Social Monitoring Report Quarterly Report April – June 2016
VIE: Power Transmission Investment Program,
Tranche 2 – 220kV Cau Bong-Hoc Mon-Binh Tan
Transmission Line
Prepared by the Southern Vietnam Power Projects Management Board for the National Power
Transmission Corporation and the Asian Development Bank.
This social monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
NATIONAL POWER TRANSMISSION CORPORATION
SOUTHERN POWER PROJECT MANAGEMENT BOARD
Project Number: 42039-035
Period: Apr - Jun, 2016
INTERNAL MONITORING REPORT ON
IMPLEMENTATION OF RESETTLEMENT PLAN
PROJECT
220KV CAU BONG - HOC MON - BINH TAN TRANSMISSION LINE
HO CHI MINH CITY, July 2016
2sd
Quarter, 2016 - Internal Monitoring Report
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 2
ABBREVIATIONS
ADB Asian Development Bank
AP (project) Affected Person
AH (project) Affected Household
CARB Compensation, Assistance and Resettlement Board
DCSCC District Compensation, Site Clearance Committee
CPC Commune People’s Committee
DMS Detailed Measurement Survey
DP Displaced Persons
DPC District People’s Committee
EVN Vietnam Electricity
GoV Government
HH Household
IOL Inventory of Losses
LURC Land Use Rights Certificate
NPT National Power Transmission Corporation
PPC Provincial Peoples Committee
ROW Right of Way
REMDF Resettlement and Ethnic Minority Development Framework
RP Resettlement Plan
SES Socio-Economic Survey
SPMB Southern Power Project Management Board
SPS Safeguard Policy Statement
USD United States Dollars
VND Viet Nam Dong
2sd
Quarter, 2016 - Internal Monitoring Report
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 3
TABLE OF CONTENTS
I. GENERAL INFORMATION .................................................................................................. 4
1.1 Project Description ...................................................................................................... 4
1.2 Project Impacts ........................................................................................................... 5
II. PROGRESS OF THE PROJECT IMPLEMENTATION ......................................................... 6
III. DETAILED ACTIVITIES UNDERTAKEN .............................................................................. 6
3.1 Progress of Safeguard Policy Implementation ............................................................. 6
3.2 Information Disclosure, Public Consultation and Participation ..................................... 8
3.3 Detailed Measurement Survey and Entitlement .......................................................... 9
3.4 Compensation Payment and Support ....................................................................... 10
3.5 Land Acquisition ....................................................................................................... 11
3.6 Issue Concerning Gender ......................................................................................... 11
3.7 Grievances Redress Mechanism .............................................................................. 12
IV. CONCLUSION AND PLAN FOR NEXT QUARTER ........................................................... 13
4.1 Conclusion ................................................................................................................ 13
4.2 Recommendations .................................................................................................... 13
4.3 Plan for Next Quarter ................................................................................................ 14
V. APPENDICES .................................................................................................................... 15
5.1 Appendix 1. Minutes of announcement meetings of compensation plan ................... 15
5.2 Appendix 2. List of AHs who have received payment in advance .............................. 28
5.3 Appendix 3. Decision on approving of adjustment coefficient plan of land price for
calculating compensation, support for AHs ............................................................... 31
5.4 Appendix 4. Decision on approving of compensation plan, section through Cu Chi
District ....................................................................................................................... 40
5.5 Appendix 5. Some pictures from Public Consultation Meetings ................................. 47
LIST OF TABLES
Table 1: Location of points ..................................................................................................... 4
Table 2: Project Impacts ........................................................................................................ 5
Table 3: Construction works up to July 2016 .......................................................................... 6
Table 4: RP implementation progress up to July 2016 ........................................................... 8
Table 5: Dates of meeting on announcing compensation plan ............................................... 9
Table 6: Summary of the detailed measurement survey in Districts ....................................... 9
Table 7: DMS implementation progress in affected communes ............................................ 10
Table 8: Situation of payment in advance ............................................................................ 10
Table 9: Summary of resolving until the end of this quarter .................................................. 12
2sd
Quarter, 2016 - Internal Monitoring Report
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 4
I. GENERAL INFORMATION
1.1 Project Description
1. The Cau Bong - Hoc Mon - Binh Tan 220 kV Transmission Line (TL) Project has a
total length of 15.94 km. The TL starts at the Cau Bong Substation (SS) at Tan Phu Trung
Commune in Cu Chi District, Ho Chi Minh City and terminates at the proposed Hoc Mon SS
in Tan Thoi Hiep ward in District 12, Ho Chi Minh. A double circuit connection is created
between the Cau Bong 220kV SS, which the World Bank would partly finance, and the new
substations in District 12, which is financed by Ho Chi Minh Electricity Company. The
corresponding TL uses partly the ROW of the existing 110kV Hoc Mon - Ben Cat and partly
the towers of the 220kV Phu Lam - Hoc Mon TL.
Table 1: Location of points
No. Starting ÷ ending point City/
Province District Commune Length (m)
1 DD2-G2.1A
Ho Chi
Minh Cu Chi
Tan Phu Trung 464
2 G2.1A-G2.1
Tan Thanh Dong
1,456
3 G2.1-G2.2 2,549
4 G2.2-G2.3 1,330
5 G2.3-G2.4 Binh My
1,077
6 G2.4-G2.5 271
Subtotal 1 1 1 3 7,147
1 G2.5-G2.6
Ho Chi
Minh
Hoc Mon
Dong Thanh
515
2 G2.6-G2.7 826
3 G2.7-G2.8 559
4 G2.8-G2.9 Thoi Tam Thon
781
5 G2.9-G2.10 870
6 G2.10-G2.11
District 12
Tan Chanh Hiep
791
1 G2.11-G2.12 707
2 G2.12-G2.13 567
3 G2.13-G2.14 748
4 G2.14-G2.15 819
5 G2.15-G2.16 Tan Thoi Hiep
150
6 G2.16-ĐC2 308
Subtotal 2 1 1 3 7,641
TOTAL(1+2) 2 2 6 14,788
2sd
Quarter, 2016 - Internal Monitoring Report
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 5
No. Starting ÷ ending point City/
Province District Commune Length (m)
1 Connect Cau Bong 220kV
Ho Chi
Minh
Cu Chi Tan Phu Trung 314
2 Connect Cau Bong 110kV 619
3 Hoc Mon 110/220 kV District 12 Tan Thoi Hiep 219
Connect to Substations 1,152
GRAND TOTAL 1 3 6 15,940
1.2 Project Impacts
2. Results of Detailed Measurement Survey (DMS) show that the implementation of the
Project causes land restrictions and acquisition in seven (07) communes. Three (03) of them
belong to Cu Chi District, namely Tan Phu Trung, Tan Thanh Dong and Binh My, two (02)
others, namely Dong Thanh and Thoi Tam Thon, belong Hoc Mon District and the last two
(02) wards, namely Tan Chanh Hiep and Tan Thoi Hiep, belong to District 12, Ho Chi Minh
City.
Table 2: Project Impacts
Province District and commune Number of AHs Number of affected
institution(s)
Ho Chi Minh City
Cu Chi District 190 3
Tan Phu Trung 54 1
Tan Thanh Dong 49 1
Binh My 87 1
Hoc Mon District 400 2
Dong Thanh 241 1
Thoi Tam Thon 159 1
District 12 322 2
Tan Chanh Hiep 218 1
Tan Thoi Hiep 104 1
Total 912 7
3. There are 912 households affected by land acquisition and restrictions. The Project
affects 352,928 m² of land, of which 327,381.6 m², equivalent to 92.8%, is subject to land use
restriction within ROW and 25,546.4 m², or 7.2% of the total affected area, is permanently
acquired. The Project affects 10,777.4 m2 of rice and other annual crops (maize, cucumber,
cassava, etc.), and 10,885 trees (including fruit trees, timbers, ornamental trees and shade
trees). 350 houses belonging to 350 AHs are located within the ROW. However, none of
these houses has to be relocated as they are allowed to exist within the ROW as long as
they are subject to certain conditions stipulated at Article 13 of the Decree No. 14/2014/ND-
CP dated February 26, 2014 stipulating in detail of Electricity Law regarding electricity safety.
2sd
Quarter, 2016 - Internal Monitoring Report
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 6
4. None of the affected households is considered severely affected as well as vulnerable
groups, which include (i) female headed households without support; (ii) disabled household
heads; (iii) poor households; (iv) children and the elderly headed households who are
landless and have no other means of support; (v) landless households; and (vi) ethnic
minorities. Therefore, that income restoration program implementation is not applied for the
project.
5. No public structure and historical or cultural place is affected by the project
implementation.
II. PROGRESS OF THE PROJECT IMPLEMENTATION
6. There are two contractors carrying out the construction for the Cau Bong - Hoc Mon -
Binh Tan 220kV TL project that are the PCC1 and PCC3.
7. In order to ensure the construction progress of the towers, for this quarter period, the
contractors have fastened almost construction items of the construction activities of both
projects include excavation of towers’ foundation and tower erection.
8. The construction works of the Cau Bong - Hoc Mon - Binh Tan 220kV TL was kick-
started in late February 2014. As the construction and installation progress, up to the end of
June 2016, the works carried out by the two contractors of PCC1 and PCC3 have been
under the planned progress as showed in the table below.
Table 3: Construction works up to July 2016
Item Activities Unit Design
volume
Construction
volume
Completion
rate
1 Foundation excavation Tower foundation 59 59 100%
2 Foundation concretion Tower foundation 59 56 94.5%
3 Backfilling Tower foundation 59 56 94.5%
4 Grounding for tower Tower 59 56 94.5%
5 Tower erection Tower 59 56 94.5%
6 Cable stringing m 15,940 12,640 79.3%
9. The contractor stringed cable at the positions: In Cu Chi District from 500KV Cau
Bong Subsation to position 27; In Hoc Mon District from position 28 to 34.
10. Currently, to meet with the progress of the construction works, at almost all positions,
the contractors and AHs have signed an agreement in which the contractor pays AHs in
advance to support for their affected land and assets and get site handover for construction
of tower foundation. It was expected to complete the project construction in September 2016.
III. DETAILED ACTIVITIES UNDERTAKEN
3.1 Progress of Safeguard Policy Implementation
11. The updated RP of the project was approved by ADB in July 2014. The updated RP
was established based on result of DMS and the approved resettlement policy framework
that was established during RP preparation stage. The policy framework is consistent with
the governing policies of the REMDF concurred by ADB and NPT that were applied in all TL
projects of the Power Transmission Investment Program.
2sd
Quarter, 2016 - Internal Monitoring Report
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 7
12. For the Cau Bong - Hoc Mon - Binh Tan 220kV TL, the Resettlement Plan is carried
out following its steps conforming to the project’s policy, and the progress of RP implementation is described as below.
13. Detail measurement survey: Until now, DCSCCs have surveyed DMS completely
for all AHs who were affected by land acquisition at foundation positions and restricted land
use within RoW. Details of DMS will be described in 3.3 "Detailed measurement survey and
Entitlement.
14. Legal verification of Records: DCSCCs and commune people’s committee have reviewed legal ownership completely since June 2015 for 221/221 belonging to Cu Chi
District, 432/432 AHs belonging to Hoc Mon District and 362/362 AHs at District 12.
15. Price survey and appraisal: Until the fourth quarter of 2015, the replacement price
survey has been conducted completely by price appraisal consultants. This price has been
determined again by Districts’ compensation site clearance committee and submitted to
DONRE and City People’s Committee for appraising and approving. On December 10th
2015, Ho Chi Minh City People’s Committee issued Decision No. 6762/QD-UBND on
approving land price adjustment coefficient plan for compensation for the 220KV Cau Bong –
Hoc Mon – Binh Tan in Cu Chi, Hoc Mon District and District 12.
16. Establishing for Compensation plan: Until present, the establishing for
compensation plan has been implemented in all Districts. The draft compensation plans have
been announced to AHs at all affected communes. On March 9th 2016, Cu Chi DPC issued
Decision No. 1494/QD-UBND on approving compensation, allowance and resettlement plan
for AHs of the 220KV Cau Bong – Hoc Mon – Binh Tân (section through Cu Chi District).
After that, on May 27th 2016, Hoc Mon District issued Decision No. 2878/QD-UBND on
approving compensation, allowance ans resettlement plan for households affected by the
project, particularly the section through Hoc Mon District. Currently, Hoc Mon and Cu Chi
DCSCC were adjusting specific compensation value of each AH to submit for approval
before compensation payment. After announcing the draft compensation plan and collecting
PAH’s opinions, DCSCC of District 12 has been revised that compensation plan. It is
expected to submit the plan to DPC for approval in July 2016.
17. The Asian Pacific Consultancy Joint Stock Company has conducted the second
independent monitoring of the project since February 2016.
18. Compensation payment: Until now, to meet with the progress of the construction
works, DCSCCs, SPMB and contractor cooperated and consulted agreements of affected
households for the project construction. The SPMB and contractors had paid in advance for
affected households before approved compensation plan (see Table 8). It is expected to
conduct compensation payment in July 2016.
2sd
Quarter, 2016 - Internal Monitoring Report
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 8
Table 4: RP implementation progress up to July 2016
RP Implementation Activities
Ho Chi Minh City
Cu Chi Dist. Hoc Mon Dist. District 12
Tan
Phu
Trung
Tan
Thanh
Dong
Binh
My
Dong
Thanh
Thoi
Tam
Thon
Tan
Chanh
Hiep
Tan
Thoi
Hiep
Information Disclosure and Public
Consultation 100% 100% 100% 100% 100% 100% 100%
Detailed Measurement Survey 100% 100% 100% 100% 100% 100% 100%
Compensation Plan preparation 100% 100% 100% 100% 100% 100% 100%
Consultation and Counseling with
the APs on compensation plan 100% 100% 100% 100% 100% 100% 100%
Compensation Plan finalization
and submission for approval 100% 100% 100% 100% 100% 80% 80%
Compensation Plan verification
and approval 100% 100% 100% 100% 100% 0% 0%
Compensation Payment 0% 0% 0% 0% 0% 0% 0%
Site Clearance 100% 100% 94.5%
Independent Monitoring* Second monitoring
3.2 Information Disclosure, Public Consultation and Participation
19. In compliance with GoV’s Land Law 2013 (Article 48, Article 67, and Article 69), SPS (2009) and ADB’s Public Communication Policy: Disclosure and Exchange of Information
(2011), the SPMB, as representative of NPT in Southern Vietnam, promotes the active
participation of the Project-based stakeholders. They have been identified during the series
of disclosures and public consultations at District, commune and village levels, including the
District level DSCCs, CPCs, mass organizations, non-AP residents, and the APs.
20. In the previous quarter, Cu Chi and Hoc Mon District organized meetings with AHs for
announcement of draft compensation plan from early of March to end of March 2016. In this
quarter, District 12 also organized meetings with AHs to announce the draft compensation
plan in May 2016. The summary of dissemination contents is described as below:
i. Scope of project, right-of-way, and location of towers;
ii. Scope of land acquisition; alternatives of land acquisition mitigation; land acquisition
for construction of tower foundations and land use restriction under ROW.
iii. Entitlements of affected households/community; gender and ethnic minority policies
and strategies;
iv. Calculating sheet of compensation value of each AHs based on result of DMS and
project’s entitlement policies for AHs.
2sd
Quarter, 2016 - Internal Monitoring Report
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 9
21. During the dissemination of the draft compensation plan, AHs were introduced to
review their compensation calculating sheet. AHs could comment or complain if their benefits
were not ensured. Besides, AHs were also distributed a form for writing their comments and
send it to competence agencies for resolving. Here under is the summary of feedback
contents of AHs and local authorities:
i. Almost all AHs agreed with draft compensation plan and had no comments; AHs have
agreed with compensation and allowance policies that applied to calculate
compensation for them.
ii. Ahs suggest that the width of ROW and methods to determine affected assets under
ROW be informed.
iii. AHs requested to submit compensation plan to competence agencies for approving
as soon as possible because AHs have waited so long for the compensation.
22. DCSCCs, resettlement consultant and representatives of SPMB were consulted
about the above-mentioned issues of concerns and proposals of the APs and then clearly
explained and discussed at the meetings in terms of project policies, entitlements as well as
obligations of the APs.
Table 5: Dates of meeting on announcing compensation plan
Communes Dates of
Consultations
Number of Participants
Total Male Female
Tan Phu Trung March 11th 2016 49 28 21
Tan Thanh Dong March 11th 2016 49 31 18
Binh My March 14th 2016 92 51 41
Dong Thanh March 10th 2016 46 27 19
Thoi Tam Thon March 9th 2016 69 45 24
Tan Chanh Hiep May 6th 2016 57 38 19
Tan Thoi Hiep May 6th 2016 43 25 18
Total 405 245 160
3.3 Detailed Measurement Survey and Entitlement
23. Detailed Measurement Survey (DMS) was carried out from the middle of June 2014.
It was completed in the end of June 2014. DCSCCs and commune people’s committee reviewed legal ownership of APs’ property for 221/221 (100%) belonging to Cu Chi District,
432/432 (100%) AHs belonging to Hoc Mon District and 362/362 (100%) AHs in District 12.
The detailed measurement survey progress is described in the Table below:
Table 6: Summary of the detailed measurement survey in Districts
No. Disitrict
Surveyed Records verification
Foundation RoW
HHs % HHs % Records %
2sd
Quarter, 2016 - Internal Monitoring Report
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 10
1 Cu Chi 56 100% 189 100% 221 100%
2 Hoc Mon 29 100% 416 100% 432 100%
3 District 12 31 100% 362 100% 362 100%
Total 116 100% 967 100% 1,015 100%
24. The DMS was implemented with the participation of many stakeholders such as
representatives of DCSCC, SPMB, head of villages, cadastral officer of affected commune,
and APs.
25. During DMS, enumeration was conducted fully and exactly for all lost land and assets
on land of the AHs and affected communities. The results of the numeration were publicly
disclosed and posted at communes’ offices for AHs to recheck and complain for correction (if
any). APs had been announced the schedule for DMS and required attending, so almost all
of APs attended in the detailed measurement survey. After DMS, APs rechecked their
affected assets and signed the DMS minutes. They were provided with a copy of the minutes
of DMS for storing. So far, no households complained about the results of the DMS. The
DMS progress is described in the table below.
Table 7: DMS implementation progress in affected communes
District Commune Detailed Measurement Survey
Starting date Finishing date
Cu Chi
Tan Phu Trung 15/6/2014 24/6/2014
Tan Thanh Dong 15/6/2014 24/6/2014
Binh My 15/6/2014 24/6/2014
Hoc Mon Dong Thanh 15/6/2014 24/6/2014
Thoi Tam Thon 15/6/2014 24/6/2014
District 12 Tan Chanh Hiep 15/6/2014 24/6/2014
Tan Thoi Hiep 15/6/2014 24/6/2014
26. Price survey and appraisal: Ho Chi Minh City People’s Committee issued Decision
No. 6762/QD-UBND dated December 10th 2015 on approving land price adjustment
coefficient plan for compensation, allowance for the 220KV Cau Bong – Hoc Mon – Binh Tan
in Cu Chi, Hoc Mon District and District 12.
3.4 Compensation Payment and Support
In Hoc Mon and Cu Chi District, although the plan of compensation and support has been
approved but DCSCCs need to re-adjust the exact compensation value of each AH before
compensation payment. Therefore, until now, the compensation payment was not done. The
compensation payment is expected to conduct in July 2016. However, to meet with the
progress of the construction works, at almost all positions, SPMB, contractors and AHs have
signed an agreement in which the SPMB pays AHs in advance to support for their affected
land and assets and get site handover for construction of tower foundation and stringing
cable. So far, The SPMB and contractors have paid in advance to 51 AHs for construction of
towers and cable stringing, with a total amount of VND 18,154,740,471. The status of
compensation payment for AHs is described in the table below.
Table 8: Situation of payment in advance
2sd
Quarter, 2016 - Internal Monitoring Report
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 11
No District/Commune Amount (VND)
(Until the previous quarter)
Amount (VND) (In this quarter)
No of AHs who have received
compensation in advance
I Cu Chi District 1,052,090,000 2,100,000,000 10
1.1 Tan Phu Trung 18,024,000 1
1.2 Tan Thanh Dong 620,000,000 2,100,000,000 4
1.3 Binh My 414,066,000 5
II Hoc Mon District 6,923,568,000 1,942,266,500 25
2.1 Dong Thanh 5,018,000,000 303,000,000 10
2.2 Thoi Tam Thon 1,905,568,000 1,639,266,500 15
III District 12 6,136,815,971 3,112,132,896 16
3.1 Tan Chanh Hiep 1,705,541,971 146,712,896 7
3.2 Tan Thoi Hiep 4,431,274,000 2,965,420,000 9
Total 14,112,473,971 4,042,266,500 51
3.5 Land Acquisition
27. The results of the DMS indicate that there is no AP that has to be relocated. Since the
updated RP has been approved, the land acquisition activities are implemented based on the
agreement among AHs, SPMB and contractors for handing over land in advance for tower
foundation construction and cable stringing. AHs were paid compensation in advance and
land handed over to contractors.
28. Up to now, although compensation payment are not done yet, all land areas (100% of
positions) have been handed over to the contractors for tower construction (including: 32/32
towers in Cu Chi District, 16/16 towers in Hoc Mon and 11/11 towers in District 12) and
98.1% of land has been handed over for for cable stringing. Present, SPMB, DSCCs and
contractors keep negotiating with AHs for handing over land for stringing cable.
3.6 Issue Concerning Gender
29. The gender objective is to help the AHs, including both men and women, participate
in the implementation of RP and benefit equitably from achievements of that development.
The gender strategy in the stage of implementation of the RP includes the following:
- Both men and women are encouraged to participate in DMS. They participated in
DMS and spoke out their opinions about the implementation process of detailed
measurement survey;
- The Project have been working closely with the District women's unions,
ward/commune women's unions to mobilize the participation of women in all
activities of RP implementation (public consultation through questionnaires,
people’s meetings...). They raised concern issues of women to implementation process of compensation, allowance, resettlement and site clearance. Thence,
they suggested solutions to redress these issues to ensure women’s benefits in all activities of RP implementation;
- Women were invited to participate in all public meetings in which at least 30% of
the participants must be women. So far, in almost public meeting women have
participated and spoken out their opinions;
2sd
Quarter, 2016 - Internal Monitoring Report
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 12
- The payment of compensation and assistance in cash will be given to the affected
households in the presence of both husbands and wives; In case, husbands or
wives are absent, the compensation payment is carried out only when the person
who wishes to receive the compensation can provide a proxy letter of his/her
spouse and the confirmation of local authorities.
- LURCs, which are newly granted, should name both husband and wife.
30. During the RP implementation, gender strategy received considerable attention.
Public consultation was organized to ensure at least 30% participants would be women.
31. In the meetings that were organized at affected communes for announcement of
compensation plan in the previous quarter and this quarter there were at least 30% women
participants. They expressed opinions for issues that mentioned in draft compensation
allowance plan (the summary of comments is described in 3.2 “information disclosure and public consultation”).
3.7 Grievances Redress Mechanism
32. During the information disclosure and public consultation campaign, the resettlement
consultant and SPPMB disclosed to the AHs the procedures and steps of logging complaints
and grievance redress mechanism by four steps based on the principles of publicity,
democracy, protection of rights and interests of the APs so that they can understand and
take actions when in need.
33. The status of complaints and redress until the end of this quarter is described as
below:
Table 9: Summary of resolving until the end of this quarter
Time Complaint contents Resolving status
By the
previous
quarter
At position 43, Mr. Pham Van Luc
requested that the compensation
price for his land be 20 million/m2.
He also requested to transfer the
land use purpose of the whole
affected land plot from agricultural
land to residential land.
Hoc Mon DCSCC, SPMB, contractor and
people's committee of project communes
have cooperated for negotiating with the
household to allow constructing project.
Until now, the AH has agreed to sign
agreement minutes to hand over the
land to contractor for project
construction. However, he has still
complained and waited for resolving.
The Hoc Mon DCSCC has been
considering the complaint and looking for
a reasonable redress option.
This quarter
On the June 29th 2016, the
household of Mr. Nguyen Ba Truu
located at Thoi Tam Thon
Commune sent a complaint to
Hoc Mon DCSCC about the land
plot under dispute with the
household of Mr. Le Dai Hung
concerning land use rights and
Currently, Hoc Mon DCSCC is
considering the complaint and looking for
a solution.
2sd
Quarter, 2016 - Internal Monitoring Report
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 13
Time Complaint contents Resolving status
requested that there be no
compensation to Mr. Le Dai Hung
for the land plot at issue.
34. Besides AHs’ the complaints, during the RP implementation some AH’s difficulties
arose. The summary of specific comments is described as below:
- Ahs suggest that the width of ROW and methods to determine affected assets under
ROW be informed.
- AHs requested to submit compensation plan to competence agencies for approving as
soon as possible because AHs have waited so long for the compensation.
35. DCSCCs, resettlement consultant and representatives of SPMB were consulted
about the above-mentioned issues of concerns and proposals of the APs and then explained
and discussed at the meetings in terms of project policies, entitlements as well as obligations
of the APs.
IV. CONCLUSION AND PLAN FOR NEXT QUARTER
4.1 Conclusion
36. The RP implementation in Ho Chi Minh City had been delayed for a long time
because Ho Chi Minh City People's Committee promulgated the regulation of compensation,
support and land clearance late. However, currently these issues have been resolved.
DCSCCs have prepared compensation plan and announced to APs. Specially, Hoc Mon and
Cu Chi DPC issued Decisions on approving compensation plan. Compensation payment was
expected to conduct in July 2016 at all Districts.
37. The DMS has been completed. District’s division of natural resources and environment have determined completely the legal ownership, reviewed the origin of land
title and relevant legal documents for formulating the compensation plan.
38. SPPMB in order to keep the project progress has in cooperation with the contractors
worked with DPCs and CPCs for negotiating with APs for implementing the construction in
advance. Until the end of this quarter, SPMB has paid in advance for 51 AHs with amount of
VND 18,154,740,471.
39. Up to now, although compensation payment are not done yet, all land areas (100% of
positions) have been acquired for tower construction and 98.1% of land has been handed
over for cable stringing. At present, SPMB, DSCCs and contractors keep negotiating with
AHs for handing over land for stringing cable. Besides, this issue has been mentioned in due
diligence report and independent monitoring report of project. These reports also mentioned
corrective activities for it and received approval of ADB.
40. AHs’ complaints have been received and effectively and timely resolved.
4.2 Recommendations
41. In order to the implementation of compensation, support and resettlement for the
APs is well-timed and effective, the consultant has some recommendations as following:
2sd
Quarter, 2016 - Internal Monitoring Report
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 14
(i) DCSCCs need to speed up compensation payment progress and at the same time,
ensure all AHs will fully receive compensation for all their affected assets.
(ii) District 12 should speed up submitting compensation plan to DPC for appraisal and
approval.
(iii) SPMB and DSCCS need to carry out surveys to assess impacts of land acquisition
before compensation. Thence, there should be accordant corrective plans for APs if
necessary.
(iv) SPMB need to continue cooperating closely with local stakeholders to consult and
negotiate with APs about entitlement policies of the project. At the same time, it is
necessary to compensation in advance for APs to construct project while waiting for
approved compensation plan and official compensation payment for APs.
4.3 Plan for Next Quarter
42. Cu Chi and Hoc Mon DCSCC should pay compensation to AHs as soon as possible.
43. In case necessary, public meeting activities will be continuously carried out to ensure
that affected households, concerns and grievances are addressed and resolved in a timely
and satisfactory manner.
44. SPPMB and contractor need to push up the payment of compensation and supports
in advance for cable stringing to ensure the project progress.
45. DCSCCs and relevant agencies will consider to resolve completely AHs’ complaints to ensure efficiently and timely of complaint resolving.
2sd
Quarter, 2016 - Internal Monitoring Report
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 15
V. APPENDICES
5.1 Appendix 1. Minutes of announcement meetings of compensation plan
2sd
Quarter, 2016 - Internal Monitoring Report
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 16
2sd
Quarter, 2016 - Internal Monitoring Report
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 17
2sd
Quarter, 2016 - Internal Monitoring Report
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 18
2sd
Quarter, 2016 - Internal Monitoring Report
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 19
2sd
Quarter, 2016 - Internal Monitoring Report
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 20
2sd
Quarter, 2016 - Internal Monitoring Report
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 21
2sd
Quarter, 2016 - Internal Monitoring Report
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 22
2sd
Quarter, 2016 - Internal Monitoring Report
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 23
2sd
Quarter, 2016 - Internal Monitoring Report
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 24
2sd
Quarter, 2016 - Internal Monitoring Report
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 25
2sd
Quarter, 2016 - Internal Monitoring Report
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 26
2sd
Quarter, 2016 - Internal Monitoring Report
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 27
2sd
Quarter, 2016 - Internal Monitoring Report
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 28
5.2 Appendix 2. List of AHs who have received payment in advance
No. Name Tower
location Amount (VND) Commune
I Until the end of 2015
1 Đặng Phước Long 14 20,000,000 Tân Thạnh Đông
2 Phạm Văn Minh 27 150,000,000 Binh Mỹ
3 Nguyễn Thị Đào 28 200,000,000 Đông Thạnh
4 Nguyễn Văn Nhạn 30 30,000,000 Đông Thạnh
5 Lê Văn Cắt 32 30,000,000 Đông Thạnh
6 Trần Văn Út 33 100,000,000 Đông Thạnh
7 Huỳnh Văn Hít 34 150,000,000 Đông Thạnh
8 Trần Mỹ Dung 39 200,000,000 Thới Tam Thôn
9 Huỳnh Ngọc Tấn 1; 3A 144,688,000 -
10 Lâm Văn Đỗ 5 30,000,000 -
11 Đỗ Hòa 9 112,860,000 -
25 350,000,000 -
12 Trần Thị Phùng 48 170,000,000 -
13 Trần Văn Nhanh
49
40,000,000 -
14 Bùi Thị Én 29,260,000 -
15 Lê Thành Chung 110,000,000 -
16 Nguyễn Thị Cang
51
100,000,000 -
17 Trần Văn Hải 100,000,000 -
18 Nguyễn Văn Xuân 18,760,000 -
19 Trần Thị Nuôi 54 400,000,000 -
SUBTOTAL 2,485,568,000
II Until the end of the previous quarter
Củ Chi 882,090,000
1 Lê Văn Tùng 17;21 107,000,000 Bình Mỹ
2 Nguyễn Thị Mọng Điệp VT18 600,000,000 Tân Thạnh Đông
3 Đỗ Hòa VT19
4 Trần Thị Sáu VT16
5 Trần Thị Liễu 3,066,000 Bình Mỹ
6 Nguyễn Thị Yến Như VT13 18,024,000 Tân Phú Trung
7 Đặng Thị Nghễ VT17-21 130,000,000 Bình Mỹ
8 Trần Văn Đạo VT17-21 24,000,000 Bình Mỹ
Hốc Môn 4,608,000,000 -
1 Đặng Văn Trước VT37-47 100,000,000 Thới Tam Thôn
2 Nguyễn Văn Dũng VT29-37 3,000,000,000 Đông Thạnh
3 Nguyễn Văn Bền VT29-37 400,000,000 Đông Thạnh
4 Nguyễn Hữu Thắng VT29-37 228,000,000 Đông Thạnh
5 Phạm Văn Lức VT43
6 Nguyễn Văn Điệp VT41-43
7 Trần Văn Lo VT33
8 Đặng Trường Sơn VT29 880,000,000 Đông Thạnh
Quận 12 6,136,815,971 0
1 Bùi Đức Thành VT37-47 106,665,936 Tân Chánh Hiệp
2 Lưu Văn Nhẹ VT37-47 1,006,057,549 Tân Chánh Hiệp
2sd
Quarter, 2016 - Internal Monitoring Report
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 29
No. Name Tower
location Amount (VND) Commune
3 Nguyễn Hữu Đồng VT37-47 78,247,250 Tân Chánh Hiệp
4 Thái Thị Hồng VT37-47 46,697,931 Tân Chánh Hiệp
5 Nguyễn Viết Ánh VT37-47 467,873,305 Tân Chánh Hiệp
6 Lương Văn Long VT37-47
7 Nguyễn Văn Triển VT37-47
8 Đỗ Văn Bắt VT37-47
9 Nguyễn Văn Trác VT37-47
10 Nguyễn Văn Điệp VT37-47
11 Huỳnh Thị Hoa VT37-47 530,000,000 Tân Thới Hiệp
12 Trần Viết Thắng VT47 58,274,000 Tân Thới Hiệp
13 Nguyễn Văn Giác VT46 2,600,000,000 Tân Thới Hiệp
14 Trịnh Xuân Bôn VT47-52 210,000,000 Tân Thới Hiệp
15 Nguyễn Minh Cương VT47-52 50,000,000 Tân Thới Hiệp
16 Trần Thị Cúc VT47-52 983,000,000 Tân Thới Hiệp
SUBTOTAL 11,626,905,971
III Until the end of this quarter
Củ Chi 2,100,000,000
1 Lê Văn Tùng 17;21 Bình Mỹ
2 Nguyễn Thị Mọng Điệp VT18 Tân Thạnh Đông
3 Đỗ Hòa VT19 400,000,000 Tân Thạnh Đông
4 Trần Thị Sáu VT16 1,700,000,000 Tân Thạnh Đông
5 Trần Thị Liễu Bình Mỹ
6 Nguyễn Thị Yến Như VT13 Tân Phú Trung
7 Đặng Thị Nghễ VT17-21 Bình Mỹ
8 Trần Văn Đạo VT17-21 Bình Mỹ
Hốc Môn 1,942,266,500 -
1 Đặng Văn Trước VT37-47 Thới Tam Thôn
2 Nguyễn Văn Dũng VT29-37 Đông Thạnh
3 Nguyễn Văn Bền VT29-37 Đông Thạnh
4 Nguyễn Hữu Thắng VT29-37 Đông Thạnh
5 Phạm Văn Lức VT43 359,266,500 Thới Tam Thôn
6 Nguyễn Văn Điệp VT41-43 1,280,000,000 Thới Tam Thôn
7 Trần Văn Lo VT33 303,000,000 Đông Thạnh
8 Đặng Trường Sơn VT29 Đông Thạnh
Quận 12 3,112,132,896 0
1 Bùi Đức Thành VT37-47 Tân Chánh Hiệp
2 Lưu Văn Nhẹ VT37-47 Tân Chánh Hiệp
3 Nguyễn Hữu Đồng VT37-47 Tân Chánh Hiệp
4 Thái Thị Hồng VT37-47 Tân Chánh Hiệp
5 Nguyễn Viết Ánh VT37-47 Tân Chánh Hiệp
6 Lương Văn Long VT37-47 116,712,896 Tân Chánh Hiệp
7 Nguyễn Văn Triển VT37-47 30,000,000 Tân Chánh Hiệp
8 Đỗ Văn Bắt VT37-47 430,141,000 Tân Thới Hiệp
9 Nguyễn Văn Trác VT37-47 55,279,000 Tân Thới Hiệp
2sd
Quarter, 2016 - Internal Monitoring Report
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 30
No. Name Tower
location Amount (VND) Commune
10 Nguyễn Văn Điệp VT37-47 2,480,000,000 Tân Thới Hiệp
11 Huỳnh Thị Hoa VT37-47 Tân Thới Hiệp
12 Trần Viết Thắng VT47 Tân Thới Hiệp
13 Nguyễn Văn Giác VT46 Tân Thới Hiệp
14 Trịnh Xuân Bôn VT47-52 Tân Thới Hiệp
15 Nguyễn Minh Cương VT47-52 Tân Thới Hiệp
16 Trần Thị Cúc VT47-52 Tân Thới Hiệp
SUBTOTAL 7,154,399,396
TOTAL 18,154,740,471
2sd
Quarter, 2016 - Internal Monitoring Report
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 31
5.3 Appendix 3. Decision on approving of adjustment coefficient plan of land price
for calculating compensation, support for AHs
2sd
Quarter, 2016 - Internal Monitoring Report
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 32
2sd
Quarter, 2016 - Internal Monitoring Report
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 33
2sd
Quarter, 2016 - Internal Monitoring Report
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 34
2sd
Quarter, 2016 - Internal Monitoring Report
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 35
2sd
Quarter, 2016 - Internal Monitoring Report
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 36
2sd
Quarter, 2016 - Internal Monitoring Report
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 37
2sd
Quarter, 2016 - Internal Monitoring Report
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 38
2sd
Quarter, 2016 - Internal Monitoring Report
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 39
2sd
Quarter, 2016 - Internal Monitoring Report
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 40
5.4 Appendix 4. Decision on approving of compensation plan, section through Cu
Chi District
2sd
Quarter, 2016 - Internal Monitoring Report
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 41
2sd
Quarter, 2016 - Internal Monitoring Report
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 42
2sd
Quarter, 2016 - Internal Monitoring Report
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 43
2sd
Quarter, 2016 - Internal Monitoring Report
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 44
2sd
Quarter, 2016 - Internal Monitoring Report
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 45
2sd
Quarter, 2016 - Internal Monitoring Report
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 46
2sd
Quarter, 2016 - Internal Monitoring Report
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 47
5.5 Appendix 5. Some pictures from Public Consultation Meetings
Tan Phu Trung Commune
Tan Thanh Dong Commune
2sd
Quarter, 2016 - Internal Monitoring Report
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 48
Binh My Commune
Thoi Tam Thon Commune
2sd
Quarter, 2016 - Internal Monitoring Report
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 49
Tan Chanh Hiep Ward
Tan Thoi Hiep Ward