VILLAGE OF BEAR LAKE MANISTEE COUNTY, MICHIGAN USDA/RD Preliminary Engineering Report Water System Improvements March, 2015 Project No. 821870

Transcript of VILLAGE OF BEAR LAKE - WordPress.com Planning Area The project planning area is the current water...

VILLAGE OF BEAR LAKE MANISTEE COUNTY, MICHIGAN

USDA/RD

Preliminary Engineering Report Water System Improvements

March, 2015

Project No. 821870

TABLE OF CONTENTS

PAGES

PROJECT PLANNING AREA ................................................................................................................ 1

EXISTING FACILITIES ............................................................................................................................. 1

PURPOSE AND NEED FOR PROJECT ................................................................................................ 1

ALTERNATIVES CONSIDERED ............................................................................................................. 2

SELECTION OF AN ALTERNATIVE & PROPOSED PROJECT (RECOMMENDED ALTERNATIVE) 3

CONCLUSIONS & RECOMMENDATIONS ............................................................................................. 1

APPENDIX

PER Summary Tables ...................................................................................................................... 4

Water Reliability Study, 2013 ............................................................................................................ 29

PROJECT PLANNING AREA

Project Planning Area The project planning area is the current water distribution service area in the Village of Bear Lake. The Village currently serves municipal water to Village residents. The median household income for the Village is $35,625. See attached map of the existing water distribution area (Figure 1). The Village of Bear Lake performed a Water Reliability Study for its water system in 2013. This report is in the appendix and is part of this preliminary engineering report. The report identified a number of old and undersized watermains and recommended a number of distribution improvements throughout the Village. Water supply improvements and the installation of a metering system for Village water customers were also recommended. The 2013 water reliability study was reviewed and accepted by the MDEQ. Environmental Resources Present

An Environmental Report dated 10/17/14 was prepared for the water system improvements described in this Preliminary Engineering Report. The Environmental Report made a finding that there are no adverse environmental impacts anticipated as a result of the proposed water system improvements. Population Trends The projected 20-year water demand for the Village was estimated using the past and estimated current population numbers obtained from the U.S. Census Bureau. The population of Bear Lake has experienced fluctuations since 1960, but is currently down from its peak in 1980. The Manistee County Planning Department predicts a growth rate of 0.37% per year between the years 2010-2020 for Manistee County. This growth rate has been applied to the current population of the Village to predict populations throughout the study period. The table below shows the past and projected populations for the Village.

POPULATION PROJECTIONS

Year Population

1960 323

1970 376 1980 388

1990 339 2000 318

2010 286

2011 287

2015 291

2020 297

2035 314

Community Engagement The Village has published public notices informing the community of the intent to pursue funding for improvements to the Village's water system. The notices encourage public comment within designated times for this project. The Village will consider input from the community while planning for the water system improvements.

U.S. 31

U

.

S

.

3

1

R

A

I

L

R

O

A

D

S

T

.

PLEASANT ST.

PLEASANT ST.

MAIN ST.

MAIN ST.

STUART ST.

MORGAN ST.

HANCOCK ST.

CODY ST.

POTTER RD.

POTTER RD.

U.S

. 31

MA

PLE

S

T.

WIS

E S

T.

LY

NN

S

T.

SM

IT

H S

T.

VIR

GIN

IA

S

T.

EU

CLID

S

T.

GR

OV

E S

T.

RU

SS

ELL S

T.

RU

SS

ELL S

T.

HO

PK

IN

S S

T.

BO

DW

ELL S

T.

TILLS

ON

S

T.

LOCUST ST.

B

E

A

R

L

A

K

E

BE

AR

LA

KE

NORTH

EXISTING WATER MAIN

EXISTING WATER MAIN SIZE

EXISTING FIRE HYDRANT

EXISTING WATER VALVE

EXISTING WELL

LEGEND

VILLAGE LIMITS

EXISITNG 150,000 GALLON STORAGE TANK

CONSTRUCTED: 2011

F&V PROJECT NO.

DESIGN TEAM:

DRAWING INFORMATION:

NOT FOR

CHECK BY:

REVISION:

VIL

LA

GE

O

F B

EA

R L

AK

E

MA

NIS

TE

E C

OU

NT

Y, M

I

WA

TE

R S

YS

TE

M IM

PR

OV

EM

EN

TS

P

RO

JE

CT

FEBRUARY 2015

821870

603 Bay St, First Floor

P: 231.932.8600F: 231.932.8700

Traverse City, MI 49684

KCM

821870 FIGURE 1

EX

IS

TIN

G W

AT

ER

S

YS

TE

M M

AP

FIGURE 1

EXISTING FACILITIES

Existing Facilities The Village of Bear Lake water system consists of two wells designated as Well No. 2 and Well No. 3, a 150,000 gallon ground-level storage tank, approximately 27,500 feet (5 miles) of watermain, hydrants, valves, water services and appurtenances. The water system serves 158 customers, comprised of both residential and commercial users. See attached Water Reliability Study for a detailed description of the system and its current deficiencies.

PURPOSE & NEED FOR PROJECT

Purpose and Need for Project Need for the project was established in the Water System Reliability Study completed in 2013, and the MDEQ Water System Evaluation completed in 2014. The MDEQ evaluation and reliability study identified the following deficiencies/violations:

1. Undersized watermains (distribution reliability): There are several areas in the Village's water distribution system that have small diameter watermains that are not capable of providing reliability, residual pressures during high demands, and recommended minimum fire flows.

2. Aged wells that are unable to meet desired flow capacity: Both of the Village's wells are aging and performance is declining. Well No. 2 exceeds the recommended age for a municipal well (50 years). The capacity of the water wells is adequate for daily demands but lacks the capacity recommended for fire-fighting.

3. There are several aged and inoperable valves and fire hydrants in the distribution system.

4. Well house disinfection equipment is unreliable, the chlorination system in Well House No. 2 was inoperable during the 2014 MDEQ evaluation (this has been repaired in a temporary manner).

5. The Village currently does not have water meters for their water customers and they cannot account for water usage in their billing structure. Water meters are also used to evaluate water loss by allowing a comparison of water pumped vs. water billed. Without meters, the Village cannot evaluate water loss in their system.

The project goals will address the noted deficiencies:

1. Improve distribution system capacity and reliability. 2. Provide adequate source capacity with reliable controls and disinfection systems. 3. Provide customer water meters to allow monitoring of system losses and usage based

billing. The planned improvements will address the water system problems in the following ways:

1. Installing larger diameter watermains in various sections of the Village to improve residual pressures, increase available flows, including fire flows.

2. Replacing the existing wells (Well No. 2 and Well No. 3) with new higher capacity wells. These new wells will improve reliability and will add needed capacity to the water supply system. (The 2013 Water System Reliability Study recommended an additional new well installation. The additional new well has been eliminated from this project scope due to anticipated hydgeological limitations that would make it challenging to install an additional new well in the aquifer beneath the project area.)

3. Installing new well house(s) that will be equipped with new disinfection equipment which will restore the reliability of the water disinfection system.

4. Replacing aged and inoperable valves and fire hydrants. 5. Installing water meters for all Village water customers so water can be billed accurately

and water loss can be evaluated.

ALTERNATIVES CONSIDERED

Alternatives Considered Three alternatives were considered for this proposed project.

1. The first alternative is the "No Action Alternative”. 2. The second alternative is to complete the recommended improvements proposed in the

Water Reliability Study including two new wells, new water meters, and distribution system improvements.

3. A third alternative would be a project with a reduced scope from the recommended improvements; however a reduced scope will not meet the project goals so this alternative will not be explored further.

Table 1 - List of the Alternatives

Alternative Estimated

Costs Beneficial Environmental

Impacts

Potential Adverse Environmental

Impacts

Alt. 1 - No Action Alternative

$0.00 None

Leaking watermains may allow potential for contamination of Village water supply.

Alt. 2 – Distribution and Water Supply Improvements

$4,020,000

• Reduced watermain breaks.

• Maintain a sustainable quality drinking water supply for the Village.

• Provide a metering system that will help the Village to evaluate water loss from their distribution system.

Temporary Disruption of surface vegetation in some areas.

Alt. 3 – Reduced Scope Distribution and Water Supply Improvements

- Does not meet project goals.

Alternative 1: No Action With regard to the No Action alternative, it is not feasible for the Village of Bear Lake to do nothing with regard to their water distribution and water supply system. Optimizing the current facilities is not a feasible alternative since the needs in the system are the replacement of old, under-sized watermain and aged wells. If “no action” was performed, it would leave the Village water system in a continuing state of disrepair and will increase maintenance costs yearly. With this Alternative, repairs are made only as necessary and on an emergency basis only, resulting in expected system failures and significantly increased operating and repair costs. Alternative 2: Complete Water Distribution and Water Supply System Improvements This alternative consists of replacement of existing wells with new higher capacity wells, replacement of aged and undersized watermains, replacement of aged or inoperable fire

hydrants and valves, and the installation of water meters for Village water customers. This alternative will address the major needs of the Village's water system and will result in higher flows and additional capacity for daily demands and fire fighting, and will develop a meter system for water usage so the Village can bill water accurately and evaluate system water loss. This is a viable alternative. Design Criteria used for the Project The design criteria to be used for the project will comply with RUS design policies (7 CFR 1780.57), the State of Michigan PA 399 and its administrative rules, AWWA guidelines, and the recommended standards for Water Works. Water System Project Map A copy of the water system map showing the recommended improvements can be found at the end of this section (Figure 2). Land Requirements Most of the proposed watermain improvements will be located within the street right-of-ways or property owned by the Village. The new wells may be installed on properties owned by the Village, or the Village may acquire additional property for the installation of the new wells. The well installations may require deed restrictions on adjacent properties to maintain the MDEQ required isolation perimeter around the new wells. Permits will be acquired per the MDEQ regulations for water systems. Construction Problems There are no known construction problems at this time. Soil borings and a geotechnical analysis of the borings will be completed as part of the design process. Project Cost Estimates Project cost estimates for each alternative are as follows: Alternative No. 1 - No Action: Total Project Cost $ 0 Alternative No. 2 - Recommended Water System Improvements Construction Costs $2,983,100 Project Contingencies $ 299,300 Design & Construction Engineering $ 594,100 Administrative and Legal Expenses $ 43,500 Existing Water System Debt Payment $ 40,000 Land acquisition $ 60,000

Total Project Cost $4,020,000

Advantages/Disadvantages

Alternative 2 meets the Village’s short and long term objectives by increasing system reliability by replacing aged watermains, valves, and fire hydrants which will reduce potential for leaks and watermain breaks; replacing aged wells and increasing system capacity; and installing a water customer metering system that will promote accurate billing and allow the Village to track water loss. Alternative 2 will cause the Village to incur costs to perform improvements to their water system.

SELECTION OF AN ALTERNATIVE

PROPOSED PROJECT

(RECOMMENDED ALTERNATIVE)

Selection of an Alternative The Village of Bear Lake identified water system needs from the 2013 Water System Reliability Study. Two alternatives were considered for Bear Lake: No action, and water supply and distribution system improvements . Alternative 2 - water distribution and water supply improvements addresses the improvements needed to maintain the reliability of the Village's water system. Proposed Project Design The proposed project will consist of replacement of existing old and undersized watermain throughout the Village, replacement of aged and inoperable fire hydrants and valves, the replacement of the Village's existing wells with new higher capacity wells, and the installation of water meters for Village water customers. Installing larger diameter watermains will improve reliability, and increase residual pressures and increase fire flows in the low flow areas and throughout the distribution system. Replacing the two existing wells with two new wells will improve the reliability of the water supply system and increase capacity of the water supply system. Installation of water meters will allow the Village to accurately bill water usage and also monitor water system loss. The locations of these improvements and the estimated costs are as follows: Distribution System Improvements:

Watermain Improvements Length Price/ft Total Price 8" watermain on Russell Street from Main Street to US-31, and US-31 from Russell Street to Virginia Street 2,400 $160.00 $384,000.00 8" watermain on Potter Road from 300' west of Smith Street to US-31, and on US-31 to Maple Street 3,400 $160.00 $544,000.00

8" watermain on Maple Street from Cody Street to Stuart Street 730 $200.00 $146,000.00

8" watermain on Wise Street from Potter Street to US-31 2,050 $200.00 $410,000.00

8" watermain on Stuart Street from Wise Street to US-31 600 $200.00 $120,000.00

8" watermain on Cody Street from Lynn Street to Smith Street 660 $200.00 $132,000.00

8" watermain on Virginia Street from Stuart Street to US-31 1,000 $200.00 $200,000.00

8" watermain on Locust Street and Euclid Street 740 $200.00 $148,000.00

Total Watermain Improvements $2,084,000.00 * $160/ft unit price anticipates that watermain installation will require minimal disturbance of existing pavement. $200/ft unit price anticipate watermain will be installed beneath roadways and will require significant disturbance of existing pavement.

• Replace aged hydrants with new hydrants (approximately 14 ea).

$40,000

• Replace aged valves (approximately 14 ea). $40,000

• Install 158 water meters for all Village water customers, including new meter reading equipment, Village computer and software necessary to complete meter readings and billings.

$213,100

Water Supply System Improvements:

• Replace Well No. 2 with a new well with increased capacity. **

$303,000

• Replace Well No. 3 with a new well with increased capacity. **

$303,000

TOTAL COST OF RECOMMENDED IMPROVEMENTS: $2,983,100

PROJECT CONTINGENCIES: $299,300 DESIGN AND CONSTRUCTION ENGINEERING: $594,100

LEGAL, BOND COUNCIL, AND ADMINISTRATIVE EXPENSES: $43,500 EXISTING WATER SYSTEM DEBT PAYMENT: $40,000

LAND ACQUISITION: $60,000

TOTAL PROJECT COST: $4,020,000

** The planned project scope is to replace both Well 2 and Well 3 with new wells of higher capacity installed through a single new wellhouse. The ability to increase capacity will be dependent on the results of the hydrogeological study that will be compiled as part of the project design. It is anticipated that the existing generator will be adequate to run at least one of the new wells and will be moved and reconnected. If the new wells require larger pump motors, a new generator may be required.

In addition to this proposed project alternative, the Village has considered additional items that fall outside of the currently proposed budget. If funds remain, the Village would like to pursue acquisition of a valve turner and portable generator to aid in completing maintenance tasks, spare meters and spare water system repair parts to establish a baseline stock of commonly used parts, and an initial purchase of disinfection chemicals compatible with the new equipment. Also, it is anticipated MDEQ will request an updated Water System Reliability Study complete with hydraulic model based on the completed improvements. Preparation of that study and development of a hydrant flushing and valve turning plan based on the hydraulic model may be requested as the project winds down.

Proposed Project Schedule

Milestone Date

Rural Development Application Submittal March 2015 Rural Development Application Approved April 2015

Property Acquisition June 2015 Project Design July 2015

Permits September 2015 Advertisement for Bids October 2015

Loan Closing March 2016 Contract Award March 2016

Initiation of Construction April 2016 Substantial Completion October 2016

Final Completion November 2016 Initiation of Operation November 2016

Permit Requirements The permits required for this project include a Soil Erosion and Sedimentation Control permit, Manistee County Building Permit, an Act 399 Water permit, and an MDOT permit.

CONCLUSIONS AND RECOMMENDATIONS

Conclusions and Recommendations The proposed recommended water system improvements are a result of the hydraulic analysis from 2013 Water Reliability Study. The study identified areas with aged and undersized watermains, aged wells with limited capacity, the presence of aged and inoperable fire hydrants and valves, and the absence of a metering system for customer water usage. The proposed improvements will improve flow and reliability of the distribution system, improve reliability and capacity of the water supply system, and provide a water metering system for Village water customers.

Existing Water System Summary(add or delete cells or rows as necessary)

Community Name: Village of Bear Lake

MDEQ Water Supply Number (WSSN): 510

Rated Date of Date of Depth Water

Well Capacity Completion Last Quality

(gpm) Maint.

Well 2 195 1958 2011 127 ft Acceptable

Well 3 313 1977 2011 124 ft Acceptable

Water Demand (MGD) Distribution System:

Material Footage Age

Firm Capacity: 0.281 MGD 4" watermain CI 9,730 78

Avg. Day Demand: 0.061 MGD 6: watermain CI 7,403 Varies

Max Day Demand: 0.186 MGD 8" watermain PVC/DI 8,483 Varies

Avg Monthly Billing N/A* MG 10" watermain DI 1,375 20

Avy Monthly Pumpage 1.87 MG 12" watermain PVC 421 5

*No water customer water meters

Storage

Ground Storage Number Brand

Volume: 150,000 Gal of Hydrants

Construction: Steel - Bolted 32 Various

Const Date: 2011

Last paint: 2011

Low Service Pumps N/A (gpm, ea.) Number of Valves: 62

High Service Pumps N/A (gpm, ea.)

Water Customer Information:

No. of Monthly No. of Users Projected

Existing Usage after Total

Customers (gallons) Project Usage

Residential Dwellings 142 approx. 710000 142 710000

Other Users 16 approx. 350000 16 350000

Totals 158 1060000 158 1060000

Existing Rate Structure: Average Monthly

Billing at Current Rates

Residential Customers: $60/Quarter/Per REU (all customers)

Commercial Customers: $60/Quarter/Per REU

Industrial Customers: $60/Quarter/Per REU $4,240.00

Yearly O & M Cost Before Improvements: $46,662.00 Yearly O & M Cost After: $43,600.00

Operating Budget

For First Full Year After Construction(add or delete rows as necessary)

Community Name: Village of Bear Lake County: Manistee

Address: 12376 Virginia Street

P.O. Box 175Bear Lake, MI 49614

A. Applicant Fiscal Year: From: 2017-Feb To: 2018-Feb

B. Operating Income: From Water Sales or Sewer Rates & Charges: $113,288

Other (e.g. hydrant rentals, etc) $0

Total Operating Income: $113,288

C. Operating Expenses:Wages and Fringes $20,350Utilities - Electric, Phone, Etc. $8,500Repairs and Maintenance $5,000Supplies $250Prof & Contracted Srvcs - licensed operator, tank/well insp., etc. $9,000Equipment Rental $500

Total Operating Expenses: $43,600

D. Net Operating Income: $69,688

E. Non Operating Income:Interest: $0Other: $0

Total Non Operating Income: $0

F. Net Income $69,688

G. Expenditures/TransfersRepair, Replacement & Improvement Fund $12,200Bond Reserve $5,200Payment to USDA Loan $51,933Payment to Other Loans $0

Total Expenditures/Transfers: $69,333

Excess/Deficit over net income: $355

USDA Confidential 7/16/2015 Page 1

Present Worth Analysis & Short Lived Depreciation(add or delete rows or cells as necessary)

Community Name: Village of Bear Lake

Federal Discount Rate for Water Resources Planning (Interest Rate) i = 0.04875

Number of Years, n = 20 years

Alternative 1: No Action

Initial Capital Costs = No Action Initial Capital Costs = $4,020,000

Annual Operations Annual Operations

& Maintenance Costs = $46,662 & Maintenance Costs = $43,600

Future Salvage Value = Future Salvage Value = $1,754,280

Present Worth Present Worth

of 20 years of O & M = $587,725 of 20 years of O & M = $549,158

PW = Annual OM *(1+i)^n-1

i*(1+i)^n

Present Worth Present Worth

of 20 yr Salvage Value = $0 of 20 yr Salvage Value = $677,110

PW =

FSV* 1

(1 + i)^n

Alternate 1 Alternative 2

Total Present Worth = #VALUE! Total Present Worth = $3,892,047

Short Lived Depreciated Assets (items listed, life expectancy, are just examples, use your own data)

Years of Life Number of Replacement Funds to Set

Item Expectancy Units Cost Aside Yearly Note:

Well Pumps 15 2 10000 $1,333 This is not intended to

Well Pump Controls 10 1 5000 $500 include every piece of

Chem Feed Equipment 10 1 3000 $300 equipment in the system.

Well Servicing 5 3 10000 $6,000 It is to itemize the critical

Tank Painting 15 1 60000 $4,000 equipment or maintenance

items that money should

Total $12,133 be set aside for via

rates and charges.

No short lived assets with more than 15

years of life expectancy

Alternative 2: Water Supply and

Distribution Improvements

Bond Schedule Date: 07/16/15

Borrower Name: Village of Bear Lake Type of Bond: Revenue

Interest Rate: 2.125%Yrs Deferred Principle 0Principal: $1,390,000 (round to nearest $1000)Ammort. Factor 0.0374Ammortized Payment: $51,933

1st 2nd Principal Total Year Loan

Year Interest Interest Paid Payment Balance

1,390,0001 14,769 14,769 22,000 51,538 1,368,0002 14,535 14,535 23,000 52,070 1,345,0003 14,291 14,291 23,000 51,581 1,322,0004 14,046 14,046 24,000 52,093 1,298,0005 13,791 13,791 24,000 51,583 1,274,0006 13,536 13,536 25,000 52,073 1,249,0007 13,271 13,271 25,000 51,541 1,224,0008 13,005 13,005 26,000 52,010 1,198,0009 12,729 12,729 26,000 51,458 1,172,000

10 12,453 12,453 27,000 51,905 1,145,00011 12,166 12,166 28,000 52,331 1,117,00012 11,868 11,868 28,000 51,736 1,089,00013 11,571 11,571 29,000 52,141 1,060,00014 11,263 11,263 29,000 51,525 1,031,00015 10,954 10,954 30,000 51,909 1,001,00016 10,636 10,636 31,000 52,271 970,00017 10,306 10,306 31,000 51,613 939,00018 9,977 9,977 32,000 51,954 907,00019 9,637 9,637 33,000 52,274 874,00020 9,286 9,286 33,000 51,573 841,00021 8,936 8,936 34,000 51,871 807,00022 8,574 8,574 35,000 52,149 772,00023 8,203 8,203 36,000 52,405 736,00024 7,820 7,820 36,000 51,640 700,00025 7,438 7,438 37,000 51,875 663,00026 7,044 7,044 38,000 52,089 625,00027 6,641 6,641 39,000 52,281 586,00028 6,226 6,226 39,000 51,453 547,00029 5,812 5,812 40,000 51,624 507,00030 5,387 5,387 41,000 51,774 466,00031 4,951 4,951 42,000 51,903 424,00032 4,505 4,505 43,000 52,010 381,00033 4,048 4,048 44,000 52,096 337,00034 3,581 3,581 45,000 52,161 292,00035 3,103 3,103 46,000 52,205 246,00036 2,614 2,614 47,000 52,228 199,00037 2,114 2,114 48,000 52,229 151,00038 1,604 1,604 49,000 52,209 102,00039 1,084 1,084 50,000 52,168 52,00040 553 553 52,000 53,105 0

VILLAGE OF BEAR LAKE MANISTEE COUNTY, MICHIGAN

Water Reliability Study & General Plan Update

November 2013

Project No. 811320

811320 TOC

TABLE OF CONTENTS

PAGES

I. EXECUTIVE SUMMARY . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-3

II. BACKGROUND AND PURPOSE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4

III. EXISTING WATER SYSTEM . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . 5-8

IV. WATER USE AND FIRE PROTECTION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8-12

V. EVALUATION OF SYSTEM CAPACITY. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13-15

VI. RECOMMENDED IMPROVEMENTS. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16-18

VII. FUNDING SOURCES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 19-20

TABLES:

1. Well Summary

2. Watermain Inventory

3. Water Usage

4. Population Projections

5. Per Capita Water Usage

6. Projected Water Demands

7. ISO Suggested and Recommended Target Fire Flow Values and Durations

8. Available Fire Flow @ 20 PSI for Select Locations

9. Comparison of Calculated Fire Flows from Field Measurements to WaterCAD Fire Flows

10. Comparison of Target Fire Flows to WaterCAD Fire Flows

11. Required Storage Capacity for Fire Fighting

12. Required Storage Capacity for Fire Fighting

13. Comparison of Available Fire Flow to Target Fire Flows After Completion of Recommended Distribution System Improvements

FIGURES:

1. Existing Water System Map

2. Hydrant Flow Test Locations

3. Existing Static Pressure

4. Existing Water System Available Fire Flow with 20 PSI (Historic Max Day Demand)

5. Recommended Improvements

6. Short Term Recommended Improvements Available Fire Flow with 20 PSI (Historic Max Day Demand)

7. Short-Term and Long-Term Recommended Improvements Available Fire Flow with 20 PSI (Historic Max Day Demand)

VILLAGE OF BEAR LAKE – WATER RELIABILITY STUDY PAGE 1

FLEIS & VANDENBRINK ENGINEERING, INC. 811320 BEAR LAKE REPORT W REVISED RD APP COSTS

I. EXECUTIVE SUMMARY

This report reviews the Village of Bear Lake’s water system facilities, capacities, and needs through the year 2032. In addition, it provides a master plan for water system improvements to be implemented as the need arises and funding permits. The system was evaluated in three categories: water supply, water storage, and water distribution. The Village of Bear Lake completed a significant water system improvements project in 2010 and 2011 totaling nearly $1 million dollars that addressed the system's most immediate needs. The project involved a new storage tank, watermain improvements, telemetry upgrade, backup power, and well improvements. In general, the water system was found to have adequate capacity for projected demands but lacks capacity to meet any ISO fire flow classification above the residential classification. It was also found that available flows are limited in the areas of the water system that are served by undersized watermains (4-inch).

A. WATER SUPPLY & TREATMENT The Village is supplied by two wells, designated No. 2 and No. 3. Both wells are active and the lead well position is rotated after each pumping cycle. The firm capacity is defined as the capacity delivered with the largest well out of service; the rated firm capacity for the Village is 195 gpm with Well No. 3 out of service. The firm capacity was lowered from the previous study period value of 220 gpm because the new water tank was installed at a higher elevation than the old tank and the additional system head reduced the flow rate of the existing wells. The MDEQ recommends the firm capacity of any water supply system meet or exceed the maximum day demands placed on the system. The historic maximum day demand (highest maximum day demand in the last 5 years) is 134 gpm, which is 69% of the Village’s firm capacity. The existing firm capacity is adequate to serve existing and future projected maximum day demands. Well inspections completed as part of the 2010 Water System Improvements Project revealed a reduction in capacity of both of the Village's wells apparently due to age, screen condition, and wear. Well No. 2 was pumping air during testing and the water level at Well No. 3 was drawn down below the top of the pump bowls. The existing wells are not in imminent danger of failure, however, it is recommended that the Village begin planning to eventually replace the existing wells.

The Village currently treats their water with chlorine solution for disinfection. The Village had one incident of disinfection equipment failure within the last 2 years that resulted in water quality issues; the disinfection equipment has been repaired and there have been no water quality issues since.

B. WATER STORAGE

The Village has a 150,000 gallon ground-level steel storage tank that supplies water pressure and emergency storage to the Village water customers. The storage tank is located south of Potter Road between Lynn Street and Smith Street as shown in Figure 1. The tank was constructed in 2011. The tank has operated flawlessly since it's construction. Based on the Ten State Standards “Recommended Standards for Water Works”, the storage capacity of a water system should exceed average daily use. The highest historic average day demand (highest in the past 5 years) was 75,227 gallons and the projected 2032 average day demand is 74,000; the existing storage tank has the required capacity to meet the existing and projected future average day demands. Tanks are also sized for fire flow

VILLAGE OF BEAR LAKE – WATER RELIABILITY STUDY PAGE 2

FLEIS & VANDENBRINK ENGINEERING, INC. 811320 BEAR LAKE REPORT W REVISED RD APP COSTS

capability, and based on current total storage and well capacity, the Village has the capacity to meet a residential ISO fire classification, but lacks the capacity to meet any classification above residential (commercial, industrial, institutional). Storage capacity improvements are not recommended to increase system capacity, as it would promote longer detention time for the water in the storage tank which may result in a degradation of water quality. Instead, it is recommended that the Village install a new well(s) to increase system capacity should they desire to meet a higher fire flow classification.

C. WATER DISTRIBUTION

The water distribution system was analyzed for system pressure and available fire flows. The static system pressures were found to range from 38 psi to 85 psi which is within the accepted range. The available fire flows were found to be lower than recommended in a few areas of the distribution system. The areas of low available flows are: US-31 from Virginia Street to Russell Street, and US-31 from Potter Road to Maple Street. Flows in these areas are restricted by undersized watermains. The distribution system is comprised of approximately 35% of 4-inch and smaller watermains, which restrict flows throughout the system. It is recommended that the 4-inch watermain in the system be replaced by 8-inch or larger watermain where fire protection is provided.

In addition to the recommended watermain improvements, many old fire hydrants remain in the system and several are reported by the Village to be inoperable or questionable. It is suspected that many of these old hydrants have 4” leads and several do not have auxiliary valves. These hydrants should be replaced with new hydrant assemblies including auxiliary valves. Distribution system improvements are recommended for the low-flow areas listed above to increase the available flows.

D. RECOMMENDED IMPROVEMENTS This report recommends improvements to the Village’s water system with costs estimated at $2,555,000. These improvements include: Short-term Improvements:

• Replace Well #2 with a new well with a target capacity of 475 gpm. • Replace aged hydrants with new hydrants.

Long-term Improvements: • Install new 8-inch watermain on Russell Street from US-31 to Main Street. • Install new 8-inch watermain on US-31 from Russell Street to Virginia Street. • Install new 8-inch watermain on Potter Road from Smith Street to US-31, on US-31

from Potter Road to Stuart Street, on Stuart Street from US-31 to Maple Street, and on Maple Street from Stuart Street to US-31.

• Replace Well No. 3 with a new well with a target capacity of 475 gpm, and if a higher fire flow classification is desired, install an additional well with a target capacity of 475 gpm.

• Replace the remaining 4-inch watermain throughout the system with minimum 8-inch watermain where fire protection is provided.

• Install water meters for Village water customers.

VILLAGE OF BEAR LAKE – WATER RELIABILITY STUDY PAGE 3

FLEIS & VANDENBRINK ENGINEERING, INC. 811320 BEAR LAKE REPORT W REVISED RD APP COSTS

A detailed list of recommended improvements and estimated costs are included in Section VI of this report. The costs are in year 2012 dollars and should be used for budgeting purposes only.

VILLAGE OF BEAR LAKE – WATER RELIABILITY STUDY PAGE 4

FLEIS & VANDENBRINK ENGINEERING, INC. 811320 BEAR LAKE REPORT W REVISED RD APP COSTS

II. BACKGROUND AND PURPOSE

The Village of Bear Lake is in Manistee County, which is located in northwestern Lower Michigan. Bear Lake has a type 1 (public) water supply and distribution system with two water production wells and a 150,000 gallon ground-level storage tank.

The purpose of this report is to provide the Village with a comprehensive analysis of their water system in order to comply with MDEQ and Act 399. The report evaluates the existing water supply, treatment, storage and distribution, and provides recommendations for improvements to serve the existing and future needs of the Village. This report is intended to be the master plan for guiding the community on the overall future water system capital improvement needs to meet future daily water and fire flow demands.

The study and service area includes the Village of Bear Lake. The service area is located in sections 4 and 5 of Township 23 N, Range 15 W.

The Contingency Plan for the system was last updated in July of 2004.

VILLAGE OF BEAR LAKE – WATER RELIABILITY STUDY PAGE 5

FLEIS & VANDENBRINK ENGINEERING, INC. 811320 BEAR LAKE REPORT W REVISED RD APP COSTS

III. EXISTING WATER SYSTEM A. WATER SUPPLY

1. Wells The Village of Bear Lake’s water supply system currently consists of two wells. The wells are designated as Wells No. 2, and No. 3. The wells rotate lead position after each pumping cycle. Both Wells are located west of Smith St. between the Potter Road and Cody Street intersections. Table 1 summarizes selected data for the wells and pumps.

TABLE 1

WELL SUMMARY

Well Number

Year Drilled

Diameter (inch)

Depth (feet)

Capacity (GPM)

2 1958 8 127 195

3 1977 12 124 313

The capacity of the wells is lower than the previous water system evaluation because the

Village completed a substantial water project in 2010 and 2011 which included a new water tank that was installed at a higher elevation than the old water tank to boost system pressures. The additional system head created by the new water tank slightly reduced the pumping rate of the wells.

Improvements were made to both wells during the 2010-2011 water system improvements project. The control systems for both wells were upgraded and both wells were inspected and cleaned as part of the project. The well cleaning improved the efficiency of both wells, however, during post cleaning performance testing it was noted that Well #2 was pumping air at flow rates over 217gpm. The post cleaning performance testing for Well #3 found that the water level drawdown was at least down to the top of the pump bowls. Well #3 did not pump air during the testing, but the operation of the pump with the water level approaching the pump bowls is not ideal.

The firm capacity is calculated by removing the capacity of the largest pump from the system. The pumping capacity that remains is the firm capacity. The Village of Bear Lake has a rated firm capacity of 195 gpm. The MDEQ recommends that the firm capacity meet or exceed the maximum day demand. The Village’s historic maximum day demand (over the past 5 years) was 134 gpm, which is 69% of the firm capacity. Both of the existing wells have decreased in capacity in recent years. Due to these issues, the Village should consider replacement of the existing wells and adding additional pumping capacity to meet future demands and provide a more reliable water source for the Village water system.

2. Well Houses

Well House No. 2 is located west of Smith Street between the Cody Street and Potter Road intersections. The well house is constructed of CMU block and is in fair condition. The distribution piping in the well house has developed a significant amount of rust.

VILLAGE OF BEAR LAKE – WATER RELIABILITY STUDY PAGE 6

FLEIS & VANDENBRINK ENGINEERING, INC. 811320 BEAR LAKE REPORT W REVISED RD APP COSTS

Well House No. 3 is also located west of Smith Street between the Cody Street and Potter Road intersections. The well house is constructed of CMU block/brick and is in good condition.

3. Water Treatment & Quality

The Village treats their water with chlorine for disinfection. The Village chlorinates by injecting a liquid sodium hypochlorite solution into the distribution piping at the well houses. The Village regularly tests the water quality of its wells and throughout the system per MDEQ requirements. Testing is performed monthly for bacteria, yearly for partial chemical and every 3 years for metals analysis. The Village had to issue a boil water notice in the fall of 2011 due to positive coliform bacteria tests. It was determined that the chlorine injection system had failed and was not injecting chlorine into the distribution system. Since the chlorine injection system was fixed there have been no water quality issues. The metals testing performed in 2008 indicate that the water met State drinking water standards. The Village tests for lead and copper on a triennial basis. Lead/copper levels met the MDEQ action levels in the most recent testing.

4. Wellhead Protection

The Village has an approved Wellhead Protection Program. It is recommended that the Village keep its Wellhead Protection Program updated.

5. Auxiliary Power As part of the 2010 Water System Improvements Project, the Village installed a new

permanent natural gas fueled stand-by generator. The new generator is located next to Well No. 3 Well house and is capable of operating Well No. 3 and Well No. 2 simultaneously.

B. DISTRIBUTION SYSTEM

1. Pipe Condition The Village of Bear Lake’s water distribution system is composed of ductile iron, cast iron, and PVC watermain. Table 2 provides a breakdown of the water distribution system’s watermain inventory by size.

TABLE 2 WATERMAIN INVENTORY

Watermain Size (inches)

Length (feet)

Percent of Total (%)

4 9,730 35%

6 7,403 27%

8 8,483 31%

10 1,375 5%

12 421 2%

Total 27,412 100.00%

VILLAGE OF BEAR LAKE – WATER RELIABILITY STUDY PAGE 7

FLEIS & VANDENBRINK ENGINEERING, INC. 811320 BEAR LAKE REPORT W REVISED RD APP COSTS

2. Low Flow Areas

The watermain improvements and the new tank installed as part of the recent water system improvements project improved system flows substantially. Adequate fire flows can be supplied throughout the majority of the Village, however there are still a few areas with lower than recommended flows. These areas of low flows are areas served by small diameter watermains (4-inch). The low flow areas are:

• The residential area along US-31 between Virginia Street and Russell Street. • The commercial area along US-31 between Potter Road and Maple Street.

Many old fire hydrants exist throughout the water system. Several of these old hydrants were reported to be inoperable or questionable. It is suspected that these old hydrants have 4-inch leads and may not have auxiliary valves. It is recommended that old hydrants throughout the system be replaced with new hydrant assemblies (including 6-inch leads and auxiliary valves).

3. System Pressures

The new storage tank was installed at a higher elevation than the old storage tank to boost system pressures. With the new tank, system pressures range from 38 psi to 85 psi. The pressures are within the acceptable range.

C. WATER STORAGE

1. Specifications

The Village of Bear Lake has a 150,000 gallon ground-level steel storage tank that was constructed in 2011. The water tank provides water storage and pressure for the Village water system. The storage tank has a head range of 29 feet and the Village operates the tank between 15 and 27 feet of head. The 2011 average day demand is 61,320 gpd, the historic maximum average day demand (highest average day in the last 5 years) is 75,227 gpd, and the projected 2032 average day demand is 74,000 gpd. It is recommended that storage capacity meet average day demands. The new storage tank exceeds current and projected average day demands.

2. Tank Maintenance The storage tank was constructed in 2011 and has not been in-service long enough to warrant a maintenance inspection. Maintenance inspections are generally recommended every five years. The Village should plan to have the storage tank inspected around the tank's 5-year anniversary.

D. CONTROLS

1. Telemetry

A new controls system was installed as part of the 2010/2011 water system improvements project. The control system operates by using a pressure transducer to monitor water level at the storage tank. The control system includes alarms for high water, low water, power failure, etc. An autodialer was also installed that calls the system operators in the event of an alarm condition.

VILLAGE OF BEAR LAKE – WATER RELIABILITY STUDY PAGE 8

FLEIS & VANDENBRINK ENGINEERING, INC. 811320 BEAR LAKE REPORT W REVISED RD APP COSTS

E. SYSTEM OPERATIONS

1. Operators The Village of Bear Lake’s water system is classified as S-4/D-4. The Village has two S-4/D-4 certified operators. The MDEQ recommends having a minimum of two people certified to operate the water system; the Village is in compliance with this recommendation. It is recommended that the Village operators maintain their licenses for system operation.

2. Meters

The Village currently does not meter any of their water customers. It is recommended that the Village install water meters for all water customers to provide equitable billing and provide a basis to track system leakage. It is unknown when the master meters at the Village’s wells were last calibrated; master meters should be calibrated at least every ten years. It is recommended that the Village have their master meters calibrated.

3. Maintenance

The Village flushes their water system bi-annually. During flushing, hydrants associated with the Village’s flushing program are operated. It is recommended that the Village develop a program to operate all valves annually and hydrants bi-annually. Detailed records should be kept of valve turning and hydrant flushing.

4. Parts

The Village stocks a variety of spare parts for the major items in the system. Some of the parts include: repair sleeves, sections of pipe for watermain repair, and service fittings. The Village utilizes several reliable local suppliers for any parts not in their inventory.

VILLAGE OF BEAR LAKE – WATER RELIABILITY STUDY PAGE 9

FLEIS & VANDENBRINK ENGINEERING, INC. 811320 BEAR LAKE REPORT W REVISED RD APP COSTS

IV. WATER USE AND FIRE PROTECTION

A. WATER USE

1. Customers The Village of Bear Lake’s water system currently serves 173 customers, consisting of roughly 16% commercial users and 84% residential users. Past water usage data is presented in Table 3 below. Peak hour demands are estimated based on a peaking factor of 4.0 applied to the average day demand.

TABLE 3 WATER USAGE

MONTH 2007 2008 2009 2010 2011

January 1,345,900 2,052,500 1,439,300 1,294,600 1,078,600

February 1,148,700 1,949,000 1,819,200 1,431,300 1,318,800

March 1,250,700 2,123,800 1,944,700 1,851,200 1,195,800

April 1,402,800 1,854,600 1,676,500 2,272,300 1,294,900

May 2,356,300 2,256,700 2,114,400 2,254,400 1,858,500

June 3,371,800 2,546,300 2,530,700 3,020,600 2,528,900

July 3,903,800 2,604,700 2,701,500 2,896,800 3,447,300

August 3,891,800 2,956,000 2,526,100 3,396,600 3,845,600

September 2,521,300 3,960,800 2,404,800 2,077,800 2,030,400

October 2,348,200 1,432,300 1,287,600 1,746,500 1,325,700

November 1,801,400 1,110,300 1,224,400 1,584,900 1,225,800

December 2,115,000 1,449,800 1,238,900 1,067,700 1,231,400

TOTAL 27,457,700 26,296,800 22,908,100 24,894,700 22,381,700

AVG DAY 75,227 72,046 62,762 68,205 61,320

MAX DAY* 192,400 147,600 147,600 167,000 185,600

Max/Ave Day Ratio 2.6 2.0 2.4 2.4 3.0

* Includes high usage days caused by hydrant flushing, tank outages, etc.

1. Historical Water Loss

The Village of Bear Lake does not meter any water customers, so system water loss cannot be estimated. It is recommended that the Village install water meters for all customers so water usage can be tracked accurately and system loss can be estimated.

B. POPULATION PROJECTIONS

The projected 20-year water demand for the Village was estimated using the past and estimated current population numbers obtained from the U.S. Census Bureau. The population of Bear Lake has experienced fluctuations since 1960, but is currently down from it's peak in 1980. The Manistee County Planning Department predicts a growth rate of 0.37% per year between the years 2010-2020 for Manistee County, this growth rate has been applied to the current population of the Village to predict populations throughout the study period. Table 4 below shows the past and projected populations for the Village.

VILLAGE OF BEAR LAKE – WATER RELIABILITY STUDY PAGE 10

FLEIS & VANDENBRINK ENGINEERING, INC. 811320 BEAR LAKE REPORT W REVISED RD APP COSTS

TABLE 4 POPULATION PROJECTIONS

Year Population

1960 323

1970 376

1980 388

1990 339

2000 318

2010 286

2011 287

2017 292

2032 309

C. PROJECTED WATER DEMANDS

The projected water demands for the 20-year study period were calculated using projected population and the current average usage per capita. Table 5 shows the current per capita water usage. Estimated populations are from the U.S. Census Bureau and report projections.

TABLE 5 PER CAPITA WATER USAGE

Year Average Day Demand (gpd)

Estimated Population

Average Day

Demand (gpcd)

2007 75,227 316 238

2008 72,046 310 232

2009 62,762 298 211

2010 68,205 286 238

2011 61,320 287 214

This study assumes the water usage will increase proportionally as population increases. The highest usage rate over the last 5 years (238 gpcd) will be used for analysis. Since 2007, the peaking factor (maximum day demand divided by average day demand) has averaged 2.5. Based on this, a maximum day peaking factor of 2.5 is used in this report to estimate future maximum day demands. Table 6 shows the projected water demands.

VILLAGE OF BEAR LAKE – WATER RELIABILITY STUDY PAGE 11

FLEIS & VANDENBRINK ENGINEERING, INC. 811320 BEAR LAKE REPORT W REVISED RD APP COSTS

TABLE 6 PROJECTED WATER DEMANDS

2017 (5 yr

Estimate)

2032 (20 yr Estimate)

Population 292 309

Average Usage (gpcd) 238 238

Average Day Demand (gallons)

69,500 74,000

Average Day Demand (gpm)

48 51

Peaking Factor 2.5 2.5

Maximum Day Demand (gallons)

174,000 185,000

Maximum Day Demand (gpm)

121 128

Peak Hour Peaking Factor

4.0 4.0

Peak Hour Demand (gpm)

193 206

D. FIRE PROTECTION

1. ISO Rating System The Insurance Services Office (ISO) establishes suggested fire flow protection standards based on various factors including building construction type, area, height, type of development and density. These factors and others such as fire fighting capabilities, when combined, result in an ISO rating of between 1 and 10, 1 being the best and 10 being the worst. This rating is used by insurance companies to determine appropriate insurance rates for its customers that live within the water supply system. The Village of Bear Lake currently has an ISO rating of 6. The current rating is based on an evaluation received in January of 2009. It is recommended that the Village have an updated ISO report completed that takes into account the recent water system improvements.

2. Recommended Fire Flows

The ISO establishes suggested fire flows at various locations throughout a community during a survey. It is not always cost-effective for a community to build a water system that meets all of the suggested ISO fire flows. In such a situation, the community can choose to adopt target fire flow values. Table 7 below presents the suggested ISO fire flows and recommended target fire flow values. These recommended target fire flows were obtained from tabular values presented in the “Fire Protection Handbook’, the “2006 International Fire Code”, and the AWWA’s Manual of Water Supply Practices – “Distribution System Requirements for Fire Protection”. It will be necessary for the Village to decide as to whether these recommended target fire flows provide the desired level of protection.

VILLAGE OF BEAR LAKE – WATER RELIABILITY STUDY PAGE 12

FLEIS & VANDENBRINK ENGINEERING, INC. 811320 BEAR LAKE REPORT W REVISED RD APP COSTS

TABLE 7 ISO SUGGESTED AND RECOMMENDED TARGET FIRE FLOW

VALUES AND DURATIONS

Classification

ISO Suggested Fire Flows @ 20 psi

Recommended Target Fire Flows @ 20 psi

Duration (Hours)

Residential 1,000-1,500 1,000 2

Commercial 2,500 2,500 2

Industrial 3,000 3,000 3

Institutional 3,500 3,500 3

3. Hydrant Flow Tests

Fleis & VandenBrink Engineering and Village staff performed fire hydrant flow tests at select locations throughout the system (See Figure 2) on May 6, 2009 in order to obtain information used in calibration of the WaterCAD hydraulic computer model. The calibration was applied to the water system prior to the 2010 Water System Improvements. This initial calibrated model was modified to reflect the improvements completed in 2010-2011 and thus remains calibrated to the Village's water system. Table 8 provides the results of the fire hydrant tests. The available fire flow amount at the minimum residual pressure of 20 psi was calculated using the following formula:

AVAILABLE FIRE FLOW @ 20 psi= Hydrant Flow *(Static Pressure – 20)0.54

(Static Pressure – Residual Pressure)0.54

TABLE 8 AVAILABLE FIRE FLOW @ 20 PSI FOR SELECT LOCATIONS (COMPLETED PRIOR TO

2010 WATER SYSTEM IMPROVMENTS PROJECT)

Test Number

Location

Actual Hydrant Flow (gpm)

Static

Pressure (psi)

Residual Pressure (psi)

Calculated Fire Flow @20psi

(gpm)

1 Potter Street at Russell St. int. 500 26.5 21 547

2 Main Street between Smith St. and Russell St.

840 53 33.5 1,116

3 Smith Street between Stuart St. and Main St.

670 48 28 803

4 South Shore Dr. west of US-31 840 69 33 992

5 US-31 between Smith St. and Russell St.

580 60.5 34 729

VILLAGE OF BEAR LAKE – WATER RELIABILITY STUDY PAGE 13

FLEIS & VANDENBRINK ENGINEERING, INC. 811320 BEAR LAKE REPORT W REVISED RD APP COSTS

V. EVALUATION OF SYSTEM CAPACITY

A. HYDRAULIC MODEL ANALYSIS

1. Model Description

In order to evaluate the water distribution system, a computer model was developed to simulate the existing system. The software used was WaterCAD V8i developed by Bentley. The watermain sizes, configuration, friction factors, well pump curves, topographic information, flow demands and storage tank data were input into the model to simulate the existing and proposed water distribution systems. Watermain friction factors were estimated based on values required to achieve model calibration to within ±10% of the calculated available fire flow at 20 psi residual for the test locations. Table 9 presents the comparison of the calculated available fire flow at 20 psi to the values obtained in the calibrated WaterCAD model for the test locations listed.

TABLE 9

COMPARISON OF CALCULATED FIRE FLOWS FROM FIELD MEASUREMENTS TO WATERCAD FIRE FLOWS (COMPLETED PRIOR TO 2010 WATER SYSTEM

IMPROVEMENTS PROJECT)

Test Number Location

Available Fire Flow @ 20 psi

(Calculated) (gpm)

Available Fire Flow @ 20 psi

(WaterCAD) (gpm)

Difference Between

Calculated & WaterCAD

(%)

1 Potter Street at Russell St. intersection 547 597 9%

2 Main Street between Smith St. and Russell St. 1,116 1,221 9%

3 Smith Street between Stuart St. and Main St. 803 869 8%

4 South Shore Dr. west of US-31 992 938 -5%

5 US-31 between Smith St. and Russell St. 729 663 -9%

2. Test Results

As the results of Table 9 show, the difference between the calculated available fire flow at 20 psi from hydrant testing and that predicted by the calibrated WaterCAD model is within a +/- 10% tolerance. Therefore, the model is an accurate approximation of the system.

3. Fire Flow Results

Fire flows were simulated throughout the Village's water system. The simulations were completed under existing firm capacity conditions. The elevated tank water levels were set at average operating depth. MDEQ recommends a minimum of 20 psi residual pressure in the system at all times. This is to ensure that positive water pressure remains in the distribution system for customer use and to ensure safe water quality. Table 10 highlights areas throughout the system that have lower than recommended fire flows.

Figure 4 shows the existing available fire flow, expressed as contours, throughout the Village under the historic maximum day demand (highest in the last 5 years).

VILLAGE OF BEAR LAKE – WATER RELIABILITY STUDY PAGE 14

FLEIS & VANDENBRINK ENGINEERING, INC. 811320 BEAR LAKE REPORT W REVISED RD APP COSTS

TABLE 10 COMPARISON OF TARGET FIRE FLOWS TO WATERCAD FIRE FLOWS

Location Number Location

Recommended Target

Fire Flow @ 20 psi (gpm)

Available Fire Flow @ 20 psi

(WaterCAD) (gpm)

Difference Between Target & Available

(%)

1 US-31 at the Russell Street intersection 1,000 916 -8%

2 US-31 at the Potter Road Intersection 2,500 1,310 -48%

3 US-31 at the Stuart Street Intersection 2,500 1,303 -48%

In order to meet recommended fire flows, undersized watermains should be replaced with larger sized watermains.

B. WATER SUPPLY

The MDEQ recommends that the firm capacity of a community’s water supply be greater than its maximum day demand. Currently, the firm capacity of the Village’s water supply is 195 gpm, the historic maximum day (highest maximum day in the last 5 years) is 134 gpm. The historic maximum day demand is 69% of the firm capacity.

C. WATER STORAGE

The recommended target fire flow for commercial areas is 2,500 gpm for two hours. To provide the required volume of water to combat a fire of this duration, 300,000 gallons of water would be used (2,500gpm times 120 minutes). Table 11 compares the volume of available water using current total well capacity and the existing storage volume for each of the classifications of recommended target fire flows and fire flow durations for the historic maximum day demand.

TABLE 11 REQUIRED STORAGE CAPACITY FOR FIRE FIGHTING

(HISTORIC MAXIMUM DAY DEMAND)

Classification

Desired Fire

Flow @ 20 psi (gpm)

Duration (hr)

Historic Maximum

Day Demand (gpm)

Total Flow

Required (system outflow)

Well Capacity (gpm)

Net System Outflow (gpm)

Total Storage Required (gallons)

Existing Storage (gallons)

Additional Capacity Required (gallons)

Residential 1,000 2 134 1,134 508 626 75,120 150,000 N/A

Commercial 2,500 2 134 2,634 508 2,126 255,120 150,000 105,120

Industrial 3,000 3 134 3,134 508 2,626 472,680 150,000 322,680

Institutional 3,500 3 134 3,634 508 3,126 562,680 150,000 412,680

As the data in Table 11 shows, the Village’s existing storage tank and wells can meet the capacity requirement for a residential fire classification but would require additional capacity to meet a commercial or better fire flow classification. Under existing conditions, an additional 105,120 gallons of system capacity would be required to meet the demand for a commercial classification fire event. If the Village desires to meet commercial fire flows, the Village would need to increase well capacity to meet desired fire flow demands. Additional fire flow capacity could be supplied by additional storage, however, this is not recommended because additional storage may affect water quality. The 150,000 gallon capacity of the existing water tank is approximately 2 times the current average day demand, meaning the

VILLAGE OF BEAR LAKE – WATER RELIABILITY STUDY PAGE 15

FLEIS & VANDENBRINK ENGINEERING, INC. 811320 BEAR LAKE REPORT W REVISED RD APP COSTS

water in the tank “turns-over” every 2 days. Adding storage would increase the detention time of the water in the tank under average demand conditions, which may result in deterioration of water quality and ice concerns in the winter. It is recommended that the Village add capacity to the water system by the adding well capacity. The additional well capacity required to meet a commercial fire flow classification would be approximately 876 gpm (to supply the needed 105,120 gallons over the 2 hour duration).

The historic average day demand is larger than the projected average day demand for 2032. The existing system storage capacities are adequate for 2032 average day demand.

VILLAGE OF BEAR LAKE – WATER RELIABILITY STUDY PAGE 16

FLEIS & VANDENBRINK ENGINEERING, INC. 811320 BEAR LAKE REPORT W REVISED RD APP COSTS

VI. RECOMMENDED IMPROVEMENTS

It has been determined that the Village's water system has areas of low available flows and lacks sufficient capacity to meet a fire flow classification above a residential classification. Distribution system improvements and water system capacity improvements are recommended to address the deficiencies of the water system. Recommended Improvements to Increase System Capacity: In order to improve the water system’s capacity, it is recommended that the Village increase pumping capacity. An additional 900 gpm would add enough capacity to meet a commercial fire flow classification for the current and projected demands of the water system. In the short-term, it is recommended that the Village replace Well No.2 with a new well with a target capacity of 475 gpm. In the long-term, it is recommended that the Village monitor the performance of and be prepared to replace Well No. 3 as the well's age and loss of capacity worsens. Well No. 3 should be replaced with a new well with a target capacity of 475 gpm. Also in the long-term, if the Village desires to add capacity to meet a commercial fire flow classification, it is recommended that an additional well with a target capacity of 475 gpm be installed. Table 12 shows the system capacity with an additional 900 gpm of well capacity. The historic maximum day demand was used for the capacity analysis because the historic maximum day demand is larger than the projected future demands for the study period.

TABLE 12 REQUIRED STORAGE CAPACITY FOR FIRE FIGHTING

(HISTORIC MAXIMUM DAY DEMAND)

Desired Fire Flow @ 20 psi Duration

Maximum Day

Demand

Total Flow Required (system outflow)

Well Flow

(system inflow)

Net System Outflow

Total Storage Required

Existing Storage

Addt’l Storage Required

Classification (gpm) (hr) (gpm) (gpm) (gpm) (gpm) (gallons) (gallons) (gallons)

Residential 1,000 2 134 1,134 1,408 -274 -32,880 150,000 N/A

Commercial 2,500 2 134 2,634 1,408 1,226 147,120 150,000 N/A

Industrial 3,000 3 134 3,134 1,408 1,726 310,680 150,000 160,680

Institutional 3,500 3 134 3,634 1,408 2,226 400,680 150,000 250,680

As you can see in Table 12, with the recommended well improvements, the Village will have the capacity to meet recommended flows for residential and commercial fire classification. Recommended Distribution System Improvements to Increase Available Flows: The distribution system contains a significant amount of 4-inch and smaller watermains that limit available flows in certain areas of the system. The areas found to have low flows were: US-31 between the Smith Street and Russell Street intersections, and US-31 between the Potter Road and Maple Street intersections. Low flows are a problem in areas where fire protection is provided and can pose problems in adequately flushing watermains. Below are recommendations to improve flows in these areas:

VILLAGE OF BEAR LAKE – WATER RELIABILITY STUDY PAGE 17

FLEIS & VANDENBRINK ENGINEERING, INC. 811320 BEAR LAKE REPORT W REVISED RD APP COSTS

US-31 from the Smith Street Intersection to the Russell Street Intersection: The land-use along this section of US-31 is residential and the current available flows cannot supply recommended fire flows for a residential area (1000 gpm). To increase flows in this area, it is recommended that new 8" watermain be installed on Russell Street from approximately 300' north of the Main Street intersection to the US-31 intersection and on US-31 from the Russell Street intersection to the Virginia Street intersection. US-31 from Potter Road to Maple Street: The area along US-31 from Potter Road to Maple Street includes some commercial properties, so the recommended flow for this area was chosen to be 2,500 gpm. In order to provide 2,500 gpm flows in this area, the watermain on Potter Road (from Smith Street to US-31) and the watermain on US-31 (from Potter Road to Maple Street) should be replaced with 8-inch watermain. If the improvements listed above are completed, recommended fire flows and capacity for a commercial classification fire event can be met. Table 13 shows available fire flow for the areas listed in Table 10 after the completion of the recommended improvements.

TABLE 13

COMPARISON OF AVAILABLE FIRE FLOW TO TARGET FIRE FLOWS AFTER COMPLETION OF RECOMMENDED DISTRIBUTION SYSTEM IMPROVEMENTS

Location Number Location

Recommended Target

Fire Flow @ 20 psi (gpm)

Available Fire Flow @ 20 psi

(WaterCAD) (gpm)

Difference Between Target & Available

(%)

1 US-31 at the Russell Street intersection 1,000 3,469 +247%

2 US-31 at the Potter Road Intersection 2,500 3,510 +40%

3 US-31 at the Stuart Street Intersection 2,500 4,057 +62%

As seen in Table 13, the recommended distribution system improvements increase the available fire flows to meet or exceed the recommended fire flow.

Recommended Improvements – Estimated Cost

Distribution system improvements are recommended to improve available fire flows and overall system reliability. These improvements should be considered and implemented by Village officials as deemed necessary. The Village should plan on replacing old 4-inch watermains as road improvements are conducted in the Village. These 4-inch lines should be replaced with minimum 8-inch lines in areas where fire protection is provided.

Estimated costs are included with the recommended improvements. These costs are meant to be rough estimates for budgeting purposes only. The estimated costs include appurtenances such as valves, hydrants, fittings, water services, restoration, engineering and contingencies. A unit price of $100 per foot was used for 8-inch watermain. This cost does not include roadway replacement or repairs. The costs are estimated to increase by anywhere from $50 per foot to $100 per foot if watermain must be constructed within the paved roadway, depending on the amount and type of road construction.

VILLAGE OF BEAR LAKE – WATER RELIABILITY STUDY PAGE 18

FLEIS & VANDENBRINK ENGINEERING, INC. 811320 BEAR LAKE REPORT W REVISED RD APP COSTS

Short Term Improvements (0 to 5 Years)

• Replace Well No. 2 with a new well with a minimum pumping capacity of 475 gpm. $400,000

• Replace aged hydrants with new hydrants.

$50,000

TOTAL COST OF SHORT TERM RECOMMENDED IMPROVEMENTS: $450,000 Long Term Improvements (20 Years)

• Replace 2,400 feet of 4-inch watermain on US-31 from Virginia Street to Russell Street, and on Russell Street from US-31 to 300' north of Main Street with 8-inch Watermain.

$408,000

• Replace Well No. 3 with a 475 gpm well, and if the Village desire to meet a commercial fire flow classification, install an additional new 475 gpm well.

$800,000

• Replace 3,400 feet of 4-inch and 6-inch watermain on Potter Road (from approximately 300' west of Smith Street to US-31) and US-31(Potter Road to Maple Street) with 8-inch watermain.

$578,000

• Replace 4-inch watermains that provide fire protection with minimum 8-inch watermain at the following locations:

• 730 feet on Maple Street • 2,050 feet on Wise Street • 340 feet on Stuart Street • 660 feet on Cody Street • 1,000 feet on Virginia Street • 740 feet on Locust Street and Euclid Street

$939,000

• Install water meters for all Village water customers $230,000

TOTAL COST OF LONG TERM RECOMMENDED IMPROVEMENTS: $2,955,000

TOTAL COST OF ALL RECOMMENDED IMPROVEMENTS: $3,405,000

VILLAGE OF BEAR LAKE – WATER RELIABILITY STUDY PAGE 19

FLEIS & VANDENBRINK ENGINEERING, INC. 811320 BEAR LAKE REPORT W REVISED RD APP COSTS

VII. FUNDING SOURCES

Five possible sources of funding have been identified for the Village of Bear Lake to complete the recommended improvement projects. A brief description of each follows:

Drinking Water Revolving Fund

The Drinking Water Revolving Fund is a low interest loan program sponsored by the Michigan Department of Environmental Quality. The current interest rate is 2-1/2 percent.

The program is competitive and projects are scored on a point system that ranks them on a priority list. Not all projects submitted are funded so it is important to maximize points on the application. Requirements include a fairly extensive project plan, but most expenses, including the project plan, are eligible activities that can be rolled into the loan. In order for a community to be competitive, they should have a completed wellhead protection program. Applications are submitted by May 1st of every year.

USDA - Rural Utilities Service Grants or Loans (formerly FHA)

Rural Utility Service offers grants and loans for water improvements to communities with a low to moderate average household income. Since the Village’s median average household income is below the low to moderate range, the Village may qualify to receive grant dollars to apply towards a portion of a project. There are two types of loans available from RUS: direct loans and guaranteed loans. Direct loans are only issued if the Village is unable to obtain funding from other sources at reasonable rates. The current interest rate is approximately 2.75 percent.

Guaranteed loans are made and serviced by lenders such as banks and savings and loan associations. Guarantees will not exceed 80 percent on any loss of interest and principal on the loan.

Special Assessment Bonds

Special assessments levied under PA 188 of 1954 are one of the most common ways to finance infrastructure improvements. The Village may levy special assessments against properties that receive special benefits from a public improvement. Property owners have petition rights that must be satisfied before the special assessment can go forward. The current bond rate is approximately 4.5 percent. Special assessments typically can be repaid in installments with interest. The bonds may not exceed the amount of the special assessment roll, and may be secured secondarily by a pledge of the Village’s full faith and credit.

Revenue Bonds

Revenue bonds are authorized by PA 94 of 1933. They authorize the Village to borrow money and issue bonds. They are paid from user fees generated by the operation of the improvements. Revenue bonds are subject to the right of referendum. Petitions for a public vote can be filed by registered Village voters during a 45-day referendum period. Voter approval is not required if the referendum period expires without petitions being filed. The current bond rate is approximately 4.5 percent.

VILLAGE OF BEAR LAKE – WATER RELIABILITY STUDY PAGE 20

FLEIS & VANDENBRINK ENGINEERING, INC. 811320 BEAR LAKE REPORT W REVISED RD APP COSTS

Contract Bonds

Contract bonds are authorized by several state laws. They authorize the Village to enter into an agreement with the County or a public authority in order to have the County or authority issue bonds on behalf of the Village.

The Village may want to consider a contract bond as the County may be able to borrow at a more favorable rate than the Village if they are willing to pledge its taxing power as secondary security for repayment of the bonds. Also contract bonds may be paid back by a number of sources including: specials assessments, connection fees, and user fees. The current bond rate is approximately 4.5 percent.