Waste Isolation Pilot Plant Compliance Certification Application … - W/Thorne... ·...
Transcript of Waste Isolation Pilot Plant Compliance Certification Application … - W/Thorne... ·...
Waste Isolation Pilot Plant
Compliance Certification Application
Reference 625
Thome, B.J., and D.K. Rudeen, 1980. Regional Effects of TRU Repository Heat, SANDS0-7161, Albuquerque, NM, Sandia National Laboratories.
Submitted in accordance with 40 CPR §194.13, Submission of Reference Materials.
I I r r r r I I I I I I I I I I I I I
THORNE,M BILLY JOE RUDEEN, D.K.
1980 REGIONAL EFFECfS OF TRU REPOSITORY
HEAT SANDS0-7161
scteNce APPIIcanoNS
INCORPORateD
I
J
--~
SAND 80-7161 csi 2053-05
Unlimited Release Printed Jan 1981
REGIONAL EFFECTS OF
TRU REPOSITORY HEAT
LONG-TERM REGULATORY COMPLIANCE
Billy Joe Thorne D. K. Rudeen
Prepared for
Sandia Laboratories P. 0. Box 5800
Albuquerque, N. M. 87185
Prepared by
Civil systems, Incorporated (CSI) 505 Marquette, N. W.
Albuquerque, N. M. 87102 (505) 247-8787
Contract No. 13-4435
INTRODUCTION
A modification of a calculation reported in Reference 1
was used to estimate the impact of heat from a 730,000 m2
(180 acre) 0.69 W/m 2 (2.8 kW/acre) RH TRU repository at the
WIPP site. The original calculation, reported in SAI-FR-145,
was designed to estimate the effect of a 81,000 m2 (20 acre)
7.4 W/m 2 (30 kW/acre) spent fuel repository. This calculation
is on much too coarse a scale to accurately predict details
of the response. However, estimates obtained by this method
are ac~urate enough to determine whether or not heat effects
are large enough to justify more finely zoned calculations.
COMPUTATIONAL SETUP
All materials models, boundary conditions, initial condi-
tions and computing techniques were identical to those described
in Reference 1. The initial temperature distribution (Figure la)
is a piece-wise linear solution to the equilibrium equations
completely determined by the surface and bottom boundary tern-
perature. Only five significant figures of the equilibrium
solution were used for initial temperatures. For the calculation
in Reference 1, this was adequate. However, the heat source
in this calculation is so weak that initial temperatures should
have been set accurate to at least 12 significant figures. The
damping was changed to w0
= 5 x 10 11 and the initial time step
1D.E. Maxwell, K.K. Wahi, B. Dial, The Thermomechanical Response of WIPP Repositories, Science Applications, Inc., SAI-FR-145, Sandia National Laboratories, SAND 79-7111, May 1980.
,~was reduced to 1 x 10 6 s (11.6 days) in order to restrict any
numerical oscillations to early time.
The major change required was a modification of the size
of the first three zones in from the center line to give a disk
area of 730,000 m2 (180 acres) to approximate the repository
size. This resulted in using zones with a 160-m radial dimension
(Figure lb). With the 151-m vertical dimension of the zone at
the 637 m (2100 feet) depth of the repository this gives a volume
of 12 million m3 (430 million cubic feet) for the center repository
zone. Thus heat in the center repository zone is spread out over
26 x 10 9 kg (290 million tons) of salt. This averaging effect
causes the peak calculated temperature to be much lower than
would be expected in a drift of the repository.
The heat source used was taken from a Sandia-Labs-provided
list of the thermal power produced by various actinides and fission
products expected to be in RH TRU wastes. The first 200 years of
the normalized decay curve is given in Figure 2. In order to
show more detail, Figure 3 gives a log-log plot of this curve
to 10,000 years assuming a start date of 10 years (since 0 can-
not be used as a reference on log paper). Emplacement density
is assumed to yield a 0.69 W/m 2 (2.8 kW/acre) initial power
density.
SOMPUTATIONAL RESULTS
The peak temperature rise of 1.6°C occurs in the central re
pository zone at 80 years (Figure 4). With such a small tempera
ture increase in the hottest source zone it is clear that the
total impact of heat will be small. This is confirmed by the
0.25°C peak temperature rise at the top of both the Salado and
the Rustler Formations (Figures 5 & 6).
In the surface zone the temperature rise is so small
(0.03°C) that a 0.006°C temperature drop is significant in Figure 7.
This smarl change in temperature is the result of the grid moving
into temperature equilibrium from initial conditions that were
in equilibrium to 5 significant digits. This initial tempera
ture drop resulted in a small downward motion of the grid which
must be taken into account when estimating uplift.
The top of the central repository zone reaches its peak
uplift of 10.4 mm at 200 years (Figure 8). At 1000 years Figure
8 indicates an uplift of 4.3 rnm. However, Figure 9 indicates that
far outside zones of the grid have moved down 2.1 mm because of the
temperature drop resulting from inaccuracies in the equilibrium
temperature. Thus the effective uplift at 1000 years is 6.4 mm.
By 1500 years (~igure 10) the effective uplift has dropped to
5.4 mm of which more than half is masked by the downward motion
resulting from the grid coming into equilibrium more accurately.
-----~~·----·--···-·····-····-··--·-· ~----------
Figures 11 thru 16 give uplift profiles at 1000 and 1500
years for the top of the Salado (Figures 11 & 12), the top of
the Rustler (Figures 13 & 14) and the surface (Figures 15 & 16).
In all cases uplift is much smaller than for the 730,000 m2
( 2 0 acre) 7. 4 ~J/m 2 ( 3 0 kl-7/acre) spent fuel re;,osi tory modeled
in Reference 1 (Figure 17). Even though the initial energy-de
position rate in the TRU repository is 84 percent of the energy
deposition rate in the spent fuel repository, the TRU-waste heat
output falls off much more rapidly, dropping to less than half
the spent fuel energy-deposition rate in 100 years. Thus, the
total energy deposited by the TRU waste is very small, resulting
in negligible temperature change and uplift.
CONCLUSION
The calculated temperature increase and uplift are so small
that further study of the regional effects of RH TRU-repository
heat is not justified.
FOREWORD
The calculations presented here were performed for Sandia
National Laboratories in 1979 and are consistent with the evalu
ation of options for the Waste Isolation Pilot Plant (WIPP) at
that time.
The information here was presented in draft form in CSI
2053-05, by Civil Systems, Incorporated.
0
"" "-.
1000 -
2000
3000
20
" \ \ I
\ \
"" "' "' "" ~ "" ~
~ ~
I I I I I I I .
30 40 50 60 TEMP. (°C)
70
'SANDSTONE
MIX A
SALT
MIX B
SALT
ANHYDRITE
SANDSTONE
~ ~ ~ ~ ~
I I I
80 90
Figure la: Initial Equilibrium Temperature Versus Depth
~
--
-O. DOE+O u
TRU Repositor y_
-1. OOE+D a_
---2. OOE+D i3_
-
-3. DDE+O ~~
O. OOE+OO
180 acres
I I 2.50E+03
Radius (m)
Jewey Lake Redbeds Rustler Salado
Anhydrite
Sandstone
Figure lb: Computational Grid Showing Repository Location and Layering.
1.0
\
.8
4-1 :::! Cl.o 4-1 :::!
0 ,.. (II
:3 0
p...
"1:! (II N .4 'ri
....-! ro 13 ,.. 0 z
0
0 so 100 150 200
Time (years)
Figure 2. RH TRU Normalized Reference Waste Power Output
1
\
.1 ~ ::l 0. ~ ::l
0
'"' (])
~ 0
p...
"tl (]) N
..-I
.--1 I'd 13
'"' 0 .01 z
.001
10. 100, 1000. 10,000 Time (years)
Figure 3. RH TRU Normalized Reference Wnste Power Output
,..._ u
0 '-'
~ ~ ....
35.875
34.5
O.OOE+OO
sd Years
S.OOE+lO
TIM (S)
u 0
-=· ,......;
Figure 4: Temperature in Central Zone of the Repository
--
.--... u
0
29.7
0. OOE+OO 5. OOE+l 0
I 320 Years TIM (S)
Figure 5: Temperature in Central Zone at Top of Salado
-·~
u 0
a. :1: 1-
27.7
27.7
c.; 0
27.6
27.6
27.S
27.51
27.50
O. OOE+OO I
480 Years
S.OOE+lO
TIM (S)
Figure 6: Temperature in Central Zone at Top of Rustler
ll"\ N
c
------------------------------~~~~·--·-··~~---·-····--------
_ ....
,........ u 0 -a. E ....
22.50
22.4639
O.OOE+OO S.OOE+lO
640 YeaiJM (S)
Figure 7: Temperature in Central Zone at Surface
u 0 C")
0 . 0
0 ..0 0 0
,......._ ;;o
'-"
c 0 ...... .u ...... tl)
0 :::;..
- ,.....; tO u ...... .u ,.... Q)
>
-560.99
-560.99
-560.99
-560.99
-561.00
O.OOE+OO S.OOE+lO I
200 Years 1000 Years TIM (S)
Figure 8: Uplift of Top of Repository Zone
E E
~
..~
,.....;
,...... E
"--'
c: 0
"M .j..J
"M cr. 0
0..
....-! Cll u
"M .j..J ,._. (l!
::>
-560.997
-561.000
-561.002
0. OOE+OO
Position
2.SOE+03 Radius (m)
~
..;:
'-'.:·
Figure 9: Uplift Profile at Repository Level at 1000 Years
~ 0
•-" .u •-" rJJ
Original Position E E
re -561.ooo ........ --1---+---- . L"'\
.-I - co
u •-" .u .... Q)
:> -561.001
-561.002
-561.003
O.OOE+OO 2.50E+03 Radius (m)
Figure 10: Uplift Profile at Repository Level at 1500 Years
-258.995
0 . cc
Original Position
-259.002
O.OOE+OO 2.SOE+03
Radius (m)
Figure 11: Uplift Profile.at Top of Salado at 1000 Years
-258.997
-259.002
O. OOE+OO
Original Position
2.SOE+03 Radius (m)
5 E
N
Figure 12: Uplift Profile at Top of Salado at 1500 Years
-E -c: 0
·r-4
-~ -164.997 ~~ 0
P-<
;=.1
Cll C)
•r-4 ... 1-1 C1J
. co
Original Position
:> -165. 000
-165.002
O.OOE+OO 2.50E+03 Radius (m}
Figure 13: Uplift Profile at Top of Rustler at 1000 Years
-·-4'
c 0 ..... ...,
..... Cll 0
p..
.--i C\l u ..... ..., H
- ClJ ::>
-164.997
-165.002
O.OOE+OO
Original Position
2.50E+03 Radius (m)
E E
Figure 14: Uplift at Top of Rustler at 1500 Years
,..... !: '-'
!: 0 .,., .u .,., Cl)
0 ~
,...; C1l
-CJ .,., .u !-< Q)
:>
:5. ODE-D
2.5DE-O
a.ooE•o
-2. 50E-O
O.OOE+OO
Position
2.50E+03
Radius (m)
Figure 15: Surface Profile at 1000 Years
E !:
..0
r-....
-s '-'
c 0 ...... ..... ...... rD 0
j:l...
,...., co u
...... ..... l-; (!)
>
-2.SDE-0
O. OOE +·oo
Figure 16:
2.SOE+03 Radius (m)
Surface Profile at 1500 Years
s s ,....,
lf"\
1 2 3
Radius (km)
Figure 17. Surface Profiles at Selected Times for 20-Acre 30kW/acre Spent Fuel Repository (Ref. 1)
4