Vestas 3MW Platform Update - EJKrauseejkrause.com.mx/mwpcamps/bitacorapdf/24-WarwickHeaney.pdf ·...

12
Vestas 3MW Platform Update Warwick Heaney, Technical Bid Manager Brazil and Mexico

Transcript of Vestas 3MW Platform Update - EJKrauseejkrause.com.mx/mwpcamps/bitacorapdf/24-WarwickHeaney.pdf ·...

Vestas 3MW Platform Update Warwick Heaney, Technical Bid Manager Brazil and Mexico

The power of data Vestas applies learnings from 27,000 WTGs worldwide to deliver quality products, world-class siting capabilities, and maintenance.

15%

Almost 15% of the total global accumulated installed base under surveillance

PRODUCT DESIGN

Data is the fundamental prerequisite for a design life of 20+ years

VALIDATION TESTING

Data ensures that accelerated lifetime simulations on key components are as realistic as possible

PROJECT SITING

Data enables siting to optimise component loads and production

SOURCING & PRODUCTION

Data ensures that the most significant CtQs (critical-to-quality) are thoroughly managed in manufacturing

OPERATIONS & MAINTENANCE

Data allows us to (through condition monitoring) implement timely predictive maintenance, thereby minimising lost production

Turbines under surveillance feed back data to the rest of Vestas value chain

Knowing wind better than anyone else translates into superior products and

capabilities

Data turned into insights via the Vestas supercomputer Firestorm

Upgraded 3 MW platform variants Increased AEP in all wind classes

V105-3.45 MW™ V112-3.45 MW™ V117-3.45 MW™

• Proven performance in high wind

• Hub heights to accomodate tip height restrictions

• Same blade family • Power modes

V126-3.45 MW™

• Strong performance in medium wind

• Available in a low noise variant (104.5 dBA)

• Large Diameter Steel Tower (LDST) available

V136-3.45 MW™

• Efficient and high energy production in low wind conditions (4270 equiv hrs)

• Advanced aerofoil • 105.5 dbA in noise mode • LDST available

Up to +10% AEP**

Up to +7% AEP*

Up to +12%

AEP***

* Site specific; compared to V112-3.3MW® IEC 2A ** Site specific; compared to V117-3.3MW® IEC 2B *** Site specific; compared to V126-3.3MW®

Boosting AEP performance in all wind classes Platform upgrade enables wind class upgrade

110m

120m

130m

3.0 MW 3.3 MW 3.45 MW

V117-3.45 MW™

V126-3.45 MW™

V136-3.45 MW™

V126-3.3 MW®

V117-3.3 MW®

V112-3.3 MW® V112-3.0 MW®

+12% AEP* Rotor size

Rating

IEC 3

IEC 2

IEC 1

*AEP=Annual Energy Production. Actual figures depend on site specific conditions.

Latest evolution on 3 MW platform Supporting wind class upgrades, increasing nominal power to 3.45 MW

Structural upgrade • Optimisation of load carrying structure

for higher rating and wind class upgrade

Drive train • Upgraded version of gearbox accommodated

to enable V136-3.45 MW™ and a low sound power V126-3.45 MW™ variant

Converter • Optimised industrial design • Enabling higher rating

Rotor • New 136 m structural shell

Future ready. Control system • Flexible and future ready

system setup based on industry 4.0 standards

• Ethernet based deterministic network

V112-3.45 MW™

9,852 m² swept area

• Introduced as V112-3.0 MW turbine for low wind in 2010

• Among the world’s most popular 3 MW turbines with more than 2,100 turbines installed*

• The upgraded V112-3.45 MW is suitable for high wind regimes

• Power modes available as option • HH 69m-84m available

*Installations include V112-3.0 MW® and V112-3.3 MW®.

V117-3.45 MW™

10,751 m² swept area

+7% AEP*

• Largest rotor for high wind sites in the Vestas turbine portfolio

• Increasing AEP on sites without tip height restrictions

• Power modes available as option • HH 80m-116.5m available

* compared to V112-3.3MW® IEC 2A

V126-3.45 MW™ IEC 2A Strong performance in medium wind, excellent sound power performance

• V126-3.45™ available for IEC 2A with a higher torque variant

• Max. sound power level at 104.5 dBA • Power modes available as option • HH 87m-166m available

* compared to existing IEC 2 class turbine (V117-3.3MW® IEC 2B)

+10% AEP*

104.5 dbA Noise mode 0

V136-3.45 MW™ rotor Advanced aerofoil design to increase lift and minimise drag

Vestas’ most advanced aerofoil design

Blade tips aerodynamically optimised for lower sound emissions

17% larger swept

area compared to V126-

3.3/3.45MW™

Swept area (m2)

3.5 MW 3.0 MW 4.0 MW

V136-3.45 MW™

E-126

GE130 SWT130

N131

Aerodynamics powered by wind data from 27,000 turbines under surveillance

V136-3.45MW™ features Vestas’ most advanced aerofoil to-date, designed specifically with cost of energy in mind. Improved aerodynamics enable improved lift to drag ratio, thereby improving AEP performance without adding load associated costs.

Swept area / Standard rating

Specific Rating

Key competitors with serial production scheduled in 2017

Key competitors with serial production scheduled in 2017

(W/swept area)

Outstanding Global Fleet Performance

Grid connection support Optimised grid compatibility and customised output control

Vestas’ Electrical PreDesign simulates plant performance and predicts generation levels for optimised grid compatibility and business case certainty

Optimised grid compatibility and control strategies

Vestas Power Plant Controller® accurately controls the output of the wind power plant at the Point of Common Coupling. The Vestas Power Plant Controller® is scalable and customisable

Vestas' Electrical PreDesign provides the surest way of building a productive and highly profitable wind power plant, and describes optimal control strategies for use with the Vestas Power Plant Controller®.

Copyright Notice The documents are created by Vestas Wind Systems A/S and contain copyrighted material, trademarks, and other proprietary information. All rights reserved. No part of the documents may be reproduced or copied in any form or by any means - such as graphic, electronic, or mechanical, including photocopying, taping, or information storage and retrieval systems without the prior written permission of Vestas Wind Systems A/S. The use of these documents by you, or anyone else authorized by you, is prohibited unless specifically permitted by Vestas Wind Systems A/S. You may not alter or remove any trademark, copyright or other notice from the documents. The documents are provided “as is” and Vestas Wind Systems A/S shall not have any responsibility or liability whatsoever for the results of use of the documents by you.

Thank you for your attention