Voltage quality regulation in Sweden

12
Voltage quality regulation in Sweden Lars Ström, Math Bollen, Rémy Kolessar Energy Markets Inspectorate Eskilstuna, Sweden

description

Voltage quality regulation in Sweden. Lars Ström, Math Bollen, Rémy Kolessar Energy Markets Inspectorate Eskilstuna, Sweden. Voltage quality in Sweden. Responsibility of the network operator Monitoring only for internal use, no publication The regulatory process is triggered by a complaint - PowerPoint PPT Presentation

Transcript of Voltage quality regulation in Sweden

Page 1: Voltage quality regulation in Sweden

Voltage quality regulation in Sweden

Lars Ström, Math Bollen, Rémy Kolessar

Energy Markets InspectorateEskilstuna, Sweden

Page 2: Voltage quality regulation in Sweden

Frankfurt (Germany), 6-9 June 2011

Responsibility of the network operator Monitoring only for internal use, no publication The regulatory process is triggered by a complaint Step 1: try to reach agreement Step 2: the regulator investigates the case Step 3: the regulator can enforce measures by the

network operator

Lars Ström – Sweden – S2 – 168

Voltage quality in Sweden

Page 3: Voltage quality regulation in Sweden

Frankfurt (Germany), 6-9 June 2011

What is acceptable voltage quality?

Existing situation: EN 50160 Soon: a new set of limits

100% values for most of the EN 50160 levels EN 50160 for flicker New requirements for dips and swells Limits on duration of interruptions

No complaints = acceptable quality

Lars Ström – Sweden – S2 – 168

Page 4: Voltage quality regulation in Sweden

Frankfurt (Germany), 6-9 June 2011

Voltage-quality variations

Harmonics EN 50160 levels hold 100% of time MV levels for HV harmonics 17 – 25

Unbalance At most 2%, 100% of time

Flicker 95% of Plt during one week less than 1.0

Slow voltage variations All 10-minute values between 90 and 110%

Lars Ström – Sweden – S2 – 168

Page 5: Voltage quality regulation in Sweden

Frankfurt (Germany), 6-9 June 2011

Responsibility sharing curve

Installations should tolerate these dips

Limitations on the number of dips

Duration of the dip

Res

idua

l vol

tage

Lars Ström – Sweden – S2 – 168

Page 6: Voltage quality regulation in Sweden

Frankfurt (Germany), 6-9 June 2011

Voltage dips: Swedish regulation

Installations should tolerate these dips

A reasonable number of dips is acceptable

Dips are unacceptable

Duration of the dip

Res

idua

l vol

tage

Lars Ström – Sweden – S2 – 168

Page 7: Voltage quality regulation in Sweden

Frankfurt (Germany), 6-9 June 2011

How to choose the curves?

Dips, up to 45 kV CIGRE/CIRED/UIE working group C4.110

Dips, above 45 kV Discussion between the stakeholders

Swells, up to 1 kV Protection requirements microgeneration Highest overvoltages during earthfaults Experiments on equipment damage

Lars Ström – Sweden – S2 – 168

Page 8: Voltage quality regulation in Sweden

Frankfurt (Germany), 6-9 June 2011

Nominal voltage 45 kV and less

Lars Ström – Sweden – S2 – 168

0.2s 0.5s 1s 5s

40%

70%

90%

60s

Page 9: Voltage quality regulation in Sweden

Frankfurt (Germany), 6-9 June 2011

Nominal voltage above 45 kV

Lars Ström – Sweden – S2 – 168

0.2s 0.5s 1s 5s

40%

70%

90%

60s

80%

Page 10: Voltage quality regulation in Sweden

Frankfurt (Germany), 6-9 June 2011

Voltage swells, up to 1 kV

Lars Ström – Sweden – S2 – 168

0.5s 5s

111%

115%

60s

135%

Page 11: Voltage quality regulation in Sweden

Frankfurt (Germany), 6-9 June 2011

Interruptions – maximum duration

Lars Ström – Sweden – S2 – 168

Page 12: Voltage quality regulation in Sweden

Frankfurt (Germany), 6-9 June 2011

Conclusions

New specification on what is considered acceptable voltage quality

Variations: 100% of time Dips and swells: responsibility sharing Interruptions: maximum duration

Experience to be gained on what are reasonable numbers of dips and swells

Lars Ström – Sweden – S2 – 168