Walton and Lonsbury, Inc. Superfund Site EPA Public ...
Transcript of Walton and Lonsbury, Inc. Superfund Site EPA Public ...
Walton and Lonsbury, Inc.
Superfund Site
EPA Public Information Meeting May 7, 2018
Attleboro Public Library
5/7/2018 1
Introductions
U.S. EPA
Ethan Finkel – Remedial Project Manager (RPM)
Sarah White – Community Involvement Coordinator (CIC)
Daniel Keefe – Superfund Section Chief
MassDEP
Dave Buckley – State Project Manager
EPA Contractor (AECOM)
Barbara Weir – Project Manager
Diane Silverman (TRC Solutions) – Project Human Health Risk Assessor
Agenda
Background Information
Remedial Investigation
Treatability Study
Feasibility Study
What’s Ahead
Q&A
Background
• Walton & Lonsbury (W&L) Operational History
• Contaminants
• EPA Removal Program
• EPA Remedial Program
Site History • Walton & Lonsbury operated a
chromium electroplating facility from 1940 to 2007
• Waste management practices during years of operation included: • Direct waste (“back door”) discharge
to abutting southern wetlands (ceased in 1970)
• Surface impoundment and lagoon (ceased in 1984)
• Underground and above-ground storage tanks
• Dry well
• Resulted in contaminated soils, sediment, surface water, groundwater, and indoor air
Walton & Lonsbury Facility
Brookside Apartments
Contaminants • Waste generated and associated with chromium electroplating include:
• Metals – chromic acid, chromic oxides • Solvents used as parts degreasers: volatile organic compounds (VOCs) – TCE, 1,1,1-
TCA) • Spent acid solution
• Primary site contaminants are chromium and trichloroethylene (TCE) • Chromium exists in different “forms” (oxidation states)
• Hexavalent chromium (Cr+6, Cr(VI), chromium(VI)) is very different from trivalent chromium (Cr+3, Cr(III), chromium(III)) • Cr(VI) more water soluble, more reactive, more toxic • Cr(III) much less toxic, essential element in humans
• “Total” chromium – accounts for both hexavalent and trivalent forms
1 H
3 Li
11
Na
1Q K
37 Rb
5!i
Cs
87 r
� Be 12
Mg
Per1iodic Table, of the Ellements � IHHII' ll'i-t!!I S
� mrnmetal· 1rnblc g ,sc•§, ro1r , · ,rth rn ·tol
27 28 Co Ni
© www. 1ements0a1flbas.e com
I cei N7' 0 9
~ , !f --------,w p s
Chromium – 22nd most abundant element in Earth’s crust
8
EPA “Removal Program” – Removal Action
Removal action (Oct 2010) to mitigate ongoing human health exposure to impacted soil and groundwater
• Removal of W&L buildings and residual waste materials
• Excavation and off-site disposal of contaminated sediment from southern wetland
• Building floor slab, cobble-filled pit, trenches, etc. remain at site
• Focus of efforts shifted east to residential areas
9
Removal Action (cont.)
• Construction of an engineered cover to prevent upwelling of groundwater and isolate surficial soils adjacent to Bliss Brook (behind residential areas)
• Construction/installation of a permeable reactive barrier (PRB) wall upgradient to Bliss Brook to intercept groundwater discharge (reduce Cr+6 to Cr+3)
EPA Remedial Program
• Walton & Lonsbury site added to the National Priorities List (NPL) in May 2013 – “Superfund” site designation
• No viable “responsible party” to conduct environmental testing or cleanup operations • Owners/operators – deceased; • Financial inability of survivors; and • No corporate entity to “order” the cleanup
• Designation as “Superfund” site allows for government-funded cleanup
125 250 000 ---===----•Feet
, inch = 250 feet
8
EPA Remedial vs. Removal Programs
• Removal program deals with acute or shorter term risks (i.e., emergency, time-critical or non-time critical actions)
• Remedial program deals with the residual or chronic risks (exposure over longer periods of time) • Iterative approach to determine the nature
and extent of contamination – what are the contaminants, how and where do they interact with the environment
Removal
Remedial
}
Remedial Program – Milestones
• Remedial Investigation (RI) – how bad is it? • Investigate the nature and extent of contamination • Human Health Risk Assessment Evaluation of current/future risks
based on site investigations • Ecological Risk Assessment
• Feasibility Study (FS) – what cleanup options exist? • Analysis and evaluation of cleanup alternatives
• EPA Proposed Plan – what EPA thinks is the best alternative(s) • Protectiveness, compliance with state, federal, local laws • Short- and long-term effectiveness, cost, implementability, reduction in
toxicity, mobility, and volume • State and community acceptance
Remedial Program – Milestones (cont.)
• Record of Decision (ROD) • Documents and memorializes final selected remedy
• Remedial Design (RD) • Design of the selected remedy
• More specific details as to how the remedy will be built and constructed
• Remedial Action (RA) • The cleanup itself
• Dependent upon construction funding
Remedial Investigation (RI) – Phased Approach
• Phase 1 (Jun 2014 – Aug 2014) • Collect soil and sediment samples, install monitoring wells into bedrock, sample surface water
and groundwater
• Phase 2 (Oct 2014 – Mar 2015) • Install additional wells, collect more samples of soil, sediment, surface water, and groundwater • Sample air beneath (sub-slab) and within (indoor) homes over or near TCE groundwater plume
• Phase 3 (Jul 2015 – May 2016) • Focused investigation of bedrock groundwater plume – how deep into rock do contaminants go?
• Focused investigation of sediment – toxicity tests and pore water sampling
• Phase 4 (Oct 2016 – Dec 2016) • Focused investigation of soil toxicity (ecological risks)
• Earthworm survival and contaminant bioaccumulation
• Seedling germination
RI – Phased Approach (cont.)
• Draft RI Report (Jun 2016) • Identify data gaps from previous phases
• Phase 5 (Nov 2017 – Jan 2018) • Updated EPA guidance – collect and analyze soil samples for lead testing
• Surface water and groundwater sampling and surveying
t
SURFACE AND SUBSURFACE SOIL SAMPLE LOCATION PLAN
• •
Surface and Subsurface Soil Sample Locations
Historic Sample Location
New Sample Location
• FARMERS
POND
SEDIMENT SAMPLE LOCATION PLAN
• •
Sediment and Surface Water Sample Locations
Historic Sample Location
New Sample Location
WALTON"''
f BUNGAY
RIVER
MONITORING WELL LOCATION PLAN
• • fl~A.Q
JI ' H" {.:J;..
~1 1-.,
Groundwater Sample Locations
Historic Monitoring Well
New Monitoring Well
WALTON ST
Total Chromium Concentration Range (mg/kg)
• <= 16
• • •
>16 -1 ,000
>1,000 - 5,000
>5,000 SURFACE SOIL TOTAL CHROMIUM
CONCENTRATION RANGES
WALTON ST
Hexavalent Chromium Concentration Range (mg/kg)
• • •
Not Detected or Detected <0.2
>0.2 - 100
>100
BUNGAY RIVER
SURFACE SOIL HEXAVALENT CHROMIUM CONCENTRATION RANGES
RI Phases – Results Total vs. Hex Chrome
FARMERS
POND t
Total Chromium Concentration Ranges (mg/kg)
• <=23
• >23-1000
• >1000 - 5000
• >5000
-" SEDIMENT TOTAL CHROMIUM CONCENTATIONS
Total Chromium in Sediment
• Highest in Southern Wetland where Walton & Lonsbury discharged waste
• Concentrations detected above reference samples found as far south as Mechanics Pond • High total chromium not
necessarily indicative of high hexavalent chromium
• Toxicity tests on sediment showed no toxicity, regardless of chromium concentrations
ST
• AECOM Surface Water Sample
HEXAVALENT CHROMIUM* IN SURFACE WATER
FALL 2014
• Field filtered results, label units are µg/L Hexavalent Chromium in Surface Water
• Detected in Bliss Brook
• Highest concentrations between SD-210 and SD-212
• Shallow groundwater plume discharging to this area of Bliss Brook
• Toxicity test results showed toxicity to water fleas at SD-210 and SD-212
3 GROUNDWATER RESULTS FOR HEXAVALENT
CHROMIUM IN OVERBURDEN (µg/L)
Hexavalent Chromium in Overburden Groundwater
• Plume extends from Walton & Lonsbury property to Bliss Brook
• Shallow overburden groundwater discharges into Bliss Brook
• Deep overburden groundwater passes underneath Bliss Brook
• Total chromium concentrations are similar to hexavalent chromium (Cr is all in Cr(VI) form)
• Permeable reactive barrier wall has some effect in reducing toxic Cr(VI) to less toxic Cr(III)
Si
Total Chromium Concentration Ranges
in Surface Soil and Sediment (mg/kg)
• <=RME Reference Sample Concentration
• >RME Reference Sample Concentration - 1000
• >1,000 - 5,000
• >5,000
--- Hexavalent Chromium Concentration, µg/L
GENERALIZED EXTENT OF CHROMIUM CONTAMINATION
Summary of Chromium Results
• Contamination found in Southern Wetland a result of direct discharge from the Walton & Lonsbury facility
• Contamination in Bliss Brook due to discharge of shallow groundwater to surface water
• Contamination moves downstream and is transported through water and on soil particles
3 GROUNDWATER RESULTS FOR TCE
IN OVERBURDEN (µg/L)
TCE in Overburden Groundwater
• TCE plume is slightly south of chromium plume – waste and disposal practices occurred at different areas of the Walton & Lonsbury property
• Several properties overlying TCE contamination plume
• Evaluation for potential vapor intrusion
~
soilv por mi raroo I
SOI con aminated w· h voes
vapor intrusion throug cracks in found ion sl
water table
I
roundwat r plume of voes
Vapor Intrusion
• Migration of vapor-forming chemicals (volatile organic compounds, such as TCE) from any subsurface source into an overlying building
• VOC-contaminated groundwater volatilization soil vapor migration vapor intrusion via cracks in building foundation slab
***
D
INDOOR AIR SAMPLE LOCATION PLAN
NOVEMBER 2016
Legend
-- Bliss 8100k
--PRB Groundwatltf Treatment Trench
Grounct«ate, Collection Pipe
D Former BuHd!ng F001prln1
[=1 &cavabon Extent
~ l.Jmit of Cap Installed by Removal Program
1111 umil of Clos.d Lagoon Area
Combined Wotl.1nds
E:::J Emergent/Open Water Wetland
~ Foras1ed/Sh1ub Welland
1111 Open Water
• Home not umpled clue to Jn&ence of SSOS. •• Home not wmpi.o beclUM c iubanclonMI ··•Aocnaforwmplingnotw-nted
0 AECOM 50
1·1,200
100 200 Feet
Testing for Vapor Intrusion • Phase 2 (2015) sampling event
• Sub-slab vapor and indoor air sampling
• SUMMA canisters – 24-hour tests
Vapor Intrusion Testing – Results
• Properties near or overlying groundwater plume were sampled (sub-slab soil gas and indoor air) • No detection or low detection below health-based screening levels
• No unacceptable risks no mitigation system required
• Properties with existing vapor mitigation systems tested to ensure functioning as intended (i.e., creating negative pressure differential) • All systems (sub-slab depressurization systems, SSDS) functioning as designed
• Periodic testing may be warranted
Surface Water and Sediment Toxicity Tests • More reliable method than a comparison of results to literature values
• Conducted using site-specific samples to directly measure toxicity and environmental risks
Surface water – 1 species Sediment – 2 species • Ceriopaphnia dubia (water flea) • Hyalella azteca (amphipod)
• Chironomus dilutus (midgefly) Measurement endpoints: • Survival Measurement endpoints: • Reproduction • Survival
• Biomass
ST
• AECOM Surface Water Sample
HEXAVALENT CHROMIUM* IN SURFACE WATER
FALL 2014
• Field filtered results, label units are µg/L
Cl) 41
~ 40 .0 0 41 z 'o 30 .0 .. 41
..0 E ~ 20 .0 41 Cl Ill
~ 10.0 <
00
>-
-
Figure 18. Average Brooder Reproduction for 6-Day C. dubia Walton & Lonsbury Surface Water Toxicity Test
Southern Wetland Bungay R. Bliss Brook
Mechanics Pond/
-- - -
f-- -- ~
~
f-- - -- - f-- >->--- -
~ - -- - ~ -~ -
240' 20 1 205 220· 305 312 207' 212 210 218
Sample Location
• Reference location
120 "ii > 100 ·s; :i 8 0)
.#- 60
40
20
0
Figl:llre 1A. Pe1rcent Survival for 6-Daiy C. ,dr.,bia Waltcm & Lo1nslbury Surface Wa-teir Toxicity Testing
240.. 201
Mech nics Pondl/ Bun ,1 R. Pili ,<; Pinnol:
200 220'" 305 312 2or 212 210 218
Sam pie L,o,caliom
• Flefereocg loca!iollS
Surface Water Toxicity Test Results
POND t
Total Chromium Concentration Ranges (mg/kg)
• <=23
• >23-1000
• >1000 - 5000
• >5000 SEDIMENT TOTAL
CHROMIUM CONCENTATIONS
Figure 1. Summary of H. azteca survival
120_ 0 ____ Mechanics _____ ---------.. ·-· ... .. . ···----·-Pond/Bungay River Southern Wetland
100.0
,.-,.
20.0 ~
····---·-------Bliss Brook
* = significant differenc~ when compared to associated reference
Figure 4. Summary of C. dilutus Average Surviva
120.0 Mechanics
··-p-o-n-d/_B_u_n_g_a_y _____________ ~-----Southem Wetland
River 100.0 ----------------- -------· . ·-- -
l 80.0 1:i :>
"! :I 60.0 "' <II
f! 40.0 <II
:,, <=:
20.0
Sample location
Bliss Brook
Sediment Toxicity Test Results
Additional Toxicity Testing • Phase 4 – Conducted to eliminate uncertainty about ecological risks at
Southern Wetland and Bliss Brook • Few literature values (benchmarks for acceptable concentrations of chromium)
• Direct measure of potential risk to chromium
Invertebrates – earthworm survival rates and chromium uptake Aquatic vegetation – seedling germination and root elongation
14-day exposure period and measurement endpoint, 100% survival 28-day exposure period and percent emergence and survival endpoints, 95% emergence and 100% survival
Two water resource protection districts within City of Attleboro
• Orrs Pond • Bungay River
Portion of the Bungay River protection district extends into site review area
“Medium” Use & Value determination for groundwater (within the protection district) as a potential future drinking water source
Evaluate cleanup options to restore groundwater to its beneficial use as a potential future drinking water supply
Groundwater Use & Value Determination
.. Ofl'!O OEP-SS
PHASE 3 GROUNDWATER RESULTS FOR HEXAVAL Cl IRO I • I BEDROCK
l ACt
• •
8 u ,
Mt\t.1010
·=· F 118
' ·
A -11S
---.. • ... ------
. . -·
, , . . . . .
. • • I
I I
' ' ' I
lrA\'- 1 S .. ,.
" 0
3 rS
Rd
Pau~ < ~ ? ro
p &Jtson
'O fr:'
()'
C: 0 -
..c. .i:, ti)
~
<J"
32
A ~oasSoi • Residential
• Wetland Soll ;th Potential RiSk orth Ave. (CIF) E,posure M•::.:tielYerds . West of ~ oil (Fl [Z] Sol 11 Res Surface/Subsulfac:e [ZJ W&L Property
_ St reams . Footpnnt
CIFonner Buid~nf ,am CJExcavatiOn ~ 1a11ed by Removal Prog r:::sa Umlt of Cap Area
Limit or Closed Lagoon
~ ml>ned Wetland~ ferWel1and
0 Emergen~;Wetlar'ld G:!I F«ested/S
- Open Water OOXionlD
S0-601: P':'3s:a1 ~=p~~ion (< 150µm): Total Leed l"I ' >200mg.4'.g
<2oomg/kg
C= Current F : FUute
J:71 155 NE.!!..,THAVE
5l NORTH AVE
j
r
Updated EPA Lead Guidance
• Updated EPA guidance for evaluation of fine fraction (<150 μm) lead in soil
• Portion of lead in soil more representative of exposure • Previous sampling evaluated “coarse” fraction
• Phase 5 (Dec 2017) data collection from 4 exposure point areas:
• Residential area west of North Ave
• Residential area east of North Ave • Wetland surface soil at the Southern Wetland
• Wetland surface soil at Bliss Brook
• Perform in-vitro bioavailability (IVBA) lead analysis to determine site-specific bioavailability of lead in soil
• Evaluate risks to lead in soil using site-specific data
34
Areas of Actionable Risk
W&L Property: Surface/Subsurface soils,
Shallow Groundwater
Bliss Brook: Surface Water
Site-Wide Groundwater: tap, irrigation, indoor air
Residential Yards West of North Ave:
Surface/wetland soils
Treatability Studies
• Evaluate feasibility of treatment of hexavalent chromium • Soil, overburden groundwater, and bedrock
groundwater
• Identify treatment reagents that are effective for each contaminated medium • Calcium Polysulfide (CaSx), Micro-scale zero valent iron
(ZVI), FerroBlack-H (FB-H), MRC
• Provide basis for estimating cost of hexavalent chromium treatment
• Titration testing followed by series of bucket tests
• Each treatment reagent blended with site soils and groundwater
• Effective treatment = removal of 90% Cr+6, total Cr
• Reagents with favorable results retained for further testing (e.g., additional metals, VOCs)
35
Re g,ent
!=et ro91aa. (FeS suspension wilh ree su ide (NeSH)l
MRC (orgatlO&ulf,ur esterJipol:Ylactate)
Calcium fl'otysu 11d
(CaSx)
sarety
2S g:enern1!Joii atlow :PH .i conoem1•
Ev.ilu.i e during bn.cht t
Must oid acidic conditions
!::)(oellent ·sli.01t.term, xce'llen lon,g-terrn
Med1um'lo good
Shoukl pr11,1ide sho •t rmtr atment and !ong•'lerm bio tJeatm n
Good ·sho1Me.rm tJ atrmn , long-te m tre· lmen ie:s on na ·ve iron, may ool be s ,effecwe as Ferro ck
Mob' e ftacf on (Na.SH) p~ible tm.piilct kl S\nf~ce water. pH may be elev ed. al a during1 nch l@S
No e identified
H. :hlly mobile and d p, eel ro or, may itll)ac stonnwater, avoid use · ear stream
Cost
Mechum $550/ton
High $700/ton
Medium
Medium $500/ton
Othe:r ot·entlal Benefits
Very effec1Ne for As, 1, Pb .ind other multwa nt rnetars E:ffecil,;en on TCE 111nknoi,,,m
W I a:s.o I at voes
Ea orln S tu nje,ction,
Su,speneion of iron r;,.il1fcle5,, relatively difficult to creale 1.1111/onn d1str1b:ut!on
Mayb diffcu o get good diWi bulion
Mod:erat:e to difft::u o, injed: and ob· ·n unifoim d'istributio:n .
High ly mobile, easy toinj easo.:i plugging of wells possible,
10.000
Figure 3-1
Cr+6 Testing Resu lts fo r Overburden Grou ndw at er
o, ... """'
Figu re3-2
Tota l Cr Test ing Resu lts fo r Overburden Groun dw ater
"""''
"""'"" � Cafu .. ..... , � fS.ltl
� M
� ce.,e1
·""' .. � l'B--HJ
� f fl.Hl ...
Treatability Studies – Conclusions Overburden Groundwater • ZVI most effective in reducing Cr+6, and (>95%) total Cr removal • FB-H also effective in reducing Cr+6, and moderate (between 30-90%) total Cr removal • CaSx effective in reducing Cr+6, but less effective for total Cr • MRC very effective in reducing Cr+6 (>99%), but very high total Cr concentration results
Bedrock Groundwater • FB-H (most feasible reagent for bedrock GW) effective in reducing Cr+6 and total Cr
Unsaturated Soil • FB-H effective in treating site soil (92% Cr+6 removal) • ZVI may also be effective (addition of water likely necessary)
36
Feasibility Study – (General) Remedy Alternatives
• No Action (required by statute)
• Limited Action (e.g., monitoring, access or use restrictions)
• Containment (e.g., capping/covering waste in place, vapor
mitigation system)
• Removal (e.g., excavation and off-site treatment/disposal)
• Treatment: In-situ (e.g., permeable reactive barrier, chemical
reduction/oxidation)
• Treatment: Ex-situ (e.g., groundwater pump and treat system) 37
Site Institutional Controls (ICs)
• Non-engineered instruments, such as administrative and legal controls, that help to minimize the potential for exposure to contamination
• Ensure protectiveness of cleanup actions where residual contamination might be left in place
• Potential Site ICs: • Property restrictions (e.g., vapor mitigation systems, engineered cover) • Walton & Lonsbury property (prohibit certain future uses) • Groundwater use (e.g., prevent well installation, withdrawal)
38
Feasibility Study – Evaluate Options
Nine Criteria Evaluation
Threshold Overall protection of human health and environment Compliance with ARARs (State and Federal Laws)
Balancing Long-term effectiveness and permanence Reduction of toxicity, mobility, volume Short-term effectiveness Implementability Cost
Modifying (evaluated after release of Proposed Plan)
State Acceptance Community Acceptance
What’s Ahead – 2018
• Finalize the Remedial Investigation • Human Health Risk Evaluation
• Ecological Risk Assessment
• Prepare Feasibility Study • Detailed Analysis of Remedial Alternatives
• Release Proposed Plan (September) • Solicit community and state feedback/acceptance
• Hold public hearing
• 30-day public comment period
• Responsiveness Summary to address comments
40
What’s Ahead (cont.)
• EPA signs Record of Decision (December) • Memorializes final selected cleanup remedy
• Remedial Design (RD) • Design of the selected remedy
• More specific details as to how the remedy will be built and constructed
• Remedial Action (RA) • The cleanup itself
• Dependent upon construction funding
41
Questions?
EPA Contacts:
Ethan Finkel Remedial Project Manager (RPM) 617-918-1293 [email protected]
Sarah White Community Involvement Coordinator (CIC) 617-918-1026 [email protected]
EPA Site Profile Page: http://www.epa.gov/superfund/walton
MassDEP Contacts:
David Buckley State Project Manager 617-556-1184 [email protected]
42