Detailed Manual Estimation Approach for Pre-sale phase
Vlada Benyukh, Volodymyr Prymakov
![Page 2: Volodymyr Prymakov and Vlada Benyukh Detailed manual estimation approach for Pre-sale phase](https://reader033.fdocuments.in/reader033/viewer/2022051404/5a649fc77f8b9a31568b5b4b/html5/thumbnails/2.jpg)
Speaker info
Vlada Benyukh, UkraineQA Consultant/QA Lead at Ciklum, TCoE
• 7 years in QA
• Manual QA Engineer, QA Lead
• Certified: SAFe, ICAgile, ISTQB
/in/vlada-benyukh
![Page 3: Volodymyr Prymakov and Vlada Benyukh Detailed manual estimation approach for Pre-sale phase](https://reader033.fdocuments.in/reader033/viewer/2022051404/5a649fc77f8b9a31568b5b4b/html5/thumbnails/3.jpg)
Speaker info
/in/vladimirprimakov/
Volodymyr Prymakov, UkraineSenior QA Manager at Ciklum, TCoE
Head of Performance QA Unit at TCoE
•14 years in QA
•45 projects experience
•Certified: ISTQB Advanced Test Analyst & Manager,
ICAgile CP, SAFE
![Page 4: Volodymyr Prymakov and Vlada Benyukh Detailed manual estimation approach for Pre-sale phase](https://reader033.fdocuments.in/reader033/viewer/2022051404/5a649fc77f8b9a31568b5b4b/html5/thumbnails/4.jpg)
Agenda
1. What is an Estimate? Why it is important?
2. Which basis and factors should be considered in estimation process?
3. What main and additional activities should be included in QA Estimation
approach?
4. How Regression testing should be calculated?
5. How QA Estimation can be adjusted by risks multipliers?
6. Demo of real-life example
![Page 5: Volodymyr Prymakov and Vlada Benyukh Detailed manual estimation approach for Pre-sale phase](https://reader033.fdocuments.in/reader033/viewer/2022051404/5a649fc77f8b9a31568b5b4b/html5/thumbnails/5.jpg)
Why we need to estimate?
![Page 6: Volodymyr Prymakov and Vlada Benyukh Detailed manual estimation approach for Pre-sale phase](https://reader033.fdocuments.in/reader033/viewer/2022051404/5a649fc77f8b9a31568b5b4b/html5/thumbnails/6.jpg)
How to estimate these tasks?
![Page 7: Volodymyr Prymakov and Vlada Benyukh Detailed manual estimation approach for Pre-sale phase](https://reader033.fdocuments.in/reader033/viewer/2022051404/5a649fc77f8b9a31568b5b4b/html5/thumbnails/7.jpg)
Assumptions
We assume that:
1. Project is planned to work based on Scrum
2. Development team size: up to 30 people
3. QA Engineer Competency is Middle Level
4. Non-functional requirements are estimated separately
![Page 8: Volodymyr Prymakov and Vlada Benyukh Detailed manual estimation approach for Pre-sale phase](https://reader033.fdocuments.in/reader033/viewer/2022051404/5a649fc77f8b9a31568b5b4b/html5/thumbnails/8.jpg)
Test Basis
Such test basis should be considered as below:
1. Functional requirements in scope (WBS) are defined
2. Test environments and their priorities are determined while pre-sale phase
3. Project duration (number of sprints) is considered before estimation
process
![Page 9: Volodymyr Prymakov and Vlada Benyukh Detailed manual estimation approach for Pre-sale phase](https://reader033.fdocuments.in/reader033/viewer/2022051404/5a649fc77f8b9a31568b5b4b/html5/thumbnails/9.jpg)
What factors?
1. Domain specific knowledge and technologies used
2. Integration-related problems/risks (within internal and external systems)
3. Complexity of the application (e.g. calculations verifications)
4. Compatibility testing (e.g. file compatibility, plugin computability etc)
![Page 10: Volodymyr Prymakov and Vlada Benyukh Detailed manual estimation approach for Pre-sale phase](https://reader033.fdocuments.in/reader033/viewer/2022051404/5a649fc77f8b9a31568b5b4b/html5/thumbnails/10.jpg)
What main activities?
1. Detailed Requirements Review*
2. Test Design
3. Test Execution
4. Bug investigation and submission. Bug Retest
5. Environments/Platforms Multipliers
![Page 11: Volodymyr Prymakov and Vlada Benyukh Detailed manual estimation approach for Pre-sale phase](https://reader033.fdocuments.in/reader033/viewer/2022051404/5a649fc77f8b9a31568b5b4b/html5/thumbnails/11.jpg)
How to estimate time?
Time calculation for main test activities = (test execution + bugs submission and retest) *environments/platforms multiplier+ test design+ detailed requirements review*
![Page 12: Volodymyr Prymakov and Vlada Benyukh Detailed manual estimation approach for Pre-sale phase](https://reader033.fdocuments.in/reader033/viewer/2022051404/5a649fc77f8b9a31568b5b4b/html5/thumbnails/12.jpg)
How to calculate env multiplier?
Environments/platforms factors to select:
1. Identify customer region and target audience where the application will be
used
2. Select top used environments/platforms based on the customer’s
region/audience
![Page 13: Volodymyr Prymakov and Vlada Benyukh Detailed manual estimation approach for Pre-sale phase](https://reader033.fdocuments.in/reader033/viewer/2022051404/5a649fc77f8b9a31568b5b4b/html5/thumbnails/13.jpg)
Example to calculate env multiplier?
Web-browser e.g. Test Type Coefficient
The highest priority web-browser Chrome 57Full Test (Positive, negative flows) 1
High priority web-browser IE 11, FF54 Only positive flows tests 0,5
Medium priority web-browser Edge14 Explorartory testing 0.25
Low priority web-browser Chrome 56Smoke test (at least 1 positive flow test) 0.1
EXAMPLE of multiplier calculation: 1 + 0.5 + 0.5 + 0.25 + 0.1 = 2.35
![Page 14: Volodymyr Prymakov and Vlada Benyukh Detailed manual estimation approach for Pre-sale phase](https://reader033.fdocuments.in/reader033/viewer/2022051404/5a649fc77f8b9a31568b5b4b/html5/thumbnails/14.jpg)
Example of estimation basis
![Page 15: Volodymyr Prymakov and Vlada Benyukh Detailed manual estimation approach for Pre-sale phase](https://reader033.fdocuments.in/reader033/viewer/2022051404/5a649fc77f8b9a31568b5b4b/html5/thumbnails/15.jpg)
What typical preparation activities?
1. Detailed evaluation of the product/project. Full Master Test Plan creation
2. Learning and getting acquainted with the product's documentation and/or
functionality. Preliminary requirements review and feedback
3. Checklist/Suite creation (with empty test cases)
4. Test Environment and Infrastructure Preparation & Access
![Page 16: Volodymyr Prymakov and Vlada Benyukh Detailed manual estimation approach for Pre-sale phase](https://reader033.fdocuments.in/reader033/viewer/2022051404/5a649fc77f8b9a31568b5b4b/html5/thumbnails/16.jpg)
Example of preparation activities?
![Page 17: Volodymyr Prymakov and Vlada Benyukh Detailed manual estimation approach for Pre-sale phase](https://reader033.fdocuments.in/reader033/viewer/2022051404/5a649fc77f8b9a31568b5b4b/html5/thumbnails/17.jpg)
What typical repetitive activities?
1. Sprint Grooming & Planning, Retrospective
2. Daily Communication Meetings
3. Demo Meetings
4. Global Release Readiness Analysis and Reporting
5. Regular Product Deploy and Configuration, Test Environment Configuration,
Test Data Preparation
* If estimated by PM, it should NOT be estimated here and it should be set to 0h
![Page 18: Volodymyr Prymakov and Vlada Benyukh Detailed manual estimation approach for Pre-sale phase](https://reader033.fdocuments.in/reader033/viewer/2022051404/5a649fc77f8b9a31568b5b4b/html5/thumbnails/18.jpg)
Example of typical repetitive activities
![Page 19: Volodymyr Prymakov and Vlada Benyukh Detailed manual estimation approach for Pre-sale phase](https://reader033.fdocuments.in/reader033/viewer/2022051404/5a649fc77f8b9a31568b5b4b/html5/thumbnails/19.jpg)
How to calculate Regression?
1. Number of sprints: (e.g. 12)
2. Number of regression testing cycles: (e.g. 6 or 3)
3. Pure New functionality testing time ⇒ (without time working with bugs and
test environment multiplier)= (e.g. 300h)
4. Percentage of regression-tested functionality: (e.g. 60%)
5. Test environments Multiplier: (e.g. 2)
![Page 20: Volodymyr Prymakov and Vlada Benyukh Detailed manual estimation approach for Pre-sale phase](https://reader033.fdocuments.in/reader033/viewer/2022051404/5a649fc77f8b9a31568b5b4b/html5/thumbnails/20.jpg)
How to calculate Regression?
Pure new functionality testing time (if 0 bugs)
![Page 21: Volodymyr Prymakov and Vlada Benyukh Detailed manual estimation approach for Pre-sale phase](https://reader033.fdocuments.in/reader033/viewer/2022051404/5a649fc77f8b9a31568b5b4b/html5/thumbnails/21.jpg)
How to calculate Regression?
Regression cycles: 6; regressed functionality: 60%
![Page 22: Volodymyr Prymakov and Vlada Benyukh Detailed manual estimation approach for Pre-sale phase](https://reader033.fdocuments.in/reader033/viewer/2022051404/5a649fc77f8b9a31568b5b4b/html5/thumbnails/22.jpg)
How to calculate Regression?
Regression testing time * Test environments Multiplier: 2
![Page 23: Volodymyr Prymakov and Vlada Benyukh Detailed manual estimation approach for Pre-sale phase](https://reader033.fdocuments.in/reader033/viewer/2022051404/5a649fc77f8b9a31568b5b4b/html5/thumbnails/23.jpg)
How to calculate Regression?
If number of regression cycles is 3
![Page 24: Volodymyr Prymakov and Vlada Benyukh Detailed manual estimation approach for Pre-sale phase](https://reader033.fdocuments.in/reader033/viewer/2022051404/5a649fc77f8b9a31568b5b4b/html5/thumbnails/24.jpg)
How to calculate Regression?
Calculation:1) Time for last regression cycle = Pure New functionality testing time (0 bugs) * % of regressed functionality * Test environments Multiplier
2) Regression increment = Time for last regression cycle * number of regression cycles
3) Time for regression testing = Regression Increment * (1+2+… number of regression cycles)
![Page 25: Volodymyr Prymakov and Vlada Benyukh Detailed manual estimation approach for Pre-sale phase](https://reader033.fdocuments.in/reader033/viewer/2022051404/5a649fc77f8b9a31568b5b4b/html5/thumbnails/25.jpg)
Example of Regression calculations
![Page 26: Volodymyr Prymakov and Vlada Benyukh Detailed manual estimation approach for Pre-sale phase](https://reader033.fdocuments.in/reader033/viewer/2022051404/5a649fc77f8b9a31568b5b4b/html5/thumbnails/26.jpg)
What basis for Smoke Testing?
1. Number of smoke testing cycles in sprint
2. Number of sprints/iterations expected
3. Approximate time for smoke
4. Test environments Multiplier
![Page 27: Volodymyr Prymakov and Vlada Benyukh Detailed manual estimation approach for Pre-sale phase](https://reader033.fdocuments.in/reader033/viewer/2022051404/5a649fc77f8b9a31568b5b4b/html5/thumbnails/27.jpg)
Example of Smoke calculations
![Page 28: Volodymyr Prymakov and Vlada Benyukh Detailed manual estimation approach for Pre-sale phase](https://reader033.fdocuments.in/reader033/viewer/2022051404/5a649fc77f8b9a31568b5b4b/html5/thumbnails/28.jpg)
What Risks should be included?
1. Changing/Not Stable Requirements, Increased scope (10%)
2. Documentation and requirements clarification problems (7%)
3. Risk of functionality integration/interdependence and regression
problems (10%)
4. Buggy application risk, because of developers competence (5%)
5. Technology risks (5%)
6. Risk of not mature processes and time spent for improving them (5%)
7. Infrastructure & environment Security & Accessibility Risks (5%)
8. Cross project communication necessity/dependency risk (5%)*
![Page 29: Volodymyr Prymakov and Vlada Benyukh Detailed manual estimation approach for Pre-sale phase](https://reader033.fdocuments.in/reader033/viewer/2022051404/5a649fc77f8b9a31568b5b4b/html5/thumbnails/29.jpg)
Example of Risks basis
![Page 30: Volodymyr Prymakov and Vlada Benyukh Detailed manual estimation approach for Pre-sale phase](https://reader033.fdocuments.in/reader033/viewer/2022051404/5a649fc77f8b9a31568b5b4b/html5/thumbnails/30.jpg)
Example of Summary calculations
![Page 31: Volodymyr Prymakov and Vlada Benyukh Detailed manual estimation approach for Pre-sale phase](https://reader033.fdocuments.in/reader033/viewer/2022051404/5a649fc77f8b9a31568b5b4b/html5/thumbnails/31.jpg)
Demo of real-life example
![Page 32: Volodymyr Prymakov and Vlada Benyukh Detailed manual estimation approach for Pre-sale phase](https://reader033.fdocuments.in/reader033/viewer/2022051404/5a649fc77f8b9a31568b5b4b/html5/thumbnails/32.jpg)
Demo of real-life example
![Page 33: Volodymyr Prymakov and Vlada Benyukh Detailed manual estimation approach for Pre-sale phase](https://reader033.fdocuments.in/reader033/viewer/2022051404/5a649fc77f8b9a31568b5b4b/html5/thumbnails/33.jpg)
Statistics
1. General amount of estimated projects: 15
2. General amount of the project where QA estimation should be adjusted, because of scope and deadlines changes: 5
3. Duration of the projects: 1 -12 months
4. Team size: 5-30
![Page 34: Volodymyr Prymakov and Vlada Benyukh Detailed manual estimation approach for Pre-sale phase](https://reader033.fdocuments.in/reader033/viewer/2022051404/5a649fc77f8b9a31568b5b4b/html5/thumbnails/34.jpg)
Questions