Wadhams Road Bridge Replacement Bridging over a Moving...

30
Wadhams Road Bridge Replacement Bridging over a Moving Site Doug Parmerlee, PE AECOM Department Manager, Bridge Design, Michigan Jane Abadir , PE, LEED® A.P. Somat Engineering, Inc. Project Manager March 17, 2015

Transcript of Wadhams Road Bridge Replacement Bridging over a Moving...

Page 1: Wadhams Road Bridge Replacement Bridging over a Moving Sitectt.mtu.edu/sites/ctt/files/resources/bridge/workshop/8parmerlee.pdfMarch 17, 2015 Page 19 • Deflections were calculated

Wadhams Road Bridge ReplacementBridging over a Moving Site

Doug Parmerlee, PEAECOM Department Manager, Bridge Design, Michigan

Jane Abadir, PE, LEED® A.P.Somat Engineering, Inc. Project Manager

March 17, 2015

Page 2: Wadhams Road Bridge Replacement Bridging over a Moving Sitectt.mtu.edu/sites/ctt/files/resources/bridge/workshop/8parmerlee.pdfMarch 17, 2015 Page 19 • Deflections were calculated

PURPOSE OF TODAY’S PRESENTATION

1) Highlight a complicated and interesting project

2) Highlight the teamwork between the bridge engineers and the geotechnical engineers.

March 17, 2015

Page 3: Wadhams Road Bridge Replacement Bridging over a Moving Sitectt.mtu.edu/sites/ctt/files/resources/bridge/workshop/8parmerlee.pdfMarch 17, 2015 Page 19 • Deflections were calculated

PROJECT BACKGROUND

• Owner is St. Clair County Road Commission (Mike Clark).

• Location is approximately 5 miles west of Port Huron.

• Only crossing within a 14 mile stretch of the Black River.

• Total bridge replacement.

• Bid through MDOT Local Agency Programs (Chris Tennes-MDOT Bridge Staff Engineer).

• MDOT Geotechnical Review (Dick Endres).March 17, 2015Wadhams Road Bridge Page 3

Page 4: Wadhams Road Bridge Replacement Bridging over a Moving Sitectt.mtu.edu/sites/ctt/files/resources/bridge/workshop/8parmerlee.pdfMarch 17, 2015 Page 19 • Deflections were calculated

DESIGN TEAM AND SCOPE

• URS Corporation (AECOM)– Bridge design

– Roadway design

– Traffic engineering

– Signal design

– Pavement markings

– Signing

• Somat Engineering, Inc.– Geotechnical engineering

• Taiga Engineering, LLC– Hydraulic analysis

– Scour analysis

• SCCRC– Survey

– Project Funding

• MDOT– Project oversight

– Geotechnical review

March 17, 2015Wadhams Road Bridge Page 4

Page 5: Wadhams Road Bridge Replacement Bridging over a Moving Sitectt.mtu.edu/sites/ctt/files/resources/bridge/workshop/8parmerlee.pdfMarch 17, 2015 Page 19 • Deflections were calculated

WHY WAS THIS PROJECT DIFFERENT?

• During a typical project:– Much of the bridge geometry and design is determined without

geotechnical input.– Geotechnical engineers usually help determine foundation type

and/or depth of deep foundations,

• During this project the geotechnical aspects directly or indirectly influenced:– Number of spans– Span lengths– Pier design– Abutment design– Bearing type– Staging

March 17, 2015Wadhams Road Bridge Page 5

Page 6: Wadhams Road Bridge Replacement Bridging over a Moving Sitectt.mtu.edu/sites/ctt/files/resources/bridge/workshop/8parmerlee.pdfMarch 17, 2015 Page 19 • Deflections were calculated

TEAM WORK

• URS and Somat worked together in partnership team rather than as a typical Prime/Sub relationship

• URS and Somat were in daily communication during the life of the project.

• Aspects of the design were iterative and required back and forth between URS and Somat.

March 17, 2015Wadhams Road Bridge Page 6

Page 7: Wadhams Road Bridge Replacement Bridging over a Moving Sitectt.mtu.edu/sites/ctt/files/resources/bridge/workshop/8parmerlee.pdfMarch 17, 2015 Page 19 • Deflections were calculated

PREVIOUS BRIDGES

March 17, 2015Wadhams Road Bridge Page 7

1st Bridge before 1914 2nd Bridge 1914-1939

3rd Bridge 1939 to date

Adapted from HistoricBridges.org

Page 8: Wadhams Road Bridge Replacement Bridging over a Moving Sitectt.mtu.edu/sites/ctt/files/resources/bridge/workshop/8parmerlee.pdfMarch 17, 2015 Page 19 • Deflections were calculated

SOMAT GEOTECHNICAL INVESTIGATION

• Review of historic documents including existing geotechnical data, subsurface studies, involvement of the Prof. Bill Housel (U of M)

• Site visit to inspect bridge distress and observe evidence and extent of slope instability

• Comprehensive Subsurface Geotechnical Investigation• Groundwater monitoring wells• Drained Tri-axial and Direct Shear testing• Developed a soil profile model• Sensitivity analysis for global stability of the south slope.

March 17, 2015Wadhams Road Bridge Page 8

Page 9: Wadhams Road Bridge Replacement Bridging over a Moving Sitectt.mtu.edu/sites/ctt/files/resources/bridge/workshop/8parmerlee.pdfMarch 17, 2015 Page 19 • Deflections were calculated

FIELD INVESTIGATION

March 17, 2015Wadhams Road Bridge Page 9

Page 10: Wadhams Road Bridge Replacement Bridging over a Moving Sitectt.mtu.edu/sites/ctt/files/resources/bridge/workshop/8parmerlee.pdfMarch 17, 2015 Page 19 • Deflections were calculated

EXISTING BRIDGE

March 17, 2015Wadhams Road Bridge Page 10

Page 11: Wadhams Road Bridge Replacement Bridging over a Moving Sitectt.mtu.edu/sites/ctt/files/resources/bridge/workshop/8parmerlee.pdfMarch 17, 2015 Page 19 • Deflections were calculated

SOIL PROFILE

March 17, 2015Wadhams Road Bridge Page 11

Page 12: Wadhams Road Bridge Replacement Bridging over a Moving Sitectt.mtu.edu/sites/ctt/files/resources/bridge/workshop/8parmerlee.pdfMarch 17, 2015 Page 19 • Deflections were calculated

INITIAL BRAINSTORMING

• The sensitivity analysis defined the problem which the slope instability that would result in horizontal pressure applied to the foundations.

• URS and Somat discussed numerous foundation options in-person and via telephone.

• Strut from pier to north abutment

• Soil/cement mixing• Over-excavating and

backfilling with EPS• Retaining wall• Bentonite debonding of

adjacent slopes• “Rocking” Pier• Soil nails• Drilled Shafts• Heavy-Duty integral

abutments

March 17, 2015Wadhams Road Bridge Page 12

Page 13: Wadhams Road Bridge Replacement Bridging over a Moving Sitectt.mtu.edu/sites/ctt/files/resources/bridge/workshop/8parmerlee.pdfMarch 17, 2015 Page 19 • Deflections were calculated

INITIAL BRAINSTORMING

• URS, Somat, SCCRC met with MDOT to discuss initial ideas and results of geotechnical investigation.

• It was decided that the slope instability would cause earth pressures equal to 9 times cohesion (9c).

• The 9c pressures were approximately 10 to 15 times greater than active earth pressure.

• The immense pressures eliminated any attempt to retain/restrain the soil due to economics.

• Immense pressures = substantial foundation elements

March 17, 2015Wadhams Road Bridge Page 13

Page 14: Wadhams Road Bridge Replacement Bridging over a Moving Sitectt.mtu.edu/sites/ctt/files/resources/bridge/workshop/8parmerlee.pdfMarch 17, 2015 Page 19 • Deflections were calculated

DESIGN DECISIONS

• It was decided to allow the soil to flow but design foundation elements to withstand the immense pressures.

• SCCRC elected to have the design performed according to LRFD and HL-93 Modified (2006-2007 time period).

• Since typical pile sections would not be strong enough, a custom rectangular “box” pile was developed.

• The rectangular shape allowed the pile to be narrow (less likely to attract direct earth pressure) and deep for increased strength.

March 17, 2015Wadhams Road Bridge Page 14

Page 15: Wadhams Road Bridge Replacement Bridging over a Moving Sitectt.mtu.edu/sites/ctt/files/resources/bridge/workshop/8parmerlee.pdfMarch 17, 2015 Page 19 • Deflections were calculated

DESIGN DECISIONS

• Estimated deflections of the box piles was excessive, therefore ground anchors were proposed to anchor the pier footing from translating.

• The box pile and ground anchor foundation would be extremely expensive, therefore the following bridge design decisions were made:

• Use one pier only• Use a span long enough to locate the south abutment (Abutment A)

outside the unstable zone• Use conventional abutment designs• Use a symmetric span arrangement• Use a fixed bearing at the pier, use expansion bearings at abutments• Conventionally designed superstructure

March 17, 2015Wadhams Road Bridge Page 15

Page 16: Wadhams Road Bridge Replacement Bridging over a Moving Sitectt.mtu.edu/sites/ctt/files/resources/bridge/workshop/8parmerlee.pdfMarch 17, 2015 Page 19 • Deflections were calculated

DESIGN REFINEMENT

• As the bridge design progressed, URS was in daily contact with Somat to refine soil properties, provide new properties, refine dimensions of elements.

• Some of the items that were refined during the design, influenced by geotechnical issues, included:

March 17, 2015Wadhams Road Bridge Page 16

• Box pile dimensions• Box pile socket

embedment due to scour• Diameter of excavated hole• No casing for excavation• Staging

• Socket details• Transverse earth pressures• Backfill around box pile• Arrangement of ground

anchors• Ground anchor length

Page 17: Wadhams Road Bridge Replacement Bridging over a Moving Sitectt.mtu.edu/sites/ctt/files/resources/bridge/workshop/8parmerlee.pdfMarch 17, 2015 Page 19 • Deflections were calculated

BOX PILE DETAILS

March 17, 2015Wadhams Road Bridge Page 17

• 2” x 40” webs.• 2¾” x 23” flanges.• 4’ embedment Into footing.• 20’ x 5’ diameter reinforced socket.• Interior filled with concrete.• Exterior filled with aggregate.

Page 18: Wadhams Road Bridge Replacement Bridging over a Moving Sitectt.mtu.edu/sites/ctt/files/resources/bridge/workshop/8parmerlee.pdfMarch 17, 2015 Page 19 • Deflections were calculated

FINITE ELEMENT ANALYSIS OF PIER

March 17, 2015Wadhams Road Bridge Page 18

Page 19: Wadhams Road Bridge Replacement Bridging over a Moving Sitectt.mtu.edu/sites/ctt/files/resources/bridge/workshop/8parmerlee.pdfMarch 17, 2015 Page 19 • Deflections were calculated

FINITE ELEMENT ANALSYSIS OF PIER

March 17, 2015Wadhams Road Bridge Page 19

• Deflections were calculated to determine the amount of in-service translation expected.

• Expansion bearings designed for translation.

• Deflections during tensioning of ground anchors calculated.

• Footing closure pour necessary.

Page 20: Wadhams Road Bridge Replacement Bridging over a Moving Sitectt.mtu.edu/sites/ctt/files/resources/bridge/workshop/8parmerlee.pdfMarch 17, 2015 Page 19 • Deflections were calculated

PIER DESIGN

• During the pier design, Somat provided refined values of soil properties for the design of the box piles and ground anchors.

• URS’s analysis estimated approximately 1” of movement of the footing during ground anchor installation.

• During the actual installation of the ground anchors, the footing movement was measured at approximately 1”.

• Footing movement measurement was confirmation of design model.

March 17, 2015Wadhams Road Bridge Page 20

Page 21: Wadhams Road Bridge Replacement Bridging over a Moving Sitectt.mtu.edu/sites/ctt/files/resources/bridge/workshop/8parmerlee.pdfMarch 17, 2015 Page 19 • Deflections were calculated

FINAL BRIDGE CONFIGURATION

March 17, 2015Wadhams Road Bridge Page 21

Page 22: Wadhams Road Bridge Replacement Bridging over a Moving Sitectt.mtu.edu/sites/ctt/files/resources/bridge/workshop/8parmerlee.pdfMarch 17, 2015 Page 19 • Deflections were calculated

OTHER ITEMS

• Removal of the existing bridge was carefully considered. The removal of the existing pile bents was minimized to reduce vibrations on the unstable slope.

• There is a storm sewer that runs down the south slope. Due to the steep slope and the instability of the slope, the design and detailing of the storm sewer was carefully considered. Somat was consulted during the storm sewer design.

• A bridge health monitoring system was included. Load cells on the ground anchors and strain gauges on the piles were specified.

March 17, 2015Wadhams Road Bridge Page 22

Page 23: Wadhams Road Bridge Replacement Bridging over a Moving Sitectt.mtu.edu/sites/ctt/files/resources/bridge/workshop/8parmerlee.pdfMarch 17, 2015 Page 19 • Deflections were calculated

Thank You

QUESTIONS?

[email protected]@somateng.com

February 25, 2015

Page 24: Wadhams Road Bridge Replacement Bridging over a Moving Sitectt.mtu.edu/sites/ctt/files/resources/bridge/workshop/8parmerlee.pdfMarch 17, 2015 Page 19 • Deflections were calculated

March 17, 2015Wadhams Road Bridge 24

Page 25: Wadhams Road Bridge Replacement Bridging over a Moving Sitectt.mtu.edu/sites/ctt/files/resources/bridge/workshop/8parmerlee.pdfMarch 17, 2015 Page 19 • Deflections were calculated

March 17, 2015Wadhams Road Bridge 25

Page 26: Wadhams Road Bridge Replacement Bridging over a Moving Sitectt.mtu.edu/sites/ctt/files/resources/bridge/workshop/8parmerlee.pdfMarch 17, 2015 Page 19 • Deflections were calculated

March 17, 2015Wadhams Road Bridge 26

Page 27: Wadhams Road Bridge Replacement Bridging over a Moving Sitectt.mtu.edu/sites/ctt/files/resources/bridge/workshop/8parmerlee.pdfMarch 17, 2015 Page 19 • Deflections were calculated

March 17, 2015Wadhams Road Bridge 27

Page 28: Wadhams Road Bridge Replacement Bridging over a Moving Sitectt.mtu.edu/sites/ctt/files/resources/bridge/workshop/8parmerlee.pdfMarch 17, 2015 Page 19 • Deflections were calculated

March 17, 2015Wadhams Road Bridge 28

Page 29: Wadhams Road Bridge Replacement Bridging over a Moving Sitectt.mtu.edu/sites/ctt/files/resources/bridge/workshop/8parmerlee.pdfMarch 17, 2015 Page 19 • Deflections were calculated

March 17, 2015Wadhams Road Bridge 29

Page 30: Wadhams Road Bridge Replacement Bridging over a Moving Sitectt.mtu.edu/sites/ctt/files/resources/bridge/workshop/8parmerlee.pdfMarch 17, 2015 Page 19 • Deflections were calculated

FUNDING SOURCE

Funding Source Federal/State

Michigan Local Bridge Program $7,000,000

Surface Transportation $1,500,000

MDOT Funds $5,000,000

Local Bridge Programs $2,000,000

TOTAL $15,500,000

$11,600,000 (Bid Price)

March 17, 2015Wadhams Road Bridge 30