Volume 4, Issue 5 30 June 2019
PROJECT STATUS
• 46 months completed
• 2 months to comple-
tion
MILESTONES
39 Achieved
3 to complete
DELIVERABLES
33 Achieved
12 to complete
TOXI-triage Project Log
WORK PACKAGE NEWS
WP 1
WP 2
WP 3
WP 4
WP 5
WP 6
WP 7
WP 8
WP 9
FTX DISPERSE
22 MAY 2019
MIKKELI, FINLAND ...
MISSION ACCOMPLISHED
conditions in a realistic large scale incident. More than 100 casualties with complex injuries were treated and the majority of casualties were decontaminated on site. The em-phasis of the exercise was on the end-user perspective and emer-gency medical staff were able to utilize the latest medical care and triage technology.
After many months of prepa-ration, FTX DISPERSE was successfully staged in Mikkeli Finland in May 2019. The trial was a comprehensive field test and evaluation of TOXI-Triage technologies and comprised the largest operational joint authority exercise in Finland. This mass chemical incident in an open pub-lic space provided challenging
![Page 2: Volume 4, Issue 5 30 June 2019 FTX DISPERSE 22 MAY 2019 MIKKELI ... - Home | Toxi … · 2019. 7. 5. · 16.10 – 16.30 Data, data everywhere though not a drop of understanding?](https://reader035.fdocuments.in/reader035/viewer/2022071604/613f79bef0f55d448e4cd194/html5/thumbnails/2.jpg)
T O X I - t r i a g e P r o j e c t
Facts and Figures
18 Partners
€12,000,000
48 Months
7 Specific Objectives
9 Work Packages
45 Deliverables
42 Milestones
Reminders
Time sheets every month
Receipts for all
expenditure
Discuss major expenditure
with co-ordinator before mak-
ing the commitment
Travel outside the EU needs
authorisation, speak with the
project co-ordinator.
Want to set up a meeting ?
Speak with Lois Child and get
a GoTo meeting link.
Names and addresses of every-
one involved in the project to
Lois Child please.
@TOXI_triage
FTX DISPERSE PREPARATIONS
P a g e 2
![Page 3: Volume 4, Issue 5 30 June 2019 FTX DISPERSE 22 MAY 2019 MIKKELI ... - Home | Toxi … · 2019. 7. 5. · 16.10 – 16.30 Data, data everywhere though not a drop of understanding?](https://reader035.fdocuments.in/reader035/viewer/2022071604/613f79bef0f55d448e4cd194/html5/thumbnails/3.jpg)
V o l u m e 4 , I s s u e 5 P a g e 3
FTX DISPERSE CASUALTIES
![Page 4: Volume 4, Issue 5 30 June 2019 FTX DISPERSE 22 MAY 2019 MIKKELI ... - Home | Toxi … · 2019. 7. 5. · 16.10 – 16.30 Data, data everywhere though not a drop of understanding?](https://reader035.fdocuments.in/reader035/viewer/2022071604/613f79bef0f55d448e4cd194/html5/thumbnails/4.jpg)
FTX
DIS
PE
RS
E
D-D
AY
IN
PIC
TU
RE
S
P a g e 4 T O X I - t r i a g e P r o j e c t L o g
![Page 5: Volume 4, Issue 5 30 June 2019 FTX DISPERSE 22 MAY 2019 MIKKELI ... - Home | Toxi … · 2019. 7. 5. · 16.10 – 16.30 Data, data everywhere though not a drop of understanding?](https://reader035.fdocuments.in/reader035/viewer/2022071604/613f79bef0f55d448e4cd194/html5/thumbnails/5.jpg)
P a g e 5 T O X I - t r i a g e P r o j e c t
Facts and Figures
18 Partners
€12,000,000
48 Months
7 Specific Objectives
9 Work Packages
45 Deliverables
42 Milestones
Reminders
Time sheets every month
Receipts for all
expenditure
Discuss major expenditure
with co-ordinator before
making the commitment
Travel outside the EU needs
authorisation, speak with the
project co-ordinator.
Want to set up a meeting ?
Speak with Lois Child and get
a GoTo meeting link.
Names and addresses of every-
one involved in the project to
Lois Child please.
@TOXI_triage
FTX DISPERSE TOXIMOTIVE
![Page 6: Volume 4, Issue 5 30 June 2019 FTX DISPERSE 22 MAY 2019 MIKKELI ... - Home | Toxi … · 2019. 7. 5. · 16.10 – 16.30 Data, data everywhere though not a drop of understanding?](https://reader035.fdocuments.in/reader035/viewer/2022071604/613f79bef0f55d448e4cd194/html5/thumbnails/6.jpg)
V o l u m e 4 , I s s u e 5 P a g e 6
Workshop Announcement
CBRN Detection Methods and Procedures
5th September 2019, Brussels
The TOXI-Triage CBRN Detection Methods and Procedures Scientific Workshop and Evening Re-ception will take place on Thursday 5th September 2019 at le Bouche à Oreille, Brussels
https://bao.be/en
Click here to register for the event and project meeting
Proposed Programme
09.30 – 10.00 Arrival and Registration 10.00 – 10.30 Introduction and Review Paul Thomas, TOXI-Triage Co-ordinator, Loughborough University 10.30 – 11.00 Verification and the role of VERIFIN Paula Vanninen, University of Helsinki 11.00 – 11.30 Break 11.30 – 11.50 The poisoning epidemic Michael Eddleston, Edinburgh University 11.50 – 12.00 Biodetection Paul Thomas, Loughborough University 12.00 – 12.30 Detectors for a new-age
Andreas Walte, Airsense Analytics / Stefan Zimmermann, University of Hannover 12.30 – 13.00 AI social media and the hybrid battle ground Tom Jackson, Loughborough University 13.00 - 14.00 Lunch 14.00 - 14.30 Where’s the baby? Tag and Trace Gert Wijnalda/ Florian Käding, Prometech 14.30 – 15.00 Drones, payloads and lessons learnt George Pallis, T4i Engineering/ Toni Leikas, Environics 15.00 – 15.20 On site validation of chemical detectors for reliable measurements Milt Statheropoulos, National Technical University of Athens 15.20 - 15.50 Break 15.50 – 16.10 Blood, Breath, sweat and tears saliva
Paul Thomas/ Dahlia Salman, Loughborough University 16.10 – 16.30 Data, data everywhere though not a drop of understanding? Dario Ruiz, ATOS 16.30 – 16.50 Systems for survival: Human Factors integration Sue Hignett, Loughborough University 16.50 – 17.30 Summary and Final comments Paul Thomas
18.30 to 21.00 Evening Drinks Reception
This project has received fund-ing from the
European Union’s Horizon 2020 Grant 653409
![Page 7: Volume 4, Issue 5 30 June 2019 FTX DISPERSE 22 MAY 2019 MIKKELI ... - Home | Toxi … · 2019. 7. 5. · 16.10 – 16.30 Data, data everywhere though not a drop of understanding?](https://reader035.fdocuments.in/reader035/viewer/2022071604/613f79bef0f55d448e4cd194/html5/thumbnails/7.jpg)
V o l u m e 4 , I s s u e 5 P a g e 7
Need to set up a GOTO Meeting? Ask Lois Child [email protected] for the TOXI-triage Login details
DIARY DATES: Date Meeting Venue
3 July 19 Project Management Board GOTO MEETING
31 Jul 19 Project Management Board GOTO MEETING
4 Sep 19 Project Meeting Brussels
5 Sep 19 Scientific Workshop CBRN Detection Methods and Procedures Brussels
5 Sep 19 Evening Reception Brussels
6 Sep 19 48 Month Review meeting Brussels
FORTHCOMING EVENTS
28 July—2 Aug 2019 28th Annual ISIMS Conference, Hannover, Germany
5 Sept 2019 CBRN Detection Methods and Procedures Workshop, Brussels, Belgium
8-11 Sept 2019 IABR Breath Summit 2019, Loughborough, UK
6-7 Nov 2019 SRE 2019 Event , Helsinki, Finland
TOXI-Triage at Altitude London Loughborough Game Changers Reception 26 June 2019
International experts and influential stake-holders – including leaders in the NHS, po-lice, military and ambulance service – attended the Loughborough University TOXI-triage research showcase at Altitude 360, London on 26 June. TOXI-Triage part-ners (pictured above) exhibited some of the technologies developed during the project.
![Page 8: Volume 4, Issue 5 30 June 2019 FTX DISPERSE 22 MAY 2019 MIKKELI ... - Home | Toxi … · 2019. 7. 5. · 16.10 – 16.30 Data, data everywhere though not a drop of understanding?](https://reader035.fdocuments.in/reader035/viewer/2022071604/613f79bef0f55d448e4cd194/html5/thumbnails/8.jpg)
Forthcoming Milestones and Deliverables
WWW.toxi-triage.eu
If you have any news to share for the next issue of the Project Log, please contact Lois: [email protected]
P a g e 8
No. Milestone name D-D
MS39 Evaluation Workshop on the Clinical investiga-tions of prototype devices 46
MS40 Completion of field exercises 45
MS41 Final report first draft 48
No Deliverable name D-D
3.3
Database of biomarkers of exposure to chemical, radiological and nuclear haz-ards (+ Technical Annex [SP-C-T])
44
2.3 Triage verification facility 46
2.4 Proceedings of meeting on Verification of C-detection methods and procedures 46
5.3 Casualty tracing system implementa-tion
44
7.7 Standardisation and harmonisation for detection systems on the semantic web
44
6.3 FTX DISPERSE 45
2.7 A verified operational guidance tool for end users 46
No. Deliverable name (Cont.) D-D
3.4 Report on the Clinical Trials 48
4.6 Laboratory system for B-detection with multiplexed aptamer sensors
48
5.4 Social media data for crises manage-ment operations implementation
48
5.5 TOXI-Triage System Integration 48
6.5 Report on Field Trials 48
7.8 Translation and co-ordination with external governmental CBRN research laboratory
48
8.4 Cross cultural and social factors in planning for crises management
48
8.5 Messages for clear and compelling communication during crises manage-ment
48
TOXI-Triage IMAGES & VIDEO LINKS
A reminder that images arising from the project are available on ownCloud. In addition, below are links to three videos from the project.
Iltalehti Video—Finnish TV video with English commentary
What is TOXI-Triage video
Finnish mass casualty exer-cise tests life-saving tech video Reuters
T O X I - t r i a g e P r o j e c t