Via email Via email - Canada.ca · 200 – 2006 West 10th Avenue Vancouver, BC V6J 2B3 tel:...

20
200 – 2006 West 10 th Avenue Vancouver, BC V6J 2B3 www.wcel.org tel: 604.684.7378 fax: 604.684.1312 toll free: 1.800.330.WCEL (in BC) email: [email protected] November 25, 2013 Via email Via email Courtney Trevis Brian Murphy Panel Co-Manager Panel Co-Manager Site C Review Panel Secretariat Site C Review Panel Secretariat Canadian Environmental Assessment Agency Environmental Assessment Office 160 Elgin Street, 22 nd floor 2n floor, 836 Yates Street Ottawa, ON K1A 0H3 Victoria, BC V8W 9V1 Re: Site C Clean Energy Project, CEAA Ref # 63919 – Submission of Expert Report Dear Sir/Madam: Please find enclosed the expert report of Dr. Marvin Shaffer, prepared on behalf of and submitted by the Peace Valley Environment Association (PVEA), an Interested Party and Participant in the environmental assessment of the proposed Site C Project. Also enclosed are Dr. Shaffer’s résumé and list of assignments current to November, 2013. We are grateful to the Panel for granting PVEA an extension to file Dr. Shaffer’s report by November 29. Due to a concerted final effort, we are pleased to be able to file the report today. Please feel free to contact me if you have any questions. Sincerely, Anna Johnston Staff Counsel, West Coast Environmental Law

Transcript of Via email Via email - Canada.ca · 200 – 2006 West 10th Avenue Vancouver, BC V6J 2B3 tel:...

Page 1: Via email Via email - Canada.ca · 200 – 2006 West 10th Avenue Vancouver, BC V6J 2B3 tel: 604.684.7378 fax: 604.684.1312 toll free: 1.800.330.WCEL (in BC) email: admin@wcel.org

200 – 2006 West 10th Avenue

Vancouver, BC V6J 2B3

www.wcel.org

tel: 604.684.7378

fax: 604.684.1312

toll free: 1.800.330.WCEL (in BC)

email: [email protected]

November 25, 2013

Via email Via email

Courtney Trevis Brian Murphy Panel Co-Manager Panel Co-Manager Site C Review Panel Secretariat Site C Review Panel Secretariat Canadian Environmental Assessment Agency Environmental Assessment Office 160 Elgin Street, 22nd floor 2n floor, 836 Yates Street Ottawa, ON K1A 0H3 Victoria, BC V8W 9V1 Re: Site C Clean Energy Project, CEAA Ref # 63919 – Submission of Expert Report

Dear Sir/Madam:

Please find enclosed the expert report of Dr. Marvin Shaffer, prepared on behalf of and submitted by the Peace Valley Environment Association (PVEA), an Interested Party and Participant in the environmental assessment of the proposed Site C Project. Also enclosed are Dr. Shaffer’s résumé and list of assignments current to November, 2013.

We are grateful to the Panel for granting PVEA an extension to file Dr. Shaffer’s report by November 29. Due to a concerted final effort, we are pleased to be able to file the report today.

Please feel free to contact me if you have any questions.

Sincerely,

Anna Johnston Staff Counsel, West Coast Environmental Law

smithj
Typewritten Text
<original signed by>
Page 2: Via email Via email - Canada.ca · 200 – 2006 West 10th Avenue Vancouver, BC V6J 2B3 tel: 604.684.7378 fax: 604.684.1312 toll free: 1.800.330.WCEL (in BC) email: admin@wcel.org

200 – 2006 West 10th Avenue

Vancouver, BC V6J 2B3

www.wcel.org

tel: 604.684.7378

fax: 604.684.1312

toll free: 1.800.330.WCEL (in BC)

email: [email protected]

November 26, 2013

Via email Via email

Courtney Trevis Sean Moore Panel Co-Manager Panel Co-Manager Site C Review Panel Secretariat Site C Review Panel Secretariat Canadian Environmental Assessment Agency Environmental Assessment Office 160 Elgin Street, 22nd floor 2n floor, 836 Yates Street Ottawa, ON K1A 0H3 Victoria, BC V8W 9V1 [email protected] [email protected]

Re: Site C Clean Energy Project, CEAA Ref # 63919 – Amended Expert Report and Clarification

Dear Sir/Madam:

Please find enclosed an amended expert report of Dr. Marvin Shaffer, prepared on behalf of and submitted by the Peace Valley Environment Association (PVEA). The amendments correct two typos in the fourth bullet on page 3 of the report submitted November 25.

Also, we understand that some PVEA members may be submitting Registration Forms that state PVEA in the “Organization” Field: for example, Hearing Document No 1767, “Written Submission of Denise Gardiner”.

To clarify, as a registered Society, PVEA is represented only by individuals authorized to make decisions on its behalf. For the purposes of the environmental assessment of the Site C Clean Energy Project, unless it states otherwise, PVEA is represented by West Coast Environmental Law, counsel Timothy Howard and PVEA coordinator Andrea Morison.

While PVEA does not dispute the right of individuals, including its members, to participate in the environmental assessment of the Site C Clean Energy Project, it wishes to clarify that any information submitted by individuals other than those authorized to represent it are submissions on those individuals’ behalf, not PVEA’s. PVEA requests that the Panel not consider submissions by Ms. Gardiner or any other individuals to be a PVEA submission unless PVEA explicitly communicates otherwise to it.

Page 3: Via email Via email - Canada.ca · 200 – 2006 West 10th Avenue Vancouver, BC V6J 2B3 tel: 604.684.7378 fax: 604.684.1312 toll free: 1.800.330.WCEL (in BC) email: admin@wcel.org

2

Please feel free to contact me if you require clarification on this or any other matters.

Sincerely,

Anna Johnston Staff Counsel, West Coast Environmental Law //enclosure

SmithJ
Typewritten Text
<original signed by>
Page 4: Via email Via email - Canada.ca · 200 – 2006 West 10th Avenue Vancouver, BC V6J 2B3 tel: 604.684.7378 fax: 604.684.1312 toll free: 1.800.330.WCEL (in BC) email: admin@wcel.org

                   

   

Assessment  of  the  Need  for  and  Alternatives  to  the  Site  C  Project  

               

Prepared  at  the  Request  of:  Peace  Valley  Environmental  Association  

for  submission  to  the:      CEAA  and  BCEAO  Joint  Review  Panel  

   by:  

Dr.  Marvin  Shaffer  Marvin  Shaffer  &  Associates  Ltd.  

   

November  25,  2013    

 

Page 5: Via email Via email - Canada.ca · 200 – 2006 West 10th Avenue Vancouver, BC V6J 2B3 tel: 604.684.7378 fax: 604.684.1312 toll free: 1.800.330.WCEL (in BC) email: admin@wcel.org

  2  

Executive  Summary    

• The  purpose  of   this  submission   is   to  present  an   independent  assessment  of  BC   Hydro’s   analysis   and   conclusions   with   respect   to   the   need   and  justification  for  the  Site  C  project.    

• BC  Hydro  is  forecasting  shortfalls  in  energy  supply  starting  in  2027  without  LNG   and   between   2021   and   2024   with   LNG.   It   is   forecasting   shortfalls   of  peak  generating  capacity  by  2020.  

 • Contributing  to  the  forecast  shortfalls  is  a  major  market  failure  in  the  pricing  

of   electricity,  with   rates   in   the   industrial   sector   less   than  half   the  marginal  cost  of  new  supply.  BC  Hydro  is  in  effect  inducing  new  mining  and  oil  and  gas  load  with  the  offer  of  low  cost  power  that  it  does  not  have,  giving  rise  to  more  load  growth  than  what  would  be  economically  efficient  –  where  the  value  of  the  use  exceeds  the  cost  it  entails.  

 • The   key   factor   underlying   the   forecast   shortfalls   is   the   elimination   of   the  

existing  gas-­‐fired  Burrard  Thermal  plant  as  a  source  of  back-­‐up  energy  and  peak   generating   capacity.   Traditionally   the  Burrard  plant   has   been  used   to  backstop   or   ‘firm   up’   non-­‐firm   hydro   and   spot  market   supplies   –   low   cost  sources  of  supply  that  very  cost-­‐effectively  defer  the  need  for  new  resources.    

 • The  elimination  of  Burrard  as  a  source  of  back-­‐up  energy  and  peak  capacity  

was   forced   on   BC   Hydro   by   the   government   without   any   supporting  economic,  environmental  or  other  analysis  and  despite  the  recommendations  of  the  BC  Utilities  Commission,  the  positions  of  all  intervenors  except  for  the  Independent  Power  Producers  Association   (IPPBC)   at   the  2008  Long  Term  Acquisition  Plan  (LTAP)  hearing,  and  even  BC  Hydro  itself.  

 • Had  BC  Hydro  been  able   to  recognize   the  back-­‐up  role  of  Burrard,   together  

with   the   spot   market   allowance   it   traditionally   assumed,   its   latest   LRB  analysis  (without  LNG)  would  show  no  shortfall  of  energy  until  2033  and  no  shortfall  of  capacity  until  2029  (the  same  year  capacity  shortfalls  would  have  to  be  addressed  even  with  the  Site  C  project).  Were  BC  Hydro  to  assume  the  back-­‐up  capability  of  Burrard  recommended  by  the  BC  Utilities  Commission  plus   the   market   allowance   implicit   in   its   current   planning   on   the   basis   of  average  water  conditions,  its  latest  LRB  analysis  (without  LNG)  would  show  no  shortfall  of  energy  until  beyond  2033.  

 • The  need   for  new  resources   that  BC  Hydro  has   identified   to  meet  non-­‐LNG  

requirements   is   a   need   to   replace   what   was   lost   with   the   elimination   of  Burrard.   As   for   LNG,   BC   Hydro   has   stated   that   because   of   the   unique  requirements  of  that  load,  it  could  better  be  served  by  north  coast  supply.  BC  Hydro   is   not   proposing,   nor   has   it   provided   any   analysis   supporting   the  development  of  Site  C  to  meet  potential  LNG  requirements.  

Page 6: Via email Via email - Canada.ca · 200 – 2006 West 10th Avenue Vancouver, BC V6J 2B3 tel: 604.684.7378 fax: 604.684.1312 toll free: 1.800.330.WCEL (in BC) email: admin@wcel.org

  3  

 • BC  Hydro  compared  Site  C  with  two  alternatives:  a  clean  portfolio  and  a  clean  

plus   thermal   portfolio,   the   latter   including   the   development   of   single   cycle  gas   turbines   (SCGTs)   to  meet   capacity   requirements.   It   concluded   Site   C   is  preferable  based  on  its  environmental  attributes  and  employment  impacts  as  well  as   its   cost  advantage.   In   fact  BC  Hydro’s  preference   for  Site  C   is  based  solely  on  its  cost  analysis,  as  BC  Hydro  did  not  assess  the  significance  of  the  different   environmental   attributes   nor   did   it   analyze   the   economic   net  benefits  (or  costs)  that  the  employment  impacts  may  entail.  

 • BC  Hydro’s  estimated  cost  advantage  for  Site  C  is  less  in  comparison  with  the  

clean  plus  thermal  portfolio  than  the  clean  portfolio.  The  SCGTs  in  the  clean  plus   thermal   portfolio   provide   relatively   low   cost   capacity   that   can   be  strategically   located   to   minimize   transmission   requirements,   and   low   cost  energy  when  used  to  meet  peak  loads.  The  estimated  cost  advantage  of  Site  C  compared  to  the  clean  plus  thermal  portfolio  BC  Hydro  analyzed  is  relatively  small  and  dependent  on  some  key  assumptions.  

 • BC  Hydro  did  not   consider   in   its   analysis   the   role   that   SCGTs   could  play   in  

backstopping   greater   use   of   non-­‐firm   and   spot  market   supplies   –   in   other  words,  they  did  not  consider  how  SCGTs  could  replace  what  was  lost  with  the  elimination  of  Burrard.  

 • The  SCGTs   in  BC  Hydro’s   clean  plus   thermal  portfolio  have   the  potential   to  

back  up  some  3700  GWh  of  non-­‐firm  and  spot  market  supply,  deferring  the  need   for  new   sources  of   energy   supply  until   2033.     Such   an   SCGT   ‘thermal  back-­‐up’   strategy   would   be   far   more   cost-­‐effective   than   what   BC   Hydro  analyzed,  and  would  be  far  less  costly  than  the  Site  C  project  that  BC  Hydro  is  proposing.   The   cost   advantage   of   the   SCGT   strategy   could   be   $1   billion   or  more.  

 • BC  Hydro  is  constrained  by  the  self-­‐sufficiency  and  clean  requirements  in  the  

Clean   Energy   Act.   However,   it   is   not   clear   that   this   SCGT   strategy   would  contravene   those   requirements.   The   SCGTs   would   give   BC   Hydro   the   firm  capability   to   meet   requirements   with   BC   resources.   At   the   same   time,   the  expected   displacement   of   SCGT   generation   by   non-­‐firm   and   spot   supplies,  would  enable  BC  Hydro  to  satisfy  the  clean  restriction  on  thermal  generation  in  B.C.  Nor  would   the  displacement   simply  necessarily  mean  more   thermal  generation   outside   B.C.   Much   of   the   spot   market   supply   would   be   from  freshet   hydro   surplus   in   the   Pacific   Northwest   as   well   as   the   increasing  amount   of  wind   generation   in   neighbouring   jurisdictions   that   is   surplus   to  requirements  when  produced.  

 • In  conclusion:  

 

Page 7: Via email Via email - Canada.ca · 200 – 2006 West 10th Avenue Vancouver, BC V6J 2B3 tel: 604.684.7378 fax: 604.684.1312 toll free: 1.800.330.WCEL (in BC) email: admin@wcel.org

  4  

There   would   be   no   need   for   new   supply   had   BC   Hydro   not   eliminated  Burrard  as  a  source  of  back-­up  energy  and  dependable  capacity.    BC  Hydro’s  conclusion  that  Site  C  is  the  preferred  source  to  meet  the  need  is   due   to   the   restrictive   nature   of   the   clean   plus   thermal   portfolio   it  analyzed.    A  strategy  of  using  the  back-­up  capability  of  SCGTs  to  restore  much  of  the  combined   thermal   back-­up   /   market   allowance   that   was   lost   with   the  elimination  of  Burrard  would  be  a   far  more  cost-­effective   strategy   than  the  development  of  Site  C  in  the  foreseeable  future.  

 There  is  not  a  need  and  justification  for  Site  C  as  proposed  by  BC  Hydro.  

 

Page 8: Via email Via email - Canada.ca · 200 – 2006 West 10th Avenue Vancouver, BC V6J 2B3 tel: 604.684.7378 fax: 604.684.1312 toll free: 1.800.330.WCEL (in BC) email: admin@wcel.org

  5  

1.0   Introduction    In   its   Environmental   Impact   Assessment   of   the   Site   C   project,   including   the  Evidentiary  update,  BC  Hydro  has  argued  that   the  proposed  project   is  needed  and  justified.   It   states   that   there   is  a  need  “based  on   the  updated   load-­resource  balance  (LRB)  analysis  even  after  taking  into  account  the  DSM  target  and  without  taking  into  account  the  potential  demand  from  LNG”.1  And  it  concludes  based  on  its  analysis  of  alternative  portfolios  capable  of  meeting  the  forecast  need  that  the  proposed  project  is   justified   –   that   it   provides   “the   best   combination   of   financial,   technical,  environmental  and  economic  attributes”.2    The   purpose   of   this   submission   is   to   present   an   independent   assessment   of   BC  Hydro’s  analysis  and  conclusions  regarding  need  and  justification.  Specifically,   this  submission  addresses  the  following  questions  and  issues:    

• What  are  the  key  factors  underlying  BC  Hydro’s  forecast  of  LRB  shortfalls  in  both  energy  and  capacity?    

• What  are  the  key  factors  underlying  BC  Hydro’s  conclusion  that  Site  C  is  the  preferred  alternative  to  meet  its  forecast  need?  

• Is   there   an   alternative   strategy   that   would   be   more   cost-­‐effective   or  otherwise  preferable  than  the  development  of  Site  C?  

 The   overriding   issue   this   submission   addresses   is  whether   there   is   in   fact   a   need  and  justification  for  the  Site  C  project  as  proposed  by  BC  Hydro.      The   submission   has   been   prepared   by   Dr.   Marvin   Shaffer   of   Marvin   Shaffer   &  Associates  Ltd.  at  the  request  of  the  Peace  Valley  Environmental  Association  (PVEA).  Dr.   Shaffer   is   a   consulting   economist   and   adjunct   professor   in   the   public   policy  program   at   Simon   Fraser   University.3   He   has   appeared   as   an   expert   witness   on  numerous  occasions  before  the  BC  Utilities  Commission  on  BC  Hydro  resource  plan  and   other   matters,   and   before   other   regulatory   bodies   and   environmental  assessment  panels,  including  panels  established  under  the  Canadian  Environmental  Assessment   Act.   The   analysis   and   conclusions   in   this   submission   are   those   of   Dr.  Shaffer  and  were  not  in  any  way  influenced  by  the  views  and  positions  of  the  PVEA.      

                                                                                                               1  BC  Hydro,  Site  C  Clean  Energy  Project  Evidentiary  Update,  September  13,  2013,  p.3.  2  Ibid.,  p.4.  3  Dr.  Shaffer’s  resume  can  be  found  at:  http://www.sfu.ca/mpp/marvinshaffer/resume/  

Page 9: Via email Via email - Canada.ca · 200 – 2006 West 10th Avenue Vancouver, BC V6J 2B3 tel: 604.684.7378 fax: 604.684.1312 toll free: 1.800.330.WCEL (in BC) email: admin@wcel.org

  6  

2.0   Need  for  New  Supply    

2.1   BC  Hydro’s  LRB  Forecast      BC  Hydro’s  LRB  forecast  for  energy  is  based  on  comparisons  of  its  forecast  of  annual  requirements   with   its   estimated   annual   firm   supply.   The   requirements   forecast  starts  with  projections  of  residential,  commercial  and  industrial  load  growth  before  demand  side  management  (DSM)  and  then  considers  the  system  requirements  after  planned  DSM  measures  and   targets   are   taken   into  account.  Estimated   firm  supply  includes  the  capability  of  BC  Hydro’s  hydro  electric  generating  plants  under  average  water   conditions;   the   firm   potential   output   of   its   thermal   plants   (excluding   the  Burrard   generating   station);   and   the   firm   supply   from   its   IPP   contract   purchases,  including  expected  renewal  as  well  as  existing  and  committed  purchases.    BC  Hydro’s  LRB  forecast  for  capacity  is  based  on  comparisons  of  its  forecast  of  peak  demand   with   its   dependable   peak   generating   capacity,   including   provision   for  forced  outage  or  other  contingency-­‐related  reserve  margins.      The  LRB   forecasts   after   taking  planned  DSM   into   account   are  developed  with   and  without  new  LNG  requirements.    In  its  Evidentiary  Update  BC  Hydro  reported  that  without  new  LNG  requirements   it  will  have   shortfalls  of   energy   supply   starting   in  2027  and  shortfalls  of  peak  generating  capacity  starting  in  2020.4  With  LNG  it  would  have  energy  shortfalls  starting  in  2021  to  2024  depending  on  the  magnitude  of  the  LNG  requirements,  and  capacity  shortfalls  starting  in  2020.5    

2.2   Underlying  Factors    

BC  Hydro’s  2012  requirements  forecast  indicates  load  growth  in  all  sectors.6  For  the  residential   and   commercial   sectors   the   growth   is   due   largely   to   increased  population  (number  of  accounts)  and  economic  activity.  In  the  industrial  sector  the  load  growth  is  due  to  the  forecast  sharp  increase  in  mining  and  oil  and  gas  industry  requirements.   Increased  mining   and   oil   and   gas   industry   requirements   constitute  the  largest  rate  of  growth  for  the  entire  system  over  the  2014-­‐2024  period.    Contributing   to   the   load   growth   in   all   sectors,   but   particularly   with   the   electric-­‐intensive  mining  and  oil  and  gas  industry,  is  what  economists  term  a  market  failure  in  the  pricing  of  electricity.  Electricity  rates  are  based  on  BC  Hydro’s  average  cost  of  supply,  which  is  dominated  by  its  low  cost  heritage  hydro  resources.  As  a  result,  the  energy   rate   (the   rate   charged   per   MWh   of   use)   for   the   industrial   sector   (the  transmission  level  customers)  currently  averages  less  than  $40/MWh.7  BC  Hydro’s  

                                                                                                               4  BC  Hydro,  Site  C  Clean  Energy  Project  Evidentiary  Update,  Tables  5  and  6,  pp.  12-­‐13.  5  Ibid.,  Tables  7  and  8,  pp.  15-­‐16.  6  BC  Hydro,  Draft  Integrated  Resource  Plan,  Chapter  2,  section  2.2.  7  Current  rates  are  set  out  in:  https://www.bchydro.com/accounts-­‐billing/customer-­‐service-­‐business/business-­‐rates-­‐overview/business-­‐rates-­‐prices.html  

Page 10: Via email Via email - Canada.ca · 200 – 2006 West 10th Avenue Vancouver, BC V6J 2B3 tel: 604.684.7378 fax: 604.684.1312 toll free: 1.800.330.WCEL (in BC) email: admin@wcel.org

  7  

most  recent  estimate  of  the  marginal  cost  of  new  energy  supply,  by  comparison,   is  $85-­‐$100/MWh.8        It  is  the  marginal  cost  of  new  electricity  supply  that  reflects  the  cost  BC  Hydro  will  incur  if,  as  it  argues,  it  will  have  to  increase  supply  to  meet  increased  requirements.  The   fact   that   rates   in   the   industrial   sector   are   less   than   half   the  marginal   cost   of  supply  means   that   new   loads   are   heavily   subsidized   –   they   pay   less   than   half   the  cost  consequences  they  add  to  the  system.  And  that  in  turn  contributes  to  more  load  growth   than   what   economists   would   consider   economically   efficient,   where   the  value  of  the  electricity  use  equals  or  exceeds  the  costs  it  entails.    The  DSM  that  BC  Hydro  takes  into  account  in  developing  its  LRB  estimates  assumes  a   continuation   of   its   long-­‐term   target   of   7800   GWh   by   2021.   This   DSM   is   based  primarily  on  incentive  and  other  programs  aimed  at  encouraging  customers  to  use  less  electricity.  However,  except  for  the  existing  stepped  rate  structures,  BC  Hydro’s  DSM  strategy  does  not  address  the  major  market  failure  in  the  pricing  of  electricity.  Indeed,  BC  Hydro  specifically  ruled  out  consideration  of  DSM  strategies  that  address  this   market   failure   because   of   its   concerns   about   government   and   customer  acceptance  as  well  as  uncertainty  about  its  effects.9    The   market   failure   in   the   pricing   of   electricity   and   the   failure   of   planned   DSM  measures   to   address   that   (beyond   the   current   stepped   rate   structure)   is   an  important   factor   underlying   BC   Hydro’s   forecast   of   future   requirements   and   its  determination   of   ‘need’.   In   effect   BC   Hydro   is   attracting   new   electric-­‐intensive  industry  and  other  new  demand  with   the  offer  of   low  cost  power   that   it  does  not  have  available  for  sale.  It  is  creating  a  ‘need’  that  BC  Hydro  is  arguing  has  to  be  met  with  high  cost  new  sources  of  supply.      On  the  supply  side,  a  key  factor  underlying  BC  Hydro’s  determination  of  need  is  its  elimination   of   the   existing  natural   gas-­‐fired  Burrard  Thermal   plant   as   a   source   of  back-­‐up   energy   capability   and,   after   2017,   as   a   source   of   dependable   peak  generating  capacity.      Prior  to  the  2008  Long  Term  Acquisition  Plan  (LTAP)  hearing  when  BC  Hydro  raised  the   issue   of   what   capability   it   should   assume   for   Burrard,   BC   Hydro   assumed   an  energy  capability  of  6100  GWh  and  900  MW  of  capacity  from  Burrard.10  For  many  years,   BC   Hydro   has   not   intended   nor   in   fact   operated   Burrard   at   its   6100   GWh  energy  capability.  Annual  production  since  2001  has  been  less  than  1000  GWh  per  year;  in  most  years  considerably  so.11  It  planned  on  the  potential  for  a  high  level  of  production,   however,   in   order   that   it   could   reliably   take   greater   advantage   of   –                                                                                                                  8  BC  Hydro,  Draft  Integrated  Resource  Plan,  Chapter  8,  p.8-­‐50.  9  Ibid.,  Chapter  3,  pp.  3-­‐86  to  3-­‐87.  10  BC  Utilities  Commission,  In  the  Matter  of  BC  Hydro  and  the  2006  Integrated  Electricity  Plan  and  Long  Term  Acquisition  Plan,  May  11,  2007,  p  69.  11  BC  Utilities  Commission,  In  the  Matter  of  BC  Hydro  and  an  Application  for  Approval  of  the  2008  Long  Term  Acquisition  Plan,  Decision,  July  27,  2009,  p.90.  

Page 11: Via email Via email - Canada.ca · 200 – 2006 West 10th Avenue Vancouver, BC V6J 2B3 tel: 604.684.7378 fax: 604.684.1312 toll free: 1.800.330.WCEL (in BC) email: admin@wcel.org

  8  

essentially  backstop  or  “firm  up”  –  non-­‐firm  hydro  as  well  as  low  cost  spot  market  supply.      When   water   conditions   were   favourable,   non-­‐firm   energy   was   used   in   lieu   of  Burrard   operation   to   meet   requirements.   If   there   were   no   non-­‐firm   and   in   any  event,   low   cost   spot   market   supply,   when   available,   could   opportunistically   be  acquired  and  used  to  meet  requirements  in  lieu  of  Burrard.  This  use  of  non-­‐firm  and  spot  market   supply  was   very   economic   because   it   enabled  BC  Hydro   to   defer   the  need   for   costly   new   sources   of   supply.   The   non-­‐firm   and   spot  market   energy   are  typically   very   low   cost   sources   of   supply,   and  with   the   thermal   back   up   they   can  reliably   be   used   because   if   non-­‐firm   energy   were   not   available   and   spot   market  supply  were   restricted  or  not   attractively  priced,   requirements   could   still   be  with  the  back-­‐up  thermal  supply.    In   addition   to   assuming   6100   GWh   of   back-­‐up   capability   at   Burrard,   BC   Hydro  historically  assumed  a  firm  ability  to  acquire  up  to  2500  GWh  of  spot  market  energy  to  meet   requirements.12   In   total,   it   assumed  a   combined  Burrard   thermal  back-­‐up  plus   market   allowance   of   8600   GWh   when   assessing   whether   or   when   new  resources  were  required.    In   its  current  assessment  of   the  need  for  Site  C,  BC  Hydro  has  assumed  that   it  can  acquire   up   to   4100   GWh   of   spot   market   energy   to   meet   its   requirements.   It  effectively  made  this  assumption  by  basing  its  hydro  supply  on  average  as  opposed  to   critical  water   conditions   (4100  GWh  being   the  difference  between  average  and  critical   or   firm   hydro   supply).13   However,   because   it   has   eliminated   Burrard   as   a  potential  source  of  supply,  it  has  assumed  no  ability  to  ‘firm  up’  potential  non-­‐firm  or  rely  on  more  spot  market  supply  beyond  4100  GWh.  BC  Hydro’s  current  market  allowance   of   4100   GWh   is   4500   GWh   less   than   the   8600   GWh   thermal   back-­‐up/  market  allowance  it  used  to  assume.    The   elimination   of   Burrard   as   a   source   of   supply  was   forced   on  BC  Hydro   by   the  government’s   Clean   Energy   Act   and   related   regulation   –   legislative   direction   not  supported  by   the  BC  Utilities   Commission,   all   intervenors   except   for   IPPBC   at   the  2008  LTAP  hearing,  and  not  even  by  BC  Hydro  itself.14    The  BC  Utilities  Commission  concluded   that  with   sustaining  capital   and  O&M,   the  Burrard  Thermal  plant   could  provide  900  MW  of  peak  generating  capacity  and  at  least  5000  GWh  of  energy  in  its  traditional  role  as  a  back-­‐up  to  the  hydro  system.15    

                                                                                                               12  BC  Utilities  Commission,  In  the  Matter  of  BC  Hydro  and  the  2006  Integrated  Electricity  Plan  and  Long  Term  Acquisition  Plan,  May  11,  2007,  p  57.  13  BC  Hydro,  Site  C  Clean  Energy  Project  Evidentiary  Update,  Figure  1,  p.18.  14  BC  Hydro  recommended  in  the  2008  LTAP  hearing  that  Burrard  should  be  maintained  to  provide  900  MW  of  capacity  and  3000  GWh  of  back-­‐up  energy  capability.  15  BC  Utilities  Commission,  In  the  Matter  of  BC  Hydro  and  an  Application  for  Approval  of  the  2008  Long  Term  Acquisition  Plan,  Decision,  July  27,  2009,  pp.113-­‐116.  

Page 12: Via email Via email - Canada.ca · 200 – 2006 West 10th Avenue Vancouver, BC V6J 2B3 tel: 604.684.7378 fax: 604.684.1312 toll free: 1.800.330.WCEL (in BC) email: admin@wcel.org

  9  

Had  BC  Hydro  been  allowed  to  continue  to  recognize  the  historic  role  of  Burrard  and  retain  a   combined   thermal  back-­‐up  plus  market   allowance  of  8600  GWh,   the   load  resource   balance  would   be   very   different.  As   shown   in  Table   1,   instead   of   energy  shortfalls   starting   in   2027,   there   would   be   no   forecast   shortfall   for   non-­‐LNG  requirements   until   2033,   the   last   year   of   BC   Hydro’s   planning   period.   And   if   BC  Hydro   were   allowed   to   recognize   a   thermal   back-­‐up/market   allowance   equal   to  9100   GWh   –   the   sum   of   the   4100   GWh   BC   Hydro   assumes   it   can   acquire   in   the  market  plus  the  5000  GWh  of  Burrard  back-­‐up  capability  the  BCUC  recommended  in  its  2008  LTAP  decision,  there  would  be  no  shortfall  until  beyond  2033.  

   

Table  1  Energy  Load  Resource  Balance  

without  LNG  -­shortfalls  in  GWh-­  

(surpluses  shown  in  parentheses)    

Year   BCH  Current  Market  Allowance:  

4100  GWh16  

Historic  Thermal  Back-­up  /  Market  

Allowance:  8600  GWh  

BCH  Current  Mkt  Allowance  plus  

BCUC  Burrard  Rec.:  9100  GWh  

F2017   (5000)   (9500)   (10000)  F2018   (3700)   (8200)   (8700)  F2019   (2800)   (7300)   (7800)  F2020   (2400)   (6900)   (7400)  F2021   (2200)   (6700)   (7200)  F2022   (1800)   (6300)   (6800)  F2023   (1100)   (5600)   (6100)  F2024   (700)   (5200)   (5700)  F2025   (300)   (4800)   (5300)  F2026   (300)   (4800)   (5300)  F2027   200   (4300)   (4800)  F2028   900   (3600)   (4100)  F2029   1800   (2700)   (3200)  F2030   2600   (1900)   (2400)  F2031   3300   (1200)   (1700)  F2032   4200   (300)   (800)  F2033   4900   400   (100)  

     

                                                                                                               16  BC  Hydro  LRB  estimates  in  BC  Hydro,  Site  C  Clean  Energy  Project  Evidentiary  Update,  Table  5,  pp.  12-­‐13.  

Page 13: Via email Via email - Canada.ca · 200 – 2006 West 10th Avenue Vancouver, BC V6J 2B3 tel: 604.684.7378 fax: 604.684.1312 toll free: 1.800.330.WCEL (in BC) email: admin@wcel.org

  10  

With  respect  to  peak  requirements,  as  shown  in  Table  2,  if  BC  Hydro  had  been  able  to   recognize   the   peak   generating   capacity   that   the   Burrard   thermal   plant   could  provide,   there  would  be  no  shortfalls  of   capacity   in   the  2020-­‐2024  period   that  BC  Hydro   is   currently   forecasting,   and   no   need   for   additional   capacity   to  meet   peak  loads  (without  LNG)  until  2029.  That  is  the  same  year  in  which  new  capacity  would  be  required  even  with  the  development  of  Site  C.    

 Table  2  

Capacity  Load  Resource  Balance  Without  LNG  

-­shortfalls  in  MW-­  (surpluses  shown  in  parentheses)  

 Year   BC  Hydro  Forecast  without  

Burrard17  Forecast  with  Burrard  

F2017   (250)   (1150)  F2018   (100)   (1000)  F2019   -­‐-­‐   (900)  F2020   100   (800)  F2021   100   (800)  F2022   150   (750)  F2023   300   (600)  F2024   400   (500)  F2025   500   (400)  F2026   550   (350)  F2027   700   (200)  F2028   850   (50)  F2029   1000   100  F2030   1150   250  F2031   1350   450  F2032   1550   650  F2033   1750   850  

     

2.3   Conclusion  with  Respect  to  Need    There  is  a  need  for  new  supply  based  on  BC  Hydro’s  forecasts  of  requirements  and  estimates   of   supply.   That   need   is   in   part   a   reflection   of   the  market   failure   in   the  pricing   of   electricity   and   the   economically   inefficient   load   growth   that   can   cause.  Primarily,   however,   it   is   due   to   the   elimination  of  Burrard   as   a   source  of   back-­‐up  energy  and  dependable  peak  generating  capacity.  Eliminating  Burrard  was  not  done  

                                                                                                               17  Ibid.,  Table  6,  p.13.  

Page 14: Via email Via email - Canada.ca · 200 – 2006 West 10th Avenue Vancouver, BC V6J 2B3 tel: 604.684.7378 fax: 604.684.1312 toll free: 1.800.330.WCEL (in BC) email: admin@wcel.org

  11  

for   technical,   economic   or   well-­‐documented   environmental   reasons,   nor   was   it  recommended   by   the   BCUC   or   broadly   supported.   It   was   a   directive   imposed   by  government  without  any  supporting  analysis  or  justification.    Eliminating   Burrard   has   greatly   reduced   BC   Hydro’s   ability   to   reliably   and   cost-­‐effectively  take  advantage  of  non-­‐firm  supply  and  low  cost  spot  market  supplies  to  meet  requirements.  The  need  for  new  supply  at  least  with  respect  to  non-­‐LNG  loads  is  basically  a  need  to  replace  what  was  lost  by  the  elimination  of  Burrard.    As   for   LNG,  BC  Hydro  has   indicated   there   is   a   great  deal   of   uncertainty   regarding  what   amount   of   electricity   it  may   be   called   upon   to   supply.   However,   because   of  transmission  constraints  between  Prince  George  and  the  North  Coast,  BC  Hydro   is  not   proposing   to   build   a   project   like   Site   C   to  meet   LNG   loads.     As   it   stated   in   its  Evidentiary  Update:  “BC  Hydro  believes  that  the  unique  requirements  of  potential  LNG  customers  may  be  better  served  by  north  coast  supply”.18    

                                                                                                               18  Ibid.,  p.8.  

Page 15: Via email Via email - Canada.ca · 200 – 2006 West 10th Avenue Vancouver, BC V6J 2B3 tel: 604.684.7378 fax: 604.684.1312 toll free: 1.800.330.WCEL (in BC) email: admin@wcel.org

  12  

3.0   Site  C  versus  Alternatives       3.1   BC  Hydro’s  Analysis    Based  on  a  technical  and  economic  screening  of  potential  resources,  and  subject  to  the   constraints   in   the   Clean   Energy   Act,   BC   Hydro   developed   two   portfolios   that  could  serve  as  alternatives  to  its  proposed  Site  C  project:  (i)  a  clean  energy  portfolio  consisting   of   wind   and   municipal   solid   waste   energy   resources   combined   with  additions   of   generating   capacity   at   Revelstoke   and   GMS,   plus   additional   Power  Smart   initiatives   to   reduce   capacity   requirements;   and   (ii)   a   clean   plus   thermal  portfolio   consisting   of   a   similar   mix   of   wind   and   municipal   solid   waste   energy  resources,   combined   with   additional   generating   capacity   at   Revelstoke   and   new  capacity  from  single  cycle  gas  thermal  (SCGT)  plants.   In  a  variant  of  the  clean  plus  thermal   portfolio,   there   is   additional   generating   capacity   at   GMS   and   a   smaller  amount  from  SCGTs.19    BC   Hydro   compared   Site   C   with   these   two   alternatives   in   terms   of   their   present  value   system   costs,   environmental   attributes   and   economic   impacts.   It   concluded  that   Site   C   was   preferred   as   it   offered   lower   present   value   system   costs,   greater  economic   development   and   employment   impacts,   and   comparatively   low   GHG  emissions.20    Under  BC  Hydro’s  base  case  set  of  assumptions,  the  magnitude  of  the  cost  advantage  of   Site  C   if  developed  as  proposed   for  2024,  was   relatively   small   compared   to   the  clean   plus   thermal   portfolio   ($150  million   in   present   value).   It  was   greater  when  compared  to  the  clean  portfolio  ($630  million).  The  cost  advantage  of  Site  C  in  both  cases  was  greater  if  the  in-­‐service  date  was  delayed  until  2026.21       3.2   Underlying  Factors    While  BC  Hydro  states  that  the  preference  for  Site  C  is  based  on  its  environmental  attributes   and   employment   impacts   as  well   cost   advantage,   it   did   not   provide   an  assessment  of  relative  significance  of  the  different  environmental  attributes,  nor  did  it  provide  any  assessment  or  analysis  of  the  net  benefits  of  the  employment  impacts.  Given   the   widely   held   expectation   of   shortages   of   construction   and   skilled   trade  workers  in  the  province22  and  the  competing  demands  from  other  projects,  it  is  not  clear  there  would  be  any  significant  net  benefit  from  the  employment  impacts  that  Site  C  would  generate  (indeed  there  could  be  a  cost  because  of  the  added  pressure  it  

                                                                                                               19  Ibid.,  Tables  14,  15  and  16,    pp.  34-­‐36.  20  Ibid.,  Tables  12,  17  and  18,  pp.  31-­‐39.  21  Ibid.,  Figure  2  and  Table  12,  pp.30-­‐31.  22  See,  e.g.,  WorkBC,  BC  Labour  Market  Conditions,  2010-­2020,  which  forecasts  shortages  of  workers  province-­‐wide  by  2016  and  sooner  on  a  regional  basis.  

Page 16: Via email Via email - Canada.ca · 200 – 2006 West 10th Avenue Vancouver, BC V6J 2B3 tel: 604.684.7378 fax: 604.684.1312 toll free: 1.800.330.WCEL (in BC) email: admin@wcel.org

  13  

would  bring  to   labour  markets   in   the  province).23    The  preference   for  Site  C   in  BC  Hydro’s  analysis  derives  solely  from  its  estimated  lower  system  cost.    The  lower  net  system  cost  is  due  to  the  significantly  lower  unit  cost  of  energy  that  BC  Hydro  estimated  for  Site  C  as  compared  to  the  renewable  energy  resources  in  the  alternative  portfolios.  The  output   from  Site  C  also   is  higher   in  value  than  what  the  renewables  offer,  providing  dependable  capacity  as  well  as  energy  plus  the  ability  to  shape  production  into  higher  valued  seasons  and  time  periods.    In  BC  Hydro’s  base  case   analysis   these   advantages   outweigh   Site   C’s   disadvantages   –   its   high   capital  cost  and  large  size  relative  to  the  annual  load  growth  it  will  serve.  In  the  initial  years  much  of  Site  C’s  output  will  be  surplus  to  requirements  and  sold  at  forecast  market  prices   far   less   than   its   unit   energy   cost.   The   main   advantage   of   the   alternative  portfolios   is   that   the   resources   can  be  brought   into   service   in   smaller   increments,  matched  better  to  load  growth.    The   sensitivity   case   results   confirm   these   advantages   and  disadvantages  of   Site  C.  The  smaller  the  gap  that  needs  to  be  filled  and  the  lower  forecast  market  prices,  the  greater  is  the  cost  of  the  lumpiness  and  the  less  favoured  is  Site  C  compared  to  the  alternatives.    For  similar  reasons,  the  earlier  the  in-­‐service  date  for  Site  C  the  less  of  a  cost  advantage  does  it  exhibit.  Also,   though  not  shown  in  BC  Hydro’s  results,   the  higher   the   assumed  discount   rate   the   less   favoured  would   Site   C   be.   By   the   same  token,  the  greater  the  gap,  the  higher  forecast  market  prices,  the  later  its  in-­‐service  date  and  the  lower  the  discount  rate,  the  more  favoured  would  Site  C  be.24    The  cost  advantage  of  Site  C   is  most  pronounced  relative  to  the  clean  portfolio.   Its  cost   advantage   relative   to   the   clean   plus   thermal   portfolio   is   much   less,   and  dependent   on   the   LRB   gap,   market   price,   capital   cost   and   in-­‐service   date  assumptions  BC  Hydro  used  in  the  analysis.      The  SCGTs   in   the  clean  plus   thermal  portfolio  offer   capacity   that   is   competitive   in  cost   and   can   be   strategically   located   to   reduce   transmission   requirements   and  expenditures.  They  also  offer  much  lower  cost  energy  compared  to  the  renewables  they   would   displace,   even   with   the   GHG   offset   costs   that   were   included.   In   its  analysis,   BC   Hydro   assumed   that   the   SCGTs   would   be   operating   to   meet   peak  requirements,  with  a  resulting  capacity  factor  of  approximately  18%.  The  588  MW  of   SCGT   capacity   in   the   clean   plus   thermal   portfolio   would   produce   924   GWh   of  

                                                                                                               23  It  is  well  understood  by  economists  that  economic  impacts  (as  BC  Hydro  estimated  for  its  portfolio  analysis)  do  not  in  themselves  constitute  economic  benefits.  Economic  benefits  depend  on  the  origin  and   opportunity   cost   of   those   hired   as   a   result   of   any   project.   In   tight   labour   markets,   a   large  percentage  of  the  workers  may  come  from  outside  the  jurisdiction  and  the  opportunity  costs  of  those  hired  can  be  very  high.  See  P.  Grady  and  R.  Muller,   “On   the  Use  and  Misuse  of   Input-­‐Output  Based  Impact  Analysis  in  Evaluation”,  Canadian  Journal  of  Program  Evaluation,  Vol.  3,  No.  2,  1968  for  a  discussion  of  the  fundamental  difference  between  impact  and  benefit-­‐cost  analysis.    24  BC  Hydro,  Site  C  Clean  Energy  Project  Evidentiary  Update,  Table  24,  p.48.  

Page 17: Via email Via email - Canada.ca · 200 – 2006 West 10th Avenue Vancouver, BC V6J 2B3 tel: 604.684.7378 fax: 604.684.1312 toll free: 1.800.330.WCEL (in BC) email: admin@wcel.org

  14  

energy  at  an  estimated  energy  cost  almost  half  that  of  the  renewables  and  roughly  three  quarter  that  of  Site  C.25    What  BC  Hydro  did  not  consider  in  its  analysis  is  the  role  that  the  SCGTs  could  play  in  backing  up  non-­‐firm  energy  and  spot  market  supplies.   In  other  words,   they  did  not   consider   how   the   SCGTs   could   replace  what  was   lost   with   the   elimination   of  Burrard.    While  one  would  not  expect  SCGTs  to  operate  at  higher  capacity  factors  than  needed  to  meet  peak  requirements,  they  could  in  practice  do  so  if  and  when  required.  And  just  like  Burrard,  their  ability  to  do  so  would  provide  a  physical  back-­‐up  to  non-­‐firm  or  spot  market  supplies.  At  a  90%  capacity  factor,26  the  588  MW  of  SCGT  capacity  in  the  clean  plus  thermal  alternative  would  have  the  potential  to  produce  4635  GWh  –  or  some  3700  GWh  more  than  what  BC  Hydro  assumed  would  be  generated  for  peak  operations.   That   3700   GWh   is   an   indication   of   the   energy   back-­‐up   potential   the  SCGTs  offer.    Recognizing  3700  GWh  of  back-­‐up  potential  would  enable  BC  Hydro  to  increase  its  thermal  back-­‐up/market  allowance  from  4100  GWh  to  7800  GWh,  an  amount  closer  to  what  it  assumed  in  the  past.  Had  BC  Hydro  taken  that  into  account  in  its  analysis,  it   would   have   greatly   reduced   the   need   for   additional   supply.   Indeed,   the   SCGTs,  both   in   what   they   might   produce   on-­‐peak   and   the   thermal   back-­‐up   /market  allowance   they   enable,   would   eliminate   BC   Hydro’s   forecast   shortfalls   of   energy  (without   LNG)   until   2033.     And   the   SCGTs   plus   the   development   of   additional  capacity   at   Revelstoke   would   eliminate   BC   Hydro’s   forecast   shortfalls   of   capacity  (without  LNG)  until  2029,  the  same  as  what  Site  C  would  do.    Such   an   SCGT   ‘thermal   back-­‐up’   strategy   would   effectively   address   the   primary  reason  for  the  forecast  shortfalls  –  the  elimination  of  Burrard.  It  would  be  far  better  than  the  clean  plus  thermal  portfolio  BC  Hydro  analyzed  because  it  would  enable  BC  Hydro   to   take   greater   advantage   of   the   potentially   large   amount   of   non-­‐firm  supply27  as  well  as  low  cost  spot  market  energy.  And,  as  with  Burrard,  it  could  do  so  with  no  physical  supply  risk.      Had  BC  Hydro  analyzed  this  strategy,  with  the  SCGT  energy  capability  reflected  in  a  larger  thermal  back-­‐up/  market  allowance,   it  would  almost  certainly  have  found  it  

                                                                                                               25  Ibid.,  Table  15,  p.35.  26   The   North   American   Electric   Reliability   Corporation   Generation   Availability   Report,   2009  indicates  availability  rates  for  SCGT-­‐size  thermal  plants  in  the  90-­‐92%  range  over  the  2004  to  2008  period.    The  link  to  that  report  can  be  found  at:    http://www.nerc.com/pa/RAPA/gads/Pages/default.aspx  27  Historical  water  flow  records  indicate  that  BC  Hydro’s  own  generating  plants  could  produce  up  as  much  as  12,000  GWh  in  excess  of  its  firm  hydro  supply.  In  the  Evidentiary  Update  BC  Hydro  reports  that  with  climate  change  the  amount  of  non-­‐firm  from  BC  Hydro’s  plants  may  increase.  In  addition,  BC  Hydro  estimates   that   the  non-­‐firm  energy   from  IPPs  under  contract  by  2017  will  average  some  2100  GWh  per  year  (Draft  Integrated  Resource  Plan,  p.2-­‐24).  

Page 18: Via email Via email - Canada.ca · 200 – 2006 West 10th Avenue Vancouver, BC V6J 2B3 tel: 604.684.7378 fax: 604.684.1312 toll free: 1.800.330.WCEL (in BC) email: admin@wcel.org

  15  

to  be  more  cost  effective  than  Site  C  under  a  wide  range  of  assumptions.  Replacing  the  back-­‐up  function  of  Burrard  would  essentially  eliminate  the  need  for  Site  C  and  the   major   capital   expenditures   it   entails   within   the   planning   period.   The   system  studies  with   and  without  different   amounts  of   back-­‐up   energy   at  Burrard   that  BC  Hydro  undertook   for   the  2008  LTAP   suggest   that   the   cost   advantage  of   this   SCGT  strategy  could  be   in  excess  of  $1  billion.28  The  difference   in   the  unit   cost  of  Site  C  and   the   non-­‐firm   or   spot   market   purchases   the   SCGT   thermal   back-­‐up   strategy  enable  would  also  suggest  potential  savings  of  that  order  of  magnitude  or  more.29      BC  Hydro   is   constrained  by   the   self-­‐sufficiency  and  93%  clean   requirement   in   the  Clean  Energy  Act.  However,  as  BC  Hydro  itself  noted  there  is  some  ambiguity  as  to  the  interpretation  of  these  requirements.30  One  could  argue  that  this  SCGT  thermal  back-­‐up   strategy   does   satisfy   these   constraints.   BC   Hydro   would   have   the   firm  capability   to  meet   its   forecast   requirements  with  BC  resources,   satisfying   the  self-­‐sufficiency   requirement.   At   the   same   time,   it   would   not   expect   to   operate   the  thermal   plants   as  much   as   their   capability   because   of   the   expected   availability   of  non-­‐firm   plus   spot   market   supply   that   could   economically   displace   the   thermal  production.  In  terms  of  what  BC  Hydro  would  expect  to  generate  in  the  province,  it  could  satisfy  the  93%  clean  requirements.31      BC  Hydro  rejected  this  interpretation  of  the  requirements,  based  on  its  assessment  of  the  intention  of  the  Act.  However,  it  is  not  clear  there  is  a  legal  imperative  to  do  so.  At  a  minimum,  before  BC  Hydro  embarks  on  a  plan  that  could  result  in  $1  billion  or  more  in  additional  system  costs,   it  should  seek  explicit  direction  on  this  matter,  making  very   clear  why   ratepayers   and  arguably   the  general  public   interest  would  best  be  served  by  an  interpretation  that  would  permit  BC  Hydro  to  cost-­‐effectively  use   the   thermal   back-­‐up   capability   of   SCGTs   to   replace  what  was   in   lost  with   the  elimination  of  Burrard.    

                                                                                                               28  BC  Utilities  Commission,  In  the  Matter  of  BC  Hydro  and  an  Application  for  Approval  of  the  2008  Long  Term  Acquisition  Plan,  Decision,  July  27,  2009,  Table  5-­‐8,  p.108.  29  BC  Hydro’s  market  forecasts  suggest  that  the  cost  saving  from  using  non-­‐firm  and  spot  supplies  as  opposed  to  a  new  source  like  Site  C  could  be  in  the  order  of  $50/MWh.  The  3700  GWh  of  non-­‐firm  and/or  spot  supply  that  the  SCGTs  could  back-­‐up  could  therefore  offer  a  saving  of  some  $185  million  per  year.  As  well   this  SCGT  back-­‐up   strategy  would  avoid   the   cost  of   the   lumpiness  of   Site  C  –   the  losses  that  would  be  incurred  on  the  supply  Site  C  generates  in  excess  of  requirements.  While  system  studies   are   required   to   confirm   the   exact   magnitude   of   the   saving   it   is   clear   they   could   be  considerable.  30  BC  Hydro,  Draft  Integrated  Resource  Plan,  Chapter  6.  pp.  6-­‐6  to  6-­‐8.  31   Nor   should   it   be   assumed   that   this   strategy  would   simply   increase   thermal   production   outside  British  Columbia.  Much  of   the   lowest  cost   spot  supply  comes   from  renewable  resources  –   the  very  large  amount  of  surplus  freshet  hydro  power  typically  available  in  the  U.S.  Pacific  Northwest   in  the  spring   time   and   the   increasing   amount   of   surplus   wind   energy   that   is   generated   in   neighbouring  jurisdictions  when   high  wind   events   coincide  with   light   load   hour   periods   or   for   other   reasons   is  surplus  to  requirements.  

Page 19: Via email Via email - Canada.ca · 200 – 2006 West 10th Avenue Vancouver, BC V6J 2B3 tel: 604.684.7378 fax: 604.684.1312 toll free: 1.800.330.WCEL (in BC) email: admin@wcel.org

  16  

  3.3   Conclusion  with  Respect  to  Alternatives    BC  Hydro’s  analysis  indicates  that  Site  C  would  be  more  cost-­‐effective  than  the  clean  and   clean   plus   thermal   portfolio   alternatives   it   examined.   However,   Site   C   is   not  more  cost-­‐effective   than  the  much  better  alternative  of  using  SCGTs  to  restore   the  thermal  back-­‐up  capability  that  BC  Hydro  lost  with  the  elimination  of  Burrard.  Non-­‐firm  and  opportunistically  acquired  spot  market  supplies  are  far  less  costly  than  Site  C   or   any   new   sources   of   supply.   Strategies   that   enable   BC   Hydro   to   take   better  advantage   of   those   low   cost   sources,   which   if   anything   are   expected   to   be  increasingly   available   with   the   development   of   wind   and   other   intermittent  resources,  offer  a  much  more  cost-­‐effective  way  to  meet  requirements.      Provided  the  SCGT  thermal  back-­‐up  strategy  is  in  fact  consistent  with  the  provisions  of  the  Clean  Energy  Act,  as  arguably  it  should  be,  it  could  be  $1  billion  or  more  less  costly  than  what  BC  Hydro  has  proposed  with  its  Site  C  development  plan  to  meet    forecast  non-­‐LNG  requirements.      As  for  LNG,  as  noted  earlier,  BC  Hydro  believes  that  these  requirements,  should  it  be  called  upon  to  supply  them,  would  better  be  met  by  north  coast  supply.  BC  Hydro  is  not   proposing   to   build   Site   C   to  meet   LNG   requirements,   nor   did   its   alternatives  analysis   address   the   relative   advantages   of   different   portfolios   and   strategies   for  that.  If  BC  Hydro  decides  that  in  fact  it  wants  to  develop  Site  C  not  because  it  is  the  most   cost   effective  way   to  meet  non-­‐LNG   requirements   (which   it   isn’t)   but   rather  because  it  can  best  accommodate  potential  LNG  demands,  a  new  set  of  issues  need  to  be   addressed   (including   transmission   requirements,   pricing,   and   the   risk   to  BC  Hydro   and   ratepayers   of   stranded   assets).   As   well,   analyses   comparing   a   much  broader  set  of  alternatives  would  need  to  be  undertaken.      

Page 20: Via email Via email - Canada.ca · 200 – 2006 West 10th Avenue Vancouver, BC V6J 2B3 tel: 604.684.7378 fax: 604.684.1312 toll free: 1.800.330.WCEL (in BC) email: admin@wcel.org

  17  

4.0   Concluding  Remarks    

1. The   need   for   new   supply   is   policy   driven   –   it   is   a   direct   result   of   the  elimination  of  the  Burrard  plant  as  a  source  of  back-­‐up  energy  and  capacity.  The   government   would   be   well-­‐advised   to   reconsider   the   elimination   of  Burrard   as   a   source   of   back-­‐up   energy   given   the   very   significant  consequences   that   has,   and   particularly   since   it   is   directly   counter   to   the  recommendation   of   the   BCUC   and   the   positions   taken   by   all   intervenors  except  IPPBC  at  the  2008  LTAP  hearing.    

2. Government   would   be   well-­‐advised   to   consider   the   very   serious   market  failure  in  the  pricing  of  electricity,  most  significantly  in  the  industrial  sector,  and  the  effect  it  has  in  encouraging  economically  inefficient  load  growth.  

 3. Site  C  is  not  the  preferred  way  to  meet  the  LRB  shortfalls  (without  LNG)  that  

BC  Hydro  has  forecast.  A  more  cost-­‐effective  strategy  is  to  replace  what  was  lost  with  the  elimination  of  Burrard  with  the  energy  backup  capability  from  new  SCGTs.    

   4. It   is   important   to   note   that   BC   Hydro   is   not   proposing   to   build   Site   C   to  

supply   new   LNG   requirements,   should   they   emerge,   nor   has   BC   Hydro  supplied  the  portfolio  analysis  that  would  support  such  a  position.    

 5. If  there  is  ambiguity  about  the  interpretation  of  the  restrictions  imposed  by  

the  Clean   Energy   Act,   BC  Hydro   should   seek   clarification   from   government  (and   possibly   reconsideration   of   the   restrictions   themselves),   and   in   the  process   clearly   inform   government   of   the   cost   and   other   implications   of   a  position   that   would   preclude   the   cost-­‐effective   use   of   the   energy   back-­‐up  capability  of  SCGTs.        

 6. In   summary,  with   regard   to   the  key  questions   this   report  has  attempted   to  address:    There   would   be   no   need   for   new   supply   had   BC   Hydro   not   eliminated  Burrard  as  a  source  of  back-­up  energy  and  dependable  capacity.    BC  Hydro’s  conclusion  that  Site  C  is  the  preferred  source  to  meet  the  need  is   due   to   the   restrictive   nature   of   the   clean   plus   thermal   portfolio   it  analyzed.    A  strategy  of  using  the  back-­up  capability  of  SCGTs  to  restore  much  of  the  combined   thermal   back-­up   /   market   allowance   that   was   lost   with   the  elimination  of  Burrard  would  be  a   far  more  cost-­effective   strategy   than  the  development  of  Site  C  in  the  foreseeable  future.  

 There  is  not  a  need  and  justification  for  Site  C  as  proposed  by  BC  Hydro.