MINISTRY OF ENERGY AND MINERAL DEVELOPMENT
VOTE 017
VOTE 123
FY2014/15 MINISTERIAL POLICY STATEMENT
Presented to Parliament for the Debate on the Estimates of Revenue and Expenditure
By
Eng Irene Muloni (MP)
MINISTER OF ENERGY AND MINERAL DEVELOPMENT
30 June 2014
THE REPUBLIC OF UGANDA
Energy and MineralsMPS:
Ministerial Policy StatementEnergy and Minerals
Table of Contents
Foreword
Executive Summary
Foreword
Abbreviations and Acronyms
Structure of Report
PRELIMINARY
Conclusion
Annex : Recommendations from parliament and
institutional responses
Vote: 017 Ministry of Energy and Mineral Development
V1: Vote Overview
V2: Vote Performance for FY 2013/14 and Planned
Outputs for FY 2014/15
V4: Proposed Budget Allocations for 2014/15 and the
Medium Term
V5: Vote Crosscutting Issues
Staff Establishment Structure
V3: Detailed Planned Outputs for FY 2014/15
Vote: 123 Rural Electrification Agency (REA)
V1: Vote Overview
V2: Vote Performance for FY 2013/14 and Planned
Outputs for FY 2014/15
V4: Proposed Budget Allocations for 2014/15 and the
Medium Term
V5: Vote Crosscutting Issues
Staff Establishment Structure
V3: Detailed Planned Outputs for FY 2014/15
Preliminary
i
Energy and MineralsMPS:
Ministerial Policy StatementEnergy and Minerals
Foreword
Abbreviations and Acronyms
Madam Speaker and Honorable Members of Parliament of this August House,
In keeping with Section 6 sub-section 2 of the Budget Act 2001, I hereby submit to you a Ministerial Policy
Statement (MPS) covering the Ministry of Energy and Mineral Development (Vote 017) and the Rural
Electrification Agency (Vote 123) for the Financial Year 2014/15.
The mandate of the Ministry of Energy and Mineral Development is to “Establish, Promote the
Development, Strategically Manage and Safeguard the Rational and Sustainable Exploitation and
Utilization of Energy and Mineral Resources for Social and Economic Development”.
Over the medium term, my Ministry will continue to focus on the implementation of the following priority
areas:
(i) increase electricity generation capacity and transmission network;
(ii) increase access to modern energy services through rural electrification and renewable energy
development;
(iii) promote and monitor petroleum exploration and development in order to achieve local production;
(iv) develop petroleum refining and pipeline transportation infrastructure.
(v) streamline petroleum supply and distribution; and
(vi) promote and regulate mineral exploration, development, production and value addition
(vii) inspect and regulate exploration and mining operations.
Other priorities include:
(i) promotion of efficient utilisation of energy; and
(ii) monitoring geotectonic disturbances and radioactive emissions.
This Ministerial Policy Statement (MPS) provides a review of sector performance up to 30th June 2014 and
the expected key outputs for the FY2014/15 within the Ministry's mandate. Budget allocations to Votes for
the medium term have been provided based on sector priorities.
The ability of the Ministry to perform the key priorities indicated above will largely depend on your
support and the availability of adequate financial resources. On the part of the Ministry and myself, we are
prepared to serve and deliver tangible outputs. I therefore submit the estimates of the Ministry of Energy
and Mineral Development Vote 017 amounting to Ush 1,775.71 billion of which Ush 4.06 billion is Wage
recurrent, Ush 4.24 billion is Non-Wage Recurrent, Ush 1,298.80 billion for Domestic Development, Ush
0.2 billion as domestic arrears and Ush 468.60 billion as donor funding.
Under Vote 123 Rural Electrification Agency, I submit estimates amounting to Ush 97.38 billion of which
Ush 52.98 billion is Domestic Development and Ushs 63.01 billion is funding from development partners.
Hon Eng. Irene Muloni, MP
MINISTER OF ENERGY AND MINERAL DEVELOPMENT
OLEBound160:
Preliminary
ii
Energy and MineralsMPS:
Ministerial Policy StatementEnergy and Minerals
Abbreviations and Acronyms
Preliminary
iii
Energy and MineralsMPS:
Ministerial Policy StatementEnergy and Minerals
Abbreviations and Acronyms
Atomic Energy CouncilABC
Atomic Energy CouncilAEC
African Development BankAfDB
Annual ReportAR
Artisanal and Small Scale MinersASM
Budget Framework PaperBFP
Build Own Operate and TransferBOOT
Barrels of Oil per dayBopd
Development Finance InstitutionsDFI
Department of Geological Survey and MinesDGSM
Exploration AreaEA
East African CommunityEAC
East African Petroleum ConferenceEAPC
Early Production SchemeEPS
Front End Engineering DesignFEED
Geological and GeophysicalG&G
Government of KenyaGOK
Government of UgandaGOU
Heavy Fuel OilHFO
International Atomic Energy AgencyIAEA
Information and Communication TechnologyICT
Islamic Development BankIDB
Independent Power ProducerIPP
Indicative Rural electrification Master PlanIREMP
jinja Storage TanksJST
Kilo VoltsKV
Local GovernmentLG
Local Purchase OrderLPO
Ministry of Energy and Mineral DevelopmentMEMD
Memorandum of UnderstandingMOU
Ministerial Polict StatementMPS
Medium TermMT
Mega wattsMW
Nuclear Energy UnitNEU
Non Tax revenueNTR
National Water and Sewarage CorporationNWSC
Petroleum Exploration and Production DepartmentPEPD
Petroleum Operating LicensePOL
Power Purchase AgreementPPA
Peace, Recovery and Development PlanPRDP
Promotion of Renewable Energy and Energy Efficiency ProjectPREEEP
Poverty and Social Impact AssessmentPSIA
Preliminary
iv
Energy and MineralsMPS:
Ministerial Policy StatementEnergy and Minerals
Power Sector Investment PlanPSIP
Resettlement Action PlanRAP
Southern and Eastern Africa Mineral CentreSEAMIC
Technical Petroleum CommitteeTPC
Preliminary
v
Energy and MineralsMPS:
Ministerial Policy StatementEnergy and Minerals
Structure of the Ministerial Policy Statement
The Ministerial Policy Statement is structured by Vote, as follows:
This section sets out past performance and future plans for Central and Local Government Votes in
more detail. It is structured as follows for each Vote: A Vote Overview sets out key details of the
vote, including past performance, future plans and key performance issues to be addressed including
costing implications.
Annex Recommendations from parliament and institutional responses
• Vote Overview
• Vote Annexes
Vote Functions
“Each Minister shall cause to be prepared and submitted to Parliament a Policy Statement of the relevant
Ministry on the preliminary [budget] estimates .... by the 30th day of June in each year”. Budget Act 2001,
Section 6 (1)
Structure
Since the FY2011/12 budget cycle, the preparation of sector BFPs, Ministerial Policy Statements and
Budget Estimates centre around the notion of Vote Functions. A Vote Function is a set of programmes,
projects, and Local Government Grants, defining the roles and responsibilities of a vote/institution, and
contributing towards the attainment of vote and overall sector objectives.
As such, a Vote Function provides detailed information on centralised services, by capturing allocations to
Central Ministries and Stand Alone Votes, and decentralised services funded via grants to Local
Governments
Provides details of approved staff structure for each programme and project (including names of staff
and vacant posts). This is clearly demonstrated in the form of an organogram.
• Staff Establishment Structure
Preliminary
vi
Energy and MineralsMPS:
Ministerial Policy StatementEnergy and Minerals
Executive Summary
1. MANDATE AND SECTOR PRIORITIES
The mandate of the ministry of Energy and Mineral Development is to “Establish, Promote the
development, Strategically Manage and Safeguard the Rational and Sustainable Exploitation and Utilisation
of Energy and Mineral Resources for Social and Economic Development”.
In line with the national development goal of structural transformation, progress has continued to occur in
the Energy and Mineral development sector. New power generation and transmission infrastructure have
been commissioned and the construction of new power generation projects, namely Karuma and Isimba, has
commenced. Implementation of the rural electrification programme is being scaled up following the new
Rural Electrification Strategy, which was launched in 2013. The process of commercialization of oil and
gas resources is being taken forward, with a target of production starting in 2017. Government is putting
efforts to acquire adequate geological data and also reorganizing the minerals sector by putting in place a
new licensing regime largely aimed at improving investment and value addition. Over the medium term, the
sector will continue to implement the following priority areas:
(i) increase electricity generation capacity and transmission network;
(ii) increase access to modern energy services through rural electrification and renewable energy
development;
(iii) promote and monitor petroleum exploration and development in order to achieve local production;
(iv) develop petroleum refining and pipeline transportation infrastructure.
(v) streamline petroleum supply and distribution; and
(vi) promote and regulate mineral exploration, development, production and value addition
(vii) inspect and regulate exploration and mining operations.
Other priorities include:
(i) promotion of efficient utilisation of energy; and
(ii) monitoring geotectonic disturbances and radioactive emissions.
Within the sector priorities, special attention is paid to the following four (4) flag bearer projects namely: i)
Development of Karuma Hydropower project; ii) Development of the Oil refinery; iii) Promotion of
investment in the Sukuru phosphates; and iv) Development of Iron and Steel Industry
2. OVERVIEW OF THE SECTOR PERFORMANCE AND MEDIUM TERM PLANS
2.1 ENERGY PLANNING, MANAGEMENT & INFRASTRURE DEVELOPMENT
2.1.1 Progress in increasing Electricity Generation Capacity
Development of Karuma Hydropower Project (600MW): Government signed the Engineering Procurement
Construction + Financing (EPC+F) contract for the construction of the Power Plant and Associated
Transmission Lines with Sinohydro Corporation of China on the 6th August, 2013 and the project is being
financed by China Exim Bank and the Government of Uganda’s Energy Fund. The ground-breaking
ceremony was officiated by H.E. the President on the 12th August, 2013. Work at the site has been taken up
at several fronts in the last six months. The contractor has submitted detailed design drawings for review by
Preliminary
vii
Energy and MineralsMPS:
Ministerial Policy StatementEnergy and Minerals
the Government’s Engineer. Access roads to the Dam Area and power intake area are being constructed.
Construction of access tunnel to the power house site is ongoing as well as excavation on the right bank of
the river for the diversion channel. Acquisition of the project land through compensation of the project
affected people is being finalized and the duration of the construction period is 60 months
Isimba Hydropower Project (183 MW): The Government signed Engineering, Procurement, Construction +
Financing (EPC+F) contract with the China International Water and Electric Corporation (CWE) for the
construction of the Isimba hydropower project and the Isimba – Bujagali 132kV interconnection line on the
6th September, 2013 and the project is being funded by China Exim Bank and the Government of Uganda.
H.E the President officiated at the groundbreaking ceremony held on the 6th October 2013. Addendum 1
was signed on 10th April 2014 mainly addressing the issue of effectiveness of the contract which was
established as 6th September 2013. Addendum 2 was signed on 20th May 2014 mainly addressing the issue
of advance payment to the EPC Contractor. The contract for the Supervision Consultant was signed on May
7th 2014. The Supervision Consultant is Energy Infratech PVT from New Delhi India.
After the ground breaking ceremony on the 5th of October 2013, the Contractor embarked on various pre-
construction works utilizing their own resources. Among other things the contractor has completed the
following:
(i) Site topographic survey, and Geological Mapping, for both the plant and the line, has carried out
seismic safety assessment and soil resistivity tests.
(ii) Basic design of the whole project involving modifying and optimizing the consultants’ original
design in the Feasibility Study in line with the above complementary geological and surveying investigation
results . The Design is presently under evaluation and optimization by the Contractor’s experts and is
expected to be submitted by Mid-July 2014.
(iii) Bujagali – Isimba 132kV transmission line route mapping and basic designs – these were
submitted and are under review.
(iv) Design of Employer & Contractor’s camp, this was reviewed and approved
(v) Construction of a 33kv power line along Busana Road from Kayunga town to the Isimba
Hydropower Project Site
(vi) The contractor signed a contract with MTN Uganda to provide the project with all
telecommunication needs and reliable network coverage and with Total Uganda Limited to supply the
Project sites with Fuel. Both Contracts were signed in March 2014
(vii) CWE has procured a shipment of goods including equipment and materials for the construction of
the workers camps and these have arrived on site.
The Contract for the Implementation of the Resettlement Action Plan was signed on 9th May 2014 with
Kagga and Partners LimitedRAP implementation is going on with progress as follows: -
Dam site area
Disclosure at 90%
Payments at 72%
Reservoir Area
Disclosure at 75%
The Contractor has commenced on the clearing of the area where acquisition is complete in preparation for
Preliminary
viii
Energy and MineralsMPS:
Ministerial Policy StatementEnergy and Minerals
the construction of the camps, fuel station and telecommunication infrastructure among other.
Ayago Hydropower Project (600MW): Government signed a Memorandum of Understanding (MoU) with
China Gezhouba Group Company Limited (CGGC) for the construction of the power plant and associated
Interconnection transmission line on EPC+ Financing Basis. CGGC will also complete the detailed
Feasibility Study that JICA study team partly conducted.
Progress
(a) A draft detailed feasibility report has been submitted for review. Comments have been generated and
submitted to CGGC.
(b) Six firms were shortlisted to provide consultancy services for the construction supervision of the
project. Shortlisted firms were issued Request for Proposals and the closing date for proposal submission is
14th July 2014.
(c ) EPC contract is expected to be signed in the 1st Quarter of the FY 2014/15.
Small Hydropower Projects: To further increase power generation capacity, government is promoting the
development of small hydros as follows:-
(i) Detailed feasibility studies for a number of small hydro sites totalling to over 80 MW have been
completed and are due for implementation. These include: Kikagati (16 MW), Mitano (2.9 MW), Lubilia
(5.4 MW), Nyagak III (4.5 MW); Siti (21.5 MW), Waki (5.4 MW), Rwimi (10.54MW) Ndugutu (0.5 MW),
Nkusi (4.8MW) Nyamwamba (9.2 MW), Nengo Bridge (6.5 MW), Esia (0.11 MW) and Muzizi (44.5 MW
Peak Power).
(ii) In addition, feasibility studies for other sites are in their final stages these include: - Nsongezi (38
MW), Ntono (2.5 MW), Sindoro (5.6MW) Achwa-Agago (88 MW), Kakaka (7.2 MW), Muvumbe
(4.5MW) Muyembe (3.2 MW) and Kyambura (8.3 MW).
Under the Global Energy Transfer Feed in Tariff (GET FiT) Program Government is fast-tracking the
development a portfolio of up to 15 small-scale renewable energy generation projects (1MW-20MW)
promoted by private developers with a total installed capacity of about 125MW. So far, twelve (12)
projects, representing 103MW have been approved under the GET Fit program. The approved projects
include: Nyamwamba (9.2 MW), Rwimi (5.5 MW), PH Industrial Farm’s (1 MW) biomass gasified maize
farm waste, Sugar Allied Industries Limited Cogeneration (6,9 MW) biomass (bagasse from sugar
production) plant in Kaliro district, Kikigati (16 MW), Kakira Cogeneration (20 MW) biomass using
bagasse from sugar production, Nengo Bridge (6.7 MW), Muvumbe (6.5 MW), Lubilia (5.4 MW), Waki
(4.8 MW), Siti I (6.1 MW) and Siti II (15 MW).
The GET FiT program targets a total capacity of 190 MW within a period of 3 to 5 years which includes 20
MW of solar fed into the main grid. This program is supported by grants from development partners
notably Norway, UK, EU Commission and Germany. The World Bank will provide a Partial Risk
Guarantee (PRG) mechanism to secure against political and commercial risks.
Other energy sources of power generation: In order to reduce overdependence on hydropower and increase
the energy mix other power generation sources being developed include: Geothermal (200 MW), Modern
Preliminary
ix
Energy and MineralsMPS:
Ministerial Policy StatementEnergy and Minerals
Biomass (150MW), Solar Thermal (200 MW), Solar PV (50 MW), Oil & Gas and Heavy Fuel Oil
(100MW).
Promotion and Development of Nuclear Energy: A strategy to develop the Nuclear Power Roadmap has
been prepared. The Roadmap will present recommendations on how major Nuclear Power Infrastructure
issues can be addressed in the short, medium and long term.
2.1.2 Grid Expansion Programmes – Transmission Infrastructure
Government will continue to expand the Transmission Network through the implementation of the
Resettlement Action Plan (RAP); undertake Feasibility Studies and construct new transmission lines and
substations as highlighted below.
For the financial year 2013/14; 150 km of 220kV lines, 1441.7 Km of 132kV and 35.2 Km of 66kV
transmission lines have been added to the national grid. In addition, 82.5 km of 132 kV Mutundwe -
Kabulasoke line was successfully re-conductored and refurbished to improve reliability of supply to
districts of South Western Uganda. A total of 16 substations were also added to the national transmission
grid infrastructure in the financial year 2013/2014.
2.1.3 Progress on Increasing Access to Modern Energy Services
(i) Grid based Rural Electrification
During the FY2013/14, a total of 1,657 km of High voltage lines (11kV and 33kV) and 806 km of Low
Voltage distribution lines were done. Ongoing Procurements in the FY2013/14 for implementation during
the FY 2014/15 are 3,279 km of high voltage lines (11kV and 33kV) and 2,977 km of low voltage
distribution lines.
In terms of connections, new customer connections made under the Rural Electrification Program during
the FY2013/2014 include 42,236 new connections in the grid areas, 4,942 new connections in the Off-grid
areas and 5,259 new solar PV connections.
Fifteen (15) district headquarters were connected to the national grid over the past one year bringing the
number to 98 out of 112 (about 87.5%) districts. The districts are: Kyegegwa, Katakwi, Amuria, Kiruhura,
Buhweju, Lamwo, Nakapiripit, Amudat, Kaberamaido, Dokolo, Amolatar, Ntoroko, Alebtong, Moroto, and
Napak.
The major schemes under construction include: Gulu-Acholibur and Paicho-Patiko-Palaro; Gulu-Amuru-
Adjumani-Moyo; Hoima-Nyantozi-Kinyara-Biso-Butiaba/ Waki small hydro – Buliisa-Wanseko; Mayuge-
Bwodha; Rwemikoma-Buremba-Rukunyu; Rushere-Mugole-Kijuma; Mayuge / Namaingo Lumino-Busia;
Iganga-Namukudembe- Bulango & Luuka-Nakabugu; Bukwa – Suam; and Narweyo-Buhimba-Hoima;
Narweyo-Kisita-Nkoko-Bukuumi; Arua-Maracha-Koboko; Nyapea-Zombo-Zeu-Warr-Vurra Zombo; and
Nebbi-Nyaravur-Packwach-Panyamur with tee-off to Parombo.
Work has commenced on new projects which will connect additional eleven (11) districts of Bulisa,
Adjumani, Moyo, Amuru, Otuke Zombo, Koboko, Maracha, Yumbe, Nwoya and Namayingo. Three (3)
districts of Kotido, Kaabong and Kalangala will be supplied by the end of 2016 and thus completing the
long but steady journey of supplying electricity to all district headquarters of the country.
Preliminary
x
Energy and MineralsMPS:
Ministerial Policy StatementEnergy and Minerals
(ii) Solar based Rural Electrification for Social Services
Government is also increasing investments, mainly in solar-based electricity, to enable the delivery of social
services especially where the national grid has not reached. Solar-based electricity is used to support health
services through lighting, microscopy and other diagnostic services and the cold chain (storage of
immunization doses). It is also applied in pumping for rural water schemes and in schools, providing
lighting and power for science laboratories
Health Centres: In the course of the financial year, Government has provided solar energy packages to 130
Health Centres (HCs) in eight (8) districts: twelve (12) HCs in Amolatar, thirty (30) HCs in Pader and
Agago, nine (9) HCs in Buliisa, twenty nine (29) HCs in Gulu, twenty two (22) HCs in Moyo and twenty
eight (28) HCs in Soroti and Serere districts.
By the end of this year, an additional 180 HCs will be provided with solar energy packages in nine (9)
districts: Bukwo, Sironko, Mbale, Mayuge, Katakwi, Amuria, Masindi, Bududa and Bundibugyo.
Water Supply Schemes: Government has completed the installation of 20 solar-based water-pumping
schemes in fourteen (14) districts. The completed schemes are: Anaka, Purongo and Alero in Nwoya
district, Itula, Obongi and Lefori in Moyo district, Adwari, Okwang and Orumo in Otuke district, Kaabong
and Karenga in Kaabong district, Palenga in Gulu district, Erussi in Nebbi district, Kati in Arua district,
Midigo in Yumbe ditrict, Koboko in Koboko district, Usuk in Katakwi district, Mucwini in Kitgum district
and Alebtong in Alebtong district.
Schools: During the Financial Year Government completed the installation of solar energy packages in 287
Post-Primary Schools in 51 districts. Solar packages were provided in 14 schools in Lira district, 9 schools
each in Kitgum, Mayuge, Kyenjonjo and Kayunga districts, eight (8) schools each in Rakai, Soroti, Gulu,
Bundibugyo and Nebbi districts, seven (7) schools each in Kiboga, Amuria, Busia, Amuru, Pader and
Kamwenge districts, six (6) schools each in Nakasongola, Bugiri, Kiruhura, Isingiro, Ibanda and Kabale
districts, five (5) schools each in Masaka, Mbarara, Lwengo, Katakwi, Kisoro, Buikwe, Iganga, Koboko
and Moyo districts, 4 schools each in Kalangala, Masindi, Bukedea, Ntungamo, Sironko, Bukwo, Kanungu,
Kabarole, Adjumani and Yumbe districts, 3 schools each in Agago, Nakaseke, Kapchorwa, Moroto,
Nakapiripirit and Maracha-Terego and 2 schools in Kween.
2.2 PETROLEUM SUB-SECTOR
Government will continue to promote the establishment of the country’s petroleum resource base so as to
achieve sustainable exploitation. These efforts include building the national expertise in the field of
petroleum exploration, development and production; attraction of oil companies to invest in exploration and
production as well as commercialization plans of the oil and gas resources. The key highlights of the
achievements include:
2.2.1 Legal Framework
The Petroleum (Exploration, Development and Production) Act, 2013 and the Petroleum (Refining,
Conversion, Storage and Transportation) Act, 2013 were enacted in April and July 2013 respectively. New
Petroleum Regulations for the two legislations Petroleum (Exploration and production) (Conduct of
Exploration Operations) Regulations will be issued this year in order to operationalize the new legislations.
Preliminary
xi
Energy and MineralsMPS:
Ministerial Policy StatementEnergy and Minerals
The process of establishing the National Oil Company (NOC), Petroleum Authority of Uganda (PAU) and
the Directorate of Petroleum has progressed. Specifically for the NOC and PAU the process of identifying
the Board members is in final stages and the drafting of the memorandum and articles of association for the
NOC progressed. These Institutions are expected to commence during 2014/15 and will require seed money
from Government. The structure for the Directorate of Petroleum was approved by the Ministry of Public
service and is expected to commence during 2014/15.
2.2.2 Licensing Status and Investment Promotion
There are still three (3) international oil companies holding exploration licenses in four out of thirteen
Exploration Areas demarcated in the Albertine Graben. These companies are: - Tullow Oil Ltd., Total E&P
Uganda Ltd and CNOOC Uganda Ltd who hold a 33.33% joint venture in Discovery Areas or oil fields of
Exploration Area (EA) 1 (Paraa – Wanseko –Pakwach Basin), EA 2 (Northern Lake Albert Basin), and EA
3A (Southern Lake Albert Basin).
Preparation for the first licensing round scheduled for 2015 progressed with, i) Building of the stratigraphic
structure of the Albertine Graben (ii) review of the model contracts for acquisition, processing and
marketing of data and licensing; and iii) putting up the regulations for sale of petroleum data.
2.2.3 Status of Exploration
To date, a total of one hundred and sixteen (116) exploration and appraisal wells have been drilled in the
country, twenty two (22) of which were drilled during 2013/14. Of these wells one hundred one (101)
encountered hydrocarbons, thirty six (36) were exploration wells and eighty (80) appraisal wells. Twenty
nine (29) of the wells have been flow tested.
To date, twenty one (21) oil and/or gas fields have been discovered in the Albertine Graben namely:
Turaco, Mputa, Waraga, Nzizi, Kajubirizi (Kingfisher), Kasamene, Ngege, Nsoga, Ngiri, Jobi, Rii, Ngassa,
Taitai, Karuka, Wairindi, Ngara, Mpyo, Jobi-East, Gunya, Rii and Lyec. Four (4) of these (Ngassa, Karuka,
Taitai, TURACO) have reverted to Government and will be licensed during the forthcoming first licensing
round in the country and 17 of the discoveries were taken forward for appraisal and development by the oil
companies.
Appraisal for 9 (Kasamene, Warindi, Kigogole, Ngege, Ngara, Nsoga, Mputa, Nzizi, Kingfisher –whose
production license was awarded) of the discoveries has been completed, and applications for production
licenses submitted to government. These applications are still under review by government. Appraisal of
the remaining 7 (Jobi-East, Jobi-Rii, Mpyo, Gunya, Ngiri, Lyec, Waraga) discoveries is still on going and
should be completed by end of 2014.
One Production Licence over the Kingfisher field was issued during September 2013 and subsequently civil
works for the development of the field commenced. The field is expected to be ready for production by
2017/18. Bulk movement of materials for the development of this field is underway.
Production licences for the fields whose appraisal has been completed are expected to be granted during the
2nd half of 2014 and their development will commence during the 1st half of 2015. These fields include
Ngiri, Kasamene-Wairindi, Kigogole, Nsoga, Ngege, Ngara, Mputa and Nzizi. Production licences for the
fields whose appraisal is ongoing are expected to be granted before end of June 2015 and their development
Preliminary
xii
Energy and MineralsMPS:
Ministerial Policy StatementEnergy and Minerals
will commence during the 1st half of 2016. These fields include Jobi, Rii, Mpyo, Gunya, Jobi-East, Lyec
and Waraga.
The Development of the National Content Policy, Strategy and Plan progressed with two national
stakeholder consultation engagements having been held. The Policy strategy and plan are expected to be
completed during the next financial year. The Policy goal is to ensure that exploitation of petroleum
resources creates lasting values to the economy and people of Uganda, through maximizing the share of
local labour, local businesses, and local goods and services; and transfer of technology and know-how to
deepen the capabilities and competiveness of Ugandan individuals and businesses
2.2.4 Appropriate Commercialization Strategies
Government and the oil companies entered into a memorandum of understanding on how to commercialize
the country’s oil and gas resources. The high level commercialization plan contained in this MOU includes
i) the use of petroleum for power generation; ii) development of a 60,000barrels per day refinery in two
phases; and iii) development of a crude oil export pipeline. A detailed implementation plan for this
commercialization plan is currently being developed. In the short term and prior to the refinery coming on
stream, crude oil/gas to power generation capacity is being promoted. Major first oil is expected 2017/18.
(i) Refinery Development Project
Government will develop the refinery on a Public–Private Partnership (PPP) basis through a joint venture
company with shareholding of 40% (forty percent) by the public sector and 60% (sixty percent) by the
private sector. Procurement of a Lead Investor for the oil refinery is on-going and six (6) firms have been
shortlisted, these include: China Petroleum Pipeline Bureau led consortium – China; Marubeni Corporation
– Japan; Petrofac led consortium – UAE; RT Global resources led Consortium – Russia; SK Energy led
Consortium – Korea; and Vitol SA (Swiss) led consortium with Samsung Engineering (Korea).
Several evaluation studies have been undertaken to enable Government make the right decisions with
regards to refinery development. The studies undertaken include an Environmental baseline study that was
concluded in December 2013. This study characterizes the current environmental and social conditions in
and around the refinery land was concluded. The environmental survey provides a benchmark for
comparing the state of the environment before the development of the refinery starts, when the operations
are being undertaken and also at decommissioning stage.
The process of acquiring land for refinery development has progressed. The implementation of the
Resettlement Action Plan (RAP) for the 29 sq.km of land proposed for the refinery in Kabaale Parish,
Buseruka Sub-county, Hoima District commenced in July 2013. Government has so far compensated about
50% of the PAPs and expects to complete the compensation process by end of 2014.
(ii) Petroleum Products Transportation and Storage
A feasibility study for the distribution and storage facilities of the refined petroleum products was
completed in 2012 and recommended a 205km long, 10 inch diameter pipeline, distribution by trucks from
Buloba to different demand centers. This proposal is to be developed as part of refinery project. The
feasibility study also recommended a refined petroleum products pipeline from Eldoret to Kampala
(Buloba) of a distance of 325km long, 12 inch pipeline and negotiations with the possible developer are
ongoing. Another feasibility study for the Kampala-Kigali Pipeline is to commence this year.
Preliminary
xiii
Energy and MineralsMPS:
Ministerial Policy StatementEnergy and Minerals
(iii) Strategic Fuel Reserves
Government through the Public Private Partnership (PPP) arrangement with Hared Petroleum Ltd
refurbished the 30 million litre Jinja storage facility and restocking is on-going
2.3 PETROLEUM SUPPLY AND DISTRIBUTION
Uganda is currently a net importer of petroleum products. It imports about 95% of the products through
Kenya and 5% through Tanzania. The average annual growth of petroleum consumption stands at about
7%, which is attributed to an average economic growth of about 6 percent. Monthly consumption of
petroleum products is 125 million litres which translates to an annual figure of 1,500,000 cubic metres and
on a monthly basis, the country spends about US$ 156 million to import petroleum products.
At present there are 167 private oil-marketing companies established in Uganda involved in supply,
transportation, distribution and marketing of Petroleum products.
Kenya-Uganda Oil Pipeline Extension
The private investor demanded excessive guarantees like capacity payments if the refinery in Uganda
negatively impacts on the importation of petroleum products. Consequently, the project is being structured
as a public project and financing is being sought.
A Contract for carrying out a feasibility study for the Kampala-Kigali pipeline segment was signed between
M/S PENSPEN Ltd and the Governments on 8th January 2014. The feasibility study will take six (6)
months to complete.
2.4 THE MINERAL SECTOR
2.4.1 Uganda’s Mineral Resources
Uganda is endowed with a variety of Mineral Resources namely: metallic mineral resources like Copper,
Cobalt, Tungsten, Beryllium, Bismuth, Columbite-Tantalite, Gold, Tin, Iron Ores, Platinum Group of
Metals, Uranium and Rare Earth Metals. The Industrial minerals include:- Marble /limestone, Phosphate
(Apatite and francolite), Vermiculite, Kaolin, Bentonite, Diatomite, Gypsum, Glass sands, Salts, Feldspar,
Quartz, Pozzolana, Dimension Stones and Gemstones
2.4.2 The recent airborne geophysical surveys and new mineral reserves and targets
Government has recently accomplished extensive acquisition, processing and interpretation of airborne
geophysical data (magnetic, radiometric and selected electromagnetic) covering 80% of the country and the
airborne surveys were followed by ground geological and geochemical mapping country wide. A rising out
of the surveys carried out, government has been able to focus investors in the mineral sector to target and
quantify commercial mineral deposits. For example, four (4) mineral commodities, namely iron ore, gold,
vermiculite and limestone have been explored in sufficient detail and as a result, there has been a
significant increase in the mineral resources base in the country.
In addition to the previously known iron ore deposits of muko (30 million tonnes), Bukusa (23 million
Preliminary
xiv
Energy and MineralsMPS:
Ministerial Policy StatementEnergy and Minerals
tonnes), and Sukulu (45 million tonnes), new ore reserves discovered at Buhara in Kabale (48 million
tonnes), Nangara Kisoro (8 million tonnes) and Rugando, Butogota in Kanungu (55 million tonnes), now
total 116 million tonnes of iron ore and have a gross value of US$ 15.6 billion. A total of 7.8 million ounces
of gold which have been proven at Tiira in Busia (500,000 ounces), Kamalenge in Mubende (5 million
ounces), Mashonga in Bushenyi (I million ounces), Kampano in Ibanda (500 ounces) and at Alupe in Busia
(800,000 ounces) have a gross value of US$ 10.9 billion. Vermiculite reserves have increased from 5
million tonnes to 54.9 million tonnes at Namekhara in Manafa district and the reserves have a gross value
of US$ 11.5 billion. The limestone/marble reserves in the country have increased from the known 30
million tonnes in Hima, Dura Muhokya and Tororo to over 300 million tonnes after quantifying reserves in
Karamoja.
Other Mineral deposits and targets identified: Besides the ore deposits which have been proven as indicated
above, there are several ore deposits and targets which have been discovered and are not yet fully
evaluated. These include the 3 billion aluminous clay reserves at Mukutu, Buwaya in Mayuge district
which contain Alumina and Rare Earths Elements; the new various mineral targets (plantinum group of
elements, iron ore, base metals and rare earths) in the country; over thirty (30) Uranium targets of which ten
(10) targets are of high priority; and bentonitic clays in Kaiso-Tonya area of Hoima.
2.4.3 New Geological Maps produced
Nineteen (19) updated geological maps with new mineral potential zones at a scale of 1:250000 have been
produced and these include:- Fort Portal, Kampala, Mbarara, Homa Bay, Masaka, Kabale, Jinja, Arua,
Didinga, Mbale, Masindi, Hoima, Moroto, Aloi, Gulu, Packwach, Kaabong-Lodwar, Kitgum and
Kapenguria. The maps can be accessed through a geological and mineral information system portal at
www.uganda-mining-go.ug:81/ugandaGMIS.
3. CHALLENGES IN THE ENERGY AND MINERAL SECTOR
Land Acquisition: To acquire land for infrastructure; and mineral development, petroleum and mineral
exploration takes a very long time and land is very costly. That delays project development and results into
high investment costs.
High Employee Turnover: Low pay for professional has affected the energy and mineral sector. Better pay
for Scientists in the sector so as to attract a strong pool of talented people including skilled and technical
personnel in the energy and mining disciplines is a requisite.
Institutional framework: The current structure makes it in-effective to cope with new challenges and
administrative burdens. The proposed new structure, if implemented, will go a long way to address this
challenge with a focus on effective service delivery.
High power system losses at both technical and commercial levels: High energy losses reduce the revenues
required to provide affordable power. The technical losses are being addressed through rehabilitation and
refurbishment of the distribution line network.
Low access to modern energy forms especially among rural households: Expanding electricity coverage to
realize the required transformation in rural areas of Uganda in reasonable time poses unique challenges.
First, rural areas are characterized by low population densities due to dispersed settlements. Second, a
significant number of households are poor and find it difficult to connect and pay for electricity services.
Preliminary
xv
Energy and MineralsMPS:
Ministerial Policy StatementEnergy and Minerals
Therefore, despite the heavy investment in the construction of the rural electrification infrastructure which
is capital intensive, the connection rates have remained very low.
Management of expectations created by the discovery of petroleum: The people of Uganda in general, and
in the areas where the discoveries have been made in particular, expect quick revenues, jobs and businesses,
among other things. There are also anxieties about the possible negative aspects of developing the oil
resources like environment degradation and how the revenues will be managed. To mitigate this challenge,
government has intensified the sharing of information on the realistic development programme of the sector.
4. MAJOR POLICY MEASURES TO BE PRONOUNCED IN THE FY 2014/15
Emplacement of the New Institutions (Petroleum Authority and the National Oil Company) to regulate
Exploration, Production and Value Addition of petroleum resources on one hand and to arrange the
commercial aspects of the country’s oil and gas business.
Opportunities to invest in Petroleum Exploration through a bidding round will be availed to investors.
Review of mining legislation in order to streamline licensing, monitoring, compliance and acquisition of
surface rights and enforcement of settlement policy.
Review of the Electricity Act in order to strengthen opportunities to increase energy mix and enhance
access through new concessions.
Preliminary
xvi
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
The chart below shows total funding allocations to the Vote by Vote Function over the medium term:
Table V1.1: Overview of Vote Expenditures (UShs Billion)(ii) Summary of Past Performance and Medium Term Budget Allocations
0
200
400
600
800
1000
1200
En
erg
y
Pla
nn
ing
,Man
agem
ent
& I
nfr
astr
uct
ure
Dev
't
Lar
ge
Hy
dro
po
wer
infr
astr
uct
ure
Min
eral
Ex
plo
rati
on
,
Dev
elo
pm
ent
&
Pro
du
ctio
n
Pet
role
um
Ex
plo
rati
on
,
Dev
elo
pm
ent
&
Pro
du
ctio
n
Pet
role
um
Su
pp
ly,
Infr
astr
uct
ure
an
d
Reg
ula
tio
n
Po
licy
, P
lan
nin
g a
nd
Su
pp
ort
Ser
vic
es
Chart V1.1: Medium Term Budget Projections by Vote Function (Excluding Taxes, Arrears)
V1: Vote Overview
MANDATE
The Mandate of the Ministry is to “Establish, Promote the Development, Strategically Manage and
Safeguard the Rational and Sustainable Exploitation and Utilisation of Energy and Mineral Resources
for Social and Economic Development”.
VISION
“A Model of Execellence in Sustainable Management and Utilisation of Energy and Mineral
Resources”.
MISSION
“To ensure reliable, adequate and sustainable exploitation, management and utilisation of energy and
mineral resources”.
ROLES AND FUNCTIONS
(i) Provide policy guidance in the development and exploitation of the Energy, Mineral, Oil and
Gas resources.
(ii) Create an enabling environment in order to attract investment in the development, provision and
utilisation of energy and mineral resources.
(iii) Acquire process and interpret technical data in order to establish the energy and mineral
resource potential of the country.
(iv) Inspect, regulate, monitor and evaluate activities of private companies in energy and mineral
sectors so that the resources are developed, exploited and used on a rational and sustainable basis.
(i) Vote Mission Statement
(iii) Non Tax Revenue 0.0000.000 0.000 7.700
Excluding Taxes, Arrears 1,650.557116.714 154.647 1,775.710
Wage
Non Wage
GoU
Donor
GoU Total
Total GoU+Donor (MTEF)
Development
Recurrent
Taxes** 22.00010.000 10.000 0.000
Total Budget 1,672.557126.714 164.647 1,768.210
(ii) Arrears
and Taxes
Arrears 0.0000.000 0.000 0.200 N/A
N/A
N/A
N/A
N/A N/A
(i) Excluding Arrears, Taxes
4.9492.6982.525 2.079 4.063 4.124
4.4584.2193.600 2.888 4.244 4.287
1,333.8611,276.648 149.680 1,291.104 1,306.598
111.804366.9920.000 0.000 468.599 174.752
1,343.2681,283.565116.714 154.647 1,299.411 1,315.008
1,455.0721,650.557116.714 154.647 1,768.010 1,489.760
2016/172012/13
Outturn
Rel. by
End Mar
Approved
Budget 2014/15 2015/16
MTEF Budget Projections2013/14
Grand Total 1,672.557126.714 164.647 1,775.910
0.0000.000
1,455.0721,489.760
N/AN/A
120.588
Vote Overview
1
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
0
200
400
600
800
1000
1200
En
erg
y
Pla
nn
ing
,Man
agem
ent
& I
nfr
astr
uct
ure
Dev
't
Lar
ge
Hy
dro
po
wer
infr
astr
uct
ure
Min
eral
Ex
plo
rati
on
,
Dev
elo
pm
ent
&
Pro
du
ctio
n
Pet
role
um
Ex
plo
rati
on
,
Dev
elo
pm
ent
&
Pro
du
ctio
n
Pet
role
um
Su
pp
ly,
Infr
astr
uct
ure
an
d
Reg
ula
tio
n
Po
licy
, P
lan
nin
g a
nd
Su
pp
ort
Ser
vic
es
Ush
s B
illi
on
2013/14 Approved Budget Estimates 2014/15 Budget Projections 2015/16 Budget Projections
Chart V1.1: Medium Term Budget Projections by Vote Function (Excluding Taxes, Arrears)
Vote Overview
2
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
V2: Vote Performance for FY 2013/14 and Planned Outputs for FY 2014/15
(i) Past Vote Outputs
This section describes past vote performance and planned Outputs, in terms of key vote outputs
OVERVIEW OF THE SECTOR PERFORMANCE AND MEDIUM TERM PLANS
ENERGY PLANNING, MANAGEMENT & INFRASTRURE DEVELOPMENT
Progress in increasing Electricity Generation Capacity
Progress in Increasing Electricity Generation Capacity and Expansion of the Transmission Network
Development of Karuma Hydropower Project (600MW): Government signed the Engineering Procurement
Construction + Financing (EPC+F) contract for the construction of the Power Plant and Associated
Transmission Lines with Sinohydro Corporation of China on the 6th August, 2013 and the project is being
financed by China Exim Bank and the Government of Uganda’s Energy Fund. The ground-breaking
ceremony was officiated by H.E. the President on the 12th August, 2013. Work at the site has been taken up
at several fronts in the last six months. The contractor has submitted detailed design drawings for review by
the Government’s Engineer. Access roads to the Dam Area and power intake area are being constructed.
Construction of access tunnel to the power house site is ongoing as well as excavation on the right bank of
the river for the diversion channel. Acquisition of the project land through compensation of the project
affected people is being finalized and the duration of the construction period is 60 months
Isimba Hydropower Project (183 MW): The Government signed Engineering, Procurement, Construction +
Financing (EPC+F) contract with the China International Water and Electric Corporation (CWE) for the
construction of the Isimba hydropower project and the Isimba – Bujagali 132kV interconnection line on the
6th September, 2013 and the project is being funded by China Exim Bank and the Government of Uganda.
H.E the President officiated at the groundbreaking ceremony held on the 6th October 2013. Addendum 1
was signed on 10th April 2014 mainly addressing the issue of effectiveness of the contract which was
established as 6th September 2013. Addendum 2 was signed on 20th May 2014 mainly addressing the issue
of advance payment to the EPC Contractor. The contract for the Supervision Consultant was signed on May
7th 2014. The Supervision Consultant is Energy Infratech PVT from New Delhi India.
After the ground breaking ceremony on the 5th of October 2013, the Contractor embarked on various pre-
construction works utilizing their own resources. Among other things the contractor has completed the
following:
(i) Site topographic survey, and Geological Mapping, for both the plant and the line, has carried out
seismic safety assessment and soil resistivity tests.
(ii) Basic design of the whole project involving modifying and optimizing the consultants’ original
design in the Feasibility Study in line with the above complementary geological and surveying investigation
results . The Design is presently under evaluation and optimization by the Contractor’s experts and is
expected to be submitted by Mid-July 2014.
(iii) Bujagali – Isimba 132kV transmission line route mapping and basic designs – these were submitted
and are under review.
(iv) Design of Employer & Contractor’s camp, this was reviewed and approved
(v) Construction of a 33kv power line along Busana Road from Kayunga town to the Isimba
Hydropower Project Site
Preliminary 2013/14 Performance
(iii) Vote Outcomes and Outcome Indicators
The table below sets out the vote outcomes and outcome indicators
Table V1.3: Vote Outcomes and Outcome Indicators
Vote Overview
3
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017(vi) The contractor signed a contract with MTN Uganda to provide the project with all
telecommunication needs and reliable network coverage and with Total Uganda Limited to supply the
Project sites with Fuel. Both Contracts were signed in March 2014
(vii) CWE has procured a shipment of goods including equipment and materials for the construction of
the workers camps and these have arrived on site.
The Contract for the Implementation of the Resettlement Action Plan was signed on 9th May 2014 with
Kagga and Partners LimitedRAP implementation is going on with progress as follows: -
Dam site area
Disclosure at 90%
Payments at 72%
Reservoir Area
Disclosure at 75%
The Contractor has commenced on the clearing of the area where acquisition is complete in preparation for
the construction of the camps, fuel station and telecommunication infrastructure among others
Ayago Hydropower Project (600MW): Government signed a Memorandum of Understanding (MoU) with
China Gezhouba Group Company Limited (CGGC) for the construction of the power plant and associated
Interconnection transmission line on EPC+ Financing Basis. CGGC will also complete the detailed
Feasibility Study that JICA study team partly conducted.
Progress
• A draft detailed feasibility report has been submitted for review. Comments have been generated and
submitted to CGGC.
• Six firms were shortlisted to provide consultancy services for the construction supervision of the
project. Shortlisted firms were issued Request for Proposals and the closing date for proposal submission is
14th July 2014.
• EPC contract is expected to be signed in the 1st Quarter of the FY 2014/15.
Small Hydropower Projects: To further increase power generation capacity, government is promoting the
development of small hydros as follows:-
i)Detailed feasibility studies for a number of small hydro sites totalling to over 80 MW have been
completed and are due for implementation. These include: Kikagati (16 MW), Mitano (2.9 MW), Lubilia
(5.4 MW), Nyagak III (4.5 MW); Siti (21.5 MW), Waki (5.4 MW), Rwimi (10.54MW) Ndugutu (0.5 MW),
Nkusi (4.8MW) Nyamwamba (9.2 MW), Nengo Bridge (6.5 MW), Esia (0.11 MW) and Muzizi (44.5 MW
Peak Power).
Ii)In addition, feasibility studies for other sites are in their final stages these include: - Nsongezi (38 MW),
Ntono (2.5 MW), Sindoro (5.6MW) Achwa-Agago (88 MW), Kakaka (7.2 MW), Muvumbe (4.5MW)
Muyembe (3.2 MW) and Kyambura (8.3 MW).
Under the Global Energy Transfer Feed in Tariff (GET FiT) Program Government is fast-tracking the
development a portfolio of up to 15 small-scale renewable energy generation projects (1MW-20MW)
promoted by private developers with a total installed capacity of about 125MW. So far, twelve (12)
projects, representing 103MW have been approved under the GET Fit program. The approved projects
include: Nyamwamba (9.2 MW), Rwimi (5.5 MW), PH Industrial Farm’s (1 MW) biomass gasified maize
farm waste, Sugar Allied Industries Limited Cogeneration (6,9 MW) biomass (bagasse from sugar
production) plant in Kaliro district, Kikigati (16 MW), Kakira Cogeneration (20 MW) biomass using
bagasse from sugar production, Nengo Bridge (6.7 MW), Muvumbe (6.5 MW), Lubilia (5.4 MW), Waki
(4.8 MW), Siti I (6.1 MW) and Siti II (15 MW).
Vote Overview
4
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
The GET FiT program targets a total capacity of 190 MW within a period of 3 to 5 years which includes 20
MW of solar fed into the main grid. This program is supported by grants from development partners notably
Norway, UK, EU Commission and Germany. The World Bank will provide a Partial Risk Guarantee (PRG)
mechanism to secure against political and commercial risks.
Other energy sources of power generation: In order to reduce overdependence on hydropower and increase
the energy mix other power generation sources being developed include: Geothermal (200 MW), Modern
Biomass (150MW), Solar Thermal (200 MW), Solar PV (50 MW), Oil & Gas and Heavy Fuel Oil
(100MW).
Promotion and Development of Nuclear Energy: A strategy to develop the Nuclear Power Roadmap has
been prepared. The Roadmap will present recommendations on how major Nuclear Power Infrastructure
issues can be addressed in the short, medium and long term.
A five year (2014 – 2018) Country Programme Framework (CPF) between Government of Uganda and
International Atomic Energy Agency (IAEA) was signed on 17th September 2013 during the 57th regular
session of the IAEA General Conference in Vienna, Austria and subsequently launched on 14th November
2013, during the Joint Sector Review. This mutually agreed strategy is expected to match nuclear
technology to national priorities for sustainable development. The focus of the cooperation will be:
i)feasibility studies for nuclear power projects;
ii)uranium exploration and evaluation;
iii)cancer management;
iv)food and agriculture;
v)water resources management and
vi)strengthening the national nuclear and radiation safety infrastructure.
Pre-feasibility studies for launching the first nuclear power plant in Uganda are therefore being conducted
with support from International Atomic Energy Agency. Results of these studies will guide formulation of a
comprehensive nuclear power roadmap, nuclear energy policy, legislation and development of human
resources.
Grid Expansion Programmes – Transmission Infrastructure
Government will continue to expand the Transmission Network through the implementation of the
Resettlement Action Plan (RAP); undertake Feasibility Studies and construct new transmission lines and
substations as highlighted below.
For the financial year 2013/14; 150 km of 220kV lines, 1441.7 Km of 132kV and 35.2 Km of 66kV
transmission lines have been added to the national grid. In addition, 82.5 km of 132 kV Mutundwe -
Kabulasoke line was successfully re-conductored and refurbished to improve reliability of supply to
districts of South Western Uganda. A total of 16 substations were also added to the national transmission
grid infrastructure in the financial year 2013/2014.
PROGRESS ON INCREASING ACCESS TO MODERN ENERGY SERVICES
Grid based Rural Electrification
During the FY2013/14, a total of 1,657 km of High voltage lines (11kV and 33kV) and 806 km of Low
Voltage distribution lines were done. Ongoing Procurements in the FY2013/14 for implementation during
the FY 2014/15 are 3,279 km of high voltage lines (11kV and 33kV) and 2,977 km of low voltage
distribution lines.
In terms of connections, new customer connections made under the Rural Electrification Program during
the FY2013/2014 include 42,236 new connections in the grid areas, 4,942 new connections in the Off-grid
areas and 5,259 new solar PV connections.
Vote Overview
5
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017Fifteen (15) district headquarters were connected to the national grid over the past one year bringing the
number to 98 out of 112 (about 87.5%) districts. The districts are: Kyegegwa, Katakwi, Amuria, Kiruhura,
Buhweju, Lamwo, Nakapiripit, Amudat, Kaberamaido, Dokolo, Amolatar, Ntoroko, Alebtong, Moroto, and
Napak.
The major schemes under construction include: Gulu-Acholibur and Paicho-Patiko-Palaro; Gulu-Amuru-
Adjumani-Moyo; Hoima-Nyantozi-Kinyara-Biso-Butiaba/ Waki small hydro – Buliisa-Wanseko; Mayuge-
Bwodha; Rwemikoma-Buremba-Rukunyu; Rushere-Mugole-Kijuma; Mayuge / Namaingo Lumino-Busia;
Iganga-Namukudembe- Bulango & Luuka-Nakabugu; Bukwa – Suam; and Narweyo-Buhimba-Hoima;
Narweyo-Kisita-Nkoko-Bukuumi; Arua-Maracha-Koboko; Nyapea-Zombo-Zeu-Warr-Vurra Zombo; and
Nebbi-Nyaravur-Packwach-Panyamur with tee-off to Parombo.
Work has commenced on new projects which will connect additional eleven (11) districts of Bulisa,
Adjumani, Moyo, Amuru, Otuke Zombo, Koboko, Maracha, Yumbe, Nwoya and Namayingo. Three (3)
districts of Kotido, Kaabong and Kalangala will be supplied by the end of 2016 and thus completing the
long but steady journey of supplying electricity to all district headquarters of the country.
Solar based Rural Electrification for Social Services
Government is also increasing investments, mainly in solar-based electricity, to enable the delivery of social
services especially where the national grid has not reached. Solar-based electricity is used to support health
services through lighting, microscopy and other diagnostic services and the cold chain (storage of
immunization doses). It is also applied in pumping for rural water schemes and in schools, providing
lighting and power for science laboratories
Health Centres: In the course of the financial year, Government has provided solar energy packages to 130
Health Centres (HCs) in eight (8) districts: twelve (12) HCs in Amolatar, thirty (30) HCs in Pader and
Agago, nine (9) HCs in Buliisa, twenty nine (29) HCs in Gulu, twenty two (22) HCs in Moyo and twenty
eight (28) HCs in Soroti and Serere districts.
By the end of this year, an additional 180 HCs will be provided with solar energy packages in nine (9)
districts: Bukwo, Sironko, Mbale, Mayuge, Katakwi, Amuria, Masindi, Bududa and Bundibugyo.
Water Supply Schemes: Government has completed the installation of 20 solar-based water-pumping
schemes in fourteen (14) districts. The completed schemes are: Anaka, Purongo and Alero in Nwoya
district, Itula, Obongi and Lefori in Moyo district, Adwari, Okwang and Orumo in Otuke district, Kaabong
and Karenga in Kaabong district, Palenga in Gulu district, Erussi in Nebbi district, Kati in Arua district,
Midigo in Yumbe ditrict, Koboko in Koboko district, Usuk in Katakwi district, Mucwini in Kitgum district
and Alebtong in Alebtong district.
Schools: During the Financial Year Government completed the installation of solar energy packages in 287
Post-Primary Schools in 51 districts. Solar packages were provided in 14 schools in Lira district, 9 schools
each in Kitgum, Mayuge, Kyenjonjo and Kayunga districts, eight (8) schools each in Rakai, Soroti, Gulu,
Bundibugyo and Nebbi districts, seven (7) schools each in Kiboga, Amuria, Busia, Amuru, Pader and
Kamwenge districts, six (6) schools each in Nakasongola, Bugiri, Kiruhura, Isingiro, Ibanda and Kabale
districts, five (5) schools each in Masaka, Mbarara, Lwengo, Katakwi, Kisoro, Buikwe, Iganga, Koboko
and Moyo districts, 4 schools each in Kalangala, Masindi, Bukedea, Ntungamo, Sironko, Bukwo, Kanungu,
Kabarole, Adjumani and Yumbe districts, 3 schools each in Agago, Nakaseke, Kapchorwa, Moroto,
Nakapiripirit and Maracha-Terego and 2 schools in Kween.
PETROLEUM SUB-SECTOR
Government will continue to promote the establishment of the country’s petroleum resource base so as to
achieve sustainable exploitation. These efforts include building the national expertise in the field of
petroleum exploration, development and production; attraction of oil companies to invest in exploration and
production as well as commercialization plans of the oil and gas resources. The key highlights of the
Vote Overview
6
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017achievements include:
Legal Framework
The Petroleum (Exploration, Development and Production) Act, 2013 and the Petroleum (Refining,
Conversion, Storage and Transportation) Act, 2013 were enacted in April and July 2013 respectively. New
Petroleum Regulations for the two legislations Petroleum (Exploration and production) (Conduct of
Exploration Operations) Regulations will be issued this year in order to operationalize the new legislations.
The process of establishing the National Oil Company (NOC), Petroleum Authority of Uganda (PAU) and
the Directorate of Petroleum has progressed. Specifically for the NOC and PAU the process of identifying
the Board members is in final stages and the drafting of the memorandum and articles of association for the
NOC progressed. These Institutions are expected to commence during 2014/15 and will require seed money
from Government. The structure for the Directorate of Petroleum was approved by the Ministry of Public
service and is expected to commence during 2014/15.
Licensing Status and Investment Promotion
There are still three (3) international oil companies holding exploration licenses in four out of thirteen
Exploration Areas demarcated in the Albertine Graben. These companies are: - Tullow Oil Ltd., Total E&P
Uganda Ltd and CNOOC Uganda Ltd who hold a 33.33% joint venture in Discovery Areas or oil fields of
Exploration Area (EA) 1 (Paraa – Wanseko –Pakwach Basin), EA 2 (Northern Lake Albert Basin), and EA
3A (Southern Lake Albert Basin).
Preparation for the first licensing round scheduled for 2015 progressed with, i) Building of the stratigraphic
structure of the Albertine Graben (ii) review of the model contracts for acquisition, processing and
marketing of data and licensing; and iii) putting up the regulations for sale of petroleum data.
Status of Exploration
To date, a total of one hundred and sixteen (116) exploration and appraisal wells have been drilled in the
country, twenty two (22) of which were drilled during 2013/14. Of these wells one hundred one (101)
encountered hydrocarbons, thirty six (36) were exploration wells and eighty (80) appraisal wells. Twenty
nine (29) of the wells have been flow tested.
To date, twenty one (21) oil and/or gas fields have been discovered in the Albertine Graben namely:
Turaco, Mputa, Waraga, Nzizi, Kajubirizi (Kingfisher), Kasamene, Ngege, Nsoga, Ngiri, Jobi, Rii, Ngassa,
Taitai, Karuka, Wairindi, Ngara, Mpyo, Jobi-East, Gunya, Rii and Lyec. Four (4) of these (Ngassa, Karuka,
Taitai, TURACO) have reverted to Government and will be licensed during the forthcoming first licensing
round in the country and 17 of the discoveries were taken forward for appraisal and development by the oil
companies.
Appraisal for 9 (Kasamene, Warindi, Kigogole, Ngege, Ngara, Nsoga, Mputa, Nzizi, Kingfisher –whose
production license was awarded) of the discoveries has been completed, and applications for production
licenses submitted to government. These applications are still under review by government. Appraisal of the
remaining 7 (Jobi-East, Jobi-Rii, Mpyo, Gunya, Ngiri, Lyec, Waraga) discoveries is still on going and
should be completed by end of 2014.
One Production Licence over the Kingfisher field was issued during September 2013 and subsequently civil
works for the development of the field commenced. The field is expected to be ready for production by
2017/18. Bulk movement of materials for the development of this field is underway.
Production licences for the fields whose appraisal has been completed are expected to be granted during the
2nd half of 2014 and their development will commence during the 1st half of 2015. These fields include
Ngiri, Kasamene-Wairindi, Kigogole, Nsoga, Ngege, Ngara, Mputa and Nzizi. Production licences for the
fields whose appraisal is ongoing are expected to be granted before end of June 2015 and their development
Vote Overview
7
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017will commence during the 1st half of 2016. These fields include Jobi, Rii, Mpyo, Gunya, Jobi-East, Lyec
and Waraga.
The Development of the National Content Policy, Strategy and Plan progressed with two national
stakeholder consultation engagements having been held. The Policy strategy and plan are expected to be
completed during the next financial year. The Policy goal is to ensure that exploitation of petroleum
resources creates lasting values to the economy and people of Uganda, through maximizing the share of
local labour, local businesses, and local goods and services; and transfer of technology and know-how to
deepen the capabilities and competiveness of Ugandan individuals and businesses
Appropriate Commercialization Strategies
Government and the oil companies entered into a memorandum of understanding on how to commercialize
the country’s oil and gas resources. The high level commercialization plan contained in this MOU includes
i) the use of petroleum for power generation; ii) development of a 60,000barrels per day refinery in two
phases; and iii) development of a crude oil export pipeline. A detailed implementation plan for this
commercialization plan is currently being developed. In the short term and prior to the refinery coming on
stream, crude oil/gas to power generation capacity is being promoted. Major first oil is expected 2017/18.
Refinery Development Project
Government will develop the refinery on a Public–Private Partnership (PPP) basis through a joint venture
company with shareholding of 40% (forty percent) by the public sector and 60% (sixty percent) by the
private sector. Procurement of a Lead Investor for the oil refinery is on-going and six (6) firms have been
shortlisted, these include: China Petroleum Pipeline Bureau led consortium – China; Marubeni Corporation
– Japan; Petrofac led consortium – UAE; RT Global resources led Consortium – Russia; SK Energy led
Consortium – Korea; and Vitol SA (Swiss) led consortium with Samsung Engineering (Korea).
Several evaluation studies have been undertaken to enable Government make the right decisions with
regards to refinery development. The studies undertaken include an Environmental baseline study that was
concluded in December 2013. This study characterizes the current environmental and social conditions in
and around the refinery land was concluded. The environmental survey provides a benchmark for
comparing the state of the environment before the development of the refinery starts, when the operations
are being undertaken and also at decommissioning stage.
The process of acquiring land for refinery development has progressed. The implementation of the
Resettlement Action Plan (RAP) for the 29 sq.km of land proposed for the refinery in Kabaale Parish,
Buseruka Sub-county, Hoima District commenced in July 2013. Government has so far compensated about
50% of the PAPs and expects to complete the compensation process by end of 2014.
Petroleum Products Transportation and Storage
A feasibility study for the distribution and storage facilities of the refined petroleum products was
completed in 2012 and recommended a 205km long, 10 inch diameter pipeline, distribution by trucks from
Buloba to different demand centers. This proposal is to be developed as part of refinery project. The
feasibility study also recommended a refined petroleum products pipeline from Eldoret to Kampala
(Buloba) of a distance of 325km long, 12 inch pipeline and negotiations with the possible developer are
ongoing. Another feasibility study for the Kampala-Kigali Pipeline is to commence this year.
Strategic Fuel Reserves
Government through the Public Private Partnership (PPP) arrangement with Hared Petroleum Ltd
refurbished the 30 million litre Jinja storage facility and restocking is on-going
PETROLEUM SUPPLY AND DISTRIBUTION
Vote Overview
8
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017Uganda is currently a net importer of petroleum products. It imports about 95% of the products through
Kenya and 5% through Tanzania. The average annual growth of petroleum consumption stands at about
7%, which is attributed to an average economic growth of about 6 percent. Monthly consumption of
petroleum products is 125 million litres which translates to an annual figure of 1,500,000 cubic metres and
on a monthly basis, the country spends about US$ 156 million to import petroleum products.
At present there are 167 private oil-marketing companies established in Uganda involved in supply,
transportation, distribution and marketing of Petroleum products.
Kenya-Uganda Oil Pipeline Extension
The private investor demanded excessive guarantees like capacity payments if the refinery in Uganda
negatively impacts on the importation of petroleum products. Consequently, the project is being structured
as a public project and financing is being sought.
A Contract for carrying out a feasibility study for the Kampala-Kigali pipeline segment was signed between
M/S PENSPEN Ltd and the Governments on 8th January 2014. The feasibility study will take six (6)
months to complete.
THE MINERAL SECTOR
Uganda’s Mineral Resources
Uganda is endowed with a variety of Mineral Resources namely: metallic mineral resources like Copper,
Cobalt, Tungsten, Beryllium, Bismuth, Columbite-Tantalite, Gold, Tin, Iron Ores, Platinum Group of
Metals, Uranium and Rare Earth Metals. The Industrial minerals include:- Marble /limestone, Phosphate
(Apatite and francolite), Vermiculite, Kaolin, Bentonite, Diatomite, Gypsum, Glass sands, Salts, Feldspar,
Quartz, Pozzolana, Dimension Stones and Gemstones
The recent airborne geophysical surveys and new mineral reserves and targets
Government has recently accomplished extensive acquisition, processing and interpretation of airborne
geophysical data (magnetic, radiometric and selected electromagnetic) covering 80% of the country and the
airborne surveys were followed by ground geological and geochemical mapping country wide. A rising out
of the surveys carried out, government has been able to focus investors in the mineral sector to target and
quantify commercial mineral deposits. For example, four (4) mineral commodities, namely iron ore, gold,
vermiculite and limestone have been explored in sufficient detail and as a result, there has been a significant
increase in the mineral resources base in the country.
Airborne geophysical surveys of Karamoja region: Government will carry out airborne surveys this
financial year, estimated at USD 15million.
In addition to the previously known iron ore deposits of muko (30 million tonnes), Bukusa (23 million
tonnes), and Sukulu (45 million tonnes), new ore reserves discovered at Buhara in Kabale (48 million
tonnes), Nangara Kisoro (8 million tonnes) and Rugando, Butogota in Kanungu (55 million tonnes), now
total 116 million tonnes of iron ore and have a gross value of US$ 15.6 billion. A total of 7.8 million ounces
of gold which have been proven at Tiira in Busia (500,000 ounces), Kamalenge in Mubende (5 million
ounces), Mashonga in Bushenyi (I million ounces), Kampano in Ibanda (500 ounces) and at Alupe in Busia
(800,000 ounces) have a gross value of US$ 10.9 billion. Vermiculite reserves have increased from 5
million tonnes to 54.9 million tonnes at Namekhara in Manafa district and the reserves have a gross value
of US$ 11.5 billion. The limestone/marble reserves in the country have increased from the known 30
million tonnes in Hima, Dura Muhokya and Tororo to over 300 million tonnes after quantifying reserves in
Karamoja.
Other Mineral deposits and targets identified: Besides the ore deposits which have been proven as indicated
above, there are several ore deposits and targets which have been discovered and are not yet fully
Vote Overview
9
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017evaluated. These include the 3 billion aluminous clay reserves at Mukutu, Buwaya in Mayuge district
which contain Alumina and Rare Earths Elements; the new various mineral targets (plantinum group of
elements, iron ore, base metals and rare earths) in the country; over thirty (30) Uranium targets of which ten
(10) targets are of high priority; and bentonitic clays in Kaiso-Tonya area of Hoima.
Flagship Mining Projects
Copper at Kilembe Mines
The Ministry participated in the evaluation of proposals and negotiations of contract award for the
privatization of Kilembe Mines Limited under Public Private Partnership (PPP). M/S Tibet Hima Auto
Limited (THAL) of the Peoples’ Republic of China and Government of Uganda signed a concession
agreement on 6th September, 2013 for 25 years to develop the copper resources at Kilembe Mines.
Sukulu Phosphates
An Exploration License for the Sukulu phosphates was granted to M/S Guangzhou Dong Song Energy
Group Company Limited on 1st August, 2013 to develop the phosphate and Rare Earth Potential at Sukulu.
The company has already undertaken a feasibility study for production of 300,000 t/year of
superphospahate, 200,000 t/year of sulphuric acid and generation of power of 5 MW and is also currently
handling modalities for compensation of lawful occupiers of the land in Osukuru in Tororo district in
preparation for applying for a Mining Lease.
Iron Ore Discoveries
Follow-up of airborne surveys with ground geological and geochemical mapping resulted into new
discoveries of iron ore deposits in Kanungu, Buhara (Kabale district) and Mayuge areas. In general a total
reserve of over 100 million tones of iron ore has been evaluated in Muko and the sorrunding areas.
Four (4) mining leases, four (4) location licences, and two (6) exploration licences were granted over Muko
iron ore deposit. Interpretation of airborne geophysical surveys also revealed more discoveries of iron ore
deposits at Karukara, Kazogo, Nyamiyaga, and Mayebe in Buchimbiri Sub-County. Proposal to map out
and re- evaluate the reserves of iron ore countrywide is in place and awaits funds for implementation.
New Geological Maps produced
Nineteen (19) updated geological maps with new mineral potential zones at a scale of 1:250000 have been
produced and these include:- Fort Portal, Kampala, Mbarara, Homa Bay, Masaka, Kabale, Jinja, Arua,
Didinga, Mbale, Masindi, Hoima, Moroto, Aloi, Gulu, Packwach, Kaabong-Lodwar, Kitgum and
Kapenguria. The maps can be accessed through a geological and mineral information system portal at
www.uganda-mining-go.ug:81/ugandaGMIS.
Government will continue to undertake monitoring of earthequakes and the development of geothermal
resources in the country.
CHALLENGES IN THE ENERGY AND MINERAL SECTOR
Land Acquisition: To acquire land for infrastructure; and mineral development, petroleum and mineral
exploration takes a very long time and land is very costly. That delays project development and results into
high investment costs.
High Employee Turnover: Low pay for professional has affected the energy and mineral sector. Better pay
for Scientists in the sector so as to attract a strong pool of talented people including skilled and technical
personnel in the energy and mining disciplines is a requisite.
Institutional framework: The current structure makes it in-effective to cope with new challenges and
administrative burdens. The proposed new structure, if implemented, will go a long way to address this
Vote Overview
10
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Table V2.1: Past and 2014/15 Planned Key Vote Outputs
challenge with a focus on effective service delivery.
High power system losses at both technical and commercial levels: High energy losses reduce the revenues
required to provide affordable power. The technical losses are being addressed through rehabilitation and
refurbishment of the distribution line network.
Low access to modern energy forms especially among rural households: Expanding electricity coverage to
realize the required transformation in rural areas of Uganda in reasonable time poses unique challenges.
First, rural areas are characterized by low population densities due to dispersed settlements. Second, a
significant number of households are poor and find it difficult to connect and pay for electricity services.
Therefore, despite the heavy investment in the construction of the rural electrification infrastructure which
is capital intensive, the connection rates have remained very low.
Management of expectations created by the discovery of petroleum: The people of Uganda in general, and
in the areas where the discoveries have been made in particular, expect quick revenues, jobs and businesses,
among other things. There are also anxieties about the possible negative aspects of developing the oil
resources like environment degradation and how the revenues will be managed. To mitigate this challenge,
government has intensified the sharing of information on the realistic development programme of the sector.
MAJOR POLICY MEASURES TO BE PRONOUNCED IN THE FY 2014/15
Emplacement of the New Institutions (Petroleum Authority and the National Oil Company) to regulate
Exploration, Production and Value Addition of petroleum resources on one hand and to arrange the
commercial aspects of the country’s oil and gas business.
Opportunities to invest in Petroleum Exploration through a bidding round will be availed to investors.
Review of mining legislation in order to streamline licensing, monitoring, compliance and acquisition of
surface rights and enforcement of settlement policy.
Review of the Electricity Act in order to strengthen opportunities to increase energy mix and enhance
access through new concessions.
Achievements by End MarchPlanned outputs Planned Outputs
2013/14Vote, Vote Function Key Output
2014/15
Vote: 017 Ministry of Energy and Mineral Development
Vote Function: 0301 Energy Planning,Management & Infrastructure Dev't
Energy Efficiency Promotion030102Output:
Disseminated 50,000 improved
household stoves
Sales have been registered of up
to 10,810 household stoves, 12
sold for productive use (SMEs),
3 for social institutions and 1
rocket oven
Disseminated 10,000 improved
household stoves
Description of Outputs:
Renewable Energy Promotion030103Output:
Nyagak III Construction to be
undertaken.
Muzizi feasibility study to be
completed.
Nyamwamba: IA and PPA
construction to commence
Solar PV Systems in 7,000
household installed Solar
Energy Packages in 160 Health
Centers. 15 Water pump
Feasibility studies have been
completed on Nyagak III,
Muzizi and Nyamwamba.
Solar sales have been registered
of up to 327 household solar
systems, 60 systems sold for
productive use (SMEs), and 52
for social institutions. Sales of
up to 2934 pico pv systems
were registered
Nyagak III Construction:
(i) Private partner procured;
(ii) Construction commenced
Muzizi PPA and
Implementation Agreement;
Financing of project obtained.
Nyamwamba feasibility studies
completed,: PPA and
Implementation Agreement
finalized.
Rwimi: Feasibility completed
Description of Outputs:
Vote Overview
11
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Achievements by End MarchPlanned outputs Planned Outputs
2013/14Vote, Vote Function Key Output
2014/15
Increased Rural Electrification030104Output:
Continued to implement Rural
Electrification schemes to
extend power to district
headquarters and rural growth
centres.
A total of 1,657 km of High
voltage lines (11kV and 33kV)
and for Low Voltage
distribution lines 806 km have
been done.
Ongoing Procurements for
implementation during the FY
2014/15 are 3,279 km of high
voltage lines (11kV and 33kV)
and 2,977 km of low voltage
distribution lines.
New customer connections
made under the Rural
Electrification Programme for
FY2013/2014 include 42,236
new connections in the grid
areas, 4,942 new connections in
the Off-grid areas and 5,259
new solar PV connections.
Fifteen (15) district
headquarters were connected to
the national grid over the past
one year bringing the
number to 98 out of 112 (about
87.5%) districts. The districts
are: Kyegegwa, Katakwi,
Amuria, Kiruhura,
Buhweju, Lamwo, Nakapiripit,
Amudat, Kaberamaido, Dokolo,
Amolatar, Ntoroko, Alebtong,
Moroto, and
Napak.
- Construct 3,279Km of
medium voltage (33kV or 11kV)
- Construct 2,977 of low
voltage distribution lines
- 40,000 consumer
Connections made end of
financial year.
Connect at least 5 district
headquarters to the national grid
Description of Outputs:
Thermal and Small Hydro Power Generation (UETCL)030152Output:
Works have been delayed due to
protracted discussions with
investors
Power Purchase Agreements
(PPAs) and negotiations for the
plant undertaken
Thermal Power Capacity
charges paid
For the financial year 2013/14;
150 km of 220kV lines, 1441.7
Km of 132kV and 35.2 Km of
66kV transmission lines have
been added to the national grid.
In addition, 82.5 km of 132 kV
Mutundwe -Kabulasoke line
was re-conductored and
refurbished to improve
reliability of supply to districts
of South Western Uganda.
A total of 16 substations were
also added to the national
transmission grid infrastructure
in the FY 2013/2014.
Negotiations and
Implementation plan for the
thermal power plant concluded.
Construct 720km of 132kV and
419km of 220kV transmission
line;
Description of Outputs:
Vote Function: 0302 Large Hydro power infrastructure
Large Hydro Power Infrastructure030280Output:
Vote Overview
12
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Achievements by End MarchPlanned outputs Planned Outputs
2013/14Vote, Vote Function Key Output
2014/15
Construction of Karuma
Hydropower Plant starts.
Sinohydro Corporation
completed the topographical
resurvey and geological
investigations at most locations,
carried out certain design
changes in the diversion
channel, dam axis, power house
audits, and various facilities.
The preliminary layout
drawings of various components
of the project have been
developed. Detailed design is
completed.
Access roads to the dam area,
power intake area, main access
tunnel (MAT) area, escape and
ventilation tunnel (EVT) area
and muck dumping yard are
being constructed
Construction of Karuma
Hydropower Plant progresses at
10% of works.
Description of Outputs:
Vote Function: 0303 Petroleum Exploration, Development & Production
Capacity Building for the oil & gas sector030303Output:
Train eight (8) members of staff
in Petroleum Geoscience,
Engineering and Refinery
Design.
Increase national participation
from the current approx 10% to
20%
9 staff continued their Master’s
degree studies in various
Universities abroad.
The process of
operationalization of the new
petroleum institutions continued.
Recruitment of ten additional
staff on contract basis
commenced
Train seven (7) members of
staff in Petroleum Geoscience,
Engineering, Economics and
Refinery Design.
Description of Outputs:
Monitoring Upstream petroleum activities030304Output:
Monitor drilling of 30 wells in
three (3) EAs in the Albertine
Graben .
Monitor testing of at least 10
wells in the Graben.
Monitor of ten (10) campaigns
of seismic and other Geological
and Geophysical (G&G)
activities.
Monitoring on a 24-hour basis
for the following activities
undertaken;
-Drilling of Rii-2;
-Drilling of Mpyo-3A
-Testing of Rii-2 ;
-Acquisition of seismic in EA1;
-Kingfisher Development Area
(KFDA) Civil works;
-Ngassa-2 Plug and Production
License for the Kingfisher
Development Area issued and
development operations
commenced;
Acquisition of 3D seismic data
in EA1 and EA1A continued;
coverage was 74% recording of
the 405.8 km2 ;
Continued review applications
for production licenses over
Kigogole-Ngege-Nsoga-Ngara
(KNNN) and Kasamene-
Wahrindi (KW) in EA2.
Continued review applications
for production licenses over
Ngiri field in EA1.abandonment.
Complete the review of field
development plans (FDPs) for
eight fields in EA2 operated by
Tullow Oil;
- Complete review of FDP for
one field in EA1 operated by
TOTAL;
- Receive and review six other
FDPs to be submitted during the
financial year by TOTAL;
-Monitor development activities
over Kingfisher field operated
by CNOOC;
- Issue a production licenses
(PL) and monitor development
activities over Kasamene-
Waihrindi license operated by
Tullow Oil;
- Issue a production license
(PL) and monitor development
activities over Kigogole-Ngege-
Nsoga-Ngara license operated
by Tullow Oil.
Description of Outputs:
Develop and implement a communication strategy for oil & gas in the country030305Output:
Vote Overview
13
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Achievements by End MarchPlanned outputs Planned Outputs
2013/14Vote, Vote Function Key Output
2014/15
Public awareness in the oil and
gas sector undertaken.
Involvement of the public and
other stakeholders in the oil and
gas activities achieved.
Departmental website
maintained.
Participated in meetings
organised by the Rural Initiative
for Community Empowerment-
West Nile in four districts
namely. Buliisa, Nwoya, Nebbi
and Arua for district leaders and
the Business community
-Participated two dialogues
organised by Buliisa Rural
Initiative for Development
Organisation on Women
participation in oil and gas and
another on Land in Buliisa and
Masindi districts, respectively.
-Held an engagement with the
Anglican Bishops update them
on the developments in the
sector.
-Held media briefing on MoU
between Government and Oil
Companies ;
-Held five Radio talk shows on
Revenue Management
-Held five Radio talk shows on
Commercialisation Plans and
Land use Management
-Held five talk shows on
Environmental Management in
the Oil and Gas sector;
-Attended and facilitated a
meeting organised by the
Association of Oil and Gas
Service Providers of Uganda in
Nwoya.
-Commenced procurement for
upgrade of Website;
-Participated in three
community sensitization
meetings with persons affected
by the refinery organised by
Hoima Caritas Development
Organisation HOCADEO;
-Held 5 sensitisation meetings
in refinery area to sensitise
communities on prudent
utilisation of compensation
money;
-Held a community meeting
with communities and cattle
keepers in the refinery area over
Pastoralists who are
encroaching on refinery land.
Public awareness in the oil and
gas sector undertaken.
Involvement of the public and
other stakeholders in the oil and
gas activities achieved.
Description of Outputs:
Oil Refinery Construction030380Output:
Vote Overview
14
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Achievements by End MarchPlanned outputs Planned Outputs
2013/14Vote, Vote Function Key Output
2014/15
Land for the refinery and
supporting infrastructure
acquired.
Continued implementation of
Logistics study
recommendations.
Transaction Advisor’s assigned
duties for Refinery development
undertaken.
Pre - Front End Engineering
Design (FEED) for refinery
development completed.
Additional 960 Project Affected
Persons (PAPs) compensated
Land for resettling the PAPs
who opted for resettlement
identified and negotiations on
purchase price ongoing.
The Request for Proposal for
refinery lead investor was
issued in January 2014
Bidder’s conference held
between 12th-14th March 2014
between the shortlisted bidders,
Government of Uganda and
upstream oil companies
Engagements with CAA and
MoWT on how to take forward
the procurement of a consultant
for the master study continued
Finalise acquisition of Land for
the refinery and supporting
infrastructure
Construction of houses and
social infrastructure for the
PAPs
Lead investor for refinery
development procured
Formation of the Special
Purpose Vehicle (SPV) for the
refinery
Master plan for development of
an aerodrome developed
Transaction Advisor’s assigned
duties for Refinery development
undertaken.
Description of Outputs:
Vote Function: 0304 Petroleum Supply, Infrastructure and Regulation
Management and Monitoring of petroleum supply Industry030402Output:
Petroleum supply market
operations monitored for
compliance to Petroleum
Supply Act, 2003. Petroleum
standards enforced; Compliance
with applications for new
licenses evalauted
Continued with the Petroleum
supply market operations were
monitored for compliance to
Petroleum Supply Act, 2003.
Petroleum standards enforced;
Compliance with applications
for new licenses evalauted
Petroleum supply market
operations monitored for
compliance to Petroleum
Supply Act, 2003. Petroleum
standards enforced; Compliance
with applications for new
licenses evalauted
Description of Outputs:
Development of Petroleum Refinery and Processing030405Output:
Activity transferred to PEPD Refinery activities transferred to
the Refinery project
Description of Outputs:
Kenya - Uganda - Rwanda Oil pipelines030406Output:
Supervise wayleaves acquisition
and compensation of Project
Affected Persons
The JCC of Uganda and Kenya
is yet to conclude the
procurement of a lead investor
Supervise RAP for Malaba-Jinja
pipeline segment implemented
Description of Outputs:
Vote Function: 0305 Mineral Exploration, Development & Production
Institutional capacity for the mineral sector030502Output:
Undetake regular mineral
market research on mineral
prices.
Two (2) workshops to review
legal framework and improve
mining laws in the subsector.
Train Two (2) members of staff
in legal and and management
best practices
Six (6) members of staff
participate in sector investment
promotion.
Continue to improve mineral
analysis laboratory
infrastructure at Geological
Survey and Mines Department.
Acquiring, processing of
geoinformation/data and
updating of geoscience
databases.
•One hundred five (105)
publications and Twenty five
(25) reports were registered and
their metadata captured in
Libero and UDIS respectively.
The details of the reports
received are in the monthly
reports.
•Continued the maintenance of
Modern Documentation Center
information systems and digital
Data access via the Intranet at
http://www.minerals.go.ug and
internet at http://www.uganda-
mining.go.ug/webudis.
•Continued with Quality control
At least ten (10) Staff trained
(short term 5 Diploma & 3
MSc ). At least two 2 Staff
trained for PhD (long term).
Five (5) Seismometers and
three (3) Mineral analysis lab
equipment installed. Four (4)
geoscientific research papers
produed Four (4) map sheets
updated. Eight (8) Staff
Participate in three (3)
International Mineral
Investiment Promotion
workshops& conferences; and
Discover three (3)new
minerals potential targets for
mining
Description of Outputs:
Vote Overview
15
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Achievements by End MarchPlanned outputs Planned Outputs
2013/14Vote, Vote Function Key Output
2014/15
of Metadata in UDIS and
Libero.
•Updated the Economic Mineral
database with mineral
occurrences.
•Filed administrative records on
geodata/information user needs.
Geoinformation dissemination
and Mineral Sector Promotion.
•The Documentation Section
attended to 20 visitors and
relevant geoinformation on
Geothermal Exploration,
Research on minerals in Uganda
and geoinformation on geology
of Uganda, Mineral potential,
dimension stone of Pallisa,
Mineral potential and rare earth
elements was availed to them.
•The Documentation Section
maintained the DGSM website
on (www.uganda-mining.go.ug)
and 9661 users visited the
Website.
•Sold publications worth
Uganda shillings One hundred
sixteen thousand (116,000).
•Provided on complementary
basis the following publications
to different stakeholders for
further promotion of the sector:
24 copies of the Mining Act, 24
copies of the Mining
Regulations and 2 copies of the
Mineral Policy.
Cartography and GIS Activities
The cartography and GIS
section is responsible for
building and maintenance of
geoscience databases related to
geology, minerals and mineral
concession to assist investors in
their exploration and mining
activities. The following
activities were undertaken:
Update and maintenance of
geoscience databases and
MCRS administration.
•A total of Thirty Seven (37)
mineral right applications were
scanned, uploaded and validated
into the Mining Cadastre and
Registry system (MCRS).
•A total of forty one (41) title
prints of which 3 were for
Mining Leases, (1) for
Retention License, (36) for
Exploration License and (1)
Location license were prepared.
Vote Overview
16
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Achievements by End MarchPlanned outputs Planned Outputs
2013/14Vote, Vote Function Key Output
2014/15
•Twelve (12) Concession and
Mineral Occurrence maps to
guide the general public on the
licencing status and Mining
Investment opportunities in the
country were prepared.
•Geothermal manifestations and
Licencing status map was
prepared
Geoinformation dissemination
and promotion of the Mineral
Sector
•Geoinformation was availed to
at least seventy six (76) clients
with various technical needs
concerning geological maps,
minerals, mineral exploration
and mining activities as well as
staff of the Ministry.
Management of a geodata portal
•National and Regional (NW,
NE, SW and SE) Concession
and Mineral Occurrence maps
for the whole country to guide
the general public on the
licencing status and Mining
Investments opportunities in the
country were prepared
•GMIS portal was maintained at
http://www.uganda-
mining.go.ug:81/UgandaGMIS/
•The portal currently links data
from geology, geophysics,
Mining Cadastre and
Documentation center: links to
other data for Geothermal,
Seismology and data obtained
from karamoja project are to be
added to the portal for further
promotions of these activities.
Laboratory Services
•Sample preparation for assay of
nine (9) rock samples from
sheet 25/2 (Kailong) being
mapped under the Airborne
Geophysical Survey and
Geological Mapping of
Karamoja Programme.
•Project (UGA/2/002): a
Corporation Project between the
International Atomic Energy
Agency (IAEA) and the
Government of Uganda (GoU)
has been approved by the IAEA
and is to run from 2014 to 2017.
As part of the preparation for its
Vote Overview
17
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Achievements by End MarchPlanned outputs Planned Outputs
2013/14Vote, Vote Function Key Output
2014/15
execution by the Department of
Geological survey and Mines
(DGSM); training needs,
personnel, and equipment
requirements to strengthen the
national capacity for uranium
exploration and evaluation have
been identified.
•Undertook a review of the
project feasibility study report
by M/s Guangzhou Dong Song
Energy Group Company
Limited for the development of
the Osukulu phosphate deposit.
The following issues were
raised that need to be addressed
if the project is to meet all
statutory requirements for
sustainable exploitation;
consideration for
comprehensive extraction of
useful elements (iron, niobium,
scandium and rare earths) in the
deposit, optimal recovery,
management of hazardous
chemicals, inclusion of all
statutory payments and other
costs in the cash flow, and
emission of heavy metals and
mitigation measures.
•Carried out inventory of the
geothermal project equipment
•Carried out sampling and
analysis of consignments for
mineral dealers as part of the
requirements for application for
export permits
•Conducted analysis of six (6)
Wolfram samples for Tungsten
(WO3), six (6) coltan samples
for Columbite and Tantalite,
three (3) iron ore samples for
iron (Fe), eleven (11) samples
for high purity gold (Au), nine
(9) geochemical samples for
gold (Au), four (4) rock sample
for quartz, one (10 kaolin
sample for Fe, Ca, Mg, Al and
SiO2, two (2) marble samples
for Iron (Fe), Calicum (Ca),
Magnesium (Mg), Aluminium
(Al) and Silcon dioxide (SiO2)
one (1) salt sample for Sodium
Chloride ( NaCl) and
potassium Carbonate (K,CO3)
and SiO2, two (2) Cassiterite
samples for tin (Sn), one (1)
sample for Phosphates
pentoxide (P2O5,) two (2)
copper ore samples for Copper
(Cu). The details are presented
Vote Overview
18
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Achievements by End MarchPlanned outputs Planned Outputs
2013/14Vote, Vote Function Key Output
2014/15
in laboratory report of GSMD.
Services to stakeholders and
increased transparency and
governance in the mineral rights
management.
Geoinformation management
and dissemination continued
through both on the counter and
online systems at www.uganda-
mining.go.ug; www.uganda-
mining.go.ug:81/ugandaGMIS
and
www.flexicadastre.com/uganda
to facilitate access and
transparency of
geoinformation/data
management.
Laboratory Services: analysed
rocks, minerals, ores, water as
well as physical tests for rocks
for both government and private
sector. The details on outputs
undertaken are as follows:
i.Conducted industrial training
to atleast ten (10) students on
from Kyambogo, Makerere and
Nkumba Universities;
ii.Installation of five (5) the
fume hoods in the Analytical
Laboratories;
iii.Calibration of the X-Ray
equipment and Atomic
Absorption (AAS) which were
installed at the DGSM
laboratories in 2012;
iv.Procurement of a water
treatment equipment, slurry
pump, pulp density balance,
viscometer, analytical balances,
drying oven and backup system
for the equipment’s, additional
lamps for AAS, standard
reference materials for the X-
Ray equipment, Installation of
shelves for chemicals and
furniture for laboratory use; and
v. Installation of dust extractor,
jaw and roll crusher in the
mineral dressing laboratory.
Industrial training in GIS:the
department offered industrial
training on Principles and
Applications of Geographic
Information System (GIS), and
Cartography.to a total of a total
of twelve (12) students, of
Vote Overview
19
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Achievements by End MarchPlanned outputs Planned Outputs
2013/14Vote, Vote Function Key Output
2014/15
which three (3) were from
Geology Department-Makerere
University; two (2) from
Kyambogo University and
Seven (7) from Institute of
Surveys and Land Management.
Human resource development
One Senior Geophysicist
continues to pursue a four year
Doctorate of Philosophy (PhD)
in Exploration Geophysics at
Oklahoma State University,
United States of America.
One Geophysical Technician
completed his one year MSc
degree training course in
Seismology, Earthquake
Engineering and Disaster
Management Policy
administered by IISEE Institute,
Tsukuba and GRIPS Institute,
Tokyo Japan.
One Senior Chemist completed
a six months geothermal
training programme at the
United Nations University in
Rejkjavik, Iceland.
One Library Attendant,
completed a 3 years Bachelor’s
Degree in Library and
Information Science at
Makerere University.
Fencing of the two new
seismological sites (vaults) at
Mubende (Butologo) and
Wakiso (Nakauka) continued
and is nearly completed.
Mineral Exploration, development, production and value-addition promoted030503Output:
Muko iron ore is being mined to
feed domestic iron and steel
industry.
Sukulu need Ug.shs135bn for
RAP of 2, 500 families.
Detailed Geological,
geophysical, geochemical
surveys of key strategic
minerals relevant for domestic
industrialization.
Enabling agriculture
productivity and mapping of
Iganga, Kitaka-
Buhweju,Masindi- Karuma,
Naigobya,Mayuge Iron
Ore,Kafunjo-Ntugamo,Kaiso-
Bukusu a follow up of 16
Muko iron ore is being mined to
feed domestic iron and steel
industry and export.
Sukulu phospahtes was licenced
to a private developer and is yet
to commence on the RAP.
Number of new mineral
investiment projects initiated (5
Mining Leases issued). Number
of mineral targets mapped (10
mineral commodities per year).
4 topographocal map sheets
Description of Outputs:
Vote Overview
20
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
ENERGY PLANNING, MANAGEMENT & INFRASTRUCTURE DEV'T:
Electricity Generation
(a)………Large Hydro Power Project
(i) Construction of Karuma Hydro Power Project (600MW)
(ii) Commence construction of Isimba Hydro Power Project (183MW)
(iii) Complete feasibility study of Ayago Hydro power Project (600MW)
(iv) Commence with the construction of Nyagak III (4.5MW) and Muzizi (44.7MW) with co-funding
from the German Government through KfW
(v) Commence Generation of about 125 MW of electricity from different renewable energy sources
under GET FiT Programme
(vi) Complete the RAP Implementation for Isimba HPP & Associated T-Line.
(vii) Complete the RAP Implementation for Karuma HPP and Associated T-Line.
(b)……..Small Power Project
(i) RAP Implementation for Muzizi HPP commenced.
(ii) Financial closure attained for the construction of Muzizi HPP
(iii) Commence the Construction of at least Five Small Hydropower plants under GETFiT
(Nyamwamba-9.2MW, Siti 1 – 5MW, Waki – 5MW, Rwimi – 5.4MW, Kikagati 16MW and Nengo Bridge-
7.5MW)
2014/15 Planned Outputs
V3: Detailed Planned Outputs for FY 2014/15
Achievements by End MarchPlanned outputs Planned Outputs
2013/14Vote, Vote Function Key Output
2014/15
mineral targets.
Promotion of Karamoja
Airborne surveys. And
Geothermal development,
upgrading installation of
earthquake monitoring network.
Promote agro-geology as
Coporate Social Responsibility
(CSR) to Agriculture sector.
Map geosites as CSR to
Tourism sector.
Licencing and inspection030505Output:
Undertake administrative
reviews of all mineral rights
(licenses).
Monitor exploration and mining
operations. Twelve (12)
inspections to mining areas (3
inspections per quarter)
Mineral exploration and mining
areas monitored
500 mineral rights issued and
NTR of at least Ug.sh 5.0 bn
collected.
Undertook 5 Field inspections
are carried out to offer technical
advice, regulate and supervise
the exploration, development
and exploitation activities of
private sector operators.
120 mineral rights
granted. 12 site
inspections
Description of Outputs:
Vote Function: 0349 Policy, Planning and Support Services
Vote Overview
21
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017(iv) Commence the construction of Nyagak III.
(v) Capitalise UECCC credit sup port Instruments in support of private sector renewable energy
project development.
Transmission Infrastructure
(i) Construction of the following 220kV and 132kV projects:
-220kV Projects: Bujagali – Tororo – Lessos, Mbarara – Mirama – Birembo, Kawanda – Masaka, Nkenda –
Fort Portal – Hoima and Bujagali switchyard upgrade to 220kV
-1320kV projects: Tororo – Opuyo – Lira 132kV line, Mbarara – Nkenda 132kV line, Mutundwe –
Kabulasoke 132kV restringing and Namanve South, Luzira, Mukono and Iganga industrial park substations
(ii) Procurement of EPC contractors for the following projects: Isimba Interconnection, Karuma
Interconnection, Ayago Interconnection, Mutundwe Entebbe 132kV line, reinforcement of Lugogo and
Mutundwe substations and Upgrade Queensway substation.
(iii) Conclusion of feasibility study of the following projects: Hoima – Kafu 220kV line, Nkenda –
Mpondwe – Beni 220kV line, Ayago Interconnection project and Opuyo-Moroto 132kV Line.
(iv) Commencement of feasibility study, EIA&RAP study of the following projects: Lira – Gulu –
Nebbi – Arua 132kV line, Kikagati – Mirama-Nsongezi 132kV line, Masaka-Mbarara 220kV line, Lira-
Gulu-Agago 132kV line, Bulambuli (Atari)-Mbale Industrial parks 132kV line, Mutundwe-Entebbe 132kV
Line and Masaka-Mwanza 220kV Line
Energy Management Planned Activities
(i) Conduct Energy Week 2014
(ii) Develop and produce energy awareness materials
(iii) Commence implementation voluntary Energy Efficiency Standards and Label to promote efficient
electrical appliances on Ugandan market
(iv) Train at least 30 energy auditors and energy managers
Atomic Energy Council
(i) The Inventorisation project (continuation of FY2013/14) for all radiation sources country wide.
(ii) Construction of a waste storage facility at Mpoma project
(iii) The EPRP project
(iv) Setting up of a dosimetry Laboratory Project
(v) Inspection of all upcountry facilities
Biogas promotion
(i) Draft standards developed for biogas by end of FY;
(ii) Continue to support the development of a 10 kW plant by APAC Energy Limited
(iii) Identify other potential IPPs to develop biogas for power generation
(iv) Technical support to Uganda National Biogas Program
(v) Partner with KCCA and other actors to manage waste for energy production
(vi) Promote biolatrine technology in schools
(vii) Support the establishment of large scale biogas systems for electricity generation
Gasification promotion
(i) Promote household gasifier stoves
(ii) Scale up the operations of recently refurbished Nyabyeya gasifiers
(iii) Relocate and rehabilitate Buddo gasifier
(iv) Rehabilitate Kyambogo gasifier system
Vote Overview
22
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017(v) Support the installation of small scale gasifier units at community and institutional level for
electricity generation
Biofuels promotion
(i) Draft bio-fuels bill presented to parliament
(ii) Provide technical support to the Energy Multi-function platforms.
(iii) Promote growing of energy crops for biofuels production
Improved cook stove promotion
(i) Partner with key actors (WWF, EEP, BEETA) to promote BETs
(ii) Backstop EEP initiatives in promotion of BETs
(iii) Promote UNACC activities and initiatives
Briquetting technology promotion
(i) Promote small scale briquetting enterprises
(ii) Support the establishment of large scale briquetting enterprises
Atomic Energy Council
(i) Registration of sources of ionising radiation in Uganda.
(ii) Search and Secure Radioactive Sources.
(iii) Continue Inspection of facilities and sources therein.
(iv) Conclude the Enforcement Policy for regulations.
(v) Continue the Licensing of facilities of radiation sources.
(vi) Continue the Monitoring of occupationally exposed workers.
(vii) Development of five Year strategic plan.
(viii) Development of Safety Standards & Guidelines
(ix) Sensitize the public about radioactive sources.
Nuclear Energy Unit
(i) Finalise the development of Nuclear Energy Policy for Uganda.
(ii) Finalise the development of the Nuclear Power roadmap.
(iii) Continue coordination of technical cooperation programme.
PETROLEUM EXPLORATION, DEVELOPMENT & PRODUCTION
(a) Legal and Regulatory Framework
i.Following the putting in place of the Petroleum (Exploration, Development and Production) Act 2013 and
the Petroleum (refining, gas conversion, transmission and midstream storage) Act 2013, new Regulations
and Guidelines for the upstream and midstream activities will be concluded;
ii.Standards and Codes of both upstream and midstream activities to be developed
iii.Model Production Sharing Agreement (PSA) is to be reviewed and updated;
iv.Monitoring and Evaluation (M&E) strategy for the National Oil and Gas Policy (NOGP) implementation
will commence.
(b) Promotion of the Country’s petroleum potential and Licensing
i.Promotion of the country's petroleum potential both within and outside the country to be continued;
ii.A petroleum licensing round and acquire geological, geophysical and geochemical data in the unlicensed
basins and new areas prepared;
Vote Overview
23
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017iii.Non-exclusive seismic surveys, to acquire more geophysical data in old and new areas, in preparations
for a licensing round held;
iv.Resource assessment and laboratory analyses on the collected data and package them for promotional
purposes conducted.
© Capacity Building
i.Human resource development for the oil and gas sector through formal and informal training to be
continued;
ii.Eight (8) members of staff to train in Petroleum Geoscience, Engineering and Refinery Design at
postgraduate level;
iii.Continue supporting Government petroleum training institutions, Uganda Petroleum Institute Kigumba
(UPIK) and the Petroleum Degree (B.Sc. And M.Sc.)courses at Makerere University;
iv.Implement the National content policy for the oil and gas sector;
v.The new institutions, i.e. the Petroleum Directorate, the Petroleum Authority and National Oil Company
to be put in place.
(d) Monitor the exploration for oil and gas activities by oil companies
i.Monitoring of appraisal 3D seismic survey and conclude drilling of appraisal wells in EA1 and E1A,
accompanying well tests, plus other field operations continued;
ii.Evaluate applications for production licenses and accompanying Field Development plans and Petroleum
Reservoir Reports for fields whose appraisal is complete;
iii.Monitor the sale of Extended Well Test Crude oil.
(e) Construction of the data centre and office block
i.Complete Phase –2 of the construction of a data centre and office block;
ii.Commence construction of phase 3 of the data centre and office block;
iii.Maintenance of existing building and related infrastructure undertaken
(f) Complete putting in place and commence implementation of the Local content strategy and plan.
i.The National Content Policy formulated.
Ii.Local content policy and plan implementation commenced;
(g) Continue implementation of the Communication Strategy
i.Dissemination of information on oil and gas continued;
ii.Stakeholder sensitization on the ongoing oil and gas activities in the country continued;
iii.Media reporting on oil and gas sector improved.
(h) Continue participating in Regional initiatives.
i. Regional conferences organized and/or attended.
Ii. Eight regional meetings on oil and gas developments attended.
MIDSTREAM
(a)Investment Priorities and core projects
i.Compensation and resettlement of refinery project affected persons completed thus land for refinery
development acquired;
ii.Special purpose vehicle for refinery development formed;
iii.A Strategy and Plan for petroleum transportation and storage facilities developed;
iv.Detailed route survey for pipelines from the refinery, Hoima to Kampala terminal undertaken;
v.RAP for pipeline from the Hoima to Kampala terminal undertaken;
vi.Environmental Baseline Study for pipelines undertaken;
Vote Overview
24
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017vii.Mater plan and detailed engineering design study for aerodrome development concluded;
viii.Support the development of the crude export pipeline
ix. Continue building capacity in refining fields and pipeline development.
(b) Financing Strategy (Both Public and Private)
The refinery project will be developed on a Private-Public Partnership (PPP) basis through a joint venture
company. The proposed shareholding is 60% (sixty) private and 40% (forty) public and a debt to equity
ratio of about 70:30. The total project investment is estimated to be about USD 4bn.
It is also proposed that the East African Community Partner States participate with 10% out of the 40% of
the public shares. Consultations with the Partner States are ongoing to determine the best arrangement for
participation.
PETROLEUM SUPPLY, INFRASTRUCTURE & REGULATION
(i) Investment Priorities and core projects
Three projects will be core in FY 2014/15. These are:-
(a) Kenya-Uganda Refined Petroleum Products Pipeline
(b) Uganda-Rwanda Refined Petroleum Products Pipeline
© Development and stocking of Nakasongola fuel reserve
(ii) Kenya-Uganda Refined Petroleum Products Pipeline
During the FY 2014/15 this project will be at developmental stage with private operator having secured an
EPC contractor. Implementation of the Resettlement Action Plan will be carried out during this period
spearheaded by the two Governments in their respective territories
(iii) Uganda-Rwanda Refined Petroleum Products Pipeline
The feasibility study for this planned pipeline will be accomplished The Private Operator will be selected
under a Public Private Partnership arrangement during the FY 2014/15. The route in which the proposed
pipeline is to transect will be selected.
(iv) Development and stocking of Nakasongola fuel reserve
Development of Nakasongola will be undertaken upon completion and recommendations of the technical
studies. Stocking will commence once the facility is ready to receive the petroleum products.
(v) Role of Private Sector, Civil Society and Development Partners
The three projects enlisted above are on a Public Private Partnership arrangement private sector is involved,
civil society and development partners prospective firms will be sourced among these stakeholders.
MINERAL EXPLORATION, DEVELOPMENT & PRODUCTION
(i) Uranium Exploration: Carry out Uranium exploration on topographic map sheets 66/1 (Mobuku),
66/2 (Kahungye) and 39/2 (Pakanyi).
(ii) Geosites and Geoparks: Map geosites and geoparks and recommend for gazetting by the line
ministry.
(iii) National Seismological Network: Refurbish earthquake research facility and extension of the
network coverage to prone zones in Uganda.
(iv) Mining Environmental Laboratory: Establish and equip a mining environmental laboratory for
analyzing environmental samples.
(v) Uganda Mining Legislation: Review the mining legislation and gazette the Earth Scientist
(vi) Exploration of Rare Earth Element (REE): Follow up on the REE exploration with the view to
support the high technology industry development in Uganda.
(vii) Geodata backup and recovery program: Install sustainable data backup and offsite recovery
infrastructure.
(viii) Publication of the new geology and minerals map of Uganda: Publish new geological data obtained
during the SMMRP project to support research and investment in the mineral sector.
Vote Overview
25
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017(ix) Karamoja Project:
Carry out airborne geophysical surveys of Karamoja region
Continue geological mapping, geochemical and geophysical surveys and mineral resources assessment
of Karamoja to completion
Select mineral targets for ground follow up
Interprete and harmonize geophysical data and maps with the rest of Uganda
Update mineral resources map of Karamoja
Carry out inspections and monitoring of mining operations in Karamoja Region
Equip the regional office and installation of a mineral mini laboratory in Karamoja
(x) Geothermal project: To continue geothermal explorations in Kibiro, Katwe, Buranga, Panyimur and
other geothermal areas.
POLICY, PLANNING AND SUPPORT SERVICES:
(i) Develop a strategy to reduce the high labour turn over.
(ii) Operationalize the newly developed communication strategy and strengthen the communication
function.
(iii) Finalize the development of a consolidated five year strategic Investment Plan, Monitoring and
Evaluation Framework.
(iv) Renovate and manage Amber house and start the development of the adjacent plot.
(v) Support the operations of the new institutions (National Oil Company and Petroleum Authority)
created by the new legislation and new staff structure.
(vi) Strengthen the public relations office to link with the focal point persons at the local governments.
(vii) Planning, Budgeting and Monitoring undertaken
(viii) Financial Management undertaken.
(ix) Procurement and Maintenance of Assets and Stores
(x) Management of Human Resources.
Table V3.1: Vote Function Profiles, Programme/Project Profiles and Workplan Outputs
Vote Function: Energy Planning,Management & Infrastructure Dev't03 01
Services:
Responsible Officer:
Vote Function Profile
The vote function under the Energy Resources Department is responsible for
promoting increased investments in power generation; renewable energy
development; rural electrification; improve energy access; promote energy
efficient technologies; and also promote private sector participation in the energy
sector.
Commissioner ERD
Vote Function Projects and Programmes:Project or Programme Name Responsible Officer
Recurrent Programmes
03 Energy Resources Department Commissioner, ERD
Development Projects
0325 Energy for Rural Transformation II Coordination Manager, ERT II
0940 Support to Thermal Generation MD - UETCL
1023 Promotion of Renewable Energy & Energy Efficiency Assistant Commissioner, NRSE
1024 Bujagali Interconnection Project MD - UETCL
1025 Karuma Interconnection Project MD - UETCL
1026 Mputa Interconnection Project MD - UETCL
1137 Mbarara-Nkenda/Tororo-LiraTransmission Lines MD - UETCL
1140 NELSAP MD - UETCL
1144 Hoima - Kafu interconnection MD - UETCL
1198 Modern Energy from Biomass for Rural Development Assistant Commissioner - Renewable Energy
1212 Electricity Sector Development Project AC/ Electric Power
Vote Overview
26
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Energy Planning,Management & Infrastructure Dev't03 01
Project or Programme Name Responsible Officer
1221 Opuyo Moroto Interconnection Project MD - UETCL
1222 Electrification of Industrial Parks Project MD UETCL
1257 Mirama-Kikagati-Nshungyenzi Transmission Line MD - UETCL
1259 Kampala-Entebbe Expansion Project MD-UETCL
Programme 03 Energy Resources Department
Workplan Outputs for 2013/14 and 2014/15
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
- Supervision and and
Monitoring -Reports on the
Operations of Power Stations in
the Country in Place.
- Supervsion and Monitoring of
Feasibility Studies for Large
Hydropower Sites (Ayago).
Reports in Place.
- Supervision and Monitoring
of the Construction of Karuma
HPP. Progress Reports in Place.
- Energy Efficiency Bill
Approved by Cabinet and
Parliament
- Bio fuel Legislation approved
by Parliament.
- The Electricity Act 1999
Ammendment Bill approved by
Parliament
Operations of Power Stations
Monitored including: Bujagali
HPP, Kiira-Nalubaale Complex,
Namanve & Electromax
Thermal Power Stations.
Supervision Reports in Place.
-Pre-Feasibility Studies
conducted on Ayago HPP and
Final Survey Reports waited
from JICA.
-Procurement of the Consultant
to supervise the construction of
Ayago HPP and Completion of
the Feasibility Studies
Commenced. Reports in Place.
-Construction of the Karuma
HPP Continues. Supervision
Reports in Place
-Cabinet Memo on the Energy
Efficiency Bill revised to
include the Implementation
Financial Implications. Memo
Draft under consultations.
-Draft bio-fuels bill presented to
the First Parliamentary Counsel.
-The Guidelines for Sustainable
Biofuels Production in Uganda
were developed and published
Energy Policy/Plans
Dissemination, Regulation
and Monitoring
Operations of Existing Power
Stations in the Country
Monitored.
Construction works of ongoing
Power projects(Plants and
Distribution and Transmission
Lines) in the Country
supervised and monitored.
Supervision and Monitoring of
the construction Works for the
West Nile Grid Extension
Projects under KFW.
Feasibility Studies for Nyamba
B Hydropower Project
monitored
Feasibility Studies for Ayago
Hydropower Project completed.
Reconnaissance Studies for
identification of small
Hydropower Projects in the
Country undertaken.
Regional Projects Developed
(Mbarara-Mirama-Birembo and
Bujagali-Tororo-Lessos).
Monitor the Implementation of
the Cross-border electrification
Policy.
Regional Power and Energy
working group meetings
attended.
Energy Efficiency Bill approved
by Cabinet and Parliament.
Bio-fuel Legislation approved
by Parliament.
010103
Total 102,628 65,333 565,788
Commissioner, ERD
- To review and put in place modern policies and legislation that offer a conducive business
environment- To increase the energy mix in power generation, promote and co-invest in the
development of new power generation and transmission- To acquire and p
The Vote Function is responsible for promoting increased investments in power generation;
renewable energy development; rural electrification; improve energy access; promote energy
efficiency; and also promote private sector participation in the energy se
Responsible Officer:
Objectives:
Outputs:
Programme Profile
Vote Overview
27
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Energy Planning,Management & Infrastructure Dev't03 01
Programme 03 Energy Resources Department
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
Wage Recurrent
Non Wage Recurrent
Total
34,027
68,600
22,266
43,066
463,160
102,628
-Energy Efficient Technologies
Promoted.
-Energy Wastes in Institutions
and Industries Reduced.
-Energy Week 2013 Held.
-Energy Effciency Materials
Developed and Produced.
-Delopment of the Voluntary
Approach Adoptation of Energy
Efficiency Standard and Labels
finalised.
-Energy Management and
Cleaner Production Training
Conducted for Energy
Managers, Consulting
Engineers & Industrialists
Conducted.
Energy Week 2013 held from
24th to 28th September.
-Draft Energy Week 2013
Report (24th to 28th September
in Place.
-Identified Promotional Energy
Efficiency Materials on LPG,
Improves Fuelwood and
Charcoal Stoves, Electricity
Consumer Tips (calendars,
brochures, etc) produced and
disseminated.
-Development of the Voluntary
Approach Adaptation of Energy
Efficiency Standard and Labels
in Progress.
- Materials including brochures
and calendars with energy
efficiency messages distributed.
-Energy Efficiency Week 2013
Report Finalised. Report in
place
-Importers guide for the
purchase of energy efficient
appliances (air conditioners,
refrigerators, lighting
appliances, freezers and motors)
developed and sent to
stakeholders for comments.
Energy Efficiency
Promotion
-Energy Week 2014 Held.
-Energy Management and
Auditing Training Conducted
for Energy Managers,
Consulting
Engineers & Industrialists
Conducted
-Awareness campaigns on
Efficient use of Energy
conducted throughout the
country.
-Energy Efficiency
Materials
Developed, Produced and
Disseminated.
020103
Wage Recurrent
Non Wage Recurrent
Total
96,077
110,100
206,177
68,530
68,453
136,983
0
185,297
185,297
-Supervision of Renewable
Energy Projects under operation
and development i.e Nyagak I,
Buseruka,Isahaha, Mpanga,
Nyamwamba,Nyagak
III,Kikagati carried out.Reports
in place.
-10kW Biogas System set up in
Apac.
-Nyabyeya Gasifiers
refurbished.
-Biofuels Standards Developed.
-Biomass Energy Strategy
Developed.
-Solar Water Heaters Bye-laws
developed.
Operations of Renewable
Energy Projects Supervised and
Monitored including: Mpanga,
Buseruka, Ishasha in Kanungu,
Mubuku I under Kilembe
Mines, II under KCCL & III
under Tronder Power, Kinyara
with 5MW capacity and
1.5MW to the Grid and Kakira
with 35MW capacity with
22MW to the Grid. Supervision
Reports in Place.
-First Phase of the
Refurbishment of the Nyabyeya
Gasifiers Completed, test runs
conducted and some spare parts
identified. Testing Report in
Place.
-Development of the Biofuels
Standards in Progress.
–Develop the Biomass Energy
Strategy
In Progress with funding from
the UNDP. Final Draft under
review at MEMD.
-Consultative Meeting on the
Development of Solar Water
Heaters Bye-laws held in Mbale
Renewable Energy
Promotion
-Dissemination of Energy
Efficient Cookstoves
Monitored: 24,000 Household
Wood/Charcoal Cookstoves
and 40Institutional Cookstoves.
-Microhydro Power Sites less
than 100kW identified.
-Solar Energy Technologies
Promoted.
030103
Vote Overview
28
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Energy Planning,Management & Infrastructure Dev't03 01
Programme 03 Energy Resources Department
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
at Mbale Hospital Report in
Place.
Wage Recurrent
Non Wage Recurrent
Total
219,109
87,810
306,919
147,992
50,742
198,734
0
106,919
106,919
.Nuclear Energy Policy for
Uganda drafted.
-Public Awareness Campaigns
on Nuclear Energy Conducted.
-Peaceful Application of Atomic
Energy in all Sectors
Coordinated. Reports in Place
-A Radioactive Waste
Management Strategy for
Uganda Drafted
-IAEA Sponsored Technical
Cooperation Projects
Coordinated.
-Atomic Energy Council
Supported.
Preparation for stakeholders
consultative workshop to
review the draft Nuclear Energy
Policy for Uganda completed.
Workshop rescheduled for next
financial year pending studies
by the working groups.
Procurement of consultancy
services to design and produce
awareness materials on nuclear
energy was completed.
IAEA-TC Programme
Management Officer’s Mission
to Uganda was received on 27th
January 2014to review the
technical cooperation
programme.
-Supervised the IAEA-
Technical Cooperation Projects.
-80% of baseline data required
to develop of radioactive waste
management strategy collected.
-Procurement of consultant to
develop the documentary on
Peaceful Applications of
Nuclear Energy in Uganda and
was completed.Filming of the
documentary was completed on
20th March 2014.
--The Country Programme
Framework (CPF), 2014 -2018
between Government of
Uganda and International
Atomic Energy Agency (IAEA)
was launched on 14th
November 2013.
- Contract staff salaries for
NEU paid.
Atomic Energy Promotion
and Coordination
Nuclear Energy Policy for
Uganda developed
IAEA Technical Cooperation
Projects Coordinated
Capacity building for nuclear
energy programme conducted
Public Awareness Campaigns
on Nuclear Energy conducted in
Universities
Directory on Peaceful
Applications of Nuclear Energy
in Uganda Developed and
Produced
Radioactive Waste
Management Strategy for
Uganda developed
050103
Wage Recurrent
Non Wage Recurrent
Total
71,667
338,331
409,998
53,696
176,701
230,396
0
139,998
139,998
- Contribution to International
Organisations (IAEA &
IRENA) made.
Part Contribution to
International Organisations
(IAEA & IRENA) made. The
balance to be paid in the
subsequent quarters
Membership to IAEA Contribution to International
Organizations (IAEA & AFRA)
510103
Wage Recurrent
Non Wage Recurrent
Total
0
30,000
30,000
0
9,688
9,688
0
100,000
100,000
Vote Overview
29
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Energy Planning,Management & Infrastructure Dev't03 01
Programme 03 Energy Resources Department
Wage Recurrent
Non Wage Recurrent
GRAND TOTAL
420,880
634,841
1,055,721
292,484
348,649
641,133
463,160
634,841
1,098,001
Annual Workplan for 2014/15 - Outputs, Activities, Inputs and their Cost
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
Operations of Existing Power Stations in the Country Monitored.
Construction works of ongoing Power projects(Plants and Distribution
and Transmission Lines) in the Country supervised and monitored.
Supervision and Monitoring of the construction Works for the West Nile
Grid Extension Projects under KFW.
Feasibility Studies for Nyamba B Hydropower Project monitored
Feasibility Studies for Ayago Hydropower Project completed.
Reconnaissance Studies for identification of small Hydropower Projects
in the Country undertaken.
Regional Projects Developed (Mbarara-Mirama-Birembo and Bujagali-
Tororo-Lessos).
Monitor the Implementation of the Cross-border electrification Policy.
Regional Power and Energy working group meetings attended.
Energy Efficiency Bill approved by Cabinet and Parliament.
Bio-fuel Legislation approved by Parliament.
Monitor and Supervise Nalubaale HP Station, Kiira HP Station and
Bujagali HP.
Monitor and supervise Electromax Thermal Plant (50MW) in Tororo,
Namanve Thermal Power Plant and the Isolated Thermal plants in Moyo
and Adjumani
- Monitor and supervise Ishasha Hydropower Station, -6.5MW, Mpanga
Hydropower Station – 18MW, Kisiizi Hydropower Station, Buseruka
Hydropower Project – 9MW, Nyagak I Hydropower Station -3.5MW,
Bugoye Hydropower Project
Kasese Cobalt Company Limited Power Plant – 10 MW
Monitor and spervise Mobuku I HP Station – 5.4MW
-RAP Implementation for Muzizi HPP
- Monitor the construction of Nyamwamba HPP
– 9.2MW
-Siti I 5mw
-Rwimi 5.4mw
-Kikagati 16MW
-Nengo Bridge 7.5MW
-Produce progress reports on the construction works for the Industrial
Parks
Namanve , Iganga , Luzira and Mukono.
Monitor the construction of Regional Interconnections, Mbarara-Mirama-
Birembo and Bujagali –Tororo-Lessos (220kV)
Progress Reports on the construction works for the West Nile Grid
Extension Projects under KFW
Energy Policy/Plans Dissemination, Regulation and Monitoring010103
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Airtime and Data on MTN, Orange and UTL Lines
(Lines)
40.0 10,000
Fuel for monitoring ERD activities (Litres) 7,142.9 25,000
Permanent Staff (Person Years) 62.0 463,160
Allowances for monitoring of ERD activities
(Quarter)
4.0 10,000
Assorted Stationery (Quarter) 4.0 5,000
Assorted Toners (Quarter) 4.0 5,000
Allowances for field activities in Uganda (Trips) 4.0 20,000
Repair and Servicing of ERD motor vehicles (Units) 20.0 27,628
Vote Overview
30
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Energy Planning,Management & Infrastructure Dev't03 01
Programme 03 Energy Resources Department
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
Provide progress reports on the Feasibility Studies for Nyamba B
Hydropower Project
Consultant in place to complete the Ayago Hydropower Project feasibility
studies
One field activity for Site Identification and Reconnaissance studies for
Small HPP carried out in the Western and West-Nile regions
One field activity for Site Identification and Reconnaissance studies for
Small HPP carried out in the Eastern (Kapchorwa-Sironko-Mbale) region
Update of the GIS database to include new information and corresponding
Maps
Produce progress Reports on the Construction of Regional
Interconnections, Mbarara-Mirama-Birembo and Bujagali – Tororo-
Lessos (220kV)
Regional meetings held in regard to identification and implementation of
cross border electrification projects
Regional Power and Energy working group meetings attended
Energy Efficiency Bill presented to Cabinet
Energy Efficiency Bill presented to Parliament
Bio fuel Legislation presented to Parliament for approval
Wage Recurrent
Non Wage Recurrent
Total
463,160
102,628
565,788
-Energy Week 2014 Held.
-Energy Management and Auditing Training Conducted for Energy
Managers, Consulting
Engineers & Industrialists
Conducted
-Awareness campaigns on Efficient use of Energy conducted throughout
the country.
-Energy Efficiency
Materials
Developed, Produced and Disseminated.
-Preparations for the Energy Week 2014 and Energy Week 2014 held and
the respective activities.
-Energy Week Report 2014 finalised and Approved
-Stakeholder Consultations done for Energy Management and auditing
Training for Energy Managers, Consulting
Engineers & Industrialists
-Energy Management and auditing Training for Energy Managers,
Consulting
Engineers & Industrialists
Conducted, activities monitored and Six Energy Audits done
-Road shows conducted in Eastern region.
-Street Advertising in Kampala
Energy Efficiency Promotion020103
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Airtime and Data for MTN, UTL and Orange Lines
(Lines)
40.0 10,000
Fuel to facilitate EED field Planned activities
(Litres)
8,571.4 30,000
Allowances for field activities (Nights) 166.7 20,000
Facilitation of field activities in the country (Nights) 333.3 40,000
Assorted Stationery e.g Papers, Pens, Clips etc
(Pieces)
201.0 10,050
Assorted toners e.g 05A, 49A etc (Pieces) 57.0 19,950
Procurement of Office Furniture e.g Chair & Table
(Pieces)
10.0 20,000
Repair and servicing of m/v under EED (Units) 16.0 25,297
Hiring of Venues for workshops and seminars
(Venue)
4.0 10,000
Vote Overview
31
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Energy Planning,Management & Infrastructure Dev't03 01
Programme 03 Energy Resources Department
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
.Energy
Efficiency Materials produced and dissemination strategy Developed and
implemented.
-Dissemination of Energy Efficiency Materials continued.
Wage Recurrent
Non Wage Recurrent
Total
0
185,297
185,297
-Dissemination of Energy Efficient Cookstoves Monitored: 24,000
Household Wood/Charcoal Cookstoves and 40Institutional Cookstoves.
-Microhydro Power Sites less than 100kW identified.
-Solar Energy Technologies Promoted.
-Disseminate Energy Efficient Cookstoves: 24,000 Household
Wood/Charcoal & 40 Institutional Cookstoves
-Identify Microhydro Power Sites less than 100kW.
-Awareness Materials to promote Solar Energy Technologies Developed,
Produced and Disseminated.
Renewable Energy Promotion030103
Wage Recurrent
Non Wage Recurrent
Total
0
106,919
106,919
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Payment of training facilitators (Days) 16.7 5,000
Airtime and Data for MTN, UTL and Orange Lines
(Lines)
20.0 5,000
Fuel for field activities (Litres) 5,714.3 20,000
Facilitation of field activities under NRSE (Nights) 250.0 30,000
Advertising and Public Relations (number) 4.0 20,000
Assorted Stationery (Pieces) 60.0 3,000
Assorted Toners (Pieces) 20.0 7,000
Procurement of Office Items (Pieces) 5.0 5,000
Repair and servicing of NRSE MVs (Units) 11.9 11,919
Nuclear Energy Policy for Uganda developed
IAEA Technical Cooperation Projects Coordinated
Capacity building for nuclear energy programme conducted
Public Awareness Campaigns on Nuclear Energy conducted in
Universities
Directory on Peaceful Applications of Nuclear Energy in Uganda
Developed and Produced
Radioactive Waste Management Strategy for Uganda developed
Conduct consultations on the draft nuclear energy policy for Uganda
Nuclear Energy Policy for Uganda presented to Cabinet
Seven (7) national and 36 regional projects monitored and progress
reports available
Conduct ten (10) international short training courses/workshops/ meetings
on nuclear energy
Nuclear energy career seminar conducted in Kyambogo and Gulu
Universities
Directory on Peaceful Applications of Nuclear Energy in Uganda drafted
Consolidation of Baseline data on the Development of the Radioactive
Waste Management Strategy in Place.
Development of the Radioactive Waste Management Strategy
Commences. Status Report in Place
Atomic Energy Promotion and Coordination050103
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Airtime for MTN and UTL Lines (Lines) 40.0 10,000
Fuel for field activities (Litres) 10,000.0 35,000
Facilitation for monitoring NEU activities (Nights) 333.3 40,000
Assorted Stationery (Pieces) 125.0 6,250
Assorted Toners (Pieces) 25.0 8,750
Office Furniture (Pieces) 5.0 10,000
Tyres (Set) 2.0 8,000
Repair and Servicing of Motor Vehicles (Units) 12.0 21,998
Vote Overview
32
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Energy Planning,Management & Infrastructure Dev't03 01
Programme 03 Energy Resources Department
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
Wage Recurrent
Non Wage Recurrent
Total
0
139,998
139,998
Contribution to International
Organizations (IAEA & AFRA)
Contribution of to IAEA and AFRA made
Membership to IAEA510103
Wage Recurrent
Non Wage Recurrent
Total
0
100,000
100,000
Activities to Deliver Outputs:
Planned Outputs:
Output:
Grant or Transfer Cost
Contribution of to IAEA and AFRA made 100,000
Wage Recurrent
Non Wage Recurrent
GRAND TOTAL
463,160
634,841
1,098,001
Vote Overview
33
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Energy Planning,Management & Infrastructure Dev't03 01
Project 0325 Energy for Rural Transformation II
Workplan Outputs for 2013/14 and 2014/15
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
-Capacity Building in Rural
Energy Development ICT and
Improved Service Delivery
-ERT II Monitoring and
Evaluation Reports
Sixteen coordination meetings
were completed. Quarterly
Progress Report in place
- Sixteen monitoring visits were
completed. Investment Status
Report is in place
Energy Policy/Plans
Dissemination, Regulation
and Monitoring
-Capacity Building in Rural
Energy Development, ICT and
Improved Socail Service
Delivery.
-Stakeholder engagement for
Implementing agencies for each
quarter to assess
implementation & investments
status.
ERT II Status of Investment
Reported.
010103
GoU Development
External Financing
Total
24,735
0
24,735
3,534
0
3,534
30,000
50,000
80,000
-Energy saved through installed
energy efficiency solutions in
high load consumers
-Promote efficiency lighting
standards
5.4MW saved from energy
efficiency solutions.
Verification and progress
reports in place (The Energy
ESCO is still conducting audits
and installations at several
industries)
- UNOPS published an ITB in
October 2013 and has since
received a bid from one
supplier. (Evaluation of the bid,
award to supplier, issue of
contract is to proceed).
Procurement progress reports in
place (Delayed procurement)
Energy Efficiency
Promotion
-Energy Saved through installed
energy efficiency solutions in
high load consumers
-CFL Test Bench installed at
UNBS and User Trained.
-Dissemination of 4,000
Rechargeable Solar Lanterns.
-Energy Efficiency Awareness
conducted in Rural
Communities of Western,
Central, Eastern & Northern
Uganda through Mini-
exhibitions and engagement of
rural schools through energy
challenges and competitions.
020103
GoU Development
External Financing
Total
57,265
0
57,265
37,629
0
37,629
172,000
261,000
433,000
-Solar water heaters promoted
-Energy GIS database updated
GIS database on Renewable
Energy investments mapped.
Maps in place
Renewable Energy
Promotion
-Solar Water Heaters promoted.
-Energy GIS database updated
and beneficiaries trained on GIS
030103
Coordination Manager, ERT II
To put in place a conducive environment and related capacity for:- a commercially oriented
service delivery of energy and ICT, - small-scale renewable power generation schemes-
investment in rural electrification schemes and scaled-up delivery of elect
- Additional power generation from small, renewable energy resources- Independent grid
systems for relatively concentrated isolated areas with a potential for the use of electricity by
rural enterprises-Individual/institutional solar PV systems
Responsible Officer:
Objectives:
Outputs:
11/1/2009 6/30/2016Start Date: Projected End Date:
Project Profile
Donor Funding for Project:
2016/172012/13
Budget
2013/14
Budget 2014/15 2015/16
MTEF Projections
Projected Donor Allocations (UShs)
International Development Association (IDA) 1.306 22.920 0.000 0.00035.945410
1.306 22.920 0.000 0.00035.945Total Donor Funding for Project
Vote Overview
34
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Energy Planning,Management & Infrastructure Dev't03 01
Project 0325 Energy for Rural Transformation II
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
-20 ministry staff are equipped
with skills to generate maps
using GIS software
887 SWH systems installed
(Interventions are now
completed)
applications.
-Feasibility studies for mini
hydro sites concluded
GoU Development
External Financing
Total
45,000
0
45,000
11,445
0
11,445
135,000
545,000
680,000
-Increased access to ICT
services in rural areas
-Increased access to electricity
in rural areas
-Improved social service
delivery
Installation of Solar Energy
Packages in 494 Health
Centres, 498 Post Primary
Schools, 33 water pumping
stations and 4 Local
Government Institutions were
completed. Progress reports in
place
-Funds Transferred to Other
ERT Implementing Agencies i.e
MOES, MOH, MOLG,
MOWE, MEMD and UECCC.
Financial reports in place
Cross Sector Transfers for
ERT (Other Components)
-Increased access to ICT
services in rural areas.
-Increased access to electricity
in rural areas.
-Improved social Service
Delivery
530103
GoU Development
External Financing
Total
2,000,000
1,306,000
3,306,000
823,441
0
823,441
2,000,000
22,064,000
31,764,000
GoU Development
External Financing
GRAND TOTAL
2,127,000
1,306,000
3,433,000
876,049
0
876,049
2,337,000
22,920,000
32,957,000
Annual Workplan for 2014/15 - Outputs, Activities, Inputs and their Cost
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
-Capacity Building in Rural Energy Development, ICT and Improved
Socail Service Delivery.
-Stakeholder engagement for Implementing agencies for each quarter to
assess implementation & investments status.
ERT II Status of Investment Reported.
-Conduct Capacity Building in Rural Energy Development, ICT and
Improved Socail Service Delivery in UCC, MOWE, MOES & MOH.
-Preparation and Review of Quarterly Implementation Activity Reports.
-Report Status on ERT II investments.
Energy Policy/Plans Dissemination, Regulation and Monitoring010103
GoU Development
External Financing
Total
30,000
50,000
80,000
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Consultancy services under ERT II (Consultant) 2.0 50,000
Fuel for monitoring of ERT II activities (Litres) 857.1 3,000
Loading of MTN, UTL Airtime and Data on
modems (Pieces)
4.0 5,000
Procurement of Assorted stationery (Pieces) 4.0 4,000
Allowances for field activities (quarters) 4.0 5,000
Allowances for officers to monitor activities
(Quarters)
4.0 10,000
Repair and servicing of motor vehicles (Units) 4.0 3,000
Energy Efficiency Promotion020103Output:
Vote Overview
35
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Energy Planning,Management & Infrastructure Dev't03 01
Project 0325 Energy for Rural Transformation II
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
-Energy Saved through installed energy efficiency solutions in high load
consumers
-CFL Test Bench installed at UNBS and User Trained.
-Dissemination of 4,000 Rechargeable Solar Lanterns.
-Energy Efficiency Awareness conducted in Rural Communities of
Western, Central, Eastern & Northern Uganda through Mini-exhibitions
and engagement of rural schools through energy challenges and
competitions.
-Inspection confirmed Power Savings for Twelve (12) Beneficiary
Industries.
-Procure and install CFL Test Bench & Technicians (CFL Test Bench
Users) Trained at UNBS.
-Disseminate 4,000 Rechargeable Solar Lanterns.
-Conduct Energy Efficiency Awareness in Rural Communities of
Western, Central, Eastern & Northern Uganda through Mini-exhibitions
and engagement of rural schools through energy challenges and
competitions.
GoU Development
External Financing
Total
172,000
261,000
433,000
Activities to Deliver Outputs:
Planned Outputs: Inputs Quantity Cost
CFL test bench training and installation
(Consultancy)
3.2 316,000
Consultant on Energy management (Consultancy) 1.0 72,000
Allowances to facilitate field activities (Nights) 250.0 30,000
Hiring of venues for workshops (Venue) 6.0 15,000
-Solar Water Heaters promoted.
-Energy GIS database updated and beneficiaries trained on GIS
applications.
-Feasibility studies for mini hydro sites concluded
-Supervise subsidy disbursements, payments and inspection of 25 solar
water heater installations per quarter
-Produce financial and installation reports
-Quarterly GIS updates and at least one beneficiary unit trained
-Consultancy works for feasibility studies monitored each quarter
Renewable Energy Promotion030103
GoU Development
External Financing
Total
135,000
545,000
680,000
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Staff training (Staff) 15.1 680,000
-Increased access to ICT services in rural areas.
-Increased access to electricity in rural areas.
-Improved social Service Delivery
- Installations completed in 20 schools and 10 health centre IVs each
quarter
- Inspection of 25 community information centres in each quarter.
Cross Sector Transfers for ERT (Other Components)530103
Activities to Deliver Outputs:
Planned Outputs:
Output:
Grant or Transfer Cost
Ministry of Health 7,764,000
Ministry of Education 7,150,000
Ministry of Water 7,150,000
UECCC 2,000,000
Vote Overview
36
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Energy Planning,Management & Infrastructure Dev't03 01
Project 0325 Energy for Rural Transformation II
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
- 50 investment sites inspected per quarter.
- Funds disbursed to Investments Maintenance Contractors, UECCC&
UEDCL quarterly&
GoU Development
External Financing
Total
2,000,000
22,064,000
7,700,000
31,764,000
NTR
GoU Development
External Financing
GRAND TOTAL
2,337,000
22,920,000
7,700,000
32,957,000
Vote Overview
37
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Energy Planning,Management & Infrastructure Dev't03 01
Project 0940 Support to Thermal Generation
Workplan Outputs for 2013/14 and 2014/15
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
Subsidy to Power Sector Paid Capacity charges for Thermal
Power generation paid
Thermal and Small Hydro
Power Generation
(UETCL)
Subsidy to Power Sector Paid520103
GoU Development
External Financing
Total
68,000,000
0
68,000,000
35,730,400
0
35,730,400
68,000,000
0
68,000,000
GoU Development
External Financing
GRAND TOTAL
68,000,000
0
68,000,000
35,730,400
0
35,730,400
68,000,000
0
68,000,000
MD - UETCL
The project is aimed at addressing the effects on the tariff due to variations in costs of
production from the thermal generation.
Fluctuations in the tariff structure stabilised- Improvement in the Government’s fiscal
sustainability
Responsible Officer:
Objectives:
Outputs:
5/1/2005 6/30/2015Start Date: Projected End Date:
Project Profile
Annual Workplan for 2014/15 - Outputs, Activities, Inputs and their Cost
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
Subsidy to Power Sector Paid
Subsidy to Power Sector Paid
Thermal and Small Hydro Power Generation (UETCL)520103
GoU Development
External Financing
Total
68,000,000
0
68,000,000
Activities to Deliver Outputs:
Planned Outputs:
Output:
Grant or Transfer Cost
UETCL 68,000,000
GoU Development
External Financing
GRAND TOTAL
68,000,000
0
68,000,000
Vote Overview
38
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Energy Planning,Management & Infrastructure Dev't03 01
Project 1023 Promotion of Renewable Energy & Energy Efficiency
Workplan Outputs for 2013/14 and 2014/15
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
-Technical Support Provided to
the Energy Resources
Department through Renewable
Energy band Energy Efficiency
Activities.
-Programme to Implement the
Energy Efficency and
Conervation Law after
Approval by Parliament
Developed.
-Energy Efficiency Strategy for
Uganda (EESU) 2010-2020
Implemented.
Organized training on the
application of the new studio
tool for capturing the energy
balance.
-Decentralisation: westnile and
lango regions continue to be
supported in energy
mainstreaming. Request to this
effect has also been received in
ERD for more support in terms
of capacity building of District
local government to integrate
energy issues in their planning.
-Continued support to the
Energy and Minerals
Development sector working
group and planning of the 3rd
Annual Joint sector review.
-Development of the
Programme to Implement the
Energy Efficiency and
Conservation Law after
Approval by Parliament in
progress.
- Supported the workshop on
the final validation of the new
proposed principles to the
Electricity Act 1999
-Implementation of Energy
Efficiency Strategy for Uganda
(EESU) 2010-2020 continues.
-20 staff members of MEMD
have been supported with
various trainings.
Energy Policy/Plans
Dissemination, Regulation
and Monitoring
-Policy for Fuel Efficiency in
Transport Sector Formulated.
-Monitoring and Evaluation
(M&E) Tool for Energy
Projects Developed.
-Technical Support offered to
the Electrical Power,
Renewable Energy and Energy
Efficiency Activities.
010103
GoU Development
External Financing
Total
200,000
0
200,000
101,824
0
101,824
385,379
1,289,350
1,674,729
Assistant Commissioner, NRSE
The main objective is to improve access to modern energy services and the efficient use of
energy by households and the private sector, especially in Northern Uganda.
Expected Outputs- 150,000 improved household stoves disseminated.- 400 improved
institutional stoves disseminated.- 1,000 solar home systems disseminated.- 100 solar
institutional systems disseminated.- At least 350,000 tons of wood saved each year
Responsible Officer:
Objectives:
Outputs:
7/1/2008 5/31/2017Start Date: Projected End Date:
Project Profile
Donor Funding for Project:
2016/172012/13
Budget
2013/14
Budget 2014/15 2015/16
MTEF Projections
Projected Donor Allocations (UShs)
Germany Fed. Rep. 21.449 25.580 14.870 15.2300.000514
21.449 25.580 14.870 15.2300.000Total Donor Funding for Project
Vote Overview
39
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Energy Planning,Management & Infrastructure Dev't03 01
Project 1023 Promotion of Renewable Energy & Energy Efficiency
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
- Energy Week 2013 held.
- Energy Efficiency Awareness
Materials Developed and
Disseminated to Targeted
Consumers.
- Voluntary Approach
Programme for Adoption of
Energy Efficiency Standards
and Labels for five (5)
appliances (Fridges, Freezers,
AC Electric Motors, Lighting
Appliances and Air
conditioners) Finalised.
- Energy Audits Conducted for
four (4) Large Energy
Consuming Enterprises.
- SMEs Programme on
Identification of Relevant
Technologies and Financing
Opportunities Developed.
- Energy Efficient Equipment
installed in Public Institutions
monitored.
- Energy Management and
Cleaner Production Training
Programme Conducted for
Energy Managers, Industrialists
and Consulting Engineers
Conducted.
- 50,000 improved household
stoves distributed.
Energy Week 2013 held from
24th to 28th September. The
key act events included: An
Energy Exhibition & Launch of
the Energy Week 2013 at the
National Theatre, Preparation &
Distribution of awareness
materials, Power Losses
Reduction Forum 2013 on 25th
September 2013 at the Sheraton
Rwenzori Ballroom, Biomass
Dialogue and Energy
Management forum including
award of certificates to trained
Energy Managers on 27th
September 2013 at the Protea
Hotel.
-Road shows in Lira and Gulu
were organised under the
energy explorers campaign in
support of the energy week
-- Materials (including Tips on
energy saving for households,
improved biomass technologies,
fuel efficiency, LPG) have been
developed and produced.
-Bill Boards, street adverts,
Radio adverts, calendars and
pull up banners have been
developed to promote efficient
energy technologies (including
efficient lighting, efficient cook
stoves and fuel efficiency).
- Road shows conducted in
Kampala and Entebbe with the
focused on dissemination of
information on energy efficient
technologies and promotion of
renewable energy technologies.
They have been held in
Kampala (5-7th December) and
Entebbe (20-21st December).
Companies which participated
include Ugastove, Green
BioEnergy, and Wana Energy
Solutions
-Awareness brochures on
energy efficiency in households
(electricity, improved stoves
etc), and transport updated.
Importers guide for the
purchase of energy efficient
appliances done and will be sent
to stakeholders in Qtr 3 of FY
2013/14 for comments
-Communication strategy for the
adoption of Minimum Energy
Performance Standards (MEPS)
for five (5) appliances (Fridges,
Freezers, AC Electric Motors,
Lighting Appliances and Air
conditioners) finalized
-Six Energy Audits were carried
out for large energy consumers
(Bakhresa Grain Milling,
Wavah Water (U) Ltd,
Kawacom (U) Ltd, Maganjo
Grain Millers, Hotel Africana,
Golf Course Hotel) and Energy
Energy Efficiency
Promotion
-SME Programme on Identified
Energy Efficient Technologies
and Financing Opportunities
Conducted.
- Energy Audits Conducted for
four (4) Public Institutions.
- Energy Management and
auditing Training Conducted for
Energy Managers, Consulting
Engineers, Public Institutions &
Industrialists
Conducted.
-Implementation of the
Voluntary Programme on
Energy Efficient Standards and
Labels for five (5) appliances
(Fridges, Freezers, AC Electric
Motors, Lighting Appliances
and Air conditioners) Started.
- Energy Week 2014 and
Associated Activities Held.
- Energy Awareness Materials
on Efficient Use of Energy for
Households, Industries, Hotels,
Commercial Buildings, Schools
& Colleges Developed,
Produced and Disseminated.
020103
Vote Overview
40
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Energy Planning,Management & Infrastructure Dev't03 01
Project 1023 Promotion of Renewable Energy & Energy Efficiency
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
Audit reports compiled
- Development of the SMEs
Programme on Identification of
Relevant Technologies and
Financing Opportunities in
advanced stages.
- Energy Efficient Equipment
installed in Public Institutions
Monitored. Reports in Place.
Energy Efficient equipment
installed in Public institutions in
Western Uganda monitored
during December 2013
Energy Auditing &
Management Training
conducted 20th May to 12th
July 2013 for Forty Seven (47)
Energy Managers, Consulting
Engineers and Industrialists and
certificates awarded during the
Energy Management Workshop
held on 27th September 2013 at
Protea Hotel.
-9,295 improved household
stoves distributed.
-TOR for the baseline survey
finalized, and survey projected
to start in Qtr 3 of FY 2013/14
-Importers guide for the
purchase of energy efficient
appliances done and will be sent
to stakeholders in Qtr 3 of FY
2013/14 for comments
GoU Development
External Financing
Total
970,000
0
970,000
558,740
0
558,740
763,447
1,324,740
2,088,187
-Technical support to private
companies and Organizations
dealing households and
institutionsl energy saving
stoves.
-Fourty (40) Energy Saving
Institutional Stoves
Disseminated.
- Five (5) instituional solar/wind
energy systems installed in rural
schools and health units
-Large community solar water
pumping systems rehabilitated.
-Bwindi, Suam Micro
Hydropower and Moyo pico
hydro monitored.
-Solar Market Development
activities and standards
monitored.
- Awareness Materials on
renewable energy technologies
and applications Produced and
Disseminated.
-Sales have been registered of
up to 10,810 household stoves,
12 sold for productive use
(SMEs), 3 for social institutions
and 1 rocket oven.
-Lira District Local Government
(DLG) failed to pay its co-
funding. Beneficiary co-funding
was a prerequisite.
Consequently the MOU for Lira
DLG was terminated by end of
November 2013.
Therefore, after excluding the 8
social institutions (Sis) for Lira,
the total number of Sis reduced
from reduced from 38 to 30.
The 30 Social Institutions now
considered are situated in the
districts of Nebbi, Zombo,
Yumbe, Otuke, and Dokolo.
They include 23 Heath Centres,
4 schools, and 3 sub county
offices.
Procurement process of solar
PV for 30 social institutions is
in progress
- In Bwindi, a nursing school
Renewable Energy
Promotion
-Energy Efficient Cooking
Technologies Promoted
through Dissemination of
Efficient Institutional and
Household Cookstoves &
Training of Artisans.
-Five (5) Micro Hydropower
Sites less than 100KW
identified for Development.
-Operations of Bwindi & Suam
Micro-Hydropower Projects
Monitored.
- Solar Water Heaters (SWHs)
rehabilitated at Lira and Mbale
Referral Hospitals Refurbished.
-Wind Energy Technologies
Promoted through Collection
and Dissemination of Wind
Data on Speeds and
Applications (Mills & Water
Pumping).
-Existing Wind Mills for Water
pumping studied and packaged
for rehabilitation.
030103
Vote Overview
41
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Energy Planning,Management & Infrastructure Dev't03 01
Project 1023 Promotion of Renewable Energy & Energy Efficiency
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
-Uganda Renewable Energy and
Energy Efficeincy directory
produced
install wind data collection
systems and demonstration
systems
has been connected
- Preparations are underway for
the handover of Suam and
Bwindi to REA. The lease
agreements to be signed
between the operators and REA
were submitted to ERA
- In Suam, 45 SMEs, 1 mosque
and 42 households have been
connected to the minigrid
-Solar sales have been
registered of up to 327
household solar systems, 60
systems sold for productive use
(SMEs), and 52 for social
institutions. Sales of up to 2934
pico pv systems were registered
-Supported the site
identification visits to 6
potential areas in Karamoja
region. 2 sites at Napak and
Kotido have been selected to as
pilots
GoU Development
External Financing
Total
606,894
0
606,894
260,997
0
260,997
585,379
1,689,740
2,275,119
Purchase of Specialised
Machinery & Equipment
- Ten (10) small wind energy
systems procured
-Two wind measuring
equipment procured
- Computers for wind data
procured
770103
GoU Development
External Financing
Total
0
0
0
0
0
0
1,292,689
21,276,170
22,568,859
GoU Development
External Financing
GRAND TOTAL
1,776,894
0
1,776,894
921,560
0
921,560
3,026,894
25,580,000
28,606,894
Annual Workplan for 2014/15 - Outputs, Activities, Inputs and their Cost
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
-Policy for Fuel Efficiency in Transport Sector Formulated.
-Monitoring and Evaluation (M&E) Tool for Energy Projects Developed.
-Technical Support offered to the Electrical Power, Renewable Energy and
Energy Efficiency Activities.
-Development of Fuel Efficiency Policy Commences, Consultative
Workshops on the Fuel Efficiency Policy Conducted, Draft Fuel
Efficiency Policy presented to Cabinet for Approval and Final Fuel
Efficiency Policy Formulated and in Place.
- M&E Terms of Reference (ToR) and Bid Document produced.
-Procurement of the M&E Energy Project Tool Consultant Commences,
Energy Policy/Plans Dissemination, Regulation and Monitoring010103
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Consultancy on Energy Management (Consultant) 9.1 455,000
Consultancy Services (consultant) 1.0 754,350
Consultant to develop the M&E System
(Consultant)
5.5 55,000
Airtime and Data for UTL, MTN and Orange Lines
(lines)
32.0 8,000
Fuel to facilitate field activities (litres) 20,000.0 70,000
Facilitation for conferences abroad (Nights) 17.0 15,379
Facilitation for field activities (Nights) 166.7 20,000
Field Allowances (Nights) 125.0 15,000
Promotional Advertising (Pages) 5.7 40,000
Contract staff (Person Years) 1.0 150,000
Assorted Stationery (Pieces) 100.0 5,000
Assorted Toners (pieces) 20.0 7,000
Vote Overview
42
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Energy Planning,Management & Infrastructure Dev't03 01
Project 1023 Promotion of Renewable Energy & Energy Efficiency
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
Procurement of the M&E Energy Project Tool Consultant Concluded and
Tool Development Begins, Draft Energy Projects M&E Tool developed &
Consultations made and Final Energy Projects M&E Tool in Place.
-Technical Support offered to the Electrical Power, Renewable Energy and
Energy Efficiency Activities. GoU Development
External Financing
Total
385,379
1,289,350
1,674,729
Desktop Computers (Units) 2.0 10,000
Repair and Servicing of Motor Vehicles (vehicles) 40.0 50,000
Hiring of Venues for Workshops (Venues) 4.0 20,000
-SME Programme on Identified Energy Efficient Technologies and
Financing Opportunities Conducted.
- Energy Audits Conducted for four (4) Public Institutions.
- Energy Management and auditing Training Conducted for Energy
Managers, Consulting
Engineers, Public Institutions & Industrialists
Conducted.
-Implementation of the Voluntary Programme on Energy Efficient
Standards and Labels for five (5) appliances (Fridges, Freezers, AC
Electric Motors, Lighting Appliances and Air conditioners) Started.
- Energy Week 2014 and Associated Activities Held.
- Energy Awareness Materials on Efficient Use of Energy for Households,
Industries, Hotels, Commercial Buildings, Schools & Colleges Developed,
Produced and Disseminated.
-Develop and Conduct the SME Programme on Identified Energy
Efficient Technologies and Financing Opportunities.
-Conduct four (4) Energy Audits in Public Institutions.
-Conduct the Energy Management and auditing Training for Energy
Managers, Consulting
Engineers, Public Institutions & Industrialists.
-Commence the Voluntary Programme on Energy Efficient Standards and
Labels for the five (5) appliances (Fridges, Freezers, AC Electric Motors,
Lighting Appliances and Air conditioners) .
-Conduct the Energy Week 2014 and Associated Activities.
- Develop, Produce and Disseminate Energy Awareness Materials on
Efficient Use of Energy Developed and printed for Households, Industries,
Hotels, Commercial Buildings, Schools & Colleges.
Energy Efficiency Promotion020103
GoU Development
External Financing
Total
763,447
1,324,740
2,088,187
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Consultancy Service on Energy Efficienct Stds
(consultant)
3.5 1,522,740
Consultant on Voluntary Programme (consultant) 1.0 169,447
Consultant to conduct Energy Audits (consultant) 1.0 22,000
Airtime and Data for UTL, MTN and Orange Lines
(lines)
32.0 8,000
Fuel for EED Motor Vehicles (liters) 11,428.6 40,000
Facilitation for field activities (nights) 750.0 90,000
Promotion during the Energy Week 2014 (pages) 9.3 65,000
Assorted Stationery (pieces) 440.0 22,000
Assorted Toner (pieces) 80.0 28,000
Office Furniture (unit) 16.0 16,000
Desktop and Laptop Computers (units) 5.0 25,000
Repair and servicing of EED Vehicles (vehicle) 16.0 20,000
Hiring of Venues for Meetings (venue) 4.0 20,000
Hiring of Venues for Workshops (venue) 8.0 40,000
-Energy Efficient Cooking Technologies Promoted through
Dissemination of Efficient Institutional and Household Cookstoves &
Training of Artisans.
-Five (5) Micro Hydropower Sites less than 100KW identified for
Development.
-Operations of Bwindi & Suam Micro-Hydropower Projects Monitored.
- Solar Water Heaters (SWHs) rehabilitated at Lira and Mbale Referral
Hospitals Refurbished.
Renewable Energy Promotion030103
Planned Outputs:
Output:
Inputs Quantity Cost
Consultancy services (Consultant) 8.1 1,689,740
Consultant to train on building cook stoves
(Consultant)
1.0 135,000
Airtime and data for UTL, MTN and Orange (Lines) 40.0 10,000
Fuel to facilitate field activities (Litres) 14,285.7 50,000
Allowances for field activities (Nights) 169.8 20,379
Facilitation of field activities (Nights) 1,333.3 160,000
Promotion during the Energy Week 2014 (Pages) 4.3 30,000
Assorted stationery (Pieces) 250.0 12,500
Assorted toners (Pieces) 50.0 17,500
Vote Overview
43
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Energy Planning,Management & Infrastructure Dev't03 01
Project 1023 Promotion of Renewable Energy & Energy Efficiency
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
-Wind Energy Technologies Promoted through Collection and
Dissemination of Wind Data on Speeds and Applications (Mills & Water
Pumping).
-Existing Wind Mills for Water pumping studied and packaged for
rehabilitation.
-Promote Energy Efficient Cooking Technologies through Construction
and Dissemination of 40 Improved Institutional stoves and 10,000
Improved Household Cookstoves.
-15 Artisans Identified and Trained in the Construction of Energy
Efficient Cookstoves.
-Identify Five (5) Micro Hydropower Sites less than 100KW for
Development.
- Supervise and Monitor the Operation of Bwindi & Suam Micro-
Hydropower Projects. Report in Place.
- Refurbish the Solar Water Heaters (SWHs) installed at Lira and Mbale
Referral Hospitals.
- Promote Wind Energy Technologies through Collection and
Dissemination of Wind Speed Data and Applications (Mills & Water
Pumping).
- Conduct Studies on the Existing Wind Mills for Water pumping and
package them for rehabilitation.
GoU Development
External Financing
Total
585,379
1,689,740
2,275,119
Activities to Deliver Outputs:
small office equipment (pieces) 8,000.0 40,000
Desktopn and laptop computers (Units) 6.0 30,000
Vehicle maintenance (vehicle) 40.0 40,000
Hiring of venues for workshops (Venues) 8.0 40,000
- Ten (10) small wind energy systems procured
-Two wind measuring equipment procured
- Computers for wind data procured
- Procurement of Ten (10) small wind energy systems commenced and
completed. Deliveries and Installations made.
- Procurment, delivery, and installation of two wind speed measuring
equipments
Purchase of Specialised Machinery & Equipment770103
GoU Development
External Financing
Total
1,292,689
21,276,170
22,568,859
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Consultant on wind systems (Consultant) 1.1 205,148
Wind systems (Supplier) 45.2 22,363,711
GoU Development
External Financing
GRAND TOTAL
3,026,894
25,580,000
28,606,894
Vote Overview
44
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Energy Planning,Management & Infrastructure Dev't03 01
Project 1024 Bujagali Interconnection Project
Workplan Outputs for 2013/14 and 2014/15
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
Thermal and Small Hydro
Power Generation
(UETCL)
- Upgrade of Bujagali
Switchyard to 220kV
520103
GoU Development
External Financing
Total
0
0
0
0
0
0
1,023,947
12,480,000
13,503,947
GoU Development
External Financing
GRAND TOTAL
0
0
0
0
0
0
1,023,947
12,480,000
13,503,947
MD - UETCL
- To provide adequate transmission capacity for evacuation of electric power from Bujagali
Power Station.
Expected Outputs: Construction of 75 km of 220 kV double circuit transmission line from
Bujagali substation to Kawanda substation-; 17 km of 132 kV double circuit transmission line
from Kawanda substation to the existing Mutundwe substation-; 5 km of 132 kV double
circuit transmission line from Bujagali substation to the existing Nalubaale –Tororo
transmission line.
Planned outputs 2012/13: - Bujagali Interconnection Transmission Infrastructure RAP
Implementation finalised.
- Construction Works of Bujagali switchyard upgrade.
Responsible Officer:
Objectives:
Outputs:
7/1/2008 6/30/2015Start Date: Projected End Date:
Project Profile
Donor Funding for Project:
2016/172012/13
Budget
2013/14
Budget 2014/15 2015/16
MTEF Projections
Projected Donor Allocations (UShs)
Japan 17.900 6.550 0.000 0.0000.000523
Africa Development Bank (ADB) 5.190 5.930 0.000 0.00023.970401
23.090 12.480 0.000 0.00023.970Total Donor Funding for Project
Annual Workplan for 2014/15 - Outputs, Activities, Inputs and their Cost
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
- Upgrade of Bujagali Switchyard to 220kV
- Construction works: Electro-mechanical works, Testing,
commissioning, handover of facility and defects liability period activities
Thermal and Small Hydro Power Generation (UETCL)520103
GoU Development
External Financing
Total
1,023,947
12,480,000
13,503,947
Activities to Deliver Outputs:
Planned Outputs:
Output:
Grant or Transfer Cost
UETCL 13,503,947
Vote Overview
45
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Energy Planning,Management & Infrastructure Dev't03 01
Project 1024 Bujagali Interconnection Project
GoU Development
External Financing
GRAND TOTAL
1,023,947
12,480,000
13,503,947
Vote Overview
46
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Energy Planning,Management & Infrastructure Dev't03 01
Project 1025 Karuma Interconnection Project
Workplan Outputs for 2013/14 and 2014/15
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
- Construction of Karuma-
Kawanda, Karuma- Lira, and
Karuma - Olwiyo transmission
lines and associated substations
- Rap Implimentation
Finalise procurement of
supervision consultant
-Achieving financial closure for
implementation of EPC contract
from China Exim Bank
Acquisition of Other
Capital Assets
-Karuma- Kawanda, Karuma-
Lira, and Karuma - Olwiyo
transmission lines and
associated substations
constructed.
- RAP for Karuma- Kawanda,
Karuma- Lira, and Karuma -
Olwiyo transmission lines and
associated substations
Implimentated
790103
GoU Development
External Financing
Total
1,920,000
0
1,920,000
960,000
0
960,000
4,000
0
4,000
GoU Development
External Financing
GRAND TOTAL
1,920,000
0
1,920,000
960,000
0
960,000
4,000
0
4,000
MD - UETCL
- To provide adequate transmission capacity for evacuation of electric power from Karuma
hydro Power Station to meet demand
Expected Outputs: Construction of Karuma – Kawanda 400 kV (approximately 265 km),
Karuma – Lira 132 kV (approximately 80 km), Karuma – Olwiyo 132 kV (approximately
60km) transmission lines
Responsible Officer:
Objectives:
Outputs:
7/1/2008 6/30/2015Start Date: Projected End Date:
Project Profile
Annual Workplan for 2014/15 - Outputs, Activities, Inputs and their Cost
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
-Karuma- Kawanda, Karuma- Lira, and Karuma - Olwiyo transmission
lines and associated substations constructed.
- RAP for Karuma- Kawanda, Karuma- Lira, and Karuma - Olwiyo
transmission lines and associated substations Implimentated
- Construction of Karuma- Kawanda, Karuma- Lira, and Karuma -
Olwiyo transmission lines and associated substations
- Rap Implimentation for Karuma- Kawanda, Karuma- Lira, and Karuma -
Olwiyo transmission lines and associated substations.
Acquisition of Other Capital Assets790103
GoU Development
External Financing
Total
4,000
0
4,000
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Per Diem (Reports) 33.3 4,000
GoU Development
External Financing
GRAND TOTAL
4,000
0
4,000
Vote Overview
47
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Energy Planning,Management & Infrastructure Dev't03 01
Project 1026 Mputa Interconnection Project
Workplan Outputs for 2013/14 and 2014/15
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
- Construction of Nkenda-
Hoima 220kV transmission line
and associated substations.
- RAP Implementation
1.Wetland permit - Field visits
with NEMA complete. Permits
under process
2.Forest permit – engagement of
NFA is on-going
3.Work permit – to be applied
for by EPC contractors
4.Import licenses - to be applied
for by EPC contractors
5.Pre-award meeting with the
Best Evaluated Bidder for
Supervision and Project
Management of the EPC works
6.Preparation of the
transmission line
prequalification report
7.preparation of the substation
of the prequalification report
8.RAP implementation –
compensation at 77%
Acquisition of Other
Capital Assets
- Nkenda-Hoima 220kV
transmission line and associated
substations constructed.
790103
GoU Development
External Financing
Total
1,500,000
8,056,800
9,556,800
441,667
0
441,667
1,500,000
90,354,068
91,854,068
GoU Development
External Financing
GRAND TOTAL
1,500,000
8,056,800
9,556,800
441,667
0
441,667
1,500,000
90,354,068
91,854,068
MD - UETCL
- To meet the energy needs of the Ugandan population for social and economic development-;
- Provision of adequate transmission capacity to evacuate power generated at Mputa thermal
Power Plant-; Provision of hydro/thermal generation mix to mitigate hydro
Expected Outputs:
- Nkenda – Hoima 220kV transmission line (approx. 226km);
- Hoima substations and substation extension at Nkenda
Planned outputs 2012/13:
- RAP implementation
- Procurement of supervision Consultant
Responsible Officer:
Objectives:
Outputs:
7/1/2008 6/30/2015Start Date: Projected End Date:
Project Profile
Donor Funding for Project:
2016/172012/13
Budget
2013/14
Budget 2014/15 2015/16
MTEF Projections
Projected Donor Allocations (UShs)
Norway 8.057 90.354 27.270 7.00032.452535
8.057 90.354 27.270 7.00032.452Total Donor Funding for Project
Vote Overview
48
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Energy Planning,Management & Infrastructure Dev't03 01
Project 1026 Mputa Interconnection Project
Annual Workplan for 2014/15 - Outputs, Activities, Inputs and their Cost
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
- Nkenda-Hoima 220kV transmission line and associated substations
constructed.
- Construction of the 220kV transmission line and associated substation.
Acquisition of Other Capital Assets790103
GoU Development
External Financing
Total
1,500,000
90,354,068
91,854,068
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Commencement of EPC Works (Line) 1,156.9 91,854,068
GoU Development
External Financing
GRAND TOTAL
1,500,000
90,354,068
91,854,068
Vote Overview
49
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Energy Planning,Management & Infrastructure Dev't03 01
Project 1137 Mbarara-Nkenda/Tororo-LiraTransmission Lines
Workplan Outputs for 2013/14 and 2014/15
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
- Construction of Mbarara-
Nkenda & Tororo-Lira
transmission lines and
associated substations
-RAP implemnetation
•Total Route approved – 233
Km (87%)
•Total DCPT completed -506
out of 740 locations (68%)
•Total Excavation Completed –
197 out of 740
•Total Foundation Completed –
190
•Total Backfilling completed –
183
•Total Tower Erection
completed - 25
•Total Tower Material
received - 2726.7 MT (56%)
•Total conductor received – 649
km
•Total earth wire received- 180
km
•OPGW received – 67 km
•Survey- 95%
Opuyo substation
•Engineering documents/
technical submissions – 75%
•Approval – 45%
•132kV SF6 CB, 132kV &
33kV Surge Arresters, 132kV
CVT and 132kV CT has been
received at site
•15 MVar Shunt Reactor
despatched
•Metallic container Store
established on site
•Survey works completed
•Civil works – 0%
•Opuyo substation progress is
estimated at 26%
LOT 2
•Total Route approved – 157.4
Km (97%)
Acquisition of Other
Capital Assets
-Mbarara-
Nkenda (Lot 2) &Tororo-Lira
(Lot 1) transmission lines and
associated substations
constructed.
790103
MD - UETCL
1) The general objective of component 1 is to provide a high voltage backbone between
Mbarara and the mid Western towns
2.) The objective of component 2 is to replace the wooden poles that are prone to fires and
other natural hazards with steel tower structures
1.) Acquistion of Right of Way (ROW) through compensation and resettlement of Project
Affected Persons
2.) Procurement of contractor(s) for works.
3.) Construction of Mbarara – Nkenda 132kV (160km) and Tororo – Opuyo –Lira 132kV
(260km) transmission line
Responsible Officer:
Objectives:
Outputs:
7/1/2010 6/30/2015Start Date: Projected End Date:
Project Profile
Donor Funding for Project:
2016/172012/13
Budget
2013/14
Budget 2014/15 2015/16
MTEF Projections
Projected Donor Allocations (UShs)
Africa Development Fund (ADF) 105.294 103.950 0.000 0.00037.770402
105.294 103.950 0.000 0.00037.770Total Donor Funding for Project
Vote Overview
50
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Energy Planning,Management & Infrastructure Dev't03 01
Project 1137 Mbarara-Nkenda/Tororo-LiraTransmission Lines
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
•Total DCPT completed - 421
out of 452 locations (93.1%)
•Total Tower Excavation
Completed – 118 out of 319
tower locations
•Total Tower Foundation
Completed – 115
•Total Tower Backfilling
completed – 112
•Total Tower Erection
Completed - 12
•Monopole foundation
excavation – 6 out of 133
locations
•Monopole foundation
completed - 0
•Total Tower Material
Received - 1845.8 MT (84%)
•Total Pole Material received -
220 MT (16%)
•Total conductor received – 550
km
•Total earthwire received – 49
km
•Total OPGW received – 65 km
•Check Survey in National Park
in progress
•Survey- 85%
Fort Portal substation
•Consignment of 132 kV
Switchgear equipment received
at site
•Survey works completed
•Mobilisation for road works
made
•55 No’s of Foundations
excavated out of a total of 103
foundations
•PCC Completed in 54 No’s of
foundations out of 55 excavated
•PCC for the balance 1 no of
foundation ( power transformer
) is being done
•Retention wall at edges of
filled substation area started
•SF6 Gas Handling device
under despatch.
•40MVA Transformer
despatched
•33kV Indoor GIS FAT
conducted in Germany
•Power Transformer & 15 Mvar
Reactor FAT concluded
•Engineering documents/
technical submissions – 89%
•Approval – 80%
•overall construction progress –
33%
GoU Development
External Financing
Total
5,400,000
105,294,300
110,694,300
3,561,872
0
3,561,872
3,518,621
103,950,000
107,468,621
GoU Development
External Financing
GRAND TOTAL
5,400,000
105,294,300
110,694,300
3,561,872
0
3,561,872
3,518,621
103,950,000
107,468,621
Vote Overview
51
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Energy Planning,Management & Infrastructure Dev't03 01
Project 1137 Mbarara-Nkenda/Tororo-LiraTransmission Lines
Annual Workplan for 2014/15 - Outputs, Activities, Inputs and their Cost
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
-Mbarara-
Nkenda (Lot 2) &Tororo-Lira (Lot 1) transmission lines and associated
substations constructed.
- Construction of Mbarara-
Nkenda (Lot 2) &Tororo-Lira (Lot 1) transmission lines and associated
substations.
Acquisition of Other Capital Assets790103
GoU Development
External Financing
Total
3,518,621
103,950,000
107,468,621
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Consultant to Supervise the Erection of Lines
(Consultant)
3.5 1,400,000
Construction EPC (Line) 10,000.0 103,950,000
Taxes (UETCL) (Taxes) 1.0 2,118,621
GoU Development
External Financing
GRAND TOTAL
3,518,621
103,950,000
107,468,621
Vote Overview
52
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Energy Planning,Management & Infrastructure Dev't03 01
Project 1140 NELSAP
Workplan Outputs for 2013/14 and 2014/15
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
-RAP implementation
- Construction works of
Bujagali-Tororo-Lessos and
Mbarara-Mirama- transmission
lines
The current disbursement level
stands at 19.73% for ADF and
21.9% for JICA.
- Foundation works commenced
for Bugali- Lessos line (lot A)
and 69 out of an estimated
399no; foundations are
complete.
- Line route alignment for
Mbarara- Mirama line (lot B) is
complete and the survey is 60%
complete.
-Lot C contractor received 3 out
of 4 sites. Pending is Mirama
site. Site clearance and levelling
commenced for Tororo and new
Mbarara substations.
-Procurement of contractors for
construction of resettlement
houses for Project Affected
Persons is ongoing.
- RAP Implementation progress
is at 72%.
Acquisition of Other
Capital Assets
- Bujagali-Tororo-Lessos and
Mbarara-Mirama- transmission
lines Lot A: Uganda-Kenya; Lot
B: Uganda-Rwanda and Lot C:
Substations constructed.
790103
MD - UETCL
Improve access to electricity in Nile Basin Initiative (NBI) countries through increased cross-
border sharing of energy and power. To lead to the construction of the Bujagali-Tororo-
Lessos and Mbarara- Mirama-Birembo transmission lines and their associated sub stations.
Expected Outputs:
A constructed, tested, commissioned and fully operational 220kV Bujagali-Tororo-
Lessos(Uganda part approximately 127.7km) and 220kV Mbarara – Mirama – Birembo
(Uganda part -66km) on self supported steel lattice towers. Mirama substation and associated
bays at Tororo and Mbarara North substations
Planned outputs 2012/13:
- RAP Implementation
- Procurement of EPC Contractor
- Construction works for Bujagali – Tororo-Lessos and Mbarara-Mirama-Birembo
transmission lines
Responsible Officer:
Objectives:
Outputs:
7/1/2010 6/30/2015Start Date: Projected End Date:
Project Profile
Donor Funding for Project:
2016/172012/13
Budget
2013/14
Budget 2014/15 2015/16
MTEF Projections
Projected Donor Allocations (UShs)
Norway 2.440 2.600 1.300 0.0000.000535
Japan 132.064 40.560 14.570 14.9600.000523
Africa Development Bank (ADB) 15.190 14.310 7.230 0.0000.000401
149.694 57.470 23.100 14.9600.000Total Donor Funding for Project
Vote Overview
53
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Energy Planning,Management & Infrastructure Dev't03 01
Project 1140 NELSAP
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
GoU Development
External Financing
Total
3,200,000
149,694,200
152,894,200
2,250,414
0
2,250,414
4,637,253
57,470,000
62,107,253
GoU Development
External Financing
GRAND TOTAL
3,200,000
149,694,200
152,894,200
2,250,414
0
2,250,414
4,637,253
57,470,000
62,107,253
Annual Workplan for 2014/15 - Outputs, Activities, Inputs and their Cost
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
- Bujagali-Tororo-Lessos and Mbarara-Mirama- transmission lines Lot A:
Uganda-Kenya; Lot B: Uganda-Rwanda and Lot C: Substations
constructed.
- Construction works of Bujagali-Tororo-Lessos and Mbarara-Mirama-
transmission lines Lot A: Uganda-Kenya; Lot B: Uganda-Rwanda and Lot
C: Substations.
Acquisition of Other Capital Assets790103
GoU Development
External Financing
Total
4,637,253
57,470,000
62,107,253
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Consultant to Supervise the EPC Works
(Consultant)
1.0 375,406
Construction EPC (Line) 108,878.9 58,794,594
Taxes (UETCL) (Taxes) 1.0 2,937,253
GoU Development
External Financing
GRAND TOTAL
4,637,253
57,470,000
62,107,253
Vote Overview
54
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Energy Planning,Management & Infrastructure Dev't03 01
Project 1144 Hoima - Kafu interconnection
Workplan Outputs for 2013/14 and 2014/15
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
-Feasibility study for Hoima-
Kafu feasibility study
concluded
- Supervision Consultant
- RAP Implementation
Contract Extension Delayed but
approved
-Feasibility Study on-going;
90% completed.
-ESIA & RAP Studies on-going
completed
Acquisition of Other
Capital Assets
- RAP Implementattion
Consultant for Hoima -
Kinyara - Kafu Interconnection
Procured.
- Supervision Consultant for
Hoima - Kinyara - Kafu
Interconnection Procured.
- EPC Contractor for Hoima -
Kinyara - Kafu Interconnection
Procured.
- Resettlement Action Plan for
Hoima - Kinyara - Kafu
Interconnection Implemented.
790103
GoU Development
External Financing
Total
3,000,000
839,600
3,839,600
1,555,255
0
1,555,255
3,000,000
1,670,000
4,670,000
GoU Development
External Financing
GRAND TOTAL
3,000,000
839,600
3,839,600
1,555,255
0
1,555,255
3,000,000
1,670,000
4,670,000
MD - UETCL
To provide adequate transmission infrastructure to meet the power supply needs of Western
Uganda and evacuate mini-hydro power plants within the project area.
Expected Outputs: Construction of Hoima-Kafu Interconnection 220kV (approximately
70km) and associated substations works at Kafu and Hoima substations
Planned outputs 2012/13: Feasibility study for Hoima-Kafu feasibility study concluded
Responsible Officer:
Objectives:
Outputs:
7/1/2009 6/30/2015Start Date: Projected End Date:
Project Profile
Donor Funding for Project:
2016/172012/13
Budget
2013/14
Budget 2014/15 2015/16
MTEF Projections
Projected Donor Allocations (UShs)
Norway 0.840 1.670 0.000 0.0000.000535
0.840 1.670 0.000 0.0000.000Total Donor Funding for Project
Annual Workplan for 2014/15 - Outputs, Activities, Inputs and their Cost
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
- RAP Implementattion Consultant for Hoima - Kinyara - Kafu
Interconnection Procured.
- Supervision Consultant for Hoima - Kinyara - Kafu Interconnection
Procured.
- EPC Contractor for Hoima - Kinyara - Kafu Interconnection Procured.
- Resettlement Action Plan for Hoima - Kinyara - Kafu Interconnection
Acquisition of Other Capital Assets790103
Planned Outputs:
Output:
Inputs Quantity Cost
Supervision Consultant (Consultant) 2.0 1,670,000
EPC (Works) 1,000.0 3,000,000
Vote Overview
55
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Energy Planning,Management & Infrastructure Dev't03 01
Project 1144 Hoima - Kafu interconnection
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
Implemented.
- Procurement of a RAP Implementattion Consultant for Hoima -
Kinyara - Kafu Interconnection.
- Procurement of a Supervision Consultant for Hoima - Kinyara - Kafu
Interconnection.
- Procurement of a EPC Contractor for Hoima - Kinyara - Kafu
Interconnection.
- Implementation of the Resettlement Action Plan for Hoima - Kinyara -
Kafu Interconnection Implemented.
GoU Development
External Financing
Total
3,000,000
1,670,000
4,670,000
Activities to Deliver Outputs:
GoU Development
External Financing
GRAND TOTAL
3,000,000
1,670,000
4,670,000
Vote Overview
56
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Energy Planning,Management & Infrastructure Dev't03 01
Project 1198 Modern Energy from Biomass for Rural Development
Workplan Outputs for 2013/14 and 2014/15
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
-Biofuel legislations established.
-Biofuels Standards Developed.
-Biogas Standards Developed.
Procurement of consultant for
biofuels legislation still ongoing
Participating in ISO process of
biofuels standards
In consultation with Association
of Biogas Constructors of
Kenya to learn from Kenya
biogas standards
Energy Policy/Plans
Dissemination, Regulation
and Monitoring
Biofuels standards developed
Biogas standards developed
Biofuels regulations developed
010103
GoU Development
External Financing
Total
223,000
0
223,000
134,186
0
134,186
220,000
0
220,000
-Biogas Technology promoted
and Standards Developed.
-Promotion ot Gasification
Technology for institutional and
demostic applications.
-Relocation of Buddo gasifier
and purchase for thermal
gasifiers for Kings College
Buddo
-Energy Farming
promoted
-Biofuel Production and
Blending Promoted.
-Charcoal Briquetting
Technology Promoted
-Establish a Biofuel Pilot
labaratory.
Call for bids to construct 10
demonstration biolatrine
systems in the country
Sensitisation on biomass
technologies done on radio, tv
and newspapers
Biogas monitoring and
promotion in Mbarara
Biofuels monitoring and
promotion in Masindi
Gasification monitoring and
promotion in Gulu
2 staff trained in biofuels
management
2 staff trained in gasification
technology
Renewable Energy
Promotion
Biogas technology promoted at
household and institutional level
Support the establishment of bio
latrine technology in institutions
Support the completion of 10kw
biogas unit in Apac
Promote large scale biogas
technology for electricity
generation
-Promotion of household
gasification stoves
Promotion of gasification for
electricity generation
Biofuels production promoted
Small scale briquetting
technology promoted
Large scale briquetting
technology promoted
030103
GoU Development
External Financing
Total
946,000
0
946,000
596,649
0
596,649
1,220,000
0
1,220,000
Assistant Commissioner - Renewable Energy
(i) Increase the use of indigenous and environmentally friendly fuel (producer gas) derived
from biomass to operate a diesel engine to generate electricity for productive uses.(ii)
Introduce a gaseous fuel, producer gas for various thermal application(iii) Introduce the use of
biogas for cooking and for electricity generation (iv)Encourage energy crop growing for
production of biofuels
- Improved rural economy and employment through rural electrification (20 MW of
electricity can be generated through decentralized systems )• The plants will also encourage
the concept of energy plantation thus resulting in greener environment.•Establishment of
decentralised minigrids powered by biomass energy sources
Responsible Officer:
Objectives:
Outputs:
7/1/2011 6/30/2021Start Date: Projected End Date:
Project Profile
Vote Overview
57
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Energy Planning,Management & Infrastructure Dev't03 01
Project 1198 Modern Energy from Biomass for Rural Development
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
Membership to IAEA Meet obligations to IRENA
membership
510103
GoU Development
External Financing
Total
0
0
0
0
0
0
10,000
0
10,000
-Purchase of Desktop computers
-Purchase of laptop computers
-Purchase of projector for
meetings and seminars
Process to procure computers,
laptops and projector ongoing
Purchase of Office and
ICT Equipment,
including Software
Purchase of scanner
Purchase of laptop computers
Purchase of desktop computers
760103
GoU Development
External Financing
Total
190,000
0
190,000
49,650
0
49,650
100,000
0
100,000
-Purchase of a briqquetting unit
to enhance briqquette
production in private sector
- Purchase of the spares for the
relocated Budo gasifier
-Purchase of four 10kw
gasifiers for use and
demonstration of technology for
schools
Requests issued for a supplier
of briquetting unit
Purchase of Specialised
Machinery & Equipment
Purchase of a biogas unit for
electricity generation
Purchase of spares for
Nyabyeya gasifier maintenance
Purchase of 4 hand held Global
Positioning Units (GPS)
Purchase materials to support
completion of 10kw Apac
biogas unit
Purchase of 4 gasifier units for
gasification technology
demonstration
Implementation plan of
gasification technology
Engineering designs (biogas
system for electricity
770103
GoU Development
External Financing
Total
1,471,000
0
1,471,000
113,020
0
113,020
2,300,000
0
2,300,000
Purchase of office furniture Process to procure furniture
ongoing
Purchase of Office and
Residential Furniture and
Fittings
Purchase of office furniture780103
GoU Development
External Financing
Total
100,000
0
100,000
0
0
0
80,000
0
80,000
GoU Development
External Financing
GRAND TOTAL
2,930,000
0
2,930,000
893,505
0
893,505
3,930,000
0
3,930,000
Annual Workplan for 2014/15 - Outputs, Activities, Inputs and their Cost
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
Biofuels standards developed
Biogas standards developed
Energy Policy/Plans Dissemination, Regulation and Monitoring010103
Planned Outputs:
Output:
Inputs Quantity Cost
Biofuels regulations () 0.0 0
Biofuels standards () 1.0 40,000
Facilitation for travel to sensitise and monitor () 4.0 40,000
Fuel field activities () 4.0 20,000
Vote Overview
58
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Energy Planning,Management & Infrastructure Dev't03 01
Project 1198 Modern Energy from Biomass for Rural Development
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
Biofuels regulations developed
Consultations on the biofuels standards
Draft biofuels standard
Consultations on the biogas standards
Draft biogas standards
Draft biofuels regulations
GoU Development
External Financing
Total
220,000
0
220,000
Activities to Deliver Outputs:
Newspapers, radio & TV () 3.2 16,000
Refreshments for meetings () 4.0 6,000
Stationery () 4.0 4,000
Telephone calling costs () 4.0 5,000
Tyres and other vehicle spares () 4.0 40,000
Biogas standards (Units) 1.0 49,000
Biogas technology promoted at household and institutional level
Support the establishment of bio latrine technology in institutions
Support the completion of 10kw biogas unit in Apac
Promote large scale biogas technology for electricity generation
-Promotion of household gasification stoves
Promotion of gasification for electricity generation
Biofuels production promoted
Small scale briquetting technology promoted
Large scale briquetting technology promoted
Construction of household biogas units
construction of biolatrines in schools
Training of biogas artisans
Renewable Energy Promotion030103
GoU Development
External Financing
Total
1,220,000
0
1,220,000
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Allowances for field work () 1.0 73,000
Allowances to staff on official duty () 4.0 40,000
Allowances to workshop participants () 4.0 20,000
Brooms, water dispensers () 5.0 10,000
Fuel and lubricants () 1.0 60,000
Implementation process for gasification () 1.0 130,000
Install and monitor large scale briquetting unit () 1.0 130,000
Installing and monitoring biogas for electricity () 1.0 140,000
Newspapers, radio & TV () 4.0 60,000
Refreshments for meetings () 4.0 12,000
Telephone costs () 4.0 5,000
Toners () 4.0 20,000
Vehicle maintenance () 1.0 70,000
Specialised trainings in biomass energy (number) 4.0 200,000
Travel abroad to study gasification activities
(number)
4.0 200,000
Establishing site for large biogas for electricity
(units)
1.0 50,000
Meet obligations to IRENA membership
membership payment to IRENA
Membership to IAEA510103
GoU Development
External Financing
Total
10,000
0
10,000
Activities to Deliver Outputs:
Planned Outputs:
Output:
Grant or Transfer Cost
Annual subscription to IRENA 10,000
Purchase of scanner
Purchase of laptop computers
Purchase of desktop computers
Procuremnt of scanner
Procurement of laptop computers
Purchase of Office and ICT Equipment, including Software760103
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Beamer (Projector) () 1.0 7,000
Hand held GPS () 5.0 25,000
Laptops () 5.0 40,000
Photocopier () 1.0 20,000
Scanner () 2.0 8,000
Vote Overview
59
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Energy Planning,Management & Infrastructure Dev't03 01
Project 1198 Modern Energy from Biomass for Rural Development
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
Procurement of desk top computers
GoU Development
External Financing
Total
100,000
0
100,000
Purchase of a biogas unit for electricity generation
Purchase of spares for Nyabyeya gasifier maintenance
Purchase of 4 hand held Global Positioning Units (GPS)
Purchase materials to support completion of 10kw Apac biogas unit
Purchase of 4 gasifier units for gasification technology demonstration
Implementation plan of gasification technology
Engineering designs (biogas system for electricity
Procurement of biogas unit for electricity generation
Procurement of spares for Nyabyeya gasifier units
Procurement of of hand held GPS
Procurement of materials to support completion of 10kw Apac biogas unit
Procurement of 4 gasifier units for demonstration of gasification
technology
Implementation plan of gasification technology
Engineering designs (biogas system for electricity
Purchase of Specialised Machinery & Equipment770103
GoU Development
External Financing
Total
2,300,000
0
2,300,000
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Biogas system for electricity generation () 1.0 720,000
EIA for biogas system for electricity () 1.0 20,000
EIA for gasification units () 1.0 20,000
Engineering designs (biogas system for electricity () 13.5 540,000
Gasification units for electricity generation () 2.0 320,000
Supervision (biogas & gasification plants) () 8.5 340,000
Support to complete 10kw Apac biogas unit () 1.0 140,000
Implementation plan of gasification technology
(Report)
10.0 200,000
Purchase of office furniture
Procurement of office furniture
Purchase of Office and Residential Furniture and Fittings780103
GoU Development
External Financing
Total
80,000
0
80,000
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Air conditioners () 7.0 43,400
Book cabins () 21.0 12,600
Tables and chairs () 8.0 24,000
GoU Development
External Financing
GRAND TOTAL
3,930,000
0
3,930,000
Vote Overview
60
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Energy Planning,Management & Infrastructure Dev't03 01
Project 1212 Electricity Sector Development Project
Workplan Outputs for 2013/14 and 2014/15
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
ToR for the JSR and Sector
Performance Report 2013
produced.
Sector Performance Report
prepared
Thematic Papers for
discussions formulated/prepared
Stakeholder Engagement
undertaken.
Joint Sector Review 2013 held
Joint Sector Review 2013/14
was held in November 2013.
Terms of Reference for the
review of the Power sector
reforms were developed and
circulated for review.
Eight Monthly meetings of the
Energy and Mineral Sector
Working Group have been held
since beginning of the FY.
Shortlist was cleared by the
Bank and the Contracts
Energy Policy/Plans
Dissemination, Regulation
and Monitoring
- Consultant in place to Review
the Power Sector Reforms
- Monthly Energy and Mineral
Development Sector Working
Group (EMD-SWG) meetings
held. Reports in place.
- Production of the Sector
Performance Report 2014
- 4th Annual JSR 2014 held.
- Supervision and monitoring
the RAP implementation for the
010103
AC/ Electric Power
1) To evacuate power from Bujagali and other proposed hydropower stations on the Nile to
central Uganda as well as serve as a high voltage backbone to the proposed regional
interconnection network between Uganda, Tanzania, Rwanda, and DR Congo.
2) To improve the reliability and increase the access to electricity supply in the northern
region of Uganda
Expected Outputs:- Construction of 137 Km of a 220 kV transmission line from Kawanda to
Masaka and associated substations
- Fmproved reliability of electricity supply in the Masaka Area
- Additional increase in the electrification levels
- Reduced load shedding
- Increased transmission line length
- Increased number of substations
- Increased number of consumers
- Increased number of streets lit in Masaka Municipality
- Increased number of electrified market places in Masaka Municipality
- MEMD Power Sector Information Centre established
- Resettlement Action Plan (RAP) implemented with all PAPs paid up.
- Awareness created in the project area regarding the benefit and safe utilization of electricity
Feasibility study for Lira – Gulu – Nebbi –Arua (350km) 132kV project
Planned Outputs 2012/13- RAP implementation
-Procurement of supervision Consultant for Kawanda- Masaka transmission lines
-Procurement of EPC Contractor for Kawanda –Masaka transmission project
-Procurement of Consultant for feasibility study Lira –Gulu- Nebbi –Arua transmission line
project
Responsible Officer:
Objectives:
Outputs:
7/1/2011 2/28/2017Start Date: Projected End Date:
Project Profile
Donor Funding for Project:
2016/172012/13
Budget
2013/14
Budget 2014/15 2015/16
MTEF Projections
Projected Donor Allocations (UShs)
International Development Association (IDA) 36.515 133.280 27.250 0.00018.187410
36.515 133.280 27.250 0.00018.187Total Donor Funding for Project
Vote Overview
61
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Energy Planning,Management & Infrastructure Dev't03 01
Project 1212 Electricity Sector Development Project
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
-Energy Sector Working Group
(SWG) Supported.
- Power Sector Information
Center (PSIC) in Place.
Committee
Contract for the Independent
consultant to monitor RAP
implementation was signed.
Kawanda - Masaka 220Kv T-
lines. Report in place.
- Staff trained in different fields
GoU Development
External Financing
Total
304,000
0
304,000
218,294
0
218,294
561,000
660,000
1,221,000
- The procurement process for
the Consultant for Street and
Market Lighting at Masaka
Municipality fianlized and
consultant in Place.Contract
signed.
-Implementation of the Street
and Market Lighting in Masaka
Municipality by Consultant
carried out.Designs produced
by consultant.
-Monitor and Supervision of
the Implementation of Masaka
Municipality Street Lighting
carried out by MEMD.Reports
in place.
-Sensitisation and Awareness
Campaigns for the Communities
in the Project Area on the
Benefits of the Project carried
out by MEMD.Reports in place.
Procurement of the Contractor
for the Implementation of Street
and Market Lighting in Masaka
Municipality carried out and
contractor in place.Contract
signed.
Contract for the designand
supervision of the installation of
street lights and electrification
of Markets within the Masaka
Municipality was signed.
Work commenced in regards to
the design and supervision of
the installation of street lights
and electrification of Markets
within the Masaka Municipality
Six sensitisation meetings have
been held with the project area
since the beginning of the
financial year – the number of
meetings is low because
sometimes there is a delay in
the release of funds therefore
the planned number of meetings
is not carried out
Energy Efficiency
Promotion
- Street and Market lighting for
Masaka Municipality carried
out.
-Sensitization of communities
on energy
management/efficiency carried
out in the kawanda-Masaka T-
line project area
020103
GoU Development
External Financing
Total
340,000
1,900,000
2,240,000
274,251
0
274,251
30,100
1,900,000
1,930,100
-Peri-Urban Electrification in
Areas around the Masaka-
Kawanda T-line Carried out.
-Contractor for the Peri-Urban
Electrification procured and
contract signed.
-Sensitisation and Awareness
Campaigns carried out for the
Communities in the Project
Area on the Benefits of the
Project.
Design and Supervision
Contract before Solicitor
General for Clearance
Increased Rural
Electrification
- Peri-urban electrification
within a 5km radius of the
Kawanda - Masaka T-line
commenced.
040103
GoU Development
External Financing
Total
820,000
1,960,000
2,780,000
626,043
0
626,043
2,958,616
2,620,000
5,578,616
Acquisition of Land by
Government
- RAP Consultancy for
Kawanda-Masaka T-line
implemented to 75%
710103
Total 0 0 163,200
Vote Overview
62
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Energy Planning,Management & Infrastructure Dev't03 01
Project 1212 Electricity Sector Development Project
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
GoU Development
External Financing
Total
0
0
0
0
163,200
0
- Construction of new Kawanda-
Masaka transmission line and
related upgrades to substations.
- Power Sector Information
Center in place
- Compesation for land for the
Kawanda-Masaka transmission
line (RAP implementation)
-Procurement of supervision
Consultant for Kawanda-
Masaka transmission lines
-Procurement of EPC
Contractor for Kawanda
–Masaka transmission project
-Procurement of Consultant for
feasibility study Lira –Gulu-
Nebbi –Arua transmission line
project
50% (1081) of the total number
of affected households (ie.
2171) have been compensated.
Contract for the independent
consultant to monitor the RAP
implementation was signed.
Bids for Potential Contractors
of the Kawanda-Masaka 220kV
line have been evaluated and
report submitted to the World
Bank.
Contract for the Supervision of
the Lira-Gulu-Nebbi T-Line
was signed.
Acquisition of Other
Capital Assets
- Establishment of the Power
Sector Information Centre
commenced
- Construction of new Kawanda-
Masaka transmission line and
related upgrades to substations.
790103
GoU Development
External Financing
Total
10,593,553
31,995,388
42,588,941
5,762,707
0
5,762,707
3,037,253
128,100,000
131,137,253
GoU Development
External Financing
GRAND TOTAL
12,057,553
35,855,388
47,912,941
6,881,295
0
6,881,295
6,750,169
133,280,000
140,030,169
Annual Workplan for 2014/15 - Outputs, Activities, Inputs and their Cost
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
- Consultant in place to Review the Power Sector Reforms
- Monthly Energy and Mineral Development Sector Working Group
(EMD-SWG) meetings held. Reports in place.
- Production of the Sector Performance Report 2014
- 4th Annual JSR 2014 held.
- Supervision and monitoring the RAP implementation for the Kawanda -
Masaka 220Kv T-lines. Report in place.
- Staff trained in different fields
- Procurement of a consultant to review of power sector reforms and
submission of the Inception Report.
- Print and diserminate the sector performance report for 2014.
- Hold preparatory stakeholder consultations, JSR 14 thermatic papers
prepared for discussion, procurement of venue, materials for the 4th JSR
2014.
- Monthly Energy and Mineral Development Sector Working Group
Energy Policy/Plans Dissemination, Regulation and Monitoring010103
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
JSR 2014 Performance Review () 1.0 150,000
Internet (Bundles) 3.0 3,000
consultant to review of power sector reforms
(Consultant)
1.0 404,000
Inputs for JSR 2014 (Inputs) 1,000.0 100,000
Airtime and Data for UTL, MTN and Orange
(Lines)
24.0 6,000
Fuel for Motor Vehicle under ESDP (Litres) 17,142.9 60,000
Facilitation of staff for monitoring activities (Nights) 625.0 75,000
Courier Services (Package) 10.0 3,000
Facilitation of staff traveling abroad (Per Diem) 55.6 50,000
Assorted Stationery (Pieces) 350.0 17,500
Assorted Toners (Pieces) 150.0 52,500
Per Diem (Reports) 279.2 33,500
Workshops (Reports) 2.2 11,000
Training of staff under ERD (Staff) 10.0 260,000
Repair and Servicing of Motor Vehicles (Vehicles) 1.8 4,500
Vote Overview
63
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Energy Planning,Management & Infrastructure Dev't03 01
Project 1212 Electricity Sector Development Project
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
(EMD-SWG) meetings held, EMD-SWG to undertake a field visit to
assess progress of activities from FY 2013/14
- Monitoring and Evaluation of the RAP implementation of Kawanda-
Masaka line.
- 5 staff trained in various fields.
GoU Development
External Financing
Total
561,000
660,000
1,221,000
- Street and Market lighting for Masaka Municipality carried out.
-Sensitization of communities on energy management/efficiency carried
out in the kawanda-Masaka T-line project area
- Street and Market lighting for Masaka Municipality carried out for at
least one market & one street (Yellow knife street, Saaza Market) and
Supervision and Monitoring reports for the Construction works for the
Street and Market Lighting.
- One sensitization campaign/drive on energy management/efficiency
carried out in the kawanda-Masaka T-line project area carried out every
quarter.
Energy Efficiency Promotion020103
GoU Development
External Financing
Total
30,100
1,900,000
1,930,100
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Consultant on Energy Management (Consultant) 1.0 1,160,000
Airtime and Data for UTL, MTN and Orange Lines
(Lines)
22.0 5,500
Fuel for field activities (Litres) 857.1 3,000
Facilitation of staff for field allowances (Per Diem) 21.7 2,600
Assorted Stationery (Pieces) 900.0 4,500
Furniture (Pieces) 1.0 3,500
Desktop and Laptop Computers (Units) 1.7 8,500
Hiring of Venue for meetings (Venue) 5.0 2,500
- Peri-urban electrification within a 5km radius of the Kawanda - Masaka
T-line commenced.
- Procurement of Contractor to implement peri-urban electrification
completed.
- Supervision and Progress reports on electrification of the benefitting
households.
Increased Rural Electrification040103
GoU Development
External Financing
Total
2,958,616
2,620,000
5,578,616
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Consultancy for Peri-Urban () 13.1 2,620,000
Repair and Servicing of Motor Vehicles () 10.0 24,000
Airtime and Data for UTL, MTN and Orange Lines
(Lines)
20.0 5,000
Fuel for ESDP motor vehicles (Litres) 10,000.0 38,000
Publications in the Newspapers (Pages) 0.7 5,000
Allowances for monitoring activities (Per Diem) 62.5 7,500
Allowances to Monitor Field Activities (Per diem) 41.7 5,000
Assorted Stationery (Pieces) 160.0 8,000
Assorted Toners (Pieces) 20.0 7,000
Works (Reports) 953.5 2,860,416
Desktop and Laptop Computers (Units) 10.0 50,000
Office Furniture (Units) 1.0 1,000
Hiring of Venues for Workshops (Venue) 7.0 3,500
- RAP Consultancy for Kawanda-Masaka T-line implemented to 75%
- RAP Consultancy services implementation. Progress Report in place.
Acquisition of Land by Government710103
GoU Development
External Financing
Total
163,200
0
163,200
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Consultant to monitor the RAP Implementation
(Consultant)
1.0 169,553
Vote Overview
64
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Energy Planning,Management & Infrastructure Dev't03 01
Project 1212 Electricity Sector Development Project
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
- Establishment of the Power Sector Information Centre commenced
- Construction of new Kawanda-Masaka transmission line and
related upgrades to substations.
- Procurement of a consultant for the Establishment of the Power Sector
Information Centre
- EPC works: Detailed surveys and designs, Factory testing, civil works,
manufacture, transportation of items, erection and installation works.
- Resettlement activities: 100% of disputes resolved.
- Acquisition of Right of Way
- Implementation of consultancy contract
Acquisition of Other Capital Assets790103
GoU Development
External Financing
Total
3,037,253
128,100,000
131,137,253
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Engineering design studies () 100.0 1,000,000
PSIC Consultant (Consultant) 1.0 335,388
EPC Works for Kawanda - Masaka (Line) 10,005.1 127,764,612
Taxes (UETCL) (Taxes) 1.0 2,037,253
GoU Development
External Financing
GRAND TOTAL
6,750,169
133,280,000
140,030,169
Vote Overview
65
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Energy Planning,Management & Infrastructure Dev't03 01
Project 1221 Opuyo Moroto Interconnection Project
Op
Workplan Outputs for 2013/14 and 2014/15
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
- Feasibility study concluded
- RAP implementation
- Supervision Consultant and
EPC Contractor procured
Completion of the feasibility
study
Procurement of RAP/ESIA
study update and RAP
Implementation consultant
Acquisition of Other
Capital Assets
•Procurement of RAP
implementation consultant
•Procurement of Supervision
Consultant
•Procurement of EPC Contractor
•RAP Implementation
790103
GoU Development
External Financing
Total
1,000,000
0
1,000,000
833,333
0
833,333
1,000,000
2,690,000
3,690,000
GoU Development
External Financing
GRAND TOTAL
1,000,000
0
1,000,000
833,333
0
833,333
1,000,000
2,690,000
3,690,000
MD - UETCL
Provision of adequate transmission capacity to cater for the projected demand in the Karamoja
region.
Planned Outputs 2012/13- RAP implementation
- Procurement of supervision Consultant for Kawanda- Masaka transmission lines
- Procurement of EPC Contractor for Kawanda –Masaka transmission project
- Procurement of Consultant for feasibility study Lira –Gulu- Nebbi –Arua transmission line
project
Expected Outputs:
Constructed Opuyo – Moroto 132kV transmission line (approx. 160km) and associated
substations at Moroto and Opuyo substation upgrade
Planned Outputs 2012/13
- Feasibility study concluded
- RAP implementation
Responsible Officer:
Objectives:
Outputs:
7/2/2012 6/30/2015Start Date: Projected End Date:
Project Profile
Donor Funding for Project:
2016/172012/13
Budget
2013/14
Budget 2014/15 2015/16
MTEF Projections
Projected Donor Allocations (UShs)
China (PR) 0.000 0.000 0.000 0.0008.830507
International Development Association (IDA) 0.000 2.690 40.870 55.5900.000410
0.000 2.690 40.870 55.5908.830Total Donor Funding for Project
Annual Workplan for 2014/15 - Outputs, Activities, Inputs and their Cost
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
Acquisition of Other Capital Assets790103Output:
Vote Overview
66
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Energy Planning,Management & Infrastructure Dev't03 01
Project 1221 Opuyo Moroto Interconnection Project
Op
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
•Procurement of RAP implementation consultant
•Procurement of Supervision Consultant
•Procurement of EPC Contractor
•RAP Implementation
•Procurement of RAP implementation consultant
•Procurement of Supervision Consultant
•Procurement of EPC Contractor
•RAP Implementation
GoU Development
External Financing
Total
1,000,000
2,690,000
3,690,000
Activities to Deliver Outputs:
Planned Outputs: Inputs Quantity Cost
EPC Contractor (number) 31.9 3,190,000
RAP (number) 50.0 500,000
GoU Development
External Financing
GRAND TOTAL
1,000,000
2,690,000
3,690,000
Vote Overview
67
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Energy Planning,Management & Infrastructure Dev't03 01
Project 1222 Electrification of Industrial Parks Project
Workplan Outputs for 2013/14 and 2014/15
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
Acquisition of Land by
Government
RAP Implementation710103
GoU Development
External Financing
Total
0
0
0
0
0
0
640,000
0
640,000
- Feasibility study and
supervision of works for
Namanve Industrial Park
132/33kV Substation and
Transmission Line Project, EIA
and RAP study.
- RAP Implementation for
Mbale Industrial Park
Namanve: Feasibility study,
ESIA & RAP Studies
completed.
-Namanve, Mukono, Iganga and
Luzira: Sourcing for financing
for construction on-going; 80%
completed
- Mukono, Iganga and Luzira:
Procurement of the ESIA &
RAP Studies & RAP
Implementation consultant
completed.
Disbursements:
USD 347,737.16 has been spent
towards the study
Acquisition of Other
Capital Assets
- Construction of Namanve
South, Luzira, Mukono and
Iganga Industrial Park
Substations and Associated
transmission lines
790103
GoU Development
External Financing
Total
3,040,000
0
3,040,000
1,154,795
0
1,154,795
400,000
0
400,000
GoU Development
External Financing
GRAND TOTAL
3,040,000
0
3,040,000
1,154,795
0
1,154,795
1,040,000
0
1,040,000
MD UETCL
Provision of adequate transmission capacity to cater for the projected demand from within the
Industrial areas.
Expected Outputs:
- Construction of Luzira Industrial Park 132/33kV Substation and transmission Line Project
(31km)
-Construction of Mukono Industrial Park 132/33kV Substation and Transmission Line Project
(5km)
-Construction of Iganga Industrial Park 132/33kV Substation and Transmission Line Projects
(12km)
-Construction of Namanve Industrial Park 132/33kV Substation and Transmission Line
Project (10km)
Planned Outputs 2012/13
- Procurement of Consultant for feasibility study and supervision of works for Namanve
Industrial Park 132/33kV Substation and Transmission Line Project
Responsible Officer:
Objectives:
Outputs:
7/2/2012 6/30/2015Start Date: Projected End Date:
Project Profile
Vote Overview
68
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Energy Planning,Management & Infrastructure Dev't03 01
Project 1222 Electrification of Industrial Parks Project
Annual Workplan for 2014/15 - Outputs, Activities, Inputs and their Cost
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
RAP Implementation
- 80% ROW acquired
- Substation land acquired
10% of ROW acquired
Acquisition of Land by Government710103
GoU Development
External Financing
Total
640,000
0
640,000
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Purchase of Land for the substation (Acres) 91.4 640,000
- Construction of Namanve South, Luzira, Mukono and Iganga Industrial
Park Substations and Associated transmission lines
- Construction works for Namanve South, Luzira, Mukono and Iganga
Industrial Substations and associated transmission Lines: 30% of works
Acquisition of Other Capital Assets790103
GoU Development
External Financing
Total
400,000
0
400,000
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Construction works on substations (Contractor) 4.0 400,000
GoU Development
External Financing
GRAND TOTAL
1,040,000
0
1,040,000
Vote Overview
69
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Energy Planning,Management & Infrastructure Dev't03 01
Project 1257 Mirama-Kikagati-Nshungyenzi Transmission Line
Workplan Outputs for 2013/14 and 2014/15
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
Feasibility Studies and Detailed
Engineering Designs
Acquisition of Other
Capital Assets
-Completion of Feasibility study
for Mirama - Kikagati -
Nshungyenzi Transmission Line.
-Complete ESIA / RAP study
for Mirama - Kikagati -
Nshungyenzi Transmission Line.
-RAP Implementation for
Mirama - Kikagati -
Nshungyenzi Transmission Line.
790103
GoU Development
External Financing
Total
0
0
0
0
0
0
0
2,284,600
2,284,600
MD - UETCL
General Objectives:
- Provide adequate transmission infrastructure to meet the energy needs for the Uganda
population in the project area for social and economic development
- Provision of transmission infrastructure to evacuate power generated from Kikagati power
plant (16MW) and Nsongezi power plant (35MW) to the load centres of Isingiro, Ntungamo,
Mbarara and border load centres in Tanzania.
- Improve power supply quality and security by providing adequate transmission
infrastructure.
- Poverty eradication through providing electricity needed for the small to medium scale
industries
- Improve the standard of living for the project area population by providing electricity needed
for improved health, education and communication infrastructure.
- Cross border electrification
Specific Objectives
•Construction of a 38 km, 132kV power transmission line from Mirama– Kikagati – Nsongezi
with associated substations.
- Constructed Mirama – Kikagati – Nsongezi, 38 km, and 132kV power transmission line
tested and fully operational.
- Extension of the proposed Mirama 220/132kV one line bay for the outgoing line to Kikagati.
- Construction of 132/33kV, 2 x 15/20MVA substation at Kikagati
- Construction of 132/33kV, 2 x 32/40MVA substation at Nsongezi
Responsible Officer:
Objectives:
Outputs:
6/1/2013 6/30/2017Start Date: Projected End Date:
Project Profile
Donor Funding for Project:
2016/172012/13
Budget
2013/14
Budget 2014/15 2015/16
MTEF Projections
Projected Donor Allocations (UShs)
Nordic Development Fund 2.285 2.285 0.000 2.2850.000416
2.285 2.285 0.000 2.2850.000Total Donor Funding for Project
Vote Overview
70
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Energy Planning,Management & Infrastructure Dev't03 01
Project 1257 Mirama-Kikagati-Nshungyenzi Transmission Line
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
GoU Development
External Financing
GRAND TOTAL
0
0
0
0
0
0
0
2,284,600
2,284,600
Annual Workplan for 2014/15 - Outputs, Activities, Inputs and their Cost
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
-Completion of Feasibility study for Mirama - Kikagati - Nshungyenzi
Transmission Line.
-Complete ESIA / RAP study for Mirama - Kikagati - Nshungyenzi
Transmission Line.
-RAP Implementation for Mirama - Kikagati - Nshungyenzi Transmission
Line.
-Feasibility study: Financial analysis, Specification and Tender document
preparation for Mirama - Kikagati - Nshungyenzi Transmission Line.
-ESIA/RAP study for Mirama - Kikagati - Nshungyenzi Transmission
Line undertaken.
-RAP Implementation for Mirama - Kikagati - Nshungyenzi Transmission
Line undertaken.
Acquisition of Other Capital Assets790103
GoU Development
External Financing
Total
0
2,284,600
2,284,600
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Consultant to conduct the feasibility studies
(Consultant)
1.0 2,000,000
Supervision Consultant (Consultant) 1.0 284,600
GoU Development
External Financing
GRAND TOTAL
0
2,284,600
2,284,600
Vote Overview
71
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Energy Planning,Management & Infrastructure Dev't03 01
Project 1259 Kampala-Entebbe Expansion Project
Workplan Outputs for 2013/14 and 2014/15
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
Provision of transmission
capacity to supply reliable and
quality power to En-tebbe town
and environs
Loan agreement signed between
GOU and KfW on 24th
October, 2013
-Consultant for ESIA/RAP/RAP
Implementation services was
commissioned. Study ongoing
-Negotiation minutes and draft
contract for supervision
consultant we approved by
Contracts Committee
-Line routing activities were
concluded
-Field activities for ESIA/RAP
study commenced
-Supervision Consultant’s
Contract was cleared by
Solicitor General
-Contract was signed between
UETCL and INTEC GOPA
Acquisition of Land by
Government
-Detailed design and tender
document for the Kampala -
Entebbe Expansion Project
prepared.
-EPC Contractor for the
Kampala - Entebbe Expansion
Project procured.
-Construction works for the
Kampala - Entebbe Expansion
Project commenced.
-RAP Implementation for the
Kampala - Entebbe Expansion
Project
710103
GoU Development
External Financing
Total
2,000,000
0
2,000,000
2,000,000
0
2,000,000
500,000
0
500,000
Acquisition of Other
Capital Assets
- Detailed design and tender
document preparation
- Procurement of EPC
contractor
- Commencement of
Construction Works
790103
GoU Development
External Financing
Total
0
0
0
0
0
0
1,500,000
2,920,000
4,420,000
MD-UETCL
Project Objective
Provision of transmission capacity to supply reliable and quality power to En-tebbe town and
environs.
Expected Outputs
•Constructed 132kV Mutundwe-Entebbe, double circuit steel tower power transmission line (
approximately 35km)
•Mutundwe substation extension by two new line bays
•New high voltage substation at Entebbe
Responsible Officer:
Objectives:
Outputs:
7/1/2013 6/30/2016Start Date: Projected End Date:
Project Profile
Donor Funding for Project:
2016/172012/13
Budget
2013/14
Budget 2014/15 2015/16
MTEF Projections
Projected Donor Allocations (UShs)
Germany Fed. Rep. 0.000 2.920 9.662 11.4350.000514
0.000 2.920 9.662 11.4350.000Total Donor Funding for Project
Vote Overview
72
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Energy Planning,Management & Infrastructure Dev't03 01
Project 1259 Kampala-Entebbe Expansion Project
GoU Development
External Financing
GRAND TOTAL
2,000,000
0
2,000,000
2,000,000
0
2,000,000
2,000,000
2,920,000
4,920,000
Annual Workplan for 2014/15 - Outputs, Activities, Inputs and their Cost
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
-Detailed design and tender document for the Kampala - Entebbe
Expansion Project prepared.
-EPC Contractor for the Kampala - Entebbe Expansion Project procured.
-Construction works for the Kampala - Entebbe Expansion Project
commenced.
-RAP Implementation for the Kampala - Entebbe Expansion Project
-Detailed design and tender document preparation for the Kampala -
Entebbe Expansion Project
-Procurement of EPC Contractor for the Kampala - Entebbe Expansion
Project.
-Commencement of construction works for the Kampala - Entebbe
Expansion Project.
-RAP Implementation for the Kampala - Entebbe Expansion Project
completed.
Acquisition of Land by Government710103
GoU Development
External Financing
Total
500,000
0
500,000
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Purchase of Land (Acre) 64.3 450,000
Monitoring of the purchase of Land (Per Diem) 416.7 50,000
- Detailed design and tender document preparation
- Procurement of EPC contractor
- Commencement of Construction Works
- Procurement of EPC contractor
- Construction works commence: Detailed designs and surveys, Civil
works (20%)
Acquisition of Other Capital Assets790103
GoU Development
External Financing
Total
1,500,000
2,920,000
4,420,000
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Monitoring Consultancy (Consultant) 15.6 3,120,000
EPC Contractor (Contractor) 1.0 1,300,000
GoU Development
External Financing
GRAND TOTAL
2,000,000
2,920,000
4,920,000
Vote Overview
73
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Large Hydro power infrastructure03 02
Services:
Responsible Officer:
Vote Function Profile
This vote function is intended to support development of large hydropower
generation facilities in the Country.The Fund is geared towards meeting
Government's endeavours to developing these large projects on a public/private
partnership in the medium term.
Commissioner ERD
Vote Function Projects and Programmes:Project or Programme Name Responsible Officer
Development Projects
1143 Isimba HPP Commissioner - ERD
1183 Karuma Hydoelectricity Power Project Commissioner, ERD
Project 1143 Isimba HPP
Workplan Outputs for 2013/14 and 2014/15
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
Acquisition of Land by
Government
-The RAP implementation for
the Isimba HPP and the
associated transmission lines
finalised.
-The Community Development
Action Plan for Isimba HPP &
the associated transmission lines
and commence on its
implementation finalised.
-The Access Road from
Kayunga Town to site and those
within the project site
completed.
-The Employer and
Contractor’s Camp along with
water supply system, power
710203
Commissioner - ERD
To develop a hydropower plant at Isimba with the associated transmission lines that will
contribute towards:
Increased generation capacity
Increased length and strengthened transmission networks
Increased power supply locally and regionally
Increased electricity access levels
Satisfaction of the fast growing electricity demand
Improved transport between the districts of Kamuli and Kayunga
- Construct 183MW Isimba Hydro power plant
- Constructed 4X45.8MW Isimba Hydro power plant
- Constructed 132kV Isimba-Bujagali , double circuit steel tower power transmission line (
approximately 41km)
Responsible Officer:
Objectives:
Outputs:
7/1/2010 6/30/2015Start Date: Projected End Date:
Project Profile
Vote Overview
74
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Large Hydro power infrastructure03 02
Project 1143 Isimba HPP
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
supply system,
telecommunication line
construction completed.
-The project detailed designs
incorporating the results of the
additional investigations carried
out by the contractor finalised.
-The construction works for the
Power Plant and the
transmission line (30%
coverage) commenced.
-The construction of the Site
Laboratory completed.
- EPC works for Isimba HPP
supervised
GoU Development
External Financing
Total
0
0
0
0
0
0
900,000
0
900,000
GoU Development
External Financing
GRAND TOTAL
0
0
0
0
0
0
900,000
0
900,000
Annual Workplan for 2014/15 - Outputs, Activities, Inputs and their Cost
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
-The RAP implementation for the Isimba HPP and the associated
transmission lines finalised.
-The Community Development Action Plan for Isimba HPP & the
associated transmission lines and commence on its implementation
finalised.
-The Access Road from Kayunga Town to site and those within the
project site completed.
-The Employer and Contractor’s Camp along with water supply system,
power supply system, telecommunication line construction completed.
-The project detailed designs incorporating the results of the additional
investigations carried out by the contractor finalised.
-The construction works for the Power Plant and the transmission line
(30% coverage) commenced.
-The construction of the Site Laboratory completed.
- EPC works for Isimba HPP supervised
-Finalise the RAP implementation for the Power Plant and the
transmission line
-Finalise the Community Development Action Plan and commence on its
implementation
-Complete the Access Road from Kayunga Town to site and those within
the project site.
Acquisition of Land by Government710203
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
RAP Supervision (reports) 1.0 900,000
Vote Overview
75
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Large Hydro power infrastructure03 02
Project 1143 Isimba HPP
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
-Complete of the Employer and Contractor’s Camp along with water
supply system, power supply system, telecommunication line construction.
-Finalization of the project detailed designs incorporating the results of
the additional investigations carried out by the contractor.
-Commence on the construction works for the Power Plant and the
transmission line (30% coverage).
-Complete the construction of the Site Laboratory.
- Supervision of works for Isimba HPP
GoU Development
External Financing
Total
900,000
0
900,000
GoU Development
External Financing
GRAND TOTAL
900,000
0
900,000
Vote Overview
76
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Large Hydro power infrastructure03 02
Project 1183 Karuma Hydoelectricity Power Project
Workplan Outputs for 2013/14 and 2014/15
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
-EPC Contract Signed and
Contractor for Karuma
Hydropower Project on Site.
-Five (5) Sensitisation
Workshops for Karuma HP
Project affected people and
local community held.
-100% of Project Affected
Persons for Karuma HPP
Compensated/Resettled.
-100% Land Freed Up for
Contractors.
-RAP implementing Agency for
Evacuation Lines in place.
-100% of the Project Affected
Persons for Karuma HPP Power
Evacuation Lines Compenseted/
Ressettled.
-Construction of Karuma HPP
Commences. 20% of the Works
Covered.
- Preparatory survey for Ayago
Continued to supervise the EPC
Contract Signed and Contractor
for Karuma Hydropower
Project on Site.
-90% of Project Affected
Persons for Karuma HPP
Compensated/Resettled.
-90% Land Freed Up for
Contractors.
-RAP implementing Agency for
Evacuation Lines in place.
-90% of the Project Affected
Persons for Karuma HPP Power
Evacuation Lines Compenseted/
Ressettled.
-10% Construction of Karuma
HPP Works Covered by M/s
Sinohydro.
Large Hydro Power
Infrastructure
-Institutions (churches mosque
and Karuma Primary school)
relocated.
-Construction of the
Resettlement Houses
commenced.
-PAPs within the affected and
host communities sensitized.
-Implementation of the
Community Development
Action Plan (CDAP) and the
Environment and Social
Management Plan (ESMP)
supervised and Monitored.
- Construction of Karuma HPP
Commences. (20%) of the
Works Covered.
- Contribution by GOU towards
the 20% construction of the
Karuma HPP.
800203
GoU Development
External Financing
Total
1,096,900,000
0
1,096,900,000
34,640,500
0
34,640,500
1,096,000,000
0
1,096,000,000
GoU Development
External Financing
GRAND TOTAL
1,096,900,000
0
1,096,900,000
34,640,500
0
34,640,500
1,096,000,000
0
1,096,000,000
Commissioner, ERD
The medium term objective of the project is the ultimate development of the Karuma Hydro
Power Plant and its associated transmission line interconnection which will contribute to the
power supply in the country and possibly in the East African region.
- Constructed 600 MW Karuma Hydro power plant
- Constructed 220kV Karuma-Kawanda, double circuit steel tower power transmission line
Responsible Officer:
Objectives:
Outputs:
7/1/2011 6/30/2016Start Date: Projected End Date:
Project Profile
Annual Workplan for 2014/15 - Outputs, Activities, Inputs and their Cost
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
-Institutions (churches mosque and Karuma Primary school) relocated.
-Construction of the Resettlement Houses commenced.
Large Hydro Power Infrastructure800203
Planned Outputs:
Output:
Inputs Quantity Cost
Consultant for the mosque and church (Consultant) 1.0 100,000
Consultant for the PAP houses (Consultant) 1.0 700,000
Constrution of Karuma Dam (Contractor) 1.0 1,046,000,000
Vote Overview
77
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Large Hydro power infrastructure03 02
Project 1183 Karuma Hydoelectricity Power Project
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
-PAPs within the affected and host communities sensitized.
-Implementation of the Community Development Action Plan (CDAP)
and the Environment and Social Management Plan (ESMP) supervised
and Monitored.
- Construction of Karuma HPP
Commences. (20%) of the Works Covered.
- Contribution by GOU towards the 20% construction of the Karuma HPP.
-Procurement of a consultant to design institutions (churches mosque and
Karuma Primary school) and supervise the construction.
- Procurement of a contractor to construct institutions (churches mosque
and Karuma Primary school).
-Procurement of a consultant to design and supervise the construction of
the resettlement houses.
- Procurement of a contractor to construct resettlement houses.
-Sensitization of PAPs within the affected and host communities.
-Supervision and Monitoring of the Implementation of the Community
Development Action Plan (CDAP) and the Environment and Social
Management Plan (ESMP).
- Contribution by GOU towards the 20% construction of the Karuma HPP.
GoU Development
External Financing
Total
1,096,000,000
0
1,096,000,000
Activities to Deliver Outputs:
Consultant for PAP houses (Contractor) 1.0 48,000,000
Consultant for the mosque & church (Contractor) 1.0 1,200,000
GoU Development
External Financing
GRAND TOTAL
1,096,000,000
0
1,096,000,000
Vote Overview
78
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Large Hydro power infrastructure03 02
Project 1256 Ayago Interconnection Project
MD-UETCL
- To evacuate power from the proposed Ayago HPP.
- Improve availability of power supply
- Ayago - Olwiyo (400kV) interconnector and related substations
Responsible Officer:
Objectives:
Outputs:
1/4/2014 12/20/2020Start Date: Projected End Date:
Project Profile
Donor Funding for Project:
2016/172012/13
Budget
2013/14
Budget 2014/15 2015/16
MTEF Projections
Projected Donor Allocations (UShs)
Japan 1.345 0.000 0.000 0.0000.000523
1.345 0.000 0.000 0.0000.000Total Donor Funding for Project
Vote Overview
79
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Petroleum Exploration, Development & Production03 03
Services:
Responsible Officer:
Vote Function Profile
The vote function effectively monitors all petroleum operations in the country for
the exploitation of the petroleum resource in an economically and environmentally
manner. The new legislation, the creation of new institutions and the strengthening
of existing ones will be undertaken to effectively carry out various mandates of the
vote function.
Commissioner, PEPD
Vote Function Projects and Programmes:Project or Programme Name Responsible Officer
Recurrent Programmes
04 Petroleum Exploration Production Department Commissioner, PEPD
Development Projects
1142 Management of the Oil and Gas Sector in Uganda Commissioner - PEPD
1184 Construction of Oil Refinery Assistant Commissioner - Geology
Programme 04 Petroleum Exploration Production Department
Workplan Outputs for 2013/14 and 2014/15
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
Geological, Geophysical and
Geochemical data in the
unlicensed basins collected and
packaged;
Investment promotion
undertaken; resource
assessment and laboratory
analyses conducted.
A reconnaissance survey
covering 60 gravity and 60
magnetic data points covering
approximately line 90km
acquired in Moroto, Napak and
Nakapiripirit districts .Also 20
surface geology field points
established and reconnaissance
geology map of Kadam –
Moroto basin made.
Basin analysis team completed
the biostratigraphy study of
Northern Lake Albert and
Pakwach basin
Basin Analysis consultant
recruited and commenced work
Promotion of the country's
petroleum potential and
licensing
400 line km of Geophysical
data acquired and geological
and geochemical mapping of
100 sq in the unlicensed and
new basins undertaken.
Processed and packaged Gand
G data;
Promotion of the country's
petroleum potential undertaken.
010303
Commissioner, PEPD
- To promote and monitor petroleum exploration, development, production and value addition
by the private sector for local consumption and export
- To carry out general and specialised manpower training, retention of national expertise and
strenghtening capacity of institutions responsible for the oil and gas sector.
- To review and put in place modern policies and legislation that offer a conducive business
environment.
- Implement, monitor and evaluate the communication strategy for the oil and gas sector.
- Implement and monitor the national participation strategy in the oil and gas sector.
- Participate in regional initiatives for oil and gas sector.
- Ensure that oil and gas activities are undertaken in a manner that conserves the environment
and biodiversity.
The vote function effectively monitors all upstream petroleum operations in the country for
the exploration of the petroleum resources in an economically and environmentally efficient
manner. The new legislation, the creation of new institutions and the strengthening of existing
ones will be undertaken to effectively carry out various mandates of the vote function.
Responsible Officer:
Objectives:
Outputs:
Programme Profile
Vote Overview
80
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Petroleum Exploration, Development & Production03 03
Programme 04 Petroleum Exploration Production Department
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
and presented the inception
report.
Review of the model contracts
(mainly acquisition, processing,
marketing and sale) completed
and are to be submitted to the
Ministry of Justice and
Constitutional Affairs for
clearance
The regulation for sale of
petroleum data concluded and
signed off the Minister of
Energy and Mineral
Development and will be
operational after publication
effective 1st July 2014.
Wage Recurrent
Non Wage Recurrent
Total
51,963
270,000
321,963
37,960
158,520
196,480
918,195
350,000
1,268,195
New Regulations and guidelines
for the upstream activities
developed; Model PSA
reviewed and updated;
Monitoring and Evaluation (M
& E) strategy for the National
Oil and Gas Policy (NOGP)
formulated.
Monitoring and Evaluation (M
& E) strategy for the National
Oil and Gas Policy
(NOGP) concluded and in place;
A zero draft for the upstream
regulations is in place;
The national content policy and
strategy continued to be
developed.
Initiate and formulate
petroleum policy and
legislation
Attendant regulations for
Upstream petroleum subsector
in place;
New regulations and guidelines
for the upstream activities in
place;
Updated Model Production
Sharing Agreement.
Monitoring and Evaluation
strategy for the National Oil and
Gas Policy implemented
020303
Wage Recurrent
Non Wage Recurrent
Total
36,543
80,000
116,543
27,065
53,487
80,551
0
60,000
60,000
National expertise for the oil
and gas developed and
maintained; National Content
policy and strategy put in place.
9 staff continued their Master’s
degree studies in various
Universities abroad.
The process of
operationalization of the new
petroleum institutions continued
Capacity Building for the
oil & gas sector
National expertise for the oil
and gas developed and
maintained.
Training of seven (7) members
of staff at M.Sc. Level in
petroleum studies commenced.
030303
Wage Recurrent
Non Wage Recurrent
Total
58,388
135,000
193,388
44,309
81,103
125,412
0
100,000
100,000
Surveys and field operations
exploration costs uncured by
licensees monitored; Petroleum
Data efficiently managed;
environmental Impact
Assessments (EIAs); Drilling
and Field Development
programs; Well proposals and
Production Reservoir reports
assessed; National oil and gas
reserves and production
volumes compiled.
Production License for the
Kingfisher Development Area
issued and development
operations commenced;
Acquisition of 3D seismic data
in EA1 and EA1A continued;
coverage was 74% recording of
the 405.8 km2 ;
Continued review applications
for production licenses over
Kigogole-Ngege-Nsoga-Ngara
(KNNN) and Kasamene-
Wahrindi (KW) in EA2.
Continued review applications
for production licenses over
Ngiri field in EA1.
Monitoring Upstream
petroleum activities
Field operations and exploration
costs incurred by licensees
monitored.
Seismic and drilling operations
in Kingfisher development Area
monitored;
Five applications for licenses
and accompanied FDP and
petroleum Reservoir reports
reviewed.
040303
Vote Overview
81
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Petroleum Exploration, Development & Production03 03
Programme 04 Petroleum Exploration Production Department
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
Wage Recurrent
Non Wage Recurrent
Total
117,783
280,000
397,783
88,614
187,969
276,583
0
116,000
116,000
Information on oil and gas
disseminated; stakeholders
sensitized on the ongoing oil
and gas activities in the country;
Departmental website upgraded
and updated; Media reporting
on the oil and Gas sector
improved.
Held 20 Radio talk shows in
Bunyoro region;
4 stakeholder meetings with
district leaders and community
members were held in Kanungu,
Arua, Hoima and Kampala.
Commenced procurement for
upgrade of Website
Develop and implement a
communication strategy
for oil & gas in the country
Information on oil and gas
dissemination;
Stakeholders sensitized on the
ongoing oil and gas activities in
the country;
Department website upgraded
and updated .
Media reporting on the oil and
gas sector improved.
050303
Wage Recurrent
Non Wage Recurrent
Total
18,120
45,000
63,120
12,918
15,252
28,170
0
35,000
35,000
Regional Conferences prepared
and eight meetings on oil and
gas attended.
-The department participated in
three EAC Energy Committee
meetings;
-The department participated in
three preparatory meetings for
the EAPCE’15 in Tanzania;
-The department participated in
three meetings on co-operation
with DRC in the oil and gas
activities.
Participate in Regional
Initiatives
The East African Petroleum
Conference and Exhibition 2015
(EAPCE'15) successfully
prepared;
Attend eight regional meetings
on oil and gas development.
060303
Wage Recurrent
Non Wage Recurrent
Total
36,819
120,000
156,819
27,712
82,101
109,813
0
269,000
269,000
Wage Recurrent
Non Wage Recurrent
GRAND TOTAL
319,615
930,000
1,249,615
238,577
578,431
817,008
918,195
930,000
1,848,195
Annual Workplan for 2014/15 - Outputs, Activities, Inputs and their Cost
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
400 line km of Geophysical data acquired and geological and geochemical
mapping of 100 sq in the unlicensed and new basins undertaken.
Processed and packaged Gand G data;
Promotion of the country's petroleum potential undertaken.
Acquire 400km of geophysical data in the unlicensed areas plus
geological and geochemical mapping of 100 sq. km in the field
Geological and Geophysical data processing, interpretation and subsurface
models.
Laboratory analyses and interpretation from PEPD office.
Promotion of the country's petroleum potential and licensing010303
Wage Recurrent
Non Wage Recurrent
Total
918,195
350,000
1,268,195
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Electricity (kwH) 20,000.0 10,000
Adverts (Number) 8.0 16,400
Computer Supplies (Number) 10.0 25,000
ICT Services (Number) 4.0 8,000
Postage (Number) 4.0 5,000
Stationery (Number) 4.0 30,000
Training (Number) 7.0 175,000
Travel Abroad (Number) 4.0 60,000
Vehicle Maint (Number) 4.0 12,000
Permanent Staff (Person Years) 70.0 918,195
Subscriptions (Quarterly) 4.0 6,000
Water (Units) 1,000.0 2,600
Initiate and formulate petroleum policy and legislation020303Output:
Vote Overview
82
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Petroleum Exploration, Development & Production03 03
Programme 04 Petroleum Exploration Production Department
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
Attendant regulations for Upstream petroleum subsector in place;
New regulations and guidelines for the upstream activities in place;
Updated Model Production Sharing Agreement.
Monitoring and Evaluation strategy for the National Oil and Gas Policy
implemented
Complete the formulation of new regulations and guidelines for the
upstream and midstream activities
Complete the review and update the model PSA
Participate in updating the Revenue Management law and attendant
legislation
Wage Recurrent
Non Wage Recurrent
Total
0
60,000
60,000
Activities to Deliver Outputs:
Planned Outputs: Inputs Quantity Cost
Fuels (Litre) 2,682.0 10,728
Allowances (Number) 20.1 30,162
Printing and Stationery (Number) 50.0 7,000
Telecomm (Number) 4.1 6,110
Vehicle Maint (Number) 4.0 6,000
National expertise for the oil and gas developed and maintained.
Training of seven (7) members of staff at M.Sc. Level in petroleum
studies commenced.
Training at formal, industrial and on the job level both abroad and in the
country undertaken
Three study visits on the areas of licensing, petroleum development and
production undertaken.
Capacity Building for the oil & gas sector030303
Wage Recurrent
Non Wage Recurrent
Total
0
100,000
100,000
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Stationery (Lots) 4.0 2,000
Allowances (Numb) 4.1 10,270
Books, Periodicals and Newspapers (Numb) 12.4 3,730
Insurance (Number) 4.0 4,000
Training (Number) 1.0 80,000
Field operations and exploration costs incurred by licensees monitored.
Seismic and drilling operations in Kingfisher development Area
monitored;
Five applications for licenses and accompanied FDP and petroleum
Reservoir reports reviewed.
Monitor Field operations and exploration costs incurred by licensees.
Monitor 3Dseismic and drilling operations in Kingfisher development
Area
Applications for licenses and accompanied FDP and petroleum Reservoir
reports reviewed.
Monitoring Upstream petroleum activities040303
Wage Recurrent
Non Wage Recurrent
Total
0
116,000
116,000
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Fuels (Litres) 5,000.0 20,000
Stationery (Lots) 4.0 18,000
Telecomm (Numb) 4.0 1,800
Travel Inland (Numb) 4.1 66,200
Vehicle Maintenance (Number) 4.0 10,000
Develop and implement a communication strategy for oil & gas in the country050303Output:
Vote Overview
83
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Petroleum Exploration, Development & Production03 03
Programme 04 Petroleum Exploration Production Department
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
Information on oil and gas dissemination;
Stakeholders sensitized on the ongoing oil and gas activities in the
country;
Department website upgraded and updated .
Media reporting on the oil and gas sector improved.
Four stakeholder consultation workshops and twelve radio talk shows held
in the Albertine Graben.
The website on petroleum exploration, development and production
operations regularly updated and maintained.
Wage Recurrent
Non Wage Recurrent
Total
0
35,000
35,000
Activities to Deliver Outputs:
Planned Outputs: Inputs Quantity Cost
Electricity (KWh) 1,200.0 600
Printing (Lots) 40.0 12,800
Adverts (Number) 4.0 18,000
Allowances (Number) 4.0 2,000
Postage (Number) 4.0 500
Telecomm (Number) 4.0 600
Water (Units) 200.0 500
The East African Petroleum Conference and Exhibition 2015 (EAPCE'15)
successfully prepared;
Attend eight regional meetings on oil and gas development.
Participate in four EAC Energy Committee meetings;
Participate in four preparatory meetings for EAPCE'15 Conference;
Participate in four meetings on cooperation with DRC in the oil and gas
activities.
Participate in Regional Initiatives060303
Wage Recurrent
Non Wage Recurrent
Total
0
269,000
269,000
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Allowances (Number) 20.0 34,000
Travel Abroad (Number) 31.3 235,000
Wage Recurrent
Non Wage Recurrent
GRAND TOTAL
918,195
930,000
1,848,195
Vote Overview
84
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Petroleum Exploration, Development & Production03 03
Project 1142 Management of the Oil and Gas Sector in Uganda
Commissioner - PEPD
The Goal of the programme is to contribute to the achievement of the goal of the National Oil
and Gas Policy which is " To use the country's oil and gas resources to contribute to early
achievement of poverty eradication and create lasting value to society" With a specific
purpose of putting in place institutional arrangements and capacities to ensure well-
coordinated and results oriented resource management, revenue management, environmental
management and HSE management in the oil and gas sector.
Resource Management Pillar
1.Legal and regulatory framework for the upstream and midstream petroleum sectors
developed.
2.Licensing strategy and plan in place.
3.Monitoring and supervision framework established.
4.Institutional development and capacity building undertaken.
5.National and local participation enhanced.
6.Data and records management.
7.Resource assessment plan and contribute to the assessment of the country's oil and gas
resources and to the national oil and gas inventory: System for continuously updating resource
inventory, capacity and procedures to assess petroleum resources developed.
8.Oil and gas sector development and investment strategy/plan developed.
9.Regional and international cooperation bilateral treaties, agreement with DRC and technical
standardization reviewed and updated.
Revenue Management Pillar
1.Oil Revenue management policy to establish collection, accounting and utilisation of oil and
gas resources, payment modalities and enforcement approved
2.Existing tax legislation and regulations reviewed and updated, ensuring coherency with the
new Revenue Management Law
3.Drafting the consolidated PFM Law including Petroleum provisions.
4.Assessment of the existing institutions conducted and human resource plan analysed and
updated
5.Revenue administration; adequate systems for fiscal measurement and tax assessment
developed and a system for collection of revenues from oil and gas activities established
6.Fiscal policy; the current fiscal framework assessed, taking into account the impact of oil
and gas activities and a fiscal policy strategy paper drafted
7.Monetary policy management; The current monetary framework assessed and updated,
taking into account the impact of oil and gas activities
8.Banking arrangements and accountability; A petroleum fund established
Environment Management Pillar
1.Strategic Environmental Assessment (SEA) for the Albertine Graben conducted and results
widely disseminated.
2.Capacity development programs developed and implemented in all relevant institutions, for
areas identified as relevant/critical to the oil and gas sector based on capacity needs
assessment.
3.Environmental and biodiversity related policies reviewed with respect to oil and gas
including biodiversity off-sets, and presented for approval.
4.Existing Acts reviewed, recommendations drafted and presented for approval
Responsible Officer:
Objectives:
Outputs:
Project Profile
Vote Overview
85
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Petroleum Exploration, Development & Production03 03
Project 1142 Management of the Oil and Gas Sector in Uganda
Workplan Outputs for 2013/14 and 2014/15
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
Geological, Geophysical and
Geochemical data in the
unlicensed basins collected and
packaged; Investment
promotion undertaken; resource
assessment and laboratory
analyses conducted.
Due diligence done on 20
companies that have shown
interest to invest in the oil and
gas sector;
One Benchmarking study visit
undertaken TPDC, Tanzania
1st Draft of TORs for a
consultant to advise and
participate on formulation of
bidding requirements,
establishment of data room,
evaluation of bids, negotiation
of PSA undertaken
Licensing strategy continued to
be developed;
The department undertook a
technical study tour to Petronas
of Malaysia.
Continued preparations for the
country’s 1st licensing round
including holding a workshop
on data room building with
Schlumberger.
Promotion of the country's
petroleum potential and
licensing
Promotional data (Geological,
geophysical and geochemical)
acquired in the unlicensed
basins collected and packaged
Undertake seismic speculative
surveys in unlicensed areas;
Plan for and undertake the 1st
Licensed Round in the Albertine
Graben;
Assessment of the country's
undiscovered petroleum
reserves undertaken.
010303
GoU Development
External Financing
Total
853,000
1,016,300
1,869,300
629,547
0
629,547
1,207,522
721,000
1,928,522
-New Regulations and
guidelines for the Upstream
A zero draft for the upstream
regulations is in place.
Initiate and formulate
petroleum policy and
New regulations and guidelines
for upstream activities
020303
5.Management plans for protected areas, and relevant sector plans for the AG, reviewed and
updated taking the oil and gas issues into consideration.
6.An environmental monitoring system for the AG, with clear and agreed indicators, is
established
7.Environmental regulations and standards relevant to the oil and gas sector developed and/or
revised
8.Hazardous waste management system strengthened.
9.Framework for compliance monitoring and enforcement of the oil and gas industry
strengthened
10.National oil spill contingency plan developed and operationalized.
3.4Programme Management (Cross-Cutting Activities)
1.Programme Coordination Committee Meetings held quarterly
2.Annual Report Submitted to the embassy and annual meetings held
3.Programme Secretariat staff recruited and salaries paid
4.Office Stationery and Equipment procured
5.Communication Strategy for the Oil and Gas sector developed and implemented
6.Monitoring and Evaluation Framework for the National Oil and Gas Policy developed
7/9/2009 6/30/2017Start Date: Projected End Date:
Donor Funding for Project:
2016/172012/13
Budget
2013/14
Budget 2014/15 2015/16
MTEF Projections
Projected Donor Allocations (UShs)
Norway 7.929 13.000 10.730 0.7304.038535
7.929 13.000 10.730 0.7304.038Total Donor Funding for Project
Vote Overview
86
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Petroleum Exploration, Development & Production03 03
Project 1142 Management of the Oil and Gas Sector in Uganda
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
activities developed;
Model PSA reviewed and
updated;
Monitoring and Evaluation (M
& E) strategy for the National
Oil and Gas Policy (NOGP)
formulated.
The M&E framework for the
National Oil and Gas Policy
was finalized; to operationalize
it is to be worked out during the
4th quarter.
legislation developed
Model PSA reviewed and
updated
Monitoring and Evaluation (M
& E) strategy for the (NOGP)
implemented
Development of the National
Content Policy and Strategic
Plan for oil and gas sector
implemented
GoU Development
External Financing
Total
1,652,000
660,000
2,312,000
1,321,814
0
1,321,814
613,263
338,100
951,363
-National expertise for the oil
and gas developed and
maintained; National Content
policy and strategy put in place.
Creation of new institutions
(The Authority, Directorate and
National Oil Company).
9 staff continued their Master’s
degree studies in various
Universities abroad.
The process of
operationalization of the new
petroleum institutions continued.
Recruitment of ten additional
staff on contract basis
commenced
Capacity Building for the
oil & gas sector
National expertise for the oil
and gas developed and
maintained;
The training at formal, industrial
and on-the-job level both
abroad and in the country for
both existing and new staff
continued.
Training seven (7) members of
staff at M.Sc. Level in
petroleum related studies
abroad, commenced.
030303
GoU Development
External Financing
Total
2,358,000
4,901,100
7,259,100
2,038,352
0
2,038,352
4,240,000
0
4,240,000
Surveys and field operations
exploration costs uncured by
licensees monitored; Petroleum
Data efficiently managed;
environmental Impact
Assessments (EIAs); Drilling
and Field Development
programs; Well proposals and
Production Reservoir reports
assessed; National oil and gas
reserves and production
volumes compiled.
9 staff continued their Master’s
degree studies in various
Universities abroad.
The process of
operationalization of the new
petroleum institutions continued.
Recruitment of ten additional
staff on contract basis
commenced
Monitoring on a 24- hour basis
for the following activities
undertaken;
- Drilling of Rii-2;
- Drilling of Mpyo-3A
-Testing of Rii-2 ;
-Acquisition of seismic in EA1;
-Kingfisher Development Area
(KFDA) Civil works;
-Ngassa-2 Plug and
abandonment operations.
The Board of survey Report
that established the reserve
price for the test crude oil was
submitted to PDU
Monitoring Upstream
petroleum activities
Field operations and exploration
costs incurred by licensees
monitored.
Monitor seismic and drilling
operations in Kingfisher
development Area;
Five applications for licenses
and accompanied FDP and
petroleum Reservoir reports
reviewed.
Petroleum Data efficiently
managed;
040303
Vote Overview
87
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Petroleum Exploration, Development & Production03 03
Project 1142 Management of the Oil and Gas Sector in Uganda
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
Continued review applications
for production licenses over
Kigogole-Ngege-Nsoga-Ngara
(KNNN) and Kasamene-
Wahrindi (KW) in EA2.
Continued review application
for production license over
Ngiri field in EA1
GoU Development
External Financing
Total
1,230,000
350,700
1,580,700
868,828
0
868,828
2,000,000
0
2,000,000
Information on oil and gas
disseminated; stakeholders
sensitized on the ongoing oil
and gas activities in the country;
Departmental website upgraded
and updated; Media reporting
on the oil and Gas sector
improved.
Press conferences held;
Queries and inquiries on the
sector responded to.
-Participated in meetings
organised by the Rural Initiative
for Community Empowerment-
West Nile in four districts
namely. Buliisa, Nwoya, Nebbi
and Arua for district leaders and
the Business community
-Participated two dialogues
organised by Buliisa Rural
Initiative for Development
Organisation on Women
participation in oil and gas and
another on Land in Buliisa and
Masindi districts, respectively.
-Held an engagement with the
Anglican Bishops update them
on the developments in the
sector.
-Held media briefing on MoU
between Government and Oil
Companies ;
-Held five Radio talk shows on
Revenue Management
-Held five Radio talk shows on
Commercialisation Plans and
Land use Management
-Held five talk shows on
Environmental Management in
the Oil and Gas sector;
-Attended and facilitated a
meeting organised by the
Association of Oil and Gas
Service Providers of Uganda in
Nwoya.
-Commenced procurement for
upgrade of Website;
-Participated in three
community sensitization
meetings with persons affected
by the refinery organised by
Hoima Caritas Development
Organisation HOCADEO;
-Held 5 sensitisation meetings
in refinery area to sensitise
communities on prudent
utilisation of compensation
money;
-Held a community meeting
Develop and implement a
communication strategy
for oil & gas in the country
Information on oil and gas
disseminated;
Stakeholders sensitized on the
ongoing oil and gas activities in
the country;
Media reporting on Oil and Gas
sector improved.
050303
Vote Overview
88
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Petroleum Exploration, Development & Production03 03
Project 1142 Management of the Oil and Gas Sector in Uganda
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
with communities and cattle
keepers in the refinery area over
Pastoralists who are
encroaching on refinery land.
GoU Development
External Financing
Total
945,000
464,000
1,409,000
573,424
0
573,424
106,475
0
106,475
Regional Conferences and
meetings on oil and gas
prepared and attended.
-The department participated in
one EAC Energy Committee
meeting;
-The department participated in
one preparatory meeting for the
EAPCE’15 in Tanzania.
Participate in Regional
Initiatives
The East African Petroleum
Conference and Exhibition 2015
(EAPCE'15) successfully
prepared;
Attend eight regional meetings
on oil and gas development.
060303
GoU Development
External Financing
Total
462,440
37,000
499,440
316,040
0
316,040
83,263
31,000
114,263
- Standards and Codes for
midstream petroleum operations
are developed.
- RAP study for the acquisition
of way eaves for the crude
pipelines to the refinery and for
products' pipeline from Hoima
to Buloba and storage terminal
commenced.
- Baseline Environmental
Survey for crude oil pipelines
and Hoima-Buloba pipeline
completed.
- Legal framework for oil
refining, gas processing and
utilization in place
- Regulations and the Licensing
framework for midstream
activities developed
Continued supporting the
activities of the transitional
Units to facilitate the new
institutions
Transfer for Petroleum
Refining (Midstream Unit)
Operationalisation of new
Institutions; i.e. PAU, NATOIL
and Petroleum Directorate.
510303
GoU Development
External Financing
Total
2,000,000
0
2,000,000
1,777,219
0
1,777,219
2,000,000
0
2,000,000
Construction of Phase-2 of the
new Data Centre completed and
Phase-3 commenced;
maintenance of existing
buildings and related
infrastructure undertaken.
The process of varying the
Phase-2 contract to include an
additional floor commenced.
Routine maintenance of office
buildings and the surrounding
environment undertaken
Government Buildings and
Administrative
Infrastructure
Construction of Phase-3 of the
new Data Centre;
Maintenance of existing
buildings and related
infrastructure undertaken;
Establishment and Rent for field
based offices.
720303
GoU Development
External Financing
Total
8,900,000
0
8,900,000
4,373,327
0
4,373,327
7,939,440
0
7,939,440
Laboratory and Geophysical
equipment procured and
maintained.
Procurement of the gas
generators, chemicals and one
gravity meter commenced
Purchase of Specialised
Machinery & Equipment
Laboratory and Geophysical
equipment procured and
maintained.
770303
GoU Development
External Financing
Total
586,000
0
586,000
146,020
0
146,020
0
11,909,900
11,909,900
GoU Development
External Financing
GRAND TOTAL
18,986,440
7,429,100
26,415,540
12,044,573
0
12,044,573
18,189,963
13,000,000
31,189,963
Vote Overview
89
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Petroleum Exploration, Development & Production03 03
Project 1142 Management of the Oil and Gas Sector in Uganda
Annual Workplan for 2014/15 - Outputs, Activities, Inputs and their Cost
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
Promotional data (Geological, geophysical and geochemical) acquired in
the unlicensed basins collected and packaged
Undertake seismic speculative surveys in unlicensed areas;
Plan for and undertake the 1st Licensed Round in the Albertine Graben;
Assessment of the country's undiscovered petroleum reserves undertaken.
Update promotional packages ;
Attend and promote the country's petroleum potential at four (04)
international conferences;
Appropriate due dilligence on companies that have expressed interest in
participating in the country's petroleum industry and licensing;
Conclusion of Model contract and bidding terms for speculative seismic
surveys;
Acquire non-exclusive seismic data in the unlincensed areas (planning
and monitoring).
Undertake licensing of the unlicensed and relinquished areas in the
Albertine Graben;
Development of a Stratigraphic Framework for the Albertine Graben.
Participate in four preparatory meetings for EAPCE'15 Conference.
Promotion of the country's petroleum potential and licensing010303
GoU Development
External Financing
Total
1,207,522
721,000
1,928,522
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Allowances () 4.0 3,000
Computer supplies (Computers) 20.0 50,000
Fuel (litres) 8,750.0 35,000
Consultancy for 1st Licensing round (Number) 7.6 760,000
Training (number) 7.6 568,498
Travel Inland (number) 20.0 100,000
Gratuity (units) 5.0 25,000
NSSF (UNITS) 4.0 10,000
Travel abroad (Units) 183.1 366,124
Workshops (units) 37.0 110,900
New regulations and guidelines for upstream activities developed
Model PSA reviewed and updated
Monitoring and Evaluation (M & E) strategy for the (NOGP) implemented
Development of the National Content Policy and Strategic Plan for oil and
gas sector implemented
Undertake Meetings for formulation of new regulations and guidelines for
upstream activities;
Undertake Consultative study visits;
Implement the Monitoring and Evaluation (M & E) strategy for the
National Oil and Gas Policy (NOGP);
Complete the formulation of new regulations and guidelines for the
upstream activities;
Complete the development of the National Content Policy and Strategy.
Initiate and formulate petroleum policy and legislation020303
GoU Development
External Financing
Total
613,263
338,100
951,363
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Fuels (litres) 10,000.0 40,000
Gratuity (numb) 2.3 14,000
Training (numb) 8.0 70,000
Travel Abroad (Numb) 2.0 40,000
Computer supplies (number) 4.0 12,000
Consultancy (Number) 10.1 506,801
NSSF (Number) 4.0 9,600
Stationery (number) 400.0 22,000
Travel Inland (Number) 4.0 50,000
Vehicle Maint (Number) 3.8 23,699
Workshops (number) 6.7 100,000
Contract staff (Person Years) 1.0 63,263
Vote Overview
90
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Petroleum Exploration, Development & Production03 03
Project 1142 Management of the Oil and Gas Sector in Uganda
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
National expertise for the oil and gas developed and maintained;
The training at formal, industrial and on-the-job level both abroad and in
the country for both existing and new staff continued.
Training seven (7) members of staff at M.Sc. Level in petroleum related
studies abroad, commenced.
National expertise for the oil and gas developed and maintained;
Training seven (7) members of staff at M.Sc. Level in petroleum related
studies abroad;
Continue to provide support to the Uganda Petroleum Institute Kigumba
and the Makerere University;
Capacity Building for the oil & gas sector030303
GoU Development
External Financing
Total
4,240,000
0
4,240,000
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Computer (Numb) 107.6 134,562
Training (numb) 8.0 1,000,000
Allowances (number) 3.5 2,198,672
Contract staff (Person Years) 43.0 906,766
Field operations and exploration costs incurred by licensees monitored.
Monitor seismic and drilling operations in Kingfisher development Area;
Five applications for licenses and accompanied FDP and petroleum
Reservoir reports reviewed.
Petroleum Data efficiently managed;
Monitoring of appraisal 3D seismic survey and drilling of appraisal wells
in EA1.
Monitor 3D seismic and drilling operations in Kingfisher development
Area (KDA).
Applications for licenses and accompanied FDP and petroleum Reservoir
reports reviewed;
Evaluation of expatrites' Work permits.
Monitoring Upstream petroleum activities040303
GoU Development
External Financing
Total
2,000,000
0
2,000,000
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Fules (Litres) 87,500.0 350,000
Allowances (numb) 244.3 1,038,226
Consultancy (Numb) 4.0 200,000
Gratuity (numb) 4.0 48,000
NSSF (NUMB) 4.0 20,000
Travel Inland (Numb) 4.0 133,000
Vehicle Maint (numb) 38.3 160,774
Workshops (Numb) 4.0 50,000
Information on oil and gas disseminated;
Stakeholders sensitized on the ongoing oil and gas activities in the
country;
Media reporting on Oil and Gas sector improved.
Develop and implement a communication strategy for oil & gas in the country050303
Planned Outputs:
Output:
Inputs Quantity Cost
Sensitisation Workshops () 3.2 80,000
Allowances (Perdiem) 220.6 26,475
Vote Overview
91
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Petroleum Exploration, Development & Production03 03
Project 1142 Management of the Oil and Gas Sector in Uganda
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
Four stakeholder consultation workshops and twelve radio talk shows held
in the Albertine Graben.
The website on petroleum exploration, development and production
operations regularly updated and maintained.
GoU Development
External Financing
Total
106,475
0
106,475
Activities to Deliver Outputs:
The East African Petroleum Conference and Exhibition 2015 (EAPCE'15)
successfully prepared;
Attend eight regional meetings on oil and gas development.
Participate in four EAC Energy Committee meetings;
Participate in four meetings on cooperation with DRC in the oil and gas
activities.
Participate in Regional Initiatives060303
GoU Development
External Financing
Total
83,263
31,000
114,263
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Workshops (Number) 5.7 51,000
Contract staff (Person Years) 6.0 63,263
Operationalisation of new Institutions; i.e. PAU, NATOIL and Petroleum
Directorate.
Establisment of new Institutions;
Support the acitivities of the Trasnitional Units
Transfer for Petroleum Refining (Midstream Unit)510303
GoU Development
External Financing
Total
2,000,000
0
2,000,000
Activities to Deliver Outputs:
Planned Outputs:
Output:
Grant or Transfer Cost
Establish New Instititions 2,000,000
Construction of Phase-3 of the new Data Centre;
Maintenance of existing buildings and related infrastructure undertaken;
Establishment and Rent for field based offices.
Procure a consultant and contractor to undertake designs for the Finishing
Stage (Phase-3)
Supervision Consultancy
Rent for extra offices at PEPD
Take up and maintain Hoima Liaison Office
Buildings.
Government Buildings and Administrative Infrastructure720303
GoU Development
External Financing
Total
7,939,440
0
7,939,440
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Building (Building) 10,000.0 6,200,000
Supervision of Works (Numb) 4.0 500,000
Buildings (number) 3.3 1,239,440
Purchase of Specialised Machinery & Equipment770303Output:
Vote Overview
92
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Petroleum Exploration, Development & Production03 03
Project 1142 Management of the Oil and Gas Sector in Uganda
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
Laboratory and Geophysical equipment procured and maintained.
Procurement of Geophysical 4 GPS sets
Procurement of Lab Equipment (Gases, Chemicals, equipment)
GoU Development
External Financing
Total
0
11,909,900
11,909,900
Activities to Deliver Outputs:
Planned Outputs:
GoU Development
External Financing
GRAND TOTAL
18,189,963
13,000,000
31,189,963
Vote Overview
93
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Petroleum Exploration, Development & Production03 03
Project 1184 Construction of Oil Refinery
Workplan Outputs for 2013/14 and 2014/15
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
-Promotion of private sector
participation in the development
and operation of the refinery
and Midstream Infrastructure.
-Promote Regional and
International cooperation for the
development of oil refining, gas
conversion, and Infrastructure in
Uganda
120 copies of the Midstream
Law printed
37 copies of the refinery
brochure printed
2 Consultative meetings on the
development of Standards held
A regulation workshop held
Zero draft of the regulations for
Promotion of the country's
petroleum potential and
licensing
Promote the development of a
crude export pipeline
Investment for the pipeline and
storage facilities promoted
Development of petrochemicals
and energy based industries
promoted
Plans for gas conversion and
utilisation developed
010303
Assistant Commissioner - Geology
(i) To develop an appropriate legal, regulatory and licensing framework for crude Oil refining,
and related infrastructure.
(ii) Plan for the development of the refinery, pipelines, storage facilities and related
midstream infrastructure
(iii) To contribute to building capacity in the new emerging areas of crude oil valuation and
Midstream Petroleum Operations.
(iv)To develop an appropriate modern institutional framework for crude Oil refining, and
related midstream petroleum operations
(v) To promote private sector participation in the development and operation of refineries and
related infrastructure.
(vi) To promote regional and international cooperation in the development of Midstream
infrastructure.
(i) A legal, regulatory and licensing framework for Midstream Operations implemented
(ii) Lead investor for the oil refinery development selected
(iii) Land acquired for refinery and title deed processed
(iv) Special Purpose Vehicle (refinery company) formed
(v) National Strategy and Plan for petroleum Transportation and storage facilities
developed
(vi) An Environmental Baseline Survey for pipeline development undertaken
(vii) Master Plan for the Aerodrome developed
(viii) Study to evaluate the utilization of gas undertaken
(ix)Pool of national expertise for Midstream Petroleum Operations developed and retained.
(x)A modern institutional framework including a structure, developed and implemented
(xi)A database of refinery technologies, licensors and other related areas well maintained
(xii)Dstrengthening of regional cooperation in development of Midstream infrastructure
achieved.
Responsible Officer:
Objectives:
Outputs:
7/1/2011 6/30/2016Start Date: Projected End Date:
Project Profile
Donor Funding for Project:
2016/172012/13
Budget
2013/14
Budget 2014/15 2015/16
MTEF Projections
Projected Donor Allocations (UShs)
Norway 6.390 0.000 0.000 0.0000.000535
6.390 0.000 0.000 0.0000.000Total Donor Funding for Project
Vote Overview
94
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Petroleum Exploration, Development & Production03 03
Project 1184 Construction of Oil Refinery
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
Midstream operations developed
Database of investors
developed
Technical Committee for
developing Standards and Codes
3 regional workshops held in
support of the pipeline
development (1 for crude oil
and 2 products pipeline )
1 regional summit workshop on
refinery development progress
held by the Refinery
Development Committee
GoU Development
External Financing
Total
1,056,780
0
1,056,780
530,386
0
530,386
1,120,500
0
1,120,500
- National expertise for crude
oil refining, gas processing and
utilization, transportation and
storage developed and
maintained;
- Mid-stream institutional
framework implemented and
required human resource
capacity developed.
Three officers undertook
training in financial analysis
facilitated by the Transaction
Advisor in between July 22nd –
26th 2013
Two officers commenced a
certificate training course in Oil
and Gas Flow Measurement and
Control Technique and
Standards at the Fluid Control
Research Institute in India.
Three officers undertook
training in Pipeline System
Design in from 7th to 18th
October 2013 in Japan
One officer attended a one
week’s National Oil Companies
Skills Transfer workshop in
October 2013 in South Africa.
3 officers undertaking training
long term training
Capacity Building for the
oil & gas sector
Human resource capacity for
crude oil refining, gas
processing and utilization,
transportation and storage
developed and maintained;
Mid-stream institutional
framework implemented.
030303
GoU Development
External Financing
Total
1,230,000
0
1,230,000
715,867
0
715,867
1,045,000
0
1,045,000
Acquisition of Land by
Government
Detailed route survey for
products pipeline from the
refinery to Buloba terminal
concluded
Resettlement Action Plan
(RAP) study crude oil from the
field to the refinery and
products pipeline from the
refinery to Buloba terminal
undertaken
Environmental Baseline Study
for pipelines undertaken
710303
GoU Development
External Financing
Total
0
0
0
0
0
0
2,929,000
0
2,929,000
- Land for the refinery and
supporting infrastructure
acquired;
- Continued implementation and
To date 1370 PAPs out of 2615
who opted for compensation
have been compensated
Oil Refinery Construction Acquisition of land for the
refinery development concluded.
Master plan and detailed
800303
Vote Overview
95
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Petroleum Exploration, Development & Production03 03
Project 1184 Construction of Oil Refinery
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
completion of Logistics study
- Transaction Advisory services
for Refinery development
undertaken;
- Pre - Front End Engineering
Design (FEED) for refinery
development completed.
- Aviation studies for
aerodrome development
undertaken
- Crude oil pipeline to the
refinery and storage facilities
study recommendations
implemented;
- Pre-FEED for refinery
products’ pipeline from Hoima
to Buloba terminal conducted.
Land for resettlement identified
Transaction Advisor hired to
assist Government procure a
lead investor/developer for the
refinery and also structure the
refinery project
Request for proposal issued to
bidders and submitted end May
2014 and evaluation completed
in Mid-June 2014
engineering design study for the
aerodrome development
concluded
Coordination of the activities of
the Transaction Advisor
GoU Development
External Financing
Total
32,695,500
6,389,900
39,085,400
24,235,791
0
24,235,791
29,880,220
0
29,880,220
GoU Development
External Financing
GRAND TOTAL
34,982,280
6,389,900
41,372,180
25,482,044
0
25,482,044
34,974,720
0
34,974,720
Annual Workplan for 2014/15 - Outputs, Activities, Inputs and their Cost
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
Promote the development of a crude export pipeline
Investment for the pipeline and storage facilities promoted
Development of petrochemicals and energy based industries promoted
Plans for gas conversion and utilisation developed
Pipeline brochure updated and printed
Attend regional meetings on the development of pipelines and other
midstream infrastructure
Undertake a study to assess the petrochemical industry potential in Uganda
Engagements with potential investors in the petrochemical industry
Undertake a study to assess the investment and utilisation options in
Uganda
Promotion of the country's petroleum potential and licensing010303
Total 1,120,500
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Fuel and lubricants (Litres) 14,285.7 50,000
Rent (Months) 3.3 10,000
Advertising (Number) 40.0 20,000
Books and periodicals (Number) 4.0 10,000
Consultancy services (Number) 14.0 70,000
Maintain machinery and equipment (Number) 4.0 20,000
Meals and drinks (Number) 8.0 2,000
Postage and courier (Number) 100.0 5,000
Purchase of computers and accessories (Number) 4.0 36,000
Purchase of small office equipment (Number) 5.0 10,000
Purchase of stationery, printing services (Number) 5.0 50,000
Subscriptions (Number) 2.0 10,000
Travel abroad (Number) 10.0 100,000
Travel inland (Number) 5.0 24,000
Welfare and entertainment (Number) 4.0 11,000
Workshops and seminars (Number) 1.0 12,000
Hiring venues for workshops, training (Numbers) 4.0 10,000
Contract staff (Person Years) 6.0 250,000
Gratuity payment to contract staff (persons) 2.0 50,000
NSSF contribution for contract staff (persons) 9.3 50,000
Payment for guards and security services (Persons) 1.0 2,500
Recruiting more staff on the refining project
(Persons)
1.0 3,000
Training of staff in refining (Persons) 2.0 175,000
Maintenance for vehicles (Times) 8.0 100,000
Electricity bills for the infrastructure unit (Units) 33,333.3 20,000
Telecommunications (Units) 10,000.0 10,000
Water bills for infrastructure unit (Units) 100,000.0 10,000
Vote Overview
96
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Petroleum Exploration, Development & Production03 03
Project 1184 Construction of Oil Refinery
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
GoU Development
External Financing
1,120,500
0
Human resource capacity for crude oil refining, gas processing and
utilization, transportation and storage developed and maintained;
Mid-stream institutional framework implemented.
Long term training
Short term training
Developing and maintaining a database of artisans
Study/industrial visits to oil refineries, pipelines and other midstream
infrastructure sites
Implementation of the Institutional Framework for oil refining, gas
convesion and utilisation, transportation and storage
Continue engagements with educational institutions on curricula
development
Capacity Building for the oil & gas sector030303
GoU Development
External Financing
Total
1,045,000
0
1,045,000
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Fuel (Litres) 7,500.0 30,000
Rent for office space (Months) 6.0 18,000
Advertiising and public relations (Number) 10.0 20,000
Computer supplies (Number) 4.0 20,000
Consultancy services (Number) 2.0 20,000
Gratuity to contract staff (Number) 10.0 50,000
Maintenance of machines (Number) 4.0 10,000
NSSF contribution by contract staff (Number) 4.0 25,000
Periodicals and books (Number) 4.0 15,000
Postage and courier (Number) 60.0 3,000
Purchase of small office equipment (Number) 5.0 10,000
Recruitment expenses (Number) 1.0 2,500
Security services (Number) 10.0 2,500
Special meals and drinks (Number) 4.0 6,000
Stationery (Number) 5.5 22,000
Training of staff (Number) 2.0 181,000
Travel abroad (Number) 3.0 150,000
Travel inland (Number) 4.8 24,000
Vehicle maintenance (Number) 10.0 100,000
Venue hire for activities outside office (Number) 4.0 10,000
Welfare and entertainment (Number) 2.0 11,000
Workshops (Number) 2.0 25,000
Contract staff (Person Years) 6.0 250,000
Payment of water bills (Unit) 100,000.0 10,000
Electricity bills (Units) 33,333.3 20,000
Telecommunication units (Units) 10,000.0 10,000
Detailed route survey for products pipeline from the refinery to Buloba
terminal concluded
Resettlement Action Plan (RAP) study crude oil from the field to the
refinery and products pipeline from the refinery to Buloba terminal
undertaken
Environmental Baseline Study for pipelines undertaken
Monitoring of the route survey activities
Stakeholder engagements to review study findings and recommendations
of the detailed route survey
Sensitisation of the persons affected by the detailed route survey
Preparation of documentation on detailed route survey.
Monitoring of the RAP study for pipelines
Stakeholder engagements to review study findings and recommendations
of the RAP for pipelines development
Sensitisation of the persons affected by the RAP study for pipelines
Acquisition of Land by Government710303
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Engineering studies on pipelines development
(Number)
4.0 2,000,000
Monitoring and supervision (Number) 46,450.0 929,000
Vote Overview
97
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Petroleum Exploration, Development & Production03 03
Project 1184 Construction of Oil Refinery
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
Preparation of documentation on RAP study for pipelines
Stakeholder engagements to review study findings and recommendations
of the Environmental Baseline Survey for pipeline development
Sensitisation engagments with the locals on the Environmental Baseline
study
Monitoring of the Environmental baseline study activities
GoU Development
External Financing
Total
2,929,000
0
2,929,000
Acquisition of land for the refinery development concluded.
Master plan and detailed engineering design study for the aerodrome
development concluded
Coordination of the activities of the Transaction Advisor
Compensation and resettlement of project affected persons (PAPs)
Sensitization of the locals in oil region through radio talk shows,
workshops on the refinery development activities
Field travel of Government officers to monitor the compensation and
resettlement process
Preparation of RAP implementation materials such as reports
Monitoring of the activities of the consultant conducting the studies for
aerodrome development
Participate in the formation of the Special Purpose Vehicle for refinery
development
Participation of officers in the process of sourcing for financing of
refinery development
Oil Refinery Construction800303
GoU Development
External Financing
Total
29,880,220
0
29,880,220
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Engineering studies in the refinery area (Number) 1.0 880,220
Compensation and relocation (Shillings) 2,000,000.0 29,000,000
GoU Development
External Financing
GRAND TOTAL
34,974,720
0
34,974,720
Vote Overview
98
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Petroleum Supply, Infrastructure and Regulation03 04
Services:
Responsible Officer:
Vote Function Profile
This vote function inspects and monitors the operations of private oil companies
with respect to volumes, prices, product quality, safety of operation, technical and
environmental standards. It manages and ensures that the country has sufficient
national strategic reserves to act as a reserve buffer when there is a supply outage
and stabilize the supply of petroleum products in the country. It also implements
the Petroleum Supply (General) Regulations, 2009.
Commissioner, Petroleum Supply Department
Vote Function Projects and Programmes:Project or Programme Name Responsible Officer
Recurrent Programmes
07 Petroleum Supply Department Commissioner, PSD
Development Projects
1258 Downstream Petroleum Infrastructure Assistant Commissioner/ Business and Economics Division
Programme 07 Petroleum Supply Department
Workplan Outputs for 2013/14 and 2014/15
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
- Participation in the East
African Community Activities
- Emergency Petroleum Supply
Plan (EPSP) implemented
-TPC meetings held on
schedule
- Staff trained in specialized
fields.
- Policy for Downstream
Petroleum sub-sector in place
1 Technical Petroleum
Committee meeting held
-1 stakeholder’s consultative
workshop on draft downstream
Petroleum Policy held
- 2 officers commenceed
longterm course for one year
each
Petroleum Policy
Development, Regulation
and Monitoring
- East African Community
meetings attended
- Emergency Petroleum Supply
Plan (EPSP) implemented
- TPC Meetings held on
Schedule
- Policy for Downstream
Petroleum sub-sector in place
- Tripartite meetings on
infrastructure development
attended
010403
Wage Recurrent
Non Wage Recurrent
Total
41,051
317,409
358,461
30,181
210,921
241,102
658,175
317,409
975,585
-Petroleum supply market
operations monitored
-Fair competition in the industry
promoted
-Petroleum standards
compliance enforced
-434 Retail facilities monitored
in southern ,Eastern, Western
and central region.
-One meeting held with
stakeholders.
Management and
Monitoring of petroleum
supply Industry
-Petroleum Supply market
operations monitored
- Fair competition in the
Industry promoted
- Petroleum standards
compliance enforced
020403
Commissioner, PSD
-To streamline petroleum supply and distribution-To develop institutional , organizational
structure and capacity of the Petroleum Supply Department.-To ensure sufficient stock of
petroleum products on the market.-To establish standards and promote product quality and
HSE- Promote efficient mode of transportion of petroleum products- Develop and
maintain the NPIS
This vote functions inspects and monitors the operations of private oil companies with respect
to volumes, prices, product quality, safety of operation, technical and environmental
standards. It also manages and ensures that the country has sufficeint national stocks of
petroleum products. Licensing of petroleum operators and facilities and enforcement of
standards. It maintains the National Petroleum Information System for effcient dissemination
of data on petroleum supply.
Responsible Officer:
Objectives:
Outputs:
Programme Profile
Vote Overview
99
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Petroleum Supply, Infrastructure and Regulation03 04
Programme 07 Petroleum Supply Department
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
-Participation in Supply co-
ordination meetings
-JST operations commence
-JST management Supervised
-JST is operational,
commissioning differed to Jan
2014 pending work of
independent certifier whose
bids are to be received.
-112 fuel installation monitored
in Western region and reports
in place
-One supply coordination
meeting held
One case prosecuted and 20
illegal facilities closed.
-220 Retail facilities monitored
in Southern and central region.
- restocking of JST continues
- Petroleum Industry supply
coordination meetings organized
-JST operations monitored
Wage Recurrent
Non Wage Recurrent
Total
130,895
231,000
361,895
97,971
168,140
266,111
0
231,000
231,000
-Petroleum data collected and
NPIS populated.
-Reports on local pump prices,
regional prices and international
prices of petroleum products
produced and disseminated.
-Reports on imports, stocks and
sales of petroleum products
produced and disseminated.
-Regional price data captured.
-Reports on local pump prices
produced and disseminated.
-Reports on imports, stocks and
sales of petroleum products
produced and disseminated.
Reports on international
petroleum prices compiled.
Maintainance of National
Petroleum Information
System
- Petroleum data on prices,
stocks, sales and imports
collected and NPIS populated
- local pump prices, regional
prices and international prices
of petroleum products monitored
- Data on petroleum data
disseminated to other
Government agencies
- Annual Subscription to
PLATTS done
030403
Wage Recurrent
Non Wage Recurrent
Total
27,032
96,000
123,032
18,061
67,920
85,981
0
96,000
96,000
- Petroleum products quality
monitored.
-Licenses and permits evaluated
and issued
-Supervision of the Petroleum
quality and fuel marking
program
-EIA/EA reviewed
- 966 outlets visited and out of
3620 samples tested
-seveteen operating licenses
issued 26 construction permits
issued
- thiry two (32) EIAs done and
5 Eas carried out
Operational Standards
and laboratory testing of
petroleum products
- Applications for Licenses and
permits evaluated and issued
- Supervision of the petroleum
quality and fuel marking
program
-EIA/EA reviewed
- Database on licenses and
permits updated
040403
Wage Recurrent
Non Wage Recurrent
Total
123,389
209,251
332,639
92,350
158,090
250,440
0
209,251
209,251
- Private operator appointed
- Route acquisition for Malaba -
Kampala section of Kenya-
Uganda Oil pipeline commenced
-Updating and signing of the
Project Agreements.
-Updating of project documents
such as FEED, etc
-Government Equity
contribution in place
- Eight meetings held in
Kampala, Kenya and Kigali.
- Project documents updated
- EPC procurement documents
preparation for Kenya-Uganda
pipeline commenced
- Feasibility study for Uganda-
Rwanda pipeline commenced
Kenya - Uganda -
Rwanda Oil pipelines
- Project Agreements prepared
and signed
- RAP implementation
supervised
- Project documents such as
FEED etc update
060403
Wage Recurrent
Non Wage Recurrent
Total
12,198
44,986
57,184
7,172
31,515
38,687
0
44,986
44,986
Wage Recurrent
Non Wage Recurrent
GRAND TOTAL
334,565
898,646
1,233,211
245,734
636,587
882,321
658,175
898,646
1,556,821
Vote Overview
100
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Petroleum Supply, Infrastructure and Regulation03 04
Programme 07 Petroleum Supply Department
Annual Workplan for 2014/15 - Outputs, Activities, Inputs and their Cost
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
- East African Community meetings attended
- Emergency Petroleum Supply Plan (EPSP) implemented
- TPC Meetings held on Schedule
- Policy for Downstream Petroleum sub-sector in place
- Tripartite meetings on infrastructure development attended
-Four Regional EAC meetings attended
- 4 Technical Petroleum Committee meetings
- 4 Stakeholders’ consultative workshops on draft downstream
Petroleum policy
- 4 sensitization meetings on EPSP organized
- Four Tripartite meetings on infrastructure development attended
Petroleum Policy Development, Regulation and Monitoring010403
Wage Recurrent
Non Wage Recurrent
Total
658,175
317,409
975,585
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
allowances for TPC () 428.6 60,000
funnel services for staff () 200.0 20,000
staff allowances () 100.0 5,000
staff eats () 1,000.0 10,000
staff perdiem () 453.3 88,000
payment to UTL (airtime) 16,666.7 10,000
fuel (liters) 10,000.0 40,000
courier services (number) 50.0 5,000
Newspaper procurement (number) 1,666.7 5,000
procurement notice publication (Number) 5.0 15,000
procurement of catridge (number) 2.3 7,000
Publication of notices (Number) 5.0 15,000
supply of reams of papers (number) 350.0 7,000
supply of various office equipments LOT (Number) 9.0 9,000
Permanent Staff (Person Years) 37.0 658,175
maintenance of equipment (report) 2.0 4,000
vehicle repairs and servicing (reports) 8.7 17,409
-Petroleum Supply market operations monitored
- Fair competition in the Industry promoted
- Petroleum standards compliance enforced
- Petroleum Industry supply coordination meetings organized
-JST operations monitored
- Four Field inspection and monitoring
- Enforcement of the Petroleum Supply Act 2003 and facilities standards
- Four Petroleum Industry supply coordination meetings organized
- Quarterly JST monitoring reports in place
- Supervision of operations of JST
- Procurement of seals for enforcement
Management and Monitoring of petroleum supply Industry020403
Wage Recurrent
Non Wage Recurrent
Total
0
231,000
231,000
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
staff allowances () 3.5 7,000
staff eats () 350.0 7,000
payment to UTL (AIRTIME) 16,000.0 8,000
FUEL (LITERS) 10,000.0 40,000
perdiem (n/a) 966.7 145,000
news paper (number) 333.3 1,000
procurement of computer accessories (number) 10.0 5,000
reams of papers (number) 250.0 5,000
small office equipmment- pins,clipps (number) 100.0 3,000
vehicle services and repairs (reports) 3.3 10,000
- Petroleum data on prices, stocks, sales and imports collected and NPIS
populated
- local pump prices, regional prices and international prices of petroleum
products monitored
- Data on petroleum data disseminated to other Government agencies
- Annual Subscription to PLATTS done
-NPIS populated with data
-Quarterly report on prices, stocks, sales and imports in place
-Quarterly report on regional and international prices in place
-Quarterly reports on prices, sales, stocks and sales disseminated
Maintainance of National Petroleum Information System030403
Wage Recurrent
Non Wage Recurrent
Total
0
96,000
96,000
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
advance to staff () 700.0 7,000
newspaper () 1,000.0 5,000
payment to utl () 1,000.0 5,000
staff allowance () 250.0 5,000
staff perdiem () 300.0 30,000
supply of computers () 3.0 6,000
supply of reams paper () 350.0 7,000
supply of fuel (liters) 5,000.0 20,000
vehicle repairs and servicing (repors) 5.5 11,000
Operational Standards and laboratory testing of petroleum products040403Output:
Vote Overview
101
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Petroleum Supply, Infrastructure and Regulation03 04
Programme 07 Petroleum Supply Department
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
- Applications for Licenses and permits evaluated and issued
- Supervision of the petroleum quality and fuel marking program
-EIA/EA reviewed
- Database on licenses and permits updated
-Evaluation of applications for licenses and permits
-Field inspection for licensing and EIA/EA reviews
-Supervision of petroleum products’ marking at the border points
-Regular field monitoring for quality assurance
-2 Stakeholders’ consultative workshops on petroleum standard
Wage Recurrent
Non Wage Recurrent
Total
0
209,251
209,251
Activities to Deliver Outputs:
Planned Outputs: Inputs Quantity Cost
advance to staff welfare () 7.0 7,000
PERDIEM FOR STAFF () 1,066.1 149,251
servicing of equipments () 4.5 9,000
staff allowances () 250.0 5,000
supply computer accessories () 6.0 3,000
payment to UTL (AIRTIME) 5,000.0 3,000
FUEL (LITERS) 4,000.0 16,000
newspaper (number) 250.0 1,000
supply of reams of paper (number) 100.0 2,000
VEHICLE REPAIRS AND SERVICING (reports) 14.0 14,000
- Project Agreements prepared and signed
- RAP implementation supervised
- Project documents such as FEED etc update
- Procurement of valuation consultant to update the RAP
- Sensittisation of the PAPs
- Consultative meetings with stakeholders on Project Agreements and
documents
Kenya - Uganda - Rwanda Oil pipelines060403
Wage Recurrent
Non Wage Recurrent
Total
0
44,986
44,986
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
staff allowances () 374.2 34,386
staff eats () 200.0 2,000
vehicle servicing and repair () 1.0 1,000
utl paymet (airtime) 833.3 500
fuel (liters) 1,750.0 7,000
pins (number) 100.0 100
Wage Recurrent
Non Wage Recurrent
GRAND TOTAL
658,175
898,646
1,556,821
Vote Overview
102
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Petroleum Supply, Infrastructure and Regulation03 04
Project 1258 Downstream Petroleum Infrastructure
Workplan Outputs for 2013/14 and 2014/15
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
•Updated RAP the Kenya-
Uganda oil pipe line in place
- Private Operator selected
-Project Agreements and
documents updated
-Wayleave acquired and
handled over to the private
investor or development
- 8 JCC meetings held
- Project Documents upated
- Govenments of Kenya and
Uganda agreed to develop the
project as a Public project.
- Penspen appointed to carry
out feasibility study for
Kampala-Kigali Pipeline
segment
-EPC document preparation
commenced
Acquisition of Land by
Government
- Project documents drafting
finalized for Kenya-Uganda.
- Drafting of Project
Agreements for Kenya-Uganda
finalized.
- EIA for Kenya-Uganda
project finalized.
- Resettlement Action Plan
(RAP) updated (Malaba-
Kampala-Uganda)
- RAP implementation for
Malaba-Kampala commenced
- EPC tendering documments
finalised
710403
Assistant Commissioner/ Business and Economics Division
- Development of Kenya-Uganda Refined Petroleum Products Pipeline
-Development of Uganda-Rwanda Refined Petroleum Products Pipeline
- Development of regional storage infrastructure for petroleum products.
- Strengthen capacity of the Department to manage the activities of the downstream petroleum
subsector.
- Develop a modern National Petroleum Information System (NPIS) to effectively monitor the
subsector.
- Develop and operationalize codes of practice for the Petroleum downstream subsector.
- Develop operational health, environment and safety standards (HSE) for activities within the
supply chain of downstream petroleum sub-sector.
- Development of downstream petroleum Policy
- Route acquired for the proposed Kenya-Uganda Refined Petroleum Products pipeline
- Development of Uganda-Rwanda Refined petroleum products pipeline promoted
- Regional storage infrastructure for petroleum products developed
- Technical Capacity of staff of Petroleum Supply Department developed
- Necessary infrastructure and equipment procured
- National Petroleum Information System acquired and operational
- Codes of practice for the sector developed
- Downstream Petroleum Policy developed
- HSE standards for downstream petroleum sector in place
- Reduction in petroleum related accidents
- Petroleum products contingency plan in place
- An informed public on handling of petroleum products
Responsible Officer:
Objectives:
Outputs:
7/1/2013 6/30/2018Start Date: Projected End Date:
Project Profile
Donor Funding for Project:
2016/172012/13
Budget
2013/14
Budget 2014/15 2015/16
MTEF Projections
Projected Donor Allocations (UShs)
Africa Development Bank (ADB) 0.000 0.000 7.000 4.5740.000401
0.000 0.000 7.000 4.5740.000Total Donor Funding for Project
Vote Overview
103
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Petroleum Supply, Infrastructure and Regulation03 04
Project 1258 Downstream Petroleum Infrastructure
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
- Feasibility study for Uganda-
Rwanda pipeline project
completed
- Pipe line routing for Uganda-
Rwanda undertaken
- RAP for Uganda-Rwanda
development commenced
GoU Development
External Financing
Total
1,900,000
0
1,900,000
849,613
0
849,613
9,400,000
0
9,400,000
•- NPIS developed and
operational
-5 staff attain specialized
training in usage of NPIS
-Necessary hardware procured
-5 year subscription to PLATTS
done
- Office equipment and
furniture procured
- TOR for development of
NPIS developed
- Office Equipment procured
-Evalaution of bids for NPIS
onsultant and necessary
infrastructure in progress.
- Office equipment supplier paid
-Evaluation of bids for NPIS
consultant finalised.
-Subscription to PLATTS in
progress.
Purchase of Office and
ICT Equipment,
including Software
-Development of NPIS
completed
- 5 staff attain specialized
training in operating and
management of NPIS
- Necessary hardware procured
- Five year subscription to
PLATTS done
760403
GoU Development
External Financing
Total
700,000
0
700,000
4,100
0
4,100
700,000
0
700,000
-Codes of practice for
downstream petroleum sub-
sector in place
-Organizing 5 regional work
shop each financial year to
sensitize the population on
petroleum products handling
-Codes of practice enforced
-HSE for downstream
petroleum sub-sector in place
-TOR for development of codes
of practise developed
- Procurement of HSE
consultant commenced with an
advert in news papers
- Consultant to develop HSE
appointed
-One regional workshop held at
Imperial Royal, Kampala on
petroleum facilities standards
Purchase of Specialised
Machinery & Equipment
- Downstream petroleum policy
in place
- Road map for revising the
regulatory framework for
downstream petroleum in place
- Supervision of the HSE
consultant continues
- 20 standards developed
- 5 stakeholders consultative
meetings on Downstream
Policy held
- 5 regional workshops for
sensitization on the developed
standards held
- HSE training manual in place
- HSE protective gears for PSD
staff procured
770403
GoU Development
External Financing
Total
1,120,000
0
1,120,000
261,224
0
261,224
720,000
0
720,000
- JST stocked with products and
operational
-Independent centifier procured
and report in place
Feasibility study for
Nakasongola fuel depot in place
- Private investor for
Nakasongola in place
- JST private operator
supervised
- JST operational and stocked
with petroleum products
- TOR for feasibility study for
Nakasongola in place
- JST supervision reports in
place
- consultant for a feasibility
study for nakasongola procured
-Independent centifier procured
Acquisition of Other
Capital Assets
- Studies and designs for
Nakasongola Strategic Reserves
completed
- Nakasongola Strategic
Reserves development
commenced
- Feasibility study of Kampala
common user terminal
commenced
790403
Vote Overview
104
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Petroleum Supply, Infrastructure and Regulation03 04
Project 1258 Downstream Petroleum Infrastructure
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
• and work is in progress
GoU Development
External Financing
Total
1,280,000
0
1,280,000
420,512
0
420,512
1,680,000
0
1,680,000
GoU Development
External Financing
GRAND TOTAL
5,000,000
0
5,000,000
1,535,449
0
1,535,449
12,500,000
0
12,500,000
Annual Workplan for 2014/15 - Outputs, Activities, Inputs and their Cost
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
- Project documents drafting finalized for Kenya-Uganda.
- Drafting of Project Agreements for Kenya-Uganda finalized.
- EIA for Kenya-Uganda project finalized.
- Resettlement Action Plan (RAP) updated (Malaba-Kampala-Uganda)
- RAP implementation for Malaba-Kampala commenced
- EPC tendering documments finalised
- Feasibility study for Uganda-Rwanda pipeline project completed
- Pipe line routing for Uganda-Rwanda undertaken
- RAP for Uganda-Rwanda development commenced
- 24 JCC meetings held
- Procurement of RAP consultant to update the previous RAP
- Supervison of RAP development
- Sensitization of Project affected persons
- EIA process supervused
- 12 tripartite meetings attended
- supervison of pipeline routing of Kampala - Kigali refined product piple
segment
Acquisition of Land by Government710403
GoU Development
External Financing
Total
9,400,000
0
9,400,000
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Procurement of an EIA consultant (number) 1.0 300,000
faciltation for jcc meetings (reports) 1.0 500,000
RAP CONSULTANT (reports) 1.0 800,000
RAP for Eldoret-Kampala product pipeline
segment (reports)
780.0 7,800,000
-Development of NPIS completed
- 5 staff attain specialized training in operating and management of NPIS
- Necessary hardware procured
- Five year subscription to PLATTS done
Purchase of Office and ICT Equipment, including Software760403
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
PLATTS subscription (reports) 1.0 400,000
Procurement of equipment to support NPIS (reports) 1.0 300,000
Vote Overview
105
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Petroleum Supply, Infrastructure and Regulation03 04
Project 1258 Downstream Petroleum Infrastructure
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
- Supervision of the development of NPIS
- Staff trained in the usage of NPIS
- Subscription Of PLATTS for International prices
- Procurement of specialized hardware to support the NPIS
GoU Development
External Financing
Total
700,000
0
700,000
- Downstream petroleum policy in place
- Road map for revising the regulatory framework for downstream
petroleum in place
- Supervision of the HSE consultant continues
- 20 standards developed
- 5 stakeholders consultative meetings on Downstream Policy held
- 5 regional workshops for sensitization on the developed standards held
- HSE training manual in place
- HSE protective gears for PSD staff procured
- Procurement of laboratory equipment at JST
- Procurement of contractor to fence off JST
- Acquiring baseline standards (working drafts)
- Develop specification for the protective gear to the prodcured
- Development of HSE training manuals
- Procurement of protective gear.
Purchase of Specialised Machinery & Equipment770403
GoU Development
External Financing
Total
720,000
0
720,000
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Procurement of HSE protective gears for PSD staff
(numbers)
1.0 50,000
Downstream petroleum policy consultant (reports) 1.0 100,000
HSE traing manuals (reports) 1.0 100,000
Monitoring and supervisio of standards
development (reports)
1.0 250,000
Procurement of standards (reports) 1.0 50,000
Training workshop facilitation of petroleum oper
(reports)
170.0 170,000
- Studies and designs for Nakasongola Strategic Reserves
completed
- Nakasongola Strategic Reserves development commenced
- Feasibility study of Kampala common user terminal commenced
- Supervision of feasibility study for Nakasongola storage tanks.
-Package Nakasongola fuel depot for private investor participation
- survey and mapping off of Nakasongola fuel depot
- Tendering of Nakasongola fuel depot for PPP
-15 staff members attend short term course
-4 staff attend master’s program
Acquisition of Other Capital Assets790403
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Laboratory setting up at JST (NUMBER) 1.0 300,000
Tuition and upkeep for msc.studies (report) 5.0 300,000
Fencing of Nakasongola and JST (REPORTS) 1.0 400,000
Supervision of works (reports) 1.0 80,000
supervision of works and consultancies (reports) 1.0 200,000
survey for JST and Nakasongola depot (reports) 200.0 200,000
Tuition for short course and upkeep (reports) 5.0 200,000
Vote Overview
106
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Petroleum Supply, Infrastructure and Regulation03 04
Project 1258 Downstream Petroleum Infrastructure
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
GoU Development
External Financing
Total
1,680,000
0
1,680,000
GoU Development
External Financing
GRAND TOTAL
12,500,000
0
12,500,000
Vote Overview
107
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Mineral Exploration, Development & Production03 05
Services:
Responsible Officer:
Vote Function Profile
The vote function is responsible for the functions under the mineral sector. This
involves mineral Exploration and Investment promotion to achieve this objective
the sub-sector undertakes collecting, collating, processing, analysing, archiving
and disseminating geodata, monitor and assist small scale miners and also enforce
regulations in the sub-sector. The vote function also undertakes airborne
geophysical surveys to acquire airborne magnetic, radiometric and some
electromagnetic covering the entire country.
Commissioner, GSMD
Vote Function Projects and Programmes:Project or Programme Name Responsible Officer
Recurrent Programmes
05 Geological Survey and Mines Department Commissioner, GSMD
Development Projects
1199 Uganda Geothermal Resources Development Commissioner, Geological Survey and Mines Dept. (C/GSMD)
1200 Airborne Geophysical Survey and Geological Mapping of Kar Commissioner Geological Survey and Mines Depart. (C/GSMD)
Programme 05 Geological Survey and Mines Department
Commissioner, GSMD
- To stimulate mining sector development by promoting private sector participation; To ensure
that mineral wealth supports national economic and social development; To regularise and
improve artisanal and small scale (ASM) mining; To minimise and mitigate the adverse social
and environmental impacts of mineral exploitation; To remove restrictive practices on women
participation in the mineral sector and protect children against mining hazards; To develop
and strengthen local capacity for mineral development; To add value to mineral ores and
increase mineral trade; To monitor geo-tectonic disturbances and radioactive emissions in the
mineral sector.
To systematically collect, interpret, preserve and disseminate geological information and
maintain national geoscience data base; To maintain human resource expertise to use the
geoscience data to advise government, public and private sector; To carryout geological
investigations and attract investments and development of mineral resources; To carry out
engineering geological investigations and monitor geotectonic disturbances ( earthquakes,
landslides and advise the public on remedies; To provide effective and reliable laboratory
services for mineral analysis; To administer the Mining legislation and regulation based on
international best practices for sustainable development. The vote function is responsible for
the functions under the mineral sector. This involves mineral Exploration and Investment
promotion to achieve this objective the sub-sector undertakes collecting, collating, processing,
analysing, archiving and disseminating geodata, monitor and assist small scale miners and
also enforce regulations in the sub-sector. The vote function also undertakes airborne
geophysical surveys to acquire airborne magnetic, radiometric and some electromagnetic
covering the entire country. Thre are specific programmes in line with NDP 2010/11-14/15
that need funding:Airbone Geophysical Surveys of Karamoja (46bn), Geothermal Resources
Development (5.1bn), Uranium Exploration (14.12bn), Rare Earth Elements/minerals
13.18bn), Laboratories Infrastructure Enhancement (11.3bn, Mining Law Reform (1.9),
Mineral Data Backup Infrastructure (3.1bn), National Seismological Network (13.4) and
Geoparks and Geosites projects (0.62 bn).
Responsible Officer:
Objectives:
Outputs:
Programme Profile
Vote Overview
108
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Mineral Exploration, Development & Production03 05
Programme 05 Geological Survey and Mines Department
Workplan Outputs for 2013/14 and 2014/15
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
Regulation of exploration and
mining operations carried out.
Participted in evaluation of
proposals and negotiations of
contract award for the
privatization of Kilembe Mines
Limited under Public Private
Partnership (PPP). M/S Tibet
Hima Auto Limited (THAL) of
the Peoples’ Republic of China
and Government of Uganda
signed a concession agreement
on 6th September, 2013 for 25
years to develop the copper
resources at Kilembe Mines.
An Exploration License for the
Sukulu phosphates was granted
to M/S Guangzhou Dong Song
Energy Group Company
Limited on 1st August, 2013 to
develop the phosphate and Rare
Earth Potential at Sukulu. The
company has already
undertaken a feasibility study
for production of 300,000 t/year
of superphospahate, 200,000
t/year of sulphuric acid and
generation of power of 5 MW
and is also currently handling
modalities for compensation of
lawful occupiers of the land in
Osukuru in Tororo district in
preparation for applying for a
Mining Lease.
Four (4) mining leases, four (4)
location licences, and two (6)
exploration licences were
granted over Muko iron ore
deposit. Interpretation of
airborne geophysical surveys
also revealed more discoveries
of iron ore deposits at
Karukara, Kazogo, Nyamiyaga,
and Mayebe in Buchimbiri Sub-
County. Proposal to map out
and re- evaluate the reserves of
iron ore countrywide is in place
and awaits funds for
implementation.
Carried out Mineral sector
promotion and monitoring by
routine review and assessment
of exploration work programs,
Quarterly reports from
exploration and Mining
operations in Mining districts
of Karamoja region, Kabale,
Kisoro, Busia, Mubende,
Kasese, Bushenyi and Buhweju
to ensure that the results of
exploration are fully and clearly
recorded for the benefit of
future explorers and also
making sure that licensees
adhere to industry standards.
Total of two (2) Environmental
Impact Assessment (EIA’s)
reports were reviewed for grant
of Mining Leases. These
projects included iron ore
mining project in Kanungu and
Marble Mining project in
Moroto.
Policy Formulation
Regulation
Review of the mineral policy,
2001, the Mining Act, 2003 and
the Mining Regulations, 2004.
Continue review of legal and
regulatory frame work of the
mineral sector
Draft mining legislation
amendment bill by First
Parliamentary Counsel (FPC)
for Cabinet consideration to
table in parliament by end of FY
2014/15
010503
Vote Overview
109
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Mineral Exploration, Development & Production03 05
Programme 05 Geological Survey and Mines Department
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
Wage Recurrent
Non Wage Recurrent
Total
676,694
60,000
736,694
503,847
36,133
539,980
1,222,905
60,000
1,282,905
Capacity building, Research and
Development conducted.
Functional laboratory for
chemical analysis, tests of rocks
and minerals.
Acquiring, processing of
geoinformation/data and
updating of geoscience
databases.
•One hundred five (105)
publications and Twenty five
(25) reports were registered and
their metadata captured in
Libero and UDIS respectively.
The details of the reports
received are in the monthly
reports.
•Continued the maintenance of
Modern Documentation Center
information systems and digital
Data access via the Intranet at
http://www.minerals.go.ug and
internet at http://www.uganda-
mining.go.ug/webudis.
•Continued with Quality control
of Metadata in UDIS and
Libero.
•Updated the Economic Mineral
database with mineral
occurrences.
•Filed administrative records on
geodata/information user needs.
Geoinformation dissemination
and Mineral Sector Promotion.
•The Documentation Section
attended to 19 DGSM staff
members, 20 visitors and
relevant geoinformation on
Geothermal Exploration,
Research on minerals in Uganda
and geoinformation on geology
of Uganda, Mineral potential,
dimension stone of Pallisa,
Mineral potential and rare earth
elements was availed to them.
•The Documentation Section
maintained the DGSM website
on (www.uganda-mining.go.ug)
and 9661 users visited the
Website.
•Sold publications worth
Uganda shillings One hundred
sixteen thousand (116,000).
•Provided on complementary
basis the following publications
to different stakeholders for
further promotion of the sector:
24 copies of the Mining Act, 24
copies of the Mining
Regulations and 2 copies of the
Mineral Policy.
Cartography and GIS Activities
The cartography and GIS
section is responsible for
building and maintenance of
geoscience databases related to
geology, minerals and mineral
concession to assist investors in
their exploration and mining
activities. The following
activities were undertaken:
Institutional capacity for
the mineral sector
Human resource trained
Offices, laboratory equipped
Geo-scientific research
undertaken
Continue acquiring, processing
of geo-information/data,
updating of geoscience
databases and upgrade
Iinformation Technology (IT)
infrastructure.
Management of geo-data portal
and promotion of the mineral
sector through dissemination of
geo-information data.
Software maintenance and
upgrades, licenses for Data
servers, MCRS, LIBERO,
UDIS, ERMS &
020503
Vote Overview
110
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Mineral Exploration, Development & Production03 05
Programme 05 Geological Survey and Mines Department
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
Update and maintenance of
geoscience databases and
MCRS administration.
•A total of Thirty Seven (37)
mineral right applications were
scanned, uploaded and
validated into the Mining
Cadastre and Registry system
(MCRS).
•A total of forty one (41) title
prints of which 3 were for
Mining Leases, (1) for
Retention License, (36) for
Exploration License and (1)
Location license were prepared.
•Twelve (12) Concession and
Mineral Occurrence maps to
guide the general public on the
licencing status and Mining
Investment opportunities in the
country were prepared.
•Geothermal manifestations and
Licencing status map was
prepared
Geoinformation dissemination
and promotion of the Mineral
Sector
•Geoinformation was availed to
at least seventy six (76) clients
with various technical needs
concerning geological maps,
minerals, mineral exploration
and mining activities as well as
staff of the Ministry.
Management of a geodata portal
•National and Regional (NW,
NE, SW and SE) Concession
and Mineral Occurrence maps
for the whole country to guide
the general public on the
licencing status and Mining
Investments opportunities in the
country were prepared
•GMIS portal was maintained at
http://www.uganda-
mining.go.ug:81/UgandaGMIS/
•The portal currently links data
from geology, geophysics,
Mining Cadastre and
Documentation center: links to
other data for Geothermal,
Seismology and data obtained
from karamoja project are to be
added to the portal for further
promotions of these activities.
Laboratory Services
•Sample preparation for assay
of nine (9) rock samples from
sheet 25/2 (Kailong) being
mapped under the Airborne
Geophysical Survey and
Geological Mapping of
Karamoja Programme.
•Project (UGA/2/002): a
Vote Overview
111
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Mineral Exploration, Development & Production03 05
Programme 05 Geological Survey and Mines Department
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
Corporation Project between
the International Atomic Energy
Agency (IAEA) and the
Government of Uganda (GoU)
has been approved by the IAEA
and is to run from 2014 to
2017. As part of the preparation
for its execution by the
Department of Geological
survey and Mines (DGSM);
training needs, personnel, and
equipment requirements to
strengthen the national capacity
for uranium exploration and
evaluation have been identified.
•Undertook a review of the
project feasibility study report
by M/s Guangzhou Dong Song
Energy Group Company
Limited for the development of
the Osukulu phosphate deposit.
The following issues were
raised that need to be addressed
if the project is to meet all
statutory requirements for
sustainable exploitation;
consideration for
comprehensive extraction of
useful elements (iron, niobium,
scandium and rare earths) in the
deposit, optimal recovery,
management of hazardous
chemicals, inclusion of all
statutory payments and other
costs in the cash flow, and
emission of heavy metals and
mitigation measures.
•Carried out inventory of the
geothermal project equipment
•Carried out sampling and
analysis of consignments for
mineral dealers as part of the
requirements for application for
export permits
•Conducted analysis of six (6)
Wolfram samples for Tungsten
(WO3), six (6) coltan samples
for Columbite and Tantalite,
three (3) iron ore samples for
iron (Fe), eleven (11) samples
for high purity gold (Au), nine
(9) geochemical samples for
gold (Au), four (4) rock sample
for quartz, one (10 kaolin
sample for Fe, Ca, Mg, Al and
SiO2, two (2) marble samples
for Iron (Fe), Calicum (Ca),
Magnesium (Mg), Aluminium
(Al) and Silcon dioxide (SiO2)
one (1) salt sample for Sodium
Chloride ( NaCl) and
potassium Carbonate (K,CO3)
and SiO2, two (2) Cassiterite
samples for tin (Sn), one (1)
sample for Phosphates
pentoxide (P2O5,) two (2)
copper ore samples for Copper
(Cu). The details are presented
in laboratory report of GSMD.
Services to stakeholders and
increased transparency and
governance in the mineral rights
Vote Overview
112
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Mineral Exploration, Development & Production03 05
Programme 05 Geological Survey and Mines Department
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
management.
Geoinformation management
and dissemination continued
through both on the counter and
online systems at www.uganda-
mining.go.ug; www.uganda-
mining.go.ug:81/ugandaGMIS
and
www.flexicadastre.com/uganda
to facilitate access and
transparency of
geoinformation/data
management.
Laboratory Services: analysed
rocks, minerals, ores, water as
well as physical tests for rocks
for both government and private
sector. The details on outputs
undertaken are as follows:
i.Conducted industrial training
to atleast ten (10) students on
from Kyambogo, Makerere and
Nkumba Universities;
ii.Installation of five (5) the
fume hoods in the Analytical
Laboratories;
iii.Calibration of the X-Ray
equipment and Atomic
Absorption (AAS) which were
installed at the DGSM
laboratories in 2012;
iv.Procurement of a water
treatment equipment, slurry
pump, pulp density balance,
viscometer, analytical balances,
drying oven and backup system
for the equipment’s, additional
lamps for AAS, standard
reference materials for the X-
Ray equipment, Installation of
shelves for chemicals and
furniture for laboratory use; and
v. Installation of dust extractor,
jaw and roll crusher in the
mineral dressing laboratory.
Industrial training in GIS:the
department offered industrial
training on Principles and
Applications of Geographic
Information System (GIS), and
Cartography.to a total of a total
of twelve (12) students, of
which three (3) were from
Geology Department-Makerere
University; two (2) from
Kyambogo University and
Seven (7) from Institute of
Surveys and Land Management.
Human resource development
Mr. Andrew Katumwehe,
Senior Geophysicist continues
to pursue a four year Doctorate
of Philosophy (PhD) in
Exploration Geophysics at
Oklahoma State University,
United States of America.
Vote Overview
113
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Mineral Exploration, Development & Production03 05
Programme 05 Geological Survey and Mines Department
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
Mr. Joseph Nyago, Geophysical
Technician completed his one
year MSc degree training
course in Seismology,
Earthquake Engineering and
Disaster Management Policy
administered by IISEE Institute,
Tsukuba and GRIPS Institute,
Tokyo Japan.
Ms. Grace Lajwe (Senior
Chemist) completed a six
months geothermal training
programme at the United
Nations University in Rejkjavik,
Iceland. The training started on
the 22th April and ends on 18th
October, 2013.
Ms.Dorothy Namuli (Library
Attendant), completed a 3 years
Bachelor’s Degree in Library
and Information Science at
Makerere University.
Conferences and workshops
Ms. A. Alaba (Ag.
AC/Geodata) participated in
workshop on geoinformation in
Africa (GIRAF-2013) in Accra-
Ghana from 23rd -27th
September, 2013. She presented
a paper on the Mining Cadastre
and Registry System of Uganda
and was nominated as the
contact person for
Geoinformation in Uganda.
Mr. Edwards Katto, Ag.
Commissioner, GSMD attended
two conferences as follows: 1)
Crans Montana Forum in
Brussels, Belgium from 13th to
20th November, 2013; and 2)
Mines and Money 2013
Conference in London, UK
from 02nd to 04th December,
2013.
Over 30 members of staff
participated in a workshop on
Kibiro geothermal prospects at
the GSMD board room on 15th
August, 2013.
Mr. H. Ngada (Ag. Principal
Staff Cartographer) Participated
in a Geothermal Resources
Exploration training from 25th -
27th September 2013, in the
geothermal fields of
Bundibugyo, Ntoroko, Kabarole
and Kasese Districts.
Mr. H. Ngada (Ag. Principal
Staff Cartographer), S. Pule
(Staff Cartographer) and Sarah
Wegosasa (Cartographer)
participated a one (1) day in-
house Geothermal workshops at
Geological Survey and Mines
Depatment Entebbe, on 15th
August, 2013.
Vote Overview
114
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Mineral Exploration, Development & Production03 05
Programme 05 Geological Survey and Mines Department
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
Ms. Nassaka Sylvia (Senior
Documentation Officer)
participated visited the British
geological survey from 27th
August to 22nd September,
2013 on a geodata training
program.
Mr. Muheirwe Morris Tabaaro
(Mines Inspector) was attached
to Rakai Resources Limited
from 16th September, 2013 to
27th September, 2013 for two
weeks to undertake a stream
sediment survey in their
concessions in Abim district,
Karamoja sub region.
Fencing of the two new
seismological sites (vaults) at
Mubende (Butologo) and
Wakiso (Nakauka) continued
and is nearly completed.
Wage Recurrent
Non Wage Recurrent
Total
0
79,000
79,000
0
46,138
46,138
0
79,000
79,000
Geological, geochemical and
geophysical mapping carried
out.
Mineral potential established
and promoted.
Geological mapping and
Mineral resource assessment of
sheets 25/1, 25/2 and 25/4 in
Abim District.
In the month of January 2014
field geological mapping and
mineral resource assessment of
sheets 25/1, 25/2 and 25/4 in
Abim district were carried out
by technical officers. The map
sheets are underlain by mainly
granite gneisses of different
types, banded gneisses and
migmatites. Other lithological
units are chanockites, granulites
and garnetiferous gneiss that are
crosscut by concordant and
discordant quartz veins and
later overlain by superficial
deposits of laterite and
Alluvium.
Existence of late phase in the
gneiss and granulite might
indicate potential for epigenetic
vein and pegmatite type of
mineralisation such as gold,
wolfram, columbite-tantalite
and tin associated. Kaolin,
tourmaline and epidote signify
hydrothermal alteration that also
indicate potential for epigenetic
vein and pegmatite type of
mineralisation such gold,
wolfram, columbite-tantalite
and tin.
The geology of area is underlain
by felsic rocks (brittle) and
mafic rocks (ductile) was
affected by shearing which is
manifested by sinistral shearing.
Similar shearing was also
mapped in Kitgum and Lira
Districts implying that was the
result of Achwa shearing. This
implies that the geology in
Mineral Exploration,
development, production
and value-addition
promoted
Establish the Mineral Wealth of
Uganda by 80% and there is
need to complete the remaining
20%.
Mineral varieties to be
quantified in monetary terms
and mines.
Complete quantification of
mineral reserves and geological
mapping of base metals, special
metals precious metals
carbonetites, carbonates
pegmatite minerals and
industrial minerals.
Geological, Geochemical and
geophysical investigations
carried.
Mineral exploration and value
addition undertaken
030503
Vote Overview
115
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Mineral Exploration, Development & Production03 05
Programme 05 Geological Survey and Mines Department
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
Abim District (25/1, 25/2, 25/3
and 25/4) might have been also
affected by Aswa
shearing.
The same geology of felsic
rocks (brittle) and mafic rocks
(ductile) were later affected by
shearing which is manifested by
formation of S and Z fold. The
Z type of folds were mapped on
the western side while S on the
eastern. When the S and Z folds
were combined they formed an
anticline. The limbs and apex of
the anticline have quartz veins.
Gold mineralisation is thought
to be associated with these
quartz veins.
Completion of the remaining
part of sheet 25/3 was
undertaken. A total of 27 stream
sediment and alluvial samples
and 5 rock samples were
collected from sheet 25/3, while
17 rock samples and 45 sites
were sampled in sheet 25/4 out
of the planned 108 sites to be
sampled. Access to the sample
sheet 25/4 was very poor due to
insecurity which made people to
abandon the area.
Artisanal alluvial gold mining is
reported at Kokano(0288188,
585492), Gul Aleri( 0288391,
0585086), Pupu Village,
Kamoya Parish Nyakwae Sub
county (0594705, 0282095) and
Olea Angolebual Sub county
0285730 0590247(Mining
area), A Draft Geological
maps and geochemical reports
for topographical map sheets
251, 25/2 and 25/4 were
prepared. Final report awaits
the completion of the study of
the thin sections of samples
collected from the area during
the geological mapping.
Petrology
Materials received from
investors including, rocks
minerals, minerals and were
examined and identifies.
Seventeen (17) samples and
specimens were received which
were mainly gemstones. Among
those identified were calcite,
quartz, amethyst, chalcedony,
epidote, hematite, ilmenite, and
they were identifies a;
rhodonite, hematite, tourmaline,
ruby, epidote, hematite,
magnetite and chalcedony.
Mineral sector promotion and
monitoring
The division provided routine in-
office client consultations and
expert advice. The division also
Vote Overview
116
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Mineral Exploration, Development & Production03 05
Programme 05 Geological Survey and Mines Department
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
undertook routine review and
assessment of exploration work
programs. Quarterly reports
were assessed to ensure that the
results of exploration are fully
and clearly recorded for the
benefit of future explorers and
that licensees adhere to industry
standards.
Fifty eight (58) Temporary
Number (TN) applications were
reviewed and assessed and fifty
one (51) Exploration Licenses
were reviewed for consideration
for renewal.
Review of exploration programs
of EL’s 1049, 1052, 1048,
1050, 1053 in Kigum district
under M/s Sipa Exploration (U)
Ltd has confirmed Ni, Cu, Cr,
Pb, Zn, Ag and Cd anomalous
zones in Northern Uganda along
Aswa shear zone.
While exploration programs of
Krishna Mining Limited in EL’s
0723, 0726, 0727 and 0728 has
indicated precious and base
metal anomalies which have
been confirmed by
IP/Resistivity survey.
Mineralisation is associated
with quartz veins and
disseminated sulphides.
Geophysical survey of Karuma
in Kiryandongo district
The geophysical team from the
DGSM carried out ground
magnetic, Moving Loop
Transient Electromagnetic
(TEM) survey and gravity field
measurements for Pearl Mining
(U) Ltd on concessions, EL’s
304 and 305 in Karuma,
Kiryandongo district from 6th –
27th January, 2014 and 2nd –
26th February, 2014
respectively. Preliminary field
data interpretations show
positive results of massive
magnetic conductors which
could probably host chromite,
Nickel, other base metals and
precious mineral (gold and
platinum).
Geophysical reconnaissance
survey of Kadam-Moroto basin
Mr. Eriya Kahwa (Geologist)
together with a field team of
Petroleum Exploration and
Production Department took
part in a reconnaissance trip to
the Kadama – Moroto basin,
24th Feb – 2nd March, 2014.
Preliminary findings indicate the
basin stretches from Kadama to
Nakapiripirit. A survey is being
planned to ascertain the geology
and thickness of the sediments
in the basin to establish the
hydro-carbon potential.
Vote Overview
117
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Mineral Exploration, Development & Production03 05
Programme 05 Geological Survey and Mines Department
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
Monitoring earthquake and
other geo-tectonic activities.
Routine maintenance and
servicing of upcountry seismic
stations of Kyahi-Mbarara
(MBAR) and Kilembe (KILD)
was carried on 10th – 11th
January 2014. During the same
visit, digital seismic data
recorded at these stations was
downloaded.
Between 5th and 6th February
2014, Hoima (HOID) seismic
station was visited for the
purpose of routine digital data
collection and servicing of the
seismic recording instruments.
During the same visit, the
AfricaArray GPS station
installed at the same site and
operated in conjunction with
Department of Geosciences,
Pennsylvanian State University,
USA was serviced and data
recorded was downloaded.
The unit continued with
requesting of waveform data
(seed files) for MBAR station
from IRIS online database, and
extraction of seismic event time
segments, database auto-
registration and phase picking
using SEISAN earthquake
analysis software.
Continued the networking and
configuration process of future
remote access of upcountry
seismic stations for the purpose
of data downloads and
equipment troubleshooting. So
far the results of this activity are
promising hoping to solve most
of problems associated with
data collection from remote
stations in near real time.
Discussions between DGSM
staff and oil exploration
companies that plan to install a
Passive Seismic Network (PSN)
in the Albertine Graben were
held on 18th March 2013. The
main issues discussed were
about the type of equipment to
be purchased by the oil
companies and other modalities
to be followed during the
implementation of the PSN.
Initiated the procurement of
specialized equipment for active
fault mapping
Follow-up of airborne surveys
with ground geological and
geochemical mapping resulted
into new discoveries of iron ore
deposits in Kanungu, Buhara
(Kabale district) and Mayuge
areas. In general a total reserve
of over 100 million tones of iron
Vote Overview
118
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Mineral Exploration, Development & Production03 05
Programme 05 Geological Survey and Mines Department
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
ore has been evaluated in Muko
and the sorrunding areas.
Undertook Geological mapping
of sheet 25/3 (Waiwer) , Abim
district;
Undertook Geological mapping
of sheet 25/3 (Waiwer) has
established that the area is
underlain by charnockite,
porphyritic granulite and fine-
medium grained granulite
lithology that have been cross
cut by late phase quartz veins
and pegmatite dykes. Thirty six
(36) rock samples were
collected for analysis and
Twelve (12) are for
miscroscopic study.
The geological report and a map
at 1:50,000 scale are under
preparation.
Geochemical mapping of sheet
25/3 (Waiwer), Abim district;
Geochemical surveys of this
area revealed hydrothermal
alteration veims manifested by
tourmalization and epidotization
in the area signify that this area
might be potential for epigenetic
vein and pegmatite type of
mineralisation such gold,
wolfram, columbite-tantalite
and tin. This thought has
already been proved by one
mineral rights holder in sheets
25/2 and 25/3 where results
indicated anomalous high values
of Niobium- Tantalite (Nb-Ta).
Therefore sixty nine (69)
geochemical samples have been
collected to be analysed for
multi-element but paying more
attention to tin, gold, tantalite
and Wolfram. The geochemical
report and a map at 1:50,000
scale are under preparation.
Undertook routine review and
assessment of exploration work
programs. Quarterly reports
were assessed to ensure that the
results of exploration are fully
and clearly recorded for the
benefit of future explorers and
that licensees adhere to industry
standards.
Workplans for One hundred and
two (102) applications for
mineral rights were reviewed as
well as thirty nine (39)
exploration Licenses were also
reviewed for consideration for
renewal.
Total 193,000 137,740 193,000
Vote Overview
119
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Mineral Exploration, Development & Production03 05
Programme 05 Geological Survey and Mines Department
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
Wage Recurrent
Non Wage Recurrent
Total
0
193,000
0
137,740
0
193,000
Poverty reduced and Livelihood
in mining communities
improved.
Miners trained on health,
Safety and social issues in
Mining improved.
Millennium development goals
attained.
A team comprising of Eng.
Joseph Okedi (Acting Principal
Inspector of Mines), Morris
Muheirwe Tabaaro (Inspector
of Mines) and James Natukunda
(Senior Geologist) carried out
an inspection in Kibarya
Village, Burere Sub-County in
Buhweju District from 12th
14th March, 2014.
A team comprising of David
Sebagala (Acting Senior
Inspector of Mines), John
Kennedy Okewling (Mining
Engineer), Morris Muheirwe
Tabaaro (Inspector of Mines),
Nathan Mushetsya (Senior
Mines Warden), Mathias
Mugere (Assistant Inspector of
Mines) and Julius Peter Beja
(Intern) carried out general
inspection at Tiira in Busia
District, Namekhera in
Manafwa District, Morilem in
Abim District, Kotido District
and Lorep in Kaabong District
from 20th – 24th January, 2014.
Created health and safety and
social awareness of Miners in
Karamoja region, Ntungamo,
and Kiryandongo Districts for
Poverty reduction and
Livelihood improvement and
diversification in mining
communities.
Manuals adopted from the
Small Scale Mining Hand Book
were prepared and disseminated
to Small Scale Mining groups in
Abim, Moroto and Nakapiripirit
Districts to guide small scale
miners in their districts on
health and safety issues.
Sensitization of communities in
Karamoja region about the
planned geological mapping and
airborne geophysical surveys
continued.
Health and safety awareness
was created in small scale
mining areas in Waiwer (sheet
25/3) in Abim district.
A consultation workshop of
Natural Resources Officers in
the districts of Karamoja region,
i.e., Napak, Nakapiripirit,
Amudat, Abim, Kotido,
Kaabong and Moroto was held
in Moroto Town and was
attended by sixteen (16)
persons.
The workshop participants were
issued with Training Manuals
plus copies of Small Scale
Health safety and Social
Awareness for Miners
Health and safety awareness in
mining operations created
Sensitisation of miners
undertaken
Environment baseline studies
undertaken in and around
orphan mines, mineral bearing
protected areas
040503
Vote Overview
120
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Mineral Exploration, Development & Production03 05
Programme 05 Geological Survey and Mines Department
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
Mining Hand Books to guide
them on health and safety issues
related to Artisanal and Small
Scale Mining.
Sensitized the mining
communities on the
environmental best practices,
health and safety, climate
change in Busia, Buhweju,
Kabale, Kisoro, Kasese &
Mubende.
Undertake train of trainers in
the Artisanal and Small Scale
Miners associations and create
awareness on the requirements
for their formalization.
Wage Recurrent
Non Wage Recurrent
Total
0
54,000
54,000
0
33,210
33,210
0
54,000
54,000
Licensing and monitoring of
mining activities carried out.
More Non Tax Revenues
(NTR) assessed and collected.
Total Mineral rights are 515
Licenses
Total vaule of mineral exports is
UGX 26.0 billion.
Total Value of Non Tax
Revenue (NTR) in UGX 7.7
billion.
Licencing and inspection Inspections of mining
operations and licensing of
mineral rights undertaken in
Mining Districts and Mineral
Exploration areas in Uganda
050503
Wage Recurrent
Non Wage Recurrent
Total
0
57,000
57,000
0
28,535
28,535
0
57,000
57,000
Subscriptions to research
activities of Regional and
International orgainsations (
SEAMIC, CTBTO, IAEA, and
ARGeo) maintained.
Paid part contribution to South
East African Mineral Centre
(SEAMIC) and CTBTO
International Atomic Energy
Agency (IAEA) approved
Uranium Exploration and
Evaluation Project
(UGA/02/002) for four years.
One Staff Participated in
National Data Centre
Development Workshop of
CTBTO in Africa on the Use of
International Monitoring System
Data and International Data
Centre Products with Emphasis
on Radionuclide Observations
from 16 to 19 December 2013,
Ouagadougou, Burkina Faso.
Contribution to
international
organisation(SEAMIC)
Payment of contributions to
international organisations
effected
510503
Wage Recurrent
Non Wage Recurrent
Total
0
22,000
22,000
0
9,391
9,391
0
122,000
122,000
Wage Recurrent
Non Wage Recurrent
GRAND TOTAL
676,694
465,000
1,141,694
503,847
291,147
794,994
1,222,905
565,000
1,787,905
Vote Overview
121
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Mineral Exploration, Development & Production03 05
Programme 05 Geological Survey and Mines Department
Annual Workplan for 2014/15 - Outputs, Activities, Inputs and their Cost
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
Review of the mineral policy, 2001, the Mining Act, 2003 and the Mining
Regulations, 2004.
Continue review of legal and regulatory frame work of the mineral sector
Draft mining legislation amendment bill by First Parliamentary Counsel
(FPC) for Cabinet consideration to table in parliament by end of FY
2014/15
Review of the mineral policy, 2001, the Mining Act, 2003 and the Mining
Regulations, 2004.
Continue review of legal and regulatory frame work of the mineral sector
Draft mining legislation amendment bill by First Parliamentary Counsel
(FPC) for Cabinet consideration to table in parliament by end of FY
2014/15
Policy Formulation Regulation010503
Wage Recurrent
Non Wage Recurrent
Total
1,222,905
60,000
1,282,905
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Fuel (Litres) 1,250.0 5,000
Allowances & perdiem for policy workshops
(Number)
50.0 6,000
Allowances during policy retreat (Number) 41.7 5,000
Consultative Workhops& fieldwork (Number) 91,666.7 11,000
Deliverly of policy documents (Number) 100.0 1,000
Electricity utilities (Number) 50.0 5,000
Fuel & lubricants (Number) 10.0 5,000
Internet services and connectivity (Number) 5.0 1,000
Metered water utilised (Number) 2,500.0 5,000
Office consumables (Number) 4.0 2,000
Printing of policy documentation and dissemination
(Number)
133.3 2,000
Promotion of mineral policy and legislation
(Number)
100.0 1,000
Scientific Journals (Number) 12.0 3,000
Supply of ICT facilities and acessories (Number) 4.0 4,000
Supply of News papers and Journals (Number) 100.0 1,000
Telephone Utilities (Number) 10.0 1,000
Training of policy makers in mining legislation
(Number)
16.7 2,000
Permanent Staff (Person Years) 79.0 1,222,905
Human resource trained
Offices, laboratory equipped
Geo-scientific research undertaken
Continue acquiring, processing of geo-information/data, updating of
geoscience databases and upgrade Iinformation Technology (IT)
infrastructure.
Management of geo-data portal and promotion of the mineral sector
through dissemination of geo-information data.
Software maintenance and upgrades, licenses for Data servers, MCRS,
LIBERO, UDIS, ERMS &
Human resource trained
Offices, laboratory equipped
Geo-scientific research undertaken
Continue acquiring, processing of geo-information/data, updating of
geoscience databases and upgrade Iinformation Technology (IT)
infrastructure.
Management of geo-data portal and promotion of the mineral sector
through dissemination of geo-information data.
Institutional capacity for the mineral sector020503
Wage Recurrent
Non Wage Recurrent
Total
0
79,000
79,000
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Electricity utilities (Number) 4.0 1,000
Expression of interest news in press (Number) 10.0 3,000
Field Airtime (Number) 4.0 1,000
Fuel and lubricants (Number) 9.6 10,000
ICT & Solar backup inflastructure (Number) 10.0 5,000
ICT Consumables (Number) 10.0 2,000
Lunch allowance & field work (Number) 16.7 2,000
News paper Subscription (Number) 800.0 2,000
Office consumables & Small Office equipment
(Number)
20.0 4,000
Postage and carrier (Number) 4.0 1,000
Printing Stationery (Number) 4.0 2,000
Recrutment of staff meetings (Number) 250,000.0 1,000
Security Services (Number) 3.0 6,000
Subscription SEAMIC (Number) 2.0 5,000
Training in value addition technologies (Number) 4.0 10,000
Travel abroad (Number) 2.0 10,000
Travel inland (Number) 2.0 4,000
Water Utilities (Number) 5.0 1,000
Welfare and Offcial Entertainmen (Number) 6.0 3,000
Workshops and seminars (Number) 50.0 6,000
Mineral Exploration, development, production and value-addition promoted030503Output:
Vote Overview
122
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Mineral Exploration, Development & Production03 05
Programme 05 Geological Survey and Mines Department
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
Establish the Mineral Wealth of Uganda by 80% and there is need to
complete the remaining 20%.
Mineral varieties to be quantified in monetary terms and mines.
Complete quantification of mineral reserves and geological mapping of
base metals, special metals precious metals carbonetites, carbonates
pegmatite minerals and industrial minerals.
Geological, Geochemical and geophysical investigations carried.
Mineral exploration and value addition undertaken
Establish the Mineral Wealth of Uganda by 80% and there is need to
complete the remaining 20%.
Mineral varieties to be quantified in monetary terms and mines.
Complete quantification of mineral reserves and geological mapping of
base metals, special metals precious metals carbonetites, carbonates
pegmatite minerals and industrial minerals.
Geological, Geochemical and geophysical investigations carried.
Mineral exploration and value addition undertaken Wage Recurrent
Non Wage Recurrent
Total
0
193,000
193,000
Activities to Deliver Outputs:
Planned Outputs: Inputs Quantity Cost
Payment of water bills (Liter) 1,333.3 2,000
Fuel for OHS awareness campaigns (Liters) 2,500.0 10,000
Advertising and public relations (Number) 3.0 3,000
Allowance for mineral exploration (Number) 83.3 10,000
Books and scientific journals (Number) 6.7 2,000
Clearing and forwarding charges (Number) 4.0 10,000
ICT infrastructure upgrade, CCTV security system
(Number)
8.0 8,000
Inspections to ensure safety mining practices
(Number)
500.0 60,000
Mineral assesment and value addition technology
(Number)
158.3 19,000
Office consumables and printing (Number) 80.0 2,000
Participate in OHS conferences on mining (Number) 4.0 10,000
Subscriptions to OHS newsletters (Number) 66.7 2,000
Technical presentations & mineral conference
venue (Number)
4.0 10,000
Training in mineral exploration technologies
(Number)
3.0 15,000
Tyres, repair and servicing of vehicles (Number) 37.5 30,000
Health and safety awareness in mining operations created
Sensitisation of miners undertaken
Environment baseline studies undertaken in and around orphan mines,
mineral bearing protected areas
Health and safety awareness in mining operations created
Sensitisation of miners undertaken
Environment baseline studies undertaken in and around orphan mines,
mineral bearing protected areas
Health safety and Social Awareness for Miners040503
Wage Recurrent
Non Wage Recurrent
Total
0
54,000
54,000
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Fuel for OHS monitoring and inspections of miners
(Liter)
250.0 1,000
Payment of water bills (Liters) 666.7 1,000
Allowances & per diem for OHS inspections
(Number)
83.3 10,000
Allowances & per diemfor OHS mining inspection
(Number)
16.7 2,000
Allowances and airfares for OHS conferences
(Number)
4.0 10,000
Clearance of electricity bills (Number) 5,454.5 3,000
Clearance of telephone bills (Number) 4.0 1,000
Hire of venues and conference facilities on OHS
(Number)
5.0 5,000
Inland postage, delivery of publications to miners
(Number)
4.0 1,000
Internet and web service charges (Number) 4.0 1,000
Local publications on OHS on best mining practices
(Number)
2,000.0 5,000
Paper & printer toner for printing OHS publication
(Number)
4.0 1,000
Pay annual subscriptions of staff in OHS bodies
(Number)
50.0 1,000
Paymeny of security services (Number) 4.0 5,000
Supply of computer, accessories data storage
(Number)
4.0 3,000
Training of staff in OHS in mining (Number) 4.0 4,000
Inspections of mining operations and licensing of mineral rights
undertaken in Mining Districts and Mineral Exploration areas in Uganda
Inspections of mining operations and licensing of mineral rights
Licencing and inspection050503
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Due diligence on mining companies (Number) 6.0 6,000
Fuel for mine inspections (Number) 33.3 4,000
Inspections and license operations (Number) 16.7 2,000
Licenses review and inspections seminars (Number) 41.7 5,000
Vote Overview
123
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Mineral Exploration, Development & Production03 05
Programme 05 Geological Survey and Mines Department
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
undertaken in Mining Districts and Mineral Exploration areas in Uganda
Wage Recurrent
Non Wage Recurrent
Total
0
57,000
57,000
Mineral inspections (Number) 250.0 30,000
Vehicle repair and servicing (Number) 25.0 10,000
Payment of contributions to international organisations effected
Pay contributions and arrears to international organisations CTBTO,
SEAMIC, ARGEO & AU
Three (3) Technical Working group Retreats and training
Three (3) Ministerial Round table meetings, seminars conferences &
working groups
Contribution to international organisation(SEAMIC)510503
Wage Recurrent
Non Wage Recurrent
Total
0
122,000
122,000
Activities to Deliver Outputs:
Planned Outputs:
Output:
Grant or Transfer Cost
Contribution to CTBTO & SEAMIC 122,000
Wage Recurrent
Non Wage Recurrent
GRAND TOTAL
1,222,905
565,000
1,787,905
Vote Overview
124
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Mineral Exploration, Development & Production03 05
Project 1199 Uganda Geothermal Resources Development
Workplan Outputs for 2013/14 and 2014/15
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
•Regulation of geothermal
exploration and license
administrative reviews carried
out.
Geothermal policy and
legislation formulated.
Reviewed Geothermal Licensee
reports
Produced a white paper on
geothermal industry
development framework.
Prepared and produced a white
paper on issues to be covered in
geothermal law, regulation and
standard contracts.
Prepared and produced a
geothermal industry
development framework
guideline
A Memorandum of
Policy Formulation
Regulation
Develop Consistent, effective
and efficient regulatory
framework for geothermal
energy.
Identify opportunities to
advance geothermal energy
projects.
010503
Commissioner, Geological Survey and Mines Dept. (C/GSMD)
- To carryout additional geophysical studies at Katwe, Buranga and Kibiro using Transient
Electromagnetics (TEM), Magneto-tellurics (MT) and Gravity methods to probe deeper and
identify the heat source and targets for deep drilling.
To carryout detailed geological, geochemical and geophysical (MT, TEM and Gravity)
surveys at Panyimur to delineate geothermal anomalous areas identify the source of heat and
targets for deep drilling.
- To carryout additional hydrological and hydrogeological surveys to study in detail the
structures that control the fluid flow mechanisms in the four areas.
- To update the current surface models based on geology, geochemistry, and geophysics; with
additional geophysical surveys (TEM and MT), and hydrology and hydrogeology results, to
come up with integrated models that will be a basis for locating deep exploration wells.
- To carryout sociological and environmental baseline studies and infrastructure assessment in
the four areas.
- To select the most promising area for the feasibility study.
- To carryout Environmental Impact Assessment for drilling in a selected prospect.
- To drill 3 deep geothermal exploration wells in one selected prospect with the aim to
discover a geothermal reservoir.
- To install the first geothermal power plant.
- To purchase equipment for geothermal exploration and well testing.
- To train Ugandans in exploration and resource testing, project design, operation and
financing.
- To put in place adequate Policy, Institutional and Regulatory frameworks for geothermal
energy development.
Expected output Geothermal surface and subsurface conceptual models of the four study
areas. Sociological and environmental baseline data. Environmental Impact Assessment
(EIA) for drilling. A geothermal reservoir with 3 boreholes drilled and teste steam to
generate electricity.
Responsible Officer:
Objectives:
Outputs:
7/1/2011 6/30/2020Start Date: Projected End Date:
Project Profile
Donor Funding for Project:
2016/172012/13
Budget
2013/14
Budget 2014/15 2015/16
MTEF Projections
Projected Donor Allocations (UShs)
European Union (EU) 0.000 0.000 4.000 0.0000.000406
0.000 0.000 4.000 0.0000.000Total Donor Funding for Project
Vote Overview
125
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Mineral Exploration, Development & Production03 05
Project 1199 Uganda Geothermal Resources Development
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
Understanding between the
Governments Uganda, Rwanda
and Kenya relating to technical
cooperation and working
together in the field of
geothermal resources
development was signed.
GoU Development
External Financing
Total
41,500
0
41,500
29,983
0
29,983
40,000
0
40,000
Geothermal Capacity building,
Research and Development
conducted.
Updated a regional and national
geothermal data base in order to
attract private investment
Retrieved historical and recent
geothermal documentation and
information into a digital format
for easy access and use
Two Project Team members
(James Olwa and Henry
Mulindwa) were trained in
geological mapping techniques
which involved identifying
active and inactive geothermal
features. The team visited the
following geothermal spots;
Kibuku, Mumbuga, Nyansimbe,
Kagoro, Rwimi, Kibenge,
Muhokya, Katwe and
Nyamunuka
Lugoko, Denis Mwesigye,
Henry Ngada, Henry Mulindwa,
James Olwa, Resty Naddumba
in Bundibugyo, Ntoroko and
Kasese.
Organized a workshop with
United Nations Environmental
Programme (UNEP)
West Jec Incl (Consultants of
JICA) Undertook a training
seminar of staff in sampling
geothermal waters, geological
mapping using satellite images
and geothermal prospectivity
mapping.
Vincent Kato (Project Manager)
trained in Project Planning and
Management at UMI.
Jacqueline Nakirrijja
(Geologist) undertook one
month training in geothermal
exploration course VIII
Naivsaha Kenya.
Grace Lajwe (Chemist)
completed a six month
specialised course in chemistry
of geothermal fluids in Iceland.
Institutional capacity for
the mineral sector
Establish a geothermal
Resources Department
Develop a Communication and
community awareness
programme.
Geothermal Technology:
Undertake R & D to support
geothermal industry
Technology Transfer:
International partnership for
geothermal technology (to
provide framework for
international cooperation in
geothermal technology, policy
and model development).
020503
GoU Development
External Financing
Total
60,000
0
60,000
39,698
0
39,698
60,000
0
60,000
Geothermal energy surveys
conducted.
Mineral potential in geothermal
prospects established
Six (6) GSMD Staff and three
(3) JICA experts explored
Sixteen (16) geothermal
potential prospects
Undertook Geological mapping
of Kibiro south-wards of Kibiro
Mineral Exploration,
development, production
and value-addition
promoted
Carry out Geothermal
exploration. Data acquisition
and management:
Acquire accurate and reliable
information on geothermal
resources in Uganda.
030503
Vote Overview
126
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Mineral Exploration, Development & Production03 05
Project 1199 Uganda Geothermal Resources Development
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
hot spring and produced a
geological map
Undertook Geochemical
Surveys in north and North
Eastern Uganda covering Nine
(9) Geothermal Potential
Prospects
Reviewed geological data
acquired by oil companies
covering Albertine Graben and
discovered a strong correlation
of accommodation zones in the
graben and geothermal activity
Undertook environmental
baseline survey of Panyimur
that will support the
development of Geothermal
Resources in Panyimur Prospect.
Reviewed oil wells data close
to geothermal prospects in
Albertine graben in order to
establish the temperature
gradients so as to guide
geothermal surface and sub-
surface exploration strategy
Reviewed seismic data close to
geothermal prospects in
Albertine graben in order to
infer structural geology and the
nature of deep seated faults that
control the flow of fluids.
Undertook ground truth field
trip to Kibiro with UNEP
Consultant.
Undertook geological mapping
in Ntoroko and Bundibugyo.
Undertook stocktaking of
existing information on
Uganda's geothermal potential.
Undertook processing,
analyzing and interpretation of
airborne magnetic data of other
geothermal sites.
Undertook ground geophysical
surveys (Gravity & Magnetics)
in Panyimur.
Produced promotional
brochures on geothermal and
environment.
Undertook a working session
with JICA Consultants on how
to undertake a preliminary
survey.
Undertook a preliminary survey
of sixteen (16) geothermal sites
in Uganda with JICA
Consultants
GoU Development
External Financing
Total
393,000
0
393,000
176,844
0
176,844
489,500
0
489,500
Poverty reduced and Livelihood
in geothermal resources
communities improved.
Millennium development goals
attained.
Developed and disseminated
health and safety information in
geothermal communities
(Katwe, Buranga, Panyimur and
Kibiro).
Procured health and Safety
gears for geothermal
exploration field teams
Undertook environmental
baseline survey in Buranga,
Health safety and Social
Awareness for Miners
Undertake three training and
awareness campaign in safety
issues during geothermal
exploration to safeguard the
health and safety of staff.
Procure Personal Protection
Equipment and Comprehensive
First Aid Kits
040503
Vote Overview
127
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Mineral Exploration, Development & Production03 05
Project 1199 Uganda Geothermal Resources Development
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
Panyimur and Katwe.
Initiated process of procuring
Personnel Protection
Equipment, first aid kits.
Distributed health and safety
literature to staff, produced
brochures
Undertook health outreach
initiatives in Kasese,
Bundibugyo
GoU Development
External Financing
Total
30,000
0
30,000
25,152
0
25,152
30,000
0
30,000
Monitoring and inspection of
geothermal activities of licensed
companies carried out.
Reviewed geothermal
exploration reports of nine (9)
geothermal licensees
M/s Katwe Geothermal Power
Project
M/s Pawakom International
Limited
M/s Cozumel Energy (U)
Limited.
M/s Clean Source Energy
Uganda Limited
M/s Moberge Finance Ltd
M/s Ascot Associates (U) Ltd
M/s Gids Consult Ltd
M/s Spencon Services Ltd
Undertook performance
appraisal of eight (8)
geothermal exploration
licensees.
Undertook field inspection to
Katwe, Buranga, Panyimur and
Kibiro
Licencing and inspection Undertake administrative
reviews for compliance and
geothermal inspections and
monitoring.
License new investors
050503
GoU Development
External Financing
Total
32,500
0
32,500
24,023
0
24,023
72,500
0
72,500
Acquire land for five (5)
seismic stations, Kigorobya,
Rukungiri, Kasese, Amuru and
Zombo
Plots boundaries of Geological
land at Hill Road and Guda
Geological Rest House Camp
marked and application for
tittles deeds are being
processed.
Initiated the procurement
process
Procured a land surveyor to
open boundaries of Geological
land at Hill Road and Guda
Geological Rest House Camp.
Acquisition of Land by
Government
Survey all the Land with
Geothermal resources and
gazette it for geothermal
development.
Survey all the land of seismic
stations and acqure title deeds.
710503
GoU Development
External Financing
Total
135,000
0
135,000
0
0
0
40,000
0
40,000
Geothermal institution, training
centre and offices established
Regional geothermal database
and network installed.
Fume hoods for the geothermal
laboratory installed.
Equipment maintained and other
laboratory consumables
purchased.
Setup and furnished a
geothermal unit office
Identified key positions of the
institutional model of
geothermal department to be
filled in phases
Created a regional and national
geothermal data base in order to
attract private investment.
Restructuring of the Geological
Survey accomplished.
Department of Geothermal
approved by Public Service.
Department of Mines approved
by public Service.
Government Buildings and
Administrative
Infrastructure
Renovation of the Buildings and
laboratories and improvement
of Security at the gates of
Geological Survey and Mines.
720503
Vote Overview
128
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Mineral Exploration, Development & Production03 05
Project 1199 Uganda Geothermal Resources Development
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
Department of Geological
Surveys approved by Public
Service.
GoU Development
External Financing
Total
30,000
0
30,000
12,030
0
12,030
30,000
0
30,000
Renovate/repair the access
roads for geothermal
exploration wells drilling
equipment.
Procurement of more
specialised equipment of
subsurface geothermal
exploration is on going
Evaluation of bids was
completed
Initiated process of procuring
One MT/TEM Equipment
Roads, Streets and
Highways
Repair of access road to the
Ministry of Energy and Mineral
Development in Entebbe
730503
GoU Development
External Financing
Total
90,000
0
90,000
20,443
0
20,443
90,000
0
90,000
Geothermal Data analysis and
modelling sofware procured.
Initiated process of geological
softwares
Evaluation of bids was
completed
Procurement of more
geophysical softwares
Purchase of Office and
ICT Equipment,
including Software
Procure computers and
Softwares and accessories.
760503
GoU Development
External Financing
Total
240,000
0
240,000
9,810
0
9,810
240,000
0
240,000
Deep subsurface geothermal
exploration equipment and
laboratory procured.
Initiated procurement of more
Magnetotellurics (MT) units,
Transient Electromagenetic
(TEM) equipment.
Evaluation of bids on the
procurement of specialised
equipment of subsurface
geothermal exploration was
completed.
Initiated process of procuring
Six (6) Magnetotellurics (MT)
units, one (1) gravity meter,
geological software, Niton X-
Ray Fluorescence (XRF)
Analyzer.
Evaluation of bids was
completed
Purchase of Specialised
Machinery & Equipment
Continue the procurement of
Deep subsurface geothermal
exploration equipment and
laboratory consumables
770503
GoU Development
External Financing
Total
2,180,000
0
2,180,000
115,703
0
115,703
2,180,000
0
2,180,000
Office funiture and
fumecupboards procured for
geothermal Unit
Installed the procured office
furniture for geothermal Unit
located at GSMD
Installed national and a regional
geothermal database.
Initiated procuring services of
clearing fume hoods and
accessories.
Office furniture procured
(tables, chairs, cabinets,
shelves, conference table)
Purchase of Office and
Residential Furniture and
Fittings
Office funiture and fume
cupboards procured for
geothermal Unit
780503
GoU Development
Total
25,000
25,000
14,580
14,580
25,000
25,000
Vote Overview
129
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Mineral Exploration, Development & Production03 05
Project 1199 Uganda Geothermal Resources Development
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
External Financing 0 0 0
GoU Development
External Financing
GRAND TOTAL
3,257,000
0
3,257,000
468,266
0
468,266
3,297,000
0
3,297,000
Annual Workplan for 2014/15 - Outputs, Activities, Inputs and their Cost
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
Develop Consistent, effective and efficient regulatory framework for
geothermal energy.
Identify opportunities to advance geothermal energy projects.
Develop Consistent, effective and efficient regulatory framework for
geothermal energy.
Identify opportunities to advance geothermal energy projects.
Policy Formulation Regulation010503
GoU Development
External Financing
Total
40,000
0
40,000
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Allowance for geothermal policy (Number) 16.7 2,000
Fuel (Number) 15,000.0 15,000
Geothermal fieldwork (Number) 83.3 10,000
Geothermal office electrity bills (Number) 1,818.2 1,000
Geothermal seminers &workshops on policy
(Number)
83.3 10,000
Water bills for geothermal lab (Number) 1,333.3 2,000
Establish a geothermal Resources Department
Develop a Communication and community awareness programme.
Geothermal Technology:
Undertake R & D to support geothermal industry
Technology Transfer:
International partnership for geothermal technology (to provide
framework for international cooperation in geothermal technology, policy
and model development).
Establish a geothermal Resources Department
Develop a Communication and community awareness programme.
Geothermal Technology:
Undertake R & D to support geothermal industry
Technology Transfer:
International partnership for geothermal technology (to provide
framework for international cooperation in geothermal technology, policy
and model development).
Institutional capacity for the mineral sector020503
GoU Development
External Financing
Total
60,000
0
60,000
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Fuel (Litres) 750.0 3,000
Field work airtime & walkie talkies (Number) 5.0 1,000
Geothermal investiment promotion (Number) 2.2 13,000
ICT infrastructre upgrade and CCTV security
(Number)
5.0 5,000
Office Consumables and printing of field reports
(Number)
160.0 4,000
Per diem Geothermal exploration and traing
(Number)
91.7 11,000
Security services (Number) 12.5 5,000
Training in Geothermal technologies (Number) 4.0 10,000
Utilities (Number) 11,090.9 8,000
Mineral Exploration, development, production and value-addition promoted030503Output:
Vote Overview
130
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Mineral Exploration, Development & Production03 05
Project 1199 Uganda Geothermal Resources Development
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
Carry out Geothermal exploration. Data acquisition and management:
Acquire accurate and reliable information on geothermal resources in
Uganda.
Carry out Geothermal exploration. Data acquisition and management:
Acquire accurate and reliable information on geothermal resources in
Uganda.
GoU Development
External Financing
Total
489,500
0
489,500
Activities to Deliver Outputs:
Planned Outputs: Inputs Quantity Cost
Electricty bills (KWH) 3,636.4 2,000
Fuel (Litres) 12,500.0 50,000
Fuel for field work (Litres) 1,500.0 6,000
Water Bills (Litres) 1,333.3 2,000
Clearing of equipment, goods & services (Number) 20.0 30,000
Geothermal exploration & support staff allowance
(Number)
87.5 10,500
Geothermal exploration and inspections (Number) 883.3 106,000
Geothermal exploration technologies workshop
(Number)
83.3 10,000
Geothermal investiment oromotion and research
work (Number)
5.0 25,000
Geothermal investment promotion in media
(Number)
2.0 5,000
ICT Infastructure & upgrade (Number) 5.0 5,000
ICT infrastructure & upgrade (Number) 5.0 5,000
Internet services and connectivity (Number) 50.0 10,000
Repair and vehicle servicing (Number) 33.3 50,000
Repair of Offices and Utilities (Number) 9.0 9,000
Training in Geothermal exploration technologies
(Number)
166.7 20,000
Contract staff (Person Years) 30.0 0
Undertake three training and awareness campaign in safety issues during
geothermal exploration to safeguard the health and safety of staff.
Procure Personal Protection Equipment and Comprehensive First Aid Kits
Undertake three training and awareness campaign in safety issues during
geothermal exploration to safeguard the health and safety of staff.
Procure Personal Protection Equipment and Comprehensive First Aid Kits
Health safety and Social Awareness for Miners040503
GoU Development
External Financing
Total
30,000
0
30,000
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Electricity bills (KWH) 1,818.2 1,000
Fuel (Litres) 1,500.0 6,000
Water bills (Litres) 666.7 1,000
Fuel and car consumables (Number) 1,250.0 5,000
Promotion of OHS & use of Geothermal in
Districts (Number)
41.7 5,000
Security services (Number) 10.0 4,000
Supervision &inspection of Geothermal fieldwork
(Number)
50.0 6,000
Vehicle repair and servicing (Number) 10.0 2,000
Undertake administrative reviews for compliance and geothermal
inspections and monitoring.
License new investors
Undertake administrative reviews for compliance and geothermal
inspections and monitoring.
License new investors
Licencing and inspection050503
GoU Development
External Financing
Total
72,500
0
72,500
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Electricity bills (KWH) 3,636.4 2,000
Fuel for field work and inspections (Litres) 2,500.0 10,000
Water bills (Litres) 28,000.0 42,000
Allowances for Geothermal licensing and appraisal
(Number)
41.7 5,000
Inspections &field work (Number) 83.3 10,000
Security services in geothermal operations (Number) 16.7 2,000
Vehicle consumables (Number) 375.0 1,500
Acquisition of Land by Government710503Output:
Vote Overview
131
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Mineral Exploration, Development & Production03 05
Project 1199 Uganda Geothermal Resources Development
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
Survey all the Land with Geothermal resources and gazette it for
geothermal development.
Survey all the land of seismic stations and acqure title deeds.
Survey all the Land with Geothermal resources and gazette it for
geothermal development.
Survey all the land of seismic stations and acqure title deeds.
GoU Development
External Financing
Total
40,000
0
40,000
Activities to Deliver Outputs:
Planned Outputs: Inputs Quantity Cost
Design geothermal faclities and department infras.
(Number)
1.0 10,000
Geothermal EIA & SCR in Geothermal
communities (Number)
41.7 5,000
Inspections and supervison of surveys (Number) 41.7 5,000
Surveying of land services (Number) 2.0 20,000
Renovation of the Buildings and laboratories and improvement of
Security at the gates of Geological Survey and Mines.
Renovation of the Buildings and laboratories and improvement of
Security at the gates of Geological Survey and Mines.
Government Buildings and Administrative Infrastructure720503
GoU Development
External Financing
Total
30,000
0
30,000
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Laboratory waste management designs (Nmber) 41.7 5,000
Building repairs and labs (Number) 5.0 5,000
Laboratory waste management plan (Number) 41.7 5,000
Supervision & monitoring of field work (Number) 1,250.0 15,000
Repair of access road to the Ministry of Energy and Mineral Development
in Entebbe
Repair of access road to the Ministry of Energy and Mineral Development
in Entebbe
Roads, Streets and Highways730503
GoU Development
External Financing
Total
90,000
0
90,000
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Design of Geothermal department infrastructure
(Number)
2.0 40,000
Repair of access road to GSMD (Number) 1.0 10,000
Supervision and Monitring (Number) 333.3 40,000
Procure computers and Softwares and accessories.
Procure computers and Softwares and accessories.
Purchase of Office and ICT Equipment, including Software760503
GoU Development
External Financing
Total
240,000
0
240,000
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Equip Geothermal data centre facility (Number) 1,000.0 240,000
Continue the procurement of Deep subsurface geothermal exploration
equipment and laboratory consumables
Continue the procurement of Deep subsurface geothermal exploration
equipment and laboratory consumables
Purchase of Specialised Machinery & Equipment770503
GoU Development
External Financing
Total
2,180,000
0
2,180,000
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Geothermal Exploration equipment (Number) 1.0 2,000,000
Supervision & Monitoring of Geothermal
operations (Number)
1,500.0 180,000
Purchase of Office and Residential Furniture and Fittings780503Output:
Vote Overview
132
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Mineral Exploration, Development & Production03 05
Project 1199 Uganda Geothermal Resources Development
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
Office funiture and fume cupboards procured for geothermal Unit
Office funiture and fume cupboards procured for geothermal Unit
GoU Development
External Financing
Total
25,000
0
25,000
Activities to Deliver Outputs:
Planned Outputs: Inputs Quantity Cost
Furnish Geothermal Offices (Number) 10.0 25,000
GoU Development
External Financing
GRAND TOTAL
3,297,000
0
3,297,000
Vote Overview
133
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Mineral Exploration, Development & Production03 05
Project 1200 Airborne Geophysical Survey and Geological Mapping of Karamoja
Workplan Outputs for 2013/14 and 2014/15
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
Mining policy and legislation
reviewed.
District leaders and Natural
Mining policy and legislation
review progressed.
District leaders and Natural
Resources Officers from Napak
Policy Formulation
Regulation
Policy Regulation and
sensitization
(a) Train Local Government
(LG) Officials on Mineral
010503
Commissioner Geological Survey and Mines Depart. (C/GSMD)
Objectives of the project
are:
-
Carrying out airborne geophysical survey of Karamoja
- Complete the gap in high quality airborne geophysical data coverage of Uganda
- Acquire remote Sensing data for Karamoja region to map mineral signatures
- Map mineral potential of Karamoja
- Package Karamoja region for mining investment opportunities in Karamoja
- Update Geophysical map of Uganda for mineral investment promotion
- Construct and equip Karamoja Office and other Regional Offices
- Procure exploration equipment for Uranium and other Minerals of economic importance.
Outputs:
-
Updated geophysical, geochemical, geological and mineral resources maps of Karamoja
- Complete geophysical maps coverage of mineral potential of Uganda
- Mineral signature maps of Karamoja.
- Regional Office for Karamoja Region and other mining regions.
- Composite regional gravity and magnetic data and maps for tectonic studies
- New magnetic data on Karamoja to enhance the knowledge of natural resources of
Karamoja.
- Radon index for the Karamoja region.
- Structural maps for targets of mineralization and enhance the knowledge of ground water
mapping and harvesting.
- Report on targets for follow-up.
- Equivalent Potassium Thorium and Uranium data. (K: Th ratio, U/K, U/Th ratios).
- Radiometric and magnetic data for publication.
- Mineral investment packages on Karamoja will increase employment opportunities and
poverty reduction in the region.
Review of the existing geological information
- Geological Maps ,Structural maps derived from Remote Sensing data, Geochemical maps,
Ground geophysical maps, Mineral potential targets, Increase in NTR from regular inspection
of mining operations, Trained human resource, Associations of Artisanal and Small Scale
Miners (ASM), A regional office in Moroto.
Responsible Officer:
Objectives:
Outputs:
7/1/2011 6/16/2015Start Date: Projected End Date:
Project Profile
Donor Funding for Project:
2016/172012/13
Budget
2013/14
Budget 2014/15 2015/16
MTEF Projections
Projected Donor Allocations (UShs)
Africa Development Bank (ADB) 0.000 0.000 10.000 0.0000.000401
0.000 0.000 10.000 0.0000.000Total Donor Funding for Project
Vote Overview
134
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Mineral Exploration, Development & Production03 05
Project 1200 Airborne Geophysical Survey and Geological Mapping of Karamoja
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
Resources Officers from the
seven districts of Karamoja
sensitized
The Mining Policy and
legislation documents
disseminated
and Moroto Districts sensitized
and consulted and 14 Mining
Policy and Legislation
Monthly consultative meetings
on mineral policy and mining
legislations were carried out at
the Department of Geological
Survey and Mines, Entebbe.
Key resource persons from
Mining Companies and Law
Firms were invited to present
their views.
Consultations with stakeholders
in Karamoja were made during
a workshop at Karamoja
Development Association
(KADP) in Moroto
Municipality.
In total, Fourty Four (44) copies
of the Mining Act, 2003 and 2
copies of the Small Scale
Mining Hand Book were given
to distinguished participants in
the International Union on
Conservation of Nature during a
workshop at Karamoja Agro
Pastoral Development Program
(KADP) premises in Moroto
Municipality.
Reviewed mining policy and
legislation and gaps identified
District leaders from all seven
districts of Karamoja were
sensitized and consulted on
mining legislation. Thirty
Copies of mining policy and
legislation were disseminated
on 25th January 2014
Policy, Regulations and Laws;
(b) Disseminate 200 copies of
the Mineral Policy, 2001; the
Mining Law, 2003; and the
Mining Regulations 2004;
(c) Review the mining laws and
regulations; (d) Promote
investment in mineral sector;
GoU Development
External Financing
Total
237,000
0
237,000
163,456
0
163,456
237,000
0
237,000
Capacity building, Research and
Mineral Development in
Karamoja Region conducted.
Establishment of a Mini
laboratory for Karamoja Region
in Moroto.
Livelihood of Artisanal and
Small Scale miners improved.
Conducted and published
market research on Karamoja
Marble and other minerals in
Karamoja. Undertook two (2)
workshops on mineral
investment promotion of
Karamoja region.
Internal workshops on
geological mapping,
geochemical surveys and
mineral resources assessment of
Karamoja were held to present
and discuss previous field
activities and results and
planned activities. It is
maintained that geological
survey standards should
conform to the SMMRP data
formats and be compatible to
Geological and Mineral
Information System (GMIS).
A one day workshop on Cost
Benefit Analysis of Mining in
Karamoja in collaboration with
the International Union of
Conservation of Nature was
Institutional capacity for
the mineral sector
Training of staff,
formalization of
artisanal and small scale miners,
facilitation of laboratories for
sample analysis.
020503
Vote Overview
135
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Mineral Exploration, Development & Production03 05
Project 1200 Airborne Geophysical Survey and Geological Mapping of Karamoja
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
held on 19th November, 2013
at KADP premises in Moroto
Municipality. The workshop
attracted participants in the
categories of Local Government
Leaders, NGOs, LSM & SSM,
MEMD and Elders.
The Project Coordinator/
Karamoja Project made a
presentation on ‘Overview of
Mineral Sector and Investments
in Karamoja’.
Collection of data to analyse
cost benefits of mining in
Karamoja.
Large Scale and Small Scale
Mining Companies were visited
and interviewed.
A follow up workshop was
made on13th December, 2013
to present the findings of Cost
Benefit Analysis of Mining in
Karamoja at Golf Course Hotel
in Kampala.
A workshop was held on 21st
and 22nd November 2013 on
Sectoral Institutional Analysis at
Sports View Hotel in Kireka in
which opportunities and
challenges in the Mineral Sector
were presented and discussed.
Broad priorities for the Mineral
Sector were set and cross
cutting issues such as the
environment, gender, HIV,
Health and Safety, child labor
were discussed.
The Project Coordinator/
Karamoja Geo-Surveys
participated in the annual
general meeting of the
InterGovernmental Forum on
Mining, Minerals, Metals and
Sustainable Development held
at the Palais des Nations,
Geneva, Switzerland from 28
October- 1st November 2013.
A presentation on the ‘Artisanal
and Small Scale Mining in
Uganda and its
Management’was made at the
conference and got actively
engaged with one another,
sharing their expertise,
knowledge and leading
practices on the challenges and
opportunities facing the mineral
sector. The IGF developed its
Mining Policy Framework, and
is now advancing
implementation of this guidance
for good governance in the
mineral sector among member
countries. In Uganda the
mineral sector is increasingly
faced with the informal and
illegal mining, environment,
health and safety issues coupled
with growth of the sector.
Vote Overview
136
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Mineral Exploration, Development & Production03 05
Project 1200 Airborne Geophysical Survey and Geological Mapping of Karamoja
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
Trained the geoscientists in
value addition, gemology,
petrological analysis of minerals
and rocks
Two (2) internal training
workshops on geological
mapping, geochemical surveys
and mineral resources
assessment were undertaken
covering the l maps sheets 25/1,
2 and 4.
Sixty eight (68) Artisanal and
Small Scale Miners (ASM) in
Moruita, Nakapiripirit District
was carried out.
GoU Development
External Financing
Total
213,000
0
213,000
129,421
0
129,421
213,000
0
213,000
Geological, geochemical and
geophysical mapping of
Karamoja carried out.
Mineral potential of Karamoja
region established and
promoted.
Commenced to process,
analyse and interpret old
airborne magnetic data covering
Karamoja region of 1960-1980s.
Organised and conducted four
(4) workshops on
standardisation of geological
surveys to existing data formats,
baseline geological data, GIMIS
compatibility and airborne
geophysical terms of reference.
Undertook refresher geological
mapping orientation training for
preparation and initiation of
geoscientists to fit Karamoja
work environment.
Initiated the recruitment of
human resources to support
Karamoja project and office.
Initiated the procurement of,
consumables, services and
equipment for Karamoja Project.
Reviewed activities of
exploration and mining
companies in Karamoja and
compiled geological data
acquired by the companies for
verification during geological
mapping and geochemical
surveys.
Compilation and review of
airborne geophysical survey
data acquired by Huntings in
1980s and hence terms of
reference was done.
The data is found to have low
resolution although zones of
low and high magnetic
signatures could be recognized
fuzzily and yet lots of spatial
gaps exist in the old geophysical
survey data.
Old airborne geophysical map
(magnetics- Huntings, 1980)
was compared to recently
acquired high resolution
airborne geophysical
Mineral Exploration,
development, production
and value-addition
promoted
Establish the Mineral Wealth of
Karamoja:
Airborne Geophysical surveys
of Karamoja (15 million USD
i.e 40bn UGX)
Review of existing
geological
Information, remote sensing,
geological mapping,
geochemical surveys, follow up
ground geophysical surveys and
mineral resources assessment.
030503
Vote Overview
137
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Mineral Exploration, Development & Production03 05
Project 1200 Airborne Geophysical Survey and Geological Mapping of Karamoja
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
data(SMMRP, 2011)
Geological mapping and
geochemical surveys of
Karamoja commenced in Sheet
25/3, Abim District. The
geology is composed of
charnockites, granulites (felsic
and intermediate), migmatitic
garnetiferous gneisses and
superficial deposits (alluvium
and laterites) rocks.
Faults, quartz veins, aplitic
veins, pegmatites, fold
structures and jointing were
remarkably observed in the
field.
Exfoliation and veins in
charnokites and micro folding in
felsic granulites
Minerals of interest found on
the sheet are: graphite, garnets,
codierite, tourmaline, mica and
ilmenites. Aluvial gold working
was encountered in the sheet at
UTM location coordinates
585438mE/288206mE.
Garnets in granulitesand alluvial
gold workings at Morulem
were discovered.
Discovered perculiar imprints
on rock surfaces at Otukei were
mapped and are known to have
potential for geo-tourism.
More work is required to assess
the age and history of events
that took place here.
At location
567390mE/274696mN,
synoptic view of sole feet
/grinding stone occur at Otukei
Charnockite
Received requests for
geological information on
marble resources in Karamoja
remained stable as investors
strive to establish cement
manufacturing plants in the
region.
Review of a Feasibility Study
Report for establishment of
cement manufacturing plant in
Moroto submitted by the CMC
was carried out in November
2013 and comments were
provided.
Seven (7) Staff participated in
promotion of the mineral sector
at the Mining Indaba
Conference in Cape Town
South Africa from 3rd -6th
February 2014.
Three (3) Staff participated in
promotion of investment in the
Mineral sector at Prospectors
Developers Association of
Vote Overview
138
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Mineral Exploration, Development & Production03 05
Project 1200 Airborne Geophysical Survey and Geological Mapping of Karamoja
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
Canada (PDAC) Toronto
Canada from 3rd -7th March
2014
Geological mapping,
geochemical surveys and
mineral resources assessment in
sheets 25/1, 2, 3 and 4 were
completed; Processing, analysis
and interpretation of the data is
on-going.
Undertook a follow up on
recommendation of Parliament
and Presidential Directive on
20% airborne geophysical
surveys of Karamoja by
reminding MoFPED about the
funding gap of USD 15 million.
GoU Development
External Financing
Total
935,000
0
935,000
502,845
0
502,845
935,000
0
935,000
Promote public health in mining
communities through local
leaders
Small scale miners trained from
Rupa in Moroto, Acerere in
Nakapiripirit, Morulem in
Abim, Amudat, Kotido and
Kaboong on health, safety,
environmental and social issues
related to mining.
Undertook Health and safety
and social awareness of Miners
in Karamoja region
Manuals adopted from the
Small Scale Mining Hand Book
were prepared to be
disseminated to Small Scale
Mining groups in Abim, Moroto
and Nakapiripirit Districts to
guide small scale miners in their
districts on health and safety
issues.
Sensitisation workshop on
Health and safety awareness
creation program in Morulem,
Abim District was carried out.
Undertook Health and safety
and social awareness of Miners
in Karamoja region
Manuals adopted from the
Small Scale Mining Hand Book
were prepared to be
disseminated to Small Scale
Mining groups in Abim, Moroto
and Nakapiripirit Districts to
guide small scale miners in their
districts on health and safety
issues.
Sensitisation workshop on
Health and safety awareness
creation program in Morulem,
Abim District was carried out
Developed specification of
health and safety kits
Awareness on health and safety
of miners at Morulem in Abim,
District and Moruita in
Nakapiripirit District was
undertaken
Health safety and Social
Awareness for Miners
Sensitise and Train miners on
health and safety
issues
040503
GoU Development
External Financing
Total
244,000
0
244,000
177,834
0
177,834
244,000
0
244,000
Inspection and monitoring of
exploration and mining
Compiled and analyzed mineral
production statistics of
Licencing and inspection Carry out inspections; record
mineral
050503
Vote Overview
139
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Mineral Exploration, Development & Production03 05
Project 1200 Airborne Geophysical Survey and Geological Mapping of Karamoja
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
activities carried out in licensed
areas.
More Non Tax Revenues
(NTR) assessed and collected.
Karamoja region.
Inspected and monitored
exploration and mining
activities in Karamoja region
(Nakapiriprit, Moroto, Napak,
Kotido, Kaboong, Abim and
Amudat).
A total of 69 drainage and
stream sediment samples were
taken from sheet 25/3. The
samples were prepared at the
Mineral Dressing Lab. of the
DGSM ready to trace element
analysis.
Undertook licensing and
inspections
During the week of 4th
November, 2013, a team from
the Department of Geological
Survey and Mines (DGSM)
undertook a field inspection on
ML1129 – Jan Mangal (U)
Limited, ML4128 – Greenstone
Resources Limited, ML4651 –
Gulf Resources Limited,
LL0989 – Busia United Small
Scale Mining Association
Limited, LL1039 – George
Onega, LL0427 – Great Lakes
Cement Limited, LL1194 –
Welt Machnen Engineering
Limited and estimated the
amount of material extracted by
M/S Dao Marble Limited.
Inspection team of the Ministry
of Energy and Mineral
Development in Nakabat (Jan
Mangal’s) and Tamtaok (Welt
Machinen’s).
Assessed exploration and
mining operations to aid
revenue determination.
Sensitized Karamoja mining
districts leaders, legislators and
communities on mining
legislation and compliance in
(Nakapiripirit, Moroto, Napak,
Kotido, Kaboong, Abim and
Amudat).
Reviewed and assessed Twenty
Seven (27) exploration licenses
in Karamoja region
Inspection of the mining
activities in Kaabong and
Kotido Karamoja region is on
going
statistics, labour, production,
income, taxes, livelihood trends;
address environmental and
social issues in mining
operations; identify training
needs of the industry and
educate miners on mining health
and safety operations trends;
(c) Address environmental and
social issues in mining
operations;
(d) Identify training needs of the
industry;
(e) Educate miners on mining
health and safety operations.
GoU Development
External Financing
Total
150,000
0
150,000
111,673
0
111,673
150,000
0
150,000
Karamoja regional training
centre and offices constructed.
Initiated procurement of a
contactor construct Karamoja
Regional Office and training
centre for mineral development.
Government Buildings and
Administrative
Infrastructure
Construct and equip a regional
minerals office for Karamoja
region; set up a training centre
for ASM in Moroto
720503
Vote Overview
140
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Mineral Exploration, Development & Production03 05
Project 1200 Airborne Geophysical Survey and Geological Mapping of Karamoja
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
Initiated procurement of project
computers and printers.
Initiated the purchase of
cartridges and procurement of
maintenance services
Initiated the purchase of anti-
virus, upgrade and back-up
systems.
Initiated the procurement of
active fault mapping equipment
and landslide investigations.
Produced regional earthquake
bulletins with difficulties of
funding.
Disseminated seismic data to
data users in infrastructure
planning, construction of
Karuam Hydro Power dam and
other small hydro power
stations.
Initiated Procure furniture and
computers.
Payment for land in Moroto,
Plots 17 and 19 Rupa Road
allocated for DGSM office
construction was made.
The land for the project was re-
allocated to another developer.
New plots are being identified.
GoU Development
External Financing
Total
800,000
0
800,000
216,754
0
216,754
800,000
0
800,000
Project computers, laptop and
printers purchased.
Catridges and computers
maintained.
Anti-virus, upgrade and back-up
systems
Procured furniture, computers
and office consumables
Initiated procurement of project
computers and printers.
Initiated the purchase of
cartridges and procurement of
maintenance services.
Initiated the purchase of anti-
virus, upgrade and back-up
systems.
Initiated Procure furniture and
computers.
Procured toners, cartridges,
office furniture and ICT facilities
Purchase of Office and
ICT Equipment,
including Software
Procurement of Office
and ICT
Equipment including software
760503
GoU Development
External Financing
Total
30,000
0
30,000
7,500
0
7,500
30,000
0
30,000
Vote Overview
141
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Mineral Exploration, Development & Production03 05
Project 1200 Airborne Geophysical Survey and Geological Mapping of Karamoja
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
Engineering geology
investigations conducted and
geo-hazards monitored, active
fault mapped
No funds were released for
Maintenance of Seismological
Network
and Servicing of Seismological
stations
Disseminated seismic data to
data users in infrastructure
planning, construction of
Karuam Hydro Power dam and
other small hydro power.
Continued with procurement of
specialised equipment for
Engineering geology
investigations to conducted.
Monitored the geo-hazards and
active faults using the National
Seismological Network stations.
Purchase of Specialised
Machinery & Equipment
Procurement and installation of
Specialised equipment.
770503
GoU Development
External Financing
Total
950,000
0
950,000
289,226
0
289,226
950,000
0
950,000
Furniture, computers and
reference books procured.
Initiated the procurement of
office curtains , Books and
fiitings
Purchase of Office and
Residential Furniture and
Fittings
Procurement of office and
residential
furniture and fittings.
780503
GoU Development
External Financing
Total
40,000
0
40,000
14,650
0
14,650
40,000
0
40,000
GoU Development
External Financing
GRAND TOTAL
3,599,000
0
3,599,000
1,613,360
0
1,613,360
3,599,000
0
3,599,000
Annual Workplan for 2014/15 - Outputs, Activities, Inputs and their Cost
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
Policy Regulation and sensitization
(a) Train Local Government (LG) Officials on Mineral Policy, Regulations
and Laws;
(b) Disseminate 200 copies of the Mineral Policy, 2001; the Mining Law,
2003; and the Mining Regulations 2004;
(c) Review the mining laws and regulations; (d) Promote investment in
mineral sector;
Policy Regulation and sensitization
(a) Train Local Government (LG) Officials on Mineral Policy, Regulations
and Laws;
(b) Disseminate 200 copies of the Mineral Policy, 2001; the Mining Law,
2003; and the Mining Regulations 2004;
(c) Review the mining laws and regulations; (d) Promote investment in
mineral sector;
Policy Formulation Regulation010503
GoU Development
External Financing
Total
237,000
0
237,000
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Electricity Utilities (KWH) 9,090.9 5,000
Fuel (Litres) 7,250.0 29,000
Water Utilities (Litres) 500.0 5,000
Deliverly of Mining documenation to stakeholders
(Number)
250.0 5,000
Field vehicle repairs (Number) 20.0 30,000
Fieldwork for Formalisation of Small Miners (SM)
(Number)
500.0 60,000
ICT infrastructure upgrade and solar power
(Number)
10.0 37,000
Internet services and connectivity (Number) 25.0 5,000
Mineral sector investiment promotion (Number) 2.0 20,000
Printing of mineral legislation (Number) 400.0 10,000
Sensitization of relevant authorities in Karamoja
(Number)
100.0 10,000
Telephone Untilites & field work airtime (Number) 10.0 1,000
Training in mineral policy (Number) 83.3 10,000
Workshop on Mineral Policy, Regulations and
Laws; (Number)
2.0 10,000
Vote Overview
142
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Mineral Exploration, Development & Production03 05
Project 1200 Airborne Geophysical Survey and Geological Mapping of Karamoja
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
Training of staff, formalization of
artisanal and small scale miners, facilitation of laboratories for sample
analysis.
Training of staff, formalization of
artisanal and small scale miners, facilitation of laboratories for sample
analysis.
Institutional capacity for the mineral sector020503
GoU Development
External Financing
Total
213,000
0
213,000
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Utilities (Litres) 4,000.0 4,000
Field work in mining districts (Number) 333.3 40,000
File folders and paper clips and printer cartridge
(Number)
10.0 10,000
Mining community sensitization W/shop $ seminar
(Number)
83.3 10,000
Mining investiment promotion and value addtion
(Number)
4.0 20,000
Other Utilities (Number) 100.0 20,000
Per diem Mining legislation training and review
(Number)
83.3 10,000
Printing and biding of reports & papers (Number) 400.0 10,000
Sample transport & analysis (Number) 35.0 7,000
Scientific books and Journals (Number) 6.7 4,000
Security services (Number) 25.0 10,000
Traing in sustainable mnagement & value addition
(Number)
5.0 25,000
Vehicle servicing for F/w community sensitization
(Numbers)
34.8 39,000
Utility payment (Units) 4.0 4,000
Establish the Mineral Wealth of Karamoja:
Airborne Geophysical surveys of Karamoja (15 million USD i.e 40bn
UGX)
Review of existing geological
Information, remote sensing, geological mapping, geochemical surveys,
follow up ground geophysical surveys and mineral resources assessment.
Geological Mapping:
Undertake field verification and ground truthing of the inferred structures
from remote sensing;
(b) Carry out detailed geological mapping –collect geological information
on the dip or strike, mineralogy, lineaments, trends and other structures;
(c) Collect geological samples for analysis (petrological, chemical); (d)
Build geological data base and plot data on maps;
(e) Prepare geological maps at appropriate scales;
(f) Prospect for economic minerals and package them for follow up and
investmentGeochemical Surveys:
(a) Undertake reconnaissance geochemical surveys to study and assess the
nature and type of geological materials to be sampled, drainage pattern,
terrain and access;
(b) Carry out systematic geochemical sampling at sample density of one
sample per square kilometre;
(c) Carry out heavy mineral concentrate survey in selected catchments;
(d) Undertake sample preparation; crushing, sieving, splitting, sample
analysis, preparation of standards, calibration of equipment and taking
readings;
(e) Carry out chemical analysis on the collected samples for an
optimum number of elements;
(f) Build geochemistry database; (g) Plot the data on maps;
(h) Interpretation of geochemical data.Ground geophysical surveys
(a) Carry out ground geophysical surveys on selected geochemical
anomalies of high grade using gravity, induced polarisation, magnetics,
Mineral Exploration, development, production and value-addition promoted030503
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Utilites for electricity (KWH) 7,272.7 4,000
Field work fuel, administration & supervision
(Litres)
25,000.0 100,000
Water bills (Litres) 3,333.3 5,000
Field wk Mineral exploration & reserves estimation
(Number)
2,966.7 356,000
Fuel for field work (Number) 15,000.0 60,000
General Staff meetings & technical presentations
(Number)
10.0 10,000
ICT based security system & Metal detectors
(Number)
2.0 2,000
ICT security system & CCTV Cameras &
servillances (Number)
20.0 20,000
Mineral exploration and reserves assessment
(Number)
333.3 40,000
Mineral exploration and support staff allowances
(Number)
116.7 14,000
Mineral investiment promotion and value addition
(Number)
10.0 80,000
Mineral potential investment promotion (Number) 4.0 10,000
Procurement of Mineral exploration text books & j
(Number)
33.3 10,000
Repair of buildings (Number) 5.0 10,000
Servicing of field vehicles (Number) 100.0 40,000
Training in exploration technology value addition
(Number)
250.0 30,000
Contract staff (Person Years) 15.0 144,000
Vote Overview
143
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Mineral Exploration, Development & Production03 05
Project 1200 Airborne Geophysical Survey and Geological Mapping of Karamoja
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
electromagnetics, radiometric, depending on the nature and type of the
anomaly.Mineral Resources Assessment
(a) Compile all available mineral potential sites in Karamoja region; both
old and new resulting from this planned exercise;
(b) Sample and analyse the minerals for grade determination, in grams per
tonne;
(c) Carry out the mapping of the mineralized zones, i.e., length and width
extent; (d) Estimation of ore reserves (inferred). ;
(e) Build data base of mineral resources.
GoU Development
External Financing
Total
935,000
0
935,000
Sensitise and Train miners on health and safety
issues
Train the ASM on the best practices, health and safety issues; (d) Train
the ASM in the mineral business and value addition;
(e) Train the new Staff of GSMD in sustainable management of mineral
resources
and value addition.
Health safety and Social Awareness for Miners040503
GoU Development
External Financing
Total
244,000
0
244,000
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Electricity bills (KWH) 5,454.5 3,000
Fuel (Litre) 10,000.0 40,000
Water bills (Litres) 2,000.0 3,000
Allowance best practices, health & safety issues;
(Number)
150.0 18,000
Field work for OHS promotion (Number) 333.3 40,000
ICT security system & CCTV monitoring (Number) 25.0 50,000
Improvement of ICT infrastructre & CCTTV
security (Number)
10.0 10,000
Office consumables (Number) 20.0 10,000
Printing of OHS awareness information & data
(Number)
400.0 10,000
Promotion of OHS in Mining communities
(Number)
166.7 20,000
Security servics (Number) 25.0 10,000
Support to HIV positve living human resource
(Number)
20.0 10,000
Training of ASM in OHS business and value
addition (Number)
166.7 20,000
Carry out inspections; record mineral
statistics, labour, production, income, taxes, livelihood trends; address
environmental and social issues in mining operations; identify training
needs of the industry and educate miners on mining health and safety
operations trends; (c) Address environmental and social issues in mining
operations;
(d) Identify training needs of the industry;
(e) Educate miners on mining health and safety operations.
Inspection of mining operations
(a) Carry out inspections in all exploration and mining activities of
Karamoja region; (b) Record mineral statistics – labour, production,
income, taxes, livelihood
Licencing and inspection050503
GoU Development
External Financing
Total
150,000
0
150,000
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Electricity bills (KWH) 3,636.4 2,000
Fuel (Litres) 7,500.0 30,000
Field work & mine inspections (Number) 333.3 40,000
Licensing & support staff, fieldwork alloowance
(Number)
83.3 10,000
Licensing stakeholders workshop (Number) 83.3 10,000
Training in Mineral statistics & NRT collection
(Number)
10.0 5,000
Vehicle consumables, fuel etc (Number) 100.0 30,000
Vehicle Servicing and repair (Number) 22.2 20,000
Water utilities (Number) 2,000.0 3,000
Construct and equip a regional minerals office for Karamoja region; set up
a training centre for ASM in Moroto
Construct and equip a regional minerals office for Karamoja region; (b)
Government Buildings and Administrative Infrastructure720503
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Constract, exploration equipment & value addition
(Number)
2.1 730,000
Mine designs and infrastructure, inspections
(Number)
250.0 30,000
Vote Overview
144
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Mineral Exploration, Development & Production03 05
Project 1200 Airborne Geophysical Survey and Geological Mapping of Karamoja
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
Set up a training centre for ASM in Moroto.Construct and equip a
regional minerals office for Karamoja region; (b) Set up a training centre
for ASM in Moroto.
GoU Development
External Financing
Total
800,000
0
800,000
Mining Environmental restoration activities
(Number)
166.7 20,000
Supervision of mining operations (Number) 166.7 20,000
Procurement of Office and ICT
Equipment including software
Procure of for data servers cooling system , computers , ICT equipment
Procure of for data servers cooling system , computers , ICT equipment
Purchase of Office and ICT Equipment, including Software760503
GoU Development
External Financing
Total
30,000
0
30,000
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
ICT Laboratory equipment & mineral value
addition (Number)
1.0 30,000
Procurement and installation of
Specialised equipment.
Procurement petrophysics equipment Mineralogical microscopes
Field XRF Mineralogical analysis microscopes
Field XRF
Procure geophysical equipment
Seismological equipment.
Maintenace of seismological network
Purchase of Specialised Machinery & Equipment770503
GoU Development
External Financing
Total
950,000
0
950,000
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
inspect design of mines and infrastructure (Number) 416.7 50,000
Laboratory, geophysical seismological equipment
(Number)
1.0 800,000
Monitoring and inspection of mining operations
(Number)
166.7 20,000
Supervison and inspections (Number) 666.7 80,000
Procurement of office and residential
furniture and fittings.
Procurement of office and residential
furniture and fittings.
Purchase of Office and Residential Furniture and Fittings780503
GoU Development
External Financing
Total
40,000
0
40,000
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Office furniture (Number) 4.0 40,000
GoU Development
External Financing
GRAND TOTAL
3,599,000
0
3,599,000
Vote Overview
145
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Policy, Planning and Support Services03 49
Services:
Responsible Officer:
Vote Function Profile
This vote function provides support services to the Energy and Minerals sector, it
guides the Policy formulation, implementation and also responsible for the
procurements, Planning, Budgeting and Policy Analysis and also the Finance and
Administrative functions.
Under Secretary
Vote Function Projects and Programmes:Project or Programme Name Responsible Officer
Recurrent Programmes
01 Headquarters Under Secretary, Finance and Administration
06 Directorate Director Energy and Mineral Development
08 Internal Audit Department Principal Internal Auditor
Development Projects
1223 Institutional Support to Ministry of Energy and Mineral Devel Under Secretary, Finance and Administration
Programme 01 Headquarters
Workplan Outputs for 2013/14 and 2014/15
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
Budget Framework Paper
(BFP), Budget Estimates,
Backgroud to the Budget
chapter, Public Investment Plan
(PIP), Performance Plans
submitted to MoFPED.
Ministerial Policy Statement
(MPS) submitted to Parliament,
progress Reports coordinated
and submitted to OPM.
The Budget Framework Paper
(BFP) for FY 2014/15, Budget
Estimates, Backgroud to the
Budget chapter, Public
Investment Plan (PIP),
Performance Plans were
submitted to MoFPED by end
of February 2014.
Q1 and Q2 FY 2013/14
progress Reports were
coordinated and submitted to
Parliament, MofPED and OPM
by end of February 2014.
Planning, Budgeting and
monitoring
Budget Framework Paper
(BFP), Budget Estimates,
Backgroud to the Budget
chapter, Public Investment Plan
(PIP), Performance Plans
submitted to MoFPED.
Ministerial Policy Statement
(MPS) submitted to Parliament,
progress Reports coordinated
and submitted to OPM.
Undertake a study to set up 4
Regional mines offices
014903
Wage Recurrent
Non Wage Recurrent
Total
131,057
159,369
290,426
99,804
100,108
199,912
743,494
159,000
902,494
Approved Departments’
payments processed.
Financial Management Function
Executed
NTR Collected, receipted &
reconciled off
Payment records documented
Continued to process
Departmental Payments.
Financial Management Function
has continued to be executed.
Continued Collection, receipt &
reconciling off of NTR
Continued documentation of
Finance Management and
Procurement
Approved Departments’
payments processed.
Financial Management Function
Executed
NTR Collected, receipted &
reconciled off
Payment records documented
024903
Under Secretary, Finance and Administration
To review and put in place modern policies and legislation that offers a conducive business
environment
To carry out specialised and general training of manpower and strengthen capacity of the
institutions responsible for managing and safeguarding the energy and mineral resources.
The vote function provides support services to the Energy and Mineral Sector through
guidance on Policy Formulation, Implementation. It provides the services of procurements,
planning, budgeting and policy analysis and also finace and administrative function.
Responsible Officer:
Objectives:
Outputs:
Programme Profile
Vote Overview
146
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Policy, Planning and Support Services03 49
Programme 01 Headquarters
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
Financial Reports /statements
prepared & submitted to
Accountant General
Responses to Audit queries
prepared.
Gross Tax Payments processed.
Payment records
Recurrent preparation and
submission of Financial Reports
/statements to Accountant
General
Continuous Response
preparation to Audit queries
Continued procession of Gross
Tax Payments.
and filed
Financial Reports /statements
prepared & submitted to
Accountant General
Responses to Audit queries
prepared.
Gross Tax Payments processed.
Wage Recurrent
Non Wage Recurrent
Total
88,038
91,850
179,888
65,781
65,329
131,109
0
92,000
92,000
Monthly Procurement Reports
Procurement Submissions made
to the Contracts committee
Contract documents prepared
Solicitation documents prepared
Aggregated procurement plan
prepared
Prequalification list of providers
prepared
An up-to-date MEMD fixed
assets register
MEMD property boarded-off
Well maintained
offices/furniture and equipment
Stationery, equipment and
office consumable available in
offices
Continued reporting of Monthly
Procurements
Continued Procurement
Submissions made to the
Contracts committee
Continuous preparation of
Contract documents
Continued preparation of
Solicitation documents
Continued preparation of
Aggregated procurement plans
Continuous update of
Prequalification list of providers
Updating of MEMD fixed
assets register
MEMD absolete property has
continued to be boarded-off
Continued maintainece of
offices/furniture and equipment
Continued availabilty of
stationery, equipment and
office consumables
Procurement &
maintainance of assets and
stores
Monthly Procurement Reports
prepared and submitted to
PPDA
Procurement Submissions made
to the Contracts committee
Solicitation and Contract
documents prepared
Aggregated procurement and
disposal plan for the Ministry
prepared
Prequalification list of providers
updated
An up-to-date MEMD fixed
assets register
MEMD obselete property
boarded-off
Well maintained
offices/furniture and equipment
Stationery, equipment and
office consumable available in
offices
034903
Wage Recurrent
Non Wage Recurrent
Total
174,076
104,555
278,631
125,661
62,908
188,569
0
105,000
105,000
Sector Strategic Plan for
Statistics implemented.
Continuous implemetation of
the Sector Strategic Plan for
Statistics
Statistical Coordination
and Management
Sector Strategic Plan for
Statistics implemented.
044903
Wage Recurrent
Non Wage Recurrent
Total
88,038
51,000
139,039
53,920
29,512
83,432
0
51,000
51,000
Staff recruitment undertaken.
Salaries paid.
Performance Management
monitored.
Staff annual performance
review workshop
Human Resource
development/training
Continuous recruitment of Staff
Recurrent payment of Salaries
Continued monitoring of
Performance Management.
Staff annual performance
review workshop held at
Entebbe and Amber House.
Continuous coordination of
Management of Human
Resource
Staff recruitment undertaken.
Salaries paid.
Performance Management
monitored.
Staff annual performance
review workshop
Human Resource
development/training
054903
Vote Overview
147
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Policy, Planning and Support Services03 49
Programme 01 Headquarters
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
coordinated.
Monitor and evaluate the
implementation of the Client
Charter
Departmental Service Delivery
Standards developed and
implemented.
Gender mainstreaming in
Human Resource Management
implemented.
Disciplinary action against
errant Officers undertaken.
Manpower analysis and staffing
undertaken.
Public Service Commission
decisions implemented
Staff welfare managed.
HIV/AIDS work place policy
implemented.
Mail received, sorted,
classified, filed, dispatched and
delivered to their final
destinations.
Records Centre Re Organized
Sensitization of staff on new
Records Centre Procedures
both at Head quarters and
Entebbe stations
Printing and distribution of
Records Retention and Disposal
Schedules for the Ministry.
All personnel files updated with
the required basic records
Human Resource
development/training.
Continued to Monitor and
evaluate the implementation of
the Client Charter
Continued the development and
implementation of Departmental
Service Delivery Standards.
Gender mainstreaming in
Human Resource Management
implemented.
Disciplinary action against
errant Officers undertaken.
Manpower analysis and staffing
undertaken.
Public Service Commission
decisions implemented
Staff welfare managed.
HIV/AIDS work place policy
implemented.
Mail received, sorted,
classified, filed, dispatched and
delivered to their final
destinations.
Records Centre Re Organized
Sensitization of staff on new
Records Centre Procedures
both at Head quarters and
Entebbe stations
Printing and distribution of
Records Retention and Disposal
Schedules for the Ministry.
All personnel files updated with
the required basic records.
coordinated.
Monitor and evaluate the
implementation of the Client
Charter
Department Service Delivery
Standards developed,
implemented and monitored.
Gender mainstreaming in
Human Resource Management
implemented.
Disciplinary action against
errant Officers undertaken.
Manpower analysis and staffing
undertaken.
Public Service Commission
decisions implemented
Staff welfare managed.
HIV/AIDS work place policy
implemented.
Mail received, sorted,
classified, filed, dispatched and
delivered to their final
destinations.
Records Centre in GSMD set up
Records retention and disposal
schedule for the ministry
dissemniated
Records management
procedures streamliened
All personnel files updated with
the required basic records
Wage Recurrent
Non Wage Recurrent
Total
43,019
140,000
183,019
31,524
83,716
115,239
0
164,567
164,567
Connect all work stations in the
ministry to internet
Servicing of all desktop
computers and printers under
F&A.
Intercom connection for offices
that are lacking.
Website maintenance.
Organize a retreat/workshop to
discuss the draft copy of the
IT/Information systems policy
Re-organize/give a facelift to
the resource center
7.0 Tracking the cables in the
IFMS server room
8.0 Newspapers for the
resource center, and stationery
Three quarters of work stations
in the ministry have been
connected to the internet
Servicing of all desktop
computers and printers under
F&A.
Intercom connection for offices
that are lacking.
Continuous website
maintenance.
Re-organization of the resource
center
7.0 Tracking the cables in the
IFMS server room
8.0 Newspapers for the
resource center, and stationery
Management of Policy
Issues, Public Relation,
ICT and Electricity
disputes resolved
Connect all work stations in the
ministry to internet
Servicing of all desktop
computers and printers under
F&A.
Intercom connection for offices
that are lacking.
Website maintenance.
Organize a retreat/workshop to
discuss the draft copy of the
IT/Information systems policy
Re-organize/give a facelift to
the resource center
7.0 Tracking the cables in the
IFMS server room
8.0 Newspapers for the
resource center, and stationery
064903
Total 427,817 256,374 275,000
Vote Overview
148
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Policy, Planning and Support Services03 49
Programme 01 Headquarters
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
Wage Recurrent
Non Wage Recurrent
Total
53,023
374,794
37,179
219,195
0
275,000
Arrears994903
Wage Recurrent
Non Wage Recurrent
Total
0
0
0
0
0
0
0
200,000
200,000
Wage Recurrent
Non Wage Recurrent
GRAND TOTAL
577,252
921,567
1,498,819
413,868
560,768
974,637
743,494
1,046,567
1,790,061
Annual Workplan for 2014/15 - Outputs, Activities, Inputs and their Cost
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
Budget Framework Paper (BFP), Budget Estimates, Backgroud to the
Budget chapter, Public Investment Plan (PIP), Performance Plans
submitted to MoFPED.
Ministerial Policy Statement (MPS) submitted to Parliament, progress
Reports coordinated and submitted to OPM.
Undertake a study to set up 4 Regional mines offices
-Hold workshops with stakeholders on the BFP for 2015/16
Prepare the Ministry’s Budget
Framework Paper (BFP) for the F/Y
2015/16.
Prepare the Ministry’s draft Budget
Estimates for the F/Y 2015/16.
Prepare the Annual Performance
Plan (APP); and Quarterly
Performance Plan (QPP) FY 2015/16
Update project profiles for FY
2015/16.
Procurement of a consultant to undertake the fesasibility study, prepare a
RAP for
Land acquisition
-Surveying
-Compensation
-Building designs
Planning, Budgeting and monitoring014903
Wage Recurrent
Non Wage Recurrent
Total
743,494
159,000
902,494
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
oils and lubricants (number) 2,638.6 9,499
Staff Allowances (number) 144.3 15,869
stationery (number) 500.0 10,000
Toners for Photocopiers (number) 17.0 17,000
Travel inland expenses (number) 4.0 24,000
vehicle mentainance (number) 20.0 20,000
Binding materials (number cartons) 100.0 3,000
telecom services (number of times) 3.9 15,632
Small office IT items (Numbers) 20.0 36,000
workshop items (numbers) 2.0 8,000
Permanent Staff (Person Years) 96.0 743,494
Approved Departments’ payments processed.
Financial Management Function Executed
NTR Collected, receipted & reconciled off
Finance Management and Procurement024903
Planned Outputs:
Output:
Inputs Quantity Cost
allowances (number) 112.5 12,378
Binding materials (number) 10.0 4,000
Lubricants and oils (number) 4,444.4 16,000
Maintainance of equipment (number) 4.2 4,150
Stationery (number) 400.0 8,000
Vote Overview
149
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Policy, Planning and Support Services03 49
Programme 01 Headquarters
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
Payment records documented and filed
Financial Reports /statements prepared & submitted to Accountant General
Responses to Audit queries prepared.
Gross Tax Payments processed.
All approved payments processed within 48hours
Adjustments for salaries ,allowances and arrears on the payroll accurately
effected and submitted toMinistry of public service on time
Payment documents filed ,marked ,sorted for annual audits
Wage Recurrent
Non Wage Recurrent
Total
0
92,000
92,000
Activities to Deliver Outputs:
telecom services (number) 4.0 17,847
Toners (number) 8.0 8,000
Travel and perdiem costs (number) 127.3 14,000
workshop items (number) 3.1 7,625
Monthly Procurement Reports prepared and submitted to PPDA
Procurement Submissions made to the Contracts committee
Solicitation and Contract documents prepared
Aggregated procurement and disposal plan for the Ministry prepared
Prequalification list of providers updated
An up-to-date MEMD fixed assets register
MEMD obselete property boarded-off
Well maintained offices/furniture and equipment
Stationery, equipment and office consumable available in offices
Monthly Procurement Reports prepared by the 15th day of the following
month
Procurement Submissions made to the Contracts committee
Solicitation and Contract documents prepared
Aggregated procurement plan for the Ministry prepared during the BFP
Prequalification list of providers updated regularly
An up-to-date MEMD fixed assets register quarterly
Undertake to anually dispose off the MEMD obselete assets
Continue to maintain offices/furniture and equipment
To conduct market survey for the most commonly used items.
Procurement & maintainance of assets and stores034903
Wage Recurrent
Non Wage Recurrent
Total
0
105,000
105,000
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
General repairs & maintenance () 10.0 10,000
Perdiems and allowances (days) 50.0 5,000
Airtickets and perdiems (number) 10.0 35,000
binding materials (number) 10.0 1,000
small office items (number) 20.0 20,000
staff quarterly allowances (number) 17.5 14,000
Stationery (number) 400.0 8,000
Toners (number) 10.0 8,000
news papers (numbers) 500.0 1,000
maintenance of assets (times) 10.0 3,000
Statistical Coordination and Management044903Output:
Vote Overview
150
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Policy, Planning and Support Services03 49
Programme 01 Headquarters
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
Sector Strategic Plan for Statistics implemented.
-Monitor, evaluate and dessiminate statistical data
-compile ,produce and distribute the quarterly statitical bulletin
-Hold statistics committee meetings
-Update meta data sheet
Wage Recurrent
Non Wage Recurrent
Total
0
51,000
51,000
Activities to Deliver Outputs:
Planned Outputs: Inputs Quantity Cost
Allowances to staff (number) 100.0 12,000
Stationery (number) 250.0 5,000
Toners (number) 10.0 5,000
Binding services and materials (number of times) 50.0 5,000
Perdiems and allownces (numbers) 125.0 15,000
Workshop materials (times) 2.0 9,000
Staff recruitment undertaken.
Salaries paid.
Performance Management monitored.
Staff annual performance review workshop
Human Resource development/training coordinated.
Monitor and evaluate the implementation of the Client Charter
Department Service Delivery Standards developed, implemented and
monitored.
Gender mainstreaming in Human Resource Management implemented.
Disciplinary action against errant Officers undertaken.
Manpower analysis and staffing undertaken.
Public Service Commission decisions implemented
Staff welfare managed.
HIV/AIDS work place policy implemented.
Mail received, sorted, classified, filed, dispatched and delivered to their
final destinations.
Records Centre in GSMD set up
Records retention and disposal schedule for the ministry dissemniated
Records management procedures streamliened
All personnel files updated with the required basic records
Staff recruitment.
Salaries paid.
Performance Management monitoring.
Hold Staff annual performance review workshop
Complete the development of the training policy and plan.
Continue Monitoring and evaluating the implementation of the Client
Charter
Impliment the Gender mainstreaming in Human Resource Management.
Management of Human Resource054903
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
IPPS Recurrent Costs () 4.0 25,000
dispatch of courier and stamps (number) 40.0 4,000
Fuel and oils and lubricants (number) 2,500.0 10,000
gender main streaming workshops (number) 4.0 20,000
Hire of printing services for the training policy
(number)
1,000.0 30,000
hosting World AIDS Day (number) 1.0 30,000
maintaance of vehicles (number) 4.0 10,000
printing of records retention and disposal schedul
(number)
350.0 7,000
Supply of computer related items (number) 8.0 4,000
workshop induction and orientation materials
(number)
2.0 7,567
Small office items (number items) 100.0 5,000
Allowances to staff (numbers) 100.0 12,000
Vote Overview
151
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Policy, Planning and Support Services03 49
Programme 01 Headquarters
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
Undertake Disciplinary action against errant Officers.
Conduct Manpower analysis and staffing.
Public Service Commission decisions implemented
management of Staff welfare.
Continue to implement the HIV/AIDS work place policy.
Strengethen the security and open registry
Records Centre in GSMD set up
Records retention and disposal schedule for the ministry dissemniated
Records management procedures streamliened
All personnel files updated with the required basic records
Wage Recurrent
Non Wage Recurrent
Total
0
164,567
164,567
Connect all work stations in the ministry to internet
Servicing of all desktop computers and printers under F&A.
Intercom connection for offices that are lacking.
Website maintenance.
Organize a retreat/workshop to discuss the draft copy of the
IT/Information systems policy
Re-organize/give a facelift to the resource center
7.0 Tracking the cables in the IFMS server room
8.0 Newspapers for the resource center, and stationery
Extend the structured Cabling to network all new work stations.
Servicing of all ICT Equipment (Acs, computers ,Photocopiers and
printers under F&A.
Intercom connection for offices that are lacking.
Website maintenance.
Organize 4 ICT training and sensitization workshops, to equip staff with
ICT skills
Re-organize/give a facelift to the resource center
Management of Policy Issues, Public Relation, ICT and Electricity disputes resolved064903
Wage Recurrent
Non Wage Recurrent
Total
0
275,000
275,000
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
computer hardware and drives (items) 36.2 18,110
Binding materials (number) 20.0 10,000
Fuels ,Lubricants and oils (number) 12,500.0 50,000
General allowances (number) 200.0 20,000
General vehicle maintainance (number) 329.8 32,980
News papers & magazines (number) 14,955.0 29,910
POSTAGE Services (number) 4.0 18,000
Small items and equipment (number) 30.0 15,000
telecom services for EDT and AEC paid (number) 4.0 48,000
Toners for photocopying (number) 20.0 20,000
Assorted stationers (numbers) -250.0 -5,000
Entertainment General (times) 4.5 18,000
Arrears994903
Activities to Deliver Outputs:
Planned Outputs:
Output:
Vote Overview
152
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Policy, Planning and Support Services03 49
Programme 01 Headquarters
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
Wage Recurrent
Non Wage Recurrent
Total
0
200,000
200,000
Wage Recurrent
Non Wage Recurrent
GRAND TOTAL
743,494
1,046,567
1,790,061
Vote Overview
153
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Policy, Planning and Support Services03 49
Programme 06 Directorate
Workplan Outputs for 2013/14 and 2014/15
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
Implementation of policies
coordinated and supervised.
Coordinate and supervise all
technical activities
Coordinate and supervise the
production of the Budget
Framework Paper (BFP),
Budget Estimates, Backgroud to
the Budget chapter, Public
Investment Plan (PIP),
Performance Plans.
Coordinate and supervise the
preparation of the Ministerial
Policy Statement (MPS),
Progress Reports.
Spearhead the production of the
Annual Report 2012.
Implementation of policies
coordinated and supervised.
Coordinating and supervising all
technical activities
Coordinating and supervising
the production of the Budget
Framework Paper (BFP),
Budget Estimates, Backgroud to
the Budget chapter, Public
Investment Plan (PIP),
Performance Plans.
Continued to Coordinate and
supervise the preparation of the
Ministerial Policy Statement
(MPS), Progress Reports.
Contiuned to spearhead the
production of the Annual
Report 2013.
Planning, Budgeting and
monitoring
Implementation of policies
coordinated and supervised.
Coordinate and supervise all
technical activities
Coordinate and supervise the
production of the Budget
Framework Paper (BFP),
Budget Estimates, Backgroud to
the Budget chapter, Public
Investment Plan (PIP),
Performance Plans.
Coordinate and supervise the
preparation of the Ministerial
Policy Statement (MPS),
Progress Reports.
Spearhead the production of the
Annual Report 2013.
014903
Wage Recurrent
Non Wage Recurrent
Total
356,825
160,474
517,299
236,297
86,447
322,744
56,879
160,474
217,353
Wage Recurrent
Non Wage Recurrent
GRAND TOTAL
356,825
160,474
517,299
236,297
86,447
322,744
56,879
160,474
217,353
Director Energy and Mineral Development
- To coordinate and supervise technical departments in the Energy and Mineral Sector
This is under vote function 49: Policy, Planning and Support Services. It guides the policy
formulation, implementation, and also responsible for the planning, budgeting and policy
analysis and administrative functions
Responsible Officer:
Objectives:
Outputs:
Programme Profile
Annual Workplan for 2014/15 - Outputs, Activities, Inputs and their Cost
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
Implementation of policies coordinated and supervised.
Coordinate and supervise all technical activities
Coordinate and supervise the production of the Budget Framework Paper
(BFP), Budget Estimates, Backgroud to the Budget chapter, Public
Investment Plan (PIP), Performance Plans.
Coordinate and supervise the preparation of the Ministerial Policy
Statement (MPS), Progress Reports.
Spearhead the production of the Annual Report 2013.
Supervise the Implementation and o coordination of policies.
Planning, Budgeting and monitoring014903
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Airtickets and Accomodation (number) 10.0 38,000
Airtime (Number) 273.7 5,474
Binding Materials (number) 4.0 1,000
computer accessories (number) 10.0 10,000
fuel (number) 4,000.0 16,000
Lubricants (number) 1,000.0 10,000
new papers and magazines (number) 1,000.0 5,000
oils (number) 500.0 4,000
perdiems and accomodation (number) 100.0 20,000
Servicing motorvehicles (number) 20.0 20,000
Small Office Equipment (number) 25.0 10,000
staff allowances (number) 100.0 12,000
stationery (number) 200.0 4,000
Vote Overview
154
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Policy, Planning and Support Services03 49
Programme 06 Directorate
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
Coordinate and supervise all technical activities
Coordinate and supervise the production of the Budget Framework Paper
(BFP), Budget Estimates, Backgroud to the Budget chapter, Public
Investment Plan (PIP), Performance Plans.
Wage Recurrent
Non Wage Recurrent
Total
56,879
160,474
217,353
Toners (number) 10.0 5,000
Permanent Staff (Person Years) 4.0 56,879
Wage Recurrent
Non Wage Recurrent
GRAND TOTAL
56,879
160,474
217,353
Vote Overview
155
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Policy, Planning and Support Services03 49
Programme 08 Internal Audit Department
Workplan Outputs for 2013/14 and 2014/15
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
Audit Plan for FY2013/14 on
Budget Implementation and
Performance prepared.
Projects implemented in
accordance to PAD, MOU and
Financing Agreements.
Performance Report on
Agencies prepared
Audit Plan for FY2013/14 on
Budget Implementation and
Performance.
Implemented Projects in
accordance to PAD, MOU and
Financing Agreements.
Performance Report on
Agencies.
Planning, Budgeting and
monitoring
Audit Plan for FY2014/15 on
Budget Implementation and
Performance prepared.
Ensure that Projects are
implemented in accordance to
PAD, MOU and Financing
Agreements.
Performance Audit Report on
Agencies prepared
014903
Wage Recurrent
Non Wage Recurrent
Total
0
124,201
124,201
0
85,848
85,848
0
124,201
124,201
Audit Report on disbursement
and accountability of public
funds.
Audit Report on accountability
of advances.
Audit Reporting on
disbursement and accountability
of public funds.
Continue to audit Report on
accountability of advances.
Finance Management and
Procurement
Audit Report on disbursement
and accountability of public
funds.
Audit Report on accountability
of advances.
Internal Audit report on Non
Tax Revenue
Internal auditing on Entity's risk
management, Internal control
systems , financial statements
and compliance to Government
process
Internal Audit report on special
investigations
024903
Wage Recurrent
Non Wage Recurrent
Total
0
35,812
35,812
0
23,221
23,221
0
35,812
35,812
Audit Report on procurement of
goods and services
Audit report on stores and
Inventories
Continue to audit Report on
procurement of goods and
services
Continue to audit report on
stores and Inventories
Procurement &
maintainance of assets and
stores
Audit Report on procurement of
goods and services
Audit report on stores and
Inventories
034903
Wage Recurrent
Non Wage Recurrent
Total
0
38,640
38,640
0
31,340
31,340
0
38,640
38,640
Pay Roll Audit Report prepared Pay Roll Audit Report preparedManagement of Human
Resource
Pay Roll Audit Report prepared054903
Wage Recurrent
Total
0
10,000
0
7,583
0
10,000
Principal Internal Auditor
The Internal Audit Unit shall appraise the soundness and application of accounting, Financial
and Operational Controls and in particular shall;•Review and report on controls over
utilization of Financial Resources•Review and Report on compliance
The Internal Audit function is mandated to carry out several quarterly systems audits, Value
for Money, Fraud investigations, IT audits, and other assurance engagements on Donor funds
and Government of Uganda funds for the Ministry.
Responsible Officer:
Objectives:
Outputs:
Programme Profile
Vote Overview
156
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Policy, Planning and Support Services03 49
Programme 08 Internal Audit Department
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
Non Wage Recurrent 10,000 7,583 10,000
Wage Recurrent
Non Wage Recurrent
GRAND TOTAL
0
208,653
208,653
0
147,992
147,992
0
208,653
208,653
Annual Workplan for 2014/15 - Outputs, Activities, Inputs and their Cost
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
Audit Plan for FY2014/15 on Budget Implementation and Performance
prepared.
Ensure that Projects are implemented in accordance to PAD, MOU and
Financing Agreements.
Performance Audit Report on Agencies prepared
Gathering back ground information
-Interviewing staff.
-Recording data
-Drafting the audit plan
-Discussing the audit plan with the Audit Committee for approval
-Inspection of project sites.
_Investigating all complaints about the project
-Checking on value for money
-Check on compliance to terms of contract
-Follow up on accountability of funds.
-Monitor performance reports
Planning, Budgeting and monitoring014903
Wage Recurrent
Non Wage Recurrent
Total
0
124,201
124,201
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Airtickets and accomodation (number) 4.0 30,000
Binding materials (number) 20.0 2,000
computer accessories and items (number) 10.0 10,000
newspapers & magazines (number) 400.0 2,000
Perdiems and fuel (number) 200.0 40,000
small office items (number) 50.0 15,000
Vehicle maintainance (number) 20.0 10,000
Airtime and telecom exp (numbers) 213.4 3,201
Stationery assorted (numbers) 400.0 8,000
Toners for copiers (numbers) 8.0 4,000
Audit Report on disbursement and accountability of public funds.
Audit Report on accountability of advances.
Internal Audit report on Non Tax Revenue
Internal auditing on Entity's risk management, Internal control systems ,
financial statements and compliance to Government process
Internal Audit report on special investigations
-Follow up on issues raised.
-Check on accountability.
-Check on value for money.
-Review systems of generating financial information and data.
-Conduct systems audit to ascertain whether or not internal controls are
appropriate.
-Conduct risk management audit
-Inspection of all mining sites in the Country
-Review of reconciliation of NTR Collected and assessed.
Finance Management and Procurement024903
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Airtime (number) 4.0 2,500
Office fuel (number) 1,250.0 5,000
perdiems and accomodations (number) 40.0 20,000
servicing of vehicles (number) 4.0 4,000
stationery and materials (numbers) 4.0 4,312
Vote Overview
157
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Policy, Planning and Support Services03 49
Programme 08 Internal Audit Department
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
-Matching of all banking against the assessed amount.
-Inspecting firms licensed for exploration and minings
Wage Recurrent
Non Wage Recurrent
Total
0
35,812
35,812
Audit Report on procurement of goods and services
Audit report on stores and Inventories
Inspect stores
-check what is delivered in stores against purchases made.
-check on pilferages in stores.
-Conduct inventory counts in stores.
-Field inspections of all assets
-checking on all assets records and conditions of assets.
Review utilization of assets.
Procurement & maintainance of assets and stores034903
Wage Recurrent
Non Wage Recurrent
Total
0
38,640
38,640
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
assorted stationery and photocopying (number) 4.0 4,000
perdiems and accomodation (number) 93.2 18,640
Training of staff (number) 2.0 16,000
Pay Roll Audit Report prepared
-Physical count of staff versus the salaries paid.
-Review the recruitment process of staff.
-Review Staff training programmes and value for money.
-Review staff Appraissal files
Management of Human Resource054903
Wage Recurrent
Non Wage Recurrent
Total
0
10,000
10,000
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
perdiems and accomodation (number) 50.0 10,000
Wage Recurrent
Non Wage Recurrent
GRAND TOTAL
0
208,653
208,653
Vote Overview
158
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Policy, Planning and Support Services03 49
Project 1223 Institutional Support to Ministry of Energy and Mineral Development
Workplan Outputs for 2013/14 and 2014/15
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
Finalise the development of an
Energy and Mineral
Development Monitoring
Framework and Tool.
Non Tax Revenue generating
sites Inspected and advocacy
areas undertaken.
Final draft for the Energy and
Mineral Development
Monitoring Framework and
Tool was submitted by the
consultant for review
Non Tax Revenue generating
sites Inspected in Hima in
Kasese and Muko in Kabale
Planning, Budgeting and
monitoring
The Energy and Mineral
Development Monitoring and
Evaluation tool automated.
Non Tax Revenue generating
sites Inspected and advocacy
undertaken.
014903
GoU Development
External Financing
Total
309,348
0
309,348
287,343
0
287,343
309,348
0
309,348
Sector Strategic Plan for
Statistics (SSPS) updated and
implmented.
Energy and Mineral Statistical
Metadata sheet populated.
Sector Data base in place
Sector Strategic Plan for
Statistics (SSPS) was
developed, discussed with
UBOS for approval.
Energy and Mineral Statistical
Metadata sheet and the Data
Base were populated and
Statistical Coordination
and Management
Data collection guidelines
developed
A comperehensice databank for
EMD Sector developed.
Energy and Mineral Statistical
Metadata sheet updated.
044903
Under Secretary, Finance and Administration
(i) To put in place an effective and efficient coordination, planning and monitoring
mechanism in the Energy and Mineral sector.
(ii) To institutionalize a mechanism for the routine replacement and retooling of the
facilities of the Ministry
(iii) To revitalize the Ministry Departments and Agencies to undertake the ministerial roles
and functions, particularly regulation, supervision, monitoring and evaluation
(iv) To institutionalize the prior development of feasibility studies and plans for sectoral
projects in power generation and transmission, oil and gas development and mineral ores
extraction.
(v) Build a reliable information system to inform decision making in the sector
(vi) To develop a Ministerial Administrative Facility
(vii) Re-design and build the Local Area Network (LAN)
(i) Sector Investment Plan developed
(ii) Feasibility studies and plans for sectoral projects developed.
(iii) Renovation of Amber house
(iv) Development of Amber house adjacent plot
(v) Development of the Nuclear Energy Roadmap
(vi) Specialized equipment for laboratory infrastructure
(vii) Capital items for technical functions in M&E including vehicles, office equipment,
field equipment procured.
(viii) Collect, process, analyze and disseminate national and international information
hence providing vital input necessary to improve national decision making.
(ix) Promote and co-ordinate the research activities and initiatives of the sector with a
view to ensure that results are utilized and are beneficial to the country and all stakeholders.
(x) Fleet Management Plan developed
(xi) Communication Strategy and Plan developed.
(xii) Ministry’s Intranet re-designed
Responsible Officer:
Objectives:
Outputs:
7/2/2012 6/30/2015Start Date: Projected End Date:
Project Profile
Vote Overview
159
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Policy, Planning and Support Services03 49
Project 1223 Institutional Support to Ministry of Energy and Mineral Development
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
database in place.
2012 Statistical Abstract
compiled out of the database.
Sector Data base updated
GoU Development
External Financing
Total
100,000
0
100,000
100,049
0
100,049
100,000
0
100,000
Support to: Atomic Energy
Council; Electricity Disputes
Tribunal; Nuclear Energy
Roadmap Development
Funds were provided as support
to: Atomic Energy Council;
Electricity Disputes Tribunal;
Nuclear Energy Roadmap
Development; UEDCL
(Complete Kyanamukaka-
Lwankoni - Nabyajwe rural
electrification line)
Management of Policy
Issues, Public Relation,
ICT and Electricity
disputes resolved
Strategy, Manual and
Guidelines for Environment
mainstreaming developed
Management of Amber house
Support to:
- Atomic Energy Council;
- Electricity Disputes Tribunal;
- Nuclear Energy Roadmap
Development;
- UEDCL on phase II
electrification schemes of:
i) Kyesiiga- Kyanamukaka;
Kyambazi - Kyantale; Mlembo
Landing site and environs.
Ii) Jesa - Kamuli -Kyesengenze
LC I (Mityana District).
064903
GoU Development
External Financing
Total
7,400,000
0
7,400,000
5,532,902
0
5,532,902
12,600,000
0
12,600,000
- Retooling of Offices at Amber
house
- Complete redesign and
implementation Voice and data
infrastructure
- Secure laboratory
infrastructure at GSMD
Office Improvement: Remedial
renovation of the Amber house
basement to repair the leaking
roofs and sewage system was
undertaken.
Voice and data infrastructure:
Phase I of the redesign voice
and data infrastructure
(Structured Cabling) was
completed. Testing of the
installations was successful.
Commissioning awaits the
completion of Phase II, whose
procurement has been
concluded. Phase I involved
redesign and structured cabling
of the data infrastructure. Phase
II will involve installation of a
centralized power supply
system.
Procured office furniture and
fixtures for various offices;
fittings filing cabinets and
equipment for records centre.
Procurement for further
remedial renovation, furnishing
of 50 offices used by MEMD,
and installation of air
conditioning systems was
concluded.
Undertook remedial renovation
of offices at Amber house.
Government Buildings and
Administrative
Infrastructure
- Comprehensively renovate and
manage Amber House and
commence development process
of the adjacent plot
724903
Vote Overview
160
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Policy, Planning and Support Services03 49
Project 1223 Institutional Support to Ministry of Energy and Mineral Development
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
Procurement of consultant for
phase 2 of the redesign voice
and data infrastructure was
concluded
GoU Development
External Financing
Total
3,725,965
0
3,725,965
265,597
0
265,597
3,025,965
0
3,025,965
Output-Data Recovery Plan
developed
ICT and Resource Centre
equiped
Procure and maintain internet
server system
Internet services maintained
Probox interchange system
Completed drafting the ToR for
Consultancy services for the
output-data recovery plan
Commenced the procurement to
equip the ICT and Resource
Centre.
Procurement of consultancy
services for the output-data
recovery plan was initiated.
Procured ten (10) Computers
and IT
Equipment - LAN Infrastructure.
Procured a server system and
accessories.
Internet maintain maintained
Purchase of Office and
ICT Equipment,
including Software
- Complete the development of
a disaster recovery solution for
the Ministry
- Complete Phase II of the
redesign and implementation of
Voice and data infrastructure
- Resource Centre equipped
- Internet services (WiFi)
procured and maintained
- Procure a consultancy to
develop an information system
for the Ministry
- Computer peripherals/
hardware and sofwares/
licencing procured
- Computer equipment serviced
764903
GoU Development
External Financing
Total
1,900,000
0
1,900,000
1,249,420
0
1,249,420
1,000,000
0
1,000,000
Equiping and retooling of the
Mineral laboratory
The Procurment process for the
laboratory mineral testing
equipment is still on going.
The procurement process to
secure a mineral laboratory
storage facility to mitigate theft
is still on going
Purchase of Specialised
Machinery & Equipment
Implement phase II of
Equipping and retooling the
GSMD Mineral Laboratory
Infrastructure
774903
GoU Development
External Financing
Total
600,000
0
600,000
307,889
0
307,889
1,000,000
0
1,000,000
Purchase of Office and
Residential Furniture and
Fittings
Procurement of office furniture
and fittings for the FA
784903
GoU Development
External Financing
Total
0
0
0
0
0
0
400,000
0
400,000
- Continue with Feasibility
Studies for Rwimi/Nyamba
Hydro Power Plant
- Complete the development of
the Energy and Mineral Invester
Master Plan
Negotiation with the Consultant
for the Feasibility Studies for
Rwimi/Nyamba Hydro Power
Plant was ongoing.
Continued with the
development of the Energy and
Mineral Investement Master
Plan
Acquisition of Other
Capital Assets
Complete the Feasibility
Studies for Rwimi/Nyamba
Hydro Power Plant
794903
GoU Development
External Financing
Total
3,840,415
0
3,840,415
3,561,793
0
3,561,793
1,440,415
0
1,440,415
Vote Overview
161
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Policy, Planning and Support Services03 49
Project 1223 Institutional Support to Ministry of Energy and Mineral Development
GoU Development
External Financing
GRAND TOTAL
17,875,728
0
17,875,728
11,304,993
0
11,304,993
19,875,728
0
19,875,728
Annual Workplan for 2014/15 - Outputs, Activities, Inputs and their Cost
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
The Energy and Mineral Development Monitoring and Evaluation tool
automated.
Non Tax Revenue generating sites Inspected and advocacy undertaken.
Automation of the energy and mineral development monitoring tool.
Inspection of non-tax revenue generating sites and advocacy areas.
Continue monitoring areas generating non tax revenue (petroleum and
mining sites)
Planning, Budgeting and monitoring014903
GoU Development
External Financing
Total
309,348
0
309,348
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Advertisement for Consultancy services (Adverts) 4.0 10,000
Airtickets and accomodation (number) 1.7 30,000
Fuel and oils (number) 7,750.0 31,000
General allowances to staff (number) 48.3 12,073
Perdiem and accomodations (number) 48.0 24,000
Printing and binding services (number) 300.0 18,000
servicing of fixtures and equipment (number) 13.3 10,000
small office items for EDT ,AEC,MEMD
(NUMBER)
48.0 48,000
Stationery (number) 500.0 10,000
Toners photocopying for EDT AEC,MEMD,
&Projects (number)
20.0 20,000
workshop items and materials (number) 2.0 6,275
servicing of vehicles (number times) 20.0 20,000
Consultancy to Automate Monitoring Framework
(Report)
1.0 70,000
Data collection guidelines developed
A comperehensice databank for EMD Sector developed.
Energy and Mineral Statistical Metadata sheet updated.
Sector Data base updated
Develop data collection guidelines
Develop and manitain a comperehensice databank for EMD Sector.
Energy and Mineral Statistical Metadata sheet updated.
Populating sector database.
Statistical Coordination and Management044903
GoU Development
External Financing
Total
100,000
0
100,000
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Fuels for various project offices (number) 4,500.0 18,000
office items for offices at AEC,EDT,AMBER
(number)
40.0 20,000
Perdiems and accomodation (number) 100.0 25,000
servicing and repairs of vehicles (number) 25.0 25,000
Allowances to staff (number of staff) 100.0 12,000
Strategy, Manual and Guidelines for Environment mainstreaming
developed
Management of Amber house
Support to:
- Atomic Energy Council;
- Electricity Disputes Tribunal;
Management of Policy Issues, Public Relation, ICT and Electricity disputes resolved064903
Planned Outputs:
Output:
Inputs Quantity Cost
Cleaning services () 4.0 300,000
Electricity payment () 400.0 400,000
Security services () 4.0 300,000
Transfer to AEC () 4.0 1,500,000
Transfer to UEDCL () 7.4 6,500,000
water payment () 4.0 400,000
Support to EDT (Reports) 2.0 1,000,000
Support to NEU (Reports) 4.4 2,200,000
Vote Overview
162
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Vote Function: Policy, Planning and Support Services03 49
Project 1223 Institutional Support to Ministry of Energy and Mineral Development
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
- Nuclear Energy Roadmap Development;
- UEDCL on phase II electrification schemes of:
i) Kyesiiga- Kyanamukaka; Kyambazi - Kyantale; Mlembo Landing site
and environs.
Ii) Jesa - Kamuli -Kyesengenze LC I (Mityana District).
Strategy, Manual and Guidelines for Environment mainstreaming
developed
Management of Amber house
Continue to Support:
- Atomic Energy Council: Pre-feasibility studies for launching the first
nuclear power plant completed; Capacity for planning and managing
nuclear power projects built; Consultation on nuclear power
infrastructure development conducted; Development of nuclear fuel
supply strategy initiated; Nuclear Information Centre established.
- Electricity Disputes Tribunal;
- Nuclear Energy Roadmap Development;
- UEDCL on phase II electrification schemes of:
i) Kyesiiga- Kyanamukaka; Kyambazi - Kyantale; Mlembo Landing site
and environs.
Ii) Jesa - Kamuli -Kyesengenze LC I (Mityana District).
GoU Development
External Financing
Total
12,600,000
0
12,600,000
Activities to Deliver Outputs:
- Comprehensively renovate and manage Amber House and commence
development process of the adjacent plot
- Procure a consultant to comprehensively study the retooling of Offices at
Amber house and development of the adjacent plot
Government Buildings and Administrative Infrastructure724903
GoU Development
External Financing
Total
3,025,965
0
3,025,965
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Consultancy to design and retool amber house
(number)
1.0 2,125,965
Supervision of capital assets (Reports) 4.0 1,000,000
- Complete the development of a disaster recovery solution for the
Ministry
- Complete Phase II of the redesign and implementation of Voice and
data infrastructure
- Resource Centre equipped
- Internet services (WiFi) procured and maintained
- Procure a consultancy to develop an information system for the Ministry
- Computer peripherals/ hardware and sofwares/ licencing procured
- Computer equipment serviced
Purchase of Office and ICT Equipment, including Software764903
Planned Outputs:
Output:
Inputs Quantity Cost
Computer ICT Equipments and software (number) 0.6 1,000,000
Vote Overview
163
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Table V3.2: Past and Medum Term Key Vote Output Indicators*
2016/172012/13
Outturn
Releases
Prel. Actual
Approved
Plan 2014/15 2015/16
MTEF Projections2013/14
Vote Function Key Output
Indicators and Costs:
Vote Function: Policy, Planning and Support Services03 49
Project 1223 Institutional Support to Ministry of Energy and Mineral Development
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
- Development of the disaster recovery solution for the Ministry
- Equip the ICT unit, sector planning unit, PDU, Personnel unit and
Resource Centre
- Laying of new cables both for voice, data and electricals; Intercom
handsets, interface cards, new LAN switches
- Procure a consultancy to develop an information system for the Ministry
- Procure Computer peripherals/ hardware and sofwares/ licencing
- Computer equipment serviced
- Training on new ICT approaches
GoU Development
External Financing
Total
1,000,000
0
1,000,000
Activities to Deliver Outputs:
Implement phase II of Equipping and retooling the GSMD Mineral
Laboratory Infrastructure
Continue equiping and retooling of the Mineral laboratory and to
complete installation of various equipment
Purchase of Specialised Machinery & Equipment774903
GoU Development
External Financing
Total
1,000,000
0
1,000,000
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Specialised machinery (Number) 2.0 300,000
Specialized Equipment for Labs (Number) 1,000.0 400,000
Training Equipment (Number) 10.0 100,000
Supervision of capital assets (reports) 2,000.0 200,000
Procurement of office furniture and fittings for the FA
Procurement of office furniture and fittings for the FA
Purchase of Office and Residential Furniture and Fittings784903
GoU Development
External Financing
Total
400,000
0
400,000
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
Executive desks for Office furniture and fixtures
(Number)
80.0 400,000
Complete the Feasibility Studies for Rwimi/Nyamba Hydro Power Plant
Complete the Feasibility Studies for Rwimi/Nyamba Hydro Power Plant
Acquisition of Other Capital Assets794903
GoU Development
External Financing
Total
1,440,415
0
1,440,415
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
consultancy studies for Rwimi &Nyamba (Number) 1.0 1,240,415
Suprevison of capital works (Reports) 10.0 200,000
GoU Development
External Financing
GRAND TOTAL
19,875,728
0
19,875,728
Vote Overview
164
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Medium Term Plans
* Excluding Taxes and Arrears
2016/172012/13
Outturn
Releases
Prel. Actual
Approved
Plan 2014/15 2015/16Vote Function Key Output
Indicators and Costs:
Vote: 017 Ministry of Energy and Mineral Development
Vote Function:0301 Energy Planning,Management & Infrastructure Dev't
566.165 270.234 207.554Vote Function Cost (UShs bn) 454.195 61.26084.187
110.566 N/A N/A102.867 61.26084.187VF Cost Excluding Ext. Fin
Percentage oAudited firms
implementing Energy efficiency
measures
N/A No info 75 100 100N/A
Number of sites demonstrating use
of improved energy technologies
N/A No info 10 10 10N/A
Number of prepaid meters installed N/A No info 100,000 175000 173000N/A
Stage of development of
Nyamwamba HPP
N/A No info Implementatio
n Agreement
executed
N/A
Number of line KM of MV (33KV)
constructed
N/A No info 3262 3500 3500N/A
Number of line KM of LV (11KV)
constructed
N/A No info 2954 3000 3000N/A
Number of District Headquaters
electrified
10 15 6 8N/A
Number of Solar systems installed N/A No info 14000 20000 20000N/A
Vote Function:0302 Large Hydro power infrastructure
1,096.900 1,023.235 1,109.997Vote Function Cost (UShs bn) 1,093.245 32.2730.000
1,096.900 N/A N/A1,091.900 32.2730.000VF Cost Excluding Ext. Fin
Vote Function:0303 Petroleum Exploration, Development & Production
68.013 65.744 55.885Vote Function Cost (UShs bn) 68.733 38.73722.034
55.013 N/A N/A54.414 38.73722.034VF Cost Excluding Ext. Fin
Number of line Km of seismic data
acquired.
N/A No info 800N/A
Level of compliance by exploration
companies with petroleum
operations guidelines
N/A No info 100N/A
Vote Function:0304 Petroleum Supply, Infrastructure and Regulation
14.057 28.607 26.081Vote Function Cost (UShs bn) 6.245 3.4111.057
6.245 3.4111.057VF Cost Excluding Ext. Fin
% of the facilities confirming to the
Petroleum facilities standards
N/A No info 55 75 100N/A
Vote Function:0305 Mineral Exploration, Development & Production
8.684 80.872 29.087Vote Function Cost (UShs bn) 8.038 4.6461.922
8.038 4.6461.922VF Cost Excluding Ext. Fin
Number of Mineral analysis
techniques developed to ISO
standards
N/A No info 2 2 2N/A
Number of Mineral Artisans and
small scale miners (ASM) trained in
Mining Districts
N/A No info 570 300 300N/A
Number of mineralized areas
discovered
N/A No info 3 3 3N/A
Number of potential Uranium
resources targets discovered
N/A No info 2 2 2N/A
Number of flagships projects
monitered
N/A No info 2 2 2N/A
Number of mining site inspectiog
conducted
N/A No info 15 24 24N/A
Vote Function:0349 Policy, Planning and Support Services
21.892 21.068 26.468Vote Function Cost (UShs bn) 20.100 14.3217.513
20.100 14.3217.513VF Cost Excluding Ext. Fin
1,775.710 1,489.760 1,455.072Cost of Vote Services (UShs Bn) 1,650.557 154.647116.714
1,775.710 N/A N/A1,283.565 154.647116.714Vote Cost Excluding Ext Fin.
Vote Overview
165
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
ENERGY PLANNING, MANAGEMENT & INFRASTRUCTURE DEVELOPMENT:
(i) Construction of Karuma Hydropower Project (600 MW) continued.
(ii) Construction of Isimba hydro power project (188MW) completed.
(iii) Commence the construction of Ayago (600MW) Hydropower Project.
PETROLEUM EXPLORATION, DEVELOPMENT AND PRODUCTION
The sector will continue to implement the oil and gas policy over the medium term, through undertaking the
following:-
(i) Promote the Country’s petroleum potential and undertake a licensing round for the unlicensed
acreage in the country;
(ii) Develop and commission a 60,000bopd refinery in the country;
(iii) Develop transport and storage infrastructure for petroleum and petroleum products in the country;
(iv) Facilitate the development of infrastructure for the export of crude oil;
(v) Coordinate the implementation of the oil and gas regulations in the sector;
(vi) Build capacity of the Oil and Gas sector in the country;
(vii) Monitor and regulate the upstream petroleum activities;
(viii) Continue the implementation a communication strategy for the Oil and Gas sector in the country;
(ix) Participate in Regional initiatives related to the oil and gas sector.
PETROLEUM SUPPLY, INFRASTRUCTURE AND REGULATION
(i) Development and stocking fuel strategic reserves.
(ii) Management and Monitoring of petroleum supply and marketing industry
(iii) Maintenance of National Petroleum Information System
(iv) Operational Standards and laboratory testing of petroleum products
(v) Development of an Emergency Petroleum Supply Plan
(vi) Develop the Kenya - Uganda; Kampala - Kigali oil products pipeline
MINERAL EXPLORATION, DEVELOPMENT & PRODUCTION:
(i) Provide basic geo-scientific information for the development of the mineral sector.
(ii) Promote optimal use of minerals and mineral trade for social improvement of the people.
(iii) Provide technical services in the field of geosciences.
(iv) Ensure best mining practices and accountability.
(v) Promote mineral value addition and trade to increase revenues.
(vi) Promote the gazetting of geosites and geoparks.
(vii) Put in place an earthquake adminstration policy, expand the network of operation centres, design an
earthquake disaster management plan, and equiping the research laboratories
(viii) Institutional Capacity for the Mineral sector.
POLICY, PLANNING AND SUPPORT SERVICES:
(i) Planning, Budgeting and Monitoring undertaken
(ii) Financial Management and Procurement undertaken
(iii) Procurement and maintenance of Assets and Stores
(iv) Management of Human Resources
(i) Measures to improve Efficiency
To improve the performance of vote budget allocations and achieve value for money in the oil and gas
sector a monitoring and evaluation framework has been formulated and efforts have been made to improve
the procurement plans.
Table V3.3: Key Unit Costs of Services Provided and Services Funded (Shs '000)Vote Overview
166
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017Table V3.3: Key Unit Costs of Services Provided and Services Funded (Shs '000)
Actual
2012/13
Actual
2013/14
Planned
2013/14
Proposed
2014/15
Costing Assumptions and Reasons for
any Changes and Variations from Plan
Unit Cost
Description
Vote Function:0301 Energy Planning,Management & Infrastructure Dev't
Cost per Mega Watt
hour (MWh) of thermal
generated electricity
The cost represents the energy price per
MW geerated at Aggreko Mutundwe
Plant priced at USD 160.78 per MWh,
calculated at a base price of 1US =
1980UShs (Feb 2009 prices)
Cost per kilo Watt hour
(kWh) sold by the
system operator
UETCL to the energy
distributors
The cost represents the peak hour cost of
electricity transmitted by UETCL
Cost per kilo Watt hour
(kWh) of electrcity
consumed by
households
Approved retail tariffs by the Electricity
Regulatory Authority
Vote Function:0302 Large Hydro power infrastructure
Cost per Mega Watt of
electricity produced per
hour by a large hydro
power station
Approved energy tariff for the power
generated at the Nalubaale - Kiira
operated by a concessionaire
Vote Function:0303 Petroleum Exploration, Development & Production
Number of line km of
seismic data acquired
in the Albertine Graben.
Costs incurred vary from licenced
companies and the areas of operation.
GoU only facilitates staff to carry out
monitoring.
0Drilling of one well Costs incurred vary from licenced
companies and the areas of operation.
GoU only facilitates staff to carry out
monitoring.
Vote Function:0304 Petroleum Supply, Infrastructure and Regulation
Cost of monitoring a
petroleum facility
Vote Function:0305 Mineral Exploration, Development & Production
91,00091,000 91,000 91,000Mineral analysis per
sample in international
laboratory for 51
elements
Mineral analysis per sample in
international laboratory for fifity (51)
elements. This is only the laboratory
expense excluding freigh or
transportation and data interpretation
39,00017,500 39,000Cost per line kilometre
of aeroborne
geophysical data
Resources Project 2004 - 2011 of USD
5.005 million for 632,681 line kilometres
covered; averaged USD 7.911 per line
kilometre. Global Inflation
and change in technology
Vote Overview
167
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
(ii) Vote Investment Plans
For the FY 2014/15, most resources have been earmarked for Karuma Hydro Power Project with a
budgetary allocation of Ush. 1,096.0 Bn; while Ush. 35.0 Bn is provided for the acquisition of land for
construction of the oil refinery. Development of transmission infrastructure has a budget provision of Ush.
41.6 billion largely for constracution implementation of Resettlement Action Plan for the Transmission
Lines. Government will continue to support capacity payments for thermal power generation to the tune of
Ush. 68.0 billion.
Table V3.4: Allocations by Class of Output over the Medium Term
Table V3.5: Major Capital Investments (Outputs of class Capital Purchases over 0.5Billion)
2013/14 2014/15 2015/16 2016/17
(ii) % Vote Budget
Billion Uganda Shillings
(i) Allocation (Shs Bn)
2013/14 2014/15 2015/16 2016/17
46.3 52.5 128.9 116.5 2.8% 3.0% 8.6% 7.8%Consumption Expendture(Outputs Provided)
73.4 115.5 45.4 48.1 4.4% 6.5% 3.0% 3.2%Grants and Subsidies (Outputs Funded)
1,530.9 1,607.7 1,315.8 1,328.7 92.7% 90.5% 88.3% 89.0%Investment (Capital Purchases)
Grand Total 1,650.6 1,775.7 1,490.0 1,493.3 100.0% 100.0% 100.0% 100.0%
Approved Budget, Planned
Outputs (Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
Expenditures and Outputs by
End March
(Quantity and Location)
Vote Function: Energy Planning,Management & Infrastructure Dev't0103
Project 1023 Promotion of Renewable Energy & Energy Efficiency
GoU Development
External Financingt
Total
0
0
0
0
0
0
1,292,689
21,276,170
22,568,859
Purchase of
Specialised
Machinery &
Equipment
- Ten (10) small wind energy
systems procured
-Two wind measuring
equipment procured
- Computers for wind data
procured
770103
Project 1026 Mputa Interconnection Project
GoU Development
External Financingt
Total
1,500,000
8,056,800
9,556,800
441,667
0
441,667
1,500,000
90,354,068
91,854,068
- Construction of Nkenda-
Hoima 220kV transmission line
and associated substations.
- RAP Implementation
1.Wetland permit - Field visits
with NEMA complete. Permits
under process
2.Forest permit – engagement of
NFA is on-going
3.Work permit – to be applied
for by EPC contractors
4.Import licenses - to be applied
for by EPC contractors
5.Pre-award meeting with the
Best Evaluated Bidder for
Supervision and Project
Management of the EPC works
6.Preparation of the
transmission line
prequalification report
7.preparation of the substation
of the prequalification report
8.RAP implementation –
compensation at 77%
Acquisition of Other
Capital Assets
- Nkenda-Hoima 220kV
transmission line and associated
substations constructed.
790103
Project 1137 Mbarara-Nkenda/Tororo-LiraTransmission Lines
- Construction of Mbarara-
Nkenda & Tororo-Lira
transmission lines and
associated substations
•Total Route approved – 233
Km (87%)
•Total DCPT completed -506
out of 740 locations (68%)
Acquisition of Other
Capital Assets
-Mbarara-
Nkenda (Lot 2) &Tororo-Lira
(Lot 1) transmission lines and
associated substations
790103
Vote Overview
168
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Approved Budget, Planned
Outputs (Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
Expenditures and Outputs by
End March
(Quantity and Location)
-RAP implemnetation
•Total Excavation Completed –
197 out of 740
•Total Foundation Completed –
190
•Total Backfilling completed –
183
•Total Tower Erection
completed - 25
•Total Tower Material
received - 2726.7 MT (56%)
•Total conductor received – 649
km
•Total earth wire received- 180
km
•OPGW received – 67 km
•Survey- 95%
Opuyo substation
•Engineering documents/
technical submissions – 75%
•Approval – 45%
•132kV SF6 CB, 132kV &
33kV Surge Arresters, 132kV
CVT and 132kV CT has been
received at site
•15 MVar Shunt Reactor
despatched
•Metallic container Store
established on site
•Survey works completed
•Civil works – 0%
•Opuyo substation progress is
estimated at 26%
LOT 2
•Total Route approved – 157.4
Km (97%)
•Total DCPT completed - 421
out of 452 locations (93.1%)
•Total Tower Excavation
Completed – 118 out of 319
tower locations
•Total Tower Foundation
Completed – 115
•Total Tower Backfilling
completed – 112
•Total Tower Erection
Completed - 12
•Monopole foundation
excavation – 6 out of 133
locations
•Monopole foundation
completed - 0
•Total Tower Material
Received - 1845.8 MT (84%)
•Total Pole Material received -
220 MT (16%)
•Total conductor received – 550
km
•Total earthwire received – 49
km
•Total OPGW received – 65 km
•Check Survey in National Park
in progress
•Survey- 85%
Fort Portal substation
•Consignment of 132 kV
Switchgear equipment received
at site
•Survey works completed
•Mobilisation for road works
made
constructed.
Vote Overview
169
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Approved Budget, Planned
Outputs (Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
Expenditures and Outputs by
End March
(Quantity and Location)
GoU Development
External Financingt
Total
5,400,000
105,294,300
110,694,300
3,561,872
0
3,561,872
3,518,621
103,950,000
107,468,621
•55 No’s of Foundations
excavated out of a total of 103
foundations
•PCC Completed in 54 No’s of
foundations out of 55 excavated
•PCC for the balance 1 no of
foundation ( power transformer
) is being done
•Retention wall at edges of
filled substation area started
•SF6 Gas Handling device
under despatch.
•40MVA Transformer
despatched
•33kV Indoor GIS FAT
conducted in Germany
•Power Transformer & 15 Mvar
Reactor FAT concluded
•Engineering documents/
technical submissions – 89%
•Approval – 80%
•overall construction progress –
33%
Project 1140 NELSAP
GoU Development
External Financingt
Total
3,200,000
149,694,200
152,894,200
2,250,414
0
2,250,414
4,637,253
57,470,000
62,107,253
-RAP implementation
- Construction works of
Bujagali-Tororo-Lessos and
Mbarara-Mirama- transmission
lines
The current disbursement level
stands at 19.73% for ADF and
21.9% for JICA.
- Foundation works commenced
for Bugali- Lessos line (lot A)
and 69 out of an estimated
399no; foundations are
complete.
- Line route alignment for
Mbarara- Mirama line (lot B) is
complete and the survey is 60%
complete.
-Lot C contractor received 3 out
of 4 sites. Pending is Mirama
site. Site clearance and levelling
commenced for Tororo and new
Mbarara substations.
-Procurement of contractors for
construction of resettlement
houses for Project Affected
Persons is ongoing.
- RAP Implementation progress
is at 72%.
Acquisition of Other
Capital Assets
- Bujagali-Tororo-Lessos and
Mbarara-Mirama- transmission
lines Lot A: Uganda-Kenya; Lot
B: Uganda-Rwanda and Lot C:
Substations constructed.
790103
Project 1144 Hoima - Kafu interconnection
-Feasibility study for Hoima-
Kafu feasibility study
concluded
- Supervision Consultant
- RAP Implementation
Contract Extension Delayed but
approved
-Feasibility Study on-going;
90% completed.
-ESIA & RAP Studies on-going
completed
Acquisition of Other
Capital Assets
- RAP Implementattion
Consultant for Hoima -
Kinyara - Kafu Interconnection
Procured.
- Supervision Consultant for
Hoima - Kinyara - Kafu
790103
Vote Overview
170
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Approved Budget, Planned
Outputs (Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
Expenditures and Outputs by
End March
(Quantity and Location)
GoU Development
External Financingt
Total
3,000,000
839,600
3,839,600
1,555,255
0
1,555,255
3,000,000
1,670,000
4,670,000
Interconnection Procured.
- EPC Contractor for Hoima -
Kinyara - Kafu Interconnection
Procured.
- Resettlement Action Plan for
Hoima - Kinyara - Kafu
Interconnection Implemented.
Project 1198 Modern Energy from Biomass for Rural Development
GoU Development
External Financingt
Total
1,471,000
0
1,471,000
113,020
0
113,020
2,300,000
0
2,300,000
-Purchase of a briqquetting unit
to enhance briqquette
production in private sector
- Purchase of the spares for the
relocated Budo gasifier
-Purchase of four 10kw gasifiers
for use and demonstration of
technology for schools
Requests issued for a supplier of
briquetting unit
Purchase of
Specialised
Machinery &
Equipment
Purchase of a biogas unit for
electricity generation
Purchase of spares for
Nyabyeya gasifier maintenance
Purchase of 4 hand held Global
Positioning Units (GPS)
Purchase materials to support
completion of 10kw Apac
biogas unit
Purchase of 4 gasifier units for
gasification technology
demonstration
Implementation plan of
gasification technology
Engineering designs (biogas
system for electricity
770103
Project 1212 Electricity Sector Development Project
GoU Development
Total
10,593,553
42,588,941
5,762,707
5,762,707
3,037,253
131,137,253
- Construction of new Kawanda-
Masaka transmission line and
related upgrades to substations.
- Power Sector Information
Center in place
- Compesation for land for the
Kawanda-Masaka transmission
line (RAP implementation)
-Procurement of supervision
Consultant for Kawanda-
Masaka transmission lines
-Procurement of EPC
Contractor for Kawanda
–Masaka transmission project
-Procurement of Consultant for
feasibility study Lira –Gulu-
Nebbi –Arua transmission line
project
50% (1081) of the total number
of affected households (ie.
2171) have been compensated.
Contract for the independent
consultant to monitor the RAP
implementation was signed.
Bids for Potential Contractors
of the Kawanda-Masaka 220kV
line have been evaluated and
report submitted to the World
Bank.
Contract for the Supervision of
the Lira-Gulu-Nebbi T-Line was
signed.
Acquisition of Other
Capital Assets
- Establishment of the Power
Sector Information Centre
commenced
- Construction of new Kawanda-
Masaka transmission line and
related upgrades to substations.
790103
Vote Overview
171
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Approved Budget, Planned
Outputs (Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
Expenditures and Outputs by
End March
(Quantity and Location)
External Financingt 31,995,388 0 128,100,000
Project 1221 Opuyo Moroto Interconnection Project
Op
GoU Development
External Financingt
Total
1,000,000
0
1,000,000
833,333
0
833,333
1,000,000
2,690,000
3,690,000
- Feasibility study concluded
- RAP implementation
- Supervision Consultant and
EPC Contractor procured
Completion of the feasibility
study
Procurement of RAP/ESIA
study update and RAP
Implementation consultant
Acquisition of Other
Capital Assets
•Procurement of RAP
implementation consultant
•Procurement of Supervision
Consultant
•Procurement of EPC Contractor
•RAP Implementation
790103
Project 1222 Electrification of Industrial Parks Project
GoU Development
External Financingt
Total
0
0
0
0
0
0
640,000
0
640,000
Acquisition of Land
by Government
RAP Implementation710103
Project 1257 Mirama-Kikagati-Nshungyenzi Transmission Line
GoU Development
External Financingt
Total
0
0
0
0
0
0
0
2,284,600
2,284,600
Feasibility Studies and Detailed
Engineering Designs
Acquisition of Other
Capital Assets
-Completion of Feasibility study
for Mirama - Kikagati -
Nshungyenzi Transmission Line.
-Complete ESIA / RAP study
for Mirama - Kikagati -
Nshungyenzi Transmission Line.
-RAP Implementation for
Mirama - Kikagati -
Nshungyenzi Transmission Line.
790103
Project 1259 Kampala-Entebbe Expansion Project
GoU Development
External Financingt
Total
0
0
0
0
0
0
1,500,000
2,920,000
4,420,000
Acquisition of Other
Capital Assets
- Detailed design and tender
document preparation
- Procurement of EPC
contractor
- Commencement of
Construction Works
790103
Vote Function: Large Hydro power infrastructure0203
Project 1143 Isimba HPP
Acquisition of Land
by Government
-The RAP implementation for
the Isimba HPP and the
associated transmission lines
finalised.
-The Community Development
Action Plan for Isimba HPP &
710203
Vote Overview
172
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Approved Budget, Planned
Outputs (Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
Expenditures and Outputs by
End March
(Quantity and Location)
GoU Development
External Financingt
Total
0
0
0
0
0
0
900,000
0
900,000
the associated transmission
lines and commence on its
implementation finalised.
-The Access Road from
Kayunga Town to site and those
within the project site
completed.
-The Employer and Contractor’s
Camp along with water supply
system, power supply system,
telecommunication line
construction completed.
-The project detailed designs
incorporating the results of the
additional investigations carried
out by the contractor finalised.
-The construction works for the
Power Plant and the
transmission line (30%
coverage) commenced.
-The construction of the Site
Laboratory completed.
- EPC works for Isimba HPP
supervised
Project 1183 Karuma Hydoelectricity Power Project
GoU Development
External Financingt
Total
1,096,900,000
0
1,096,900,000
34,640,500
0
34,640,500
1,096,000,000
0
1,096,000,000
-EPC Contract Signed and
Contractor for Karuma
Hydropower Project on Site.
-Five (5) Sensitisation
Workshops for Karuma HP
Project affected people and
local community held.
-100% of Project Affected
Persons for Karuma HPP
Compensated/Resettled.
-100% Land Freed Up for
Contractors.
-RAP implementing Agency for
Evacuation Lines in place.
-100% of the Project Affected
Persons for Karuma HPP Power
Evacuation Lines Compenseted/
Ressettled.
-Construction of Karuma HPP
Commences. 20% of the Works
Covered.
- Preparatory survey for Ayago
Continued to supervise the EPC
Contract Signed and Contractor
for Karuma Hydropower Project
on Site.
-90% of Project Affected
Persons for Karuma HPP
Compensated/Resettled.
-90% Land Freed Up for
Contractors.
-RAP implementing Agency for
Evacuation Lines in place.
-90% of the Project Affected
Persons for Karuma HPP Power
Evacuation Lines Compenseted/
Ressettled.
-10% Construction of Karuma
HPP Works Covered by M/s
Sinohydro.
Large Hydro Power
Infrastructure
-Institutions (churches mosque
and Karuma Primary school)
relocated.
-Construction of the
Resettlement Houses
commenced.
-PAPs within the affected and
host communities sensitized.
-Implementation of the
Community Development
Action Plan (CDAP) and the
Environment and Social
Management Plan (ESMP)
supervised and Monitored.
- Construction of Karuma HPP
Commences. (20%) of the
Works Covered.
- Contribution by GOU towards
the 20% construction of the
Karuma HPP.
800203
Vote Overview
173
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Approved Budget, Planned
Outputs (Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
Expenditures and Outputs by
End March
(Quantity and Location)
Vote Function: Petroleum Exploration, Development & Production0303
Project 1142 Management of the Oil and Gas Sector in Uganda
GoU Development
External Financingt
Total
8,900,000
0
8,900,000
4,373,327
0
4,373,327
7,939,440
0
7,939,440
Construction of Phase-2 of the
new Data Centre completed and
Phase-3 commenced;
maintenance of existing
buildings and related
infrastructure undertaken.
The process of varying the
Phase-2 contract to include an
additional floor commenced.
Routine maintenance of office
buildings and the surrounding
environment undertaken
Government
Buildings and
Administrative
Infrastructure
Construction of Phase-3 of the
new Data Centre;
Maintenance of existing
buildings and related
infrastructure undertaken;
Establishment and Rent for field
based offices.
720303
GoU Development
External Financingt
Total
586,000
0
586,000
146,020
0
146,020
0
11,909,900
11,909,900
Laboratory and Geophysical
equipment procured and
maintained.
Procurement of the gas
generators, chemicals and one
gravity meter commenced
Purchase of
Specialised
Machinery &
Equipment
Laboratory and Geophysical
equipment procured and
maintained.
770303
Project 1184 Construction of Oil Refinery
GoU Development
External Financingt
Total
0
0
0
0
0
0
2,929,000
0
2,929,000
Acquisition of Land
by Government
Detailed route survey for
products pipeline from the
refinery to Buloba terminal
concluded
Resettlement Action Plan (RAP)
study crude oil from the field to
the refinery and products
pipeline from the refinery to
Buloba terminal undertaken
Environmental Baseline Study
for pipelines undertaken
710303
Total 39,085,400 24,235,791 29,880,220
- Land for the refinery and
supporting infrastructure
acquired;
- Continued implementation and
completion of Logistics study
- Transaction Advisory services
for Refinery development
undertaken;
- Pre - Front End Engineering
Design (FEED) for refinery
development completed.
- Aviation studies for aerodrome
development undertaken
- Crude oil pipeline to the
refinery and storage facilities
study recommendations
implemented;
- Pre-FEED for refinery
products’ pipeline from Hoima
to Buloba terminal conducted.
To date 1370 PAPs out of 2615
who opted for compensation
have been compensated
Land for resettlement identified
Transaction Advisor hired to
assist Government procure a
lead investor/developer for the
refinery and also structure the
refinery project
Request for proposal issued to
bidders and submitted end May
2014 and evaluation completed
in Mid-June 2014
Oil Refinery
Construction
Acquisition of land for the
refinery development concluded.
Master plan and detailed
engineering design study for the
aerodrome development
concluded
Coordination of the activities of
the Transaction Advisor
800303
Vote Overview
174
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Approved Budget, Planned
Outputs (Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
Expenditures and Outputs by
End March
(Quantity and Location)
GoU Development
External Financingt
Total
32,695,500
6,389,900
24,235,791
0
29,880,220
0
Vote Function: Petroleum Supply, Infrastructure and Regulation0403
Project 1258 Downstream Petroleum Infrastructure
GoU Development
External Financingt
Total
1,900,000
0
1,900,000
849,613
0
849,613
9,400,000
0
9,400,000
•Updated RAP the Kenya-
Uganda oil pipe line in place
- Private Operator selected
-Project Agreements and
documents updated
-Wayleave acquired and
handled over to the private
investor or development
- 8 JCC meetings held
- Project Documents upated
- Govenments of Kenya and
Uganda agreed to develop the
project as a Public project.
- Penspen appointed to carry out
feasibility study for Kampala-
Kigali Pipeline segment
-EPC document preparation
commenced
Acquisition of Land
by Government
- Project documents drafting
finalized for Kenya-Uganda.
- Drafting of Project
Agreements for Kenya-Uganda
finalized.
- EIA for Kenya-Uganda project
finalized.
- Resettlement Action Plan
(RAP) updated (Malaba-
Kampala-Uganda)
- RAP implementation for
Malaba-Kampala commenced
- EPC tendering documments
finalised
- Feasibility study for Uganda-
Rwanda pipeline project
completed
- Pipe line routing for Uganda-
Rwanda undertaken
- RAP for Uganda-Rwanda
development commenced
710403
GoU Development
External Financingt
Total
700,000
0
700,000
4,100
0
4,100
700,000
0
700,000
•- NPIS developed and
operational
-5 staff attain specialized
training in usage of NPIS
-Necessary hardware procured
-5 year subscription to PLATTS
done
- Office equipment and
furniture procured
- TOR for development of
NPIS developed
- Office Equipment procured
-Evalaution of bids for NPIS
onsultant and necessary
infrastructure in progress.
- Office equipment supplier paid
-Evaluation of bids for NPIS
consultant finalised.
-Subscription to PLATTS in
progress.
Purchase of Office
and ICT Equipment,
including Software
-Development of NPIS
completed
- 5 staff attain specialized
training in operating and
management of NPIS
- Necessary hardware procured
- Five year subscription to
PLATTS done
760403
-Codes of practice for
downstream petroleum sub-
sector in place
-Organizing 5 regional work
shop each financial year to
sensitize the population on
petroleum products handling
-Codes of practice enforced
-HSE for downstream petroleum
sub-sector in place
-TOR for development of codes
of practise developed
- Procurement of HSE
consultant commenced with an
advert in news papers
- Consultant to develop HSE
appointed
-One regional workshop held at
Imperial Royal, Kampala on
petroleum facilities standards
Purchase of
Specialised
Machinery &
Equipment
- Downstream petroleum policy
in place
- Road map for revising the
regulatory framework for
downstream petroleum in place
- Supervision of the HSE
consultant continues
770403
Vote Overview
175
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Approved Budget, Planned
Outputs (Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
Expenditures and Outputs by
End March
(Quantity and Location)
GoU Development
External Financingt
Total
1,120,000
0
1,120,000
261,224
0
261,224
720,000
0
720,000
- 20 standards developed
- 5 stakeholders consultative
meetings on Downstream
Policy held
- 5 regional workshops for
sensitization on the developed
standards held
- HSE training manual in place
- HSE protective gears for PSD
staff procured
GoU Development
External Financingt
Total
1,280,000
0
1,280,000
420,512
0
420,512
1,680,000
0
1,680,000
- JST stocked with products and
operational
-Independent centifier procured
and report in place
Feasibility study for
Nakasongola fuel depot in place
- Private investor for
Nakasongola in place
- JST private operator supervised
•
- JST operational and stocked
with petroleum products
- TOR for feasibility study for
Nakasongola in place
- JST supervision reports in
place
- consultant for a feasibility
study for nakasongola procured
-Independent centifier procured
and work is in progress
Acquisition of Other
Capital Assets
- Studies and designs for
Nakasongola Strategic Reserves
completed
- Nakasongola Strategic
Reserves development
commenced
- Feasibility study of Kampala
common user terminal
commenced
790403
Vote Function: Mineral Exploration, Development & Production0503
Project 1199 Uganda Geothermal Resources Development
GoU Development
External Financingt
Total
2,180,000
0
2,180,000
115,703
0
115,703
2,180,000
0
2,180,000
Deep subsurface geothermal
exploration equipment and
laboratory procured.
Initiated procurement of more
Magnetotellurics (MT) units,
Transient Electromagenetic
(TEM) equipment.
Evaluation of bids on the
procurement of specialised
equipment of subsurface
geothermal exploration was
completed.
Initiated process of procuring
Six (6) Magnetotellurics (MT)
units, one (1) gravity meter,
geological software, Niton X-
Ray Fluorescence (XRF)
Analyzer.
Evaluation of bids was
completed
Purchase of
Specialised
Machinery &
Equipment
Continue the procurement of
Deep subsurface geothermal
exploration equipment and
laboratory consumables
770503
Project 1200 Airborne Geophysical Survey and Geological Mapping of Karamoja
Karamoja regional training
centre and offices constructed.
Initiated procurement of a
contactor construct Karamoja
Regional Office and training
centre for mineral development.
Government
Buildings and
Administrative
Infrastructure
Construct and equip a regional
minerals office for Karamoja
region; set up a training centre
for ASM in Moroto
720503
Vote Overview
176
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Approved Budget, Planned
Outputs (Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
Expenditures and Outputs by
End March
(Quantity and Location)
GoU Development
External Financingt
Total
800,000
0
800,000
216,754
0
216,754
800,000
0
800,000
Initiated procurement of project
computers and printers.
Initiated the purchase of
cartridges and procurement of
maintenance services
Initiated the purchase of anti-
virus, upgrade and back-up
systems.
Initiated the procurement of
active fault mapping equipment
and landslide investigations.
Produced regional earthquake
bulletins with difficulties of
funding.
Disseminated seismic data to
data users in infrastructure
planning, construction of
Karuam Hydro Power dam and
other small hydro power
stations.
Initiated Procure furniture and
computers.
Payment for land in Moroto,
Plots 17 and 19 Rupa Road
allocated for DGSM office
construction was made.
The land for the project was re-
allocated to another developer.
New plots are being identified.
GoU Development
External Financingt
Total
950,000
0
950,000
289,226
0
289,226
950,000
0
950,000
Engineering geology
investigations conducted and
geo-hazards monitored, active
fault mapped
No funds were released for
Maintenance of Seismological
Network
and Servicing of Seismological
stations
Disseminated seismic data to
data users in infrastructure
planning, construction of
Karuam Hydro Power dam and
other small hydro power.
Continued with procurement of
specialised equipment for
Engineering geology
investigations to conducted.
Monitored the geo-hazards and
active faults using the National
Seismological Network stations.
Purchase of
Specialised
Machinery &
Equipment
Procurement and installation of
Specialised equipment.
770503
Vote Function: Policy, Planning and Support Services4903
Vote Overview
177
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Approved Budget, Planned
Outputs (Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
Expenditures and Outputs by
End March
(Quantity and Location)
Project 1223 Institutional Support to Ministry of Energy and Mineral Development
GoU Development
External Financingt
Total
3,725,965
0
3,725,965
265,597
0
265,597
3,025,965
0
3,025,965
- Retooling of Offices at Amber
house
- Complete redesign and
implementation Voice and data
infrastructure
- Secure laboratory
infrastructure at GSMD
Office Improvement: Remedial
renovation of the Amber house
basement to repair the leaking
roofs and sewage system was
undertaken.
Voice and data infrastructure:
Phase I of the redesign voice
and data infrastructure
(Structured Cabling) was
completed. Testing of the
installations was successful.
Commissioning awaits the
completion of Phase II, whose
procurement has been
concluded. Phase I involved
redesign and structured cabling
of the data infrastructure. Phase
II will involve installation of a
centralized power supply system.
Procured office furniture and
fixtures for various offices;
fittings filing cabinets and
equipment for records centre.
Procurement for further
remedial renovation, furnishing
of 50 offices used by MEMD,
and installation of air
conditioning systems was
concluded.
Undertook remedial renovation
of offices at Amber house.
Procurement of consultant for
phase 2 of the redesign voice
and data infrastructure was
concluded
Government
Buildings and
Administrative
Infrastructure
- Comprehensively renovate and
manage Amber House and
commence development process
of the adjacent plot
724903
Output-Data Recovery Plan
developed
ICT and Resource Centre
equiped
Procure and maintain internet
server system
Internet services maintained
Probox interchange system
Completed drafting the ToR for
Consultancy services for the
output-data recovery plan
Commenced the procurement to
equip the ICT and Resource
Centre.
Procurement of consultancy
services for the output-data
recovery plan was initiated.
Procured ten (10) Computers
and IT
Equipment - LAN Infrastructure.
Procured a server system and
accessories.
Internet maintain maintained
Purchase of Office
and ICT Equipment,
including Software
- Complete the development of
a disaster recovery solution for
the Ministry
- Complete Phase II of the
redesign and implementation of
Voice and data infrastructure
- Resource Centre equipped
- Internet services (WiFi)
procured and maintained
- Procure a consultancy to
develop an information system
for the Ministry
- Computer peripherals/
hardware and sofwares/
licencing procured
- Computer equipment serviced
764903
Vote Overview
178
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
(iii) Priority Vote Actions to Improve Sector Performance
A number of action plans have been planned in order to improve vote performance
- Continue implementing plans to increase power generation capacity and associated transmission
infrastructure;
- Continue increasing access to modern energy services
- Development of Kenya - Uganda, and Kampala - Kigali oil products pipeline
- A number of action plans have been planned in order to improve vote performance within the oil and gas
sector. These include:
•Continue implementation of the new petroleum laws that govern the activities of the oil and gas sector
•Develop regulations for the upstream and midstream activities
•Support and spearhead the restructuring and creation of new institutions provided for by the new laws
•Develop standards and codes for the upstream and midstream activities
•Formulation of the monitoring and evaluation framework
•Implementation Communication strategy
•Development and Implementation of the National Content Policy and Plan
•Effective management of the oil and gas sector
•Promote the investment opportunities in the country’s oil and gas sector within and outside the country
•Engage in training of staff at various levels in order to enable availability of the necessary manpower and
increase efficiency in performance
- Support and spearhead the restructuring and creation of new institutions provided for by the new laws
- Develop standards and codes for the upstream and midstream activities
- Formulation of the monitoring and evaluation framework
- Implementation Communication strategy
- Development of the National Content Policy and Plan
- Effective management of the oil and gas management
- Promote the investment opportunities to potential investors within and outside the country
Approved Budget, Planned
Outputs (Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
Expenditures and Outputs by
End March
(Quantity and Location)
GoU Development
External Financingt
Total
1,900,000
0
1,900,000
1,249,420
0
1,249,420
1,000,000
0
1,000,000
GoU Development
External Financingt
Total
600,000
0
600,000
307,889
0
307,889
1,000,000
0
1,000,000
Equiping and retooling of the
Mineral laboratory
The Procurment process for the
laboratory mineral testing
equipment is still on going.
The procurement process to
secure a mineral laboratory
storage facility to mitigate theft
is still on going
Purchase of
Specialised
Machinery &
Equipment
Implement phase II of
Equipping and retooling the
GSMD Mineral Laboratory
Infrastructure
774903
GoU Development
External Financingt
Total
3,840,415
0
3,840,415
3,561,793
0
3,561,793
1,440,415
0
1,440,415
- Continue with Feasibility
Studies for Rwimi/Nyamba
Hydro Power Plant
- Complete the development of
the Energy and Mineral Invester
Master Plan
Negotiation with the Consultant
for the Feasibility Studies for
Rwimi/Nyamba Hydro Power
Plant was ongoing.
Continued with the
development of the Energy and
Mineral Investement Master
Plan
Acquisition of Other
Capital Assets
Complete the Feasibility
Studies for Rwimi/Nyamba
Hydro Power Plant
794903
Vote Overview
179
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017- Engage in training of staff at various levels in order to increase efficiency in performance
Table V3.6: Vote Actions to Improve Sector Performance
2013/14 Planned Actions: 2014/15 Planned Actions: MT Strategy:2013/14 Actual Actions:
Sector Outcome 0:
Policy, Planning and Support Services4903Vote Function:
VF Performance Issue: - Access to adequate financial resources Monitoring and Evaluation of the sub-sectors
Develop capacity to monitor
and evaluate the sector.
Present a funding proposal to
the MoFPED
Develop capacity to monitor
and evaluate the sector.
Continued with the
Development of capacity to
monitor and evaluate the
sector.
Increased access to affordable and efficient sources of energy Sector Outcome 1:
Energy Planning,Management & Infrastructure Dev't0103Vote Function:
VF Performance Issue: - High cost of electricity generation
Commence the development
of Karuma and Isimba hydro
power projects
Increaase generation mix to
include variuos options
Develop more cheaper sources
of power and increase their
mix in power generation
Commenced the development
of Karuma and Isimba hydro
power projects
VF Performance Issue: - Poor transmission and distribution network resulting into energy losses.
Continue the refurblishment
of the transmission and
distribution infrastructure (i.e
line, transformer and
substaion upgrade)
Continue the refurblishment of
the transmission and
distribution infrastructure (i.e
line, transformer and substaion
upgrade)
Refurblishment of the
transmission and distribution
infrastructure (i.e line,
transformer and substaion
upgrade)
Continued with the
refurblishment of the
transmission and distribution
infrastructure (i.e line,
transformer and substaion
upgrade)
Sustainable management of mineral resources for developmentSector Outcome 2:
Mineral Exploration, Development & Production0503Vote Function:
VF Performance Issue: - Complicated procedures for access of land for the development of mining infrastructure
A formal request is to be
submitted to MoFPED in
regard to the RAP Sukulu
Phosphates project
amounting to UGX135bn.
Request for increase of
funding from 0.465bn to 6.42
bn (recurrent) and
development budget from
6.8bn to 108.72 bn to enable
the sector takeover its primary
role of growth driver and
industrialisation in line wth
NDP and Vision 40.
Sensitisation of local
communities and land owners
on the benefits of the intended
projects. Attracted private
investors to take over the
development of Mineral
resources in Sukulu
(phosphates) and Kilembe
(copper).
The investor for the Sukulu
Phosphates project had
commenced on carrying out
RAP but legal conflicts
stopped the exercise.
VF Performance Issue: - Limited access to adequate resources for inspection and monitoring of exploration and mining
operations
Requested MoFPED for AIA
to support the Mineral Sub-
sector recurrent budget from
NTR to meet the funding gap
in mineral exploration, mine
inspections and monitoring.
Request for increase of
funding from 0.465bn to 6.42
bn (recurrent) and
development budget from
6.8bn to 108.72 bn to enable
the sector takeover its primary
role of growth driver and
industrialisation in line with
NDP and Vision 40.
(a) Ten (10) development
projects packaged. MoFPED
to borrow for the funding gap
of 115.14 bn for priority
projects in the Mineral Sector.
(b) To allow the use of NTR at
Source to cater for
Appripriation in Aid (AIA)
and increase more NTR from
mining.
Appropriation In Aid to
support the Mineral Sub-
sector recurrent budget from
NTR to meet the funding gap
in mineral exploration, mine
inspections and monitoring
being followed up with
MoFPED.
Sustainable management of the country's Oil and Gas resourcesSector Outcome 3:
Petroleum Exploration, Development & Production0303Vote Function:
VF Performance Issue: - Insufficient capacity to efficiently manage the country's oil and gas potential
Train five (5) members of
staff at Postgraduate Level in
Petroleum related studies.
Continue the implementation
of local content strategy and
plan.
In-house training and field
excursions, including
Stratigraphic scheme.
Continue with cpapcity
biulding programs
Continued strengthening of
the institutional capacity
Nine (9) members of staff at
Postgraduate Level in
Petroleum related studies.
Have Continued with the
implementation of local
content strategy and plan.
In-house training and field
excursions, including
Stratigraphic scheme.
VF Performance Issue: - The Enactment of the Oil and Gas Resource Management Law.
Vote Overview
180
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
V4: Proposed Budget Allocations for 2014/15 and the Medium Term
(i) The Total Budget over the Medium Term
Table V4.1: Past Outturns and Medium Term Projections by Vote Function*
The total budget allocation over the next financial year is Ush. 1,775.709 billion, of which Ush. 4.063
billion is wage recurrent, Ush. 4.244 billion is non wage recurrent, GoU development is Ush. 1,298.804
billion and 468.599 billion is Donor Development.
This section sets out the proposed vote budget allocations for 2014/15 and the medium term, including
major areas of expenditures and any notable changes in allocations.
(ii) The major expenditure allocations in the Vote for 2014/15
For the FY 2014/15, Karuma Hydro Power Project has has the largest sector budgetary allocation of Ush.
1,096.0 bn. Transmission infrastructure development follows with 41.6 billion largely for construction and
implementation of resettlement anction plans for the various transmission lines. Ush. 35.0 bn is earmarked
for oil refinery development activities and there is need for more funding to facilitate pipeline development
activities.
(iii) The major planned changes in resource allocations within the Vote for 2014/15
Budgetary allocation to the sector has incrased by 125.153 billion. This incriment is largely to support the
development of Karuma hydropower project and the development partner support to the power
infrastructure.
* Excluding Taxes and Arrears
Table V4.2: Key Changes in Vote Resource Allocation
2013/14 Planned Actions: 2014/15 Planned Actions: MT Strategy:2013/14 Actual Actions:
New Regulations and
guidelines for the upstream
activities developed;
Model PSA reviewed and
updated
Monitoring and Evaluation
(M & E) strategy for the
National Oil and Gas Policy
(NOGP) formulated.
Implement the newly
approved legislation
Continue the implementation
of the oil and gas policy and
legislations.
Commenced on the
development of the New
Regulations and guidelines for
the upstream activities
Model PSA reviewed and
updated
Monitoring and Evaluation (M
& E) strategy for the National
Oil and Gas Policy (NOGP)
formulated and in place.
2016/172012/13
Outturn
Releases
End Mar
Appr.
Budget 2014/15 2015/16
MTEF Budget Projections2013/14
Vote: 017 Ministry of Energy and Mineral Development
207.554454.19584.187 61.260 566.165 270.2340301 Energy Planning,Management & Infrastructure Dev't
1,109.9971,093.2450.000 32.273 1,096.900 1,023.2350302 Large Hydro power infrastructure
55.88568.73322.034 38.737 68.013 65.7440303 Petroleum Exploration, Development & Production
26.0816.2451.057 3.411 14.057 28.6070304 Petroleum Supply, Infrastructure and Regulation
29.0878.0381.922 4.646 8.684 80.8720305 Mineral Exploration, Development & Production
26.46820.1007.513 14.321 21.892 21.0680349 Policy, Planning and Support Services
Total for Vote: 1,455.0721,650.557116.714 154.647 1,775.710 1,489.760
Justification for proposed Changes
in Expenditure and Outputs
Changes in Budget Allocations and Outputs
in 2014/15 from 2013/14 Planned Levels:
Vote Function:0302 Energy Planning,Management & Infrastructure Dev't
02 Energy Efficiency Promotion0301Output:
UShs Bn: 1.163
Promotion of Renewable Energy technologies, and step up
energy audits to conserve power and also address the
problem of power losses
Promotion of Renewable Energy technologies, involving and step
up energy audits to conserve power and also address the problem
of power losses
Vote Overview
181
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Justification for proposed Changes
in Expenditure and Outputs
Changes in Budget Allocations and Outputs
in 2014/15 from 2013/14 Planned Levels:
03 Renewable Energy Promotion0301Output:
UShs Bn: 1.717
Six new small hydro power projects will come on board
under the GETFiT program. These will need to be supported.
Six new small hydro power projects will come on board under the
GETFiT program. These will need to be supported.
04 Increased Rural Electrification0301Output:
UShs Bn: 2.589
On-grid service expansion.
Densification of the grid
Subsidised consumer connections and micro-credits for
house wiring
Mini-grids
Stand alone off-grid (PV) electricity services
52 Thermal and Small Hydro Power Generation (UETCL)0301Output:
UShs Bn: 13.504
Cost requirements for the development and consumption
needs for power generated by thermal capacity.
The resources are geared towards the generation of 50MW of
thermal power.
53 Cross Sector Transfers for ERT (Other Components)0301Output:
UShs Bn: 6.394
Development partners' allocation towards ERT
Development partners' allocation towards ERT
71 Acquisition of Land by Government0301Output:
UShs Bn: -2.981
These resources are to support RAP for transmission lines
RAP implementation for the transmission infrastructure
76 Purchase of Office and ICT Equipment, including Software0301Output:
UShs Bn: -21.689
The cost of this output was met during the previous budget
period
The cost of this output was met during the previous budget period
77 Purchase of Specialised Machinery & Equipment0301Output:
UShs Bn: 23.398
The equipment is needed for setting up demonstration on
modern energy technologies in biomas and energy efficiency
The equipment is needed for setting up demonstration on modern
energy technologies in biomas and energy efficiency
79 Acquisition of Other Capital Assets0301Output:
UShs Bn: 65.912
Resource allocation in line with the priority need to decelop
power infrastructre.
Resource allocation in line with the priority need to decelop
power infrastructre.
Vote Function:0380 Large Hydro power infrastructure
80 Large Hydro Power Infrastructure0302Output:
UShs Bn: 4.100
This amount is intended for the development of Karuma HPP.
It is expected that the financing of Karuma HPP is under the
bilateral arrangement and GoU will meet the 15% while the
China EXIM Bank will meet the 85%
Vote Function:0301 Petroleum Exploration, Development & Production
01 Promotion of the country's petroleum potential and licensing0303Output:
UShs Bn: 1.069
Part of the work will be done under the new institutions that
are expected to come on board
02 Initiate and formulate petroleum policy and legislation0303Output:
UShs Bn: -1.417
The Oil and Gas Legislation was finalised
-The Petroleum (refining, gas conversion, transmission and
midstream storage) Act 2013 which was enacted by parliament
was assented to by the President and subsequently gazetted in
July 2013;
-Following the putting in place of the Petroleum (refining, gas
conversion, transmission and midstream storage ) Act 2013 and
the Petroleum (Exploration, Development and Production) Act
2013, development of New Regulations and Guidelines for the
upstream and midstream activities has progressed;
-Monitoring and Evaluation (M&E) strategy for the National Oil
and Gas Policy (NOGP) was finalized.
03 Capacity Building for the oil & gas sector0303Output:
UShs Bn: -3.297
Training fee from the oil companies will fill the gap
Training fee from the oil companies will fill the gap
05 Develop and implement a communication strategy for oil & gas in the country0303Output:
Vote Overview
182
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
Table V4.3: 2013/14 and 2014/15 Budget Allocations by Item
GoU Ext. Fin Total GoU Ext. Fin TotalAIAMillion Uganda Shillings
2013/14 Approved Budget 2014/15 Draft Estimates
AIA
Output Class: Outputs Provided 31,544.7 14,747.6 46,292.3 41,042.3 11,429.9 52,472.20.0 0.0
2,626.4 0.0 2,626.4 4,062.8 0.0 4,062.80.0 0.0211101 General Staff Salaries
2,395.8 0.0 2,395.8 1,971.3 0.0 1,971.30.0 0.0211102 Contract Staff Salaries (Incl. Casuals, Temp
2,472.9 6.0 2,478.9 3,744.5 30.0 3,774.50.0 0.0211103 Allowances
110.2 0.0 110.2 114.6 0.0 114.60.0 0.0212101 Social Security Contributions
11.0 0.0 11.0 20.0 0.0 20.00.0 0.0213002 Incapacity, death benefits and funeral expen
217.7 0.0 217.7 187.0 0.0 187.00.0 0.0213004 Gratuity Expenses
452.4 0.0 452.4 352.4 35.0 387.40.0 0.0221001 Advertising and Public Relations
505.5 946.0 1,451.5 797.5 146.9 944.40.0 0.0221002 Workshops and Seminars
2,203.3 3,778.8 5,982.1 2,556.4 905.1 3,461.50.0 0.0221003 Staff Training
12.0 0.0 12.0 6.5 0.0 6.50.0 0.0221004 Recruitment Expenses
93.5 0.0 93.5 56.0 10.0 66.00.0 0.0221005 Hire of Venue (chairs, projector, etc)
48.0 0.0 48.0 60.0 0.0 60.00.0 0.0221006 Commissions and related charges
81.8 0.0 81.8 97.6 0.0 97.60.0 0.0221007 Books, Periodicals & Newspapers
712.6 0.0 712.6 617.3 0.0 617.30.0 0.0221008 Computer supplies and Information Technol
207.4 0.0 207.4 104.0 0.0 104.00.0 0.0221009 Welfare and Entertainment
12.0 0.0 12.0 18.0 0.0 18.00.0 0.0221010 Special Meals and Drinks
915.4 0.0 915.4 695.6 0.0 695.60.0 0.0221011 Printing, Stationery, Photocopying and Bind
643.3 0.0 643.3 396.5 0.0 396.50.0 0.0221012 Small Office Equipment
Justification for proposed Changes
in Expenditure and Outputs
Changes in Budget Allocations and Outputs
in 2014/15 from 2013/14 Planned Levels:
UShs Bn: -1.331
The resources have been reduced due to the scale down of
activities as reflected in the implementation of the
communication strategy
Resources have been moved to other implementation areas
intended for the refinery RAP and FEED study
71 Acquisition of Land by Government0303Output:
UShs Bn: 2.929
Additional land for aerodrone and attendant infrastructure
like pipelines and storage facilities
Additional land for aerodrone and attendant infrastructure like
pipelines and storage facilities
72 Government Buildings and Administrative Infrastructure0303Output:
UShs Bn: 1.039
Finalisation of the laboratory and office building
Finalisation of the laboratoey and office building
76 Purchase of Office and ICT Equipment, including Software0303Output:
UShs Bn: -1.421
Done in the previous financial year
Done in the previous financial year
77 Purchase of Specialised Machinery & Equipment0303Output:
UShs Bn: 11.324
80 Oil Refinery Construction0303Output:
UShs Bn: -9.205
Part of the RAP for refinery infrastructure will have been
compensated
Part of the RAP for refinery infrastructure will have been
compensated
Vote Function:0371 Petroleum Supply, Infrastructure and Regulation
71 Acquisition of Land by Government0304Output:
UShs Bn: 7.500
Resources for the acqusition of pipeline corridor in line with
the need to reduce cost of fuel transpotation
Resources for the acqusition of pipeline corridor in line with the
need to reduce cost of fuel transpotation
Vote Function:0306 Policy, Planning and Support Services
06 Management of Policy Issues, Public Relation, ICT and Electricity disputes resolved0349Output:
UShs Bn: 5.047
This is needed to support the development of a Nuclear
Energy Read Map and strengthen Atomic Energy Regulation.
Also, support will be provided to the Electricity Disputes
Tribunal and Uganda Energy Credit Cxapitalisation Company
There is need to ensure that the new establishments rae supported
for them to attain self reliance.
79 Acquisition of Other Capital Assets0349Output:
UShs Bn: -2.400
Part of the strauctured cabling infrastructure has been
accomplished
Part of the strauctured cabling infrastructure has been
accomplished
Vote Overview
183
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
V5: Vote Cross-Cutting Policy and Other Budgetary IssuesThis section discusses how the vote's plans will address and respond to the cross-cutting policy, issues of
gender and equity; HIV/AIDS; and the Environment, and other budgetary issues such as Arrears and NTR..
(i) Cross-cutting Policy Issues
(a) Gender and Equity
GoU Ext. Fin Total GoU Ext. Fin TotalAIAMillion Uganda Shillings
2013/14 Approved Budget 2014/15 Draft Estimates
AIA
76.2 0.0 76.2 27.0 0.0 27.00.0 0.0221017 Subscriptions
0.0 0.0 0.0 25.0 0.0 25.00.0 0.0221020 IPPS Recurrent Costs
289.8 0.0 289.8 255.2 0.0 255.20.0 0.0222001 Telecommunications
99.0 0.0 99.0 58.5 0.0 58.50.0 0.0222002 Postage and Courier
334.9 0.0 334.9 77.0 0.0 77.00.0 0.0222003 Information and communications technolog
10.0 0.0 10.0 28.0 0.0 28.00.0 0.0223003 Rent – (Produced Assets) to private entities
71.6 0.0 71.6 347.0 0.0 347.00.0 0.0223004 Guard and Security services
88.6 0.0 88.6 488.6 0.0 488.60.0 0.0223005 Electricity
54.2 0.0 54.2 502.1 0.0 502.10.0 0.0223006 Water
5.0 0.0 5.0 216.0 0.0 216.00.0 0.0223007 Other Utilities- (fuel, gas, firewood, charcoa
10.0 0.0 10.0 0.0 0.0 0.00.0 0.0224002 General Supply of Goods and Services
0.0 0.0 0.0 300.0 0.0 300.00.0 0.0224004 Cleaning and Sanitation
769.0 4,839.8 5,608.8 15,106.4 7,140.5 22,246.90.0 0.0225001 Consultancy Services- Short term
2,835.0 5,132.0 7,967.0 992.1 3,162.5 4,154.60.0 0.0225002 Consultancy Services- Long-term
3.6 0.0 3.6 4.0 0.0 4.00.0 0.0226001 Insurances
2,578.2 0.0 2,578.2 2,418.6 0.0 2,418.60.0 0.0227001 Travel inland
931.5 45.0 976.5 1,583.5 0.0 1,583.50.0 0.0227002 Travel abroad
20.0 0.0 20.0 40.0 0.0 40.00.0 0.0227003 Carriage, Haulage, Freight and transport hir
1,122.7 0.0 1,122.7 1,472.5 0.0 1,472.50.0 0.0227004 Fuel, Lubricants and Oils
10.0 0.0 10.0 10.0 0.0 10.00.0 0.0228001 Maintenance - Civil
1,051.3 0.0 1,051.3 1,143.6 0.0 1,143.60.0 0.0228002 Maintenance - Vehicles
60.8 0.0 60.8 80.2 0.0 80.20.0 0.0228003 Maintenance – Machinery, Equipment & Fu
2.0 0.0 2.0 9.0 0.0 9.00.0 0.0228004 Maintenance – Other
7,400.0 0.0 7,400.0 0.0 0.0 0.00.0 0.0321440 Other grants
Output Class: Outputs Funded 72,092.0 1,306.0 73,398.0 73,255.9 34,544.0 115,499.90.0 7,700.0
52.0 0.0 52.0 232.0 0.0 232.00.0 0.0262101 Contributions to International Organisations
0.0 0.0 0.0 71,023.9 12,480.0 83,503.90.0 0.0263104 Transfers to other govt. units
72,000.0 1,306.0 73,306.0 2,000.0 22,064.0 31,764.00.0 7,700.0263204 Transfers to other govt. units
40.0 0.0 40.0 0.0 0.0 0.00.0 0.0263323 Conditional transfers for feeder roads maint
Output Class: Capital Purchases 1,201,928.4 350,938.2 1,552,866.6 1,185,113.1 422,624.7 1,607,737.80.0 0.0
10,140.0 0.0 10,140.0 7,900.0 0.0 7,900.00.0 0.0231001 Non Residential buildings (Depreciation)
0.0 0.0 0.0 50,000.0 0.0 50,000.00.0 0.0231002 Residential buildings (Depreciation)
80.0 0.0 80.0 10.0 0.0 10.00.0 0.0231003 Roads and bridges (Depreciation)
9,868.0 21,948.7 31,816.7 8,192.7 33,186.1 41,378.80.0 0.0231005 Machinery and equipment
400.0 0.0 400.0 545.0 0.0 545.00.0 0.0231006 Furniture and fittings (Depreciation)
1,097,026.0 308,970.2 1,405,996.2 10,148.9 379,163.3 389,312.20.0 0.0231007 Other Fixed Assets (Depreciation)
1,550.0 10,000.0 11,550.0 390.0 0.0 390.00.0 0.0281501 Environment Impact Assessment for Capital
18,983.6 10,019.3 29,002.9 14,021.6 6,360.0 20,381.60.0 0.0281503 Engineering and Design Studies & Plans for
7,050.4 0.0 7,050.4 9,494.8 3,915.4 13,410.20.0 0.0281504 Monitoring, Supervision & Appraisal of cap
34,830.5 0.0 34,830.5 37,910.0 0.0 37,910.00.0 0.0311101 Land
0.0 0.0 0.0 1,046,000.0 0.0 1,046,000.00.0 0.0312104 Other Structures
22,000.0 0.0 22,000.0 0.0 0.0 0.00.0 0.0312206 Gross Tax
0.0 0.0 0.0 500.0 0.0 500.00.0 0.0312302 Intangible Fixed Assets
Output Class: Arrears 0.0 0.0 0.0 200.0 0.0 200.00.0 0.0
0.0 0.0 0.0 200.0 0.0 200.00.0 0.0321605 Domestic arrears (Budgeting)
1,305,565.1 366,991.8 1,672,556.9 1,299,611.3 468,598.7 1,775,910.0Grand Total:
Total Excluding Taxes, Arrears and AIA 1,283,565.1 366,991.8 1,650,556.9 1,299,411.3 468,598.7 1,768,010.0
0.0
0.0
7,700.0
0.0
***where AIA is Appropriation in Aid
To create gender equality in the MinistryObjective:
Vote Overview
184
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017
(b) HIV/AIDS
(c) Environment
(ii) Verrified Outstanding Arrears for the Vote
(iii) Non Tax Revenue Collections
No arrears have yet been verified
Non tax revenue amounting to Ush 9.43 billion was realised from: Exploration Licence: Ush 0.58 billion; Mineral
Dealers licence Ush 0.25 billion; Mineral Royalties Ush 5.51 billion; Mining rent Ush 0.69 billion, Prospecting licence
Ush 0.03 billion; preparation fees Ush 0.10 billion; registration fee Ush 0.005 billion; tender documents Ush 0.01
billion; sale of maps Ush 0.03 billion; rental, surface and submission of Refinery development Ush 2.05 billion;
Source of NTR UShs Bn
2014/15
Projected
2013/14
Prel
Actual
2013/14
Budget
2012/13
Actual
Royalties 5.513
Total: 5.513
- Creating gender awareness in the Ministry
- Capacity Development of Focal Point Persons in MEMD
- Sensitizing staff on gender concerns
- Building Capacity of Ministry Focal Point Persons
- No. of Focal Point Persons trained
- No. of sensitization workshops conducted
- No. of meetings held
Issue of Concern :
Proposed Intervensions
Budget Allocations
Performance Indicators
UGX billion
Objective: To create HIV/AIDS awareness and integrate mitigation priorities in the mainstream
development planning, budget allocation and development plans.
- Behavioural change
- Capacity development of the Focal Point Persons/Peer Educators
- Inadequate funding for mainstreaming activities
- Sensitization of staff on HIV/AIDS
- Building capacity of the Focal Point Persons/Peer Educators
- Provision of funding for mainstreaming/support and treatment.
- No of sensitization seminars/workshops/ meetings conducted.
- No of HCT sessions conducted
- Revised HIV/AIDS policy in place
Issue of Concern :
Proposed Intervensions
Budget Allocations
Performance Indicators
UGX billion
Objective: To conserve the Environment
Conservation of the Environment
- The use of low voltage power lines with minimal effect on the environment
- Environment awareness programs like tree planting
- Better and Environmentally friendly energy access programs are designed like solar systems.
- Minimised effects on the Environment as a result of energy
access programs countrywide.
Issue of Concern :
Proposed Intervensions
Budget Allocations
Performance Indicators
UGX billion
Vote Overview
185
Ministry of Energy and Mineral DevelopmentVote:
Ministerial Policy StatementMinistry of Energy and Mineral Development
017Miscellaneous revenue Ush 0.168 billion
Vote Overview
186
Ministry of Energy and Mineral DevelopmentVote 017 FY 2014/15
Vote Function 0301: Energy Planning,Management & Infrastructure Dev't
Program : Energy Resources Department
CostCentre: Energy Resources
District : Kampala
File Number Annual
Salary as per
Salary
Scale as
per payslip
Monthly
Salary as per
payslip
Staff Names Annual
Salary as per
Appointing
Authority
Salary
Scale as
per
Appointing
Monthly
Salary as per
Appointing
Authority
Annual
Salary
Variance
P6471 Tumwesigye Diana Rose 2,114,028U8 Upp 176,169 2,114,028U8 Upp 176,169 0
P6466 Ali Ibrahim 2,114,028U8 Upp 176,169 2,114,028U8 Upp 176,169 0
P4797 Sserwada Gideon 2,321,856U8 Upp 193,488 2,321,856U8 Upp 193,488 0
P6001 Buyungo Edward 2,278,632U8 Upp 189,886 2,278,632U8 Upp 189,886 0
P6404 Kaggwa Henry 2,113,920U8 Upp 176,160 2,113,920U8 Upp 176,160 0
P6402 Tweheyo Edmund 2,114,028U8 Upp 176,169 2,114,028U8 Upp 176,169 0
P6287 Namyalo Damalie 2,114,028U8 Upp 176,169 2,114,028U8 Upp 176,169 0
P6458 Kabengyere Lillian 3,217,548U7 Upp 268,129 3,217,548U7 Upp 268,129 0
P6412 Alanyo Joyce 3,841,824U7 Upp 320,152 3,841,824U7 Upp 320,152 0
P6247 Kakayi Jane Lillian 6,385,920U4 L 532,160 6,385,920U4 L 532,160 0
P6419 Ssekulima Edward Baleke 11,570,268U4 SC 964,189 11,570,268U4 SC 964,189 0
P6452 Nsubuga Emmanual Sande 11,620,440U4 SC 968,370 11,620,440U4 SC 968,370 0
P6420 Kaggwa Usamah Lutu 11,570,268U4 SC 964,189 11,570,268U4 SC 964,189 0
P6421 Natabo Miriam 11,570,268U4 SC 964,189 11,570,268U4 SC 964,189 0
P6276 Nafuna Sarah 13,137,684U3 SC 1,094,807 13,137,684U3 SC 1,094,807 0
P6129 Simon Kalanzi 13,137,684U3 SC 1,094,807 13,137,684U3 SC 1,094,807 0
P6354 Wamala Julius Namusanga 13,137,684U3 SC 1,094,807 13,137,684U3 SC 1,094,807 0
P6105 Ahimbisibwe Michael 13,650,864U3 SC 1,137,572 13,650,864U3 SC 1,137,572 0
ME/STF/285 John Tumuhimbise 14,353,800U3 SC 1,196,150 14,353,800U3 SC 1,196,150 0
Page 1
187
Ministry of Energy and Mineral DevelopmentVote 017 FY 2014/15
Vote Function 0301: Energy Planning,Management & Infrastructure Dev't
Program : Energy Resources Department
CostCentre: Energy Resources
District : Kampala
File Number Annual
Salary as per
Salary
Scale as
per payslip
Monthly
Salary as per
payslip
Staff Names Annual
Salary as per
Appointing
Authority
Salary
Scale as
per
Appointing
Monthly
Salary as per
Appointing
Authority
Annual
Salary
Variance
P6171 Atwine Abdon 13,650,864U3 SC 1,137,572 13,650,864U3 SC 1,137,572 0
P6516 Tamusuza Kambagira Amos 13,650,864U3 SC 1,137,572 13,650,864U3 SC 1,137,572 0
ME/STF/286 Godfrey Kimuli 14,353,800U3 SC 1,196,150 14,353,800U3 SC 1,196,150 0
P5432 Mbonye Arsen 18,852,948U2 SC 1,571,079 18,852,948U2 SC 1,571,079 0
P6106 Wafula Wilson 18,993,588U2 SC 1,582,799 18,993,588U2 SC 1,582,799 0
P6010 Cecilia Nakiranda Menya. 19,438,008U2 SC 1,619,834 19,438,008U2 SC 1,619,834 0
P5433 James Baanabe Isigoma 24,547,224U1E (SC) 2,045,602 24,547,224U1E (SC) 2,045,602 0
P6009 Bidasala Henry Igaga 24,547,224U1E (SC) 2,045,602 24,547,224U1E (SC) 2,045,602 0
P4589 Ndawula Godfrey 24,547,224U1E (SC) 2,045,602 24,547,224U1E (SC) 2,045,602 0
Total Annual Salary (Ushs) for Program : Energy Resources Departmen 314,946,516 314,946,516 0
Vote Function 0303: Petroleum Exploration, Development & Production
Program : Petroleum Exploration Production Department
CostCentre: Petroleum Exploration and Produc
District : PEPD Entebbe
File Number Annual
Salary as per
Salary
Scale as
per payslip
Monthly
Salary as per
payslip
Staff Names Annual
Salary as per
Appointing
Authority
Salary
Scale as
per
Appointing
Monthly
Salary as per
Appointing
Authority
Annual
Salary
Variance
P.6275 Dogu Christino 2,134,164177,847 2,134,164U8 L 177,847 0
Page 2
188
Ministry of Energy and Mineral DevelopmentVote 017 FY 2014/15
Vote Function 0303: Petroleum Exploration, Development & Production
Program : Petroleum Exploration Production Department
CostCentre: Petroleum Exploration and Produc
District : PEPD Entebbe
File Number Annual
Salary as per
Salary
Scale as
per payslip
Monthly
Salary as per
payslip
Staff Names Annual
Salary as per
Appointing
Authority
Salary
Scale as
per
Appointing
Monthly
Salary as per
Appointing
Authority
Annual
Salary
Variance
P.6474 Nakkazi Joan 2,114,028U8 L 176,169 2,114,028U8 L 176,169 0
P.6092 Joseph Mubongi 2,134,164U8 L 177,847 2,134,164U8 L 177,847 0
P.6288 Omuturu ondia Florence 2,114,028U8 L 176,169 2,114,028U8 L 176,169 0
P.6473 Nakawesi Moureen 2,114,028U8 L 176,169 2,114,028U8 L 176,169 0
P.6265 Nelson Agiryo 2,114,028U8 Upp 176,169 2,114,028U8 Upp 176,169 0
P.6268 Robert Biryaho 2,114,028U8 Upp 176,169 2,114,028U8 Upp 176,169 0
P.6478 Kimala Musisi David 2,114,028U8 Upp 176,169 2,114,028U8 Upp 176,169 0
P.6432 Kijoma Patrick 2,114,028U8 Upp 176,169 2,114,028U8 Upp 176,169 0
P.6400 Olwora Fred Willies 2,114,028U8 Upp 176,169 2,114,028U8 Upp 176,169 0
P.6388 Keeya Fred Kintu 2,114,028U8 Upp 176,169 2,114,028U8 Upp 176,169 0
P.6384 Katula Frank 2,114,028U8 Upp 176,169 2,114,028U8 Upp 176,169 0
P.6385 Bwana Alexis 2,114,028U8 Upp 176,169 2,114,028U8 Upp 176,169 0
P.6140 Edward .M. Takorakubi 2,410,872U8 Upp 200,906 2,410,872U8 Upp 200,906 0
P.6387 Byamukama Wilson 2,114,028U8 Upp 176,169 2,114,028U8 Upp 176,169 0
P.5327 James Sande 2,366,004U8 Upp 197,167 2,366,004U8 Upp 197,167 0
P.6062 Sebugenyi Musoke David 2,321,856U8 Upp 193,488 2,321,856U8 Upp 193,488 0
P.6064 Edward Ssenyondo 2,278,632U8 Upp 189,886 2,278,632U8 Upp 189,886 0
P.5443 Aaron Sserubiri Musoke 2,366,004U8 Upp 197,167 2,366,004U8 Upp 197,167 0
P6460 Namulwanyi Robinah 3,848,268U7 L 320,689 3,848,268U7 L 320,689 0
Page 3
189
Ministry of Energy and Mineral DevelopmentVote 017 FY 2014/15
Vote Function 0303: Petroleum Exploration, Development & Production
Program : Petroleum Exploration Production Department
CostCentre: Petroleum Exploration and Produc
District : PEPD Entebbe
File Number Annual
Salary as per
Salary
Scale as
per payslip
Monthly
Salary as per
payslip
Staff Names Annual
Salary as per
Appointing
Authority
Salary
Scale as
per
Appointing
Monthly
Salary as per
Appointing
Authority
Annual
Salary
Variance
P.6383 Wathum Peter 3,217,548U7 Upp 268,129 3,217,548U7 Upp 268,129 0
P.6368 Kasasa William 3,217,548U7 Upp 268,129 3,217,548U7 Upp 268,129 0
P.6382 Lule Amos 3,217,548U7 Upp 268,129 3,217,548U7 Upp 268,129 0
P6493 Okello Charles 3,217,548U7 Upp 268,129 3,217,548U7 Upp 268,129 0
P.6379 Yahaya Muzani 4,031,784U6 Upp 335,982 4,031,784U6 Upp 335,982 0
P.6431 Ssenabulya Andrew 13,223,868U6 Upp 1,101,989 13,223,868U6 Upp 1,101,989 0
P.6407 Byona Susan 5,263,524U6 Upp 438,627 5,263,524U6 Upp 438,627 0
P.6267 Michael S.T.Weteeka 4,031,784U6 Upp 335,982 4,031,784U6 Upp 335,982 0
P.3839 Kenneth Karusya 4,336,380U6 Upp 361,365 4,336,380U6 Upp 361,365 0
P.6378 Anicet Mbonye 4,031,784U6 Upp 335,982 4,031,784U6 Upp 335,982 0
P.5338 Ngabirano Arthur 4,497,960U6 Upp 374,830 4,497,960U6 Upp 374,830 0
P.6367 Naome Katambara 4,919,616U5 L 409,968 4,919,616U5 L 409,968 0
P.6204 Ainobyona Christine 6,624,756U5 Upp 552,063 6,624,756U5 Upp 552,063 0
P.6376 Kuhasire David Dias 6,842,592U5 Upp 570,216 6,842,592U5 Upp 570,216 0
P.6377 Etano Godfrey 6,624,756U5 Upp 552,063 6,624,756U5 Upp 552,063 0
P.6454 Ekunu Moses 6,616,596U4 L 551,383 6,616,596U4 L 551,383 0
P.6418 Ariko Denis 11,570,268U4 SC 964,189 11,570,268U4 SC 964,189 0
P.6138 Mulinde David 11,738,172U4 SC 978,181 11,738,172U4 SC 978,181 0
P.6448 Basiima David Ahimbisibwe 11,570,268U4 SC 964,189 11,570,268U4 SC 964,189 0
Page 4
190
Ministry of Energy and Mineral DevelopmentVote 017 FY 2014/15
Vote Function 0303: Petroleum Exploration, Development & Production
Program : Petroleum Exploration Production Department
CostCentre: Petroleum Exploration and Produc
District : PEPD Entebbe
File Number Annual
Salary as per
Salary
Scale as
per payslip
Monthly
Salary as per
payslip
Staff Names Annual
Salary as per
Appointing
Authority
Salary
Scale as
per
Appointing
Monthly
Salary as per
Appointing
Authority
Annual
Salary
Variance
P.6174 Irumba Bright Clovice 11,620,440U4 SC 968,370 11,620,440U4 SC 968,370 0
P.6491 Ayaa Anthony 11,570,268U4 SC 964,189 11,570,268U4 SC 964,189 0
P.6511 Ssuubi Joshua 11,125,248U4 SC 927,104 11,125,248U4 SC 927,104 0
P.6179 Ochan Andrew 11,570,268U4 SC 964,189 11,570,268U4 SC 964,189 0
P.6366 Mugumya Winston 11,620,440U4 SC 968,370 11,620,440U4 SC 968,370 0
P.6194 Nyombi Alex 12,488,796U4 SC 1,040,733 12,488,796U4 SC 1,040,733 0
P.6004 Naboth Mugerwa 11,738,172U4 SC 978,181 11,738,172U4 SC 978,181 0
P.6280 Tonny Ssuna Ddungu 11,570,268U4 SC 964,189 11,570,268U4 SC 964,189 0
P.6361 Richard Nuwagaba 11,570,268U4 SC 964,189 11,570,268U4 SC 964,189 0
P.6300 Sserubiri Tonny 12,020,892U4 SC 1,001,741 12,020,892U4 SC 1,001,741 0
P.6357 Tumushabe Wilson Mbile 11,570,268U4 SC 964,189 11,570,268U4 SC 964,189 0
P.6358 Mugizi Herbert 11,570,268U4 SC 964,189 11,570,268U4 SC 964,189 0
P.6359 Enach Steven 11,570,268U4 SC 964,189 11,570,268U4 SC 964,189 0
P.6360 Wandera Robert Omwembe 11,570,268U4 SC 964,189 11,570,268U4 SC 964,189 0
P.6363 Sempala Vivienne 11,570,268U4 SC 964,189 11,570,268U4 SC 964,189 0
P.6285 Njabire Nurudin 11,570,268U4 SC 964,189 11,570,268U4 SC 964,189 0
P.6284 Korutaro Caroline 11,570,268U4 SC 964,189 11,570,268U4 SC 964,189 0
P.6364 Okello Michael 11,570,268U4 SC 964,189 11,570,268U4 SC 964,189 0
P.6365 Amusugut Catherine Padde 11,570,268U4 SC 964,189 11,570,268U4 SC 964,189 0
Page 5
191
Ministry of Energy and Mineral DevelopmentVote 017 FY 2014/15
Vote Function 0303: Petroleum Exploration, Development & Production
Program : Petroleum Exploration Production Department
CostCentre: Petroleum Exploration and Produc
District : PEPD Entebbe
File Number Annual
Salary as per
Salary
Scale as
per payslip
Monthly
Salary as per
payslip
Staff Names Annual
Salary as per
Appointing
Authority
Salary
Scale as
per
Appointing
Monthly
Salary as per
Appointing
Authority
Annual
Salary
Variance
P.6510 Padde Semu 11,125,248U4SC 927,104 11,125,248U4 SC 927,104 0
P.6172 Ongodia Bernard 13,650,864U3 SC 1,137,572 13,650,864U3 SC 1,137,572 0
P.6111 Lukaye Joshua 13,839,324U3 SC 1,153,277 13,839,324U3 SC 1,153,277 0
P.6116 Obita Philip 13,137,684U3 SC 1,094,807 13,137,684U3 SC 1,094,807 0
P.6114 Nabbanja Proscovia 13,650,744U3 SC 1,137,562 13,650,744U3 SC 1,137,562 0
P.5523 Robert Tugume 21,735,864U2SC 1,811,322 21,735,864U2SC 1,811,322 0
P.5425 Frank Mugisha 22,453,920U2SC 1,871,160 22,453,920U2SC 1,871,160 0
P.6104 Abeinomugisha Dozith. 18,852,948U2SC 1,571,079 18,852,948U2SC 1,571,079 0
P.5385 Fred Kabanda 21,735,864U2SC 1,811,322 21,735,864U2SC 1,811,322 0
P.5424 Honey Malinga 24,547,224U1 SC 2,045,602 24,547,224U1 SC 2,045,602 0
P.4886 Robert Kasande 24,858,324U1E SC 2,071,527 24,858,324U1E SC 2,071,527 0
P.4477 Ernest N.T. Rubondo 27,378,600U1SE 2,281,550 27,378,600U1SE 2,281,550 0
Total Annual Salary (Ushs) for Program : Petroleum Exploration Produ 612,016,680 612,016,680 0
Vote Function 0304: Petroleum Supply, Infrastructure and Regulation
Program : Petroleum Supply Department
CostCentre: Petroleum Supply
Page 6
192
Ministry of Energy and Mineral DevelopmentVote 017 FY 2014/15
Vote Function 0304: Petroleum Supply, Infrastructure and Regulation
Program : Petroleum Supply Department
CostCentre: Petroleum Supply
District : Kampala
File Number Annual
Salary as per
Salary
Scale as
per payslip
Monthly
Salary as per
payslip
Staff Names Annual
Salary as per
Appointing
Authority
Salary
Scale as
per
Appointing
Monthly
Salary as per
Appointing
Authority
Annual
Salary
Variance
P.6472 Nakato Moureen 2,113,920U8 L 176,160 2,113,920U8 L 176,160 0
P.6405 Sekate Robert 2,114,028U8 Upp 176,169 2,114,028U8 Upp 176,169 0
P.6326 Batabeirwe Munono Maggie 4,031,784U6 L 335,982 4,031,784U6 L 335,982 0
P.6373 Mugabe Esau 6,842,592U5 SC 570,216 6,842,592U5 SC 570,216 0
P.6440 Oketch Ogola Dominic 6,624,756U5 SC 552,063 6,624,756U5 SC 552,063 0
P.6429 Kaganzi Godfrey 6,624,756U5 SC 552,063 6,624,756U5 SC 552,063 0
P.6374 Karungi Betty 6,624,756U5 SC 552,063 6,624,756U5 SC 552,063 0
P.6428 Kyambadde George 6,624,756U5 SC 552,063 6,624,756U5 SC 552,063 0
P.6375 Egangu Joseph 6,624,756U5 SC 552,063 6,624,756U5 SC 552,063 0
P.6515 Nakyanzi Miriam 6,847,272U4 L 570,606 6,847,272U4 L 570,606 0
P.6447 Agaba Charles 11,570,268U4 SC 964,189 11,570,268U4SC 964,189 0
P.6448 Ahimbisibwe Daudi 11,570,268U4 SC 964,189 11,570,268U4SC 964,189 0
P.6330 Odoch Robert 11,738,172U4 SC 978,181 11,738,172U4SC 978,181 0
P.6505 Tinkasiimire Peter 11,125,248U4 SC 927,104 11,125,248U4SC 927,104 0
P.6331 Andrew Oboke 11,570,268U4 SC 964,189 11,570,268U4SC 964,189 0
P.6344 Byaruhanga Jane Mbabazi 11,570,268U4 SC 964,189 11,570,268U4SC 964,189 0
P.6332 Wilbrod Byamukama 11,570,268U4 SC 964,189 11,570,268U4SC 964,189 0
P.6508 Nyakahuma Joel 11,125,248U4SC 927,104 11,125,248U4SC 927,104 0
P.6444 Niwamanya Shallon 11,570,268U4 Upp 964,189 11,570,268U4Upp 964,189 0
Page 7
193
Ministry of Energy and Mineral DevelopmentVote 017 FY 2014/15
Vote Function 0304: Petroleum Supply, Infrastructure and Regulation
Program : Petroleum Supply Department
CostCentre: Petroleum Supply
District : Kampala
File Number Annual
Salary as per
Salary
Scale as
per payslip
Monthly
Salary as per
payslip
Staff Names Annual
Salary as per
Appointing
Authority
Salary
Scale as
per
Appointing
Monthly
Salary as per
Appointing
Authority
Annual
Salary
Variance
P.6333 Maali Nelson 13,137,684U4Upp 1,094,807 13,137,684U4Upp 1,094,807 0
P.6446 Bateebe Irene Pauline 11,570,268U4Upp 964,189 11,570,268U4Upp 964,189 0
P.6449 Wanakoli Julius Masera 11,570,268U4Upp 964,189 11,570,268U4Upp 964,189 0
P.6347 Byokunda Sperato 13,282,284U3 SC 1,106,857 13,282,284U3 SC 1,106,857 0
P.6345 Sherura Stephen Bainenama 13,137,684U3 SC 1,094,807 13,137,684U3 SC 1,094,807 0
P.6415 Mitango Abubaker Ahmed 13,282,284U3 SC 1,106,857 13,282,284U3 SC 1,106,857 0
P.6181 Kiguli Disan 13,282,284U3 SC 1,106,857 13,282,284U3 SC 1,106,857 0
P.6424 Ssenoga James 13,137,684U3 SC 1,094,807 13,137,684U3 SC 1,094,807 0
P.6423 Nakayiza Faridah Nsanja 13,282,284U3 SC 1,106,857 13,282,284U3 SC 1,106,857 0
P.6353 Aguti Caroline 13,650,864U3Upp 1,137,572 13,650,864U3Upp 1,137,572 0
P.6346 Mwesigye Nuwamanya Edward 18,852,948U2 SC 1,571,079 18,852,948U2 SC 1,571,079 0
P.6426 Rwakasanga Gershom 18,993,588U2 SC 1,582,799 18,993,588U2 SC 1,582,799 0
P.6242 Elangot Joseph 19,894,188U2 SC 1,657,849 19,894,188U2 SC 1,657,849 0
P.6108 Banaga Baingi .G 18,993,588U2 SC 1,582,799 18,993,588U2 SC 1,582,799 0
P.6136 Barisigara Stephen 19,438,008U2 SC 1,619,834 19,438,008U2 SC 1,619,834 0
P.6349 John Friday 18,852,948U1E 1,571,079 18,852,948U1E 1,571,079 0
P.6356 Habumugisha John Bosco 18,850,980U1E (SC) 1,570,915 18,850,980U1E (SC) 1,570,915 0
P.6015 Frank Justaf Tukwasibwe 27,378,600U1SE 2,281,550 27,378,600U1SE 2,281,550 0
Total Annual Salary (Ushs) for Program : Petroleum Supply Departmen 449,072,088 449,072,088 0
Page 8
194
Ministry of Energy and Mineral DevelopmentVote 017 FY 2014/15
Vote Function 0305: Mineral Exploration, Development & Production
Program : Geological Survey and Mines Department
CostCentre: Geological Survey and Mines
District : GSMD Entebbe
File Number Annual
Salary as per
Salary
Scale as
per payslip
Monthly
Salary as per
payslip
Staff Names Annual
Salary as per
Appointing
Authority
Salary
Scale as
per
Appointing
Monthly
Salary as per
Appointing
Authority
Annual
Salary
Variance
P.6260 Mulindwa Silaji 2,726,880U8 Upp 227,240 2,726,880U8 Upp 227,240 0
P.6210 Kwezi Julius 2,410,872U8 Upp 200,906 2,410,872U8 Upp 200,906 0
P.6258 Namuli Dorothy 2,114,028U8 Upp 176,169 2,114,028U8 Upp 176,169 0
P.5335 Norah Kansiime 2,366,004U8 Upp 197,167 2,366,004U8 Upp 197,167 0
P.6281 Eunice Namono 2,321,856U8 Upp 193,488 2,321,856U8 Upp 193,488 0
P.6203 Kayiwa Joseph 2,366,004U8Upp 197,167 2,366,004U8Upp 197,167 0
P.6282 Kiggundu Muhammed 2,366,004U8Upp 197,167 2,366,004U8Upp 197,167 0
P.6403 Akaa Morris 2,114,028U8Upp 176,169 2,114,028U8Upp 176,169 0
P.6208 GodfreyWabbi 2,321,856U8Upp 193,488 2,321,856U8Upp 193,488 0
P.6209 Denis Musisi Kanoonya 2,321,856U8Upp 193,488 2,321,856U8Upp 193,488 0
P.6401 Baguma Stephen 2,114,028U8Upp 176,169 2,114,028U8Upp 176,169 0
P.6198 Atwine Mark 3,217,548U7 Upp 268,129 3,217,548U7 Upp 268,129 0
P.3381 Namukasa Grace 4,605,120U6 L 383,760 4,605,120U6 L 383,760 0
P.6261 Nyago Joseph 4,031,784U6 Upp 335,982 4,031,784U6 Upp 335,982 0
P.6302 Eneku Gerald 4,031,784U6 Upp 335,982 4,031,784U6 Upp 335,982 0
P.6306 Mubiru Yosia 6,624,756U5 L 552,063 6,624,756U5 L 552,063 0
P.6305 Wegosasa Sarah 6,624,756U5 L 552,063 6,624,756U5 L 552,063 0
P.6430 Ajule Moses 6,842,592U5 SC 570,216 6,842,592U5 SC 570,216 0
P.6002 Mathias Mugere 8,411,604U5 SC 700,967 8,411,604U5 SC 700,967 0
Page 9
195
Ministry of Energy and Mineral DevelopmentVote 017 FY 2014/15
Vote Function 0305: Mineral Exploration, Development & Production
Program : Geological Survey and Mines Department
CostCentre: Geological Survey and Mines
District : GSMD Entebbe
File Number Annual
Salary as per
Salary
Scale as
per payslip
Monthly
Salary as per
payslip
Staff Names Annual
Salary as per
Appointing
Authority
Salary
Scale as
per
Appointing
Monthly
Salary as per
Appointing
Authority
Annual
Salary
Variance
P.6196 Muzito Muhamad 7,303,680U5 SC 608,640 7,303,680U5 SC 608,640 0
P.6315 Robert Mufuta 8,411,604U5 SC 700,967 8,411,604U5 SC 700,967 0
P.5410 Godfrey Birabi 7,303,680U5 SC 608,640 7,303,680U5 SC 608,640 0
P.6488 Onyege Henry 11,570,268U4 SC 964,189 11,570,268U4 SC 964,189 0
P.6158 Nandutu Seera 8,480,016U4 L 706,668 8,480,016U4 L 706,668 0
P.6336 Eriya Kahwa 11,738,172U4 SC 978,181 11,738,172U4 SC 978,181 0
P.6307 Namboyera Annet 11,570,268U4 SC 964,189 11,570,268U4 SC 964,189 0
P.6509 Olwa James 11,125,248U4 SC 927,104 11,125,248U4 SC 927,104 0
P.6507 Mulindwa Henry 11,125,248U4 SC 927,104 11,125,248U4 SC 927,104 0
P.6490 Mayanja Jackson 11,570,268U4 SC 964,189 11,570,268U4 SC 964,189 0
P.6487 Tuunde Keith 11,570,268U4 SC 964,189 11,570,268U4 SC 964,189 0
P.6486 Nnakirijja Jacqueline 11,570,268U4 SC 964,189 11,570,268U4 SC 964,189 0
P.6484 Sudan Birungi Unity 11,570,268U4 SC 964,189 11,570,268U4 SC 964,189 0
P.6453 Bagiire Timothy 11,570,268U4 SC 964,189 11,570,268U4 SC 964,189 0
P.6451 Nangoku Naomi Mumoita 11,570,268U4 SC 964,189 11,570,268U4 SC 964,189 0
P.6328 Vicent Kedi 11,570,268U4 SC 964,189 11,570,268U4 SC 964,189 0
P.4731 Kibalama Harriet Molly 12,497,076U4 SC 1,041,423 12,497,076U4 SC 1,041,423 0
P.6301 Nyakecho Catherine 11,570,268U4 SC 964,189 11,570,268U4 SC 964,189 0
P.6227 Lugoko Paul 11,570,268U4 SC 964,189 11,570,268U4 SC 964,189 0
Page 10
196
Ministry of Energy and Mineral DevelopmentVote 017 FY 2014/15
Vote Function 0305: Mineral Exploration, Development & Production
Program : Geological Survey and Mines Department
CostCentre: Geological Survey and Mines
District : GSMD Entebbe
File Number Annual
Salary as per
Salary
Scale as
per payslip
Monthly
Salary as per
payslip
Staff Names Annual
Salary as per
Appointing
Authority
Salary
Scale as
per
Appointing
Monthly
Salary as per
Appointing
Authority
Annual
Salary
Variance
P.5411 Isaiah Tumwikirize 12,145,428U4 SC 1,012,119 12,145,428U4 SC 1,012,119 0
P.5427 Ruth Nasingwa 12,497,076U4 SC 1,041,423 12,497,076U4 SC 1,041,423 0
P.6148 Esau Arinaitwe 11,570,268U4 SC 964,189 11,570,268U4 SC 964,189 0
P.6226 Lugaizi Isa 12,506,424U4 SC 1,042,202 12,506,424U4 SC 1,042,202 0
P.6279 Kiggwe Richard 11,570,268U4 SC 964,189 11,570,268U4 SC 964,189 0
P.6229 Ekiryagana Martin 11,570,268U4 SC 964,189 11,570,268U4 SC 964,189 0
P.6231 Muhwezi Katomi Deus 11,570,268U4 SC 964,189 11,570,268U4 SC 964,189 0
P.6240 Lajwe Grace 11,570,268U4 SC 964,189 11,570,268U4 SC 964,189 0
P.6254 Edward Marimira 11,570,268U4 SC 964,189 11,570,268U4 SC 964,189 0
P.6224 Mawejje Peter 11,570,268U4 SC 964,189 11,570,268U4 SC 964,189 0
P.6514 Richard Nelson Birungi 6,140,304U4L 511,692 6,140,304U4L 511,692 0
P.6450 Naiga Erios 11,570,268U4 SC 964,189 11,570,268U4SC 964,189 0
P.6417 Pule Stellah 11,570,268U4 SC 964,189 11,570,268U4SC 964,189 0
P.6335 Sebagala David 11,570,268U4 SC 964,189 11,570,268U4SC 964,189 0
P.6416 Okewling John Kennedy 11,570,268U4 SC 964,189 11,570,268U4SC 964,189 0
P.6221 Kobusheshe Joseph 12,492,948U4 SC 1,041,079 12,492,948U4SC 1,041,079 0
P.6506 Tabaaro Muheirwe Morris 11,125,248U4SC 927,104 11,125,248U4SC 927,104 0
P.6180 Natukunda James Francis 13,137,684U3 SC 1,094,807 13,137,684U3 SC 1,094,807 0
P.3479 Peter Turyasingura 14,754,708U3 SC 1,229,559 14,754,708U3 SC 1,229,559 0
Page 11
197
Ministry of Energy and Mineral DevelopmentVote 017 FY 2014/15
Vote Function 0305: Mineral Exploration, Development & Production
Program : Geological Survey and Mines Department
CostCentre: Geological Survey and Mines
District : GSMD Entebbe
File Number Annual
Salary as per
Salary
Scale as
per payslip
Monthly
Salary as per
payslip
Staff Names Annual
Salary as per
Appointing
Authority
Salary
Scale as
per
Appointing
Monthly
Salary as per
Appointing
Authority
Annual
Salary
Variance
P.6383 Nassaka Sylivia Grace 13,137,684U3 SC 1,094,807 13,137,684U3 SC 1,094,807 0
P.6253 Ngada Henry 12,050,640U3 SC 1,004,220 12,050,640U3 SC 1,004,220 0
P.6235 Fred Kigereigu 14,030,568U3 SC 1,169,214 14,030,568U3 SC 1,169,214 0
P.6222 Tumwine Annet 13,137,684U3 SC 1,094,807 13,137,684U3 SC 1,094,807 0
P.6147 Joseph Patrick Okedi 13,839,324U3 SC 1,153,277 13,839,324U3 SC 1,153,277 0
P.6144 Grace Deborah Nakku Nvule 13,282,284U3 SC 1,106,857 13,282,284U3 SC 1,106,857 0
P.6020 Andrew Katumwehe 13,137,684U3 SC 1,094,807 13,137,684U3 SC 1,094,807 0
P.5264 Edward Isabirye 13,137,648U3 SC 1,094,804 13,137,648U3 SC 1,094,804 0
P.5438 Gabriel Data 14,030,568U3 SC 1,169,214 14,030,568U3 SC 1,169,214 0
P.6013 Fred .A. Tugume 19,438,008U2 SC 1,619,834 19,438,008U2 SC 1,619,834 0
P.6016 Grace Lubembe Nassuna 21,972,132U2 SC 1,831,011 21,972,132U2 SC 1,831,011 0
P.5384 Agnes Alaba 21,735,864U2 SC 1,811,322 21,735,864U2 SC 1,811,322 0
P.5380 Christopher Benon Rudigizah 19,438,008U2 SC 1,619,834 19,438,008U2 SC 1,619,834 0
P.6234 Lubangakene Chris 18,852,948U2 SC 1,571,079 18,852,948U2 SC 1,571,079 0
P.5260 Vincent Kato 19,214,388U2 SC 1,601,199 19,214,388U2 SC 1,601,199 0
P.5025 Zachary Baguma 22,453,920U2 SC 1,871,160 22,453,920U2 SC 1,871,160 0
P.4741 Edwards Katto 24,858,324U1E (SC) 2,071,527 24,858,324U1E (SC) 2,071,527 0
P.5262 Godfery Bahati 23,902,236U1E (SC) 1,991,853 23,902,236U1E (SC) 1,991,853 0
Page 12
198
Ministry of Energy and Mineral DevelopmentVote 017 FY 2014/15
Vote Function 0305: Mineral Exploration, Development & Production
Program : Geological Survey and Mines Department
CostCentre: Geological Survey and Mines
District : Hoima Station
File Number Annual
Salary as per
Salary
Scale as
per payslip
Monthly
Salary as per
payslip
Staff Names Annual
Salary as per
Appointing
Authority
Salary
Scale as
per
Appointing
Monthly
Salary as per
Appointing
Authority
Annual
Salary
Variance
P.6273 Safian Katusiime 2,366,004U8 Upp 197,167 2,366,004U8 Upp 197,167 0
District : Kabale Station
File Number Annual
Salary as per
Salary
Scale as
per payslip
Monthly
Salary as per
payslip
Staff Names Annual
Salary as per
Appointing
Authority
Salary
Scale as
per
Appointing
Monthly
Salary as per
Appointing
Authority
Annual
Salary
Variance
P.6304 Amunyo Gideon 4,031,784U6 Upp 335,982 4,031,784U6 Upp 335,982 0
District : Ntungamu Station
File Number Annual
Salary as per
Salary
Scale as
per payslip
Monthly
Salary as per
payslip
Staff Names Annual
Salary as per
Appointing
Authority
Salary
Scale as
per
Appointing
Monthly
Salary as per
Appointing
Authority
Annual
Salary
Variance
P.6297 Gabriel Muhairwe 1,908,408U8L 159,034 1,908,408U8L 159,034 0
District : Tororo Station
File Number Annual
Salary as per
Salary
Scale as
per payslip
Monthly
Salary as per
payslip
Staff Names Annual
Salary as per
Appointing
Authority
Salary
Scale as
per
Appointing
Monthly
Salary as per
Appointing
Authority
Annual
Salary
Variance
P.4708 Nathan Mushetsya 11,570,268U5 SC 964,189 11,570,268U5 SC 964,189 0
Total Annual Salary (Ushs) for Program : Geological Survey and Mines 828,790,176 828,790,176 0
Vote Function 0349: Policy, Planning and Support Services
Page 13
199
Ministry of Energy and Mineral DevelopmentVote 017 FY 2014/15
Vote Function 0349: Policy, Planning and Support Services
Program : Headquarters
CostCentre: Headquarters
District : GSMD Entebbe
File Number Annual
Salary as per
Salary
Scale as
per payslip
Monthly
Salary as per
payslip
Staff Names Annual
Salary as per
Appointing
Authority
Salary
Scale as
per
Appointing
Monthly
Salary as per
Appointing
Authority
Annual
Salary
Variance
P6476 Kellen Kabaramagi 3,217,548U7 Upp 268,129 3,217,548U7 Upp 268,129 0
P6534 Alumo Aggrey 3,269,772U7 Upp 272,481 3,269,772U7 Upp 272,481 0
District : Gulu Branch
File Number Annual
Salary as per
Salary
Scale as
per payslip
Monthly
Salary as per
payslip
Staff Names Annual
Salary as per
Appointing
Authority
Salary
Scale as
per
Appointing
Monthly
Salary as per
Appointing
Authority
Annual
Salary
Variance
P6321 Ajok Alice 2,321,856U8 Upp 193,488 2,321,856U8 Upp 193,488 0
District : Kampala
File Number Annual
Salary as per
Salary
Scale as
per payslip
Monthly
Salary as per
payslip
Staff Names Annual
Salary as per
Appointing
Authority
Salary
Scale as
per
Appointing
Monthly
Salary as per
Appointing
Authority
Annual
Salary
Variance
P6096 Kiffude Lukuman 2,321,856U8 L 193,488 2,321,856U8 L 193,488 0
P4818 Naggai Immaculate 2,410,872U8 L 200,906 2,410,872U8 L 200,906 0
P6264 Wakoko Patrick 2,114,028U8 L 176,169 2,114,028U8 L 176,169 0
P6188 Akankwansa Aeron 2,278,632U8 Upp 189,886 2,278,632U8 Upp 189,886 0
P6398 Lokol Joseph 2,321,856U8 Upp 193,488 2,321,856U8 Upp 193,488 0
P6246 Namara Judith 2,321,856U8 Upp 193,488 2,321,856U8 Upp 193,488 0
P4375 Kasumba Leonard 2,366,004U8 Upp 197,167 2,366,004U8 Upp 197,167 0
Page 14
200
Ministry of Energy and Mineral DevelopmentVote 017 FY 2014/15
Vote Function 0349: Policy, Planning and Support Services
Program : Headquarters
CostCentre: Headquarters
District : Kampala
File Number Annual
Salary as per
Salary
Scale as
per payslip
Monthly
Salary as per
payslip
Staff Names Annual
Salary as per
Appointing
Authority
Salary
Scale as
per
Appointing
Monthly
Salary as per
Appointing
Authority
Annual
Salary
Variance
P3381 Namukasa Gertrude 2,321,856U8 Upp 193,488 2,321,856U8 Upp 193,488 0
P5370 Kagoya Annet 2,321,856U8 Upp 193,488 2,321,856U8 Upp 193,488 0
P4172 Kyanzi John 2,366,004U8 Upp 197,167 2,366,004U8 Upp 197,167 0
P6391 Byaruhanga Franklin 3,841,824U7 Upp 320,152 3,841,824U7 Upp 320,152 0
P6390 Muwonge Mathew 3,217,548U7 Upp 268,129 3,217,548U7 Upp 268,129 0
P6367 Harriet Kamugisha Katushabe 3,217,548U7 Upp 268,129 3,217,548U7 Upp 268,129 0
P6468 Naggayi Sarah 3,841,824U7 Upp 320,152 3,841,824U7 Upp 320,152 0
P6523 Mbatuusa Harriet 3,177,396U7 Upp 264,783 3,177,396U7 Upp 264,783 0
P6338 Nalule Stella 3,323,028U7 Upp 276,919 3,323,028U7 Upp 276,919 0
P6479 Muzaale Mugabi Harriet 3,269,772U7 Upp 272,481 3,269,772U7 Upp 272,481 0
P6427 Kagoya Joyce Kawuma 3,217,548U7 Upp 268,129 3,217,548U7 Upp 268,129 0
P6480 Musisi Grace 3,217,548U7 Upp 268,129 3,217,548U7 Upp 268,129 0
P6498 Akullu Janet Anita 3,217,548U7 Upp 268,129 3,217,548U7 Upp 268,129 0
P6263 Namukwaya Harriet 3,217,548U7 Upp 268,129 3,217,548U7 Upp 268,129 0
P6255 Namalera Margaret 3,841,824U7 Upp 320,152 3,841,824U7 Upp 320,152 0
P6213 Kyamuni Mary 3,841,824U7 Upp 320,152 3,841,824U7 Upp 320,152 0
P6477 Nakamate Ruth 3,217,548U7 Upp 268,129 3,217,548U7 Upp 268,129 0
P5312 Echongu Henry 3,841,824U7 Upp 320,152 3,841,824U7 Upp 320,152 0
P6428 Timalirwe Beatrice 4,694,976U6 L 391,248 4,694,976U6 L 391,248 0
Page 15
201
Ministry of Energy and Mineral DevelopmentVote 017 FY 2014/15
Vote Function 0349: Policy, Planning and Support Services
Program : Headquarters
CostCentre: Headquarters
District : Kampala
File Number Annual
Salary as per
Salary
Scale as
per payslip
Monthly
Salary as per
payslip
Staff Names Annual
Salary as per
Appointing
Authority
Salary
Scale as
per
Appointing
Monthly
Salary as per
Appointing
Authority
Annual
Salary
Variance
P6241 Kizza Stephen 4,031,784U6 Upp 335,982 4,031,784U6Upp 335,982 0
P5195 Mpiriirwe Grace 4,105,680U6Upp 342,140 4,105,680U6Upp 342,140 0
P6437 Cherotich Allen 4,605,120U5 L 383,760 4,605,120U5 L 383,760 0
P6436 Ssenyonga Godfrey 4,605,120U5 L 383,760 4,605,120U5 L 383,760 0
P6337 Orena Vincent 5,521,572U5 Upp 460,131 5,521,572U5Upp 460,131 0
P6289 Wofuba Christopher Buyi 5,013,228U5 Upp 417,769 5,013,228U5Upp 417,769 0
P6442 Acii Joyce Alice 6,359,172U5 Upp 529,931 6,359,172U5Upp 529,931 0
P6520 Okok David 4,258,764U5Upp 354,897 4,258,764U5Upp 354,897 0
P6492 Namala Juliet 6,385,920U4 L 532,160 6,385,920U4 L 532,160 0
P6499 Namasaba Mary Mushikori 8,140,764U4 L 678,397 8,140,764U4 L 678,397 0
P6513 Nanyanzi Asiat 9,305,016U4 L 775,418 9,305,016U4 L 775,418 0
P6517 Kasozi Kizito 6,362,772U4 L 530,231 6,362,772U4 L 530,231 0
P6339 Akullo Judith 7,144,692U4 L 595,391 7,144,692U4 L 595,391 0
P6322 Bridget Lumala. M 7,144,692U4 L 595,391 7,144,692U4 L 595,391 0
P6496 Ahebwa K. Bruce 8,488,392U4 Upp 707,366 8,488,392U4 Upp 707,366 0
P6422 Kisawuzi Ian 11,570,268U4 Upp 964,189 11,570,268U4 Upp 964,189 0
P6341 Muhindo Partrick 9,305,016U4 Upp 775,418 9,305,016U4 Upp 775,418 0
P6518 Mughuma Constance 0U4 Upp 0U4 Upp 0
P6502 Kizito Mugerwa 8,481,420U4 Upp 706,785 8,481,420U4 Upp 706,785 0
Page 16
202
Ministry of Energy and Mineral DevelopmentVote 017 FY 2014/15
Vote Function 0349: Policy, Planning and Support Services
Program : Headquarters
CostCentre: Headquarters
District : Kampala
File Number Annual
Salary as per
Salary
Scale as
per payslip
Monthly
Salary as per
payslip
Staff Names Annual
Salary as per
Appointing
Authority
Salary
Scale as
per
Appointing
Monthly
Salary as per
Appointing
Authority
Annual
Salary
Variance
P6410 Hibajo Stephen Wabwire 9,957,504U3 L 829,792 9,957,504U3 L 829,792 0
P6395 Barasa Sam Philly 10,806,420U3 L 900,535 10,806,420U3 L 900,535 0
P6521 Nansubuga Rose 0U3 L 0U3 L 0
P6519 Atino Hellen 10,806,420U3 L 900,535 10,806,420U3 L 900,535 0
P6293 Nagwomu Alfred 10,806,420U3 L 900,535 10,806,420U3 L 900,535 0
P6324 Akol Grace 10,183,212U3 L 848,601 10,183,212U3 L 848,601 0
P6522 Hamza Wanusha 0 U3 L 0U3 L 0
P6185 Tibananuka Moses 10,298,076 U3 L 858,173 10,298,076U3 L 858,173 0
P6340 Oryema Charles 13,988,892U3 Upp 1,165,741 13,988,892U3 Upp 1,165,741 0
P6425 Dedeya Catherine 9,846,672U3 Upp 820,556 9,846,672U3 Upp 820,556 0
P6512 Ibrahim Mukwaya 10,955,256U3 Upp 912,938 10,955,256U3 Upp 912,938 0
P6184 Baziwe Isaac 10,688,772U3 Upp 890,731 10,688,772U3 Upp 890,731 0
P6484 Mulungwa Monica Eunice 10,806,420U3L 900,535 10,806,420U3L 900,535 0
P6475 Watera Susan 10,806,420U3Upp 900,535 10,806,420U3Upp 900,535 0
P6439 Carmella Atto 14,093,244U2 L 1,174,437 14,093,244U2 L 1,174,437 0
P6251 Muganwa Immaculate 13,109,316U2 L 1,092,443 13,109,316U2 L 1,092,443 0
P6456 Odoi Joseph Ochieng 16,660,812U2 Upp 1,388,401 16,660,812U2 Upp 1,388,401 0
P6130 Ajutu Emmanuel 14,423,004U2 Upp 1,201,917 14,423,004U2 Upp 1,201,917 0
P6504 Birabwa K. Dorothy 14,093,244U2 Upp 1,174,437 14,093,244U2 Upp 1,174,437 0
Page 17
203
Ministry of Energy and Mineral DevelopmentVote 017 FY 2014/15
Vote Function 0349: Policy, Planning and Support Services
Program : Headquarters
CostCentre: Headquarters
District : Kampala
File Number Annual
Salary as per
Salary
Scale as
per payslip
Monthly
Salary as per
payslip
Staff Names Annual
Salary as per
Appointing
Authority
Salary
Scale as
per
Appointing
Monthly
Salary as per
Appointing
Authority
Annual
Salary
Variance
P3444 F. A. Kabagambe-Kaliisa 30,150,684U1S 2,512,557 30,150,684U1S 2,512,557 0
P6461 Ssegawa Gyagenda Ronald 20,284,920U1SE 1,690,410 20,284,920U1SE 1,690,410 0
P6234 Ssenkole Stephen 2,114,028 U8 L 176,169 2,114,028 U8 L 176,169 0
District : PEPD Entebbe
File Number Annual
Salary as per
Salary
Scale as
per payslip
Monthly
Salary as per
payslip
Staff Names Annual
Salary as per
Appointing
Authority
Salary
Scale as
per
Appointing
Monthly
Salary as per
Appointing
Authority
Annual
Salary
Variance
P6175 Aheebwa Peninah 9,846,672U3 Upp 820,556 9,846,672U3 Upp 820,556 0
District : Tororo Station
File Number Annual
Salary as per
Salary
Scale as
per payslip
Monthly
Salary as per
payslip
Staff Names Annual
Salary as per
Appointing
Authority
Salary
Scale as
per
Appointing
Monthly
Salary as per
Appointing
Authority
Annual
Salary
Variance
P6277 Obbo Raphael 2,366,004U8 Upp 197,167 2,366,004U8 Upp 197,167 0
Total Annual Salary (Ushs) for Program : Headquarters 476,072,928 476,072,928 0
Program : Directorate
CostCentre: Directorate
Page 18
204
Ministry of Energy and Mineral DevelopmentVote 017 FY 2014/15
Vote Function 0349: Policy, Planning and Support Services
Program : Directorate
CostCentre: Directorate
District : Kampala
File Number Annual
Salary as per
Salary
Scale as
per payslip
Monthly
Salary as per
payslip
Staff Names Annual
Salary as per
Appointing
Authority
Salary
Scale as
per
Appointing
Monthly
Salary as per
Appointing
Authority
Annual
Salary
Variance
P6456 Kimbugwe John 2,278,632U8 Upp 189,886 2,278,632U8 Upp 189,886 0
P5238 Nuwamanya Vicent 2,321,856U8 Upp 193,488 2,321,856U8 Upp 193,488 0
P6411 Kantu Faith Irene 4,497,960U6 L 374,830 4,497,960U6 L 374,830 0
P5413 Eng. Paul Mubiru 29,047,008U1SE 2,420,584 29,047,008U1SE 2,420,584 0
Total Annual Salary (Ushs) for Program : Directorate 38,145,456 38,145,456 0
Total Annual Salary (Ushs) for : Ministry of Energy and Mineral Develop 2,719,043,844 2,719,043,844 0
Page 19
205
Rural Electrification Agency (REA)Vote:
Ministerial Policy StatementRural Electrification Agency (REA)
123
The chart below shows total funding allocations to the Vote by Vote Function over the medium term:
Table V1.1: Overview of Vote Expenditures (UShs Billion)(ii) Summary of Past Performance and Medium Term Budget Allocations
0
10
20
30
40
50
60
70
Ru
ral
Ele
ctri
fica
tio
n
Ush
s B
illi
on
2013/14 Approved Budget Estimates 2014/15 Budget Projections 2015/16 Budget Projections
Chart V1.1: Medium Term Budget Projections by Vote Function (Excluding Taxes, Arrears)
V1: Vote Overview
"To facilitate provision of electricity for socio-economic rural transformation in an equitable and
sustainable manner."
(i) Vote Mission Statement
(iii) Non Tax Revenue 77.7710.000 46.850 36.000
Excluding Taxes, Arrears 102.9380.000 69.589 97.380
Wage
Non Wage
GoU
Donor
GoU Total
Total GoU+Donor (MTEF)
Development
Recurrent
Taxes** 20.0000.000 0.000 1.663
Total Budget 45.1670.000 22.739 63.044
(ii) Arrears
and Taxes
Arrears 0.0000.000 0.000 0.000 N/A
N/A
N/A
N/A
N/A N/A
(i) Excluding Arrears, Taxes
0.0000.0000.000 0.000 0.000 0.000
0.0000.0000.000 0.000 0.000 0.000
18.03916.976 11.858 16.976 17.180
13.1128.1910.000 10.881 44.404 33.735
18.03916.9760.000 11.858 16.976 17.180
31.15025.1670.000 22.739 61.380 50.915
2016/172012/13
Outturn
Rel. by
End Mar
Approved
Budget 2014/15 2015/16
MTEF Budget Projections2013/14
Grand Total 122.9380.000 69.589 99.044
36.00036.000
67.15086.915
N/AN/A
0.000
Vote Overview
206
Rural Electrification Agency (REA)Vote:
Ministerial Policy StatementRural Electrification Agency (REA)
123
V2: Vote Performance for FY 2013/14 and Planned Outputs for FY 2014/15
(i) Past Vote Outputs
This section describes past vote performance and planned Outputs, in terms of key vote outputs
Table V2.1: Past and 2014/15 Planned Key Vote Outputs
REA continued to complete its core mandate of;
-Extension of the power Grid to Rural area targeting district head quarters, trading centers, and health
facilities, schools and agricultural expensenses.
-Provision of off grid solutions to communities that are far from the diesel powered generators and
extending subsidies for PV solar systems. Currently there are 5914 installations of PV solar systems.
For the period of July 2013 to December 2013 REA had construction works totaling to 2,496km of medium
voltage networks plus 4,409km of low voltage reticulation networks progressed. These works involved the
construction of rural electrification schemes in over 70 districts country wide.
In the FY2013/14, REA has most of the projects at level that is above 60% completion of works and others
have already been completed and commissioned. Some projects funded by the Government of Uganda (10
Lots) and the Arab Bank for Economic Development of Africa (BADEA) (10 Lots) had their contracts
signed in the month of April 2014.
i. Completion of construction of 36524Km of medium voltage (33kV or 11kV)
ii. Completion of construction of 2 5908 of low voltage (240v)
iii.100% completion of projects under BADEA/SFD
iv. OFID/OPEC 50% construction works, Update of design and procurement of contractor, Monitoring of
Defects Liability period. Undertake Way leaves acquisition
v. G GOU FUNDED PROJECTS WILL projected to have 100% completion of projects
vi.G GoU consolidated fund projects are projected to have 100% completion of projects
vii.JICA III projects are projected to have 100%completion of construction works
viii.French Development Agency projects will have 70% construction works for Grid extensions in North
West, Rwenzori, Western, Mid western, South and South Western Service Territories
ix. Arican Development Bank will have 100% completion of projects Grid extensions in North Eastern,
Eastern and Central Service Territories.
x. 50% construction of projects funded by the World Bank funded grid extensions under ERT III.
xi. 50% completion of construction works for projects funded by the French development agency projects
like Grid extensions in North West, Rwenzori, Western, Mid western, South and South Western Service
Territories’.
xii. 50% completion of construction works for projects funded by Islamic Development Bank
Preliminary 2013/14 Performance
2014/15 Planned Outputs
(iii) Vote Outcomes and Outcome Indicators
The table below sets out the vote outcomes and outcome indicators
Table V1.3: Vote Outcomes and Outcome Indicators
V3: Detailed Planned Outputs for FY 2014/15
Achievements by End MarchPlanned outputs Planned Outputs
2013/14Vote, Vote Function Key Output
2014/15
Vote: 123 Rural Electrification Agency (REA)
Vote Function: 0351 Rural Electrification
Outcome Statement Outcome Indicators Baseline Target
FY2014/15
Base year
Increased access to affordable and
more efficient sources of energy
Number of consumers accessing
electricity
55000
Number of consumers accessing solar
energy
14000
Vote Overview
207
Rural Electrification Agency (REA)Vote:
Ministerial Policy StatementRural Electrification Agency (REA)
123xiii.40,000 connections under OBA funded by KfW
Table V3.1: Vote Function Profiles, Programme/Project Profiles and Workplan Outputs
Vote Function: Rural Electrification03 51
Services:
Responsible Officer:
Vote Function Profile
- Construction of rural electrification power lines
- Installation of PV systems
- Promotion of small renewable energy projects
- Promotion of private sector management of service territories
Executive Director, REA
Vote Function Projects and Programmes:Project or Programme Name Responsible Officer
Development Projects
1261 West Nile Grid Extension Program-GBOBA Executive Director, REA
1262 Rural Electrification Project Executive Director, REA
Programme 01 Rural Electrification Management
Workplan Outputs for 2013/14 and 2014/15
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
- Staff remuneration
- Purchase of necessary goods
and services
- Payment for utilities
Policy planning,
monitoring, and advisory
services
- Staff remuneration
- Purchase of necessary goods
and services
- Payment for utilities
015103
Wage Recurrent
Non Wage Recurrent
Total
0
0
15,974,047
15,974,047
0
0
6,332,660
6,332,660
0
0
16,962,677
16,962,677
NTR
Wage Recurrent
Non Wage Recurrent
GRAND TOTAL
0
0
15,974,047
15,974,047
0
0
6,332,660
6,332,660
0
0
16,962,677
16,962,677
NTR
Executive Director, REA
Provision of electricity for socio-economic transformation of rural areas
The programme outputs are as follows;
- Promotion of household connections to electricity
- Promotion of district head quarters connection to electricity
- Promotion of renewable energy projects
- Promotion of access to PV systems for areas that are not covered by the grid
The activities under this programme include;
- Construction of rural electrification power lines
- Facilitate connectivity of rural households and commercial enterprises
- Facilitate construction of small renewable energy projects
- Facilitate acquistion of PV systems by households and commercial enterprises
- Mobilisation of communities for productive and efficient use of electricity
- Facilitate private sector participation in rural electrification
Responsible Officer:
Objectives:
Outputs:
Programme Profile
Vote Overview
208
Rural Electrification Agency (REA)Vote:
Ministerial Policy StatementRural Electrification Agency (REA)
123
Vote Function: Rural Electrification03 51
Programme 01 Rural Electrification Management
Annual Workplan for 2014/15 - Outputs, Activities, Inputs and their Cost
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
- Staff remuneration
- Purchase of necessary goods and services
- Payment for utilities
- Staff remuneration
- Purchase of necessary goods and services
- Payment for utilities
Policy planning, monitoring, and advisory services015103
Wage Recurrent
Non Wage Recurrent
Total
0
0
16,962,677
16,962,677
Activities to Deliver Outputs:
Planned Outputs:
Output:
NTR
Inputs Quantity Cost
Contract staff () 85.0 7,035,075
Fuel (litres) 4.0 261,540
Local travel (nights) 4.0 70,800
Travel abroad (nights) 4.0 229,600
Advertising (number) 4.0 42,000
Bank Charges and other Bank related costs
(number)
4.0 8,000
General expenses (number) 395.4 4,952,000
Group Personnel Accident Insurance (number) 4.0 63,198
IFMS Recurrent costs (number) 4.0 61,500
Newspapers, books & periodicals (number) 4.0 28,976
Postage and Courier (number) 4.0 7,000
Printing, Stationery, Photocopying and Binding
(number)
4.0 207,250
Recruitment expenses (number) 4.0 4,750
Repair & Maintenance (number) 4.0 250,200
Small Office Equipment (number) 4.0 39,000
Staff medical insurance (number) 4.0 212,160
Staff training (number) 4.0 783,713
Subscriptions (number) 4.0 27,000
Telecommunications (number) 4.0 103,500
Venue hire (number) 4.0 41,000
Welfare/Entertainment and office tea (number) 4.0 52,000
Contract staff (Person Years) 0.0 0
Electricity (quarter) 4.0 12,000
Water (quarter) 4.0 12,000
Wage Recurrent
Non Wage Recurrent
GRAND TOTAL
0
0
16,962,677
16,962,677
NTR
Vote Overview
209
Rural Electrification Agency (REA)Vote:
Ministerial Policy StatementRural Electrification Agency (REA)
123
Vote Function: Rural Electrification03 51
Project 1261 West Nile Grid Extension Program-GBOBA
Workplan Outputs for 2013/14 and 2014/15
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
- 40,000 consumer connections
countrywide
-There are 1608 consumer
connections countrywide
Increased rural household
connections
WORLD BANK FUNDED
OBA PROGRAM
-40000 consumer Connections
made end of financial year.
-consumer subsidy connections
in Kanungu and
Kibaale/Kyenjojo concession
areas
825103
GoU Development
External Financing
Total
3,000,000
8,191,050
11,191,050
951,828
0
951,828
3,000,000
3,554,306
6,554,306
GoU Development
External Financing
GRAND TOTAL
3,000,000
8,191,050
11,191,050
951,828
0
951,828
3,000,000
3,554,306
6,554,306
Executive Director, REA
To provide connection material to households and enterprises that have been under the grid
for a period of 18 months without connection.
140,000 connections for households and business enterprises
Responsible Officer:
Objectives:
Outputs:
6/2/2012 6/1/2017Start Date: Projected End Date:
Project Profile
Donor Funding for Project:
2016/172012/13
Budget
2013/14
Budget 2014/15 2015/16
MTEF Projections
Projected Donor Allocations (UShs)
International Finance Corporation (IFC) 8.191 3.554 33.735 13.1120.000412
International Development Association (IDA) 8.191 0.000 0.000 0.0000.000410
16.382 3.554 33.735 13.1120.000Total Donor Funding for Project
Annual Workplan for 2014/15 - Outputs, Activities, Inputs and their Cost
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
WORLD BANK FUNDED OBA PROGRAM
-40000 consumer Connections made end of financial year.
-consumer subsidy connections in Kanungu and Kibaale/Kyenjojo
concession areas
-obilisation of consumers
-Connection of consumers
-verification of consumers
-Consultancy for Consumers Connections/ poverty mapping under OBA
Increased rural household connections825103
GoU Development
External Financing
Total
3,000,000
3,554,306
6,554,306
Activities to Deliver Outputs:
Planned Outputs:
Output:
Inputs Quantity Cost
consultancy services services (service) 2.9 6,554,306
Vote Overview
210
Rural Electrification Agency (REA)Vote:
Ministerial Policy StatementRural Electrification Agency (REA)
123
Vote Function: Rural Electrification03 51
Project 1261 West Nile Grid Extension Program-GBOBA
GoU Development
External Financing
GRAND TOTAL
3,000,000
3,554,306
6,554,306
Vote Overview
211
Rural Electrification Agency (REA)Vote:
Ministerial Policy StatementRural Electrification Agency (REA)
123
Vote Function: Rural Electrification03 51
Project 1262 Rural Electrification Project
Workplan Outputs for 2013/14 and 2014/15
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
a. GOU & 5% levy outputs:
- 30 Kms completed under
Defects liability period (DLP)
for Namutumba - Bugobi
Trading Centre, Nakulyaku -
Nabwigulu line (Namutumba &
Kamuli Districts)
- 35 Kms completed under DLP
for Bujwahya - Bulyango,
Migyera – Nyakitoma line
(Hoima & Nakasongola
Districts)
- 255 Kms completed under
DLP for Katakwi - Moroto with
tee - offs to Matany and
Lorengdwat
- 207 Kms completed under
DLP for Lwala-Kaberamaido,
Dokolo, Amolatar, Otuboi;
- 103 Kms completed under
DLP for Kitgum - Palabek and
Lira - Apala - Aloi;
- 78 Kms completed under DLP
for Ibanda - Kabujogera and
Muhanga - Kamwezi;
- 125 Kms completed under
DLP for Kakumiro - Birembo -
Nalweyo, Bukwiri -
Kyankwanzi and Kayunga -
Busaana;
- 95 Kms completed under DLP
for Masafu-Bushiko –Buhasaba
–Bunyadeti Health Centre III
(Busia), Namawanga - Kimaluli
– Nabweya,
Magale,Bumbo,Butiru,Munamba
,
Lwakhakha,Nalondo,Bugobero,
(Manafwa), Bufumbo-Bokonde
(Mbale)
- 155 Kms completed under
DLP for Serere - Apapai –
Bugondo, (Soroti) Kanginima-
Namiyembe- Kabelai T/C
Scheme, (Pallisa), Bukedea-
Malera (Bukedea), Iyowa
(Tororo)
- 53 Kms completed under DLP
for Katugo - Ngoma
- Kaddugala - Lwamanyonyi
project completed under DLP
- 22 Kms completed under DLP
- Feasibility studies undertaken
-Supervision contracts signed
-Commissioning of completed
works.
-Acquisition of wayleaves.
-Completion of ongoing
construction works like:
PROJECTS FINANCED BY
ENERGY FUND (US$20
Million)
Lot1 at 90% completion of
Wakiso/Mpigi/mityana/Busujuu
Lot3 at 65% completion of
mbale/manafwa/Tororo/Butaleja/
kapchorwa/palisa/Bulambuli/siro
nko
Lot 4 at 60% completion of
masindi/Lira/ Nakasongola
Lot 5 at 80% completion of
Lwengo/
Mbarara/Isingiro/Ibanda/Kiruhur
a
Lot 6 at 100% completion of
Bushenyi/ Buhweju/Kyenjojo
Lot 7 at 75% completion
Rukungiri/Kanumgu/Ntugamo/K
abale
2 LOTS:
Lot 1 RE SCHEMES in
kayunga/jinja/Iganga/Luuka/Ka
muli/ Buyende/ Tororo/Busia/
Manfwa with 60% completion
of works.
Lot 2 RE SHEMES in
Bundibugyo/Mubende/Sembabul
e/Kiruhura/Kisoro/Lyantonde/Na
kasongola/Ibanda/Rukungiri
with 30% completion of works
RURAL ELECTRIFICATION
SCHEMES FUNDED BY GoU
10 LOTS projects have
contracts already signed and are
under procurement
Lot 1 wakiso,Butambala,Mpigi,
mityana,Mubende districts and
environ.
Lot 2 Masaka, Sembabule,
Rakai, Gomba,Kiruhura,
Districts and environs.
Lot 3 Nakasongaola, Luwero,
Nakaseke, Hoima districts and
Construction of Rural
Electrification Schemes
(On-grid)
BADEA/SFD
100% completion of projects of
Kapchorwa-Bukwo-Suam
Mayuge-Bwondha Landing Site
Kasambira-Bugulumbya-
Bukuutu
Mityana-Lusalira
Lake Victoria free Trade Zone
Apac – Chegere – Alemi
Hoima – Nalweyo
Kitgum – Namokora,
OFID/OPEC
Update of design and
procurement of contractor, 50%
construction works, Monitoring
of Defects Liability period.
Undertake Way leaves
acquisition, Undertake EA,
Storage yard
Ntenjeru-Mpenja
Biafra-Nakusubyaki
Ziba – Namaseke – Nansagazi –
Kiwale –Buyiira – Lugonjo –
Ntimbe – Bukasa – Kisimbize –
Buzzu – Banda – Kalambya –
Natyole
Lukonda – Wangege village
Nansagazi – Ssenyi Landing
sites
Aduku-Cawente, Aduku-
Nambieso, Aduku-Inomo
Lira-Bala
Aloi-Omoro
Dogapio-Atura
GOU $20 MILLIONS
FUNDED PROJECTS
Lot 1: EASTERN
100% completion of projects
Kayunga/Jijan/Iganga/Luuka/Ka
muli/Buyende/Tororo/Busia/Ma
nafa
Lot 2: WESTERN
100% completion of
projectsBundibugyo/Mubende/S
embabule/Kiruhura/Kisoro/Lyant
onde/Nakasongola/Ibanda/Ruku
ngiri
Lot
1:Wakiso,Mpigi,Mityana,Busunj
u
805103
Executive Director, REA
To achieve rural electrification of 26% by June 2022.
1,280,000 new connections by the end of the project in June 2022.
Responsible Officer:
Objectives:
Outputs:
5/13/2013 6/30/2022Start Date: Projected End Date:
Project Profile
Donor Funding for Project:
2016/172012/13
Budget
2013/14
Budget 2014/15 2015/16
MTEF Projections
Projected Donor Allocations (UShs)
International Development Association (IDA) 0.000 40.850 0.000 0.0000.000410
0.000 40.850 0.000 0.0000.000Total Donor Funding for Project
Vote Overview
212
Rural Electrification Agency (REA)Vote:
Ministerial Policy StatementRural Electrification Agency (REA)
123
Vote Function: Rural Electrification03 51
Project 1262 Rural Electrification Project
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
for Kasese Phase I line
- Nyagak hydro completed
under DLP
- Procurement of Kasese -
Prepaid Meters
- Grid Intensification
- 70% construction on
Kapchorwa-Bukwo-Suam line
(Kapchorwa)
- 70% construction on Mayuge-
Bwondha Landing Site
(Mayuge)
- 70% construction on
Kasambira-Bugulumbya-
Bukuutu line (Kamuli)
- 70% construction on Mityana-
Lusalira line (Mityana)
- 70% construction on Lake
Victoria free Trade Zone
(Rakai)
- 70% construction of Apac-
Chegere-Alemi line (Apac)
- 70% construction on Hoima-
Nalweyo line (Hoima)
- 70% construction on Kitgum-
Namokora/Padipe line (Kitgum)
- 20% construction of LV
Component of JICA Project -
Mayuge - Lumino
- Payment of VAT on
Government of Norway projects
- Wayleaves Compensation for
Donor Projects
- 45% construction of
Kyeibanga - Bugongi,
Kyabuyonga TC, Nyakasinga,
Nyamabaare, Kyemptitsi High
Sch, Ruyonza Riverside
Academy, Kanekye, Kashonzi
and Rwanyamukinya,
Rwabutura/Mbagwa-Kiziba,
Nyabuhama/Migina-Omukapera
& Mushogwa (Bushenyi),
Nyakagyeme - Rugando -
Nyabitete/ Nyabikuku -
Omukagashe-Bugangari
(Rukungiri)
- 60% construction of
Wakiso/Mpigi/Mityana/Busunju
- Lot 1
- 80% construction of
Kamuli/Buyende/Kayunga/Jinja
- Lot 2
- 60% construction of
Mbale/Manafwa/Tororo/Butalej
a/Kapchorwa/Pallisa - Lot 3
- 60% construction of
Masindi/Lira - Lot 4
- 60% construction of
Lwengo/Mbarara/Isingiro/Iband
a/Kiruhura - Lot 5
- 60% construction of
Bushenyi/Buhweju/Kasese/Kyen
jojo - Lot 6
- 60% construction of
Rukungiri/Kanungu/Ntungamo/
Kabale - Lot 7
- 80% construction of Kasese
Phase II
- 70% construction of
Sembabule/Mbarara/Bundibugy
o/Mubende/Kiroso/Kiruhura/Lya
ntonde/Nakasongola/Ibanda
- UEDCL Management
Contracts
- Kilembe Investments
compensation
environs
Lot 4 Kyunga, Mukono, Jinja,
Luuka Kamuli Districts and
environs
Lot 5 manafwa, mbale , Toror,
Sironko,Butaleja,
Budaka,Bulambuli,
Bududa,Districts and environs
Lot 6 Serere, Soroti, Palisa,
Kapchorwa, Kumi Districts and
environs
Lot 7 Mbarara, Sheema,
Busheny, Ibanda,Districts and
environs
Lot 8 Ntugamo, Rukungiri,
Kabake Kanangu, Kisoro
Districts and environs
lLot 9 Bundibugyo, Kasese,
Rubirizi Districts and
environs.Gulu Kitgum,Padar,
Otuke,Lira, Lamwo, Districts
and environs.
CONSOLIDATED FUND
AND TRANSMISSION LEVY
FUNDED GRID
EXTENSIONS
Kasese Schemes
100% works completed and
commissioned for Kasese 1
100% works completed and
commissioned for Kasese 2
RE PROJECTS FUNDED BY
DEVELOPMENT PARTNERS.
A)WORLD BANK FUNDED
PROJECTS
Lot1 Ntenjeru and environs
with 100% works complete
lot 2 Ruhiira Millenium village
with 95% works complete
Lot 1 Gulu- Acholibur with
100% works complete
Lot 2 Opeta- Acholibur with
100% works complete
Lot 1 Masindi-wak-Bulisa with
90% works complete
Lot 2 Nkonge-Kashozi with
95% works complete
-Contracts signed for Electricity
supply to selected Agricultural
farms and enterprises
- Contracts signed for Kagando
Hydropower Evacuation project
-Intesfication works under ERT
funded RE project areas is
under procurement
B) ROYAL GOVERNMENT
OF NORWAY
- Rwamucucu-Kisiizi-kyepene
with 100% works complete and
under DLP.
-Additional scope in
Rwamucucu-Kisiizi-kyempene
with 80% works complete
-Low voltage networks in
Rukungiri and Kanungu
Districts with 50% works
-Myanzi-Kiganda at 100%
works complete and under DLP
Lot 1 Mubende - Kyenjojo with
100% works complete.
Lot 2 Rakai-Isingiro: Lumbugu-
Lyatonde,Sebabule-Lwemiyaga;
Lyantonde-Lwebitakuli with
100% works complete
Lot 3Kabale-Kisoro 100%
Kikera and Ssekihuka Villages
Kibugga and Buwambo Village
Farm
Nangabo Village Farm (Kedaf)
Wamala Parish and Environs
Galamba Village
Kawafu (Rono) Farm in Busunju
Kabankonyo TC and Environs
Lot 3:
Mbale/Manafwa/Tororo/Butalej
a/Kapchorwa/Pallisa
Muwafu TC in Mulanda sub-
county
Busiu TC - Kidok Health center
Buwaya TC and Environs
Buluganya, Buyaga - Bunalwere
and Kaduwa
Maizimasa sub-county, Doho
and Bugosa TC
National High Altitude Center
at Teryet
Kabwangasi Parish, Kakutu and
Kagumu sub-county
Lot 4: Masindi/Lira
Ogur Health center and Apii Pe
Village
Kisindi - Masindi Farm Inputs
care center
Rukondwa Village
Kafu TC and Kafu Farm
Bujwahya and Bulyango TC
Lot 5:
Lwengo/Mbarara/Isingiro/Iband
a/Kiruhura
Katovu - Mudaala and
Kalengero,
Bwizibwera - Biharwe and
Bukiro
Rwentanga Community - Phase I
Mile 17 at Byakatimba TC
Nyabuhikye TC and Environs
Akacucu TC and Environs
Lot 6:
Bushenyi/Buhweju/Kasese/Kyen
jojo
Bukonzo Mixed Farm
Nsiika TC in Buhweju
Katenga - Rubaare - Katooma –
Rwagashane
Rukakarwe Appropriate
Technology Center
Nyakatooke Village
Maddox Secondary School
Lot7:
Rukungiri/Kanungu/Ntungamo/
Kabale
Kitwe Farm and Environs
Nyakibobo - Itojo sub-county
Nyabushabi – Muyumba
Bunyonyi Wildlife Island
Rubaaya to Bigaaga
Kicumbi TC and Environs
Garubunda to Mabanga TC and
Nyaruzinga to Kashenyi TC and
Kafunjo TC
Mburameizi barracks and
Kiruruma water pump
Mpangango
Rukungiri Primary Teachers
College
Bwindi Community Hospital
and Environs
GoU CONSOLIDATED FUND
PROJECTS.
100% completion of projects
Lot1:Wakiso/Butambala/Mpigi/
Vote Overview
213
Rural Electrification Agency (REA)Vote:
Ministerial Policy StatementRural Electrification Agency (REA)
123
Vote Function: Rural Electrification03 51
Project 1262 Rural Electrification Project
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
- Consultancies - Investment
Planning & Promotion
- Consultancies - Project
Development & Management
- 20% line construction for
Bulondo Health Center IV in
Tongolo
- 20% line construction from
Lugo to Wamirongo in
Kyadondo North
- 20% line construction for
Gonero Village and World
Brain Rays Training center
(Wakiso)
- 20% line construction for
Budde TC (Butambala)
- 20% construction of
Rwampanga - Migyera line
(Nakasongola)
- 20% construction of
Dekabusa-Kasiiso-
Kilyamulondo line (Luwero)
- 20% construction of Kikyusa-
Wabusana-Kamila-Vumba-
Zirobwe (Luwero)
- 20% line construction from
Kalagala to Mugenyi Village,
Kasangombe
- 20% construction of Kikoboza-
Bugambakimu-Katalekamese
Kamboja line (Nakaseke)
- 20% construction of Buwundo-
Kidusu line (Buikwe)
- 20% construction of Matte-
Namiganvu-Nakwaya line
(Mityana)
- 20% line construction to
Kitanswa Village (Mityana)
- 20% construction of
Sembabule-Rutunku-Lugushulu
line (Sembabule)
- 20% line construction from
Bukomansimbi to Bigasa
(Bukomansimbi)
- 20% line construction to
Kiwomya Village (Masaka)
- 20% construction of Ntawo -
Nyenje line (Mukono)
- 20% construction of Luswa -
Kiwoggo Trading center
(Mubende)
- 20% line construction to
Maddu in Gomba
- 20% line construction to
Kimaluli TC (Manafa)
- 20% line construction to
Kireka TC (Mbale)
- 20% construction of
Zabanyanya TC and Napuru
line (Mbale)
- 20% line construction to Ikam
Farmers (Luuka)
- 20% line construction to Pett
HC III (Tororo)
- 20% line construction to
Pasule C in Nawire Village
(Tororo)
- 20% line construction to
Panyangasi TC in Rubongi
(Tororo)
- 20% line construction to
Kyere - Iningo HC III (Serere)
- 20% line construction of
Kateta Village - Omunyolo -
Kamod SS line (Serere)
- 20% line construction to
Bukumbale, Bumausi, Bugusege
works complete
Lot 1 Gulu-Adjumani- Moyo
with 90% works complete
LoT 2 Apla-Adwari- Kiiru with
T-off Morulem with 100%
works complete
Lot 3 Rackokoko-Awere-Lalogi
with 100% works complete
C) BADEA/SFD projects have
contracts already signed and
under procurement
Lot1 Kasambira-Wandago with
Tee-offs toBusandha
Lot2 Kapchorwa-BukwoSuam
Lot 3 mayuge-kaluba-bwondha
with Tee-off to kasutaime
Bugoto and Bukoba.
Lot 4 Mityana Banda-Lusalira-
with T-off to Gulwe
Lot 5 Kyotere-Kabira-Mitondo
with t-offs to lake victoria Free
trade Zone,Bbaka and Bbale
Lot 6 Hoima-Nalweyo-Kisiiti-
Nkooko with t-offs to Ndibata
and extensions in Kakumiro
Lot 7 Apac-Chegere-Kole-
Akalo-Baala and Arapai-Tuburu
Lot 8 kitgum-Namokora-Madi
Opei and Kitgum-Lmola-Okidi
5914 PV Solar installations
have been made to date.
Mityana/Mubende
Lot2:Masaka/Sembabule/Rakai/
Gomba/Kiruhura
Lot 3:
Nakasongola/Luwero/Nakaseke/
Hoima
Lot 4:
Kayunga/Mukono/Jinja/Luuka/K
amuli
Lot 5:
Manafwa/Mbale/Tororo/Sironko
/Butaleja/Budaka/Bulambuli/Bud
uda
Lot 6:
Serere/Soroti/Pallisa/Kapchorwa
/Kumi
Lot 7:
Mbarara/Sheema/Bushenyi/Iban
da
Lot 8:
Ntungamo/Rukungiri/Kabale/Ka
nungu/ Kisoro
Lot 9:
Bundibugyo/Kasese/Rubirizi
Lot 10:
Gulu/Kitgum/Pader/Otuke/Lira/
Lamwo
JICA III
100% construction of Mayuge-
Namaingo, Lumino-Namaingo,
Namaingo-Bumeru, Lutolo-
Lufudu
FRENCH DEVELOPMENT
AGENCY PROJECTS
70% construction of Grid
extensions in North West,
Rwenzori, Western, Mid
western, South and South
Western Service Teritories
AFRICAN DEVELOPMENT
BANK
100% completion of projects.
Grid extensions in North
Eastern, Eastern and Central
Service Teritories.
WORLD BANK FUNDED
GRID EXTENSIONS UNDER
ERT III
50% construction of
projects.Grid extensions in
North Eastern, Eastern and
Central, North North West,
Central North, North Western,
Western and Rwenzori Service
Teritories
FRENCH DEVELOPMENT
AGENCY PROJECTS.
Grid extensions in Norrth West,
Rwenzori, Western, Mid
western, South and South
Western Service Teritories with
50% completion of projects.
ISLAMIC DEVELOPMENT
BANK PROJECTS
Distribution net works in
Karamoja region with 50%
completion of works.
Vote Overview
214
Rural Electrification Agency (REA)Vote:
Ministerial Policy StatementRural Electrification Agency (REA)
123
Vote Function: Rural Electrification03 51
Project 1262 Rural Electrification Project
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
(Sironko)
- 20% line construction to
Camp Swahili Village (Soroti)
- 20% line construction to
Buyala A and C (Jinja)
- 20% line construction to
Kakira Community Technical
Institute (Jinja)
- 20% construction of
Bunaporo - Bulucheke line
(Bududa))
- 20% construction of
Kachonga - Buguna-Buhasango-
Obama-Kibuku line (Butaleja)
- 20% line construction to
Ongino community
- 20% line construction to
Omagoro B TC (Ngora)
- 20% line construction to
Katine TC and HC (Soroti)
- 20% line construction to
Bulindi and Kibaire TC &
Kabonesa High School (Hoima)
- 20% construction of Ibaare -
Kashekure line in Rwampara
- 20% construction of Kiyagi -
Omubutunda - Kitonda -
Kahengye - Kagamba
- Kagarama line (Ntungamo)
- 20% line construction to
Batuga TC (Kisoro)
- 20% line construction to
Maziba Health Center IV
(Kabale)
- 20% line construction to
Ruburankono TC in Gasiza
Parish (Kisoro)
- 20% line construction to
Mgahinga Tourist (Kisoro)
- 20% line construction to
Kamwenge Vocational Institute
(Kamwenge)
- 20% line construction to
Hapuyo Military School
(Kyegegwa)
- 20% line construction to
Nyahuka TC (Bundibugyo)
- 20% line construction to
Ndeebo TC (Sheema)
- 20% line construction to
Katojo in Rwampara
(Rwampara)
- 20% line construction to
Karera - Additional (Bushenyi)
- 20% line construction to
Nyabubare (Bushenyi)
- 20% line construction to
Rwakabengo TC and
community (Rukungiri)
- 20% line construction to
Nyarushanje s/county
(Rukungiri)
- 20% line construction to
Omukafensi Kagongi (Ibanda)
- 20% line construction to
Rwempiri Village (Ibanda)
- 20% line construction to
Mirama Cell (Kiruhura)
- 20% construction of
Akatongole-Ekyaapa-
Kyakabunga-Bijubwe line
(Kiruhura)
- 20% line construction to
Mwaro TC (Kasese)
- 20% line construction to
Kahendero Fishing Village &
Ibamba Safari Lodge (Kasese)
Vote Overview
215
Rural Electrification Agency (REA)Vote:
Ministerial Policy StatementRural Electrification Agency (REA)
123
Vote Function: Rural Electrification03 51
Project 1262 Rural Electrification Project
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
- 20% line construction to
Mwongera SS in Katerera
(Rubirizi)
- 20% line construction to Bara
and Amach SS (Lira)
- 20% line construction to Agari
sub-county (Lira)
- 20% line construction to
Opong Village (Gulu)
- 20% line construction to
Pongdwong Parish (Kitgum)
- 20% line construction to
Bishop Flynn SS (Pader)
- 20% construction of Baralegi
State Lodge (Adwari - Okwang
line) (Otuke)
- 20% line construction to
Kaberamaido (Kaberamaido)
- 20% line construction to
Kamuli (Kamuli)
- 20% line construction to
Wanale & Bumungu (Mbale)
- 20% line construction to
Sembabule (Sembabule)
- 20% line construction to
Buhara (Kabale)
- 20% line construction to
Nyaburiza (Ntungamo)
- 20% line construction to
Alebtong (Alebtong)
- 20% line construction to
NyamigoyeTC (Kanungu)
- 20% line construction to
Katojo TC near Kambuga
(Kanungu)
- 20% line construction to
Savana (Kanungu)
- 20% line construction to
Kamwenge (Kamwenge)
- 20% line construction to
Mirama Hill on mirama road
(Ntungamo)
- 20% line construction to
Kyamate Church Area
(Ntungamo)
- 20% construction of
Nyaruzinga -
Kagogo/Kyatoko/Ruruku line
(Rukungiri)
- 20% construction of
Ruyonza - Nyabushenyi line
- 20% construction of
Nyakeina - kibunda/ kafunjo line
- 20% line construction to
Rutokye (Mitooma)
- 20% line construction to
Kabingo Parish
- 20% line construction to Bbale
(Kayunga)
- 20% construction of
Nyakishoroza -Katonya /
Mabindi line (Rukungiri)
- 20% line construction to
Lutengo / Naggalama Model
Village (Kayunga)
- 20% line construction to
Kyanya TC and Kisawo Kibira
(Kayunga)
- 20% construction of
Bumwangu-Bwirusa-Bubwaya-
Bumkoya line (Manafa)
- 20% line construction to
Nalidi Village (Pallisa)
- 20% line construction to
Nakalanga and Lugoloire
(Kamuli)
- 20% line construction to
Vote Overview
216
Rural Electrification Agency (REA)Vote:
Ministerial Policy StatementRural Electrification Agency (REA)
123
Vote Function: Rural Electrification03 51
Project 1262 Rural Electrification Project
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
Ngaimbirir - Kamuke -
Kaptanya TCs (Kapchorwa)
- 20% line construction to
Tadameri TC (Budaka)
- 20% line construction to
Kagoma Buwolomera Village
(Jinja)
- 20% construction of Nyondo-
Katwelatwela-Bulah line
(Mbale)
- 20% line construction to
Bungogo Cell in Kihiihi Town
Council (Kanungu)
- 20% line construction from
Nyamunuka / Kyaruhunga to
Kahunga (Ntungamo)
- 20% line construction to
Kabale Polytechnic School
(Kabale)
- 20% line construction to
Muguri Rubaya via Katuna
(Kabale)
- 20% line construction to
Kabuga TC (Kamwenge)
- 20% line construction to
Kangalaba Village (Butaleja)
b. ERT II outputs:
- 287 Kms completed under
DLP for Soroti-Katakwi, Ayer-
Kamudin, Ibanda-Kazo line
- Completion of Ntenjeru Project
- Completion of 106 Km for
Ruhiira Millenium village
- Completion of 125 Km for
Gulu-Acholibur and Tee-off
Paicho-Patiko-Palaro
- Completion of 53 Km under
DLP for Opeta-Achokora with
Tee-off Iceme-Otwal;
- Completion of 177 Km for
Masindi-Waki-Buliisa - Tee-off
to Hoima
- Completion of 175 Km for
Nkonge – Kashozi and environs
- 100% procurement of
Connection Materials
- 100% payment of UEDCL
Management Contract
- Payment of Output Based Aid
(OBA) subsidies
- Payment of subsidies for PV,
households and institutional
systems
- Payment of subsidy support to
Kagando small hydro power
plant
- Consultancies undertaken
c. Government of Norway
outputs
- Completion of 156 Km under
DLP for Muhanga-Rwamucucu-
Kisiizi-Kyempene with Tee-offs
to Rugyeyo Via Nyakishenyi -
Original Scope
- Completion of 164 Km under
DLP for Mubende-Kyenjojo
line,
- 271 Km completed under DLP
for Rakai-Sembabule line,
- Completion of 166 Km for
Kabale-Kisoro line
- Completion of 236 Km for
Gulu - Adjumani - Moyo line
- Completion 68 Km for
Rackokoko -Awere - Lalogi line
- Completion of 117 Km for
Apala-Adwar-Kiiru with tee-off
Vote Overview
217
Rural Electrification Agency (REA)Vote:
Ministerial Policy StatementRural Electrification Agency (REA)
123
Vote Function: Rural Electrification03 51
Project 1262 Rural Electrification Project
Approved Budget, Planned
Outputs (Quantity and
Location)
Expenditure and Prel.
Outputs by End Mar
(Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and
Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
to Morulem,
- Consultancies undertaken
d. BADEA/SAUDI FUND
outputs
- 70% construction of
Kapchorwa-Bukwo-Suam line
(Kapchorwa)
- 70% construction of Mayuge-
Bwondha Landing Site line
(Mayuge)
- 70% construction of
Kasambira-Bugulumbya-
Bukuutu line (Kamuli)
- 70% construction of Mityana-
Lusalira line (Mityana)
- 70% line construction for
Lake Victoria free Trade Zone
(Rakai)
- 70% construction of Apac-
Chegere-Alemi line (Apac)
- 70% construction of Hoima-
Nalweyo line (Hoima)
- 70% construction of Kitgum-
Namokora/Padipe line (Kitgum)
- Consultancies undertaken
e. Kfw outputs
- Payment of Output Based Aid
(OBA) connection subsidies
GoU Development
External Financing
Total
33,976,000
0
61,797,144
95,773,144
9,914,683
8,833,369
19,964,796
38,712,848
15,639,223
40,850,000
19,037,323
75,526,546
NTR
GoU Development
External Financing
GRAND TOTAL
33,976,000
0
61,797,144
95,773,144
9,914,683
8,833,369
19,964,796
38,712,848
15,639,223
40,850,000
19,037,323
75,526,546
NTR
Annual Workplan for 2014/15 - Outputs, Activities, Inputs and their Cost
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
BADEA/SFD
100% completion of projects of Kapchorwa-Bukwo-Suam
Mayuge-Bwondha Landing Site
Kasambira-Bugulumbya-Bukuutu
Mityana-Lusalira
Lake Victoria free Trade Zone
Apac – Chegere – Alemi
Hoima – Nalweyo
Kitgum – Namokora,
OFID/OPEC
Update of design and procurement of contractor, 50% construction works,
Monitoring of Defects Liability period. Undertake Way leaves acquisition,
Undertake EA, Storage yard
Ntenjeru-Mpenja
Biafra-Nakusubyaki
Ziba – Namaseke – Nansagazi – Kiwale –Buyiira – Lugonjo – Ntimbe –
Bukasa – Kisimbize – Buzzu – Banda – Kalambya – Natyole
Lukonda – Wangege village
Nansagazi – Ssenyi Landing sites
Aduku-Cawente, Aduku-Nambieso, Aduku-Inomo
Construction of Rural Electrification Schemes (On-grid)805103
Planned Outputs:
Output:
Inputs Quantity Cost
consultance services (service) 29.0 13,003,089
construction materials (suppes) 29.9 60,860,234
Vote Overview
218
Rural Electrification Agency (REA)Vote:
Ministerial Policy StatementRural Electrification Agency (REA)
123
Vote Function: Rural Electrification03 51
Project 1262 Rural Electrification Project
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
Lira-Bala
Aloi-Omoro
Dogapio-Atura
GOU $20 MILLIONS FUNDED PROJECTS
Lot 1: EASTERN
100% completion of projects
Kayunga/Jijan/Iganga/Luuka/Kamuli/Buyende/Tororo/Busia/Manafa
Lot 2: WESTERN
100% completion of
projectsBundibugyo/Mubende/Sembabule/Kiruhura/Kisoro/Lyantonde/Na
kasongola/Ibanda/Rukungiri
Lot 1:Wakiso,Mpigi,Mityana,Busunju
Kikera and Ssekihuka Villages
Kibugga and Buwambo Village Farm
Nangabo Village Farm (Kedaf)
Wamala Parish and Environs
Galamba Village
Kawafu (Rono) Farm in Busunju
Kabankonyo TC and Environs
Lot 3: Mbale/Manafwa/Tororo/Butaleja/Kapchorwa/Pallisa
Muwafu TC in Mulanda sub-county
Busiu TC - Kidok Health center
Buwaya TC and Environs
Buluganya, Buyaga - Bunalwere and Kaduwa
Maizimasa sub-county, Doho and Bugosa TC
National High Altitude Center at Teryet
Kabwangasi Parish, Kakutu and Kagumu sub-county
Lot 4: Masindi/Lira
Ogur Health center and Apii Pe Village
Kisindi - Masindi Farm Inputs care center
Rukondwa Village
Kafu TC and Kafu Farm
Bujwahya and Bulyango TC
Lot 5: Lwengo/Mbarara/Isingiro/Ibanda/Kiruhura
Katovu - Mudaala and Kalengero,
Bwizibwera - Biharwe and Bukiro
Rwentanga Community - Phase I
Mile 17 at Byakatimba TC
Nyabuhikye TC and Environs
Akacucu TC and Environs
Lot 6: Bushenyi/Buhweju/Kasese/Kyenjojo
Bukonzo Mixed Farm
Nsiika TC in Buhweju
Katenga - Rubaare - Katooma – Rwagashane
Rukakarwe Appropriate Technology Center
Nyakatooke Village
Maddox Secondary School
Lot7: Rukungiri/Kanungu/Ntungamo/Kabale
Kitwe Farm and Environs
Nyakibobo - Itojo sub-county
Nyabushabi – Muyumba
Bunyonyi Wildlife Island
Rubaaya to Bigaaga
Kicumbi TC and Environs
Garubunda to Mabanga TC and Nyaruzinga to Kashenyi TC and Kafunjo
TC
Mburameizi barracks and Kiruruma water pump
Mpangango
Rukungiri Primary Teachers College
Bwindi Community Hospital and Environs
GoU CONSOLIDATED FUND PROJECTS.
100% completion of projects
Lot1:Wakiso/Butambala/Mpigi/Mityana/Mubende
Lot2:Masaka/Sembabule/Rakai/Gomba/Kiruhura
Lot 3: Nakasongola/Luwero/Nakaseke/Hoima
Lot 4: Kayunga/Mukono/Jinja/Luuka/Kamuli
Lot 5:
Manafwa/Mbale/Tororo/Sironko/Butaleja/Budaka/Bulambuli/Bududa
Vote Overview
219
Rural Electrification Agency (REA)Vote:
Ministerial Policy StatementRural Electrification Agency (REA)
123
Focus will be on the following: -
- Construction of 5000 Km of power lines.
Medium Term Plans
Table V3.2: Past and Medum Term Key Vote Output Indicators*
* Excluding Taxes and Arrears
2016/172012/13
Outturn
Releases
Prel. Actual
Approved
Plan 2014/15 2015/16
MTEF Projections2013/14
Vote Function Key Output
Indicators and Costs:
Vote: 123 Rural Electrification Agency (REA)
Vote Function:0351 Rural Electrification
97.380 86.915 67.150Vote Function Cost (UShs bn) 102.938 69.5890.000
54.639 N/A N/A94.747 58.7070.000VF Cost Excluding Ext. Fin
97.380 86.915 67.150Cost of Vote Services (UShs Bn) 102.938 69.5890.000
97.380 N/A N/A94.747 58.7070.000Vote Cost Excluding Ext Fin.
Vote Function: Rural Electrification03 51
Project 1262 Rural Electrification Project
Planned Outputs and Activities to Deliver Outputs
(Quantity and Location)
Inputs to be purchased to deliver outputs and their cost
Input UShs Thousand
Lot 6: Serere/Soroti/Pallisa/Kapchorwa/Kumi
Lot 7: Mbarara/Sheema/Bushenyi/Ibanda
Lot 8: Ntungamo/Rukungiri/Kabale/Kanungu/ Kisoro
Lot 9: Bundibugyo/Kasese/Rubirizi
Lot 10: Gulu/Kitgum/Pader/Otuke/Lira/Lamwo
JICA III
100% construction of Mayuge-Namaingo, Lumino-Namaingo, Namaingo-
Bumeru, Lutolo-Lufudu
FRENCH DEVELOPMENT AGENCY PROJECTS
70% construction of Grid extensions in North West, Rwenzori, Western,
Mid western, South and South Western Service Teritories
AFRICAN DEVELOPMENT BANK
100% completion of projects. Grid extensions in North Eastern, Eastern
and Central Service Teritories.
WORLD BANK FUNDED GRID EXTENSIONS UNDER ERT III
50% construction of projects.Grid extensions in North Eastern, Eastern
and Central, North North West, Central North, North Western, Western
and Rwenzori Service Teritories
FRENCH DEVELOPMENT AGENCY PROJECTS.
Grid extensions in Norrth West, Rwenzori, Western, Mid western, South
and South Western Service Teritories with 50% completion of projects.
ISLAMIC DEVELOPMENT BANK PROJECTS
Distribution net works in Karamoja region with 50% completion of works.
-procurement of contractors and construction materials
-construction works
-sonstruction supervion
-Monitoring of Defects Liability Period
-payment of wayleaves
GoU Development
External Financing
Total
15,639,223
40,850,000
19,037,323
75,526,546
Activities to Deliver Outputs:
NTR
GoU Development
External Financing
GRAND TOTAL
15,639,223
40,850,000
19,037,323
75,526,546
NTR
Vote Overview
220
Rural Electrification Agency (REA)Vote:
Ministerial Policy StatementRural Electrification Agency (REA)
123- Connection of 20,000 consumers
- Install 7000 PV systems
(i) Measures to improve Efficiency
To improve efficiency in budget allocation, REA has identified priority projects which have a high impact
on society. Focus has been on district headquarters, rural growth centres, health centres, commercial
enterprices, and agricultural centres. These areas are high density areas in which the unit cost of exention of
electricity services is lower.
Table V3.3: Key Unit Costs of Services Provided and Services Funded (Shs '000)
Actual
2012/13
Actual
2013/14
Planned
2013/14
Proposed
2014/15
Costing Assumptions and Reasons for
any Changes and Variations from Plan
Unit Cost
Description
Vote Function:0351 Rural Electrification
54,000Kilometer Each kilometer is estimated to cost UGX
54000which includes the cost of the
conductor, poles, transformers and pole
accessories.
The variations are as a result of
differences in terrain, weather
conditions, nature of settlements &
changes in prices.
250Connections This is a no pole connection which
includes a service cable and meter.
The variations are as a result of different
service providers that include UMEME,
FERDSULT, cooperatives who charge
different rates.
Changes in prices of connection materials.
Vote Overview
221
Rural Electrification Agency (REA)Vote:
Ministerial Policy StatementRural Electrification Agency (REA)
123
(ii) Vote Investment Plans
Over 80% of available funding will be used for construction of rural electrification power lines. This level
of funding will be able to construct at least 6524Km of medium voltage (33kV or 11kV), 5908 kmof low
voltage (240v) and 40,000 connections per year.
Table V3.4: Allocations by Class of Output over the Medium Term
Table V3.5: Major Capital Investments (Outputs of class Capital Purchases over 0.5Billion)
2013/14 2014/15 2015/16 2016/17
(ii) % Vote Budget
Billion Uganda Shillings
(i) Allocation (Shs Bn)
2013/14 2014/15 2015/16 2016/17
16.0 17.0 18.5 0.0 15.5% 17.4% 20.7% 0.0%Consumption Expendture(Outputs Provided)
87.0 80.4 70.7 21.5 84.5% 82.6% 79.3% 100.0%Investment (Capital Purchases)
Grand Total 102.9 97.4 89.2 21.5 100.0% 100.0% 100.0% 100.0%
Approved Budget, Planned
Outputs (Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
Expenditures and Outputs by
End March
(Quantity and Location)
Vote Function: Rural Electrification5103
Project 1261 West Nile Grid Extension Program-GBOBA
GoU Development
External Financingt
Total
3,000,000
8,191,050
11,191,050
951,828
0
951,828
3,000,000
3,554,306
6,554,306
- 40,000 consumer connections
countrywide
-There are 1608 consumer
connections countrywide
Increased rural
household
connections
WORLD BANK FUNDED
OBA PROGRAM
-40000 consumer Connections
made end of financial year.
-consumer subsidy connections
in Kanungu and
Kibaale/Kyenjojo concession
areas
825103
Project 1262 Rural Electrification Project
a. GOU & 5% levy outputs:
- 30 Kms completed under
Defects liability period (DLP)
for Namutumba - Bugobi
Trading Centre, Nakulyaku -
Nabwigulu line (Namutumba &
Kamuli Districts)
- 35 Kms completed under DLP
for Bujwahya - Bulyango,
Migyera – Nyakitoma line
(Hoima & Nakasongola
Districts)
- 255 Kms completed under
DLP for Katakwi - Moroto with
tee - offs to Matany and
Lorengdwat
- 207 Kms completed under
DLP for Lwala-Kaberamaido,
Dokolo, Amolatar, Otuboi;
- 103 Kms completed under
DLP for Kitgum - Palabek and
Lira - Apala - Aloi;
- 78 Kms completed under DLP
for Ibanda - Kabujogera and
Muhanga - Kamwezi;
- 125 Kms completed under
DLP for Kakumiro - Birembo -
Nalweyo, Bukwiri -
Kyankwanzi and Kayunga -
Busaana;
- 95 Kms completed under DLP
for Masafu-Bushiko –Buhasaba
–Bunyadeti Health Centre III
(Busia), Namawanga - Kimaluli
– Nabweya,
Magale,Bumbo,Butiru,Munamb
a,
- Feasibility studies undertaken
-Supervision contracts signed
-Commissioning of completed
works.
-Acquisition of wayleaves.
-Completion of ongoing
construction works like:
PROJECTS FINANCED BY
ENERGY FUND (US$20
Million)
Lot1 at 90% completion of
Wakiso/Mpigi/mityana/Busujuu
Lot3 at 65% completion of
mbale/manafwa/Tororo/Butaleja/
kapchorwa/palisa/Bulambuli/sir
onko
Lot 4 at 60% completion of
masindi/Lira/ Nakasongola
Lot 5 at 80% completion of
Lwengo/
Mbarara/Isingiro/Ibanda/Kiruhur
a
Lot 6 at 100% completion of
Bushenyi/ Buhweju/Kyenjojo
Lot 7 at 75% completion
Rukungiri/Kanumgu/Ntugamo/K
abale
2 LOTS:
Lot 1 RE SCHEMES in
kayunga/jinja/Iganga/Luuka/Ka
muli/ Buyende/ Tororo/Busia/
Manfwa with 60% completion
of works.
Lot 2 RE SHEMES in
Bundibugyo/Mubende/Sembabu
le/Kiruhura/Kisoro/Lyantonde/N
akasongola/Ibanda/Rukungiri
Construction of
Rural Electrification
Schemes (On-grid)
BADEA/SFD
100% completion of projects of
Kapchorwa-Bukwo-Suam
Mayuge-Bwondha Landing Site
Kasambira-Bugulumbya-
Bukuutu
Mityana-Lusalira
Lake Victoria free Trade Zone
Apac – Chegere – Alemi
Hoima – Nalweyo
Kitgum – Namokora,
OFID/OPEC
Update of design and
procurement of contractor, 50%
construction works, Monitoring
of Defects Liability period.
Undertake Way leaves
acquisition, Undertake EA,
Storage yard
Ntenjeru-Mpenja
Biafra-Nakusubyaki
Ziba – Namaseke – Nansagazi –
Kiwale –Buyiira – Lugonjo –
Ntimbe – Bukasa – Kisimbize –
Buzzu – Banda – Kalambya –
Natyole
Lukonda – Wangege village
Nansagazi – Ssenyi Landing
sites
Aduku-Cawente, Aduku-
Nambieso, Aduku-Inomo
Lira-Bala
Aloi-Omoro
Dogapio-Atura
GOU $20 MILLIONS
805103
Vote Overview
222
Rural Electrification Agency (REA)Vote:
Ministerial Policy StatementRural Electrification Agency (REA)
123
Approved Budget, Planned
Outputs (Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
Expenditures and Outputs by
End March
(Quantity and Location)
Lwakhakha,Nalondo,Bugobero,
(Manafwa), Bufumbo-Bokonde
(Mbale)
- 155 Kms completed under
DLP for Serere - Apapai –
Bugondo, (Soroti) Kanginima-
Namiyembe- Kabelai T/C
Scheme, (Pallisa), Bukedea-
Malera (Bukedea), Iyowa
(Tororo)
- 53 Kms completed under DLP
for Katugo - Ngoma
- Kaddugala - Lwamanyonyi
project completed under DLP
- 22 Kms completed under DLP
for Kasese Phase I line
- Nyagak hydro completed
under DLP
- Procurement of Kasese -
Prepaid Meters
- Grid Intensification
- 70% construction on
Kapchorwa-Bukwo-Suam line
(Kapchorwa)
- 70% construction on Mayuge-
Bwondha Landing Site
(Mayuge)
- 70% construction on
Kasambira-Bugulumbya-
Bukuutu line (Kamuli)
- 70% construction on Mityana-
Lusalira line (Mityana)
- 70% construction on Lake
Victoria free Trade Zone (Rakai)
- 70% construction of Apac-
Chegere-Alemi line (Apac)
- 70% construction on Hoima-
Nalweyo line (Hoima)
- 70% construction on Kitgum-
Namokora/Padipe line (Kitgum)
- 20% construction of LV
Component of JICA Project -
Mayuge - Lumino
- Payment of VAT on
Government of Norway projects
- Wayleaves Compensation for
Donor Projects
- 45% construction of
Kyeibanga - Bugongi,
Kyabuyonga TC, Nyakasinga,
Nyamabaare, Kyemptitsi High
Sch, Ruyonza Riverside
Academy, Kanekye, Kashonzi
and Rwanyamukinya,
Rwabutura/Mbagwa-Kiziba,
Nyabuhama/Migina-Omukapera
& Mushogwa (Bushenyi),
Nyakagyeme - Rugando -
Nyabitete/ Nyabikuku -
Omukagashe-Bugangari
(Rukungiri)
- 60% construction of
Wakiso/Mpigi/Mityana/Busunju
- Lot 1
- 80% construction of
Kamuli/Buyende/Kayunga/Jinja
- Lot 2
- 60% construction of
Mbale/Manafwa/Tororo/Butaleja
/Kapchorwa/Pallisa - Lot 3
- 60% construction of
Masindi/Lira - Lot 4
with 30% completion of works
RURAL ELECTRIFICATION
SCHEMES FUNDED BY GoU
10 LOTS projects have
contracts already signed and are
under procurement
Lot 1 wakiso,Butambala,Mpigi,
mityana,Mubende districts and
environ.
Lot 2 Masaka, Sembabule,
Rakai, Gomba,Kiruhura,
Districts and environs.
Lot 3 Nakasongaola, Luwero,
Nakaseke, Hoima districts and
environs
Lot 4 Kyunga, Mukono, Jinja,
Luuka Kamuli Districts and
environs
Lot 5 manafwa, mbale , Toror,
Sironko,Butaleja,
Budaka,Bulambuli,
Bududa,Districts and environs
Lot 6 Serere, Soroti, Palisa,
Kapchorwa, Kumi Districts and
environs
Lot 7 Mbarara, Sheema,
Busheny, Ibanda,Districts and
environs
Lot 8 Ntugamo, Rukungiri,
Kabake Kanangu, Kisoro
Districts and environs
lLot 9 Bundibugyo, Kasese,
Rubirizi Districts and
environs.Gulu Kitgum,Padar,
Otuke,Lira, Lamwo, Districts
and environs.
CONSOLIDATED FUND AND
TRANSMISSION LEVY
FUNDED GRID EXTENSIONS
Kasese Schemes
100% works completed and
commissioned for Kasese 1
100% works completed and
commissioned for Kasese 2
RE PROJECTS FUNDED BY
DEVELOPMENT PARTNERS.
A)WORLD BANK FUNDED
PROJECTS
Lot1 Ntenjeru and environs
with 100% works complete
lot 2 Ruhiira Millenium village
with 95% works complete
Lot 1 Gulu- Acholibur with
100% works complete
Lot 2 Opeta- Acholibur with
100% works complete
Lot 1 Masindi-wak-Bulisa with
90% works complete
Lot 2 Nkonge-Kashozi with
95% works complete
-Contracts signed for Electricity
supply to selected Agricultural
farms and enterprises
- Contracts signed for Kagando
Hydropower Evacuation project
-Intesfication works under ERT
funded RE project areas is
under procurement
B) ROYAL GOVERNMENT
FUNDED PROJECTS
Lot 1: EASTERN
100% completion of projects
Kayunga/Jijan/Iganga/Luuka/Ka
muli/Buyende/Tororo/Busia/Ma
nafa
Lot 2: WESTERN
100% completion of
projectsBundibugyo/Mubende/S
embabule/Kiruhura/Kisoro/Lyan
tonde/Nakasongola/Ibanda/Ruku
ngiri
Lot
1:Wakiso,Mpigi,Mityana,Busunj
u
Kikera and Ssekihuka Villages
Kibugga and Buwambo Village
Farm
Nangabo Village Farm (Kedaf)
Wamala Parish and Environs
Galamba Village
Kawafu (Rono) Farm in Busunju
Kabankonyo TC and Environs
Lot 3:
Mbale/Manafwa/Tororo/Butaleja
/Kapchorwa/Pallisa
Muwafu TC in Mulanda sub-
county
Busiu TC - Kidok Health center
Buwaya TC and Environs
Buluganya, Buyaga - Bunalwere
and Kaduwa
Maizimasa sub-county, Doho
and Bugosa TC
National High Altitude Center
at Teryet
Kabwangasi Parish, Kakutu and
Kagumu sub-county
Lot 4: Masindi/Lira
Ogur Health center and Apii Pe
Village
Kisindi - Masindi Farm Inputs
care center
Rukondwa Village
Kafu TC and Kafu Farm
Bujwahya and Bulyango TC
Lot 5:
Lwengo/Mbarara/Isingiro/Ibanda
/Kiruhura
Katovu - Mudaala and
Kalengero,
Bwizibwera - Biharwe and
Bukiro
Rwentanga Community - Phase I
Mile 17 at Byakatimba TC
Nyabuhikye TC and Environs
Akacucu TC and Environs
Lot 6:
Bushenyi/Buhweju/Kasese/Kyen
jojo
Bukonzo Mixed Farm
Nsiika TC in Buhweju
Katenga - Rubaare - Katooma –
Rwagashane
Rukakarwe Appropriate
Technology Center
Nyakatooke Village
Maddox Secondary School
Lot7:
Rukungiri/Kanungu/Ntungamo/
Kabale
Kitwe Farm and Environs
Vote Overview
223
Rural Electrification Agency (REA)Vote:
Ministerial Policy StatementRural Electrification Agency (REA)
123
Approved Budget, Planned
Outputs (Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
Expenditures and Outputs by
End March
(Quantity and Location)
- 60% construction of
Lwengo/Mbarara/Isingiro/Ibanda
/Kiruhura - Lot 5
- 60% construction of
Bushenyi/Buhweju/Kasese/Kyen
jojo - Lot 6
- 60% construction of
Rukungiri/Kanungu/Ntungamo/
Kabale - Lot 7
- 80% construction of Kasese
Phase II
- 70% construction of
Sembabule/Mbarara/Bundibugy
o/Mubende/Kiroso/Kiruhura/Lya
ntonde/Nakasongola/Ibanda
- UEDCL Management
Contracts
- Kilembe Investments
compensation
- Consultancies - Investment
Planning & Promotion
- Consultancies - Project
Development & Management
- 20% line construction for
Bulondo Health Center IV in
Tongolo
- 20% line construction from
Lugo to Wamirongo in
Kyadondo North
- 20% line construction for
Gonero Village and World
Brain Rays Training center
(Wakiso)
- 20% line construction for
Budde TC (Butambala)
- 20% construction of
Rwampanga - Migyera line
(Nakasongola)
- 20% construction of Dekabusa-
Kasiiso-Kilyamulondo line
(Luwero)
- 20% construction of Kikyusa-
Wabusana-Kamila-Vumba-
Zirobwe (Luwero)
- 20% line construction from
Kalagala to Mugenyi Village,
Kasangombe
- 20% construction of Kikoboza-
Bugambakimu-Katalekamese
Kamboja line (Nakaseke)
- 20% construction of Buwundo-
Kidusu line (Buikwe)
- 20% construction of Matte-
Namiganvu-Nakwaya line
(Mityana)
- 20% line construction to
Kitanswa Village (Mityana)
- 20% construction of
Sembabule-Rutunku-Lugushulu
line (Sembabule)
- 20% line construction from
Bukomansimbi to Bigasa
(Bukomansimbi)
- 20% line construction to
Kiwomya Village (Masaka)
- 20% construction of Ntawo -
Nyenje line (Mukono)
- 20% construction of Luswa -
Kiwoggo Trading center
(Mubende)
- 20% line construction to
Maddu in Gomba
OF NORWAY
- Rwamucucu-Kisiizi-kyepene
with 100% works complete and
under DLP.
-Additional scope in
Rwamucucu-Kisiizi-kyempene
with 80% works complete
-Low voltage networks in
Rukungiri and Kanungu
Districts with 50% works
-Myanzi-Kiganda at 100%
works complete and under DLP
Lot 1 Mubende - Kyenjojo with
100% works complete.
Lot 2 Rakai-Isingiro: Lumbugu-
Lyatonde,Sebabule-Lwemiyaga;
Lyantonde-Lwebitakuli with
100% works complete
Lot 3Kabale-Kisoro 100%
works complete
Lot 1 Gulu-Adjumani- Moyo
with 90% works complete
LoT 2 Apla-Adwari- Kiiru with
T-off Morulem with 100%
works complete
Lot 3 Rackokoko-Awere-Lalogi
with 100% works complete
C) BADEA/SFD projects have
contracts already signed and
under procurement
Lot1 Kasambira-Wandago with
Tee-offs toBusandha
Lot2 Kapchorwa-BukwoSuam
Lot 3 mayuge-kaluba-bwondha
with Tee-off to kasutaime
Bugoto and Bukoba.
Lot 4 Mityana Banda-Lusalira-
with T-off to Gulwe
Lot 5 Kyotere-Kabira-Mitondo
with t-offs to lake victoria Free
trade Zone,Bbaka and Bbale
Lot 6 Hoima-Nalweyo-Kisiiti-
Nkooko with t-offs to Ndibata
and extensions in Kakumiro
Lot 7 Apac-Chegere-Kole-
Akalo-Baala and Arapai-Tuburu
Lot 8 kitgum-Namokora-Madi
Opei and Kitgum-Lmola-Okidi
5914 PV Solar installations
have been made to date.
Nyakibobo - Itojo sub-county
Nyabushabi – Muyumba
Bunyonyi Wildlife Island
Rubaaya to Bigaaga
Kicumbi TC and Environs
Garubunda to Mabanga TC and
Nyaruzinga to Kashenyi TC and
Kafunjo TC
Mburameizi barracks and
Kiruruma water pump
Mpangango
Rukungiri Primary Teachers
College
Bwindi Community Hospital
and Environs
GoU CONSOLIDATED FUND
PROJECTS.
100% completion of projects
Lot1:Wakiso/Butambala/Mpigi/
Mityana/Mubende
Lot2:Masaka/Sembabule/Rakai/
Gomba/Kiruhura
Lot 3:
Nakasongola/Luwero/Nakaseke/
Hoima
Lot 4:
Kayunga/Mukono/Jinja/Luuka/K
amuli
Lot 5:
Manafwa/Mbale/Tororo/Sironko
/Butaleja/Budaka/Bulambuli/Bu
duda
Lot 6:
Serere/Soroti/Pallisa/Kapchorwa
/Kumi
Lot 7:
Mbarara/Sheema/Bushenyi/Iban
da
Lot 8:
Ntungamo/Rukungiri/Kabale/Ka
nungu/ Kisoro
Lot 9:
Bundibugyo/Kasese/Rubirizi
Lot 10:
Gulu/Kitgum/Pader/Otuke/Lira/
Lamwo
JICA III
100% construction of Mayuge-
Namaingo, Lumino-Namaingo,
Namaingo-Bumeru, Lutolo-
Lufudu
FRENCH DEVELOPMENT
AGENCY PROJECTS
70% construction of Grid
extensions in North West,
Rwenzori, Western, Mid
western, South and South
Western Service Teritories
AFRICAN DEVELOPMENT
BANK
100% completion of projects.
Grid extensions in North
Eastern, Eastern and Central
Service Teritories.
WORLD BANK FUNDED
GRID EXTENSIONS UNDER
ERT III
Vote Overview
224
Rural Electrification Agency (REA)Vote:
Ministerial Policy StatementRural Electrification Agency (REA)
123
Approved Budget, Planned
Outputs (Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
Expenditures and Outputs by
End March
(Quantity and Location)
- 20% line construction to
Kimaluli TC (Manafa)
- 20% line construction to
Kireka TC (Mbale)
- 20% construction of
Zabanyanya TC and Napuru
line (Mbale)
- 20% line construction to Ikam
Farmers (Luuka)
- 20% line construction to Pett
HC III (Tororo)
- 20% line construction to
Pasule C in Nawire Village
(Tororo)
- 20% line construction to
Panyangasi TC in Rubongi
(Tororo)
- 20% line construction to
Kyere - Iningo HC III (Serere)
- 20% line construction of
Kateta Village - Omunyolo -
Kamod SS line (Serere)
- 20% line construction to
Bukumbale, Bumausi,
Bugusege (Sironko)
- 20% line construction to
Camp Swahili Village (Soroti)
- 20% line construction to
Buyala A and C (Jinja)
- 20% line construction to
Kakira Community Technical
Institute (Jinja)
- 20% construction of
Bunaporo - Bulucheke line
(Bududa))
- 20% construction of
Kachonga - Buguna-Buhasango-
Obama-Kibuku line (Butaleja)
- 20% line construction to
Ongino community
- 20% line construction to
Omagoro B TC (Ngora)
- 20% line construction to
Katine TC and HC (Soroti)
- 20% line construction to
Bulindi and Kibaire TC &
Kabonesa High School (Hoima)
- 20% construction of Ibaare -
Kashekure line in Rwampara
- 20% construction of Kiyagi -
Omubutunda - Kitonda -
Kahengye - Kagamba
- Kagarama line (Ntungamo)
- 20% line construction to
Batuga TC (Kisoro)
- 20% line construction to
Maziba Health Center IV
(Kabale)
- 20% line construction to
Ruburankono TC in Gasiza
Parish (Kisoro)
- 20% line construction to
Mgahinga Tourist (Kisoro)
- 20% line construction to
Kamwenge Vocational Institute
(Kamwenge)
- 20% line construction to
Hapuyo Military School
(Kyegegwa)
- 20% line construction to
Nyahuka TC (Bundibugyo)
- 20% line construction to
50% construction of
projects.Grid extensions in
North Eastern, Eastern and
Central, North North West,
Central North, North Western,
Western and Rwenzori Service
Teritories
FRENCH DEVELOPMENT
AGENCY PROJECTS.
Grid extensions in Norrth West,
Rwenzori, Western, Mid
western, South and South
Western Service Teritories with
50% completion of projects.
ISLAMIC DEVELOPMENT
BANK PROJECTS
Distribution net works in
Karamoja region with 50%
completion of works.
Vote Overview
225
Rural Electrification Agency (REA)Vote:
Ministerial Policy StatementRural Electrification Agency (REA)
123
Approved Budget, Planned
Outputs (Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
Expenditures and Outputs by
End March
(Quantity and Location)
Ndeebo TC (Sheema)
- 20% line construction to
Katojo in Rwampara
(Rwampara)
- 20% line construction to
Karera - Additional (Bushenyi)
- 20% line construction to
Nyabubare (Bushenyi)
- 20% line construction to
Rwakabengo TC and
community (Rukungiri)
- 20% line construction to
Nyarushanje s/county
(Rukungiri)
- 20% line construction to
Omukafensi Kagongi (Ibanda)
- 20% line construction to
Rwempiri Village (Ibanda)
- 20% line construction to
Mirama Cell (Kiruhura)
- 20% construction of
Akatongole-Ekyaapa-
Kyakabunga-Bijubwe line
(Kiruhura)
- 20% line construction to
Mwaro TC (Kasese)
- 20% line construction to
Kahendero Fishing Village &
Ibamba Safari Lodge (Kasese)
- 20% line construction to
Mwongera SS in Katerera
(Rubirizi)
- 20% line construction to Bara
and Amach SS (Lira)
- 20% line construction to Agari
sub-county (Lira)
- 20% line construction to
Opong Village (Gulu)
- 20% line construction to
Pongdwong Parish (Kitgum)
- 20% line construction to
Bishop Flynn SS (Pader)
- 20% construction of Baralegi
State Lodge (Adwari - Okwang
line) (Otuke)
- 20% line construction to
Kaberamaido (Kaberamaido)
- 20% line construction to
Kamuli (Kamuli)
- 20% line construction to
Wanale & Bumungu (Mbale)
- 20% line construction to
Sembabule (Sembabule)
- 20% line construction to
Buhara (Kabale)
- 20% line construction to
Nyaburiza (Ntungamo)
- 20% line construction to
Alebtong (Alebtong)
- 20% line construction to
NyamigoyeTC (Kanungu)
- 20% line construction to
Katojo TC near Kambuga
(Kanungu)
- 20% line construction to
Savana (Kanungu)
- 20% line construction to
Kamwenge (Kamwenge)
- 20% line construction to
Mirama Hill on mirama road
(Ntungamo)
- 20% line construction to
Vote Overview
226
Rural Electrification Agency (REA)Vote:
Ministerial Policy StatementRural Electrification Agency (REA)
123
Approved Budget, Planned
Outputs (Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
Expenditures and Outputs by
End March
(Quantity and Location)
Kyamate Church Area
(Ntungamo)
- 20% construction of
Nyaruzinga -
Kagogo/Kyatoko/Ruruku line
(Rukungiri)
- 20% construction of
Ruyonza - Nyabushenyi line
- 20% construction of
Nyakeina - kibunda/ kafunjo line
- 20% line construction to
Rutokye (Mitooma)
- 20% line construction to
Kabingo Parish
- 20% line construction to Bbale
(Kayunga)
- 20% construction of
Nyakishoroza -Katonya /
Mabindi line (Rukungiri)
- 20% line construction to
Lutengo / Naggalama Model
Village (Kayunga)
- 20% line construction to
Kyanya TC and Kisawo Kibira
(Kayunga)
- 20% construction of
Bumwangu-Bwirusa-Bubwaya-
Bumkoya line (Manafa)
- 20% line construction to
Nalidi Village (Pallisa)
- 20% line construction to
Nakalanga and Lugoloire
(Kamuli)
- 20% line construction to
Ngaimbirir - Kamuke -
Kaptanya TCs (Kapchorwa)
- 20% line construction to
Tadameri TC (Budaka)
- 20% line construction to
Kagoma Buwolomera Village
(Jinja)
- 20% construction of Nyondo-
Katwelatwela-Bulah line
(Mbale)
- 20% line construction to
Bungogo Cell in Kihiihi Town
Council (Kanungu)
- 20% line construction from
Nyamunuka / Kyaruhunga to
Kahunga (Ntungamo)
- 20% line construction to
Kabale Polytechnic School
(Kabale)
- 20% line construction to
Muguri Rubaya via Katuna
(Kabale)
- 20% line construction to
Kabuga TC (Kamwenge)
- 20% line construction to
Kangalaba Village (Butaleja)
b. ERT II outputs:
- 287 Kms completed under
DLP for Soroti-Katakwi, Ayer-
Kamudin, Ibanda-Kazo line
- Completion of Ntenjeru Project
- Completion of 106 Km for
Ruhiira Millenium village
- Completion of 125 Km for
Gulu-Acholibur and Tee-off
Paicho-Patiko-Palaro
- Completion of 53 Km under
DLP for Opeta-Achokora with
Vote Overview
227
Rural Electrification Agency (REA)Vote:
Ministerial Policy StatementRural Electrification Agency (REA)
123
Approved Budget, Planned
Outputs (Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
Expenditures and Outputs by
End March
(Quantity and Location)
Tee-off Iceme-Otwal;
- Completion of 177 Km for
Masindi-Waki-Buliisa - Tee-off
to Hoima
- Completion of 175 Km for
Nkonge – Kashozi and environs
- 100% procurement of
Connection Materials
- 100% payment of UEDCL
Management Contract
- Payment of Output Based Aid
(OBA) subsidies
- Payment of subsidies for PV,
households and institutional
systems
- Payment of subsidy support to
Kagando small hydro power
plant
- Consultancies undertaken
c. Government of Norway
outputs
- Completion of 156 Km under
DLP for Muhanga-Rwamucucu-
Kisiizi-Kyempene with Tee-offs
to Rugyeyo Via Nyakishenyi -
Original Scope
- Completion of 164 Km under
DLP for Mubende-Kyenjojo
line,
- 271 Km completed under DLP
for Rakai-Sembabule line,
- Completion of 166 Km for
Kabale-Kisoro line
- Completion of 236 Km for
Gulu - Adjumani - Moyo line
- Completion 68 Km for
Rackokoko -Awere - Lalogi line
- Completion of 117 Km for
Apala-Adwar-Kiiru with tee-off
to Morulem,
- Consultancies undertaken
d. BADEA/SAUDI FUND
outputs
- 70% construction of
Kapchorwa-Bukwo-Suam line
(Kapchorwa)
- 70% construction of Mayuge-
Bwondha Landing Site line
(Mayuge)
- 70% construction of
Kasambira-Bugulumbya-
Bukuutu line (Kamuli)
- 70% construction of Mityana-
Lusalira line (Mityana)
- 70% line construction for Lake
Victoria free Trade Zone (Rakai)
- 70% construction of Apac-
Chegere-Alemi line (Apac)
- 70% construction of Hoima-
Nalweyo line (Hoima)
- 70% construction of Kitgum-
Namokora/Padipe line (Kitgum)
- Consultancies undertaken
e. Kfw outputs
- Payment of Output Based Aid
(OBA) connection subsidies
Vote Overview
228
Rural Electrification Agency (REA)Vote:
Ministerial Policy StatementRural Electrification Agency (REA)
123
(iii) Priority Vote Actions to Improve Sector Performance
REA has come up some actions that will help improve on the sector performance and they include the
following.
-REA has planned to strengthen UMEME participation in connections. This will help to increase on the
number of connections made countrywide.
-During the FY2014/15, there will be preparatory activities for the donor funded projects before the
effectiveness of loans to allow an increment on the funds absorption.
-Lobbying for harmonized policy for handling way leaves which affects the implementation process.
Table V3.6: Vote Actions to Improve Sector Performance
V4: Proposed Budget Allocations for 2014/15 and the Medium Term
(i) The Total Budget over the Medium Term
Table V4.1: Past Outturns and Medium Term Projections by Vote Function*
Focus will be on grid access to district headquarters, rural growth centres, health centres, commercial
enterprices, and agricultural centres.
This section sets out the proposed vote budget allocations for 2014/15 and the medium term, including
major areas of expenditures and any notable changes in allocations.
(ii) The major expenditure allocations in the Vote for 2014/15
The reources will mainly be concentrated on the grid extension programs and consumer connections
countrywide
(iii) The major planned changes in resource allocations within the Vote for 2014/15
During the financial year, REA has come up with a number of projects . The new projects packaged for the
financial year and they include:
Lot1.wakiso/Butambala/Mpigi/Mubende
Lot2. Masaka/sembabule/Rakai/Gomba/Kiruhura
Lot3. Nakasongola/Lwero/Nakaseke/Hoima
Lot4. Kayunga/Mukono/Jinja/Luuka/Kamuli
Lot5. Manafwa/Mbale/Tororo/Sironko/Butaleja/Budaka/Bulambuli/Bududa
Lot6. Seres/Soroti/Palisa/Kapchorwa/Kumi
Lot7. Mbarara /Sheema/Bushenyi/Ibanda
Lot8. Ntugamo/Rukungiri/Kabale/Kanungu/Kisoro
Lot9.Bundibugyo/Kasese/Rubirizi
Lot10. Gulu/Kitgum/pader/Otuke/Lamwo
The inflow of financial resources from development partners like NORAD will be ending in the financial
2013/14. This therefore means that there will be reduced funding in the coming years.
* Excluding Taxes and Arrears
Table V4.2: Key Changes in Vote Resource Allocation
2016/172012/13
Outturn
Releases
End Mar
Appr.
Budget 2014/15 2015/16
MTEF Budget Projections2013/14
Vote: 123 Rural Electrification Agency (REA)
67.150102.9380.000 69.589 97.380 86.9150351 Rural Electrification
Total for Vote: 67.150102.9380.000 69.589 97.380 86.915
Justification for proposed Changes
in Expenditure and Outputs
Changes in Budget Allocations and Outputs
in 2014/15 from 2013/14 Planned Levels:
Approved Budget, Planned
Outputs (Quantity and Location)
Proposed Budget, Planned
Outputs (Quantity and Location)
Project, Programme
Vote Function Output
UShs Thousand
2014/152013/14
Expenditures and Outputs by
End March
(Quantity and Location)
GoU Development
External Financingt
Total
33,976,000
0
61,797,144
95,773,144
9,914,683
8,833,369
19,964,796
18,748,052
15,639,223
40,850,000
19,037,323
75,526,546
NTR
Vote Overview
229
Rural Electrification Agency (REA)Vote:
Ministerial Policy StatementRural Electrification Agency (REA)
123
Table V4.3: 2013/14 and 2014/15 Budget Allocations by Item
GoU Ext. Fin Total GoU Ext. Fin TotalAIAMillion Uganda Shillings
2013/14 Approved Budget 2014/15 Draft Estimates
AIA
Output Class: Outputs Provided 0.0 0.0 15,974.0 0.0 0.0 16,962.715,974.0 16,962.7
0.0 0.0 5,816.9 0.0 0.0 6,455.75,816.9 6,455.7211102 Contract Staff Salaries (Incl. Casuals, Temp
0.0 0.0 228.7 0.0 0.0 0.0228.7 0.0211103 Allowances
0.0 0.0 717.4 0.0 0.0 796.5717.4 796.5212201 Social Security Contributions
0.0 0.0 281.5 0.0 0.0 258.8281.5 258.8213001 Medical expenses (To employees)
0.0 0.0 50.0 0.0 0.0 0.050.0 0.0213002 Incapacity, death benefits and funeral expen
0.0 0.0 1,287.0 0.0 0.0 1,508.91,287.0 1,508.9213004 Gratuity Expenses
0.0 0.0 818.6 0.0 0.0 42.0818.6 42.0221001 Advertising and Public Relations
0.0 0.0 1,006.4 0.0 0.0 0.01,006.4 0.0221002 Workshops and Seminars
0.0 0.0 730.9 0.0 0.0 632.1730.9 632.1221003 Staff Training
0.0 0.0 5.3 0.0 0.0 5.35.3 5.3221004 Recruitment Expenses
0.0 0.0 41.0 0.0 0.0 41.041.0 41.0221005 Hire of Venue (chairs, projector, etc)
0.0 0.0 31.5 0.0 0.0 31.531.5 31.5221007 Books, Periodicals & Newspapers
0.0 0.0 141.0 0.0 0.0 0.0141.0 0.0221008 Computer supplies and Information Technol
0.0 0.0 130.0 0.0 0.0 130.0130.0 130.0221009 Welfare and Entertainment
0.0 0.0 36.0 0.0 0.0 0.036.0 0.0221010 Special Meals and Drinks
0.0 0.0 267.3 0.0 0.0 171.3267.3 171.3221011 Printing, Stationery, Photocopying and Bind
0.0 0.0 40.9 0.0 0.0 36.440.9 36.4221012 Small Office Equipment
0.0 0.0 15.0 0.0 0.0 20.015.0 20.0221014 Bank Charges and other Bank related costs
0.0 0.0 16.5 0.0 0.0 16.516.5 16.5221016 IFMS Recurrent costs
0.0 0.0 27.0 0.0 0.0 32.027.0 32.0221017 Subscriptions
0.0 0.0 81.6 0.0 0.0 35.481.6 35.4222001 Telecommunications
0.0 0.0 9.0 0.0 0.0 9.09.0 9.0222002 Postage and Courier
0.0 0.0 0.0 0.0 0.0 172.20.0 172.2222003 Information and communications technolog
0.0 0.0 554.7 0.0 0.0 639.3554.7 639.3223003 Rent – (Produced Assets) to private entities
0.0 0.0 48.0 0.0 0.0 0.048.0 0.0223004 Guard and Security services
0.0 0.0 48.0 0.0 0.0 48.048.0 48.0223005 Electricity
0.0 0.0 12.0 0.0 0.0 12.012.0 12.0223006 Water
0.0 0.0 50.1 0.0 0.0 0.050.1 0.0224002 General Supply of Goods and Services
0.0 0.0 690.5 0.0 0.0 0.0690.5 0.0225001 Consultancy Services- Short term
0.0 0.0 0.0 0.0 0.0 74.00.0 74.0225003 Taxes on (Professional) Services
0.0 0.0 82.4 0.0 0.0 96.882.4 96.8226001 Insurances
0.0 0.0 1,834.2 0.0 0.0 96.01,834.2 96.0227001 Travel inland
0.0 0.0 436.3 0.0 0.0 202.5436.3 202.5227002 Travel abroad
0.0 0.0 168.6 0.0 0.0 248.1168.6 248.1227004 Fuel, Lubricants and Oils
0.0 0.0 264.0 0.0 0.0 0.0264.0 0.0228002 Maintenance - Vehicles
0.0 0.0 6.0 0.0 0.0 199.66.0 199.6228003 Maintenance – Machinery, Equipment & Fu
0.0 0.0 0.0 0.0 0.0 4,952.00.0 4,952.0228004 Maintenance – Other
Output Class: Capital Purchases 36,976.0 8,191.0 106,964.2 18,639.2 44,404.3 82,080.961,797.1 19,037.3
0.0 0.0 500.0 0.0 0.0 0.0500.0 0.0231001 Non Residential buildings (Depreciation)
0.0 0.0 953.9 0.0 0.0 0.0953.9 0.0231005 Machinery and equipment
0.0 0.0 57.0 0.0 0.0 0.057.0 0.0231006 Furniture and fittings (Depreciation)
Justification for proposed Changes
in Expenditure and Outputs
Changes in Budget Allocations and Outputs
in 2014/15 from 2013/14 Planned Levels:
Vote Function:0301 Rural Electrification
01 Policy planning, monitoring, and advisory services0351Output:
UShs Bn: 0.989
-There will increased activity when it comes to the
monitoring and supervision of the ongoing projects.
The additional outputs and funding will contribute to the sector
objectives in a way that there will be an incraese in Rural
Electrificationan and household connections country wide .
80 Construction of Rural Electrification Schemes (On-grid)0351Output:
UShs Bn: -1.910
The reduction is mainly attriuted to the reduction in
allocation of development partners
The reduced resourcs allocation is a result that financial resource
inflows from development partners like NORAD will end in the
fiancial year 2013/14 and therefore there will be reduced funding
in the finacial year 2014/15
82 Increased rural household connections0351Output:
UShs Bn: -4.637
The allocation to the project reduced reduction in the
funding from the developmet parners.
The project commenced in the FY2013/14 in which most of the
activities are in the first year . There in the following years, there
will be ruduced expenditure. There will be reduced funding from
the development pateners.
Vote Overview
230
Rural Electrification Agency (REA)Vote:
Ministerial Policy StatementRural Electrification Agency (REA)
123
V5: Vote Cross-Cutting Policy and Other Budgetary IssuesThis section discusses how the vote's plans will address and respond to the cross-cutting policy, issues of
gender and equity; HIV/AIDS; and the Environment, and other budgetary issues such as Arrears and NTR..
(i) Cross-cutting Policy Issues
(a) Gender and Equity
(b) HIV/AIDS
(c) Environment
(ii) Verrified Outstanding Arrears for the Vote
There are no outstanding payment arrears
GoU Ext. Fin Total GoU Ext. Fin TotalAIAMillion Uganda Shillings
2013/14 Approved Budget 2014/15 Draft Estimates
AIA
16,976.0 8,191.0 85,453.3 16,976.0 44,404.3 80,417.660,286.2 19,037.3231007 Other Fixed Assets (Depreciation)
0.0 0.0 0.0 1,663.2 0.0 1,663.20.0 0.0312204 Taxes on Machinery, Furniture & Vehicles
20,000.0 0.0 20,000.0 0.0 0.0 0.00.0 0.0312206 Gross Tax
36,976.0 8,191.0 122,938.2 18,639.2 44,404.3 99,043.5Grand Total:
Total Excluding Taxes, Arrears and AIA 16,976.0 8,191.0 25,167.0 16,976.0 44,404.3 61,380.3
77,771.2
0.0
36,000.0
0.0
***where AIA is Appropriation in Aid
To ensure Equitable access to mordern energy sevicesObjective:
Need for Gender balance
- Gender mainstreaming which assesses the different implications for women and men in any planned
policy action, including legislation and programmes.
1.6
-Equal acces to modern energy services
Issue of Concern :
Proposed Intervensions
Budget Allocations
Performance Indicators
UGX billion
Objective: To sensitise members about HIV/AIDS
HIV/AIDS sensitisation
- There are HIV/AIDS awareness programs put in place.
- General staff testing
1.6
-The number of new cases HIV/AIDS positive members.
Issue of Concern :
Proposed Intervensions
Budget Allocations
Performance Indicators
UGX billion
Objective: To conserve the Enviroment
- Consevation of the Enviroment
- There is use of low voltage power lines with minimal effect on the environment
- Environment awareness programs like tree planting are in place
- Better and Environment friendly energy access programs are designed like solar systems.
1.6
-Minimised effects on the Enviroment as a result of energy
extension programs countrywide.
Issue of Concern :
Proposed Intervensions
Budget Allocations
Performance Indicators
UGX billion
Vote Overview
231
Rural Electrification Agency (REA)Vote:
Ministerial Policy StatementRural Electrification Agency (REA)
123(iii) Non Tax Revenue Collections
The NTR forecasts are made from the sale of bids. Therefore the forecasted NTR money will be used for the Rural
Electrification Management activities and for the implementation of the planned outputs during the Financial Year.
Source of NTR UShs Bn
2014/15
Projected
2013/14
Prel
Actual
2013/14
Budget
2012/13
Actual
Interest from private entities - Domestic 36.000
Total: 36.000
Vote Overview
232
Rural Electrification Agency (REA)Vote 123 FY 2014/15
Vote Function 0351: Rural Electrification
Program : Rural Electrification Management
CostCentre: Rural Electrification Management
District : Kampala
File Number Annual
Salary as per
Salary
Scale as
per payslip
Monthly
Salary as per
payslip
Staff Names Annual
Salary as per
Appointing
Authority
Salary
Scale as
per
Appointing
Monthly
Salary as per
Appointing
Authority
Annual
Salary
Variance
REA40507 Kuteesa Edith 41,658,756R9 3,471,563 41,658,756R9 3,471,563 0
REA40562 Atukunda Flavia 83,317,500R9 6,943,125 83,317,500R9 6,943,125 0
REA40569 Fred Assimwe Arali 41,658,756R8 3,471,563 41,658,756R8 3,471,563 0
REA40557 Kamukama Cynthia 41,658,756R8 3,471,563 41,658,756R8 3,471,563 0
REA0563 Kirangi Patricia 41,658,756R8 3,471,563 41,658,756R8 3,471,563 0
REA40570 Joseph Onzia 41,658,756R8 3,471,563 41,658,756R8 3,471,563 0
REA40568 Raymond Kimera 41,658,756R8 3,471,563 41,658,756R8 3,471,563 0
REA40530 Drabo Sylvia 49,990,500R8 4,165,875 49,990,500R8 4,165,875 0
REA40567 Kenneth Kahuma 41,658,756R8 3,471,563 41,658,756R8 3,471,563 0
REA40566 Mbekeke Molly 41,658,756R8 3,471,563 41,658,756R8 3,471,563 0
REA40565 Bisikwa Sarah 41,658,756R8 3,471,563 41,658,756R8 3,471,563 0
REA40564 Ecatre Michael 41,658,756R8 3,471,563 41,658,756R8 3,471,563 0
REA40518 Balihikya Diana 58,322,256R7 4,860,188 58,322,256R7 4,860,188 0
REA40560 Baguma Harriet Kyalimpa 58,322,256R7 4,860,188 58,322,256R7 4,860,188 0
REA40552 Sharon Jerusha Okodi 58,322,256R7 4,860,188 58,322,256R7 4,860,188 0
REA40546 Charles William Lutwama 83,317,500R6 6,943,125 83,317,500R6 6,943,125 0
REA40559 Anabo Peace Patricia 83,317,500R6 6,943,125 83,317,500R6 6,943,125 0
REA40558 Annet Alitusabira 83,317,500R6 6,943,125 83,317,500R6 6,943,125 0
REA40555 Joel Leku 83,317,500R6 6,943,125 83,317,500R6 6,943,125 0
Page 1
233
Rural Electrification Agency (REA)Vote 123 FY 2014/15
Vote Function 0351: Rural Electrification
Program : Rural Electrification Management
CostCentre: Rural Electrification Management
District : Kampala
File Number Annual
Salary as per
Salary
Scale as
per payslip
Monthly
Salary as per
payslip
Staff Names Annual
Salary as per
Appointing
Authority
Salary
Scale as
per
Appointing
Monthly
Salary as per
Appointing
Authority
Annual
Salary
Variance
REA40561 Birikadde Grace Kasirye 83,317,500R6 6,943,125 83,317,500R6 6,943,125 0
REA40553 Pamela T. Kusimba 83,317,500R6 6,943,125 83,317,500R6 6,943,125 0
REA40547 Daniel Kisira 83,317,500R6 6,943,125 83,317,500R6 6,943,125 0
REA40542 Nyabutundu B.K. Wilson 83,317,500R6 6,943,125 83,317,500R6 6,943,125 0
REA40541 Wegulo Swaliki Byakatonda 83,317,500R6 6,943,125 83,317,500R6 6,943,125 0
REA40540 Mutaremwa S. Arthur 83,317,500R6 6,943,125 83,317,500R6 6,943,125 0
REA40539 Nakku Kawagga Patricia Irene 83,317,500R6 6,943,125 83,317,500R6 6,943,125 0
REA40537 Aine Henry Ishungisa 83,317,500R6 6,943,125 83,317,500R6 6,943,125 0
REA40535 Uwayezu Flavia 83,317,500R6 6,943,125 83,317,500R6 6,943,125 0
REA40533 Turyagyenda Abouf Jhon 83,317,500R6 6,943,125 83,317,500R6 6,943,125 0
REA40531 Amaku Abelle Thom 83,317,500R6 6,943,125 83,317,500R6 6,943,125 0
REA40527 Nantume Pamela Deborah 83,317,500R6 6,943,125 83,317,500R6 6,943,125 0
REA40525 Litho Patricia 116,644,500R6 9,720,375 116,644,500R6 9,720,375 0
REA40516 Muhangi Richard 83,317,500R6 6,943,125 83,317,500R6 6,943,125 0
REA40514 Ggayi Francis Paul Philip 83,317,500R6 6,943,125 83,317,500R6 6,943,125 0
REA40548 Susan Namwanje Kavuma 83,317,500R6 6,943,125 83,317,500R6 6,943,125 0
REA40556 Sylvia Birungi 83,317,500R 6 6,943,125 83,317,500R6 6,943,125 0
REA40521 Sakwa Ian Eric 116,644,500R5 9,720,375 116,644,500R5 9,720,375 0
REA40513 Muguwa Andrew 116,644,500R5 9,720,375 116,644,500R5 9,720,375 0
Page 2
234
Rural Electrification Agency (REA)Vote 123 FY 2014/15
Vote Function 0351: Rural Electrification
Program : Rural Electrification Management
CostCentre: Rural Electrification Management
District : Kampala
File Number Annual
Salary as per
Salary
Scale as
per payslip
Monthly
Salary as per
payslip
Staff Names Annual
Salary as per
Appointing
Authority
Salary
Scale as
per
Appointing
Monthly
Salary as per
Appointing
Authority
Annual
Salary
Variance
REA40532 Mbabazi Emily 116,644,500R5 9,720,375 116,644,500R5 9,720,375 0
REA40501 Kasozi Mukota Geofrey 116,644,500R5 9,720,375 116,644,500R5 9,720,375 0
REA40538 Joan Dhamutundha Kayanga Mutiib 116,644,500R5 9,720,375 116,644,500R5 9,720,375 0
REA40512 Kasule Assiimwe Barbra 166,635,000R3 13,886,250 166,635,000R3 13,886,250 0
REA40517 Werikhe Khauka Godfrey 166,635,000R3 13,886,250 166,635,000R3 13,886,250 0
REA40523 Benon Bena 166,635,000R3 13,886,250 166,635,000R3 13,886,250 0
REA11706 Kyakulaga Patrick 166,635,000R3 13,886,250 166,635,000R3 13,886,250 0
REA40536 Muganzi Medard 166,635,000R3 13,886,250 166,635,000R3 13,886,250 0
REA11701 Turyahikayo Rweihunga Godfrey 283,279,500R1 23,606,625 283,279,500R1 23,606,625 0
REA40511 Nambuya Barbara 29,994,300R10 2,499,525 29,994,300R10 2,499,525 0
REA40509 Nakassujja Barbara 29,994,300R10 2,499,525 29,994,300R10 2,499,525 0
REA40550 Annette Kimuli Muhairwe 24,995,256R11 2,082,938 24,995,256R11 2,082,938 0
REA40508 Odongo James 24,995,256R11 2,082,938 24,995,256R11 2,082,938 0
REA40510 Nyakana Evelyn 24,995,256R11 2,082,938 24,995,256R11 2,082,938 0
REA40526 Nyangoma Helena 24,995,256R11 2,082,938 24,995,256R11 2,082,938 0
REA40529 Mugabe Robert 15,830,328R12 1,319,194 15,830,328R12 1,319,194 0
REA40544 Ssekungu Deogratius 15,830,328R12 1,319,194 15,830,328R12 1,319,194 0
REA40545 Birungi Jackie 15,830,328R12 1,319,194 15,830,328R12 1,319,194 0
REA40505 Atim Sarah Pamela 15,830,328R12 1,319,194 15,830,328R12 1,319,194 0
Page 3
235
Rural Electrification Agency (REA)Vote 123 FY 2014/15
Vote Function 0351: Rural Electrification
Program : Rural Electrification Management
CostCentre: Rural Electrification Management
District : Kampala
File Number Annual
Salary as per
Salary
Scale as
per payslip
Monthly
Salary as per
payslip
Staff Names Annual
Salary as per
Appointing
Authority
Salary
Scale as
per
Appointing
Monthly
Salary as per
Appointing
Authority
Annual
Salary
Variance
REA40504 Kyomugisha Emily 15,830,328R12 1,319,194 15,830,328R12 1,319,194 0
REA40554 Sebakijje Saadic 15,830,328R12 1,319,194 15,830,328R12 1,319,194 0
REA40503 Nsubuga Cyrus 15,830,328R12 1,319,194 15,830,328R12 1,319,194 0
REA40502 Tumuramye Peter 15,830,328R12 1,319,194 15,830,328R12 1,319,194 0
REA40543 Menya Moses Nkuutu 15,830,328R12 1,319,194 15,830,328R12 1,319,194 0
REAT039 Magarura Daniel 14,400,000per day 1,200,000 14,400,000per day 1,200,000 0
REAT038 Tukamushabe simpson 14,400,000per day 1,200,000 14,400,000per day 1,200,000 0
REAT040 Kyagaba Ibra 14,400,000per day 1,200,000 14,400,000per day 1,200,000 0
REAT037 Mooli Robert 9,600,000per day 800,000 9,600,000per day 800,000 0
REAT036 Bbumba Francis 9,600,000per day 800,000 9,600,000per day 800,000 0
REAT025 Ssekunda Herbert 9,600,000per day 800,000 9,600,000per day 800,000 0
REAT015 Namugerere Elizabeth 9,600,000per day 800,000 9,600,000per day 800,000 0
REAT016 Mulekwa David F 9,600,000per day 800,000 9,600,000per day 800,000 0
REAT017 Claire Komuhendo 14,400,000per day 1,200,000 14,400,000per day 1,200,000 0
REAT018 Kobusingye Doreen 9,600,000per day 800,000 9,600,000per day 800,000 0
REAT019 Nakato Flossy 9,600,000per day 800,000 9,600,000per day 800,000 0
REAT041 Kodet Connie 14,400,000per day 1,200,000 14,400,000per day 1,200,000 0
REAT021 Gidudu Kiven 9,600,000per day 800,000 9,600,000per day 800,000 0
REAT022 Birimumaiso Jassy 14,400,000per day 1,200,000 14,400,000per day 1,200,000 0
Page 4
236
Rural Electrification Agency (REA)Vote 123 FY 2014/15
Vote Function 0351: Rural Electrification
Program : Rural Electrification Management
CostCentre: Rural Electrification Management
District : Kampala
File Number Annual
Salary as per
Salary
Scale as
per payslip
Monthly
Salary as per
payslip
Staff Names Annual
Salary as per
Appointing
Authority
Salary
Scale as
per
Appointing
Monthly
Salary as per
Appointing
Authority
Annual
Salary
Variance
REAT034 Lukwiya Jackson 14,400,000per day 1,200,000 14,400,000per day 1,200,000 0
REAT024 Nabweteme Carolyne 14,400,000per day 1,200,000 14,400,000per day 1,200,000 0
REAT035 Mastaka Martin 9,600,000per day 800,000 9,600,000per day 800,000 0
REAT026 Kangume Isaac 14,400,000per day 1,200,000 14,400,000per day 1,200,000 0
REAT027 Mukombe Ronnie Prince 14,400,000per day 1,200,000 14,400,000per day 1,200,000 0
REAT028 Kasolo Nickson 14,400,000per day 1,200,000 14,400,000per day 1,200,000 0
REAT029 Arinaitwe Prossy 14,400,000per day 1,200,000 14,400,000per day 1,200,000 0
REAT030 Kato Moses 14,400,000per day 1,200,000 14,400,000per day 1,200,000 0
REAT031 Lydia Nabugonyi 14,400,000per day 1,200,000 14,400,000per day 1,200,000 0
REAT032 Maria Tusiime Mwesigwa 14,400,000per day 1,200,000 14,400,000per day 1,200,000 0
REAT012 Mutakubwa Derrick 14,400,000per day 1,200,000 14,400,000per day 1,200,000 0
REAT033 Nanyonga Mable 14,400,000per day 1,200,000 14,400,000per day 1,200,000 0
REAT023 Kalvamuki Marianne Helga 14,400,000per day 1,200,000 14,400,000per day 1,200,000 0
Total Annual Salary (Ushs) for Program : Rural Electrification Manage 4,855,576,404 4,855,576,404 0
Total Annual Salary (Ushs) for : Rural Electrification Agency (REA) 4,855,576,404 4,855,576,404 0
Page 5
237
Energy and MineralsMPS:
AnnexEnergy and Minerals
(i) Improved household stoves
The Committee observed that the Ministry of Energy and Mineral Development is promoting the use of
energy saving stoves to save energy especially for cooking. This will go a long way in saving forests which
are the major source for household energy and improve the health of mothers in the country. However, the
energy saving stoves on the market are very expensive and ordinary Ugandans cannot afford them. It also
releases women’s time to engage in development activities.
Issue: The committee recommends that government subsidizes energy saving stoves so as to reduce the
amount of energy wasted during cooking and reduce destruction of forests to make charcoal.
Response:
The Ministry has continued to train the stove artisans in various villages in a bid to bring down the cost of
the stoves in those villages.
In addition, Uganda has joined a Global Alliance for clean cook stoves to assess support from other partners
to disseminate three million stoves by 2020. A Country Action Plan has been adopted together with other
partners.
Since 2008, the Ministry with support from the German Government through Deutsche
GesellschaftfuerInternationaleZusammenarbeit (GIZ) has implemented the Improved Household Stove
Programme under the Promotion of Renewable Energy and Energy Efficiency Partnership (PREEEP). The
overall objective of PREEEP is to improve access to modern energy services and the efficient use of energy
by households and the private sector, especially in Northern Uganda.
Districts where Improved Efficiency Household Stoves are Disseminated
The improved efficiency stoves that have been constructed and disseminated under the improved household
stove programme include the shielded mud stoves, the metal rocket stoves, ceramic metal clad charcoal
stoves and fixed brick charcoal stoves. By the end of 2013, the stove programme had been disseminated in:
Budaka, Kibuku, Pallisa, Adjumani, Arua, Koboko, Maracha, Nebbi, Zombo, Amolatar, Dokolo,
Kaberamaido, Oyam, and Soroti.
In addition, the PREEEP programme has disseminated improved institutional stoves in schools, hotels,
restaurants, bakeries and other Small and Medium Enterprises (SMEs). These have been disseminated in
Hoima, Kalangala, Kampala, Kasese, Kiryandongo, Lira, Mukono and Wakiso.
Training of Trainers under the Improved Household Stove Programme
During dissemination of improved stoves, regular training of Energy Service Providers (ESPs) was carried
with a view to train Trainers in construction of improved household and institutional stoves. The table
below summarizes the number of ESPs (trainers) trained under the improved household stove programme.
Number of Trainers trained in different Districts
West Nile sub region (199): Adjumani (29), Arua (54), Koboko (23), Maracha (14), Nebbi (49), Zombo
(30).
Lango sub region (162): Amolatar (34), Dokolo (24), Kaberamaido (34), Oyam (32), Soroti (38)
BIOGAS PROGRAMME
Recommendations from Parliament for FY2013/14 And Responses by MDA
238
Energy and MineralsMPS:
AnnexEnergy and Minerals
The recent intervention in the biogas field has been the Uganda Domestic Programme (UDBP)
implemented by Heifer International Uganda with support from the Ministry. The 5-year programme (2009
– 2013) was being funded by the Netherlands Government through the Netherlands Development
Organization (SNV) and HIVOS. This programme was completed last year in 2013 with 5,100 household
biogas systems constructed and 250 biogas artisans trained.
A second Project implementation Document (PID) for phase two was developed highlighting a target of
13,600 household biogas systems to be installed in the country within a period of 4 years with support from
SNV. Phase II
The Ministry is working towards increased adoption of the biogas technology in the country through the
following approaches:
(a) Development of a credit facility for biogas technology
In Phase II, Micro Finance Institutions (MFIs) are being mobilized so as to develop a credit facility in
which households will acquire biogas systems on credit through the MFI which works hand in hand with
the Biogas Construction Enterprises (BCEs). The households will then pay back the MFI in accordance to
the agreed terms of payment.
(b) Public awareness campaigns
The Ministry has a working partnership with the Vision Group to do radio and television shows as well as
newspaper articles aimed at promoting the use and creating awareness on various modern and efficient
biomass technologies including the biogas technology among the general public. These campaigns are
ongoing on in several parts of the country on various radio and TV stations affiliated to the Vision Group
and are being conducted in different local languages to enable the users to understand each technology.
(c) Developments of Biogas standards
The Ministry, working with UNBS, has partnered with the biogas association in Kenya to develop the
standards for Biogas in Uganda while comparing them with the Kenyan biogas standards. The lack of
standards has affected the quality in construction of the systems hence affecting the adoption of the
technology. The development of biogas standards is expected to significantly contribute towards the
adoption of the technology.
(d) Promotion of alternative biogas designs
The Ministry is also promoting other biogas digester designs which are cheaper and easy to install to
address the challenges of high upfront costs of biogas systems. These technologies include the floating
drum by Crestanks (U) Limited, the PVC tubular system by Q Energy Consultants and the Fibre glass
Reinforced Plastic (FRP) digesters.
(i) Solar systems programme
The Committee observed that under the ERT II Project, Government is supporting solar PV projects
through grants for social services (implemented by line Ministries of Education, Water and Health), as well
as those based on commercial sales implemented by REA through the Photo Voltaic Targeted Market
Approach (PVTMA) framework. The mechanism for accessing solar PV systems under the PVTMA is
designed to be purely commercial and private sector led, with PV companies doing the marketing, selling
and installing solar systems; financial institutions providing solar loans; and Government playing a
239
Energy and MineralsMPS:
AnnexEnergy and Minerals
facilitation role including provision of consumer subsidies. Apparently, the solar components installed by
the prequalified vendors appear to be more expensive because they are certified and good quality products
compared to the products on the open market that unsuspecting customers buy.
Issue: The Committee recommends that government subsidizes the purchase of solar panels which will
reduce on the demand for hydroelectric power so that it can be used for production purposes. Solar also
helps the poor since it does not have monthly bills.
Uganda National Bureau of Standards should ensure that all solar panels on the market meet the required
standard.
Response:
Government through the ERT II programme is subsidising solar packages to households under the PVTMA
programme being implemented by REA. REA has developed a strategy for scaling up of dissemination
Solar PV under ERT III
On the issue of quality, UNBS has continued to monitor the standard of solar products that are on the
market.
(iii) Petroleum development agencies
The Committee observed that Parliament considered and passed the Petroleum Exploration, Production and
Development Act, 2012 which established the Petroleum Authority, the National Oil Company and the
Directorate of Petroleum to manage the oil resources. However, up to now, these institutions have not yet
started to operate. This is slowing down the development of the petroleum industry since the private oil
companies are continuing to operate while these institutions are not in place.
Issue: The Committee recommends that government fast tracks the incorporation of the National Oil
Company., appoints the Board and Executive Director of the Petroleum Authority and the Ministry of
Public Services considers the organizational structure for the Directorate of Petroleum urgently so that
these agencies can start their work.
Response:
Following the enactment into law of the Petroleum (Refining, Conversion, Transmission and Midstream
Storage) Act 2013, the Ministry of Energy and Mineral Development embarked on the formulation of
detailed regulations to operationalize certain provisions in the Act.
A Working Group to formulate these regulations and guidelines was constituted comprising of members
from the Ministry of Energy and Mineral Development, Ministry of Justice and Constitutional Affairs,
Ministry of Finance, Planning and Economic Development, Ministry of Gender, Labour and Social
Development and National Environment Management Authority, was constituted. The “Zero Draft” of
these regulations was also completed during October 2013 has been shared with the Norwegian consultants,
SimonsenVogtWiig for review.
A series of workshops and stakeholder engagements have been planned between April – June 2014 to
transform the drafts into workable documents. The tentative date for issuing of these regulations is end of
June 2014.
240
Energy and MineralsMPS:
AnnexEnergy and Minerals
(iv) Electricity tariffs
The Committee observed that electricity tariffs have remained high despite the coming on board of 350MW
from Bujagali Hydropower Plant. This is affecting economic development since energy is one of the major
factors that propel production through industrialization. High tariffs also encourage power theft which has
led to electrocutions in some parts of the country.
Issue: The Committee recommends that government work with UMEME to reduce power system losses
both technical and commercial so that the impact of losses on the tariff is minimized. Prepaid metering
should be rolled out to other parts of the country so that consumers can manage electricity consumption
within their means and the Ministry should carry out sensitization on efficient utilization of energy.
Response:
This has been addressed the loss level target for 2014 is 20% this will keep reducing up to the target of
14.7% by 2018.
Umeme is implementing a prepayment metering roll out plan, which has been shared with ERA and
Government and under the plan all domestic customers will be converted to prepayment metering systems.
From 2014, all new domestic customers will be connected to prepaid meters. The pre-payment roll out plan
targets a total of 863,000 connections by 2018.
(v) Umeme Escrow accounts
The Umeme escrow account was established in 2005 under the escrow account agreement between
UEDCL, Umeme and Citibank as an Escrow agent, in which real amounts are deposited from time to time
by UEDCL to serve as security for potential claims which may be made by Umeme under the terms of the
privatization agreement. The funding of the Escrow account is by depositing all lease fees due to UEDCL
to the account on monthly basis. Currently the balance on the Escrow account is zero and yet the minimum
amount required on the escrow account is USD 20 million.
The total cumulative amount offset by Umeme from 2005 to date arising out of nonpayment of energy bills
is Ushs. 62.77 billion. According to the lease and Assignment Agreement with UEDCL, and the Support
Agreement, in the event that government defaults to pay their invoices on time, Umeme can offset energy
arrears exceeding 60 days, against rental payable to UEDCL in the first instance and a withdrawal from the
escrow account in the absence of rent payable.
Issue: The Committee recommends that the Lease and Assignment Agreement be reviewed and Umeme be
stopped from claiming unpaid for electricity from the escrow account. Umeme should disconnect those
institutions as it is with other electricity users since each government department has a budget for
electricity. This should be done within three months and the Minister should report the new agreement to
the Committee.
The Auditor General should conduct an audit of all government departments that have refused to settle their
electricity bills on how they used the funds appropriated for electricity.
The Ministry of Finance, Planning and Economic Development should provide adequate funds for
Ministries, Departments and Agencies to cater for electricity bills.
Response:
241
Energy and MineralsMPS:
AnnexEnergy and Minerals
In order to mitigate this concern, Government is working with Umeme to have all Government Ministries
Departments and Agencies (MDAs) put on pre-Paid metering system. This will ensure that MDAs will
comply and pay bills. To-date, 42,998 prepayment meter conversions have been made including 306 out of
the 1,462 Government entities accounts.
As Part of the Lease and Assignment Agreement (LAA), GOU provided a security package, which
consisted of the Escrow Account and Liquidity Facility which provides a pool of funds meant to reimburse
UMEME for losses in the case of specified events. The funding of the Escrow account is by depositing all
lease fees due to UEDCL (excluding Administration fees) to the account on monthly basis.
The offset mechanism by Umeme Ltd per the agreement is such that offsets are first made from lease fees
and then escrow account where the lease fee is insufficient. This arrangement protects the balances on the
Escrow account as the agreement requires a minimum amount at any given time.
During March 2013 Umeme Ltd issued notice of withdrawal from the escrow account to the tune of
Shs.31.05 billion (US$11.7 million) due to none payment of energy bills by some GoU agencies
/departments. The Escrow account became the first call as there was no lease fee since 2012. Subsequently
the withdrawal certificate was issued and the amount was withdrawn. Again in May 2013 Umeme issued
another withdraw notice to cover revenue deficiency (US$ 1.959 million) which Umeme said was caused
by failure of the regulator (ERA) to approve the tariff as per the supply license. Currently the balance on
Escrow account is zero and yet the minimum amount required on the escrow account as of April 2013 is
US$ 20 million.
The total cumulative amount of offsets by Umeme Ltd from 2005 to date arising out of nonpayment of
energy bills by GoU agencies is Shs.62.77 billion.
(vi) Restoration of the Earthquake Research Facility
The seismological Centre at Entebbe was vandalized by what government later termed as land grabbers.
Note must be taken that these so called land grabbers had title Deeds which they used to claim the land and
vandalise the government institution. The Committee was informed that the police is investigation the
matter. The Ministry now needs Ugshs. 4,600,000,000 to re-construct retool and equip the Earthquake
Research Facility
Issue: The Committee recommends that the people who were involved in this matter be prosecuted; the
government institutes civil proceedings against them so that they can obtain compensation and disciplinary
proceedings be instituted against the officials in Ministry of Lands, Housing and Urban Development who
issued the phased manner to enable the Ministry reconstruct this important Earth Centre. The money
recovered from the land grabbers should be deposited in the consolidated fund. The Minister for Energy
and Mineral Development should report to the Committee on the progress made within four months.
Response:
The Special Investigation Division of Uganda Police undertook investigations and now the matter is
between the Uganda Police and Director of Public Prosecution for consideration of preferred charges. In
addition, the Ministry hired a Surveyor who opened the boundaries of the land to enable the Ministry
acquire the Land Title Deed. The Ministry has initiated procurement process for fencing of the land and
redesigning of the earthquake research facility with modern state of the art technologies for testing
infrastructure models to be earthquake compliant. The activity for re-reconstruction and restoration of the
242
Energy and MineralsMPS:
AnnexEnergy and Minerals
seismological Centre is planned in FY 2014/15 budget.
(vii) Mining reserves
Uganda is a Country endowed with huge reserves of various minerals in various parts of the country. If
these minerals were well extracted and refined, it would spur economic growth at unprecedented levels.
This would go a long way in improving household incomes, created employment and raise our foreign
exchange earnings. However, the mineral sector continues to be among the most heavily underfunded
despite the potential of the country. The Ministry has been allocated UShs 500 million for inspection and
regulation of the Mining activities. In order to effectively inspect, regulate and promote the Mining
activities in the country, the Ministry requires additional funding of UShs 2.5 billion.
The Ministry has been allocated UShs 3.59 billion in the FY2013/14 for airborne geological and
geophysical mapping of the Karamoja region. However to effectively conduct airborne geological activities,
the Ministry requires UShs 37.6 billion.
Issue: The Committee recommends that government provides UShs 3,000,000,000 to enable the Ministry
inspect and regulate mining activities. Government should also provide UShs 37,599,000,000 in a phased
manner to enable the Ministry conduct geological mapping in Karamoja region.
Response:
The recommendation that Government provides UShs 3,000,000,000 to enable the Ministry inspect and
regulate mining activities was not implemented in the FY 2013/14. It is only after the intervention from
State House that the Ministry of Finance and Planning and Economic Development promised to release
UShs 1,000,000,000 only to the Ministry for the above activity in the FY 2014/15.
On the recommendation for airborne geophysical surveys of Karamoja region, UShs 37,599,000,000 has
been planned for beginning with the FY 2014/15.
(viii) Mining leases
The Committee observed that the governing principle for allocation of mineral rights (licenses) is based on
First-come-first-serve system. This regulatory practice poses some limitations. The law on mining is silent
on the minimum level of investment requirement and minimum work obligations by mineral right holders.
Such obligations give allowance for the applicant to determine the minimum investment and work
obligation in line with the exploration and mining plans and the period for which the mineral right is
sought. In addition, certain provisions of the Mining Act are not precise especially when it comes to
requirements for evaluation of an application for a mineral right. The law requires an applicant to have
sufficient funds to carryout exploration/mining but does not precisely state how this should be proved to the
Commissioner whether by performance bond, bank statement or statement of financial capacity.
Issue: The Committee recommends that the Ministry invests in mineral exploration and adopts Competitive
bidding for mineral rights. The Mining Act be amended to strengthen the provisions regarding suspension
and cancellation of mineral rights for non-compliance. It should impose heavy fees for licenses who apply
for transfer of their mineral rights and restrict transfer where no work is done and conducts a due diligence
on all active licenses for compliance with the provisions of the Mining Act, 2003.
Response:
The Ministry does not have funds to invest in mineral exploration. This is evidenced by failure to
implement your recommendation to Government to provide Ushs 3,000,000,000 to inspect and regulate
243
Energy and MineralsMPS:
AnnexEnergy and Minerals
mining activities. Government again can only adopt the competitive bidding for mineral rights where
proven reserves have been established. This does not apply to Exploration Licenses where the potential
reserves are not yet known.
On amendment of the Mining Act 2003, the process has already started with technical review of the mining
legislation. Gaps have been identified. The remaining activity is the redrafting of the legislation to address
the gaps. The Ministry is to engage a consultant to assist in redrafting of the Mining Laws.
(ix) Compensation for the refinery development project
A total of 29 square kilometers of land is being acquired for the refinery and attendant infrastructure as well
as other related industries for which the total population of persons affected is 7118 with 1221 households.
The total amount of funds required for compensation is Ugsh. 73,000,000,000. However, only Ugshs.
44,000,000,000 has been provided leaving a funding gap of Ugshs. 29,000,000,000. This will cause a
shortfall and delay the construction since some of the affected persons cannot be compensated.
Issue: The Committee recommends that government provides Ugshs. 29,000,000,000 to enable the Ministry
compensate people and resettle them so that the project can start on time.
Response:
We take note of this support from the Committee. The Ministry is in contact with the MoFPED regarding
this issue. A letter asking MoFPED for a full release of the funds budgeted for compensation this financial
year has been submitted.
(X) Karuma Hydropower Project (600MW)
The procurement process for the Engineering, Procurement and Construction (EPC) contractor for the
Karuma Hydropower Project has been characterized by numerous injunctions and petitions from whistle
blowers! Concerned citizens’ and bidders as well as investigations by CID and Inspector General of
Government (IGG). A High Court ruling in favour of one of the bidders as well as investigations quashed
the first Evaluation Report and ordered a Re-valuation by an independent Evaluation Team. The Ministry
of Energy and Mineral Development as the procuring entity abided y the decision of the High Court and
conducted a Re-evaluation. The IGG halted the process to carry out investigations. The IGG submitted a
Report of the findings to the entity in March 2013. The entity went ahead to consult the Attorney General
on the Report.
In April 2013, the entity received a directive of Cabinet to cancel the current procurement process and
instead go into a bilateral arrangement with the Government of the People’s Republic of China to develop
the project.
On 18th April 2013, the entity received an Interlocutory Order issued by the High Court at Nakawa,
Application №162 of 2013 in matter of Hon. Andrew Baryayanga Vs. Attorney General. The entity sought
a legal opinion from the Solicitor General on this matter on how to proceed. The Solicitor General
responded on 23rd April 2013 advising the entity to go ahead and implement Cabinet directive.
Consequently, on that day, 23rd April 2013, the Contracts Committee, under minute MIN.444/12-13/CC
cancelled the procurement process. All bidders were notified of the cancellation of the process and
requested to collect their unopened financial bids.
Government intends to construct the project using resources from the Energy Fund, the Consolidated fund
244
Energy and MineralsMPS:
AnnexEnergy and Minerals
and a mixed credit comprised of concessional and commercial funding from the Chinese government. In
that regard, the allocation for the Karuma hydropower project is premised on the fact that the expected
funding from the Chinese government will not be fully on concession terms. The Chinese government will
provide US$500 million as concession funding and the balance will be on commercial basis. To moderate
the cost of commercial financing, government will raise US$700 million from the Energy Fund to co-
finance the project, which will be part of GoU equity on this project. The total project cost (the
Hydropower plant, the Power Substations, and the Transmission lines) is estimated at US$1.69 billion. The
implementation of the Resettlement Action Plan for the power plant is near completion with about 80% of
the affected persons paid and construction is expected to start before the end of calendar year 2013.
Issue: The Committee recommends that the process for the construction of Karuma Hydropower Plant be
expedited and should be cost conscious to avoid high tariff.
Response:
Construction of Karuma Hydropower Plant has started under a bilateral agreement with China.
The ground-breaking ceremony was held on 12th August, 2013 and a team from the China Exim Bank
carried out project appraisal in December, 2013. The duration of the construction period is 60 months.
Sino hydro has mobilized man power and some construction equipment and work has commenced.
The preliminary layout drawings of various components of the project have been developed.
Access roads to the dam area, power intake area, main access tunnel (MAT) area, escape and ventilation
tunnel (EVT) area and muck dumping yard are being constructed. Surface finishing and protection works
are expected to be taken during the next half year.
Topographical resurvey and geological investigations at most locations have been completed.
Design changes in the diversion channel, dam axis, power house audits, and various facilities has been
carried out.
Status of Resettlement Action Plan Implementation
The Total land intake is 465.52 ha. The 414 households, 621 property parcels are affected. So far 87% of
the Project Affected Persons have been paid.
Pending now is Payments to (183) Project Affected Persons for land in Awoo village not done due to a land
dispute between the occupants and the indigenous.
(xi) Investment in transmission
The Committee observed that Government was investing a lot of money in the generation of electricity.
However, there is no corresponding investment in evacuating and eventual distribution of electricity to the
consumers. A case in point is the Buseruka Hydro Electricity Project in Hoima which was commissioned
with no power lines to evacuate the electricity produced yet government is paying for the generation
capacity.
Issue: The Committee recommends that government should equally budget for transmission and distribution
lines to ensure that the energy produced is evacuated and eventually distributed to the consumers.
Response:
Progress to expand transmission grid from current 1,300 km to 2,750 km and increase transmission voltage
from the current 132 kV to cover 220kV and 400kV is as follows:-
245
Energy and MineralsMPS:
AnnexEnergy and Minerals
The construction of the following Transmission Lines commenced:- Bujagali-Tororo - Lessos (Kenya)
220kV transmission line (127km); Mbarara-Mirama Hill -Birembo (Rwanda) 220 kV transmission
line(66km) and Mirama Hill substation; Tororo – Opuyo – Lira 132kv TL (260 km), Mbarara – Nkenda
132kV Transmission Line(160km); Bujagali Interconnection Project (BIP) - Bujagali switchyard upgrade to
220kV.
Procurement of EPC contractor and the supervision consultant for the following lines is ongoing:-
Kawanda – Masaka 220kV transmission line(142km); Nkenda - Fort Portal-Hoima 220kV lines(234km);
Mutundwe-Entebbe 132kV transmission line (35km), Opuyo – Moroto 132kv line (160km) and the
substation, Mirama – Kabale 132kv line (76km); .
Feasibility studies for the following Transmission Lines have been concluded and Resettlement Action Plan
implementation on-going: Karuma Interconnection; Isimba Interconnection; Electrification of Industrial
Parks substations.
Feasibility studies on-going for Hoima-Kafu 220 kv TL (70km); Lira-Gulu-Nebbi-Arua 132 kv (350 km);
Lira–Gulu-Agago 132kV (175km)
Procurement of consultants to undertake studies of the following lines is on-going:- Kabulasoke-Kiboga-
Hoima 132kV (210km); Kikagati-Nshongezi-Mirama 132kV (55km); Masaka – Mbarara 220kV (135km);
Nkenda (Uganda)-Mpondwe – Beni (DR Congo) 220kV transmission line(70km)
Industrial Parks
Mbalala Industrial Park
(a) Feasibility Studies Completed
(b) Acquisition of way-leaves is on-going and is expected to be completed by June 2014
© Contractor was procured
(d) Construction expected to last one year and eight months to the first half of 2016.
A substation will be established at Mbalala as part of the Mbalala Industrial Park interconnection project.
This substation is to be used to serve all additional loads in the entire Mukono area including this Industrial
estate. The substation will be communicated by mid-2016.
Iganga Industrial Park
(a) Feasibility Studies Completed
(b) Acquisition of way-leaves is on-going and is expected to be completed by June 2014
© Contractor was procured
(d) Construction expected to last one year and eight months to the first half of 2016
Luzira Industrial Park
(a) Feasibility Studies Completed.
(b) Acquisition of way-leaves is on-going and is expected to be completed by Last quarter of 2014 given
the concentrated settlement in the area
© Contractor was procured
(d) Construction expected to last one year and eight months to the second half of
246
Energy and MineralsMPS:
AnnexEnergy and Minerals
247