viNGN CCI Build Update
description
Transcript of viNGN CCI Build Update
viNGN CCI Build UpdateBroadband Business and Technology Committee
MeetingOctober 7, 2013
Agenda1. Introductions2. Fiber cable deployment progress3. FAP construction progress and
completion schedule4. Connecting to CAI’s5. Undersea cable deployment
progress
STX02DROPS: 100%CAI: 2/27
STX03DROPS: 100%CAI: 0/13
STX04DROPS: 0%CAI: 0/4
STX05DROPS: 0%CAI: 0/11
STX06DROPS: 50%CAI: 0/6
STX16DROPS: 0%CAI: 0/7
STX15DROPS: 76%CAI: 0/17
St. Croix (West)
Backbone Fiber Installed
Backbone Innerduct Placed
STX12DROPS: 0%CAI: 0/1
STX09DROPS: 57%CAI: 0/14
STX13DROPS: 0%CAI: 0/7
STX17DROPS: 0%CAI: 0/22
STX07DROPS: 0%CAI: 0/4
St. Croix (East)
Backbone Fiber Installed
Backbone Innerduct Placed
STT01DROPS: 44%CAI: 0/17
STT02DROPS: 88%CAI: 0/8
STT05DROPS: 0%CAI: 0/7
STT16DROPS: 70%CAI: 0/30
St. Thomas (West)
Backbone Fiber Installed
Backbone Innerduct Placed
STT14DROPS: 95%CAI: 0/43 STT12
DROPS: 84%CAI: 0/19
STT13DROPS: 0%CAI: 0/6
STT10DROPS: 67%CAI: 0/3
STT09DROPS: 38%CAI: 0/8
St. Thomas (East)
Backbone Fiber Installed
Backbone Innerduct Placed
STT11
STT11DROPS: 88%CAI: 0/17
STJ01DROPS: 0%CAI: 0/20
STJ02DROPS: 0%CAI: 0/11
St. John
Backbone Fiber Installed
Backbone Innerduct Placed
Splicing the fiber cables into a complete network
Fusion splicing fibersand training a local tech
Completed spliced fibersin tray
Splice tray enclosure for pole mounting
Fiber/Facility Access Point (FAP) STT10 (Nadir)
Cisco ME 3800 Aggregation Switch (1)
FAP #Local Name Contractor
% Building complete Gen/Power HVAC
Racking & Duct DC Power
% Completed Drops
BB Fiber Terminated Notes
STX02 Frederiksted Benton/JBC 100 100
STX03 Boy & Girls Club Benton/JBC 100↑ 10/09 10/09 100 .
STX04 UVI Benton/JBC 100↑ 10/11 10/14 10/15 0
STX05 Villa La Reine AT 100 10/19 10/23 10/24 0
STX06 Woodson School AT 100 10/23 10/24 10/24 50
STX07 Dept Education AT 90 ↑ 10/28 10/27 10/27 0
Working on epoxy flooring and elect trim
STX09 Gov’t House Benton/JBC n/a 75 57
STX12 Cotton Valley Benton/JBC 100 ↑ 10/13 10/18 10/18 0
STX13 DPW Benton/JBC 100 0
STX15 Juan Luis Hospital Eleven 10 11/02 11/23 11/23 76
STX16 Roebuck – Ind. Park Benton/JBC 100 ↑ 10/07 10/12 10/12
STX17 WAPA Richmond AT 15 11/07 11/26 11/26
STT01 Vitema Balbo 44
STT02 UVI Benton/JBC65↑
10/29 11/11 11/11 88
STT03 Bonne Esperance CancelledCancel
STT05 Estate Dorothea Benton/JBC5 hold
STT09 Eudora Keane Benton/JBC100 ↑
09/29 10/30 10/30 38
STT10 Nadir Benton/JBC 100 ↑ 10/04 11/02 11/02 67
STT11 Ft. Mylner Rumina 65 ↑ 11/12 11/14 11/14 88
STT12 Schneider Hospital Benton/JBC 100 ↑ 10/11 11/05 11/05 84
STT13 WICO – Havensight Benton/JBC 15 ↑
STT14 Boy Scouts Apex
Pending reassignment
100
STT16 Nisky Center Rumina 75 ↑ 10/24 11/09 11/09 70
STJ01 Cruz Bay Custom 100 ↑ 10/29 11/17 11/17 0
STJ02 Myra Keating Custom 100 ↑ 11/03 11/20 11/20 0
Super FAP STX02 (Frederiksted):
Cisco ASR 9006Core Router (1)
Cisco ME 3800Aggregation Switch (2)
Community Anchor Institutions• Schools……………………... 82• Libraries……………………. 7• Healthcare Providers….. 19• Public Safety……………… 42• Colleges……………………. 4• Government Offices…… 124• Public Broadcast Sys…. 2• Community Centers…… 37 Total 316
viNGN is bringing a 4-fiber cable and interface to each CAI at no cost to them and which is capable of delivering at least 1 gigabit service through an ISP of their choosing!
Athalie McFarlane Petersen Public Library-Frederiksted
Aerial Attachment Building Entry Point
Patch PanelCisco ME 3400Premise Aggregation Switch
…and 100 megabit+service becomes a reality in the USVI!
CAI Connection Schedule
Beach Manhole Installations
Summary and Conclusions
• Construction is proceeding on all aspects of the network.
• As CAI’s are connected and their segment of the network is lit, gigabit service may begin.
• Completion of the network build is expected by year end 2013.