VIRGINIA TECH - apps.vpfin.vt.edu

46

Transcript of VIRGINIA TECH - apps.vpfin.vt.edu

Page 1: VIRGINIA TECH - apps.vpfin.vt.edu
Page 2: VIRGINIA TECH - apps.vpfin.vt.edu
Page 3: VIRGINIA TECH - apps.vpfin.vt.edu

Dewberry Engineers Inc. Table of Contents Advanced Design and Construction Facility (0336) 00 01 02 - 1 DEI# 50095905

VIRGINIA TECH

ADVANCED DESIGN AND CONSTRUCTION FACILITY (0336)

100% CONSTRUCTION DOCUMENTS

DATE – APRIL 6, 2018

PROCUREMENT AND CONTRACT DOCUMENTS

DGS-30-256 Notice of Invitation for Bids

00 01 07 Seals Page

00 01 15 List of Drawing Sheets

HECO-6a Statement of Special Inspections

HECO-6b Schedule of Special Inspections

HECO-6d Interim Report of Special Inspections

HECO-6e Statement of Contractors Responsibility

HECO-6f Fabricators Certificate of Compliance

CO-7 Commonwealth of Virginia General Conditions of the Construction Contract Virginia Tech Supplemental General Conditions to the General Conditions of the

Construction Contract

Virginia Tech Special Terms and Conditions

CO-7a Instructions to Bidders DGS-30-272 Pre-Bid Question Form

DGS-30-220 Bid Form

CO-10.2 Standard Bid Bond

CO-9 Contract Between University and Contractor CO-9a Workers’ Compensation Certificate of Coverage

CO-10 Standard Performance Bond

CO-10.1 Standard Labor and Material Payment Bond CO-11 Contract Change Order CO-GC-1 Change Order Estimate (General Contractors)

CO-SC-1 Change Order Estimate (Subcontractors)

CO-SS-1 Change Order Estimate (Sub-Subcontractors) CO-12 Schedule of Values and Certificate for Payment

CO-13 Affidavit of Payment of Claims HECO 13.1 Certificate of Completion by A/E or Project Manager

HECO 13.1a Certificate of Completion by A/E

HECO 13.1b Final Report of Structural and Special Inspections HECO-13.2 Certificate of Completion by Contractor

HECO-13.2a Certificate of Partial or Substantial Completion by Contractor Qualifications of Inspectors and Testing Technicians

TECHNICAL SPECIFICATIONS

Division 01 – General Conditions

01 00 00 General Provisions

01 01 10 Summary of Work

01 01 40 Work Restrictions

01 01 80 Project Utility Sources

01 02 90 Payment Procedures

01 03 10 Project Management and Coordination

Page 4: VIRGINIA TECH - apps.vpfin.vt.edu

Dewberry Engineers Inc. Table of Contents Advanced Design and Construction Facility (0336) 00 01 02 - 2 DEI# 50095905

01 03 30 Submittal Procedures

01 04 30 Quality Assurance and Control

01 05 00 Temporary Facilities and Controls

01 05 10 Temporary Utilities

01 05 20 Construction Facilities

01 05 50 Vehicular Access and Parking

01 05 60 Temporary Barriers and Enclosures

01 07 00 Contract Closeout

01 07 20 Project Record Documents and Contractors As-Builts

Division 02 – Site Work

02 41 19 Site Demolition

Division 03 – Concrete

03 30 00 Cast-in-Place Concrete

Division 07 – Thermal and Moisture Protection

07 72 53 Snow Guards

Division 08 – Doors and Windows

08 11 13 Hollow Metal Doors and Frames

08 71 00 Door Hardware

Division 09 – Finishes

09 22 16 Non-Structural Metal Framing

09 29 00 Gypsum Board

09 65 13 Resilient Base and Accessories

09 91 23 Interior Painting

Division 10 – Specialties

10 28 00 Toilet, Bath, and Laundry Accessories

10 44 16 Fire Extinguishers

Division 13 – Special Construction

13 34 19 Metal Building Systems

Division 21 – Fire Suppression

21 13 13 Wet Pipe Sprinkler Systems

Division 22 – Plumbing

22 05 17 Sleeves and Sleeve Seals

22 05 19 Meters and Gages for Plumbing Piping

22 05 23 General Duty Valves for Plumbing Piping

22 05 29 Hangers and Supports

22 05 53 Identification for Plumbing Piping and Equipment

22 07 19 Plumbing Piping Insulation

22 11 16 Domestic Water Piping

22 11 19 Domestic Water Piping Specialties

22 13 16 Sanitary Waste and Vent Piping

22 14 16 Fuel Gas Piping

22 33 00 Electric, Domestic-Water Heaters

Page 5: VIRGINIA TECH - apps.vpfin.vt.edu

Dewberry Engineers Inc. Table of Contents Advanced Design and Construction Facility (0336) 00 01 02 - 3 DEI# 50095905

22 40 00 Commercial Plumbing Fixtures

Division 23 – Heating, Ventilations, and Air Conditioning

23 00 10 HVAC Summary

23 01 00 HVAC General Work Requirements

23 01 10 HVAC Submittal List

23 02 00 HVAC Systems Owner Training

23 05 11 HVAC Electrical Provision

23 05 13 HVAC Equipment Motors

23 05 14 Variable Speed Controllers

23 05 29 Hangers and Supports

23 05 53 HVAC Systems Identification

23 05 93 Testing Adjusting and Balancing

23 07 13 Duct Insulation

23 31 13 Metal Ducts

23 33 00 Metal Duct Accessories

23 34 23 HVAC System Fans

23 37 13 Diffusers Grilles and Registers

23 41 00 Particulate Air Filtration Standard Efficiency

23 62 13 Packaged Rooftop Units

23 82 16 Air Coils

23 82 39 Unit Heaters

23 82 40 Infrared Heaters

Division 25 – Integrated Automation

25 01 00 Digital Controls and Instrumentation

Division 26 – Electrical

26 01 00 Basic Electrical Requirements

26 05 00 Basic Electrical Materials and Methods

26 05 19 Conductors and Cables

26 05 26 Grounding and Bonding

26 05 29 Hangers and Supports

26 05 33 Raceways and Boxes

26 05 53 Identification for Electrical Systems

26 09 23 Lighting Control Devices

26 22 00 Dry-type Transformers

26 24 16 Panelboards

26 27 26 Wiring Devices

26 28 13 Fuses

26 28 16 Enclosed Switches and Circuit Breakers

26 41 13 Lightning Protection for Structures

26 51 00 Lighting

26 83 11 Fire Alarm

Division 31 – Earthwork

31 10 00 Site Preparation: Clearing and Grubbing

31 20 00 Earth Moving

31 23 19 Dewatering

31 25 00 Erosion and Sediment Control

Page 6: VIRGINIA TECH - apps.vpfin.vt.edu

Dewberry Engineers Inc. Table of Contents Advanced Design and Construction Facility (0336) 00 01 02 - 4 DEI# 50095905

Division 32 – Exterior Improvements

32 12 16 Asphalt Paving

32 13 13 Concrete Paving

Division 33 – Utilities

33 01 00 Utility Line Testing

33 05 00 Earthwork for Utilities

33 05 26 Utility Location and Identification

33 31 13 Sanitary Sewer Piping

Division 99 – Crane Documents (For Reference Only)

5 Ton Crane Specifications

Crane Operators Manual

END OF SECTION 00 01 02

Page 7: VIRGINIA TECH - apps.vpfin.vt.edu

Dewberry Engineers Inc. Interior Painting Storage Facility Building 09 91 23 - 1 DEI# 50095905

SECTION 099123 - INTERIOR PAINTING

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions

and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes surface preparation and the application of paint systems on interior substrates.

1.3 ACTION SUBMITTALS

A. Product Data: For each type of product. Include preparation requirements and application

instructions.

1.4 MAINTENANCE MATERIAL SUBMITTALS

A. Furnish extra materials, from the same product run, that match products installed and that are

packaged with protective covering for storage and identified with labels describing contents.

1. Paint: 5% percent, but not less than 1 gal. of each material and color applied.

1.5 QUALITY ASSURANCE

A. Mockups: Apply mockups of each paint system indicated and each color and finish selected to verify

preliminary selections made under Sample submittals and to demonstrate aesthetic effects and set

quality standards for materials and execution.

1. Owner will select one surface to represent surfaces and conditions for application of each paint

system specified in Part 3.

a. Vertical and Horizontal Surfaces: Provide samples of at least 100 sq. ft..

b. Other Items: Architect will designate items or areas required.

2. Final approval of color selections will be based on mockups.

a. If preliminary color selections are not approved, apply additional mockups of additional

colors selected by Architect at no added cost to Owner.

Page 8: VIRGINIA TECH - apps.vpfin.vt.edu

Dewberry Engineers Inc. Interior Painting Storage Facility Building 09 91 23 - 2 DEI# 50095905

3. Approval of mockups does not constitute approval of deviations from the Contract

Documents contained in mockups unless Architect specifically approves such deviations

in writing.

4. Subject to compliance with requirements, approved mockups may become part of the

completed Work if undisturbed at time of Substantial Completion.

1.6 DELIVERY, STORAGE, AND HANDLING

A. Store materials not in use in tightly covered containers in well-ventilated areas with ambient

temperatures continuously maintained at not less than 45 deg F.

1. Maintain containers in clean condition, free of foreign materials and residue.

2. Remove rags and waste from storage areas daily.

1.7 FIELD CONDITIONS

A. Apply paints only when temperature of surfaces to be painted and ambient air temperatures are

between 50 and 95 deg F

B. Do not apply paints when relative humidity exceeds 85 percent; at temperatures less than 5 deg F

above the dew point; or to damp or wet surfaces.

PART 2 - PRODUCTS

2.1 MANUFACTURERS

A. Manufacturers: Subject to compliance with requirements, provide products by one of the

following

1. Benjamin Moore & Co.

2. ICI Paints.

3. PPG Architectural Finishes, Inc.

4. Sherwin-Williams Company (The).

2.2 PAINT, GENERAL

A. MPI Standards: Provide products that comply with MPI standards indicated and that are listed in its

"MPI Approved Products List." B. Material Compatibility:

1. Provide materials for use within each paint system that are compatible with one another

and substrates indicated, under conditions of service and application as demonstrated by

manufacturer, based on testing and field experience.

2. For each coat in a paint system, provide products recommended in writing by

manufacturers of topcoat for use in paint system and on substrate indicated.

Page 9: VIRGINIA TECH - apps.vpfin.vt.edu

Dewberry Engineers Inc. Interior Painting Storage Facility Building 09 91 23 - 3 DEI# 50095905

C. VOC Content: Products shall comply with VOC limits of authorities having jurisdiction and, for

interior paints and coatings applied at Project site, the following VOC limits, exclusive of

colorants added to a tint base, when calculated according to 40 CFR 59, Subpart D (EPA Method

24).

1. Flat Paints and Coatings: 50 g/L.

2. Nonflat Paints and Coatings: 150 g/L.

3. Dry-Fog Coatings: 400 g/L.

4. Primers, Sealers, and Undercoaters: 200 g/L.

5. Anticorrosive and Antirust Paints Applied to Ferrous Metals: 250 g/L.

6. Zinc-Rich Industrial Maintenance Primers: 340 g/L.

7. Pretreatment Wash Primers: 420 g/L.

8. Floor Coatings: 100 g/L.

9. Shellacs, Clear: 730 g/L.

10. Shellacs, Pigmented: 550 g/L.

D. Colors: As selected by Architect from manufacturer's full range

2.3 SOURCE QUALITY CONTROL

A. Testing of Paint Materials: Owner reserves the right to invoke the following procedure:

1. Owner may direct Contractor to stop applying coatings if test results show materials being used

do not comply with product requirements. Contractor shall remove noncomplying paint

materials from Project site, pay for testing, and repaint surfaces painted with rejected

materials. Contractor will be required to remove rejected materials from previously painted

surfaces if, on repainting with complying materials, the two paints are incompatible.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine substrates and conditions, with Applicator present, for compliance with requirements

for maximum moisture content and other conditions affecting performance of the Work.

B. Maximum Moisture Content of Substrates: When measured with an electronic moisture meter as

follows:

1. Concrete: 12 percent.

2. Masonry (Clay and CMU): 12 percent.

3. Wood: 15 percent.

4. Gypsum Board: 12 percent.

5. Plaster: 12 percent.

C. Gypsum Board Substrates: Verify that finishing compound is sanded smooth.

Page 10: VIRGINIA TECH - apps.vpfin.vt.edu

Dewberry Engineers Inc. Interior Painting Storage Facility Building 09 91 23 - 4 DEI# 50095905

D. Verify suitability of substrates, including surface conditions and compatibility with existing

finishes and primers.

E. Proceed with coating application only after unsatisfactory conditions have been corrected.

1. Application of coating indicates acceptance of surfaces and conditions.

3.2 PREPARATION

A. Comply with manufacturer's written instructions and recommendations in "MPI Manual"

applicable to substrates indicated.

B. Remove hardware, covers, plates, and similar items already in place that are removable and are

not to be painted. If removal is impractical or impossible because of size or weight of item,

provide surface-applied protection before surface preparation and painting.

1. After completing painting operations, use workers skilled in the trades involved to reinstall

items that were removed. Remove surface-applied protection if any.

C. Clean substrates of substances that could impair bond of paints, including dust, dirt, oil, grease,

and incompatible paints and encapsulants.

1. Remove incompatible primers and reprime substrate with compatible primers or apply tie coat

as required to produce paint systems indicated.

D. Steel Substrates: Remove rust, loose mill scale, and shop primer, if any. Clean using methods

recommended in writing by paint manufacturer.

1. SSPC-SP 2, "Hand Tool Cleaning."

2. SSPC-SP 3, "Power Tool Cleaning."

3. SSPC-SP 7/NACE No. 4, "Brush-off Blast Cleaning."

4. SSPC-SP 11, "Power Tool Cleaning to Bare Metal."

E. Shop-Primed Steel Substrates: Clean field welds, bolted connections, and abraded areas of shop

paint, and paint exposed areas with the same material as used for shop priming to comply with

SSPC-PA 1 for touching up shop-primed surfaces.

F. Galvanized-Metal Substrates: Remove grease and oil residue from galvanized sheet metal

fabricated from coil stock by mechanical methods to produce clean, lightly etched surfaces that

promote adhesion of subsequently applied paints.

G. Aluminum Substrates: Remove loose surface oxidation.

3.3 APPLICATION

A. Apply paints according to manufacturer's written instructions and to recommendations in "MPI

Manual."

Page 11: VIRGINIA TECH - apps.vpfin.vt.edu

Dewberry Engineers Inc. Interior Painting Storage Facility Building 09 91 23 - 5 DEI# 50095905

1. Use applicators and techniques suited for paint and substrate indicated.

2. Paint surfaces behind movable equipment and furniture same as similar exposed surfaces.

Before final installation, paint surfaces behind permanently fixed equipment or furniture

with prime coat only.

3. Paint front and backsides of access panels, removable or hinged covers, and similar hinged

items to match exposed surfaces.

4. Do not paint over labels of independent testing agencies or equipment name, identification,

performance rating, or nomenclature plates.

5. Primers specified in painting schedules may be omitted on items that are factory primed or

factory finished if acceptable to topcoat manufacturers.

B. Tint each undercoat a lighter shade to facilitate identification of each coat if multiple coats of

same material are to be applied. Tint undercoats to match color of topcoat, but provide sufficient

difference in shade of undercoats to distinguish each separate coat.

C. If undercoats or other conditions show through topcoat, apply additional coats until cured film

has a uniform paint finish, color, and appearance.

D. Apply paints to produce surface films without cloudiness, spotting, holidays, laps, brush marks,

roller tracking, runs, sags, ropiness, or other surface imperfections. Cut in sharp lines and color

breaks.

3.4 FIELD QUALITY CONTROL

A. Dry Film Thickness Testing: Owner may engage the services of a qualified testing and inspecting

agency to inspect and test paint for dry film thickness.

1. Contractor shall touch up and restore painted surfaces damaged by testing.

2. If test results show that dry film thickness of applied paint does not comply with paint

manufacturer's written recommendations, Contractor shall pay for testing and apply

additional coats as needed to provide dry film thickness that complies with paint

manufacturer's written recommendations.

3.5 CLEANING AND PROTECTION

A. At end of each workday, remove rubbish, empty cans, rags, and other discarded materials from

Project site.

B. After completing paint application, clean spattered surfaces. Remove spattered paints by washing,

scraping, or other methods. Do not scratch or damage adjacent finished surfaces.

C. Protect work of other trades against damage from paint application. Correct damage to work of

other trades by cleaning, repairing, replacing, and refinishing, as approved by Architect, and leave

in an undamaged condition.

D. At completion of construction activities of other trades, touch up and restore damaged or defaced

painted surfaces.

Page 12: VIRGINIA TECH - apps.vpfin.vt.edu

Dewberry Engineers Inc. Interior Painting Storage Facility Building 09 91 23 - 6 DEI# 50095905

3.6 INTERIOR PAINTING SCHEDULE

A. Steel Substrates- Included, but not limited to: Steel Structure, frames and doors.

1. Latex over Alkyd Primer System:

a. Prime Coat: Primer, alkyd, anti-corrosive, for metal or primer, alkyd, quick dry, for

metal.

b. Prime Coat: Shop primer specified in Section where substrate is specified.

c. Intermediate Coat: Latex, interior, matching topcoat.

d. Topcoat: Latex, interior, semi gloss B. Galvanized-Metal Substrates:

1. High-Performance Architectural Latex System:

a. Prime Coat: Primer, galvanized, water based

b. Intermediate Coat: Latex, interior, high performance architectural, matching

topcoat.

c. Topcoat: Latex, interior, high performance architectural, Semi Gloss C.

Gypsum Board Substrates:

1. High-Performance Architectural Latex System:

a. Prime Coat: Primer sealer, latex, interior

b. Intermediate Coat: Latex, interior, high performance architectural, matching

topcoat.

c. Topcoat: Latex, interior, high performance architectural, Satin

END OF SECTION 099123

Page 13: VIRGINIA TECH - apps.vpfin.vt.edu

Dewberry Engineers Inc. General Duty Valves for Plumbing Piping Advanced Design and Construction Facility (0336) 22 05 23 - 1 DEI# 50095905

SECTION 220523 – GENERAL DUTY VALVES FOR PLUMBING PIPING

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary

Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Brass ball valves.

2. Bronze ball valves.

3. Iron ball valves.

4. Iron, single-flange butterfly valves.

5. Bronze lift check valves.

6. Bronze swing check valves.

7. Iron swing check valves.

8. Bronze globe valves.

9. Iron gate valves.

1.3 DEFINITIONS

A. CWP: Cold working pressure.

B. NRS: Non-rising stem.

C. OS&Y: Outside screw and yoke.

D. EPDM: Ethylene propylene-diene terpolymer rubber.

E. NBR: Acrylonitrile-butadiene, Buna-N, or nitrile rubber.

1.4 ACTION SUBMITTALS

A. Product Data: For each type of valve.

1. Certification that products comply with NSF 61 Annex G and NSF 372.

1.5 DELIVERY, STORAGE, AND HANDLING

A. Prepare valves for shipping as follows:

Page 14: VIRGINIA TECH - apps.vpfin.vt.edu

Dewberry Engineers Inc. General Duty Valves for Plumbing Piping Advanced Design and Construction Facility (0336) 22 05 23 - 2 DEI# 50095905

1. Protect internal parts against rust and corrosion.

2. Protect threads, flange faces, grooves, weld ends, and soldered ends.

3. Set ball valves open to minimize exposure of functional surfaces.

4. Set butterfly valves closed or slightly open.

5. Set check valves in either closed or open position.

6. Set gate valves closed to prevent rattling.

B. Use the following precautions during storage:

1. Maintain valve end protection.

2. Store valves indoors and maintain at higher-than-ambient-dew-point temperature. If

outdoor storage is necessary, store valves off the ground in watertight enclosures.

C. Use sling to handle large valves; rig sling to avoid damage to exposed parts. Do not use

operating handles or stems as lifting or rigging points.

PART 2 - PRODUCTS

2.1 GENERAL REQUIREMENTS FOR VALVES

A. Source Limitations for Valves: Obtain each type of valve from single source from single

manufacturer.

B. ASME Compliance:

1. ASME B1.20.1 for threads for threaded end valves.

2. ASME B16.1 for flanges on iron valves.

3. ASME B16.5 for flanges on steel valves.

4. ASME B16.10 and ASME B16.34 for ferrous valve dimensions and design criteria.

5. ASME B16.18 for solder-joint connections.

6. ASME B31.9 for building services piping valves.

C. NSF Compliance: NSF 61 Annex G and NSF 372 for valve materials for potable-water service.

D. Bronze valves shall be made with dezincification-resistant materials. Bronze valves made with

copper alloy (brass) containing more than 15 percent zinc are not permitted.

E. Valve Pressure-Temperature Ratings: Not less than indicated and as required for system

pressures and temperatures.

F. Valve Sizes: Same as upstream piping unless otherwise indicated.

G. Valve Actuator Types:

1. Gear Actuator: For quarter-turn valves NPS 6 and larger.

2. Hand lever: For quarter-turn valves smaller than NPS 6.

H. Valves in Insulated Piping:

1. Include 2-inch stem extensions.

Page 15: VIRGINIA TECH - apps.vpfin.vt.edu

Dewberry Engineers Inc. General Duty Valves for Plumbing Piping Advanced Design and Construction Facility (0336) 22 05 23 - 3 DEI# 50095905

2. Extended operating handles of non-thermal-conductive material and protective sleeves

that allow operation of valves without breaking vapor seals or disturbing insulation.

3. Memory stops that are fully adjustable after insulation is applied.

I. Gate Valve Valve Bypass and Drain Connections: MSS SP-45

2.2 BRASS BALL VALVES

A. Brass Ball Valves, Two-Piece with Full Port and Brass Trim:

1. Description:

a. Standard: MSS SP-110.

b. CWP Rating: 600 psig.

c. Body Design: Two piece.

d. Body Material: Forged brass.

e. Ends: Threaded and soldered.

f. Seats: PTFE.

g. Stem: Brass.

h. Ball: Chrome-plated brass.

i. Port: Full.

B. Brass Ball Valves, Two-Piece with Full Port and Stainless-Steel Trim:

1. Description:

a. Standard: MSS SP-110.

b. CWP Rating: 600 psig.

c. Body Design: Two piece.

d. Body Material: Forged brass.

e. Ends: Threaded and soldered.

f. Seats: PTFE.

g. Stem: Stainless steel.

h. Ball: Stainless steel, vented.

i. Port: Full.

C. Brass Ball Valves, Three-Piece with Full Port and Stainless-Steel Trim:

1. Description:

a. Standard: MSS SP-110.

b. CWP Rating: 600 psig.

c. Body Design: Three piece.

d. Body Material: Forged brass.

e. Ends: Threaded and soldered.

f. Seats: PTFE or TFE.

g. Stem: Stainless steel.

h. Ball: Stainless steel, vented.

i. Port: Full.

Page 16: VIRGINIA TECH - apps.vpfin.vt.edu

Dewberry Engineers Inc. General Duty Valves for Plumbing Piping Advanced Design and Construction Facility (0336) 22 05 23 - 4 DEI# 50095905

2.3 BRONZE BALL VALVES

A. Bronze Ball Valves, Two-Piece with Full Port and Stainless-Steel Trim:

1. Description:

a. Standard: MSS SP-110.

b. CWP Rating: 600 psig.

c. Body Design: Two piece.

d. Body Material: Bronze.

e. Ends: Threaded or soldered.

f. Seats: PTFE.

g. Stem: Stainless steel.

h. Ball: Stainless steel, vented.

i. Port: Full.

B. Bronze Ball Valves, Two-Piece with Regular Port and Stainless-Steel Trim:

1. Description:

a. Standard: MSS SP-110.

b. CWP Rating: 600 psig.

c. Body Design: Two piece.

d. Body Material: Bronze.

e. Ends: Threaded.

f. Seats: PTFE.

g. Stem: Stainless steel.

h. Ball: Stainless steel, vented.

i. Port: Regular.

C. Bronze Ball Valves, Three-Piece with Full Port and Stainless-Steel Trim:

1. Description:

a. Standard: MSS SP-110.

b. CWP Rating: 600 psig.

c. Body Design: Three piece.

d. Body Material: Bronze.

e. Ends: Threaded.

f. Seats: PTFE.

g. Stem: Stainless steel.

h. Ball: Stainless steel, vented.

i. Port: Full.

2.4 IRON BALL VALVES

A. Iron Ball Valves, Class 125:

1. Description:

Page 17: VIRGINIA TECH - apps.vpfin.vt.edu

Dewberry Engineers Inc. General Duty Valves for Plumbing Piping Advanced Design and Construction Facility (0336) 22 05 23 - 5 DEI# 50095905

a. Standard: MSS SP-72.

b. CWP Rating: 200 psig.

c. Body Design: Split body.

d. Body Material: ASTM A 126, gray iron.

e. Ends: Flanged or threaded.

f. Seats: PTFE.

g. Stem: Stainless steel.

h. Ball: Stainless steel.

i. Port: Full.

2.5 IRON, SINGLE-FLANGE BUTTERFLY VALVES

A. Iron, Single-Flange Butterfly Valves with Stainless-Steel Disc:

1. Description:

a. Standard: MSS SP-67, Type I.

b. CWP Rating: 200 psig.

c. Body Design: Lug type; suitable for bidirectional dead-end service at rated

pressure without use of downstream flange.

d. Body Material: ASTM A 126, cast iron or ASTM A 536, ductile iron.

e. Seat: EPDM.

f. Stem: One- or two-piece stainless steel.

g. Disc: Stainless steel.

2.6 BRONZE LIFT CHECK VALVES

A. Bronze Lift Check Valves with Bronze Disc, Class 125:

1. Description:

a. Standard: MSS SP-80, Type 1.

b. CWP Rating: 200 psig.

c. Body Design: Vertical flow.

d. Body Material: ASTM B 61 or ASTM B 62, bronze.

e. Ends: Threaded or soldered.

f. Disc: Bronze.

2.7 BRONZE SWING CHECK VALVES

A. Bronze Swing Check Valves with Bronze Disc, Class 125:

1. Description:

a. Standard: MSS SP-80, Type 3.

b. CWP Rating: 200 psig.

c. Body Design: Horizontal flow.

d. Body Material: ASTM B 62, bronze.

Page 18: VIRGINIA TECH - apps.vpfin.vt.edu

Dewberry Engineers Inc. General Duty Valves for Plumbing Piping Advanced Design and Construction Facility (0336) 22 05 23 - 6 DEI# 50095905

e. Ends: Threaded or soldered. See valve schedule articles.

f. Disc: Bronze.

2.8 IRON SWING CHECK VALVES

A. Iron Swing Check Valves with Metal Seats, Class 125:

1. Description:

a. Standard: MSS SP-71, Type I.

b. CWP Rating: 200 psig.

c. Body Design: Clear or full waterway.

d. Body Material: ASTM A 126, gray iron with bolted bonnet.

e. Ends: Flanged or threaded. See valve schedule articles.

f. Trim: Bronze.

g. Gasket: Asbestos free.

2.9 BRONZE GLOBE VALVES

A. Class 125, Bronze Globe Valves with Bronze Disc:

1. Description:

a. Standard: MSS SP-80, Type 1.

b. CWP Rating: 200 psig.

c. Body Material: ASTM B 62, bronze with integral seat and screw-in bonnet.

d. Ends: Threaded or solder joint.

e. Stem and Disc: Bronze.

f. Packing: Asbestos free.

g. Hand wheel: Malleable iron, bronze, or aluminum.

2.10 IRON GATE VALVES

A. Iron Gate Valves, NRS, Class 150:

1. Description:

a. Standard: MSS SP-70, Type I.

b. CWP Rating: 200 psig.

c. Body Material: Gray iron with bolted bonnet.

d. Ends: Flanged.

e. Trim: Bronze.

f. Disc: Solid wedge.

g. Packing and Gasket: Asbestos free.

Page 19: VIRGINIA TECH - apps.vpfin.vt.edu

Dewberry Engineers Inc. General Duty Valves for Plumbing Piping Advanced Design and Construction Facility (0336) 22 05 23 - 7 DEI# 50095905

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine valve interior for cleanliness, freedom from foreign matter, and corrosion. Remove

special packing materials, such as blocks, used to prevent disc movement during shipping and

handling.

B. Operate valves in positions from fully open to fully-closed. Examine guides and seats made

accessible by such operations.

C. Examine threads on valve and mating pipe for form and cleanliness.

D. Examine mating flange faces for conditions that might cause leakage. Check bolting for proper

size, length, and material. Verify that gasket is of proper size, that its material composition is

suitable for service, and that it is free from defects and damage.

E. Do not attempt to repair defective valves; replace with new valves.

3.2 VALVE INSTALLATION

A. Install valves with unions or flanges at each piece of equipment arranged to allow service,

maintenance, and equipment removal without system shutdown.

B. Locate valves for easy access and provide separate support where necessary.

C. Install valves in horizontal piping with stem at or above center of pipe.

D. Install valves in position to allow full stem movement.

E. Install valve tags. Comply with requirements in Section 220553 "Identification for Plumbing

Piping and Equipment" for valve tags and schedules.

F. Install check valves for proper direction of flow and as follows:

1. Swing Check Valves: In horizontal position with hinge pin level.

2. Lift Check Valves: With stem upright and plumb.

3.3 ADJUSTING

A. Adjust or replace valve packing after piping systems have been tested and put into service but

before final adjusting and balancing. Replace valves if persistent leaking occurs.

3.4 GENERAL REQUIREMENTS FOR VALVE APPLICATIONS

A. If valve applications are not indicated, use the following:

1. Shutoff Service: Ball or butterfly valves.

Page 20: VIRGINIA TECH - apps.vpfin.vt.edu

Dewberry Engineers Inc. General Duty Valves for Plumbing Piping Advanced Design and Construction Facility (0336) 22 05 23 - 8 DEI# 50095905

2. Throttling Service: Globe, ball, or butterfly valves.

3. Pump-Discharge Check Valves:

a. NPS 2 and Smaller: Bronze swing check valves with bronze disc.

b. NPS 2-1/2 and Larger for Domestic Water: Iron swing check valves with lever and

weight or with spring or iron, center-guided, metal-seat check valves.

B. If valves with specified CWP ratings are unavailable, the same types of valves with higher CWP

ratings may be substituted.

C. Select valves with the following end connections:

1. For Copper Tubing, NPS 2 and Smaller: Threaded ends except where solder-joint valve-

end option is indicated in valve schedules below.

2. For Copper Tubing, NPS 2-1/2 to NPS 4: Flanged ends except where threaded valve-end

option is indicated in valve schedules below.

3. For Copper Tubing, NPS 5 and Larger: Flanged ends.

4. For Steel Piping, NPS 2 and Smaller: Threaded ends.

5. For Steel Piping, NPS 2-1/2 and Larger: Flanged ends except where threaded valve-end

option is indicated in valve schedules below.

3.5 DOMESTIC HOT- AND COLD-WATER VALVE SCHEDULE

A. Pipe NPS 2 and Smaller:

1. Ball Valves:

a. Bronze and Brass Valves: May be provided with solder-joint ends instead of

threaded ends.

b. Brass ball valves, two-piece with full port and stainless-steel trim.

c. Bronze ball valves, two-piece with full port and stainless-steel trim.

d. Brass ball valves, three-piece with full port and stainless-steel trim.

e. Bronze ball valves, three-piece with full port and stainless-steel trim.

2. Check Valves:

a. Bronze swing check valves with bronze disc, Class 125, with soldered or threaded

end connections.

B. Pipe NPS 2-1/2 and Larger:

1. Ball Valves:

a. Iron Valves, NPS 2-1/2 to NPS 4: May be provided with threaded ends instead of

flanged ends.

b. Iron ball valves, Class 150.

2. Butterfly Valves:

a. Iron, Single-Flange Butterfly Valves: 200 CWP, EPDM seat, stainless-steel disc.

3. Check Valves:

a. Iron swing check valves with metal seats, Class 125, with threaded of flanged end

connections.

Page 21: VIRGINIA TECH - apps.vpfin.vt.edu

Dewberry Engineers Inc. General Duty Valves for Plumbing Piping Advanced Design and Construction Facility (0336) 22 05 23 - 9 DEI# 50095905

4. Iron Gate Valves:

a. NRS, Class 125 with flanged ends.

END OF SECTION 220523

Page 22: VIRGINIA TECH - apps.vpfin.vt.edu

Dewberry Engineers Inc. Fuel Gas Piping Advanced Design and Construction Facility (0336) 22 14 16 - 1 DEI# 50095905

SECTION 221416 – FUEL GAS PIPING

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary

Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Pipes, tubes, and fittings.

2. Piping specialties.

3. Piping and tubing joining materials.

4. Valves.

5. Pressure regulators.

6. Concrete bases.

1.3 DEFINITIONS

A. Finished Spaces: Spaces other than mechanical and electrical equipment rooms, furred spaces,

pipe and duct shafts, unheated spaces immediately below roof, spaces above ceilings,

unexcavated spaces, crawlspaces, and tunnels.

B. Exposed, Interior Installations: Exposed to view indoors. Examples include finished occupied

spaces and mechanical equipment rooms.

C. Exposed, Exterior Installations: Exposed to view outdoors or subject to outdoor ambient

temperatures and weather conditions. Examples include rooftop locations.

1.4 PERFORMANCE REQUIREMENTS

A. Minimum Operating-Pressure Ratings:

1. Piping and Valves: 100 psig minimum unless otherwise indicated.

2. Service Regulators: 100 psig minimum unless otherwise indicated.

B. Natural-Gas System Pressure within Buildings: 0.5 psig or less.

1.5 ACTION SUBMITTALS

A. Product Data: For each type of the following:

Page 23: VIRGINIA TECH - apps.vpfin.vt.edu

Dewberry Engineers Inc. Fuel Gas Piping Advanced Design and Construction Facility (0336) 22 14 16 - 2 DEI# 50095905

1. Piping specialties.

2. Corrugated, stainless-steel tubing with associated components.

3. Valves. Include pressure rating, capacity, settings, and electrical connection data of

selected models.

4. Pressure regulators. Indicate pressure ratings and capacities.

5. Dielectric fittings.

1.6 INFORMATIONAL SUBMITTALS

A. Welding certificates.

B. Field quality-control reports.

1.7 CLOSEOUT SUBMITTALS

A. Operation and Maintenance Data: For pressure regulators to include in emergency, operation,

and maintenance manuals.

1.8 QUALITY ASSURANCE

A. Steel Support Welding Qualifications: Qualify procedures and personnel according to

AWS D1.1/D1.1M, "Structural Welding Code - Steel."

B. Pipe Welding Qualifications: Qualify procedures and operators according to ASME Boiler and

Pressure Vessel Code.

C. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, by

a qualified testing agency, and marked for intended location and application.

1.9 DELIVERY, STORAGE, AND HANDLING

A. Deliver pipes and tubes with factory-applied end caps. Maintain end caps through shipping,

storage, and handling to prevent pipe end damage and to prevent entrance of dirt, debris, and

moisture.

B. Store and handle pipes and tubes having factory-applied protective coatings to avoid damaging

coating, and protect from direct sunlight.

C. Protect stored PE pipes and valves from direct sunlight.

1.10 COORDINATION

A. Coordinate sizes and locations of concrete bases with actual equipment provided.

B. Coordinate requirements for access panels and doors for valves installed concealed behind

finished surfaces. Comply with requirements in Section 083113 "Access Doors and Frames."

Page 24: VIRGINIA TECH - apps.vpfin.vt.edu

Dewberry Engineers Inc. Fuel Gas Piping Advanced Design and Construction Facility (0336) 22 14 16 - 3 DEI# 50095905

PART 2 - PRODUCTS

2.1 PIPES, TUBES, AND FITTINGS

A. Steel Pipe: ASTM A 53/A 53M, black steel, Schedule 40, Type E or S, Grade B.

1. Malleable-Iron Threaded Fittings: ASME B16.3, Class 150, standard pattern.

2. Wrought-Steel Welding Fittings: ASTM A 234/A 234M for butt welding and socket

welding.

3. Unions: ASME B16.39, Class 150, malleable iron with brass-to-iron seat, ground joint,

and threaded ends.

4. Forged-Steel Flanges and Flanged Fittings: ASME B16.5, minimum Class 150, including

bolts, nuts, and gaskets of the following material group, end connections, and facings:

a. Material Group: 1.1.

b. End Connections: Threaded or butt welding to match pipe.

c. Lapped Face: Not permitted underground.

d. Gasket Materials: ASME B16.20, metallic, flat, asbestos free, aluminum o-rings,

and spiral-wound metal gaskets.

e. Bolts and Nuts: ASME B18.2.1, carbon steel aboveground and stainless steel

underground.

5. Protective Coating for Underground Piping: Factory-applied, three-layer coating of

epoxy, adhesive, and PE.

a. Joint Cover Kits: Epoxy paint, adhesive, and heat-shrink PE sleeves.

6. Mechanical Couplings:

a. Steel flanges and tube with epoxy finish.

b. Buna-nitrile seals.

c. Steel bolts, washers, and nuts.

d. Coupling shall be capable of joining PE pipe to PE pipe, steel pipe to PE pipe, or

steel pipe to steel pipe.

e. Steel body couplings installed underground on plastic pipe shall be factory

equipped with anode.

7. Tubing: ASTM A 240/A 240M, corrugated, Series 300 stainless steel.

8. Coating: PE with flame retardant.

a. Surface-Burning Characteristics: As determined by testing identical products

according to ASTM E 84 by a qualified testing agency. Identify products with

appropriate markings of applicable testing agency.

1) Flame-Spread Index: 25 or less.

2) Smoke-Developed Index: 50 or less.

9. Fittings: Copper-alloy mechanical fittings with ends made to fit and listed for use with

corrugated stainless-steel tubing and capable of metal-to-metal seal without gaskets.

Include brazing socket or threaded ends complying with ASME B1.20.1.

Page 25: VIRGINIA TECH - apps.vpfin.vt.edu

Dewberry Engineers Inc. Fuel Gas Piping Advanced Design and Construction Facility (0336) 22 14 16 - 4 DEI# 50095905

10. Striker Plates: Steel, designed to protect tubing from penetrations.

11. Manifolds: Malleable iron or steel with factory-applied protective coating. Threaded

connections shall comply with ASME B1.20.1 for pipe inlet and corrugated tubing

outlets.

12. Protective Coating for Underground Tubing: Factory-applied, extruded PE a minimum of

0.022 inch thick.

13. Flare Fittings: Comply with ASME B16.26 and SAE J513.

a. Copper fittings with long nuts.

b. Metal-to-metal compression seal without gasket.

c. Dryseal threads complying with ASME B1.20.3.

14. Protective Coating for Underground Tubing: Factory-applied, extruded PE a minimum of

0.022 inch thick.

B. PE Pipe: ASTM D 2513, SDR 11.

1. PE Fittings: ASTM D 2683, socket-fusion type or ASTM D 3261, butt-fusion type with

dimensions matching PE pipe.

2. PE Transition Fittings: Factory-fabricated fittings with PE pipe complying with

ASTM D 2513, SDR 11; and steel pipe complying with ASTM A 53/A 53M, black steel,

Schedule 40, Type E or S, Grade B.

3. Anodeless Service-Line Risers: Factory fabricated and leak tested.

a. Underground Portion: PE pipe complying with ASTM D 2513, SDR 11 inlet.

b. Casing: Steel pipe complying with ASTM A 53/A 53M, Schedule 40, black steel,

Type E or S, Grade B, with corrosion-protective coating covering.

c. Aboveground Portion: PE transition fitting.

d. Outlet shall be threaded or flanged or suitable for welded connection.

e. Tracer wire connection.

f. Ultraviolet shield.

g. Stake supports with factory finish to match steel pipe casing or carrier pipe.

4. Transition Service-Line Risers: Factory fabricated and leak tested.

a. Underground Portion: PE pipe complying with ASTM D 2513, SDR 11 inlet

connected to steel pipe complying with ASTM A 53/A 53M, Schedule 40, Type E

or S, Grade B, with corrosion-protective coating for aboveground outlet.

b. Outlet shall be threaded or flanged or suitable for welded connection.

c. Bridging sleeve over mechanical coupling.

d. Factory-connected anode.

e. Tracer wire connection.

f. Ultraviolet shield.

g. Stake supports with factory finish to match steel pipe casing or carrier pipe.

h. PE body with molded-in, stainless-steel support ring.

i. Buna-nitrile seals.

j. Acetal collets.

k. Electro-zinc-plated steel stiffener.

l.

m. Fiber-reinforced plastic body.

Page 26: VIRGINIA TECH - apps.vpfin.vt.edu

Dewberry Engineers Inc. Fuel Gas Piping Advanced Design and Construction Facility (0336) 22 14 16 - 5 DEI# 50095905

n. PE body tube.

o. Buna-nitrile seals.

p. Acetal collets.

q. Stainless-steel bolts, nuts, and washers.

5. Steel Mechanical Couplings: Capable of joining plain-end PE pipe to PE pipe, steel pipe

to PE pipe, or steel pipe to steel pipe.

a. Steel flanges and tube with epoxy finish.

b. Buna-nitrile seals.

c. Steel bolts, washers, and nuts.

d. Factory-installed anode for steel-body couplings installed underground.

2.2 PIPING SPECIALTIES

A. Appliance Flexible Connectors:

1. Indoor, Fixed-Appliance Flexible Connectors: Comply with ANSI Z21.24.

2. Indoor, Movable-Appliance Flexible Connectors: Comply with ANSI Z21.69.

3. Outdoor, Appliance Flexible Connectors: Comply with ANSI Z21.75.

4. Corrugated stainless-steel tubing with polymer coating.

5. Operating-Pressure Rating: 0.5 psig.

6. End Fittings: Zinc-coated steel.

7. Threaded Ends: Comply with ASME B1.20.1.

8. Maximum Length: 72 inches

B. Quick-Disconnect Devices: Comply with ANSI Z21.41.

1. Copper-alloy convenience outlet and matching plug connector.

2. Nitrile seals.

3. Hand operated with automatic shutoff when disconnected.

4. For indoor or outdoor applications.

5. Adjustable, retractable restraining cable.

C. Y-Pattern Strainers:

1. Body: ASTM A 126, Class B, cast iron with bolted cover and bottom drain connection.

2. End Connections: Threaded ends for NPS 2 and smaller; flanged ends for NPS 2-1/2 and

larger.

3. CWP Rating: 125 psig.

4. Strainer Screen: 40 mesh startup strainer, and perforated stainless-steel basket with 50

percent free area.

5. CWP Rating: 125 psig.

D. T-Pattern Strainers:

1. Body: Ductile or malleable iron with removable access coupling and end cap for strainer

maintenance.

2. End Connections: Grooved ends.

Page 27: VIRGINIA TECH - apps.vpfin.vt.edu

Dewberry Engineers Inc. Fuel Gas Piping Advanced Design and Construction Facility (0336) 22 14 16 - 6 DEI# 50095905

3. Strainer Screen: 40 mesh startup strainer, and perforated stainless-steel basket with 57

percent free area.

4. CWP Rating: 750 psig.

E. Weatherproof Vent Cap: Cast- or malleable-iron increaser fitting with corrosion-resistant wire

screen, with free area at least equal to cross-sectional area of connecting pipe and threaded-end

connection.

2.3 JOINING MATERIALS

A. Joint Compound and Tape: Suitable for natural gas.

B. Welding Filler Metals: Comply with AWS D10.12/D10.12M for welding materials appropriate

for wall thickness and chemical analysis of steel pipe being welded.

C. Brazing Filler Metals: Alloy with melting point greater than 1000 deg. F complying with

AWS A5.8/A5.8M. Brazing alloys containing more than 0.05 percent phosphorus are

prohibited.

2.4 MANUAL GAS SHUTOFF VALVES

A. General Requirements for Metallic Valves, NPS 2 and Smaller: Comply with ASME B16.33.

1. CWP Rating: 125 psig.

2. Threaded Ends: Comply with ASME B1.20.1.

3. Dryseal Threads on Flare Ends: Comply with ASME B1.20.3.

4. Tamperproof Feature: Locking feature for valves indicated in "Underground Manual Gas

Shutoff Valve Schedule" and "Aboveground Manual Gas Shutoff Valve Schedule"

Articles.

5. Listing: Listed and labeled by an NRTL acceptable to authorities having jurisdiction for

valves 1 inch and smaller.

6. Service Mark: Valves 1-1/4 inches to NPS 2 shall have initials "WOG" permanently

marked on valve body.

B. General Requirements for Metallic Valves, NPS 2-1/2 and Larger: Comply with ASME B16.38.

1. CWP Rating: 125 psig.

2. Flanged Ends: Comply with ASME B16.5 for steel flanges.

3. Tamperproof Feature: Locking feature for valves indicated in "Underground Manual Gas

Shutoff Valve Schedule" and "Aboveground Manual Gas Shutoff Valve Schedule"

Articles.

4. Service Mark: Initials "WOG" shall be permanently marked on valve body.

C. Two-Piece, Full-Port, Bronze Ball Valves with Bronze Trim: MSS SP-110.

1. Body: Bronze, complying with ASTM B 584.

2. Ball: Chrome-plated bronze.

3. Stem: Bronze; blowout proof.

4. Seats: Reinforced TFE; blowout proof.

5. Packing: Threaded-body packnut design with adjustable-stem packing.

Page 28: VIRGINIA TECH - apps.vpfin.vt.edu

Dewberry Engineers Inc. Fuel Gas Piping Advanced Design and Construction Facility (0336) 22 14 16 - 7 DEI# 50095905

6. Ends: Threaded, flared, or socket as indicated in "Underground Manual Gas Shutoff

Valve Schedule" and "Aboveground Manual Gas Shutoff Valve Schedule" Articles.

7. CWP Rating: 600 psig.

8. Listing: Valves NPS 1 and smaller shall be listed and labeled by an NRTL acceptable to

authorities having jurisdiction.

9. Service: Suitable for natural-gas service with "WOG" indicated on valve body.

D. Bronze Plug Valves: MSS SP-78.

1. Body: Bronze, complying with ASTM B 584.

2. Plug: Bronze.

3. Ends: Threaded, socket, or flanged as indicated in "Underground Manual Gas Shutoff

Valve Schedule" and "Aboveground Manual Gas Shutoff Valve Schedule" Articles.

4. Operator: Square head or lug type with tamperproof feature where indicated.

5. Pressure Class: 125 psig.

6. Listing: Valves NPS 1 and smaller shall be listed and labeled by an NRTL acceptable to

authorities having jurisdiction.

7. Service: Suitable for natural-gas service with "WOG" indicated on valve body.

E. Cast-Iron, Non-lubricated Plug Valves: MSS SP-78.

1. Body: Cast iron, complying with ASTM A 126, Class B.

2. Plug: Bronze or nickel-plated cast iron.

3. Seat: Coated with thermoplastic.

4. Stem Seal: Compatible with natural gas.

5. Ends: Threaded or flanged as indicated in "Underground Manual Gas Shutoff Valve

Schedule" and "Aboveground Manual Gas Shutoff Valve Schedule" Articles.

6. Operator: Square head or lug type with tamperproof feature where indicated.

7. Pressure Class: 125 psig.

8. Listing: Valves NPS 1 and smaller shall be listed and labeled by an NRTL acceptable to

authorities having jurisdiction.

9. Service: Suitable for natural-gas service with "WOG" indicated on valve body.

F. Cast-Iron, Lubricated Plug Valves: MSS SP-78.

1. Body: Cast iron, complying with ASTM A 126, Class B.

2. Plug: Bronze or nickel-plated cast iron.

3. Seat: Coated with thermoplastic.

4. Stem Seal: Compatible with natural gas.

5. Ends: Threaded or flanged as indicated in "Underground Manual Gas Shutoff Valve

Schedule" and "Aboveground Manual Gas Shutoff Valve Schedule" Articles.

6. Operator: Square head or lug type with tamperproof feature where indicated.

7. Pressure Class: 125 psig.

8. Listing: Valves NPS 1 and smaller shall be listed and labeled by an NRTL acceptable to

authorities having jurisdiction.

9. Service: Suitable for natural-gas service with "WOG" indicated on valve body.

2.5 EARTHQUAKE VALVES

A. Earthquake Valves: Comply with ASCE 25.

Page 29: VIRGINIA TECH - apps.vpfin.vt.edu

Dewberry Engineers Inc. Fuel Gas Piping Advanced Design and Construction Facility (0336) 22 14 16 - 8 DEI# 50095905

1. Listing: Listed and labeled by an NRTL acceptable to authorities having jurisdiction.

2. Maximum Operating Pressure: 0.5 psig.

3. Cast-aluminum body with stainless-steel internal parts.

4. Nitrile-rubber, reset-stem o-ring seal.

5. Valve position, open or closed, indicator.

6. Composition valve seat with clapper held by spring or magnet locking mechanism.

7. Level indicator.

8. End Connections: Threaded for valves NPS 2 and smaller; flanged for valves NPS 2-1/2

and larger.

2.6 PRESSURE REGULATORS

A. General Requirements:

1. Single stage and suitable for natural gas.

2. Steel jacket and corrosion-resistant components.

3. Elevation compensator.

4. End Connections: Threaded for regulators NPS 2 and smaller; flanged for regulators

NPS 2-1/2 and larger.

B. Service Pressure Regulators: Comply with ANSI Z21.80.

1. Body and Diaphragm Case: Cast iron or die-cast aluminum.

2. Springs: Zinc-plated steel; interchangeable.

3. Diaphragm Plate: Zinc-plated steel.

4. Seat Disc: Nitrile rubber resistant to gas impurities, abrasion, and deformation at the

valve port.

5. Orifice: Aluminum; interchangeable.

6. Seal Plug: Ultraviolet-stabilized, mineral-filled nylon.

7. Single-port, self-contained regulator with orifice no larger than required at maximum

pressure inlet, and no pressure sensing piping external to the regulator.

8. Pressure regulator shall maintain discharge pressure setting downstream, and not exceed

150 percent of design discharge pressure at shutoff.

9. Overpressure Protection Device: Factory mounted on pressure regulator.

10. Atmospheric Vent: Factory- or field-installed, stainless-steel screen in opening if not

connected to vent piping.

11. Maximum Inlet Pressure: 100 psig.

C. Line Pressure Regulators: Comply with ANSI Z21.80.

1. Body and Diaphragm Case: Cast iron or die-cast aluminum.

2. Springs: Zinc-plated steel; interchangeable.

3. Diaphragm Plate: Zinc-plated steel.

4. Seat Disc: Nitrile rubber resistant to gas impurities, abrasion, and deformation at the

valve port.

5. Orifice: Aluminum; interchangeable.

6. Seal Plug: Ultraviolet-stabilized, mineral-filled nylon.

7. Single-port, self-contained regulator with orifice no larger than required at maximum

pressure inlet, and no pressure sensing piping external to the regulator.

Page 30: VIRGINIA TECH - apps.vpfin.vt.edu

Dewberry Engineers Inc. Fuel Gas Piping Advanced Design and Construction Facility (0336) 22 14 16 - 9 DEI# 50095905

8. Pressure regulator shall maintain discharge pressure setting downstream, and not exceed

150 percent of design discharge pressure at shutoff.

9. Overpressure Protection Device: Factory mounted on pressure regulator.

10. Atmospheric Vent: Factory- or field-installed, stainless-steel screen in opening if not

connected to vent piping.

11. Maximum Inlet Pressure: 2 psig.

2.7 DIELECTRIC FITTINGS

A. General Requirements: Assembly of copper alloy and ferrous materials with separating

nonconductive insulating material. Include end connections compatible with pipes to be joined.

B. Dielectric Unions:

1. Description:

a. Standard: ASSE 1079.

b. Pressure Rating: 125 psig minimum at 180 deg. F.

c. End Connections: Solder-joint copper alloy and threaded ferrous.

C. Dielectric Flanges:

1. Description:

a. Standard: ASSE 1079.

b. Factory-fabricated, bolted, companion-flange assembly.

c. Pressure Rating: 125 psig minimum at 180 deg.

d. End Connections: Solder-joint copper alloy and threaded ferrous; threaded solder-

joint copper alloy and threaded ferrous.

D. Dielectric-Flange Insulating Kits:

1. Description:

a. Non-conducting materials for field assembly of companion flanges.

b. Pressure Rating: 150 psig.

c. Gasket: Neoprene or phenolic.

d. Bolt Sleeves: Phenolic or polyethylene.

e. Washers: Phenolic with steel backing washers.

2.8 LABELING AND IDENTIFYING

A. Detectable Warning Tape: Acid- and alkali-resistant, PE film warning tape manufactured for

marking and identifying underground utilities, a minimum of 6 inches wide and 4 mils thick,

continuously inscribed with a description of utility, with metallic core encased in a protective

jacket for corrosion protection, detectable by metal detector when tape is buried up to 30 inches

deep; colored yellow.

Page 31: VIRGINIA TECH - apps.vpfin.vt.edu

Dewberry Engineers Inc. Fuel Gas Piping Advanced Design and Construction Facility (0336) 22 14 16 - 10 DEI# 50095905

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine roughing-in for natural-gas piping system to verify actual locations of piping

connections before equipment installation.

B. Proceed with installation only after unsatisfactory conditions have been corrected.

3.2 PREPARATION

A. Inspect natural-gas piping according to the International Fuel Gas Code to determine that

natural-gas utilization devices are turned off in piping section affected.

B. Comply with the International Fuel Gas Code requirements for prevention of accidental

ignition.

3.3 OUTDOOR PIPING INSTALLATION

A. Comply with the International Fuel Gas Code for installation and purging of natural-gas piping.

B. Install underground, natural-gas piping buried at least 18 inches below finished grade. Comply

with requirements in Section 312000 "Earth Moving" for excavating, trenching, and backfilling.

1. If natural-gas piping is installed less than 18 inches below finished grade, install it in

containment conduit.

C. Install underground, PE, natural-gas piping according to ASTM D 2774.

D. Steel Piping with Protective Coating:

1. Apply joint cover kits to pipe after joining to cover, seal, and protect joints.

2. Repair damage to PE coating on pipe as recommended in writing by protective coating

manufacturer.

3. Replace pipe having damaged PE coating with new pipe.

E. Copper Tubing with Protective Coating:

1. Apply joint cover kits over tubing to cover, seal, and protect joints.

2. Repair damage to PE coating on pipe as recommended in writing by protective coating

manufacturer.

F. Install fittings for changes in direction and branch connections.

G. Install pressure gage upstream and downstream from each service regulator. Pressure gages are

specified in Section 230519 "Meters and Gages for HVAC Piping."

Page 32: VIRGINIA TECH - apps.vpfin.vt.edu

Dewberry Engineers Inc. Fuel Gas Piping Advanced Design and Construction Facility (0336) 22 14 16 - 11 DEI# 50095905

3.4 INDOOR PIPING INSTALLATION

A. Comply with the International Fuel Gas Code for installation and purging of natural-gas piping.

B. Drawing plans, schematics, and diagrams indicate general location and arrangement of piping

systems. Indicated locations and arrangements are used to size pipe and calculate friction loss,

expansion, and other design considerations. Install piping as indicated unless deviations to

layout are approved on Coordination Drawings.

C. Arrange for pipe spaces, chases, slots, sleeves, and openings in building structure during

progress of construction, to allow for mechanical installations.

D. Install piping in concealed locations unless otherwise indicated and except in equipment rooms

and service areas.

E. Install piping indicated to be exposed and piping in equipment rooms and service areas at right

angles or parallel to building walls. Diagonal runs are prohibited unless specifically indicated

otherwise.

F. Install piping above accessible ceilings to allow sufficient space for ceiling panel removal.

G. Locate valves for easy access.

H. Install natural-gas piping at uniform grade of 2 percent down toward drip and sediment traps.

I. Install piping free of sags and bends.

J. Install fittings for changes in direction and branch connections.

K. Verify final equipment locations for roughing-in.

L. Comply with requirements in Sections specifying gas-fired appliances and equipment for

roughing-in requirements.

M. Drips and Sediment Traps: Install drips at points where condensate may collect, including

service-meter outlets. Locate where accessible to permit cleaning and emptying. Do not install

where condensate is subject to freezing.

1. Construct drips and sediment traps using tee fitting with bottom outlet plugged or capped.

Use nipple a minimum length of 3 pipe diameters, but not less than 3 inches long and

same size as connected pipe. Install with space below bottom of drip to remove plug or

cap.

N. Extend relief vent connections for service regulators, line regulators, and overpressure

protection devices to outdoors and terminate with weatherproof vent cap.

O. Conceal pipe installations in walls, pipe spaces, utility spaces, above ceilings, below grade or

floors, and in floor channels unless indicated to be exposed to view.

P. Concealed Location Installations: Except as specified below, install concealed natural-gas

piping and piping installed under the building in containment conduit constructed of steel pipe

Page 33: VIRGINIA TECH - apps.vpfin.vt.edu

Dewberry Engineers Inc. Fuel Gas Piping Advanced Design and Construction Facility (0336) 22 14 16 - 12 DEI# 50095905

with welded joints as described in Part 2. Install a vent pipe from containment conduit to

outdoors and terminate with weatherproof vent cap.

1. Above Accessible Ceilings: Natural-gas piping, fittings, valves, and regulators may be

installed in accessible spaces without containment conduit.

2. In Walls or Partitions: Protect tubing installed inside partitions or hollow walls from

physical damage using steel striker barriers at rigid supports.

a. Exception: Tubing passing through partitions or walls does not require striker

barriers.

3. Prohibited Locations:

a. Do not install natural-gas piping in or through circulating air ducts, clothes or trash

chutes, chimneys or gas vents (flues), ventilating ducts, or dumbwaiter or elevator

shafts.

b. Do not install natural-gas piping in solid walls or partitions.

Q. Use eccentric reducer fittings to make reductions in pipe sizes. Install fittings with level side

down.

R. Connect branch piping from top or side of horizontal piping.

S. Install unions in pipes NPS 2 and smaller, adjacent to each valve, at final connection to each

piece of equipment. Unions are not required at flanged connections.

T. Do not use natural-gas piping as grounding electrode.

U. Install strainer on inlet of each line-pressure regulator and automatic or electrically operated

valve.

V. Install pressure gage upstream and downstream from each line regulator. Pressure gages are

specified in Section 230519 "Meters and Gages for HVAC Piping."

W. Install sleeves for piping penetrations of walls, ceilings, and floors. Comply with requirements

for sleeves specified in Section 230517 "Sleeves and Sleeve Seals for HVAC Piping."

X. Install sleeve seals for piping penetrations of concrete walls and slabs. Comply with

requirements for sleeve seals specified in Section 230517 "Sleeves and Sleeve Seals for HVAC

Piping."

Y. Install escutcheons for piping penetrations of walls, ceilings, and floors. Comply with

requirements for escutcheons specified in Section 230518 "Escutcheons for HVAC Piping."

3.5 SERVICE-METER ASSEMBLY INSTALLATION

A. Install metal shutoff valves upstream from service regulators. Shutoff valves are not required at

second regulators if two regulators are installed in series.

B. Install strainer on inlet of service-pressure regulator and meter set.

Page 34: VIRGINIA TECH - apps.vpfin.vt.edu

Dewberry Engineers Inc. Fuel Gas Piping Advanced Design and Construction Facility (0336) 22 14 16 - 13 DEI# 50095905

C. Install service regulators mounted outside with vent outlet horizontal or facing down. Install

screen in vent outlet if not integral with service regulator.

D. Install metal shutoff valves upstream from service meters. Install dielectric fittings downstream

from service meters.

3.6 VALVE INSTALLATION

A. Install manual gas shutoff valve for each gas appliance ahead of corrugated stainless-steel

tubing, aluminum, or copper connector.

B. Install underground valves with valve boxes.

C. Install regulators and overpressure protection devices with maintenance access space adequate

for servicing and testing.

D. Install earthquake valves aboveground outside buildings according to listing.

E. Install anode for metallic valves in underground PE piping.

3.7 PIPING JOINT CONSTRUCTION

A. Ream ends of pipes and tubes and remove burrs.

B. Remove scale, slag, dirt, and debris from inside and outside of pipe and fittings before

assembly.

C. Threaded Joints:

1. Thread pipe with tapered pipe threads complying with ASME B1.20.1.

2. Cut threads full and clean using sharp dies.

3. Ream threaded pipe ends to remove burrs and restore full inside diameter of pipe.

4. Apply appropriate tape or thread compound to external pipe threads unless dry seal

threading is specified.

5. Damaged Threads: Do not use pipe or pipe fittings with threads that are corroded or

damaged. Do not use pipe sections that have cracked or open welds.

D. Welded Joints:

1. Construct joints according to AWS D10.12/D10.12M, using qualified processes and

welding operators.

2. Bevel plain ends of steel pipe.

3. Patch factory-applied protective coating as recommended by manufacturer at field welds

and where damage to coating occurs during construction.

E. Brazed Joints: Construct joints according to AWS's "Brazing Handbook," "Pipe and Tube"

Chapter.

F. Flanged Joints: Install gasket material, size, type, and thickness appropriate for natural-gas

service. Install gasket concentrically positioned.

Page 35: VIRGINIA TECH - apps.vpfin.vt.edu

Dewberry Engineers Inc. Fuel Gas Piping Advanced Design and Construction Facility (0336) 22 14 16 - 14 DEI# 50095905

G. Flared Joints: Cut tubing with roll cutting tool. Flare tube end with tool to result in flare

dimensions complying with SAE J513. Tighten finger tight, then use wrench. Do not

overtighten.

H. PE Piping Heat-Fusion Joints: Clean and dry joining surfaces by wiping with clean cloth or

paper towels. Join according to ASTM D 2657.

1. Plain-End Pipe and Fittings: Use butt fusion.

2. Plain-End Pipe and Socket Fittings: Use socket fusion.

3.8 HANGER AND SUPPORT INSTALLATION

A. Install seismic restraints on piping. Comply with requirements for seismic-restraint devices

specified in Section 230548 "Vibration and Seismic Controls for HVAC."

B. Comply with requirements for pipe hangers and supports specified in Section 230529 "Hangers

and Supports for HVAC Piping and Equipment."

C. Install hangers for horizontal steel piping with the following maximum spacing and minimum

rod sizes:

1. NPS 1 and Smaller: Maximum span, 96 inches; minimum rod size, 3/8 inch.

2. NPS 1-1/4: Maximum span, 108 inches; minimum rod size, 3/8 inch.

3. NPS 1-1/2 and NPS 2: Maximum span, 108 inches; minimum rod size, 3/8 inch.

4. NPS 2-1/2 to NPS 3-1/2: Maximum span, 10 feet; minimum rod size, 1/2 inch.

5. NPS 4 and Larger: Maximum span, 10 feet; minimum rod size, 5/8 inch.

D. Install hangers for horizontal drawn-temper copper tubing with the following maximum spacing

and minimum rod sizes:

1. NPS 3/8: Maximum span, 48 inches; minimum rod size, 3/8 inch.

2. NPS 1/2 and NPS 5/8: Maximum span, 72 inches; minimum rod size, 3/8 inch.

3. NPS 3/4 and NPS 7/8: Maximum span, 84 inches; minimum rod size, 3/8 inch.

4. NPS 1: Maximum span, 96 inches; minimum rod size, 3/8 inch.

E. Install hangers for horizontal, corrugated stainless-steel tubing with the following maximum

spacing and minimum rod sizes:

1. NPS 3/8: Maximum span, 48 inches; minimum rod size, 3/8 inch.

2. NPS 1/2: Maximum span, 72 inches; minimum rod size, 3/8 inch.

3. NPS 3/4 and Larger: Maximum span, 96 inches; minimum rod size, 3/8 inch.

3.9 CONNECTIONS

A. Install natural-gas piping electrically continuous, and bonded to gas appliance equipment

grounding conductor of the circuit powering the appliance according to NFPA 70.

B. Install piping adjacent to appliances to allow service and maintenance of appliances.

Page 36: VIRGINIA TECH - apps.vpfin.vt.edu

Dewberry Engineers Inc. Fuel Gas Piping Advanced Design and Construction Facility (0336) 22 14 16 - 15 DEI# 50095905

C. Connect piping to appliances using manual gas shutoff valves and unions. Install valve within

72 inches of each gas-fired appliance and equipment. Install union between valve and

appliances or equipment.

D. Sediment Traps: Install tee fitting with capped nipple in bottom to form drip, as close as

practical to inlet of each appliance.

3.10 LABELING AND IDENTIFYING

A. Comply with requirements in Section 230553 "Identification for HVAC Piping and Equipment"

for piping and valve identification.

B. Install detectable warning tape directly above gas piping, 12 inches below finished grade,

except 6 inches below subgrade under pavements and slabs.

3.11 PAINTING

A. Comply with requirements in Section 099113 "Exterior Painting" and Section 099123 "Interior

Painting" for painting interior and exterior natural-gas piping.

B. Paint exposed, exterior metal piping, valves, service regulators, service meters and meter bars,

earthquake valves, and piping specialties, except components, with factory-applied paint or

protective coating.

1. Alkyd System: MPI EXT 5.1D.

a. Prime Coat: Alkyd anticorrosive metal primer.

b. Intermediate Coat: Exterior alkyd enamel matching topcoat.

c. Topcoat: Exterior alkyd enamel semi-gloss.

d. Color: Gray.

C. Damage and Touchup: Repair marred and damaged factory-applied finishes with materials and

by procedures to match original factory finish.

3.12 CONCRETE BASES

A. Concrete Bases: Anchor equipment to concrete base.

1. Construct concrete bases of dimensions indicated, but not less than 4 inches larger in both

directions than supported unit.

2. Install dowel rods to connect concrete base to concrete floor. Unless otherwise indicated,

install dowel rods on 18-inch centers around the full perimeter of the base.

3. Install epoxy-coated anchor bolts for supported equipment that extend through concrete

base, and anchor into structural concrete floor.

4. Place and secure anchorage devices. Use supported equipment manufacturer's setting

drawings, templates, diagrams, instructions, and directions furnished with items to be

embedded.

5. Install anchor bolts to elevations required for proper attachment to supported equipment.

Page 37: VIRGINIA TECH - apps.vpfin.vt.edu

Dewberry Engineers Inc. Fuel Gas Piping Advanced Design and Construction Facility (0336) 22 14 16 - 16 DEI# 50095905

6. Use 3000-psig, 28-day, compressive-strength concrete and reinforcement as specified in

Section 033000 "Cast-in-Place Concrete."

3.13 FIELD QUALITY CONTROL

A. Perform tests and inspections.

B. Tests and Inspections:

1. Test, inspect, and purge natural gas according to the International Fuel Gas Code and

authorities having jurisdiction.

C. Natural-gas piping will be considered defective if it does not pass tests and inspections.

D. Prepare test and inspection reports.

3.14 DEMONSTRATION

A. Engage a factory-authorized service representative to train Owner's maintenance personnel to

adjust, operate, and maintain earthquake valves.

3.15 OUTDOOR PIPING SCHEDULE

A. Underground natural-gas piping shall be one of the following:

1. PE pipe and fittings joined by heat fusion, or mechanical couplings; service-line risers

with tracer wire terminated in an accessible location.

2. Steel pipe with wrought-steel fittings and welded joints, or mechanical couplings. Coat

pipe and fittings with protective coating for steel piping.

3. Annealed temper copper tube with wrought-copper fittings and brazed joints. Coat pipe

and fittings with protective coating for copper tubing.

B. Aboveground natural-gas piping shall be one of the following:

1. Steel pipe with malleable-iron fittings and threaded joints.

2. Steel pipe with wrought-steel fittings and welded joints.

C. Containment Conduit: Steel pipe with wrought-steel fittings and welded joints. Coat pipe and

fittings with protective coating for steel piping.

3.16 INDOOR PIPING SCHEDULE FOR SYSTEM PRESSURES LESS THAN 0.5 PSIG

A. Aboveground, branch piping NPS 1 and smaller shall be one of the following:

1. Annealed-temper, copper tube with wrought-copper fittings and brazed joints.

2. Aluminum tube with flared fittings and joints.

3. Steel pipe with malleable-iron fittings and threaded joints.

B. Aboveground, distribution piping shall be one of the following:

Page 38: VIRGINIA TECH - apps.vpfin.vt.edu

Dewberry Engineers Inc. Fuel Gas Piping Advanced Design and Construction Facility (0336) 22 14 16 - 17 DEI# 50095905

1. Steel pipe with malleable-iron fittings and threaded joints.

2. Steel pipe with wrought-steel fittings and welded joints.

3. Drawn-temper copper tube with wrought-copper fittings and brazed joints.

3.17 ABOVEGROUND MANUAL GAS SHUTOFF VALVE SCHEDULE

A. Valves for pipe sizes NPS 2 and smaller at service meter shall be one of the following:

1. One-piece, bronze ball valve with bronze trim.

2. Two-piece, full-port, bronze ball valves with bronze trim.

3. Bronze plug valve.

B. Valves for pipe sizes NPS 2-1/2 and larger at service meter shall be one of the following:

1. Two-piece, full-port, bronze ball valves with bronze trim.

2. Bronze plug valve.

3. Cast-iron, non-lubricated plug valve.

C. Distribution piping valves for pipe sizes NPS 2 and smaller shall be one of the following:

1. One-piece, bronze ball valve with bronze trim.

2. Two-piece, full-port, bronze ball valves with bronze trim.

3. Bronze plug valve.

D. Distribution piping valves for pipe sizes NPS 2-1/2 and larger shall be one of the following:

1. Two-piece, full-port, bronze ball valves with bronze trim.

2. Bronze plug valve.

3. Cast-iron, lubricated plug valve.

E. Valves in branch piping for single appliance shall be one of the following:

1. One-piece, bronze ball valve with bronze trim.

2. Two-piece, full-port, bronze ball valves with bronze trim.

3. Bronze plug valve.

END OF SECTION 231123

Page 39: VIRGINIA TECH - apps.vpfin.vt.edu

CO-9

Page 1 of 4

VIRGINIA POLYTECHNIC INSTITUTE and STATE UNIVERSITY

(VIRGINIA TECH)

CONTRACT BETWEEN OWNER AND CONTRACTOR

This Contract, dated this 20th day of July, 2018 between

_______________________________________________________________________ (“Owner”) and

_______________________________________________________________________ (“Contractor”),

is binding among and between these parties as of the date of the Owner’s signature.

RECITALS

1. The legal address for the Owner and for the Contractor and the addresses for delivery of Notices and

other project documents are as follows:

Owner:Virginia Polytechnic Institute and State University

Attn: Larry Doyle

Address: 330 Sterrett Dr, Suite 201

City, State, Zip: Blacksburg, VA 24061

Telephone: 540-418-5525 FAX:

Contractor:

Attn:

Address:

City, State, Zip:

Telephone: FAX:

Contractor’s Virginia License #:

FEIN/SSN:

SCC ID #:

2. The Project is identified as:

Project Title: Advanced Design and Construction Facility (0336)

Project Code: G1213-18-294-761

General Project Description: Construction of a pre-engineered metal storage/workshop building and

associated utilities at Virginia Polytechnic Institute and State University (Virginia Tech) located in Blacksburg,

VA.

Page 40: VIRGINIA TECH - apps.vpfin.vt.edu

CO-9

Page 2 of 4

The Project Code (PC#) indicated above is required to be shown for identification purposes on all project-related material and

documents including but not limited to, Notices, Change Orders, Submittals, Requests For Information, Requests For Quotes,

Field Orders, minutes of meetings, correspondence, Schedule of Values and Certificate For Payment (Form CO-12), test

reports, and related materials.

3. After competitive sealed bidding pursuant to the Virginia Public Procurement Act, Contractor is

awarded this Contract to perform the Work described by the Contract Documents for the above-

described project (“the Project”).

THEREFORE, in consideration of the Recitals set forth above, and good and valuable consideration as

set forth below, the parties agree as follows:

1. STATEMENT OF WORK: The Contractor shall furnish all labor, equipment, and materials and

perform all Work for the Project in strict accordance with the Contract Documents.

2. CONTRACT DOCUMENTS: This Contract shall consist of the following:

- this Contract Between Owner and Contractor (Form CO-9);

- the Bid Form submitted by the Contractor;

- Post Bid Modification(s), if any, dated _______________________;

- the General Conditions of the Construction Contract (Form CO-7),

referred to as the “General Conditions”;

- the Supplemental General Conditions, if any;

- the Special Conditions attached to the Owner’s Invitation for Bids;

- the Owner’s Project Plans and Specifications dated _April 6, 2018 ;

All of these documents are incorporated herein by reference.

3. TIME FOR COMPLETION: The Work shall be commenced on a date to be specified in a written

order of the Owner and shall be Substantially Completed within ____ calendar days or not later than the

Contract Completion Date which is _________________. The Work shall be finally completed within

30 days after the date of Substantial Completion of the Work.

4. COMPENSATION TO BE PAID TO THE CONTRACTOR: The Owner agrees to pay and the

Contractor agrees to accept as just and adequate compensation for the performance of the Work in

accordance with the Contract Documents the sum of

_____________________________________________dollars ($__________________).

5. PAYMENTS: The procedures for establishing a Schedule of Values for the Work, for requesting

monthly progress payments for Work in place, and for requesting payments for properly stored materials

are stated in the General Conditions. Unless otherwise provided under the Contract Documents, interest

on payments due the Contractor shall accrue at the rate of one percent per month. §2.2-4354 of the Code

of Virginia.

Page 41: VIRGINIA TECH - apps.vpfin.vt.edu

CO-9

Page 3 of 4

eVA Vendor Registration: The bidder or offeror shall be a registered vendor in eVA. See the attached

eVA Vendor Registration Requirements.

GCPay: Contract payments shall be made through GCPay. Go to www.dgs.virginia.gov/deb to see the fee

schedule and the instructions on how to process pay applications.

6. CONTRACTUAL CLAIMS: Any contractual claims shall be submitted in accordance with the

contractual dispute procedures set forth in Section 47 of the General Conditions and the supplemental

instructions or procedures of the contracting State Agency, if any, attached to this Contract.

7. NON-DISCRIMINATION: § 2.2-4311 of the Code of Virginia applies to this contract. See Section

4 of the General Conditions.

8. AUTHORIZATION TO TRANSACT BUSINESS: The Contractor certifies that, if it is organized

as a stock or nonstock corporation, limited liability company, business trust, or limited partnership or

registered as a registered limited liability partnership, it is authorized to transact business in the

Commonwealth as a domestic or foreign business entity if so required by Title 13.1 or Title 50 of the

Code of Virginia, or as otherwise required by law, and shall not allow its existence to lapse or its

certificate of authority or registration to transact business in the Commonwealth, if so required under

Title 13.1 or Title 50, to be revoked or cancelled at any time during the term of the Contract. The

Contractor understands and agrees that the Owner may void this Contract if the Contractor fails to

comply with these provisions.

9. DEBARMENT AND ENJOINMENT: By signing contract, the undersigned certifies that this

Contractor or any officer, director, partner or owner is not currently barred from bidding on contracts by

any Agency of the Commonwealth of Virginia, or any public body or agency of another state, or any

agency of the federal government, nor is this Contractor a subsidiary or affiliate of any firm/corporation

that is currently barred from bidding on contracts by any of the same.

10. “ALL RISK” BUILDER’S RISK INSURANCE: As this project is a modification to an existing

building, in accordance with Section 12(b)- Owner Controlled During Construction of the General

Conditions, the requirements of Section 12(a)- Contractor Controlled During Construction of the

General Conditions do not apply.

IN WITNESS WHEREOF, the parties hereto on the day and year written below have executed this

agreement in three (3) counterparts, each of which shall, without proof or accountancy for the other

counterparts, be deemed on original thereof.

Page 42: VIRGINIA TECH - apps.vpfin.vt.edu

CO-9

Page 4 of 4

For the CONTRACTOR: For the OWNER:

By: _______________________________ By: _______________________________ (signature in ink) (date) (signature in ink) (date)

_______________________________ Sherwood G. Wilson (typed name) (typed name)

_______________________________ Vice President for Operations (typed title) (typed title)

Attest: Attest:

_______________________________ _______________________________

(signature in ink) (date) (signature in ink) (date)

Attachments:

- Bid Form Submitted by the Contractor

- Post Bid Modification, if any

Page 43: VIRGINIA TECH - apps.vpfin.vt.edu

Standard Bid Form Format Page 1 of 4

BID FORM

DATE: July 20, 2018

PROJECT: Advanced Design and Construction

Facility (0336)

VT Project Number: G1213-18-294-761

IFB #: R0057116

To: Virginia Polytechnic Institute and State University (Virginia Tech)

330 Sterrett Drive, Suite 201

Blacksburg, Virginia 24061. Attention: Larry Doyle

In compliance with and subject to your Invitation for Bids and the documents therein specified, all of

which are incorporated herein by reference, the undersigned bidder proposes to furnish all labor,

equipment, and materials and perform all work necessary for construction of this project, in accordance

with the Plans and Specifications dated April 6, 2018, and the Addenda noted below, as prepared by

Dewberry Engineers Inc. in Charlotte, NC for the consideration of the following amount:

BASE BID (including the following parts but excluding work in Additive Bid Items):

PART A.

Lump sum price for Advanced Design and Construction Facility (0336), in accordance with

the Plans and Specifications:

PART A = ________________________________________ Dollars ($ ).

PART B.

Lump sum price for (2) 14’ diameter suspended fans and associated electrical breakers,

circuits, and raceways :

PART B = ________________________________________ Dollars ($ ).

TOTAL BASE BID AMOUNT (Sum of PARTs A and B) IS:

_______________________________________________________ DOLLARS ($ )

ADDITIVE BID ITEM 1: Add (1) 16’x16’ coiling door along the front of the building for a

total of (3) coiling doors.

____________________________________________ Dollars ($ ).

Page 44: VIRGINIA TECH - apps.vpfin.vt.edu

Standard Bid Form Format Page 2 of 4

ADDITIVE BID ITEM 2: Add steel crane runway beams on both sides of the building for (1)

5-ton crane. Add electrical breakers in the electrical panel for the (1) 5-ton crane. Electrical

circuits and raceways from the panel to the crane are not part of this project.

____________________________________________ Dollars ($ ).

ADDITIVE BID ITEM 3: Add HVAC for the full building and associated electrical work and

gas piping. Remove the (2) suspended fans included in the Base Bid Par B and associated

electrical work. Remove wall ventilation louvers, fans, and associated electrical work. Remove

rasiant heater and associated gas piping.

____________________________________________ Dollars ($ ).

The Contractor shall also provide an achievable Construction Schedule based on the critical path

method concurrently with their bid. The schedule which is submitted shall be followed by the

contractor, no exceptions.

Contract award will be based on the TOTAL BASE BID AMOUNT shown above (including any

properly submitted bid modifications) plus such successive Additive Bid Items as the Owner in its

discretion decides to award in the manner set forth in Paragraph 12 of the Instructions to Bidders.

The bidder has relied upon the following public historical climatological records:

National Weather Service for Blacksburg, VA.

The undersigned understands that time is of the essence and agrees that the date for Substantial

Completion of the entire project shall be on or before March 5, 2019 based on a Notice authorizing

Work to proceed on or before July 1, 2018, and Final Completion shall be achieved within 30

consecutive calendar days after the date of Substantial Completion as determined by the A/E. The

undersigned further understands that the Notice to Proceed will authorize all planning,

prefabrication, material procurement, and any other preparatory efforts but will not permit

renovation work to commence within the Advanced Design and Construction Facility before October

5, 2018.

If notice of acceptance of this bid is given to the undersigned within 60 days after the date of

opening of bids, or any time thereafter before this bid is withdrawn, the undersigned will execute and

deliver a contract in the prescribed form (Commonwealth of Virginia Contract Between Owner and

Contractor, Form CO-9) within 10 days after the contract has been presented to him for signature.

Immigration Reform and Control Act of 1986: The undersigned certifies that it does not and shall not

during the performance of the Contract for this project violate the provisions of the Federal

Immigration Reform and Control Act of 1986, which prohibits employment of illegal aliens, or

knowingly employ an unauthorized alien as defined in the Federal Immigration Reform and Control

Act of 1986.

DISQUALIFICATION OF CONTRACTORS: By signing this bid or proposal, the undersigned

certifies that this Bidder or any officer, director, partner or owner is not currently barred from

bidding on contracts by any Agency of the Commonwealth of Virginia, or any public body or agency

of another state, or any agency of the federal government, nor is this Bidder a subsidiary or affiliate

of any firm/corporation that is currently barred from bidding on contracts by any of the same. We

have attached an explanation of any previous disbarment(s) and copies of notice(s) of

reinstatement(s).

Page 45: VIRGINIA TECH - apps.vpfin.vt.edu

Standard Bid Form Format Page 3 of 4

Either the undersigned or one of the following individuals, if any, is authorized to modify this bid

prior to the deadline for receipt of bids by writing the modification and signing his name on the face

of the bid, on the envelope in which it is enclosed, on a separate document, or on a document which

is telefaxed to the Owner:

_________________________________________________________

_________________________________________________________

_____________________________________________________

I certify that the firm name given below is the true and complete name of the bidder and that the bidder

is legally qualified and licensed by the Virginia Department of Professional and Occupational

Regulation, Board for Contractors, to perform all Work included in the scope of the Contract.

Virginia License No.: ______________ Bidder: ______________________________ (Name of Firm)

Contractor Class: ________________ By:___________________________________ (Signature)

Specialty: _______________________ Valid until: ______________________

FEIN/SSN: _____________________ Title: _______________________________

If General Partnership (List Partners' Names)

_________________________________

_________________________________

_________________________________

_________________________________

Business Address:

____________________________________

____________________________________

____________________________________

____________________________________

Telephone # ________________________

FAX # _______________________________

If Corporation, affix Corporate Seal &

list State of Incorporation

State: _____________________________

(Affix Seal)

Page 46: VIRGINIA TECH - apps.vpfin.vt.edu

Standard Bid Form Format Page 4 of 4

Virginia State Corporation Commission ID No.: _______________; or

If Contractor is a foreign business entity not required to be authorized to transact business in the

Commonwealth under Titles 13.1 or 50 of the Code of Virginia, or as otherwise required by law, please

provide an explanation as to why such entity is not required to be so authorized: ____________________

_____________________________________________________________________________________

____________________________________________________________________________________.