nromoef.gov.innromoef.gov.in/SMPR/13102014/272.docx · Web viewEmployment growth is a primary...
Transcript of nromoef.gov.innromoef.gov.in/SMPR/13102014/272.docx · Web viewEmployment growth is a primary...
Executive Summary
ABOUT PROJECT
Name of Project :Viva Drugs Pvt. Ltd.
Location :Village Phirour, Tehsil- Khamano,
Distt- Fatehgarh, Punjab
Product :Atenolol, Atorvastatin calcium, Diclofenac
Sodium, Mefenamic acid, Losartan potassium
Clopidogrel bisulfate, Fexofenadine HCl,
Terbinafine hydrochloride & Fluconazole
Nitazoxanide
Capacity (TPA):15-20
Total
Type of Project:Bulk Drug & Intermediates
Cost of the Project:Rs. 2Crore
Total Land:2.2 Acres
Power Requirement:421 KW
Source of power: From Pb. State Power Corporation Ltd
& DG Sets
Source of Water Supply :Own bore well
Quantity of Water (KLD):TotalFresh Water Recycle
26 KLD8 KLD18 KLD
Effluent treatment :Domestic= ETP cum STP
Process= ETP cum STP
Alternate source of power: 1 No. DG Set (85KVA), 1 No. DG Set
(25KVA), 1 No. DG Set (5KVA)
Air Pollution Control :Cyclones, Scrubber & Stack
Solid Waste :Common storage, Treatment & Disposal
Facility (NIMBUA)
Hazardous:Used oil by GOLDEN PETRO (authorized recycler)
1. INTRODUCTION:
M/s Viva Drugs Pvt. Ltd. is proposing to enhance capacity of the unit & addition of chemical products like Atenolol, Atorvastatin calcium, Diclofenac Sodium, Mefenamic acid, Losartan potassium,Clopidogrel bisulfate, Fexofenadine HCl, Terbinafine hydrochloride & Fluconazole, Nitazoxanide at Village Phirour, Tehsil Khamano, Distt. Fatehgarh Sahib, Punjab.As per MOEF, GOI Notification dated 14-09-2006 they are required to have Environmental Clearance of their project before establishing the same. As per schedule of the Notification the Organic Chemical Industries are listed at S. No. 5(f) and general condition given in the Notification is applicable to the unit. Further, the project is to be treated as Category A and thus the Environmental clearance is to be given by the Central Govt. MOEF for which necessary documents were submitted to the SEIAA who have desired to submit an E.I.A. report as per TOR laid out by them. One of the conditions of the TOR is to have Public Hearing. Accordingly a Draft E.I.A report had been prepared to assess the likely impact of the proposed project on various factors which may be affected with the implementation of the programme and to suggest remedial/ precautionary measures, if any, which has been submitted separately. This is a summary of the main Draft EIA Report.
2. NEED OF PROJECT:
The proposed expansion project Viva Drugs Pvt. Ltd. aims to manufacture Bulk Drugs & its Intermediates.
Cardiovascular diseases (CVD) continue to be the major cause of mortality representing about 30% of all deaths worldwide. Lifestyle diseases like hypertension, diabetes mellitus, dyslipidaemia and overweight/obesity are the major risk factor for the development of CVD. With rapid economic development and increasing westernization of lifestyle in past few decades prevalence of those diseases has reached alarming proportion among Indians in the recent years. Many studies from different Indian States showed that the prevalence of prehypertension in the country is about 40-50% therefore there is high demand of drugs to treat cardiovascular diseases in India.
Non-steroidal anti-inflammatory drugs provide analgesic and antipyretic (fever-reducing) effect, and in higher doses anti-flammatory effects, this class of drug is always in demand due to anti-inflammatory effects.
Allergies bring more than the misery of a stuffy nose, watery eyes, and sneezing. If we do not treat allergies, they can aggravate or lead to other conditions such as asthma and sinusitis. Treatment for allergies can involve several different medications, including steroids and allergy shots, but usually the first line of attack is with antihistamines and so far Fexofedine is the best available medicine in Indian market.
3. BASELINE SETTING:
Prevailing Baseline Conditions in the study area of 10 km around the unit have been studied. Primary data has been collected through visits & discussion with local people Secondary data has been taken from the IMD record for Chandigarh station. Thus information regarding climatic conditions like climate, rainfall, humidity, cloudiness, winds etc. are based on IMD data for the years 2004-2009. Other information regarding drainage, land use, cropping pattern & demographic structure has been obtained from the revenue record of Punjab Govt. Details of Forests; Flora & Fauna have been checked from Forest Deptt. & site visits.
4. ENVIRONMENTAL BENCH MARK CONDITIONS:
In order to know the impact of the project on various parameters, it is necessary to know their existing levels. The anticipated effect of the pollutants from the project, if any, shall be superimposed on this to assess the final levels as compared to the permissible limits.
Monitoring stations were established at eight different places within the study area and the existing levels of various parameters in respect of the following were observed to see their quality.
I) Ambient Air
II) Ground & Surface water
III) Noise
IV) Soil
It has been seen that all parameters are well within the permissible limits. Demographic, Socio Economic aspects & Eco Biodiversity angles were also studied & results documented.
5. PROJECT DESCRIPTION:
The project involves manufacture of Atenolol, Atorvastatin calcium, Diclofenac Sodium, Mefenamic acid, Losartan potassium, Clopidogrel bisulfate, Fexofenadine HCl, Terbinafine hydrochloride & Fluconazole, Nitazoxanide.
EMPLOYMENT GENERATION (Direct and Indirect) DUE TO THE PROJECT:
Direct Employment:
Employment generation has been one of the important objectives of development / industrialization. Employment growth is a primary economic development goal of most small communities. More jobs generally mean more residents, more spending at local businesses, and more tax revenues for local governments. Thus job growth permits the expansion and improvement of public goods and services, leading to an improved local quality of life and enhanced prospects for future employment growth. Hence considering the technicality and complexity involved in the Drug Manufacturing, the staffing and employment is critical therefore local people will be given employment based on appropriate knowledge, qualification and expertise.
Small and medium pharma enterprises have played a key role in driving the growth and current status of the Indian pharmaceutical sector. In terms of number of units and employment generation, the SME sector is at the forefront.
Proposed Employment Generation in various departments viz.:-
Production Department
Maintenance Department
Quality Control Department
Quality Assurance
Research and Development / IPM
Purchase Department
EHS
ADMINISTRATION
Indirect Employment:
There is lot of places in-which employment generates indirectly:
Transportation and warehousing
Travel & Tourism Sector
Packaging and printing sector
Information Technology
Agency employment
Telecom Sector
Automobile Sector
Courier Sector
6. RAW MATERIAL USED IN PROCESS:
The raw materials consumption norms involved with respect to products is given below:
TABLE: RAW MATERIAL CONSUMPTION NORMS OF ATENOLO
RAW MATERIALs
CON.
PHPA (Para Hydroxy Phenyl Acetamide)
0.71
Epichlorohydrin
0.91
Mono Iso Propylamine
0.71
Caustic Flakes
0.43
Activated Carbon
0.10
Hyflo
0.02
Hydrochloric acid (CP)
0.53
Sod. Bi Carbonate
0.02
FOR 1.0 KG OF BCFI
1.0
TABLE: RAW MATERIAL CONSUMPTION NORMS OF DICLOFENAC-Na
RAW MATERIALs
CON.
N-CHLOROACETYL-N-PHENYL-2, 6-DICHLOROANILINE
1.46
ALUMINIUM CHLORIDE
0.915
POT WATER
15
SODIUM HYDROXIDE
0.45
SODIUM DITHIONITE
0.004
METHANOL
0.125
FOR 1.0 KG OF DICLOFENAC-Na
1.0
TABLE: RAW MATERIAL CONSUMPTION NORMS OF BCFI
RAW MATERIALs
CON.
ACRYLONITRILE
1.5
HYDROCHLORIC ACID
0.4
POCL3
6
TOLUENE
1
DIMETHYL FORMAMIDE
2
SODIUM CARBONATE
1
METHANOL
4
GLYCINE
0.6
TETRA BUTYL AMMONIUM BROMIDE
0.1
AMMONIA
1
CAUSTIC
1.6
FOR 1.0 KG OF BCFI
1.0
TABLE: RAW MATERIAL CONSUMPTION NORMS OF LOSARTAN-K
RAW MATERIALs
CON.
BCFI (2-butyl-5-chloro-1H-imidazole-4-carbaldehyde-)
0.6
OTBN(2-Cyano-4-methylbiphenyl)
0.7
AIBN(Azobisisobutyronitrile)
0.03
DBH(5,5-Dimethyl-1,3-dibromohydantoin)
0.6
DICHLORO METHANE
3
TOLUENE
12
METHANOL
7
SODIUM BOROHYDRIDE
0.1
TETRA BUTYL AMMONIUM BROMIDE
0.12
SODIUM HYDROXIDE
0.75
N-METHYL PYROLIDONE
1
TEA.HCl
1.5
SODIUM AZIDE
0.7
SODIUM METABISULPHITE
0.11
CARBON
0.2
ETHYL ACETATE
0.7
ACETIC ACID
1.4
POTASSIUM HYDROXIDE
0.2
SODIUM BICARBONATE
0.04
FOR 1.0 KG OF LOSARTAN
1.0
TABLE: RAW MATERIAL OF MEFENAMIC ACID
RAW MATERIALs
Qty
2-Chloro-benzoic acid
1
2,3-Dimethyl-phenylamine
0.88
Cuprous chloride
0.025
DMF
0.1
Toluene
0.75
Potassium carbonate
0.88
TABLE: RAW MATERIAL OF ATORVASTATIN CALCIUM
RAW MATERIALs
Qty
4-Fluoro-alpha-(2-methyl-1-oxopropyl)-gamma-oxo-N,beta-diphenylbenzene butaneamide
0.76
Butylester side chain
0.6
Pivalic acid
0.2
DMF
1.0
Heptane
2.0
Caustic
0.227
Toluene
2.0
Potassium carbonate
0.2
FEXOFENADINE-HCl
Stage : I
Raw Material
Unit
Qty
Benzyl Cyanide
Kg
1.00
DNS
Kg
3.00
Potassium Hydroxide
Kg
2.50
DMSO
Ltr
1.50
Con.HCl
Ltr
2.00
Toluene
Ltr
5.00
Output
Kg
1.2
Stage : II
Raw Material
Unit
Qty
FEX-I
Kg
1.00
EDC
Ltr
2.00
Sodium Hydroxide
Kg
0.80
Con. HCl
Ltr
2.00
Output
Kg
1.1
Stage : III
Raw Material
Unit
Qty
FEX-II
Kg
1.00
Methanol
Ltr
3.00
Sodium Bicarbonate
Kg
0.10
Toluene
Ltr
4.00
Output
Kg
1.00
Stage : IV
Raw Material
Unit
Qty
FEX-III
Kg
1.00
Sodium Borohydride
Kg
0.70
Aluminium Chloride
Kg
0.02
1,2-DME
Ltr
1.50
Con. HCl
Ltr
0.80
Toluene
Ltr
3.00
Output
Kg
0.8
Stage : V
Raw Material
Unit
Qty
FEX-IV
Kg
1.00
Acetic anhydride
Kg
0.80
Hexane
Ltr
3.00
Sodium Bicarbonate
Kg
0.15
Output
Kg
1.1
Stage : VI
Raw Material
Unit
Qty
FEX-V
Kg
1.00
4-CBC
Kg
0.80
Aluminium Chloride
Kg
1.50
MDC
Ltr
5.00
Con.HCl
Ltr
1.50
Output
Kg
1.5
Stage : VII
Raw Material
Unit
Qty
FEX-VI
Kg
1.00
Sodium Hydroxide
Kg
0.30
DMF
Ltr
1.00
Toluene
Ltr
3.00
Output
Kg
0.7
Stage : VIII
Raw Material
Unit
Qty
FEX-VII
Kg
1.00
Potassium permanganate
Kg
1.20
Sodium Hydroxide
Kg
0.40
Sodium metabisulphite
Kg
0.10
MDC
Ltr
1.50
Toluene
Ltr
4.00
Con.HCl
Ltr
1.00
Output
Kg
0.9
Stage : X
Raw Material
Unit
Qty
FEX-VIII
Kg
1.00
Azacyclonol
Kg
0.90
MIBK
Kg
1.00
Potassium iodide
Kg
0.01
Potassium bicarbonate
Kg
1.00
DNS
Kg
1.50
Methanol
Kg
0.20
Methanol-HCl
Kg
4.50
Sodium chloride
Kg
0.10
Sodium bicarbonate
Kg
0.10
Sodium Hydroxide
Kg
0.10
Output
Kg
1.5
Stage :XI
Raw Material
Unit
Qty
FEX-X
Kg
1.00
Methanol
Kg
2.50
Sodium borohyride
Kg
0.06
Sodium Hydroxide
Kg
0.20
Con.HCl
Kg
0.60
Acetone
Kg
0.30
DNS
Kg
4.00
Output
Kg
0.5
Stage : XII
Raw Material
Unit
Qty
FEX-XI
Kg
1.00
Con.HCl
Kg
0.50
Sodium Hydroxide
Kg
0.10
Hyflow
Kg
0.10
Output
Kg
0.9
Stage :API
Raw Material
Unit
Qty
FEX-XII
Kg
1.00
IPA
Kg
2.50
Ethyl acetate
Kg
3.00
Hyflow
Kg
0.05
A. carbon
Kg
0.02
Output
Kg
0.90
CLOPIDOGREL BIDULPHATE
Stage:1
Sr.No
Name
Unit
Qty
1
2-Chloro Phenyl Glycine
Kg
1.00
2
Methanol
Kg
5.00
3
Thionyl Chloride
Kg
1.00
4
MDC
Ltr
2.00
5
Water
Ltr
1.00
6
Aq.Ammonia
Ltr
0.60
Stage : 1 Output(Oily mass)
Kg
1.00
Stage:2
1
Stage 1
Kg
1.00
2
Methanol
Kg
5.00
3
L-(+)-tartaric acid
Kg
0.75
4
Acetone
Ltr
0.35
Stage : 2 Output
Kg
1.40
Stage:3
Purification
1
Stage 3
Kg
1.40
2
Water
Ltr
7.00
3
MDC
Ltr
3.30
4
Aq.Ammonia
Ltr
0.30
Stage : 3 Output(Oily mass)
Kg
0.77
Stage:4
1
Thiophene-2-ethanol
Kg
0.71
2
Toluene
Ltr
4.30
3
PTSChloride
Kg
1.45
4
Water
Ltr
5.70
5
Caustic lye
Ltr
1.40
6
PTC
Kg
0.04
Stage : 4
Kg
1.50
Stage:5
1
Stage 3
Kg
0.77
2
Acetonitrile
Ltr
4.00
3
Sodium Bicarbonate
Kg
1.15
4
Stage 4
Kg
1.50
5
Ethyl acetate
Ltr
2.70
6
Con.HCl
Ltr
0.57
7
Hexane
Ltr
0.77
8
Water
Ltr
1.50
Stage:5 Output
Kg
1.00
Stage:6
1
Stage 5
Kg
1.00
2
Methanol
Ltr
0.30
3
Toluene
Kg
2.70
4
Water
Ltr
1.00
Stage:6 Output
Kg
0.90
Stage:7
1
Stage 6
Kg
0.90
2
IPA
Ltr
4.50
3
Para formaldehyde
Kg
0.20
4
Con.HCl
Ltr
0.01
5
Hexane
Ltr
7.20
6
Aq.Ammonia
Ltr
0.15
7
Sodium Bicarbonate
Kg
0.25
8
Act. Carbon
Kg
0.10
9
Celite
Kg
0.20
Stage:7 Output (Oily mass)
Kg
0.72
Stage:8
1
Stage 7
Kg
0.72
2
Acetone
Ltr
2.16
3
Con.Sulfuric acid
Kg
0.22
Stage:8 Output
Kg
0.86
Source of Raw Material
It is proposed to procure raw materials from the domestic market and certain quantity of some raw materials can be imported from China / any other country. The mode of transport will be by Air or Sea
Final Products
The final product will be Bulk Drugs, Active Pharmaceutical Ingredients & its Intermediates which will transported in India by Rail / Road or Air while the same will be exported to out-side by Air or Sea.
7. BUILDINGS IN PLANT
The firm has already acquired 2.2 acres of land where part factory building has been constructed and no other building required for expansion. It provides adequate space for the following areas of working:-
1.Stores for raw material and finished goods.
2.Production hall
3.Store
4.Offices
5.Engineering workshop
Open space will be landscaped and trees will be planted in due course of time.
8. EMISSIONS:-
There are no emissions from the process as no gaseous material is generated. All materials which become vapors during process are condensed through series of condensers, as all process occur in tightly closed system. However there may be some secondary emissions due to moving of vehicles which will be controlled through sprinkling of water.
9. WASTE HANDLING TREATMENT:-
SOLID WASTE:-
There is no generation of Solid wastes from process.
HAZARDOUS WASTE:-
The Hazardous wastes generated from the unit send to NIMBUA which is a Common Storage, Treatment, & Disposal Facility.
10.0 POLLUTION CONTROL MEASURES:-
i)AIR POLLUTION:-
DG SET:-
There are three DG sets proposed of 85KVA, 25 KVA and 5 KVA. As per guidelines of CPCB/PPCB a stack height of 3.5mt from roof level has been provided to control the pollutants from the diesel fuel to be used.
ii)WATER POLLUTION:-
Requirement Daily fresh water demand will be 8.0 KLD.
The industrial water demand for the proposed expansion will be 22.0 KLD and domestic water demand will be 4.0 KLD. The total water demand in the plant will be 26.0 KLD, out of which we will recycled 18.0 KLD in the industrial process.
The industrial wastewater will be recycled and reused in cooling towers, boilers, scrubbers and where ever possible. An ETP cum STP for the waste water generated is installed to reduce water requirement thus indirectly help the out-put of the plant.
iii) NOISE POLLUTION:-
There is no noise producing machinery. Thus no noise of significant level shall go outside the working area which may disturb the general noise environment. DG set installed shall be noise less type & with canopy.
11.0 ENVIRONMENT IMPACT ASSESSMENT & MITIGATION MEASURES:
GENERAL:
Impact of the project on various Environmental Factors in the project area has been checked on short term & long term basis. Short term impacts are during construction development stage. Long term impacts relate to the operation stage. In both the cases following factors have been considered.
Ambient Air Quality
Water Quality
Noise Quality
Land use pattern
Demographic & Socio economic pattern
ENVIRONMENTAL
FACTORS
SHORT TERM
(CONSTRUCTION STAGE)
LONG TERM
(OPERATIONAL STAGE)
Ambient Air Quality
During the construction no air pollution will be generated. The development stage impacts will not be of any significance. Since there is no point source of air pollution and the fugitive dust generation will be suppressed with sprinkling of water, there will be no effect on this account.
There is only one source of likely pollution which is vapours from the manufacturing process. All the process are closed circuits as such emission to the open atmosphere will be minimum, however, APCD, will be provided at the exit point to neutralize the pollutants. So there will be not any effect on the Air Environment.
Water Quality
Requirement of water during construction is hardly about 1 KLD which will be consumed. There will be no discharge outside the unit on this account. Labour working on the machinery will be provided with a toilet facility & the waste will go to the public sewer. Thus, there will be no impact of the unit on water Environment.
Requirement Daily fresh water demand will be 8.0 KLD. The industrial water demand for the proposed expansion will be 22.0 KLD and domestic water demand will be 4.0 KLD. The total water demand in the plant will be 26.0 KLD, out of which we will recycled 18.0 KLD in the industrial process. The industrial wastewater will be recycled and reused in cooling towers, boilers, scrubbers and where ever possible. An ETP cum STP for the waste water generated is installed to reduce water requirement thus indirectly help the out-put of the plant. This will have some positive effects.
Noise Quality
Since there is no large scale machinery, the installation of the same & movement of vehicles is not likely to have and significant effect over the noise environment.
There is no use of noise producing machinery. DG sets will be noiseless type with additional canopy. Noise Environment in the area thus, will not be affected.
Land
Developed land for the unit has been given to the proponent in the Industries dept. since no debris from the unit is thrown on any land; there will not be any effect on land environment.
The project is coming up in an existing Industrial land. No new land is being acquired. Since no waste is thrown on land, soil quality in the area will not be affected.
Demographic & Socio economic pattern
There is not any adverse impact on the local people of this project during construction phase.
It does not interfere in the life of the people in the study area. There will be no adverse impact on them due to this project. However, it will provide some direct & indirect employment to the local people for running the plant, maintenance of machinery, & security etc. This will have positive effects.
CONCLUSION:-
In view of the proper pollution control measure proposed for the unit as stated above it is concluded that there will be improvement in the development of commercial activities, generation of direct and indirect employment opportunities & the overall, improvement of Quality of life in the surrounding area.
13.0ENVIRONMENT MANAGEMENT PLAN:
To achieve the results as per the measures proposed for mitigation of the various pollutants, the following management practices have been suggested for various factors.
Air Environment
Vehicles shall be checked for their vehicular emissions. Drivers of the vehicles shall be asked to provide PUC certificates. During operation phase air pollution control devices shall be provided to neutralize pollutants from process, to keep it within permissible limits. Tree plantation shall be done along the boundary which will further improve the air Environment in general.
Water Environment
The fresh water will draw through tube-well. The domestic waste water will be use for irrigation purpose after passing through septic tank. Rain water harvesting shall be done for recharging of ground water.
Noise Environment
NO HORN signs shall be displayed at prominent places. Vehicle owners will be asked to maintain them in proper condition. Canopy shall be provided on noiseless types DG sets. Trees with thick foliage shall be planted all around.
Land Environment
No wastage from the unit shall be thrown on any land. Requirement of sand and aggregates during construction shall be obtained from approved vendors.
Solid Waste
There will be no source of solid waste generation in the industry.
Monitoring of various parameters will be done at frequent intervals in the study area, so as to ensure that no deterioration takes place. The results of the monitoring shall be documented and watched properly. The frequency of the checking is as under:
S.No
Item
Parameters to be checked
Frequency
1
Ambient Air
RSPM, SPM, NOX Silica & SO2
Every six months
2
Vehicles
PUC
Every Quarter
3
Noise Level
dB (A)
Once in a year
4
Ground water
As per IS 10500
Once in a year
In order to ensure the implementation of the EMP a structured Environment Management Cell (EMC) interwoven with the existing management system will be created. This will include:-
Representative of the management
Process in charge
In charge maintenance Dept.
A representative of Environment consultants.
All actions of the cell shall be documented.
14.0 COST OF ENVIRONMENT MEASURES:
The total cost of the pollution control measures in the unit is likely to be Rs. 8.0 Lacs. Another Rs. 1.0 Lacs per year shall be needed for their maintenance.
25