Expressway Authority of Thailand Ministry of Transport Market Sounding Documentation For Udonratthaya-Ayutthaya Expressway Project

Transcript of · Web viewOn-off ramp Kao Koet Royal Folk Arts and Crafts Center On-off ramp Ban Klueng...

Expressway Authority of Thailand

Ministry of Transport

Market Sounding Documentation

For

Udonratthaya-Ayutthaya Expressway Project

April 2015

1. Introduction

Expressway Authority of Thailand (EXAT) realizes great benefits of Udonratthaya-Ayutthaya Expressway Project as the infrastructure development for transportation of Thailand. The beginning of the project is started at the end route of the existing Udonratthaya Expressway and the end of the project connects to highway No. 32 at Bang Pahan District in Ayutthaya Province. Total distance of project is 42 kilometer. The objective of the project is to develop the expressway network for the linkage of travelling and goods transportation between Bangkok and Ayutthaya Province and also including the provinces in the North of Thailand.According to the Act on Private Investment in State Undertaking B.E. 2556 (2013), EXAT would like to invite private sectors to participate in giving suggestions and opinions on the project investment forms. Market sounding of Udonratthaya-Ayutthaya Expressway Project is conducted to obtain suggestions and opinions in order to implement this project efficiently. The information obtained from investors will used for this project only.

2. ObjectivesThe purpose of this market sounding is for market testing on private sectors’ interest of Udonratthaya-Ayutthaya Expressway Project’s investments. The suggestions and recommendations from private investors will enhance successful implementation of the project.

3. Target Groups

- 1 -

3.1 Thai or international company that operate and maintain expressway projects3.2 Thai or international private investors3.3 Any financial institutions that are interested in expressway projects

4. Project Details4.1 Reason and Necessity

The demand volume of cargo and passenger between Bangkok and Ayutthaya province has rapidly increased because of the development of land use such as Real Estate and Industrial Estate sections. At present there are very high traffic volumes on highway No. 32 which is the main road to service the demand volume and the traffic characteristic is not in good condition. Apart from that, Ayutthaya province is also the location of much tourist attraction such as Ayutthaya Historical Park, Bang Sai Arts and Crafts Centre, Bang Pa-In Palace etc. and every year there are a lot of tourists come to visit. So the expansion of transportation network is critical to serve that demand.

4.2 Alignment of Project(1) Main line

The beginning of the main line of

- 2 -

Udonratthaya-Ayutthaya Expressway Project is started at the end route of the existing Udonratthaya Expressway at Bang Pa-in District. The main line moves forward to the North and parallels with highway No. 347 in the west side. The main line is across Chaophaya River at Kao Koet District and after that it passes through the area of Ayutthaya Province. The main line will connect to the highway in Ayutthaya Province, such as highway No. 3442 highway No. 347 highway No. 356 highway No. 3263 highway No. 309 highway No. 329. The end of the main line will connects to highway No. 32 at Bang Pahan District and total distance of Udonratthaya-Ayutthaya Expressway Project is 42 km. as Figure 1.

- 3 -

Figure 1 Alignment of Udonratthaya-Ayutthaya Expressway Project

- 3 -

(2) Typical Section of Viaduct StructureThe viaduct structure of Udonratthaya-Ayutthaya Expressway Project is design T-shaped column and I-Girder shape. It has 4-lane, (2-lane each direction). Each traffic lane is 3.50 meters wide with outer shoulder of 2.00 meters wide and inner shoulder of 0.50 meters wide as shown in Figure 2.

Figure 2 Typical Cross Section of Udonratthaya-Ayutthaya Expressway

Project

(3) On-off rampThere are 8 locations of on-off ramp as shown in Figure 3, as followed:1)On-off ramp Bang Pa-in2)On-off ramp Kanchanaphisek Road

- 4 -

3)On-off ramp Bang Sai Royal Folk Arts and Crafts Center

4)On-off ramp Kao Koet Royal Folk Arts and Crafts Center

5)On-off ramp Ban Klueng6)On-off ramp Worrachet7)On-off ramp Phut Lao8) On-off ramp Bang Pahan

- 5 -

Figure 3 On-off Ramps of Udonratthaya-Ayutthaya Expressway Project

- 5 -

4.3 Traffic VolumeThe traffic volume forecasting of Udonratthaya-Ayutthaya Expressway Project show as follows:

Year Traffic on the expressway (PCU/day)

2022(Opening Year) 27,026

2026 31,1532031 43,0832036 55,1762041 69,0142046 78,9062051 93,186

4.4 The toll collectionToll collection of the Udonratthaya-Ayutthaya Expressway Project is a close system based on 42 kilometers distance. In the year 2022 (The opening year to the traffic), the toll rate of each vehicles are as follows:

Types of vehicleEntry rate

(Baht)

Distance rate(Baht/km.)

Maximum toll rate(Baht)

4 wheels vehicle 35 0.50 55

6 to 10 wheels vehicle

70 1.00 110

More than 10 wheels vehicle

105 1.50 165

- 6 -

4.5 Project Implementation PlanUdonratthaya-Ayutthaya Expressway Project has a plan to implement during fiscal year 2014-2022 and opens to the traffic in 2022 as follows:

Oct

Nov

Dec

Jan Feb Mar

Apr

May

Jun Jul Aug

Sep Oct

Nov

Dec

Jan Feb Mar

Apr

May

Jun Jul Aug

Sep Oct

Nov

Dec

Jan Feb Mar

Apr

May

Jun Jul Aug

Sep Oct

Nov

Dec

Jan Feb Mar

Apr

May

Jun Jul Aug

Sep Oct

Nov

Dec

Jan Feb Mar

Apr

May

Jun Jul Aug

Sep Oct

Nov

Dec

Jan Feb Mar

Apr

May

Jun Jul Aug

Sep Oct

Nov

Dec

Jan Feb Mar

Apr

May

Jun Jul Aug

Sep Oct

Nov

Dec

Jan Feb Mar

Apr

May

Jun Jul Aug

Sep Oct

Nov

Dec

Jan Feb Mar

Apr

May

Jun Jul Aug

Sep Oct

Nov

Dec

Jan Feb Mar

Apr

May

Jun Jul Aug

Sep

Feasibility Study -

- Land acquisition

- Construction (include detail design)

2021 2022 2023Project 2014 2015 2016 2017 2018 2019 2020ǰ 9months

ǰ 8months

ǰ36months

- 7 -

4.6 Project Investment Costs An investment budget for Udonratthaya-Ayutthaya Expressway project is approximately 31,432.51 Million Baht consisting of:- Land acquisition cost 2,766.51 Million

Baht- Construction cost 28,666.00 Million

Baht(Including detailed design and consultants cost)

4.7 The Economic Feasibility Study Shows that the project will be worthwhile economically as follows:- Net Present Value (NPV) = 24,850.25 Million

Baht (at the discount rate of 12%)- Economic Internal Rate of Return (EIRR) =

19.81- Benefit Cost Ratio (B/C) = 2.22

- 8 -

5. Scopes of InvestmentThe private sector who has been appointed by the EXAT as a concessionaire of Udonratthaya-Ayutthaya Expressway Project is obliged to carry out the following scopes of project investment and the EXAT is obliged to perform the following scopes of project investment:5.1 The private sector who has been granted

for a concession is committed to project investment and operation in 2 phases as follows:Phase 1 Expressway Design and ConstructionThe concessionaire will be responsible for the design and construction costs of Udonratthaya-Ayutthaya Expressway Project and make it complied with the concession agreement as well as provide installation of Mechanical and Electrical system, toll collection system, communication system, traffic control system and any other systems as considered necessary.Phase 2 Expressway Operations and MaintenanceThe concessionaire will be responsible for the operation cost of the expressway so that it can render service to public in an effective way with safety according to the international standard and the expressway can be maintained in good condition throughout the concession period of the project.

5.2 The government will support for land acquisition cost in relation to the expressway construction project while the EXAT will assist in coordination with government sectors as well as give all the possible supports to the investor. So,

- 9 -

it can be provided with maximum benefits according to the law of investment promotion.

5.3 Concession Period: The concession period of this project is 30 years beginning from the construction period. The concession holder obtains the right to receive the toll revenues generated from Udonratthaya-Ayutthaya Expressway Project and will have to pay a portion of the toll revenues to the government as mutually agreed in the concession agreement.

5.4 Project Operation Rules and Regulations for Udonratthaya-Ayutthaya Expressway Project, Ayutthaya Province will be according to the Private Investment in State Undertakings Policy Committee Act, B.E. 2556 (2013), the EXAT Act, B.E. 2550 (2007) and all the concerned rules, regulations and agreements.

- 10 -

6. Private Partner Selection CriteriaA selection of the private partner for Udonratthaya-Ayutthaya Expressway Project will follow the Public Private Partnership Act, B.E. 2556 (2013), while a Selection Committee will be nominated by the EXAT to set up initial selection criteria, as followed:6.1 Qualifications of the Investor

The concession holder must possess business management skill and a good financial status with at least 500 Million Baht paid-up registered capital. He/she should has experiences and records of the design–construction, project management as well as operation and maintenance of the expressways.

6.2 Proposal PreparationThe interesting private partners will prepare proposals in accordance with the requirements stipulated in the proposal preparation documentation, arranged by the Selection Committee of Udonratthaya-Ayutthaya Expressway Project, Ayutthaya Province.

6.3 Private Partner Selection Process for Build-Transfer-Operate (BTO) ConcessionThis is a concession given to private partner to operate the expressway which will be in compliance with the Public Private Partnership Act, B.E. 2556 and the Expressway Authority of Thailand Act, B.E. 2550 (2007).

- 11 -

7. Procedure in Market SoundingThe questionnaire responders are kindly requested to fill in their ideas or suggestions and returned to the following address, from 16th April to 24th April, 2015, between 8.30 a.m. to 4.30 p.m. or send E-mail to [email protected] or returned to the following address from 16th April to 24th April 2015.The Governor of The Expressway Authority of ThailandExpressway Authority of Thailand2380 Phahonyothin Road Senanikom ChatuchakBangkok 10900.With a word on the envelop corner “(Market Sounding)”For more information, Please contact Tel. +66 2 558 9800 Ext. 2540 Fax +66 2 940 1226EXAT will neither be responsible for the expenses incurred from questionnaire responses nor committed to taking actions according to the suggestions or information provided by the responders.

- 12 -

8. Questions8.1 What form of investments are you interested

in?___________________________________________________________________________________________________________________________________________________________________________________________________

8.2 Are you in interested in the investment of Udonratthaya-Ayutthaya Expressway Project? Please specify the scope of your investment that you are interested in.

As a company that operates and maintains an expressway

As a private sector As a financial institution Others; please specify

_______________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

- 13 -

8.3 Considering allocation of project funding, do you have any suggestions, opinions, or requests for financial supports from the government?______________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

- 14 -

8.4 As Thai government is responsible for providing land and cooperating with facility agencies, do you have suggestions and/or opinions in order to implement this project efficiently?____________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

8.5 As Udonratthaya-Ayutthaya Expressway Project is a megaproject which requires tremendous amount of investment, do you have any suggestions and/or opinions in order to implement this project efficiently?______________________________________________________________________________________________________________________________________________________________________________________________________________________________________

- 15 -

__________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

- 16 -

8.6 Considering operation and maintenance of the project, do you have any suggestions, opinions, and/or requests for financial supports from the government?______________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

8.7 As this project shall follow Build - Transfer - Operate (BTO), do you have any suggestions and/or opinions concerning reasonable financial return to the Thai government and private sector?_____________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

- 17 -

_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

- 18 -

8.8 As Udonratthaya-Ayutthaya Expressway Project is a megaproject, in order to implement this project efficiently, do you think you should be offered some supports from the government? If yes, please specify:

1)Privilege Tax/Account2)Co-operations & supports from government

agencies3)Public concerns4)Others

________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

8.9 Do you have any opinions and/or suggestions concerning investors’ cost of capital and the

- 19 -

proper figure for the rate of return of this project?____________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

- 20 -

8.10 Do you have any opinions and/or suggestions on the implementation plan of Udonratthaya-Ayutthaya Expressway Project?____________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

8.11 Other suggestions__________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

- 21 -

__________________________________________________________________________