W 3 alex gilbert on ppps and transportation
-
Upload
guillermo-aranda-mena -
Category
Documents
-
view
216 -
download
1
description
Transcript of W 3 alex gilbert on ppps and transportation
PPP: Construction Planning Design A designer’s perspective RMIT Presentation | 6 August 2013
Alex Gilbert – Technical Director - Aurecon
1. Transport PPPs over the last 15 years – my experience
2. The past – East Link 3. The present – Peninsula Link 4. The future – East West Link 5. Summary 6. Discussion
Agenda
Personal Project Experience
Year Major Project Country Procurement type
1998 Bute Avenue PFI United Kingdom PPP (PFI model)
1999 Roads in Dubai United Arab Emirates Traditional “construct only”
2000 New Providence Road Improvement Project Bahamas D&C
2001-2 A43 Towcester to M40 Dualling United Kingdom D&C
2002-3 A303 Stonehenge Improvement United Kingdom ECI
2004 M1 Westlink United Kingdom PPP (DBFO model)
2004 PPP Motorways in Slovak Republic Slovakia PPP (study of options)
2005-6 EastLink Australia PPP (Tolled)
2006 Calder Freeway Australia D&C
2007 Acacia Ridge Grade Road / Rail separation Australia Alliance
2009-12 Peninsula Link PPP Australia PPP (availability model)
2013 Port Capacity Project – Roads and Services Australia D&C (novated) 2014 East West Link Australia PPP (Tolled)
Year Major Project Country Procurement type
1998 Bute Avenue PFI United Kingdom PPP (PFI model)
1999 Roads in Dubai United Arab Emirates Traditional “construct only”
2000 New Providence Road Improvement Project Bahamas D&C 2001-2 A43 Towcester to M40 Dualling United Kingdom D&C
2002-3 A303 Stonehenge Improvement United Kingdom ECI
2004 M1 Westlink United Kingdom PPP (DBFO model)
2004 PPP Motorways in Slovak Republic Slovakia PPP (study of options)
2005-6 EastLink Australia PPP (Tolled)
2006 Calder Freeway Australia D&C
2007 Acacia Ridge Grade Road / Rail separation Australia Alliance
2009-12 Peninsula Link PPP Australia PPP (availability model)
2013 Port Capacity Project – Roads and Services Australia D&C (novated)
2014 East West Link Australia PPP (Tolled availability model)
• 39 km of tollway • 3 freeway to freeway connections • Twin, 3-lane 1.6km tunnels under the Mullum Mullum
Creek • Additional 6kms of untolled connecting roads
Ringwood Bypass • Dandenong Bypass • 17 interchanges • 88 bridges • 2 railway crossings
East Link – Project Summary
East Link – PPP Structure
Victorian Government
SEITA
ConnectEastOperations & Maintenance Transfield Services
Design & ConstructionThiess John Holland
DesignersCW D&S, PB & Hyder
Tolling System SupplierSICE
Construction Sub-Contractors & Suppliers
Independent Reviewer
East Link Planning and design challenges
• Availability or resources • Engineering (Design and Construction) • Plant • Materials
• Coordination of design • 3 major consultants • Consistency and high quality
• External stakeholders
• Performance spec vs detailed spec • Maximise traffic volumes • Programme pressure • Tolling issues • Whole of Life costs
East Link Specific issues associated with PPP model
Peninsula Link Strategic Context
East Link
Peninsula Link
• Up to 40 minutes travel time savings in peak periods
• Ease congestion on existing roads • Bypass eight sets of traffic lights, six
major roundabouts and a rail crossing • Completion of missing link • Road safety • New Shared Use Path
Project Benefits
PenLink– Project Description
• 27 kilometres of freeway standard road • Two traffic lanes in each direction • On and off ramps to 11 roads including three freeway to
freeway connections • 28 bridges (45 separate structures) • Three million cubic metres of earthworks • Around 1.5 million trees and plants requiring 80,000
cubic metres of mulch • 25 kilometre shared walking and cycling path • High standard urban design, environmental
management and community information
What is an Availability PPP? • 1st of its kind in Australia • Toll free – payment based on
lane availability and a series of KPI’s
• $759 million fully underwritten (debt and equity)
• Concession period – Delivery (D&C) + 25 years
Procurement Model Availability PPP
Contractual Framework
EOI Released 31 March 2009
EOI Submitted 5 May 2009
RFP Released 24 June 2009
RFP Submitted 20 October 2009
Preferred Bidder 15 January 2010
Financial Close 8 February 2010
First Sod Turn 17 February 2010
Date of Completion 18 January 2013
Hand back to State 18 January 2038
Project Lifecycle
Design Management Challenges
• 110 Design packages • 6 Stages of review • 600+ Design Deliverables in 14 months • Over 5,000 construction drawings • 14 Consultants • Multiple stakeholders
Design Team Structure
• 200 designers (75 FTE at peak)
Resourcing
Review Process
Programme
Interface Management
Technical Challenges
21
DESIGN CRITERIA • Impact on Plains Grassy Wetlands • Geotechnical • Major flood catchment
Soft ground
EastLink Interchange The Challenge
22
East Link
Peninsula Link
Retaining walls
Straighten alignment
Major art piece
Relocate watercourse
EastLink Interchange The Solution
23
How it should look
24
How it looked during construction
25
Stony Point Rail Bridge
26
Stony Point Rail Bridge
27
Peninsula Link – PPP issues
• Whole Life Cost • Optimise Pavement • Efficient Maintenance
• Sculpture programme • Commercial opportunities
28
The next PPP East West Link
29
PPP Structure
• PPPs have been around for about 20 years are evolving
• PPPs are a popular way to deliver major Transport Infrastructure and becoming more so
• Most of the challenges in planning, designing and constructing major transport projects occur irrespective of procurement model
• With PPPs, WLC and operational considerations are built into the design more effectively
Conclusion
Discussion