VIE: Ha Noi and Ho Chi Minh City Power Grid Development ...passing Vinhomes Riverside urban area,...

15
RESETTLEMENT DUE DILIGENCE REPORT Project Number: 46391 - 001 November 2018 VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project Prepared by Hanoi City Power Corporation, Electricity of Vietnam for Asian Development Bank

Transcript of VIE: Ha Noi and Ho Chi Minh City Power Grid Development ...passing Vinhomes Riverside urban area,...

Page 1: VIE: Ha Noi and Ho Chi Minh City Power Grid Development ...passing Vinhomes Riverside urban area, Long Bien District Project” for earthing 110kV power system in Long Bien District.

RESETTLEMENT DUE DILIGENCE REPORT

Project Number: 46391 - 001

November 2018

VIE: Ha Noi and Ho Chi Minh City Power Grid

Development Sector Project

Prepared by Hanoi City Power Corporation, Electricity of Vietnam for Asian Development Bank

Page 2: VIE: Ha Noi and Ho Chi Minh City Power Grid Development ...passing Vinhomes Riverside urban area, Long Bien District Project” for earthing 110kV power system in Long Bien District.

Resettlement Due Diligence 110kV Connection line to Sai Dong Industrial Complex Subproject

2

Resettlement Due Diligence

November 2018

Vietnam: Hanoi and Ho Chi Minh City Power Grid

Development Sector Project

(EVN HANOI: 110 kV Connecting line to Sai Dong Industrial Complex)

Prepared by the Hanoi Power Corporation (EVN HANOI) for the Asian

Development Bank (ADB)

Page 3: VIE: Ha Noi and Ho Chi Minh City Power Grid Development ...passing Vinhomes Riverside urban area, Long Bien District Project” for earthing 110kV power system in Long Bien District.

Resettlement Due Diligence 110kV Connection line to Sai Dong Industrial Complex Subproject

3

ABBREVIATIONS

ELECTRICAL TERMINOLOGY

kV (kilovolt) - 1,000 volts MW (Megawatt) - 1,000 kW MVA (Megavolt-ampere) - 1,000 kVA Transmission System - 500 kV, 220 kV, 110 kV lines Medium Voltage Distribution (MV) - 35 kV, 22 kV or 10 kV lines supplying distribution substations Low Voltage Distribution (LV) - 400/230 V distribution and service lines Load Factor - Ratio of average power demand to maximum power demand Electrical Losses - Difference between energy delivered and energy sent out

REMARKS

In this report, "$" refers to US dollars.

This Resettlement Due Diligence is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. Your attention is directed to the “terms of use” section of this website.

In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the ADB does not intend to make any judgments as to the legal or other status of any territory or area.

ADB : Asian Development Bank

AH : Affected Household

EVN : Vietnam Electricity

EVN HANOI : Hanoi Power Corporation

EVNNPT : National Power Transmission Corporation

GoV : Government of Vietnam

LFDC : Land Fund Development Center

NPMB : Northern Power Projects Management Board

SS : Substation

TEP : Transmission Efficiency Project

WB : World Bank

WPC : Ward People’s Committee

Page 4: VIE: Ha Noi and Ho Chi Minh City Power Grid Development ...passing Vinhomes Riverside urban area, Long Bien District Project” for earthing 110kV power system in Long Bien District.

Resettlement Due Diligence 110kV Connection line to Sai Dong Industrial Complex Subproject

4

TABLE OF CONTENTS

ABBREVIATIONS ........................................................................................................... 3

ELECTRICAL TERMINOLOGY ....................................................................................... 3

REMARKS....................................................................................................................... 3

A. Introduction ............................................................................................................... 5

B. Subproject Description .............................................................................................. 5

C. Methodology on Preparation of Resettlement Due Diligence .................................... 6

D. Impacts of Subproject ............................................................................................... 7

E. Current status of resident and infrastructure in Project area ..................................... 8

F. Compensation and implementation plan ................................................................. 10

G. Conclusions ............................................................................................................ 10

H. Annexes .................................................................................................................. 12

LIST OF FIGURES

Figure 1. Map of subproject location ............................................................................... 6

Figure 2. Current status of Project area ”Construction of technical facility for installment of 110kV underground cables section passing Vinhomes Riverside 2 urban area, Long Bien District Project” ................................................................................................................ 8

Figure 3. Gate of 220kV Long Bien SS .......................................................................... 9

Figure 4. Area for construction of 110kV Sai Dong 2 SS .............................................. 10

Page 5: VIE: Ha Noi and Ho Chi Minh City Power Grid Development ...passing Vinhomes Riverside urban area, Long Bien District Project” for earthing 110kV power system in Long Bien District.

Resettlement Due Diligence 110kV Connection line to Sai Dong Industrial Complex Subproject

5

A. Introduction

1. Long Bien District and Gia Lam District are currently supplied with electricity from

regional substations including 110kV E1 - Dong Anh, E2 - Gia Lam, E15 - Sai Dong. This

is an area with rapid loading development due to the appearance of industrial parks, urban

areas, factories, while the existing substations are overloaded. Therefore, in order to meet

the demand and orientation of power grid planning, the Hanoi Municipal People's

Committee issued Decision No. 1940/QD-UBND dated 21/04/2016 on the promulgation

of the power grid development plan period 2016 – 2020, in which 110 kV Sai Dong

Industrial complex SS ( 110kV Sai Dong 2 SS) with capacity of 63MVA, 110/22kV will

supply electricity for Sai Dong Industrial Complex and Long Bien District.

B. Subproject Description

Objectives

2. The subproject was constructed with the purpose:

• Supply 110kV input power for 110kV Sai Dong 2 SS.

• Exploit loading of 220kV Long Bien SS.

• Enhance circuit connection, improve reliability of power supply.

• Reduce the leakage on the system, contribute to the efficiency of power

production and business of EVN

Alignment and feature of the subproject

3. 110kV underground cable supplying power to 110kV Sai Dong 2 SS converses

wards including: Giang Bien, Viet Hung, Phuc Loi in Long Bien District, Hanoi with a total

length of about 3.770m. The route mainly the cable line goes inside a existing cable trench

along the road and sidewalks of Hoi Xa, Doan Khue and Tran Danh Tuyen streets.

Page 6: VIE: Ha Noi and Ho Chi Minh City Power Grid Development ...passing Vinhomes Riverside urban area, Long Bien District Project” for earthing 110kV power system in Long Bien District.

Resettlement Due Diligence 110kV Connection line to Sai Dong Industrial Complex Subproject

6

Figure 1. Map of subproject location

4. Main features

Voltage level 110kV

Number of circuits 02

Starting point 02 bays of 220kV Long Bien SS

Ending point 02 bays of transmission line of 110kV Sai Dong 2 SS

Length 3770m

UGC Single phase, core copper, cross section 1,200mm2, XLPE insulation.

Layout type Combining various types of cable layout, the main one is trefoil,

special ones are flat.

Laying cable

Configuration

Set in HDPE pipe, buried directly in the ground

Telecommunication

fiber cable

A NMOC 24 fiber cable along the 110kV underground cable

Fiber cable controlling

cable temperature

Fiber cable inside the bearing cable (only phase B)

Temperature control

equipment

Distributed Thermal System was invested in 220kV Long Bien SS

Earthing Mixed, sheath crossing and earthing one side

Facility (Bending cable

trench, connecting

cable trench)

Reinforced concrete (invested by other project)

C. Methodology on Preparation of Resettlement Due Diligence

5. A number of research methods were utilized, including:

Page 7: VIE: Ha Noi and Ho Chi Minh City Power Grid Development ...passing Vinhomes Riverside urban area, Long Bien District Project” for earthing 110kV power system in Long Bien District.

Resettlement Due Diligence 110kV Connection line to Sai Dong Industrial Complex Subproject

7

• Desk study method: the Consultant reviewed Feasibility Study Report for

subproject features and scale

• Some consultation meetings were conducted to collect information and data

related to the project from the stakeholders about the 110 kV Connecting line to

Sai Dong Industrial Complex

• Field trips were conducted to observe and assess the project impacts.

D. Impacts of Subproject

6. The Project only put the cable through the trench, the trench system is conducted in

02 following projects and not in the scope of Environment Impact Assessment. The project

cable has length of 3,770m divided into 02 sections, as following:

➢ Section 1: From 220kV Long Bien SS to the tower No.83, with length of 2,457m,

the cable converses through the trench system invested by “Construction of

technical facility for installment of 110kV underground cable from 220kV Long

Bien SS Project”.

➢ Section 2: From the tower No.83 to 110kV Sai Dong 2 SS with length of about

1.313, the cable converses through the trench system invested by

“Construction of technical facility for installment of 110kV underground cables

section passing Vinhomes Riverside urban area, Long Bien District Project”.

Status of Subproject area

7. Currently, the subproject area is under construction for cable trench system

belonging to scope of 02 projects: (1) Project 1 - Construction of technical facility for

installment of 110kV underground cable from 220kV Long Bien SS Project and (2) Project

02 Construction of technical facility for installment of 110kV underground cables section

passing Vinhomes Riverside urban area, Long Bien District Project” for earthing 110kV

power system in Long Bien District.

Current status of cable trench system under construction (for 02 aboved projects)

8. The aboved cable trench in section 1 and 2 has width x depth of 2 x 1.8m. The

project cable alignment includes 11 connecting cable trenchs and 02 bending cable

trenchs are placed in right positions according to the design from 220kV Long Bien SS to

110kV Sai Dong 2 SS.

9. Cable trench system belongs to 02 aboved projects is under construction and

expected to be competed in Quarter IV/2018, detailed schedule as following:

✓ Section 1 (2,457m): Currently, 35% of work has been done in the area of Viet

Hung ward, 65% of remaining work has not been constructed in Giang Bien and

Phuc Loi wards.

Page 8: VIE: Ha Noi and Ho Chi Minh City Power Grid Development ...passing Vinhomes Riverside urban area, Long Bien District Project” for earthing 110kV power system in Long Bien District.

Resettlement Due Diligence 110kV Connection line to Sai Dong Industrial Complex Subproject

8

✓ Section 2 (1,313m): At present, 40% of work has been completed in Giang Bien

ward, the remaining one (60%) in Viet Hung and Phuc Loi wards has not been

constructed.

Figure 2. Current status of Project area ”Construction of technical facility for

installment of 110kV underground cables section passing Vinhomes Riverside 2

urban area, Long Bien District Project”

E. Current status of resident and infrastructure in Project area

10. There are no people as well as structures in the Project area. The underground cable

system will be located in the existing cable trench system along the roadside and

pavements of the roads: The Xa, Doan Khue and Tran Danh Tuyen are invested in two

other projects, therefore, there is no permanently land acquisition impacts.

11. The project carried out the work of cable pulling at connecting cable trenchs and

bending cable trenchs along the underground cable alignment. The project cable system

is curled and placed right at the connecting trench, bending trench for convenience in

cable pulling. Therefore, the project does not occupy land permanently, the temporarily

occupied land is only the area at the head of each connecting trench according to the

construction schedule. The connecting trench has an area of about 10m2 is insignificant,

the occupancy time is short and only a few days in each construction phase, so it can be

considered that the project does not occupy the land temporarily.

12. 110kV Connection line to Sai Dong Industrial Complex Subproject connects and

transmits power between 220kV Long Bien SS and 110kV Sai Dong 2 SS. These two

subprojects are considered as connection infrastructures of 110kV Connection line to Sai

Dong Industrial Complex Subproject.

Page 9: VIE: Ha Noi and Ho Chi Minh City Power Grid Development ...passing Vinhomes Riverside urban area, Long Bien District Project” for earthing 110kV power system in Long Bien District.

Resettlement Due Diligence 110kV Connection line to Sai Dong Industrial Complex Subproject

9

Current status of 220kV Long Bien SS and 110kV Sai Song 2 SS

220kV Long Bien SS

13. The substation located in Giang Bien ward, Long Bien district, Hanoi and went into

operation since September 26, 2017. The SS includes 3 transformers 220/110/22kV-

250MVA, 02 transformers 220kV and 250 MVA were installed during phase 1. The SS

includes function parts such as equipment room, control room, distribution room,

attendant room, canteen, access road, parking lot… Currently, the SS is supplying for

220kV Dong Anh 1 transmission line and 220kV Dong Anh 2 transmission line.

14. 220kV Long Bien SS is considered as connection infrastructure of 110kV Connection

line to Sai Dong Industrial Complex Subproject.

Figure 3. Gate of 220kV Long Bien SS

15. 220kV Long Bien SS Subproject acquired 70.254m2 of agricultural land belonging

to 205 households in Giang Bien Ward, Long Bien District. Land acquisition has been

completed in March 2016 with total amount of 53.554.360.100 VND paid to 205

households.

16. According results of interviewing representatives of Northern Power Projects

Management Board (NPMB), Long Bien District Land Fund Development Center (LFDC),

affected households, Giang Bien Ward authority and results of final independent

monitoring report, there is no outstanding related to land acquisition, compensation of

subproject;

17. 220kV Long Bien SS is one of 05 subprojects under Transmission Efficiency Project

(TEP) financed by WB. Compensation, assistance and resettlement process of project

was conducted in accordance with Resettlement Plan of subproject1 - compliance with

policy on Involuntary Resettlement of WB (OP 4.12) and Land Law 2013 of GoV;

18. Due to the policy equivalent of two donors and there is no outstanding related to

involuntary resettlement of this subproject, therefore, it is not necessary to develop a

corrective action plan.

1 Resettlement Plan of 220kV Long Bien SS was prepared in 2015 by Power Engineering Consulting Joint Stock Company 1 (PECC1);

Page 10: VIE: Ha Noi and Ho Chi Minh City Power Grid Development ...passing Vinhomes Riverside urban area, Long Bien District Project” for earthing 110kV power system in Long Bien District.

Resettlement Due Diligence 110kV Connection line to Sai Dong Industrial Complex Subproject

10

110kV Sai Dong 2 SS

19. The SS located in Phuc Loi ward, Long Bien district, Hanoi. Current status of SS

construction site is vacant land, mainly grass and herbaceous plants. There is no river,

stream and pond passing through the area. There are no people living as well as

infrastructure in the SS area.

20. Sai Song 2 SS will be constructed financed by ADB loan, therefore, activities on

compensation, assistance and resettlement (if any) will be implemented according to ADB

policies.

Figure 4. Area for construction of 110kV Sai Dong 2 SS

F. Compensation and implementation plan

21. The project only pull cable through cable trench and there is no impact on land

acquisition and people incomes, therefore, compensation cost is not necessarily

calculated for the subproject.

22. The subproject is expected to implement by the end of 2018 and complete by the

beginning of 2019. EVN HANOI will inform ADB project activities through semi-annually

internal monitoring report.

G. Conclusions

23. The construction of underground cable connecting Long Bien SS with Sai Dong 2

SS will not cause permanent and temporary land acquisition impacts. There is no house,

Page 11: VIE: Ha Noi and Ho Chi Minh City Power Grid Development ...passing Vinhomes Riverside urban area, Long Bien District Project” for earthing 110kV power system in Long Bien District.

Resettlement Due Diligence 110kV Connection line to Sai Dong Industrial Complex Subproject

11

structure or public utility will be affected by the project. There is also no household affected

livelihood or income generated by the project implementation.

24. There is no people living and doing business in the subproject area, therefore the

subproject does not have impacts on livelihood or incomes of people.

25. According to the results of consultations with representatives of Project Owner of

220kV Long Bien SS, LFDC and 02 affected households, there is no outstanding on land

acquisition for 220kV Long Bien SS;

26. Due to the policy equivalent of two donors and there is no outstanding related to

involuntary resettlement of this subproject, therefore, it is not necessary to develop a

corrective action plan;

Page 12: VIE: Ha Noi and Ho Chi Minh City Power Grid Development ...passing Vinhomes Riverside urban area, Long Bien District Project” for earthing 110kV power system in Long Bien District.

Resettlement Due Diligence 110kV Connection line to Sai Dong Industrial Complex Subproject

12

H. Annexes

1. List of interviewees related to 220kV Long Bien SS

No. Full name Organization/Address

1 Do Duc Manh Head of Compensation office - NPMB

2 Vu Manh Quan Staff of Compensation office - NPMB

3 Nguyen Quoc Tuan Deputy director of Long Bien District LFDC

4 Bui Anh Tuan Vice president of Giang Bien WPC

5 Nguyen Thi Duc Affected household in Giang Bien Ward

6 Dao Van Nhung Affected household in Giang Bien Ward

2. List of public consultation participants

No. Full name Organization/Address Male Female

Giang Bien Ward

1 Pham Trung Kien Giang Bien Ward x

2 Dao Thi Chung Giang Bien Ward x

3 Ngo Minh Duc Giang Bien Ward x

4 Nguyen Duy Giang Giang Bien Ward x

5 Trinh Thi Hanh Giang Bien Ward x

6 Nguyen Thi Thuy Cau Giang Bien Ward x

7 Nguyen Tien Binh Giang Bien Ward x

8 Pham Thi Lien Giang Bien Ward x

9 Do Duc Hieu Giang Bien Ward x

10 Dinh Hoai Thanh Giang Bien Ward x

11 Nguyen Thi Phuong Lan Giang Bien Ward x

12 Nguyen Ngoc Hung Giang Bien Ward x

13 Ha Thi Nhu Quynh Giang Bien Ward x

14 Vu Duc Thuan Giang Bien Ward x

15 Nguyen Van Hoa Giang Bien Ward x

16 Nguyen Tien Luyen Giang Bien Ward x

17 Pham Van Du Giang Bien Ward x

18 Pham Thi Thuy Hang Giang Bien Ward x

Page 13: VIE: Ha Noi and Ho Chi Minh City Power Grid Development ...passing Vinhomes Riverside urban area, Long Bien District Project” for earthing 110kV power system in Long Bien District.

Resettlement Due Diligence 110kV Connection line to Sai Dong Industrial Complex Subproject

13

No. Full name Organization/Address Male Female

19 Nguyen Thi Hoai Giang Bien Ward x

20 Nguyen Cong Duc Giang Bien Ward x

21 Nguyen Manh Cuong Giang Bien Ward x

22 Nguyen Thi Huyen Trang Giang Bien Ward x

23 Nguyen Hong Nhung Giang Bien Ward x

24 Tran Quoc Huy Giang Bien Ward x

Phuc Loi Ward

1 Ha Huy Men Phuc Loi Ward x

2 Kieu Van Bao Phuc Loi Ward x

3 Duong Van Suc Phuc Loi Ward x

4 Nguyen Van Quyet Phuc Loi Ward x

5 Ngo Van Luong Phuc Loi Ward x

6 Pham Quang An Phuc Loi Ward x

7 Nguyen Dinh Do Phuc Loi Ward x

8 Nguyen Van Hoach Phuc Loi Ward x

9 Nguyen Duy Theu Phuc Loi Ward x

10 Nguyen Van Hao Phuc Loi Ward x

11 Ha Thi Nuong Phuc Loi Ward x

12 Duong Thi Dung Phuc Loi Ward x

13 Nguyen Thi Toan Phuc Loi Ward x

14 Duong Thi Mong Phuc Loi Ward x

15 Nguyen Thi Vach Phuc Loi Ward x

16 Le Thi Lien Phuc Loi Ward x

17 Pham Thi Thinh Phuc Loi Ward x

18 Le Van Diep Phuc Loi Ward x

19 Nguyen Van Tuy Phuc Loi Ward x

20 Nguyen Duy Khanh Phuc Loi Ward x

Viet Hung Ward

1 Dinh Quang Luan Viet Hung Ward x

2 Dang Van Vui Viet Hung Ward x

Page 14: VIE: Ha Noi and Ho Chi Minh City Power Grid Development ...passing Vinhomes Riverside urban area, Long Bien District Project” for earthing 110kV power system in Long Bien District.

Resettlement Due Diligence 110kV Connection line to Sai Dong Industrial Complex Subproject

14

No. Full name Organization/Address Male Female

3 Nguyen Duy Hung Viet Hung Ward x

4 Nguyen Kim Anh Viet Hung Ward x

5 Truong Duc Thao Viet Hung Ward x

6 Duong Van Hai Viet Hung Ward x

7 Tran Duc Tan Viet Hung Ward x

8 Tran Thi Thai Ha Viet Hung Ward x

9 Nguyen Dinh Khu Viet Hung Ward x

10 Do Tinh Viet Hung Ward x

11 Nguyen Van Tao Viet Hung Ward x

12 Oa Hanh San Viet Hung Ward x

13 Nguyen Thi Ngoc Quy Viet Hung Ward x

14 Nguyen Dinh Hung Viet Hung Ward x

15 An Manh Tung Viet Hung Ward x

16 Giap Thi Thanh Nhan Viet Hung Ward x

17 Nguyen Thi Thu Viet Hung Ward x

18 Truong Van Che Viet Hung Ward x

19 Nguyen Van Vong Viet Hung Ward x

20 Nguyen Van Tham Viet Hung Ward x

Page 15: VIE: Ha Noi and Ho Chi Minh City Power Grid Development ...passing Vinhomes Riverside urban area, Long Bien District Project” for earthing 110kV power system in Long Bien District.

Resettlement Due Diligence 110kV Connection line to Sai Dong Industrial Complex Subproject

15

3. Some photos of public consultation