RESETTLEMENT DUE DILIGENCE REPORT
Project Number: 46391 - 001
November 2018
VIE: Ha Noi and Ho Chi Minh City Power Grid
Development Sector Project
Prepared by Hanoi City Power Corporation, Electricity of Vietnam for Asian Development Bank
Resettlement Due Diligence 110kV Connection line to Sai Dong Industrial Complex Subproject
2
Resettlement Due Diligence
November 2018
Vietnam: Hanoi and Ho Chi Minh City Power Grid
Development Sector Project
(EVN HANOI: 110 kV Connecting line to Sai Dong Industrial Complex)
Prepared by the Hanoi Power Corporation (EVN HANOI) for the Asian
Development Bank (ADB)
Resettlement Due Diligence 110kV Connection line to Sai Dong Industrial Complex Subproject
3
ABBREVIATIONS
ELECTRICAL TERMINOLOGY
kV (kilovolt) - 1,000 volts MW (Megawatt) - 1,000 kW MVA (Megavolt-ampere) - 1,000 kVA Transmission System - 500 kV, 220 kV, 110 kV lines Medium Voltage Distribution (MV) - 35 kV, 22 kV or 10 kV lines supplying distribution substations Low Voltage Distribution (LV) - 400/230 V distribution and service lines Load Factor - Ratio of average power demand to maximum power demand Electrical Losses - Difference between energy delivered and energy sent out
REMARKS
In this report, "$" refers to US dollars.
This Resettlement Due Diligence is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. Your attention is directed to the “terms of use” section of this website.
In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the ADB does not intend to make any judgments as to the legal or other status of any territory or area.
ADB : Asian Development Bank
AH : Affected Household
EVN : Vietnam Electricity
EVN HANOI : Hanoi Power Corporation
EVNNPT : National Power Transmission Corporation
GoV : Government of Vietnam
LFDC : Land Fund Development Center
NPMB : Northern Power Projects Management Board
SS : Substation
TEP : Transmission Efficiency Project
WB : World Bank
WPC : Ward People’s Committee
Resettlement Due Diligence 110kV Connection line to Sai Dong Industrial Complex Subproject
4
TABLE OF CONTENTS
ABBREVIATIONS ........................................................................................................... 3
ELECTRICAL TERMINOLOGY ....................................................................................... 3
REMARKS....................................................................................................................... 3
A. Introduction ............................................................................................................... 5
B. Subproject Description .............................................................................................. 5
C. Methodology on Preparation of Resettlement Due Diligence .................................... 6
D. Impacts of Subproject ............................................................................................... 7
E. Current status of resident and infrastructure in Project area ..................................... 8
F. Compensation and implementation plan ................................................................. 10
G. Conclusions ............................................................................................................ 10
H. Annexes .................................................................................................................. 12
LIST OF FIGURES
Figure 1. Map of subproject location ............................................................................... 6
Figure 2. Current status of Project area ”Construction of technical facility for installment of 110kV underground cables section passing Vinhomes Riverside 2 urban area, Long Bien District Project” ................................................................................................................ 8
Figure 3. Gate of 220kV Long Bien SS .......................................................................... 9
Figure 4. Area for construction of 110kV Sai Dong 2 SS .............................................. 10
Resettlement Due Diligence 110kV Connection line to Sai Dong Industrial Complex Subproject
5
A. Introduction
1. Long Bien District and Gia Lam District are currently supplied with electricity from
regional substations including 110kV E1 - Dong Anh, E2 - Gia Lam, E15 - Sai Dong. This
is an area with rapid loading development due to the appearance of industrial parks, urban
areas, factories, while the existing substations are overloaded. Therefore, in order to meet
the demand and orientation of power grid planning, the Hanoi Municipal People's
Committee issued Decision No. 1940/QD-UBND dated 21/04/2016 on the promulgation
of the power grid development plan period 2016 – 2020, in which 110 kV Sai Dong
Industrial complex SS ( 110kV Sai Dong 2 SS) with capacity of 63MVA, 110/22kV will
supply electricity for Sai Dong Industrial Complex and Long Bien District.
B. Subproject Description
Objectives
2. The subproject was constructed with the purpose:
• Supply 110kV input power for 110kV Sai Dong 2 SS.
• Exploit loading of 220kV Long Bien SS.
• Enhance circuit connection, improve reliability of power supply.
• Reduce the leakage on the system, contribute to the efficiency of power
production and business of EVN
Alignment and feature of the subproject
3. 110kV underground cable supplying power to 110kV Sai Dong 2 SS converses
wards including: Giang Bien, Viet Hung, Phuc Loi in Long Bien District, Hanoi with a total
length of about 3.770m. The route mainly the cable line goes inside a existing cable trench
along the road and sidewalks of Hoi Xa, Doan Khue and Tran Danh Tuyen streets.
Resettlement Due Diligence 110kV Connection line to Sai Dong Industrial Complex Subproject
6
Figure 1. Map of subproject location
4. Main features
Voltage level 110kV
Number of circuits 02
Starting point 02 bays of 220kV Long Bien SS
Ending point 02 bays of transmission line of 110kV Sai Dong 2 SS
Length 3770m
UGC Single phase, core copper, cross section 1,200mm2, XLPE insulation.
Layout type Combining various types of cable layout, the main one is trefoil,
special ones are flat.
Laying cable
Configuration
Set in HDPE pipe, buried directly in the ground
Telecommunication
fiber cable
A NMOC 24 fiber cable along the 110kV underground cable
Fiber cable controlling
cable temperature
Fiber cable inside the bearing cable (only phase B)
Temperature control
equipment
Distributed Thermal System was invested in 220kV Long Bien SS
Earthing Mixed, sheath crossing and earthing one side
Facility (Bending cable
trench, connecting
cable trench)
Reinforced concrete (invested by other project)
C. Methodology on Preparation of Resettlement Due Diligence
5. A number of research methods were utilized, including:
Resettlement Due Diligence 110kV Connection line to Sai Dong Industrial Complex Subproject
7
• Desk study method: the Consultant reviewed Feasibility Study Report for
subproject features and scale
• Some consultation meetings were conducted to collect information and data
related to the project from the stakeholders about the 110 kV Connecting line to
Sai Dong Industrial Complex
• Field trips were conducted to observe and assess the project impacts.
D. Impacts of Subproject
6. The Project only put the cable through the trench, the trench system is conducted in
02 following projects and not in the scope of Environment Impact Assessment. The project
cable has length of 3,770m divided into 02 sections, as following:
➢ Section 1: From 220kV Long Bien SS to the tower No.83, with length of 2,457m,
the cable converses through the trench system invested by “Construction of
technical facility for installment of 110kV underground cable from 220kV Long
Bien SS Project”.
➢ Section 2: From the tower No.83 to 110kV Sai Dong 2 SS with length of about
1.313, the cable converses through the trench system invested by
“Construction of technical facility for installment of 110kV underground cables
section passing Vinhomes Riverside urban area, Long Bien District Project”.
Status of Subproject area
7. Currently, the subproject area is under construction for cable trench system
belonging to scope of 02 projects: (1) Project 1 - Construction of technical facility for
installment of 110kV underground cable from 220kV Long Bien SS Project and (2) Project
02 Construction of technical facility for installment of 110kV underground cables section
passing Vinhomes Riverside urban area, Long Bien District Project” for earthing 110kV
power system in Long Bien District.
Current status of cable trench system under construction (for 02 aboved projects)
8. The aboved cable trench in section 1 and 2 has width x depth of 2 x 1.8m. The
project cable alignment includes 11 connecting cable trenchs and 02 bending cable
trenchs are placed in right positions according to the design from 220kV Long Bien SS to
110kV Sai Dong 2 SS.
9. Cable trench system belongs to 02 aboved projects is under construction and
expected to be competed in Quarter IV/2018, detailed schedule as following:
✓ Section 1 (2,457m): Currently, 35% of work has been done in the area of Viet
Hung ward, 65% of remaining work has not been constructed in Giang Bien and
Phuc Loi wards.
Resettlement Due Diligence 110kV Connection line to Sai Dong Industrial Complex Subproject
8
✓ Section 2 (1,313m): At present, 40% of work has been completed in Giang Bien
ward, the remaining one (60%) in Viet Hung and Phuc Loi wards has not been
constructed.
Figure 2. Current status of Project area ”Construction of technical facility for
installment of 110kV underground cables section passing Vinhomes Riverside 2
urban area, Long Bien District Project”
E. Current status of resident and infrastructure in Project area
10. There are no people as well as structures in the Project area. The underground cable
system will be located in the existing cable trench system along the roadside and
pavements of the roads: The Xa, Doan Khue and Tran Danh Tuyen are invested in two
other projects, therefore, there is no permanently land acquisition impacts.
11. The project carried out the work of cable pulling at connecting cable trenchs and
bending cable trenchs along the underground cable alignment. The project cable system
is curled and placed right at the connecting trench, bending trench for convenience in
cable pulling. Therefore, the project does not occupy land permanently, the temporarily
occupied land is only the area at the head of each connecting trench according to the
construction schedule. The connecting trench has an area of about 10m2 is insignificant,
the occupancy time is short and only a few days in each construction phase, so it can be
considered that the project does not occupy the land temporarily.
12. 110kV Connection line to Sai Dong Industrial Complex Subproject connects and
transmits power between 220kV Long Bien SS and 110kV Sai Dong 2 SS. These two
subprojects are considered as connection infrastructures of 110kV Connection line to Sai
Dong Industrial Complex Subproject.
Resettlement Due Diligence 110kV Connection line to Sai Dong Industrial Complex Subproject
9
Current status of 220kV Long Bien SS and 110kV Sai Song 2 SS
220kV Long Bien SS
13. The substation located in Giang Bien ward, Long Bien district, Hanoi and went into
operation since September 26, 2017. The SS includes 3 transformers 220/110/22kV-
250MVA, 02 transformers 220kV and 250 MVA were installed during phase 1. The SS
includes function parts such as equipment room, control room, distribution room,
attendant room, canteen, access road, parking lot… Currently, the SS is supplying for
220kV Dong Anh 1 transmission line and 220kV Dong Anh 2 transmission line.
14. 220kV Long Bien SS is considered as connection infrastructure of 110kV Connection
line to Sai Dong Industrial Complex Subproject.
Figure 3. Gate of 220kV Long Bien SS
15. 220kV Long Bien SS Subproject acquired 70.254m2 of agricultural land belonging
to 205 households in Giang Bien Ward, Long Bien District. Land acquisition has been
completed in March 2016 with total amount of 53.554.360.100 VND paid to 205
households.
16. According results of interviewing representatives of Northern Power Projects
Management Board (NPMB), Long Bien District Land Fund Development Center (LFDC),
affected households, Giang Bien Ward authority and results of final independent
monitoring report, there is no outstanding related to land acquisition, compensation of
subproject;
17. 220kV Long Bien SS is one of 05 subprojects under Transmission Efficiency Project
(TEP) financed by WB. Compensation, assistance and resettlement process of project
was conducted in accordance with Resettlement Plan of subproject1 - compliance with
policy on Involuntary Resettlement of WB (OP 4.12) and Land Law 2013 of GoV;
18. Due to the policy equivalent of two donors and there is no outstanding related to
involuntary resettlement of this subproject, therefore, it is not necessary to develop a
corrective action plan.
1 Resettlement Plan of 220kV Long Bien SS was prepared in 2015 by Power Engineering Consulting Joint Stock Company 1 (PECC1);
Resettlement Due Diligence 110kV Connection line to Sai Dong Industrial Complex Subproject
10
110kV Sai Dong 2 SS
19. The SS located in Phuc Loi ward, Long Bien district, Hanoi. Current status of SS
construction site is vacant land, mainly grass and herbaceous plants. There is no river,
stream and pond passing through the area. There are no people living as well as
infrastructure in the SS area.
20. Sai Song 2 SS will be constructed financed by ADB loan, therefore, activities on
compensation, assistance and resettlement (if any) will be implemented according to ADB
policies.
Figure 4. Area for construction of 110kV Sai Dong 2 SS
F. Compensation and implementation plan
21. The project only pull cable through cable trench and there is no impact on land
acquisition and people incomes, therefore, compensation cost is not necessarily
calculated for the subproject.
22. The subproject is expected to implement by the end of 2018 and complete by the
beginning of 2019. EVN HANOI will inform ADB project activities through semi-annually
internal monitoring report.
G. Conclusions
23. The construction of underground cable connecting Long Bien SS with Sai Dong 2
SS will not cause permanent and temporary land acquisition impacts. There is no house,
Resettlement Due Diligence 110kV Connection line to Sai Dong Industrial Complex Subproject
11
structure or public utility will be affected by the project. There is also no household affected
livelihood or income generated by the project implementation.
24. There is no people living and doing business in the subproject area, therefore the
subproject does not have impacts on livelihood or incomes of people.
25. According to the results of consultations with representatives of Project Owner of
220kV Long Bien SS, LFDC and 02 affected households, there is no outstanding on land
acquisition for 220kV Long Bien SS;
26. Due to the policy equivalent of two donors and there is no outstanding related to
involuntary resettlement of this subproject, therefore, it is not necessary to develop a
corrective action plan;
Resettlement Due Diligence 110kV Connection line to Sai Dong Industrial Complex Subproject
12
H. Annexes
1. List of interviewees related to 220kV Long Bien SS
No. Full name Organization/Address
1 Do Duc Manh Head of Compensation office - NPMB
2 Vu Manh Quan Staff of Compensation office - NPMB
3 Nguyen Quoc Tuan Deputy director of Long Bien District LFDC
4 Bui Anh Tuan Vice president of Giang Bien WPC
5 Nguyen Thi Duc Affected household in Giang Bien Ward
6 Dao Van Nhung Affected household in Giang Bien Ward
2. List of public consultation participants
No. Full name Organization/Address Male Female
Giang Bien Ward
1 Pham Trung Kien Giang Bien Ward x
2 Dao Thi Chung Giang Bien Ward x
3 Ngo Minh Duc Giang Bien Ward x
4 Nguyen Duy Giang Giang Bien Ward x
5 Trinh Thi Hanh Giang Bien Ward x
6 Nguyen Thi Thuy Cau Giang Bien Ward x
7 Nguyen Tien Binh Giang Bien Ward x
8 Pham Thi Lien Giang Bien Ward x
9 Do Duc Hieu Giang Bien Ward x
10 Dinh Hoai Thanh Giang Bien Ward x
11 Nguyen Thi Phuong Lan Giang Bien Ward x
12 Nguyen Ngoc Hung Giang Bien Ward x
13 Ha Thi Nhu Quynh Giang Bien Ward x
14 Vu Duc Thuan Giang Bien Ward x
15 Nguyen Van Hoa Giang Bien Ward x
16 Nguyen Tien Luyen Giang Bien Ward x
17 Pham Van Du Giang Bien Ward x
18 Pham Thi Thuy Hang Giang Bien Ward x
Resettlement Due Diligence 110kV Connection line to Sai Dong Industrial Complex Subproject
13
No. Full name Organization/Address Male Female
19 Nguyen Thi Hoai Giang Bien Ward x
20 Nguyen Cong Duc Giang Bien Ward x
21 Nguyen Manh Cuong Giang Bien Ward x
22 Nguyen Thi Huyen Trang Giang Bien Ward x
23 Nguyen Hong Nhung Giang Bien Ward x
24 Tran Quoc Huy Giang Bien Ward x
Phuc Loi Ward
1 Ha Huy Men Phuc Loi Ward x
2 Kieu Van Bao Phuc Loi Ward x
3 Duong Van Suc Phuc Loi Ward x
4 Nguyen Van Quyet Phuc Loi Ward x
5 Ngo Van Luong Phuc Loi Ward x
6 Pham Quang An Phuc Loi Ward x
7 Nguyen Dinh Do Phuc Loi Ward x
8 Nguyen Van Hoach Phuc Loi Ward x
9 Nguyen Duy Theu Phuc Loi Ward x
10 Nguyen Van Hao Phuc Loi Ward x
11 Ha Thi Nuong Phuc Loi Ward x
12 Duong Thi Dung Phuc Loi Ward x
13 Nguyen Thi Toan Phuc Loi Ward x
14 Duong Thi Mong Phuc Loi Ward x
15 Nguyen Thi Vach Phuc Loi Ward x
16 Le Thi Lien Phuc Loi Ward x
17 Pham Thi Thinh Phuc Loi Ward x
18 Le Van Diep Phuc Loi Ward x
19 Nguyen Van Tuy Phuc Loi Ward x
20 Nguyen Duy Khanh Phuc Loi Ward x
Viet Hung Ward
1 Dinh Quang Luan Viet Hung Ward x
2 Dang Van Vui Viet Hung Ward x
Resettlement Due Diligence 110kV Connection line to Sai Dong Industrial Complex Subproject
14
No. Full name Organization/Address Male Female
3 Nguyen Duy Hung Viet Hung Ward x
4 Nguyen Kim Anh Viet Hung Ward x
5 Truong Duc Thao Viet Hung Ward x
6 Duong Van Hai Viet Hung Ward x
7 Tran Duc Tan Viet Hung Ward x
8 Tran Thi Thai Ha Viet Hung Ward x
9 Nguyen Dinh Khu Viet Hung Ward x
10 Do Tinh Viet Hung Ward x
11 Nguyen Van Tao Viet Hung Ward x
12 Oa Hanh San Viet Hung Ward x
13 Nguyen Thi Ngoc Quy Viet Hung Ward x
14 Nguyen Dinh Hung Viet Hung Ward x
15 An Manh Tung Viet Hung Ward x
16 Giap Thi Thanh Nhan Viet Hung Ward x
17 Nguyen Thi Thu Viet Hung Ward x
18 Truong Van Che Viet Hung Ward x
19 Nguyen Van Vong Viet Hung Ward x
20 Nguyen Van Tham Viet Hung Ward x
Resettlement Due Diligence 110kV Connection line to Sai Dong Industrial Complex Subproject
15
3. Some photos of public consultation