding multiple alternatives for end uses of the waste, namely reuse on site, recycling, donation for reuse on another site. All of these diversion methods count towards credit compliance 75% construction waste diverted for two points. For BEAM Plus, two credit is for 60% of construction waste recycled.

    Predict activities & estimate waste

    generation

    Set waste diversion target

    Identify & select recyclers

    Planning of logistic & resources

    Planning of manpower

    Regular Review

    Management Cycle

  • Waste Management Handbook for Building Division Rev. 0

    7

    7.3 Identify & select recycler according to actual market availability

    Contact recyclers using this handbook, Appendix E, or EPD Recycling Directories. https://www.wastereduction.gov.hk/en/quickaccess/vicinity.htm#1 To deal with recyclers, there are several points to pay attention.

    The condition of recyclable materials Any drop boxes and pick-up service available Options of collection: call for service, scheduled pick-up, or send to their

    collection points The charge of services including drop box rental and transport fee Provide receipts for types and quantities of materials collected

    7.4 Planning of mode of logistic, transportation and sorting facilities

    Better planning of hardware support would encourage on-site sorting. Since it is difficult to separate the waste materials after they mixed, project team should make sorting convenient by placing recycling bins, designated areas close to the work on each floor or designated area near the refuse chute. Centralize sorting area with different recycling bins are recommended to facilitate the final collection for different types of waste.

    To plan the logistic routine for the waste collection from different floor, refuse chute, jump lift and hoist are preferred. Landfill waste, recyclables and inert waste should be transported down separately to avoid contamination; thus, one more refuse chute in site is recommended to facilitate waste collection as well as vertical transportation. Operation team better to have different arrangement on using vertical logistic to balance the demand of material delivery and waste collection. The location of rubbish skip and collection points should be closed to site entrance for easy removed by collectors.

    7.5 Planning of manpower by subletting, task force etc

    Implement processes to ensure the separation of chosen wastes by subcontractors and task force. Ensure that everyone is aware of their obligations and responsibilities. Subcontractors have to sort their waste before disposal of designated areas that reduces the burden of task force. Consider back-charging a subcontractor who doesnt separate their waste. Conduct training about the materials to be separated and getting any ideas from staff.

    7.6 Regular review on the efficiency of overall sorting, collection and disposal

    Once construction has started, keep the receipts from recycling and garbage disposal for planning estimates in future waste management budget. Regular meeting with staff to get feedback on how sorting can best be done onsite. Consider review the management when the construction stage change.

  • Waste Management Handbook for Building Division Rev. 0

    8

    8 WASTE REDUCTION MEASURES

    Measures and Descriptions Rethink Reduce Reuse Recycle Design and Planning Stage

    Project designs for waste prevention and minimization - adopting construction design and method which prevent and provide

    less waste

    Lean Construction - adopting designs using thinner internal walls and floor slabs and

    reducing foundation size which could minimize the amount of raw materials being used and thus reduce the amount of waste

    Modular Building Designs and Pre-casting of Construction Components - pre-casting of construction components and install them on-site

    BIM application - The use of BIM 3D CAD Models for design co-ordination of the

    architectural, structural, E&M components to reduce the wastage from abortive work

    Better Scheduling of Construction Tasks by Stage - carrying out of one task at a time by scheduling tasks by stage to

    prevent contamination and mixing of waste

    Better Site Planning and Logistic Planning - allocating waste facilities at the right places and making sure the logistic

    is convenient for implementing on-site waste management

    Construction Waste Management and Reduction Plan - planning for waste handling, sorting, collection and disposal, allocating

    spaces for placing waste facilities and for waste management, appointing staffs for managing and monitoring and etc before the construction

  • Waste Management Handbook for Building Division Rev. 0

    9

    Measures and Descriptions Rethink Reduce Reuse Recycle

    Construction Stage

    Prevent waste with efficient purchasing - avoiding over-estimation and ordering too many materials which could

    not be fully utilized in the construction - purchase materials with minimal packaging, while ensuring goods are

    not damaged during delivery - coordinate materials delivery to coincide with its use to reduce material

    damage and waste

    Make Good Use of Internal Materials Exchange System - the marketplace allow both buyers and sellers to exchange information

    and post message online for excessive or 2nd hand items located in their sites and offices and ready for transfer internally.

    -

    Building Better Coordination and Cooperation among Stakeholders in the Supply Chain - developing linkages and coordinating with other stakeholders in the

    supply to transport unwanted construction materials to other places where these materials could be utilized. For examples, materials suppliers could take back surplus materials and packing materials from contractors; unwanted inert materials could be transported to concrete plant and/or used in other concurrent projects; contractors could coordinate with recyclers to pick up recyclables; and etc.

    The Use of Reusable Metals for Formwork - replacing wooden panels which could only be used once with metals

    which could be reused for many times for formwork

    Provision of Waste Management and Facilities - providing accessible waste collection and sorting facilities on site

    On-Site Sorting - avoiding mixing of construction materials and conduct sorting on-site as

    early as once the waste are produced when the construction labours are doing their tasks

  • Waste Management Handbook for Building Division Rev. 0

    10

    Creating Incentives to Reduce Waste - waste charging is a common example of financial incentive by

    internalizing costs of waste management to the producers; other non-financial incentives include voluntary schemes, creating co-benefits for practicing waste reduction measures and award schemes; and etc

    For the detailed measures, please refer to Appendix F.

  • Waste Management Handbook for Building Division Rev. 0

    11

    9 MONITORING AND REVIEWING

    9.1 Internal site Inspection

    The execution team shall arrange regular inspection to inspect the site to ensure satisfactory performance on compliance with the waste management plan with due regards to the followings:

    i. inert C&D materials suitable for recycling into aggregates are recovered and delivered to designated recycling facilities as notified by the Architect or the Public Fill Committee (Port Works Division of CED);

    ii. if the Contract involves demolition works, appropriate sequential demolition has been employed to facilitate recovering as much as possible reusable and recyclable materials;

    iii. a disposal recording system is operating satisfactorily for recording C&D materials removed from the Site; and

    iv. on-site sorting of C&D materials is properly carried out to recover inert C&D materials and reusable and/or recyclable materials before disposal.

    Team may arrange the regular inspection on waste management performance to be carried out along with the regular internal safety & environmental walks.

    9.2 Record Keeping and Reporting

    Environmental Engineer shall keep adequate and proper records such as delivery dockets and measurement records relating to the implementation of the waste management plan. All waste treatment should be properly recorded by receipt, photo, delivery form and summary, supporting document should also be provided for individual waste.

    Smart Waste Account was introduced to all projects for tracing back the quantities of waste to public fill, landfill and designated areas. Data analysis charts are also provided for project team to review. Environmental Performance Data (EPD) will be used to record all waste removed off site each month. The estimated and actual quantities of wastes that will be generated each month from the project will be reported in a monthly basis.

    9.3 Waste Audit

    The waste reduction should be assessed in two ways:

    Project-wise Targeting the waste management on site and seeking out or developing

    ways to divert waste from disposal

    To review the site management, the project-based waste baseline audit should be conducted. By identifying the measures of waste reduction, the facilities support on site and etc, the scoring of baseline audit would reflect the implementation of waste management. A waste baseline audit scorecard was developed to quantify site waste management efforts, shown as Appendix G. A kick-off example and waste management audit schedule are provided in Appendix H. The good practices and difficulties can also be discussed in the audit meeting and presented in the revised version of the waste management handbook.

  • Waste Management Handbook for Building Division Rev. 0

    12

    Building Home The overall waste reduction would be reviewed regularly. The waste data of

    building projects would be used to calculate the landfill waste intensity (tonnes of landfill waste per HK$ 1million turnover). The Interim Review will be carried in mid-2013, end-2013, 2015 and 2017.

    A mix of both approaches should be considered using the waste reduction hierarchy to set priorities.

    10 TRAINING AND PROMOTION

    The environmental engineer shall arrange and provide training on waste management in the site-specific induction and its refresher training for all persons employed by the Contractor or his sub-contractor on the Works or in connection with the Contract. The training should cover the waste management policy, targets, measures for on-site sorting of C&D materials and measurement on waste management performance on the Site.

    The environmental engineer is allowed to develop and provide toolbox talks for the topic on on-site sorting of C&D materials to promote the workers' awareness on handling, sorting, reuse and recycling of C&D materials. Training material for environmental toolbox talks with regard to waste management shall be prepared by the environmental engineer and disseminated to supervisor/foremen and subcontractor's representatives for conducting tool-box talks to all workers or labourers at regular intervals.

    To motivate subcontractors participation, Waste Management Key Performance Index (WMKPI) should be introduced to rank subcontractors on performance indicators tracked across implementation of waste management, Appendix I. Set some standards and common vision so that subcontractors have more understanding of our objectives and follow easily. Project team and Operation team would help in the assessment by reporting subcontractors performance to environmental engineer. The index and rating can be different from each project according its statues. Best subcontractor of the month in waste management could be awarded to praise their effort.

  • APPENDIX A

    Cost saving from waste minimization

  • Cost Saving Breakdown (Building)

    Waste target: 4.13 to 2.89 tonnes/HK$1M Waste saving per HK$1B: 1,240 tonne

    Average loading per truck: 3.5 tonne Each trip to landfill: HK$600 Cost of dumping 1 tonne general refuse: (3.5 x 125)+600 3.5 Cost Saving: HK$300/tonne x 1,240 tonne Cost Saving to achieve target: HK$0.37M for HK$1B project

    Cost of labour: HK$650 / man-day $0.37M $650/man-day

    = $300 per tonne

    = ~ 572 man-day saving

  • APPENDIX B

    Figure of different projects

  • J5201 Tamar Development Project, Hong Kong The works under this contract comprise the design and construction of The Central Government Complex, The Legislative Council Complex, An Open Space and two Elevated Walkways and Associated car parking spaces and ancillary facilities Contract Sum: $4,940,279,465.23 Landfill Waste Intensity: 3.6 tonne/HK$ 1M turnover

    J3286 Centennial Campus, The University of Hong Kong Foundation and construction of two 9-storey and one 10-storey academic buildings with three level basement and three level podiums Construction of West Gate Tower & Footbridge to future MTR station and Open Footbridge Contract Sum: HK$1,968,268,300.00 Landfill Waste Intensity: 5.4 tonne/HK$ 1M turnover

  • J3262 Hennessy Centre Redevelopment The construction of 4 levels carpark/retail basement, 15 floors retail podium and 20 floors office tower Contract Sum: HK$1,736,838,000.00 Landfill Waste Intensity: 5.3 tonne/HK$ 1M turnover

    J3193 Redevelopment of No. 63 Nathan Road The construction of a 32-storeys high retail complex (including 3-storeys of Basement, a Podium of 10-storeys, a Tower of 5-storeys and a Tower of 19-storeys) Contract Sum: HK$1,075,491,247.00 Landfill Waste Intensity: 15.8 tonne/HK$ 1M turnover

  • J3338 Proposed Residential Development at RBL 224, 53 Stubbs Road, The Peak, Hong Kong 12-storey residential building (10-storey super flats & 2-storey duplex units) with swimming pools (2 nos. at podium floor and 3 nos. at roof) Contract Sum: HK$515,138,000.00 Landfill Waste Intensity: 1.6 tonne/HK$ 1M turnover

    J3293 Redevelopment of No. 31 Queen's Road Central The Construction of an office tower including 1 level of basement and 3 levels of podium retail, 1 level of restaurant, 2 of levels of mechanical floor and 21 levels of office. Contract Sum: HK$333,000,000 Landfill Waste Intensity: 3.2 tonne/HK$ 1M turnover

  • APPENDIX C

    Waste generated at different construction stage

  • Site Office Site Hoarding Demolition Site Setup & Demolition Furniture and Containers after use

    Waste concrete

    Building Debris Facilities, Furniture

    Piling Substructure Drainage & Underground works Foundation

    and Underground Works

    Soil, Marine mud Temp wood

    Grouting Cement Bag

    Soil, Marine mud Waste timber

    Packaging waste in ELS

    Soil, Marine mud Cable, cable drum

    Waste concrete, metallic pipe & waste timber

    Formwork Concreting Scaffolding Plastering

    Superstructure Waste timber

    Waste concrete Slump test concrete

    Concrete cube

    Bamboo Metal Scaffold Dust Screen

    Cement Bag Chemical containers

    Waste block Interior / Exterior fitting

    out E&M Installation Curtain wall

    Fitting Out and MEP

    Stone, granite and tiles Fire rated board

    Aluminium product Plywood

    Air duct Insulation

    Trunking and pipe Fitting for E&M services

    Timber packaging

    Miscellaneous Packaging waste

    Wrapping sheet

    Broken concrete

    Plastic (barrier)

    Domestic waste

    C

    o

    n

    s

    t

    r

    u

    c

    t

    i

    o

    n

    P

    r

    o

    j

    e

    c

    t

    T

    i

    m

    e

    l

    i

    n

    e

    C

    o

    n

    s

    t

    r

    u

    c

    t

    i

    o

    n

    P

    r

    o

    j

    e

    c

    t

    T

    i

    m

    e

    l

    i

    n

    e

  • 201

    0 G

    am

    mo

    n Co

    nst

    ruct

    ion

    Li

    mite

    d. Al

    l Rig

    hts

    Re

    serv

    ed

    Miscellaneous

    Office Furniture Container Site hoarding (footing)

    Disused

    facilities / furniture

    Packaging waste

    Plastic (barrier)

    Domestic waste

    Dem

    olitio

    nFacilities

    Setup

    Site Setup

    201

    0 G

    am

    mo

    n Co

    nst

    ruct

    ion

    Li

    mite

    d. Al

    l Rig

    hts

    Re

    serv

    ed

    Substructure

    Underground utilities & drainage

    Temp wood

    Cement bag

    Surplus grout

    Wasted Timber*

    Packaging waste

    Cable, plastic, cable drum Metallic pipe

    Pilin

    g

    Foundation &

    Underground

    works

  • 201

    0 G

    am

    mo

    n Co

    nst

    ruct

    ion

    Li

    mite

    d. Al

    l Rig

    hts

    Re

    serv

    ed

    Form

    wor

    kConcreting

    ScaffoldingPl

    aste

    ring

    & P

    aint

    ing

    Super-

    structure

    Waste timber Waste concrete/

    cement/instant mortar

    Bamboo

    Metal Scaffolding

    Dust screen

    Cement Bag

    Chemical containers waste block wall

    Wooden pallets

    201

    0 G

    am

    mo

    n Co

    nst

    ruct

    ion

    Li

    mite

    d. Al

    l Rig

    hts

    Re

    serv

    ed

    Curtain

    wall

    / glass

    wall

    Interior/ exterior fitting

    Air duct

    Insulation

    Trunking & pipe

    Stone, granite, tiles Fire rated boardPlywood

    Aluminum product

    timber packaging

    Sealant, adhesive

    E&M

    Instal

    lation

    Fitting Out &

    MEP

  • APPENDIX D

    Project Specific Waste Management Plan Template

  • Gammon Construction Limited

    Waste Management Plan

    Template

    for

    Building Project

    COPYRIGHT

    This document is copyrighted by Gammon Construction Limited and may not be reproduced within licence or written permission.

    28/F Devon House, Taikoo Place, 979 Kings Road, Hong Kong

    Tel.: (852) 2516-8823 Fax.: (852) 2516-6260

  • Rev. No. :

    Effective Date :

    Waste Management Plan Template for Building

    Project Page No. i

    Revision Status Sheet

    Rev. No. Effective Date Summary of Revision

  • Rev. No. :

    Effective Date :

    Waste Management Plan Template for Building

    Project Page No. ii

    Contents

    Section Description

    1. Background

    2. Purpose of the Plan

    3. Waste Management Strategies

    4. Organization Structure

    5. Analysis of Waste

    6. Waste Reduction Measures

    7. Approach for Achieving Waste Diversion Target

    8. Training and Incentive

    Appendices Description

    Appendix A Waste Management Key Performance Index

    Appendix B Building Waste Baseline Audit Scorecard

    Figure Description

    Figure 1 Temporary on Site Sorting Facilities

  • Rev. No. :

    Effective Date :

    Waste Management Plan Template for Building

    Project Page No. 1

    1. Background

    Environmental protection and sustainable development are part and parcel of the daily operations of the Gammon Construction Limited (referred to hereinafter as the GCL). GCL will initiate appropriate actions in order to minimize, and where possible eliminate, the environmental impact arising from the construction of this project.

    (Project description)

    2. Purpose of the Plan

    With the baseline of 2007 (4.13 tons per HKD 1M turnover), building division aimed to achieve 30% reduction in landfill intensity by the end of 2018 (2.89 tons per HKD 1M turnover), we must: 1. exercise better planning and design; 2. reduce the waste generated and; 3. reduce sent to landfill by increasing reuse and recycle arrangements

    Set the target for this project is to diverting construction and demolition debris from disposal in landfills and incinerators; redirecting recyclable resources back to the manufacturing process or redirecting reusable materials to appropriate sites. (Please refer to waste management handbook, section 7.2.)

    This Project-Specific Waste Management Plan (WMP) aims to describe the arrangements for minimising the generation of surplus construction and demolition (C&D) materials and carrying out effective on-site sorting of C&D materials and minimising the generation of C&D waste from equipment/material packaging during the course of the Works. The WMP shall address the potential and actual impacts and necessary mitigation measures in light of the preferred construction programme and consists of the following:- A review of the ordinances, regulations, codes of practices as well as contractual

    obligations that are applicable to the wastes arising from the Works; An organisation chart setting out the roles and responsibilities of the Contractors

    personnel responsible for waste management and appropriate mitigation measures;

    An analysis of timing, quantities and types of Construction and Demolition (C&D) materials are anticipated to be generated in the course of the execution of the Works;

    A classification of C&D materials into inert portion (Public Fill) and non-inert portion (C&D Waste);

  • Rev. No. :

    Effective Date :

    Waste Management Plan Template for Building

    Project Page No. 2

    Proposals for avoiding/minimizing, handling, recycling, reuse, return, storage and disposal of C&D materials, chemical waste and general refuse;

    An appraisal of the potential establishment on site of a sorting facility, including the identification of potential area on-site of facilitate the waste sorting;

    A monitoring and auditing proposal to ensure that the requirements of the WMP are properly implemented.

    3. Waste Management Strategies

    3.1 Hierarchy

    The various waste management options shall be categorised in terms of preference from an environmental viewpoint. The options considered to be more preferable have the least impacts and are more sustainable in the longer term. Hence, the hierarchy of waste management is as follows: Rethink is careful planning at the design and drawing stages. It is at this stage

    that the greatest reductions in waste can be achieved.; Reduce waste by eliminating over-ordering of construction materials, waste is

    avoided and costs are reduced both in terms of purchasing of raw materials and in disposing of waste.;

    On site, the Reuse and Recycle of materials should be maximized to avoid Disposal; and

    Treatment and disposal, according to relevant laws, guidelines and good practice.

    This hierarchy shall be used to evaluate waste management options, thus allowing maximum waste reduction.

    4. Organization Structure

    The project organisation with respect to waste management works is outlined in the following sections.

    4.1 Project Manager

    The Project Manager is responsible to the Contract Manager for overall planning, site operations, appointment of committee members for waste management, staff supervision control co-ordination and external liaison. He is ultimately responsible for all aspects of waste management issues within the Project, which they achieve by implementation of the WMH. He is also responsible for provision of necessary support to the environmental engineer for the preparation and review of waste management and arrangement of site staff to

  • Rev. No. :

    Effective Date :

    Waste Management Plan Template for Building

    Project Page No. 3

    attend environmental training with regard to waste management organised by other bodies or the environmental engineer.

    The Project Manager has the following responsibilities in relation to waste management:

    i. Keep abreast of the requirements of the statutory regulations in relation to waste management;

    ii. Ensure works are executed in accordance with the WMH; iii. Arrange routine joint site inspection with environmental engineer and review

    environmental inspection report submitted by the environmental engineer; iv. Ensure appropriate waste management mitigation measures are properly

    implemented; v. Ensure follow up actions are properly undertaken in the event of non-compliance of

    the waste management plan; vi. Review method statement to ensure appropriate mitigation measures are

    implemented prior to execution of work; and vii. Monitor the following documents.

    any statutory required waste management permits/licenses including dumping licence, chemical waste producer, admission ticket and etc;

    C&D material disposal delivery record; and, waste reuse / recycle / disposal summary.

    4.2 Site Agent

    He shall have the following duties in relation to environmental control:

    i. Assist the Project Manager in implementing the waste management plan; ii. Monitor and control the works including those of subcontractors to ensure

    compliance of WMH; iii. Report to the Project Manager regarding non-compliance of any waste

    management issues; iv. Ensure the remedial actions or mitigation measures are carried out as planned;

    and v. Supervise and arrange the maintenance of waste management facilities.

    4.3 Foremen

    Foremen are responsible for the following duties in relation to environmental control:

    i. Assist the Site Agent in implementing the WMH; ii. Control the works including those of subcontractors to fulfil the requirement of

    waste management issues; iii. Report to the Site Agent any non-compliance of any waste management issues; iv. Maintain the on-site waste management facilities including sorting area, temporary

    storage area, general refuse bins, recycling bins and etc; v. Leading task force to do sorting and separation at source, housekeeping, waste

    collection, disposal management in site vi. Carry out remedial actions or mitigation measures to rectify the non-compliance; vii. They shall carry out routine maintenance of waste management facilities.

    Maintenance records shall be kept in site office.

  • Rev. No. :

    Effective Date :

    Waste Management Plan Template for Building

    Project Page No. 4

    4.4 Environmental Engineer

    The Environmental Engineer shall oversee the implementation and the performance of the WMH and shall also be responsible for:

    i. Reviewing works programmes, method statements, licence application and other relevant documentation so as to ensure the best practice would be implemented to generate no unacceptable impacts with respect to waste management to the established guidelines/standards;

    ii. Identifying any potential unanticipated or greater than expected waste impacts; iii. Formulating any necessary preventative or remedial measures to be taken for

    these potential impacts; iv. Liaising and consulting with all relevant parties during implementing WMH; v. Preparing training material for environmental toolbox talks with regard to waste

    management and disseminating guidance notes to operatives.

    4.5 Task Force for Waste Management

    Depending on the size of individual project, task force led by a project coordinator/supervisor provided with direct labours and technically supported by the project environmental team shall implement waste management on site (planning, waste identification of each construction stage, sorting and separation at source, housekeeping, waste collection, disposal management and reporting).

    5. Analysis of Waste

    5.1 Analysis of Waste Generation

    Different types and quantities of waste will be generated throughout the construction period of the Project from various construction activities and daily operation of the construction site. Please refer to Waste Management Handbook, Appendix C

    Construction Phase Activities Predicted Waste Type

    Site setup Site hoarding Demolition

    Waste concrete Building rubbles etc

    Foundation / ELS Protection Grouting Excavation Steel platform

    Temp Wood Cement bag Excavated materails Steel

    (Please insert construction activities involved)

  • Rev. No. :

    Effective Date :

    Waste Management Plan Template for Building

    Project Page No. 5

    6. Waste Reduction Measures

    6.1 Reduce Waste at Source

    This section is the measures taken in Design and Planning Stage and Procurement that is more focusing on Rethink and Reduce. Waste Management Handbook, Section 8 & Appendix E)

    For example, the formworks will be designed to maximise the use of standard wooden panels so that high reuse levels can be achieved. More durable alternatives such as reusable metal formwork, falsework, trench supports and the like shall be optimized for use in repetitive areas to increase the potential for reuse, if applicable.

    Precast unit or pre-fabricated unit is also encouraged to adopt since it will reduce the wastage from the waste generation on site. BIM application is also an effective tool to avoid the wastage due to crushing of E&M services.

    6.2 Management of Construction and Demolition Materials

    All Construction and Demolition (C&D) materials arising from or in connection with the Works will be sorted on the Site to recover reusable and/or recyclable materials. The system will include the identification of waste, estimated quantity, arrangement for on-site sorting and/or collection, temporary storage areas, etc. The temporary on site sorting facilities layout plan for sorting facilities is provided and reviewed regularly, Figure 1.

    Description of the planning of logistic mode, sorting facilities

    Materials should be sorted at source but not limited to the following categories: Hard Rock and Large Broken Concrete suitable for Reuse on the Site or recycling

    at a designated location;

    Residue Concrete

    Metals;

    Paper and plastics;

    Timber waste;

    Chemical waste; and

    Materials suitable for Disposal at Public Fill Reception Facilities and Landfills/Outlying Islands Transfer Facilities.

    The planning of logistic routine for the waste collection from different floor should be considered, refuse chute, jump lift and hoist. Landfill waste, recyclables and inert waste should be transported down separately to avoid contamination.

  • Rev. No. :

    Effective Date :

    Waste Management Plan Template for Building

    Project Page No. 6

    Waste facilities to facilitate on-site sorting, collection and temporary storage of waste materials is continued to maintain. The waste facilities including the following:

    1. Designated area for temporary storage of Inert C&D Material 2. Designated waste skip for temporary storage of non-inert C&D Material 3. Recycling cages for collection of waste metal, plastic and paper. 4. Recycling bins for collection of waste papers, cans and plastic bottles 5. Designated storage area for chemical waste

    Sufficient space for temporary storage of C&D materials will be identified and provided to facilitate collection and/or sorting on the Site. Except for those inert C&D materials to be reused on the Site, all other C&D materials off the Site will be removed as soon as practicable to optimise the use of the on-site storage space.

    As presented in the Waste Management Hierarchy, the GCL accords the highest priority to managing waste through reduction at source. To this end, the following measures shall be implemented.

    Management of construction materials such that over-ordering, poor storage and maintenance, mishandling as well as improper operation procedures shall be avoided;

    Restriction on use of hardwood such that softwood, metal props and/or proprietary steel system shall be considered for falsework and the shoring of trenches and pits;

    The formwork shall be designed to maximise the use of standard wooden panels so that high reuse levels can be achieved. More durable alternatives such as steel formwork or plastic facing shall be considered for repetitive areas to increase the potential for reuse;

    C&D materials shall be, as much as possible and practicable, separated into reusable items and materials to be disposed of or recycled. It shall be conducted at the immediate working area to avoid loss / leakage and cross contamination during handling;

    All C&D materials arising from or in connection with the construction and demolition work shall be sorted on-site and be separated into different categories for disposal at landfills, public filling areas, or reuse and recycling as appropriate. The sorting area may be revised from time to time in order to suit the construction activities;

    Useful materials such as timber, rubble and steel / metal shall be segregated for reuse. For example formwork and timber shall be cleaned for reuse, off-cuts of reinforcement shall be sorted into usable lengths and short off cuts stacked for scrap metal. Where it is no longer reusable, scrap steel and metal items will be collected by recycling companies;

    Segregated materials shall be temporarily stored at designated areas for reuse on site. Steel will be stored at the reinforcement yards, timber at the formwork yard and rubble in a stockpile (either covered or sprayed to control dust). Cardboard and paper packaging recovered from site shall be properly stockpiled in dry condition and covered;

    The remaining non-reusable C&D materials shall be sorted on-site into the inert portion (e.g. rock, brick, bituminous material, concrete and soil, etc.) as the public fill and the non-inert portion (e.g. timber, vegetation and paper, etc.) as the C&D waste. All inert C&D materials shall be broken down according to the

  • Rev. No. :

    Effective Date :

    Waste Management Plan Template for Building

    Project Page No. 7

    Dumping License conditions prior to disposal to government approved public filling outlets. The hard inert construction and demolition (C&D) materials, such as broken rock and concrete which can be recycled into aggregates for reuse in construction works, shall be delivered to the C&D material sorting and recycling facility at Chai Wan Barging Point. The non-recyclable portion of C&D waste (containing no more than 30% by weight of inert content) shall be tipped at the landfill such as SENT Landfill. Recycling companies will be arranged to collect the recyclable portion of C&D waste;

    In order to avoid over-order of concrete, accurate calculation shall be made prior to concrete pouring. Close supervision shall also be arranged during concrete pouring to avoid over-cast; and

    Surplus concrete shall be used for paving of temporary road or cast of concrete blocks for bunding etc. as far as practicable. In case immediate use of surplus concrete cannot be identified, the surplus concrete will be temporarily poured into designated surplus concrete pouring areas on site for further disposal to public filling areas.

    Materials suppliers could take back surplus materials and packing materials.

    (Please inert appropriate measures adopted on site)

    6.3 Cut and Fill Balance of Inert Waste

    In order to maximize the reuse of surplus inert construction waste generated from the site, team will strike for reusing excavated material as back fill material to balance cut and fill on site. If cut and fill could not be balanced on site, team will try their best endeavour to identify the alternative disposal site (i.e. other construction project) in order to reuse surplus inert C&D material.

    6.4 Recycling

    To minimise the amount of waste disposal to landfills, the general refuse shall be reused and recycled as much as practical. Waste sorting and segregation shall be carried out in accordance with the following categories for recycling:

    Steel Bars

    Plastic (i.e. plastic bag, plastic bottle, plastic packaging, etc.) Rubber;

    Paper;

    Wood/ timber; and

    Metal (i.e. aluminium can, steel metal, ferrous metal, and non-ferrous metal).

    Equipment and material packaging (ie paper and cardboard) will be recovered, properly stockpiled in dry and covered condition to prevent cross contamination by other C&D materials. Particular attention will be paid to avoid cross contamination in the course of collecting paper for recycling. Arrangements will be made with recycling contractors to ensure that recyclable materials sorted from the Site are collected with reasonable care.

  • Rev. No. :

    Effective Date :

    Waste Management Plan Template for Building

    Project Page No. 8

    Proposed types of waste facilities, waste handler and collection frequency are given below. (Please refer to Waste Management Handbook, Section 7.3 and Appendix D) Waste Categories Waste handler* Treatment approach Collection Frequency**

    General packing waste

    Confidential Materials Destruction Service Limited or other recycled company registered under EPD for collection of waste paper

    Sorted into groups of metal, paper and plastic and collect for recycling.

    Once the bins are filled.

    Wastage of steel Subcontractor to collect scrap metals.

    Scrap metals/steel bars will be collected and send to EPDs register recycle company for recycle purpose.

    Once the temporary steel storage bins/areas are filled

    Surplus concrete Gammon All excess concrete would be reused for consolidate the haul road within site or return to concrete plant for recycling.

    Once the concrete work begin.

    Timber Hong Kong Hung Wai Artifical Board

    Timber should be collected by timber recycle plant for recycle.

    After

    Plastic Yai Oi Tong EcoPark Plastic Resources Recycling Center or other recycler approved by EPD

    Plastic should be collected by the recycler and reuse.

    Once the bin is filled.

    * The waste handler will be reviewed and updated if necessary.

    * Recycle material will be collected by EPD approved recycler. If the approved recycler is not available, Gammon will submit to EPMs review and approval.

    7. Approach for Achieving Waste Diversion Target

    7.1 Internal Inspection and Review

    In order to facilitate successful achievement for the Project, the following action will be implemented:

    Regular Internal Inspection will be arrange to inspect the site to ensure satisfactory performance on compliance with the WMP;

    Bi-weekly Environmental and Sustainability Meeting will be carried out with Executive Project Manager, Lead Design Consultant, Sustainability Consultant, Environmental Consultant and the Gammon's Representative in review the progress of LEED and BEAM Plus;

  • Rev. No. :

    Effective Date :

    Waste Management Plan Template for Building

    Project Page No. 9

    Regular Meeting with the Subcontractor to discuss the implementation status of WMP;

    Training related to waste management of the project will be provided to the operation team to increase their awareness;

    Closely monitor the recycling rate to ensure successful outcome of achieving recycling rate.

    7.2 Record Keeping and Reporting

    All waste treatment (i.e. recycle, reuse etc) should be properly recorded by receipt, photo, delivery form and summary, supporting document should also be provided for individual waste.

    Smart Waste Account was introduced to all projects for tracing back the quantities of waste to public fill, landfill and designated areas. Data analysis charts are also provided for project team to review. Environmental Performance Data (EPD) will be used to record all waste removed off site each month. The estimated and actual quantities of wastes that will be generated each month from the project will be reported in a monthly basis.

    7.3 Waste Audit

    To review the site management, the project-based waste baseline audit will be conducted quarterly. Project shall be audited by a committee though site visit. A waste baseline audit scorecard was developed to quantify site waste management efforts, shown as Appendix A. By identifying the measures of waste reduction, the facilities support on site and etc, the scoring of baseline audit would reflect the implementation of waste management.

    8. Training and Incentive

    The Environmental engineer shall be arranged to attend training on waste management organised by training institutes or organisations as considered appropriate.

    The EE shall arrange and provide training on waste management in the site-specific induction and its refresher training for all persons. The training should cover the waste management policy, targets, measures for on-site sorting of C&D materials and measurement on waste management performance on the Site.

    The EE is allowed to develop and provide toolbox talks for the topic on on-site sorting of C&D materials to promote the workers' awareness on handling, sorting, reuse and

  • Rev. No. :

    Effective Date :

    Waste Management Plan Template for Building

    Project Page No. 10

    recycling of C&D materials at regular intervals. The record of the toolbox talk training record will be presented in the monthly environmental report.

    Environmental Promotion and Incentive (such as the supermarket coupon) to encourage good waste management performance on site. Waste Management Key Performance Index (WMKPI) was introduced to rank subcontractors on performance indicators tracked across implementation of waste management, Appendix B.

  • Appendix A Building Waste Baseline Audit Scorecard Waste

  • Appendix B Waste Management Key Performance Index

  • Figure 1 Temporary on Site Sorting Facilities

  • APPENDIX (

    Waste Recycling Companies / Charities

  • Waste Contacts Services & charges 3R Hong Kong International Eco-Action Limited Mr. Thomas Ng Phone: 8203 8508 Email: [email protected] Website: www.3r.com.hk

    (a) Frequency: ad hoc, need to contact Mr Thomas Ng two days in advance to confirm availability of space (b) Transport: self-transport of waste to 3R warehouse at Fanling (c) Fee: free of charge for self-transport waste. (d) Collection: could be arranged with charges on each order subject to site visit.

    Not accept: cement bag

    Paper

    Fook Woo Waste Paper Company Limited Ms. Sandy Fung Phone: 2676 8800

    (a) Each job / location to submit application form to open account. (b) provide nylon bag/ cage for waste collection free of charge (c) Transport: to be collected by Fook Woo. (d) Frequency: need to be agreed with the collection schedule to arrange staffing logistics. (f) Record: can provide monthly report upon request.

    Not accept: cement bag 3R Hong Kong International Eco-Action Limited Mr. Thomas Ng Phone: 8203 8508 Email: [email protected] Website: www.3r.com.hk

    Fook Woo Waste Paper Company Limited Ms. Sandy Fung Phone: 2676 8800

    Procedures are same as above

    Not accept: Plastic waste mixed with inert waste PVC Thick plastic pipe

    Plastic

    Yan Oi Tong EcoPark Plastic Resources Recycling Centre Ms Kit Hui Phone: 2212 5811 Email: [email protected] Website : http://prrc.yot.org.hk/

    (a) Each job / location to submit application form to Yan Oi Tong to open account. (b) Yan Oi Tong will provide suitable bin / metal cage for plastic waste collection free of charge subject to its availability and approval by Yan Oi Tong. (c) Transport: self-transport plastic waste to Yan Oi Tong. (d) Frequency: need to contact Yan Oi Tong 2 days in advance to arrange staffing logistics. (e) Fee: HK$27 weight bridge charge waived for Gammon accounts. (f) Record: can provide monthly report upon request.

  • Condition of materials: Minor concrete or grouting on materials is accepted separated each type of plastic

    Not accept:

  • APPENDIX )

    Detailed Waste Reduction Measures

  • Construction stage Activities involved Type of Landfilled

    Waste Generated

    Corresponding measures to reduce waste or recycling BEAM Plus / Green & Caring Guideline Possible Cost involved

    Tendering and planning

    stage

    Planning for site setup and

    facilities

    N/A 1. Plan to provide sufficient waste sorting facilities for different type of waste

    2. Reserve task force to carry out the collection and sorting of waste

    3. To determine the recycler for collection

    4. To plan the logistic for the waste collection and recycling from different floor, e.g. Refuse

    chute,jump lift or hoist

    5. Modular design for design and build project

    6. Use of BIM to reduce abortive work

    7. Use of LCC/LCA estimation model

    8. Use of prefabricated elements

    BEAM Plus MA P3 Construction and Demolition

    Waste Management Plan

    submit tender documents, contract conditions and

    specifications to demonstrate that the contractor was

    required and able to prepare and implement a waste

    management system

    how materials are recovered for collection by

    recycling contractors; and

    how waste from c&d works is sorted to recover

    broken concrete and other inert non-metallic

    materials

    GnC Newsletter Jun 2011

    Innovation - Planning ahead - avoid unnecessary

    wastage

    a. Recycling bins, refuse chutes

    b. Cost per worker x no of workers

    c. Transportation cost

    d. Cost for recycling

    e. Lift, hoist or chutes

    a. Site office 1. Furniture 1. Reuse furniture from other project and/or for NGOs

    2. buy 2nd hand furniture if possible

    3. send to other site or charity during demolish site office

    Transporation cost

    2. container 1. Reuse containers from other project

    2. buy 2nd hand products if possible

    3. send to other site after use

    b. Site hoarding 3. Waste concrete from

    footing

    1. Reuse footing from other project

    for concreting

    2. To well plan the order quantities

    3. To reuse the concrete for road paving or any other means

    4. To sort out with non-inert waste

    5. Directly send back to concrete plant for recycling

    c. Demolition 4. facilities / furniture 1. send to charity and/or to other projects for reuse GnC Newsletter Jun 2011

    Best Practice - Waste turns into resources

    a. Protection 1. Temp wood 1. Replaced by durable protection, e.g. metal pad

    2. Provision of waste sorting containers for timber waste

    3. Reserve task force to carry out the collection and sorting of waste

    4. Provision of recycler to collect

    a. Recycling container ($300/month)

    b. Cost per worker x no. of workers

    c. Transporation cost ($600/track)

    b. Grouting 2. Cement bag for grouting 1. Provision of waste sorting bins for general refuse

    2. Reserve task force to carry out the collection and sorting of waste from others

    3. Precise order of cement

    a. Waste container

    b. Cost per worker x no. of workers

    c. Free / transporation cost ($600/track)

    3. Surplus grout 1. To sort out from non-inert waste a. Waste container

    b. Cost per worker x no. of workers

    c. Free / transporation cost ($600/track)

    c. Excavation 4. Soil / Marine mud 1. reduce and/or recycle marine mud for backfilling and/or mud bricks

    a. Pile Cap 1. Wasted Timber (hard &

    softwood) from formwork

    1. Use of metal formwork to reduce the timber waste

    2. Reuse timber as many as possible

    3. Remove the nails before reycycle

    3. Provision of waste sorting containers for timber waste

    4. Reserve task force to carry out the collection and sorting of waste

    5. Provision of recycler to collect

    a. Recycling container for timber formwork

    b. Cost per worker x no of workers

    c. Transporation cost ($600/truck)

    d. Use of metal formwork

    b. ELS 1.) Packaging waste for

    welding

    1. Provision of waste sorting bins for packaging waste

    2. Reserve task force to carry out the collection and sorting of waste

    3. Provision of recycler to collect

    4. Selection of bulk quantities per pack to reduce packing materails.

    a. Recycling bins (Free)

    b. Cost per worker x no. of workers

    c. Free / transporation cost ($600/track)

    c. Excavation 4. Soil / Marine mud 1. reduce and/or recycle marine mud for backfilling and/or mud bricks

    a. Utilities Cable, plastic, cable drum

    from cable laying works

    1. Provision of waste sorting bins for cable waste

    2. Reserve task force to carry out the collection and sorting of waste

    3. Provision of recycler to collect

    4. Precise order of utilites

    a. Recycling bins (Free)

    b. Cost per worker x no. of workers

    c. Free / transporation cost ($600/track)

    b. Drainage works (manhole

    & pipe)

    Concrete / metallic pipe &

    timber waste

    1. Provision of waste sorting bins for timber waste

    2. Reserve task force to carry out the collection and sorting of waste

    3. Provision of recycler to collect

    4. Precise order of drainage materials (pipe, concrete and timber)

    a. Recycling bins (Free)

    b. Cost per worker x no. of workers

    c. Free / transporation cost ($600/track)

    c. Excavation 4. Soil / Marine mud 1. reduce and/or recycle marine mud for backfilling and/or mud bricks

    a. Formwork 1. Waste timber from

    formwork

    1. Use of metal formwork to reduce the timber waste

    2. Precise ordering

    3. maxmize to reuse the timber fomwork or change to system formwork

    4. Restricted the s/c to collect the timber for reuse (>1m)

    5. Provision of waste sorting bins for timber waste

    6. Provision of task force to carry out the collection and sorting of waste

    a. Recycling bins

    b. cost per worker x no of workers

    c. Transporation and handling free for recycling

    d. Use of Metal formwork

    b. Concreting 2. Waste concrete 1. Using precast units

    2. To well plan the order quantities

    3. To reuse the concrete for road paving or any other means

    4. Directly send back to concrete plant for recycling

    5. To sort out with non-inert waste before disposal

    6. Reuse slunp test concrete and crushing concrete cube for backfilling

    7. Recycle broken concrete and rock pieces to form recycled aggregates to be used in between pile

    caps and footing

    BEAM Plus MA 3 Prefabrication

    1 credit when the manufacture of 20% of listed

    prefabricated building elements

    2 credits where the manufacture of 40% of listed

    prefabricated building elements

    facades; staircases; slabs; balcony/utility platform;

    parapet; partition walls; bridge-decks; and

    footbridges.

    a. task force for sorting concrete waste

    b. Service charge returning of waste concrete

    d. A statement from the Contractors quantity surveyor that confirms the quantity of timber used in

    the Temporary Works.

    e. Evidence from the Contractor to confirm the quantity and types of timber supplied to the Site were

    installed in the project.

    c. curtain wall / glasswall 3. timber packaging 1. maxmize to use the metal frame for protection

    2. Precise ordering

    3. Provision of waste sorting bins for timber waste

    4. Provision of task force to carry out the collection and sorting of waste

    a. Recycling bins

    b. cost per worker x no of workers

    c. Transporation and handling free for recycling

    d. Use of Metal frame

    d. Scaffolding 4. Bamboo 1. Replaced by metal scaffolding

    2. Restricted s/c to collect the bamboo for reuse

    2. Provision of waste sorting bins for general refuse

    3. Reserve task force to carry out the collection and sorting of waste from others

    Substructure Stage

    Drainage works &

    underground works

    Site setup

    RC Structure

    Foundation stage

    Page 1 of 2

  • Construction stage Activities involved Type of Landfilled

    Waste Generated

    Corresponding measures to reduce waste or recycling BEAM Plus / Green & Caring Guideline Possible Cost involved

    5. Metal Scaffolding 1. Ensure materials are handled and stored in good condition to prevent deterioration and wastage

    2. Restricted the s/c to collect for reuse

    3. Provision of waste sorting bins for metal recyling

    4. Reserve task force to carry out the collection and sorting of waste from others

    6. Dust screen 1. Provision of waste sorting bins for general refuse

    2. Reserve task force to carry out the collection and sorting of waste from others

    a. Plasting works 1. Cement Bag 1. Provision of waste sorting bins for general refuse

    2. Reserve task force to carry out the collection and sorting of waste from others

    3. Precise order of cement

    a. containers for general refuse

    b. cost per worker x no of workers

    c. Transporation and handling free for disposal

    2. empty plastic

    containers (admixture)

    1. Provision of chemical waste containers

    2. Reserve task force to carry out the collection and sorting of waste from others

    3. Precise order of chemicals

    a. containers for chemical waste

    b. cost per worker x no of workers

    c. Transporation and handling free for disposal

    3. Joint filler 1. Provision of waste sorting bins for general refuse

    2. Reserve task force to carry out the collection and sorting of waste from others

    3. Precise order of product

    a. containers for general refuse

    b. cost per worker x no of workers

    c. Transporation and handling free for disposal

    b. Painting 4. empty paint cans 1. Provision of chemical waste containers

    2. Reserve task force to carry out the collection and sorting of waste from others

    3. Precise order of chemicals

    a. containers for chemical waste

    b. cost per worker x no of workers

    c. Transporation and handling free for disposal

    c. Block wall 5. waste block wall 1. Precise order of product

    2. Provision of waste sorting bins for inert waste

    3. Reserve task force to carry out the collection and sorting of waste from others

    a. containers for general refuse

    b. cost per worker x no of workers

    c. Transporation and handling free for disposal

    d. Gysum block 6. Gysum 1. Precise order of product

    2. Provision of waste sorting bins for gerenal refuse

    3. Reserve task force to carry out the collection and sorting of waste from others

    E&M services installation 1. Air duct 1. Provision of waste sorting bins for air duct

    2. Reserve task force to carry out the collection, sorting of waste and removing insulation

    3. Provision of recycler to collect

    4. Precise order of ducting

    a. Recycling bins (Free)

    b. Cost per worker x no. of workers

    c. Free / transporation cost ($600/track)

    2. Insulation 1. Provision of waste bins for general refuse

    2. Reserve task force to carry out the collection and sorting of waste from others

    3. Precise order of product

    a. containers for general refuse/refuse chute

    b. cost per worker x no of workers

    c. Transporation and handling free for disposal

    3. Truking & pipe

    4. Fitting for E&M services

    1. Provision of waste sorting bins for truking/pipe

    2. Reserve task force to carry out the collection and sorting of waste

    3. Provision of recycler to collect

    4. Precise order of ducting

    GnC Newsletter Oct 2012

    Dust suppression sprinklers using recycled plastic

    pipes and attachments

    a. Recycling bins (Free)

    b. Cost per worker x no. of workers

    c. Free / transporation cost ($600/track)

    Interior / exterior fitting out 1. Stone, granite, tiles 1. Precise order and distribution of product

    2. Provision of waste bins for general refuse

    3. Reserve task force to carry out the collection and sorting of waste from others

    a. containers for general refuse/ refuse chute

    b. cost per worker x no of workers

    c. Transporation and handling free for disposal

    2. Fire rated board 1. Provision of waste bins for general refuse

    2. Reserve task force to carry out the collection and sorting of waste from others

    3. Precise order of product

    a. containers for general refuse/ refuse chute

    b. cost per worker x no of workers

    c. Transporation and handling free for disposal

    3. Plywood 1. Provision of waste sorting bins for timber product

    2. Reserve task force to carry out the collection and sorting of waste

    3. Provision of recycler to collect

    4. Precise order of timber

    a. Recycling bins (Free)

    b. Cost per worker x no. of workers

    c. Free / transporation cost ($600/track)

    4. Aluminum product

    cladding / ceiling

    1. Provision of waste sorting bins for Al

    2. Reserve task force to carry out the collection and sorting of waste

    3. Provision of recycler to collect

    4. Precise order of Product

    a. Recycling bins (Free)

    b. Cost per worker x no. of workers

    c. Free / transporation cost ($600/track)

    Builders, fitting out, E&M 1. Packaging waste 1. Provision of waste sorting bins for paper packaging

    2. Reserve task force to carry out the collection and sorting of waste

    3. Provision of recycler to collect

    4. Deal with supplier for bulk packing

    a. Recycling bins (Free)

    b. Cost per worker x no. of workers

    c. Free / transporation cost ($600/track)

    2. Sealant, adhesive 1. Provision of waste sorting bins for plastic container

    2. Reserve task force to carry out the collection and sorting of waste

    3. Provision of recycler to collect

    a. Recycling bins (Free)

    b. Cost per worker x no. of workers

    c. Free / transporation cost ($600/track)

    3. Waste wooden pallets 1. Provision of waste sorting area for wooden pallets

    2. Reserve task force to carry out the collection

    3. Deal with supplier to collect

    4. Deal with supplier to change the pallet from timber to metal/plastic

    E&S Newsletter Aug 2011

    a. Cost per worker x no. of workers

    4. Plastic (barrier) 1. Provision of waste sorting bins for plastic container

    2. Reserve task force to carry out the collection and sorting of waste

    3. Provision of recycler to collect

    E&S Newsletter Aug 2011 a. Recycling bins (Free)

    b. Cost per worker x no. of workers

    c. Free / transporation cost ($600/track)

    5. Domestic waste 1. Provision of waste sorting bins for domestic waste, 3 color recycling bins & general refuse bin

    2. Workers having lunch in restricted areas

    E&S Newsletter Aug 2011

    Mis

    Plastering

    E&M installation

    Fitting Out

    Page 2 of 2

  • APPENDIX *

    Building Waste Baseline Audit Scorecard

  • Building Waste Baseline Audit Checklist (v.1) P.1

    Building Division Waste Baseline Audit

    Job no.: __________________________ Date: __________________________ Audit team: __________________________

    For those question rated as Yes, please score from 1 to 3. (1 Unacceptable, 2 General, 3 Excellent,). For those question rated as No, please score 0.

    % score = (Actual score / Total score) x 100%

    Waste Management Planning and Management Item Description (Yes / No / NA) Score

    1 Project Waste Management Plan establishment (Specific )

    2 Waste prevention and minimization achieved through designs or addressed in the shop drawings

    3 Waste reduction achieved through Modular Building design and Precasting/prefabrication of construction components

    4 Better Site and Logistic Planning in consideration of waste management

    5 Setting of waste diversion targets according to BEAM Plus/LEED

    6 Waste sorting, storage, collection and disposal planning

    7 Manpower Planning for waste management (Subcontractors and/or task force)

    8 Regular review in internal meetings/SSEC/SSEMC

    9 Training and education of project waste management

    10 Promotion and incentives to stakeholders for enhancement of waste management

    11 Supply Chain Initiatives and procurement strategies

    12 Innovation in preventing waste generation

    13 Proper Recording and Reporting System in place

    Sub-total

  • Building Waste Baseline Audit Checklist (v.1) P.2

    Review of Waste Reduction Item Description (Yes / No / NA) Score

    1 Benchmarking for waste reduction (typical wastage rates of a product or material)

    2 Preventing waste from being produced (waste reduction planning including prevention of over-ordering)

    3 Achievement of Green Building Standards for waste reduction

    4 BIM Application (e.g. according to the scope of application)

    Sub-total

    Waste Reduction for High-rise Building Project (>10 floors) Item Description (Yes / No / NA) Score

    1 Measures to allocate sorting and waste storage / collection space on each floor

    2 Measures to regulate period of waste collection and disposal

    3 More Specific Measures to enhance waste management

    Sub-total

    Waste Receptacles & Usage Item Description (Yes / No / NA) Score

    1 Sub - contractors keep all the working areas clean and regularly deposit rubbish in bins

    2 Adequate and labeled waste bins are provided within close proximity of all work fronts

    3 Ensure all waste bins are emptied frequently and no evidence of overloading

    4 Pro-active efforts/actions to coordinate with other projects for reuse of materials/equipment

    5 Any specific vertical logistic model or facilities for waste collection

    6 Waste separated into inert waste, non-inert waste, recyclables and chemical waste

    Engage different recycler to collect different types of waste Timber: wooden pallet, timber protection Inert waste: concrete, rock Metal: trunking, cladding Paper: packing, office paper

    7

    Plastic: packing, barriers 8 Specific facilities adopted to facilitate the waste collection or recycling

    (e.g Different types of container / bins )

    9 Adoption of KPI system for awarding good performance subcontractors

    Sub-total

  • APPENDIX +

    Project-base Waste Management Kick-off and Audit Schedule

  • Kick-off meeting regarding Waste Management Handbook Application

    Date: Time: Venue:

    1 March 2013 9:00a.m. to 11:00a.m. Seymour Road Conference Room

    Present: Mr. Vincent YUEN Mr. Percy CHAN Mr. Sherman TANG Mr. Jason FUNG Ms. Selina CHIN

    (VY) (PC) (ST) (JF) (SC)

    Item Description Action 1 Data analysis The landfill waste data of Seymour Rd project and Shiu Fai Terrace was

    analyzed. The forthcoming activities were discussed to predict the types and amount of waste generation.

    Note

    2 Difficulties of waste management/reduction at High-rise residential development sitting on congested site

    ST and JF expressed that they have several difficulties to tackle with in waste management.

    - limited space on site access level for waste collection and cart away - no buffer area to be provided for temporary waste storage - only one refuse chute cannot cater for vertical transportation of

    sorted/separated waste. Proper time schedule has to be sought for waste management

    - since each residential unit on each floor is not sizable enough to allow for proper waste sorting and segregation

    - only small quantities of inert waste/other waste generated each day which cannot fully load one dump truck for disposal

    3 Developing Centralized Collection Project managers stated that they have to store inert waste / recyclables

    for long time in site as the quantities is low. Developing a centralized collection was suggested. A dump truck was hired by Building Home to collect inert waste / recyclables from different projects.

    PC

    There is a concern about the trip ticket issue since it would involve different projects.

    Post-meeting note: After clarified with EPD, centralized collection is only possible for those project with contract sum below $1M (small scale - fitting out), for those project / construction site with large than $1M, it is necessary to apply their own billing account with using their own chit ticket and can not be shared with other project and it is all required under Waste Disposal (charges for Disposal of construction Waste) Regulation.

    4 Details of Recycling Companies Managers suggested that details of recycling companies should be stated

    in Waste Management Handbook - type and condition of waste they accept - any pick-up service provided - service charging

    SC

  • 5 Site Walk

    The vehicle access Materials Storage Area on G/F

    Congested site area Temporary storage of landfill waste

  • Tai Hang figure for reference

    Seymour Road current figure

    Shiu Fai Terrace current figure

  • Tentative Schedule for On-site Waste Audit

    Job Project Name Start End Tentative Schedule J3478 Construction of Lower Ngau Tau Kok Estate Redevelopment Phases 2 & 6,

    Demolition and Minor Works at Tung Tau Estate Redevelopment Phase 8, Alteration & Addition Works at Homantin Estate

    25 Feb 13 24 Apr 15 Week 2 of April 13*

    J3482 Site Formation, Foundation and Superstructure Works for Proposed House Development at Lot No. 724 & 726, Cheung Sha, Lantau Island

    17 Jan 13 21 Apr 15 Week 3 of April 13*

    J3500 Main Contract for the Proposed Residential Development at No.8 Mount Nicholson Road, Hong Kong

    TBC TBC Week 4 of April 13*

    J3466 Development of Hong Kong Science Park Phase 3a & 3b 20 Jun 12 1 Dec 13 Week 1 of May 13 J3463 Construction of Public Rental Housing Development at Lei Yue Mun Phase 3

    (Contract No. 20110025) 3 Jul 12 2 Aug 15 Week 2 of May 13

    J3437 Proposed Redevelopment The Forum, Exchange Square Superstructure (GMP) Contract

    11 Jun 12 22 Dec 13 Week 3 of May 13

    J3416 Central Police Station Conservation and Revitalisation Project 1 Jul 11 30 Jun 14 Week 4 of May 13 J3389 Construction of an Annex Building at the Ko Shan Theatre 21 Jan 11 19 Jan 13 Week 5 of May 13 J3383 SS X301 Redevelopment of Kwun Tong Swimming Pool Complex and Kwun Tong

    Recreation Ground Section 2 17 Dec 10 14 Sep 14 Week 1 of June 13

    J3470 TaiKoo Place Phase 2A Advanced Work 30 Jul 12 9 Jul 13 Week 2 of June 13 J3448 Main Contract Works for Proposed Redevelopment at 12 Shiu Fai Terrace Hong

    Kong 9 Mar 12 1 Jul 13 Week 3 of June 13

    J3456 Proposed Residential Development at 33 Seymour Road, Hong Kong 18 Jan 12 13 Oct 14 Week 4 of June 13 J3409 J3408

    Term Contract for Alteration and Addition Works at Happy Valley Racecourse of the Hong Kong Jockey Club for Year 2011 - 2014

    30 May 11 29 May 14 Week 1 of July 13

    J3299 SS T333 - Redevelopment of Victoria Park Swimming Pool Complex Section 2-5 23 Nov 09 31 May 14 Week 2 of July 13

    * Kick-off meeting would be conducted with new projects

  • APPENDIX ,

    Waste Management Key Performance Index (WMKPI) Template

  • Project: Month:_________ Year Subcontractors A B C D E F G Adequate?

    (Y/N) Adequate?

    (Y/N) Adequate?

    (Y/N) Adequate?

    (Y/N) Adequate?

    (Y/N) Adequate?

    (Y/N) Adequate?

    (Y/N) Common accesses are free of obstruction

    Proper storage and stacking of materials / Waste

    Are materials stored in good condition to avoid damage and wastage

    Reuse materials / sent to other projects for reuse

    Collect the exact amount of materials and return the surplus to stock

    Appoint recyclers to collect your own waste materials

    Proper sorting of waste materials

    Disposal of waste materials regularly in designated location

    Domestic waste shall be bagged and removed from site

    Total

    Comment