S/N Description Page #

1 Table of Content 2

2 An Overview 3

3 Specized Activities / Operations 4-5

4 Safety Award Certificate 6

5 Copy of ISO 9001 : 2008 Certificate 7

6 Quality Policy 8

7 KNPC / KOC Category Approval status 9-10

8 List of Clients 11-12

9 List of Equipments, Vehicle & Machinery 13-14

10 List of Ongoing & Completed projects 15-24

11 Contact us 25

2

An OverviewSKS Group Co. W.L.L. is a corporate entity, rendering engineering, procurement & construction,

industrial maintenance, specized services and trading activities for Oil & Gas and Power sector in .

Over the years the company has grown as a dependable EPC building its assets base, including

skilled human resources. SKS Group is accredited with ISO 9001:2000 QUality management.

SKS Group was established by Mr. S K Shamsudeen, Founder & Managing Director as proprietary

company in 1980. Since the beginning, SKS Group has been in the fore-front, providing turnkey

engineering, procurement and construction of electromechanical works for Oil & Gas and other

Industrial sectors. Some of SKS Group's major customers are –

Kuwait Oil KOC

Kuwait National Petroleum KNPC

Petrochemical Industries PIC

EQUATE Petrochemical EQUATE

Kuwait Gulf Oil KGOC

Ministry of Energy MEW / MOE

Ministry of Defense MOD

SKS Group offers a wide range of construction services from concept to commissioning. With a

flexible and adaptive approach, the company is able to provide total solution to their clients.

3

Specialized Activities/ Operations

Providing Turnkey contracting services to Owners, Government, Ministry and many other international EPC contractors & private sector in Project Engineering, Construction Maintenance of Refinery units, petrochemical plants, Power Plants, Distillation units etc including refurbishment, repair, revamp of rotary, static equipment, valves, Manpower on secondmend,etc.,

Engineering & Construction

Civil & Structural :Design, Engineering and construction of buildings, Excavations, foundations, tank dykes, pre-cast concrete, geographical surveys, consultancy and all type of civil worksMechanical, Piping &Tank Construction :Piping fabrication and erection structural fabrication & erection, Equipment vessels & tank fabrication, heavy lifts, Critical Rigging and Equipments erection, pipinginstallation, start-up assistance and commissioningElectrical &Instrumentation: Installation of substation transformers and cabling, installation, calibration and commissioning of DCS, analogue and pneumatic process instrumentation.

MaintenanceCivil Maintenance: Maintenance of Tank Farm, Roads, and Foundations.Mechanical Maintenance :Piping refurbishment, repair, revamp of rotary, static equipment, valves etc.,Electrical &Instrumentation Maintenance :Maintenance services of power distribution,

Cabling, HT Transformers, HT&LT motors actuators, Switch gear motor control centers etc.,

4

Specialized & Support ServicesScaffolding and Access Systems:

Consultancy, installation, rental and removal in accordance with BS 1136 for materials and BS 5973 for erected systems of all types of access scaffolding. Hiring of equipments and / or skilled scaffolders.Insulation, Refractory and Fire Proofing:

Supply and application of Thermal (hot & cold) insulation to boilers, Turbines, piping, machinery, ducting etc., Refractory, Fire retarding and fire proofing barriers, Acoustic insulation.Blasting & Painting:

Painting System Design based on process temperature, Surface preparation by Automatic steel Shop blasting, manual grit blasting and /or power brushing and needle gunning, paint or coating application using air sprays, airless spray, brush or roller application.Procurement and Trading:

Activities to serve the Oil and Power sector – extensive pipe fittings, valves MOV, HVL & armored Electrical Cables etc,

5

6

7

Quality Policy Statement

SKS Group as an EPC contracting company is committed to meetcustomer expectations of quality and delivery in the most effective waythrough continual improvement of business process performance while

implementing good environmental and safety practices

Safety, Health & Environmental policySKS Group is committed to providing a safe and healthy environment

to all employees, clients and public considering the environmentalimpacts of our operations, activities, products and services

SKS Group will establish an effective environment managementprogram to minimize the impact on the environmental aspects and

the people who work and live in that environment.

SKS Group will strive to improve continually its processes incompliance with relevant safety, health and environment laws,

regulations and other applicable requirements by establishing andmeeting environmental targets and objectives

All employees are expected to understand, promote, and assist in theimplementation of this policy and the associated principles. We all are

accountable for conforming with anddeploying our SHE value and principles.

8

SN Approval CategoryRef. & Date Approval Category Contract Work Description

1 V/C-C1416-10-1375L dated 18.04.2010

5 02 A102.TANKS FOR PETROLEM PRODUCTS (TANK CONSTRUCTION & REPAIR) A1 CONSTRUCTION STEEL AND ALLOY TANKS

4 02 A3

02.TANKS FOR PETROLEM PRODUCTS (TANK CONSTRUCTION & REPAIR) A3 PLATE WELDING ROOF REPLACEMENT AND RE-BOTTOMING FOR FIXED & FLOATING ROOF TANKS

2 V/C-C-1416-07-2100L dated 02.09.2007

4 05 A105. PLANT INSTALLATION & MAINTENANCE A1. Plant Installations and Integrated Project Execution including Civil, Mechanical, Electrical & Instrument works

5 05 A105. PLANT INSTALLATION & MAINTENANCE : A1. Plant Installations and Integrated Project Execution including Civil, Mechanical, Electrical & Instrument works

3 V/C-C1416-07-0384L dated 17.03.2007

4 09 A109. INDUSTRIAL COATING & PLATING : A1 - Sand Blasting & Painting (Garnet & Grit / Shot blasting and Painting)

5 09 A109. INDUSTRIAL COATING & PLATING : A1 - Sand Blasting & Painting (Garnet & Grit / Shot blasting and Painting)

4 16 A1 16. INDUSTRIAL INSULATION & REFRACTORY WORKS : A1 - Insulation and Metal Sheet Works

5 16 A1 16. INDUSTRIAL INSULATION & REFRACTORY WORKS : A1 - Insulation and Metal Sheet Works

4 V/C-C-1416-05-0391 dated 23.03.2005

1 03 A103 - PIPING, VALVES AND ASSOCIATED WORKS : Field and Site Pipe Welding and Erection works A1 : Steel Pipes (Carbon / Alloy)

2 03 A103 - PIPING, VALVES AND ASSOCIATED WORKS : Field and Site Pipe Welding and Erection works A1 : Steel Pipes (Carbon / Alloy)

4-1 V/C-C-1416-05-0391 dated 23.03.2005

1 03 A203 - PIPING, VALVES AND ASSOCIATED WORKS : Field and Site Pipe Welding and Erection works A2 : Shop Fabrication

2 03 A203 - PIPING, VALVES AND ASSOCIATED WORKS : Field and Site Pipe Welding and Erection works A2 : Shop Fabrication

9

SN Approval CategoryRef. & Date Approval Category Contract Work Description

4-2 V/C-C-1416-05-0391 dated 23.03.2005

1 05 A105. PLANT INSTALLATION & MAINTENANCE A1. Plant Installations and Integrated Project Execution including Civil, Mechanical, Electrical & Instrument works

2 05 A105. PLANT INSTALLATION & MAINTENANCE A1. Plant Installations and Integrated Project Execution including Civil, Mechanical, Electrical & Instrument works

3 05 A105. PLANT INSTALLATION & MAINTENANCE A1. Plant Installations and Integrated Project Execution including Civil, Mechanical, Electrical & Instrument works

5 V/C-C-301-04-0964/4 dated 16.06.2004

'6-7 03 A103 - PIPING, VALVES AND ASSOCIATED WORKS : Field and Site Pipe Welding and Erection works A1 : Steel Pipes (Carbon / Alloy)

'6-7 03 A2 03 - PIPING, VALVES AND ASSOCIATED WORKS : Field and Site Pipe Welding and Erection works A2 : Shop Fabrication

'6-7 05 A105. PLANT INSTALLATION & MAINTENANCE A1. Plant Installations and Integrated Project Execution including Civil, Mechanical, Electrical & Instrument works

6 March 09, 2003

'6-7 09 A1 09. INDUSTRIAL COATING & PAINTING : A1 - Sand Blasting & Painting (Garnet & Grit / Shot blasting and Painting)

'6-7 14 A5 14. REFINERY PLANT MAINTENANCE AND SERVICES : A5 -Scaffolding services

'6-7 16 A1 16. INDUSTRIAL INSULATION & REFRACTORY WORKS : A1 -Insulation and Metal Sheet Works

7 'February 23, 2003

6 09 A1 09. INDUSTRIAL COATING & PAINTING : A1 - Sand Blasting & Painting (Garnet & Grit / Shot blasting and Painting)

6 14 A5 14. REFINERY PLANT MAINTENANCE AND SERVICES : A5 -Scaffolding services

6 16 A1 16. INDUSTRIAL INSULATION & REFRACTORY WORKS : A1 -Insulation and Metal Sheet Works

8 KOC - FSK/OMA/06/FX/36157 dated 15 Mar 2006 4 C Plant Installation & Piping works

9 Tanks - Maintenance, Repair, Painting and Fiberglass Treatment to Tanks 1C Tank Maintenance and Repair Work

10Pre – Qualification of Specialized Companies for Repair and Roof Replacement of Fuel Tanks at MEW Power & Water Distillation Stations

MEW Repair and Roof Replacement of Fuel Tanks at MEW Power & Water Distillation Stations

10

S.N Government Clients

1 Kuwait National Petroleum Company(KNPC)

2 Kuwait Oil Company(KOC)

3 Saudi Arabian CheveronOperations (JO)

4 Gulf Oil Company – Joint Operations (KGOC)

5 Ministry of Electricity & Water(MEW)

6 Ministry of Public Works(MPW)

7 Ministry of Interior (MOI)

8 Ministry of Defense (MOD)

9 Ministry of Energy (MOE)

10 Petroleum Industries Company (PIC),Shuaiba

11 Kuwait Aviation Fuelling Company(KAFCO)

S.N International Clients

1 US Army, Arifjan (CIRCLEX Group)

2 BTEC Turbines Corp., USA

3 SK Engineering &ConstructionCompany (SKEC),KOREA

4 TORR CANADA Inc., CANADA

5 Hyundai Engineering & ConstructionCompany, KOREA

6 FFE Minerals India Ltd., INDIA

7 Hyundai Heavy Industries Co.,KOREA

8 Larsen & Toubro Ltd.,(ECC Division), INDIA

9 Human & Technologies Corp.,KOREA

10 Metalex Construction Industry Trading Co. Inc.,Turkey

11

S.N Local Clients

1Petroleum Coke Industries

Company,

2Alghanim Gen. Trading &

Contracting

3 Kuwait Catalyst Company (KCC)

4Kuwait Lube Oil Company

(KLOC)

5 Kharafi National Company

6 Consolidated Contractors Co.

7F & K Ibrahim Al- Shuwayer &

Partners

8 Khalid Ali Al Kharafi & Bros. Co.

S.N Local Clients

9 Kuwait Refinery Maintenance Co.

10SBC General Trading &Contracting Co.

11 Gulf Spic Contracting Co .W.L.L.

12Mechanical Engineering & Const. Co. (MECC)

13SAFWAN Petroleum Technology Co. W.L.L.

14Arab Information Management Services

15 Combined Group Contracting Co.

16 Al-Julaiah Petroleum Services Co.

12

S.N Description Range /Capacity Quantity Available

1 Welding Diesel / Tig / Plasma Cutting Machines

Various Range 95

2 Compressors 200CFM ~ 825CFM 25

3 Generators 5KVA – 100KVA 324 Special Machineries Various Range 295 Blasting & Painting Equipments Various Range 1206 Insulation, Refractory Equipments Various Range 28

7 Scaffolding materials with accessories Various Range / Size

~50,000 CuMeter

8 Pre Heating Units Various 4

9 Painting Automatic Blasting M/c Electrical Automatic 1

13

S.N Description Range /Capacity Quantity Available

1 Bus Various capacity 162 Pickup Various capacity 233 Cars Various capacity 184 Hydraulic Cranes 20 Ton – 160 Ton 35 Truck Various capacity 156 Fork Lifts 3 Ton - 8 Ton 37 Bobcat S130 1

14

S. N Project Title Location Scope of work Duration Client Status

1Procurement & Construction for Mechanical Projects with Associated Civil, Electrical & Instrumentation Works - CA 3903

Mina AhmadiRefinery

Mechanical, Civil, Electrical & Instrumentation 60 Month Kuwait National Petroleum

Co.Completion Jan

2017

2 Construction of 10 Nos Tanks for AGRP Project @ MAA Refinery

KNPC MAA Tank Construction 35 Month TecnimontCompletion Feb

2016

3 Kettle Replacement & Related Works KLOC Repair & Maintenance – Machinery Equipments 1 Month KLOC Completion Nov

2015

15

S. N Project Title LocationStart / End

DateBrief Scope Duration Client

Mechanical & General Projects

1 Installation of Air Intake System & Exhaust Stack for Al-Zour GTPS - MEW/L-00410 Al-Zour

Feb-2004 Heavy Haulage, Mechanical & Structural Erection, Stack & Air Intake - Ere action and Pre commissioning Works

8 Month

Ministry of Electricity & Water / Alghanim Intl. Sep-2004

2 Replacement of fresh water pumps at pump house No:2 - CA/PD/3616

Mina Ahmadi Refinery

Aug-2005 Civil, Structural & Mechanical Erection & Related Scaffolding, Piping, Electrical, Instrumentation &

Painting works

12 Month

Kuwait National Petroleum Co. / Alghanim Int'lSep-2006

3

Erection commissioning & start-up of modifications of existing ARD off-gas compressors C-48-051 & C-88-051 -CA/PD/3631

Mina Ahmadi Refinery

Jun-2006Mechanical erection , Electrical & Instrumentation,

Structural, painting, piping19

MonthKuwait National Petroleum

CompanyFeb-2008

4EPC For Provision of Electrostatic Precipitator in Fluid Catalyst Cracking Unit (FCCU) -CA/PD/3603

Mina Ahmadi Refinery

Aug-2005 Mechanical Erection , Civil, Electrical, Instrumentation, structural, painting, insulation, scaffolding & piping

12 Month

Kuwait National Petroleum Co. / Alghanim Int'lAug-2006

5Erection and site Installation of Acid Gas Incinerator, Tail Gas Incinerator and Flare Stack at EPF Site at North Kuwait.

GC - 24Feb-2008

Heavy Haulage, Alignment & Mechanical Erection & Pre commissioning.

1 Month

SAFWAN Petroleum Technologies Co.W.L.L.

Mar-2008

6Fire Hydrant, Civil, Electrical & Structural Works At POD Village ( US Army Arifjan Camp ) - W 912d1-06-C-0019

Arifjan Camp

Jun-2006Electrical, Civil, Fire Hydrant & Structural works 1

Month Circle X Group Kuwait.Jul-2006

7 Repair & Painting of CBM Buoys & Mooring Buoys Al-Zour

Jul-2008 Mechanical Refurbishment & Structural Repair & Hyghbuild Epoxy Painting works

4 Month Saudi Arabian Chevron Inc.

Nov-2008

8LM/0045 Supply,Installation,Commissioningand one year Maintenance of Paintbooth At KNPC Sabhan Depot Painting Work shop

KNPC -Local

Marketing -SabhanDepot

Jun-2010Supply,Installation,Commissioning and one year

Maintenance of Paintbooth6

Month KNPC - Local Marketing

Dec-2010

16

S. N Project Title Location Start / End Date Brief Scope Duration Client

Mechanical & General Projects

9CS-1983 -Refurnishing of Sea water system with other Associated works at Shuaiba refinery -SHUTDOWN WORKS

KNPC -Shuaiba Refinery

Apr-2011Fabrication, Piping, Scaffolding,NDT,Glass Flake

internal coating and painting works20 Days Kuwait National Petroleum Co

May-2011

10

Installation of Markers for Flow lines, Transit lines and other facilities in South, East, North and West Kuwait field areas

KOC Field Areas

Sep-2008Site Survey,Design,Drawing,procurement &

Installation of Pipe line Markers36 Month Kuwait Oil Company

Aug-2011

11

Procurement & Construction for Mechanical Projects with Associated Civil, Electrical & Instrumentation Works - CA 3527

Mina AhmadiRefinery

Jun-2005Mechanical, Civil, Electrical & Instrumentation 72 Month Kuwait National Petroleum Co.

/Alghanim int'lOct-2011

12Additional dry slop cooler for RMP & FUP units at MAA Refinery -CA/PD-3672

Mina AhmadiRefinery

Jul-2007Additional dry slop cooler 6 Month Kuwait National Petroleum

CompanyDec-2007

13 GSEC - NLTF Demolition Package (3) KNPC MAAJul-2011 Demolition of Pipe Line, Equipment 15, Steel

Structures and Tank Insulation removal 6 Month GSEC - KOREA

Dec-2011

14 Construction of 15 MT lube oil Purification Plant KLOC

Sep-2014 Plant Piping ( Supply, Fabrication & Installation) with Electrical works at New lube oil company 6 Month KLOC

Feb-2015

17

S. N Project Title LocationStart / End

DateBrief Scope Duration Client

Tank Projects

1 Provision of Side entry Mechanical Mixtures on Tank-61-620 & Tank-61-621 - CA/PD/3638

Mina Ahmadi Refinery

May-2006 Mechanical Erection & Related Piping, Electrical, Painting & Civil works

11Month

Kuwait National Petroleum Company Apr-2007

2 Project and Construction services Tank-00 2B repairs at MGC - JO/SC 18/MP0 JO, Wafra

Jul-2003 Tank Refurbishment, Total Roof Replacement, Mechanical, Piping, Elec. & Instrumentation, Painting

5 Month Joint Operations Wafra

Jan-2004

3 Project and construction services - MGC -Tank - 07 - JO/SC-106/SC-0017/MP # 770 JO, Wafra

Aug-2005Tank Refurbishment, Mechanical, Piping & Internal &

External Painting5

Month

Joint Operations / Combined Group Co. For

Trading & Contracting W.L.L.

Dec-2005

4Engineering, Procurement & construction of 1000 Cu.m,307 Cu.m & 100 Cu.m & Tank Farm

KLOC, MAB Industrial Area

Oct-2006Mech., Civil, Elec. & Inst, Scaff., Ins. & Painting works 5

MonthKuwait Lube Oil

CompanyMar-2007

5 Design,Supply,Fabrication,Installation of 500K Gallon Water Tank

Ali Al-Salem Air Base

May-2009 Engineering Procurement & Construction - Fabrication, Erection, Testing and Commissioning of Fresh Water

Tank

6 Month

Ministry Of Defense / PRIMEONE 1 Construction.Dec-2009

6 Modification and repair work - TK-61-821 Mina AhmadiRefinery

Dec-2007 Roof Repair, Structural Apprentuces replacement, Shell replacement, Bottom repair Scaffolding, Insulation &

Painting works11

Month

Kuwait National Petroleum Co. /

Alghanim Int'lNov-2008

7 JO-LV200/MM09 - Demolition of Tanks JO WafraJun-2010

Demolition of tanks - T-02J-03 & T04 at SUG Area 6 Month KGOC - SAC : JO Wafra

Dec-2010

8 Mechanical Modification of Tank 1100, TK,12,TK06 AT MGC Wafra

JO Wafra Oct-2009 Modification, Replacement of tank internal, Shell nozzle, bottom shell plate repair, Blasting & painting of piping &

internal, Hydro test and commissioning

18 Month KGOC - JO Wafra /CGC

Mar-2011

9 Installation of 2nos of Stiffner Rings at TK-34-051 Shuaiba

Jun-2012Installation of 2nos of Stiffner Rings at TK-34-051

4 Month

Kuwait National Petroleum Company

Oct-2012

10 Construction of 2 Tanks @ KNPC KNPC MAAMar-2012

Storage Tank Works-LPG Train-4 at MAA. 15 Month Daelim –KNPC

Jun-2013

11 SAC#345 for cleaning & Desludging of Tanks1 &16 SAC

Jun-2012Mechanical & Painting Works 23 Month Bin Nowiran(SAC)

April 2014

18

S. N Project Title Location Start / End Date Brief Scope Duration Client

Piping Projects

1 Extension works of sea water pipelines to Tank nos.950 & 951 - CA/PD/3626

Mina Ahmadi Refinery

Mar-2006 Mech.,Civil, Inst., piping, painting, struct. & Scaffolding 16 Month Kuwait National Petroleum

Company Jun-2007

2Replacement of 20" dia LSFO/HFO Filling system & 16" HFO pipe line -CA/PD/3563

Mina Ahmadi Refinery

Dec-2004Mechanical and Painting 18 Month Kuwait National Petroleum

Co. /Alghanim int'lJun-2006

3Providing Individual Bank Isolation Facilities for Air Coolers at Shuaiba Refinery - CS/PD/1768

Shuaiba Refinery

Dec-2005 Mech., Piping, Civil, Elect.&Inst., Painting, Struct., Insulation, Scaff., & Tie-in works 8 Month Kuwait National Petroleum

CompanyAug-2006

4 Segregation of HP Condensate Headers from IP & LP Headers - CB/1208

Mina Abdulla Refinery

May-2006 Mech.,Piping, Painting, Inst., Insulation, Scaff., & Tie-in works 6 Month Kuwait National Petroleum

CompanyDec-2006

5 Enhanced (42 MBPD) VRSD Spiking into MAA ARDR for MAB - CA/PD/3520

Mina Ahmadi Refinery

May-2004 Mechanical, Piping, Electrical, Instrumentation & Painting 15 Month Kuwait National Petroleum

Co. / TGM GTCAug-2005

6Provision of Manpower and equipment for GC-15 stream outlet lines for KOC -KOC 21109

GC-15Mar-2004

Manpower supply for piping work 12 MonthKuwait Oil Company /

Ahmed Ghuloom Redha Ashkanani Co., W.L.L.Mar-2005

7 Eocene Upgrade project for joint operations - JO/SC19/MP03 JO, Wafra

Oct-2003Mechanical, Piping, Painting & Insulation 4 Month

Joint Operations / F & K Ibrahim Al-Shuwayer &

Partners GTCJun-2004

8 Mechanical Shut Down Works @ Various GC's

8 GC's (Burgan / Magwa)

Jun-2009 Mechanical Piping, Fabrication, Replacement of MOV & ESVD 5 Month Mushrif Construction Co.

KSCCNov-2009

9 Piping works at GC-24 GC - 24 (North Kuwait)

Nov-2008Piping Prefabrication and Welding 6 Month Gulf Spic/SKEC/KOC

Feb-2009

19

S. N Project Title Location Start / End Date Brief Scope Duration Client

Piping Projects

10 Replacement of ERW Pipes at Unit-08 /05/ 10 , Shuaiba Refinery Shuaiba Refinery

Apr-2007Mechanical Piping shutdown works 1

MonthKuwait National Petroleum

Co. / KREMENCOMay-2007

11 Replacement of ERW Pipes at Unit-7A, Shuaiba Refinery Shuaiba Refinery

Feb-2008 Fabrication, Piping, Scaffolding & Insulation works

45 Days

Kuwait National Petroleum Co. / KREMENCOMar-2008

12Mechanical Works for Utilities & Associated systems for Petroleum Coke Calcinations Plant Project, PCIC, Shuaiba

PCIC, Shuaiba Authority Area

Sep-2007Mechanical, Piping, Civil, Insulation, Painting,

Scaffolding & Structural works12

MonthHuman & Technologies

Corporation, KoreaAug-2008

13 Removal of Redundant line at MAA refinery for KOC

MAA Refinery area (KOC property)

July-2005 Draining , Gas freeing , Excavation and Removal of Redundant line and reinstatement

of earth and construction of Valve Pits.

8 Month Alganim / KOC

Mar-2006

14Piping, Pipeline, Civil and other misc. works inside MAA Refinery - NDP -KAFCO

Mina Ahmadi Refinery

Dec-2007 Underground & above Ground Piping Works & Civil Works

4 Month Larsen & Toubro Limited

Mar-2008

15Replacement of convection section tubes of Hydrogen Heaters H-02-01 &H-62-01 in SHU Refinery

Shuaiba RefineryJun-2009 Super Heated Steam Pipe and Conventional

Tube replacement, Piping & Erection, Scaffolding works

10 Month

Kuwait National Petroleum CompanyApr-2010

16Install Blinds on unused pipelines at Amm.III / New instrument Air Compressor C-901 A

PIC-ShuaibaSep-2007

Fabrication,Pipings works 1 Month

Petrochemical Industries Company – KuwaitSep-2007

17 Piping Works at SabiyaCombined Cycle Gas Turbine Project (CCGT) at SUBIYA

SABIYA - NORTH KUWAIT

Dec-2010Fabrication, Piping, Scaffolding,NDT,Works 6

MonthKuwait National Petroleum

Co. /Alghanim int'lMay-2011

18 Field Installation of A/G Piping works at ISBL area KNPC MAA

Mar-2013Field Installation of A/G Piping works 10

Month DAELIM - KNPCDec-2013

20

S. N Project Title Location Start / End Date Brief Scope Duration Client

Industrial Surface Coating & Lining / Painting & Insulation Projects

1KOC Crude Export Facilities Piping works at NPP & MS, STF Area - Internal & External Paint works, KOC

KOC North Tank Farm Area

Jan-2007 Surface preparation Internal Blasting & Painting And Application of Heat Shrinking

Sleeves & Ultra High Built Epoxy works

8 Month

Hyundai Heavy Industries Co. Ltd. / Mechanical

Engg. & Cont. Co.W.L.L.Aug-2007

2FMP Blasting and Painting of Steel Structure as per KOC Specification (3 Phases)

MAB YARDJan-2007 Surface preparation, Blasting & Painting

works 7 Month SK Engg. & Const. Co.Ltd., KuwaitJul-2007

3 Blasting & Painting External, Internal & Cut Back Spools

KOC Crude Export Facility NORTH &

SOUTH TANK FARM Area

Mar-2007Surface preparation, Blasting & Painting

works4

MonthMechanical Engg. & Cont.

Co.W.L.L., KuwaitJun-2007

4Painting works for Utilities & Associated systems for Petroleum Coke Calcinations Plant Project, PCIC, Shuaiba

PCIC, Shuaiba Authority Area

Jan-2007Painting & Civil Works 6

MonthHuman & Technologies

Corporation, KoreaJul-2007

5 Tank Painting Works

KOC Crude Export Facility North &

South Tank Farm Area

Sep-2007Surface preparation, Blasting & Painting

works for Mega Tanks: Internal and External8

MonthKuwait Oil Company /

Hyundai Heavy IndustriesMay-2008

6 Surface Preparation & Painting Works with KPPC Equate

Jul-2007 Surface preparation, Blasting & Painting works

22 Month

SBC General Trading & Contracting. Co. - KPPC,

KuwaitMay-2009

7 Painting works for structural steel GC - 11Dec-2008 Surface preparation, Blasting, Painting and

scaffolding works4

MonthSK Engg. & Const. Co.Ltd.,

KuwaitMar-2009

8 KOC-42375 - HBE Coating for Pipes KOC South, East Area

Apr-2010 Wrapping Tape removal.insitu Blasting & External Coating with HBE(Interzone

485)inside KOC South and East Kuwait

21 Month

Kuwait Oil Company /ArabiEntertech

Dec-2011

21

S. N Project Title Location Start / End Date Brief Scope Duration Client

Industrial Surface Coating & Lining / Painting & Insulation Projects

9 JOHC092FEB09-Wafra Trunk lines Replacement at JO Wafra JO Wafra

Jan-2011External Painting works in 20inch Pipe 2

MonthKGOC - JO Wafra /F&K

Ibrahim Al-Shuwayer Mar-2011

10 Blasting & Painting KOCFeb-2008

Blasting & Painting of Pipes & Spools 6 Month Metalex /KOC

Apr-2008

11 Blasting & Painting for pipe spools KOC

Mar-2007

Blasting & Painting of Pipes & Spools 5 Month National Kharafi

Jul-2007

12 Contract No :42153 - Installation of Flow line and Associated works in SEK area SEK Area -Kuwait

Jan-2010 Blasting (External & Internal) application, Internal epoxy lining & external Highbuld

epoxy

34 Month MECC / KOC

Oct-2012

13 Spool Pipes Painting of work MABSep-2012

Spool Pipes painting work 10 Month Daelim -KNPC

July-2013

14 JO-SC-214-CD-008- Project and Construction Services JO Wafra

Feb-2010 Blasting ,External & Internal Painting, wrapping and insulation

61 Month KGOC - JO Wafra /CGC

Feb-2015

15 Painting (SMP-1) Works North LPG Tank Project KNPC MAA

May-2013Painting Works 24

Month GS EngineeringApr-2015

22

S. N Project Title Location Start / End Date Brief Scope Duration Client

Industrial Insulation

1 Insulation & HVAC Ducting works at Symphony

Symphony Complex

Mar-2011Insulation and HVAC Ducting works 6 Month National Kharafi

Sep-2011

2 Piping & Equipment Insulation works KOC - FUPApr-2007

Insulation works in Piping and Equipment 5 Month National KharafiSep-2007

3 Carry out Insulation and Fire proofing Work Shuaiba Refinery

Sep-2008 Carry out Installation and Fire proofing Work 1 Month ABJ Engineering

Oct-2008

4

Installation of Aluminum Cladding Works for all insulated Ducts & Chilled water Pipes at the roof of Entertainment and Market Building

Al-Khot –Fahaheel

Jul-2004

Insulation & Cladding 4 Month The National Company

Oct-2004

5 KOC EPF 120 MBOPD KOC North Kuwait

Jun-2010 Supply and Installation of insulation,Clading and Metallic materials -

TK-310 & TK-4003 Month Processes Unlimited / KOC

Aug-2010

6 HEISCO- HFO Thermal Insulation HEISCO

May-2010

Insulation & Cladding for HFO 1 Month HEISO

Jun-2010

23

S. N Project Title Location Start / End Date Brief Scope Duration Client

Manpower Supply

1 Supply of Technical Manpower to H & TC PCIC, Shuaiba

Feb-2007Manpower supply 9

MonthHuman & Technologies

Corporation, KoreaOct-2007

2 Supply of Technical Manpower to PCIC PCIC, ShuaibaFeb-2007

Manpower supply 8 Month

Petroleum Coke Industries Company , KuwaitSep-2007

3 Supply of Certified Welders KNPC Shuaiba KNPC Shuaiba

Nov-2006Manpower supply 3

MonthKNPC Shuiba engineering

MaintenanceJan-2007

4Service & Maintenance of Electrical equipments in 6th Brigade, KOC, Abdely, North Kuwait

KOC, AbdelyDec-2004

Maintenance works 32 Month

Military Engineering Projects, Ministry of Defense, KuwaitJul-2007

5 Supply of Shutdown Crew to KOC Area KOC GC 09Feb-2008

Shutdown works to TVS Project 3 Month HEISCO

Apr-2008

6 Manpower Supply to EPC for Proves ion Of ESP in FCC Unit @ MAA Refinery CA/PD/3603

Aug-2005Specified Manpower Supply 5

Month AGITC / MAADec-2005

7 Supply of Shutdown Mechanical Crew KOC Area KOC GC 28

Feb-2009Shutdown works & Emergency Tie Ins 45

Days GulfspicMar-2009

8 Providing Services to KOC Jurassic Wells at North Kuwait KOC North Kuwait

Mar-2010Supply of Technical Manpower & Vehicles 11

Month Kuwait Oil CompanyFeb-2011

9Provision of Specialized Technical manpower for Border Security Sector, Kuwait

MOIApr-2007

Specialized Manpower supply 48 Month

Ministry of Interior (MOI), Kuwait. / AIMS.Sep-2011

10 PCIC Annual Maintenance Manpower Supply Shuaiba

May-2011 Specialized, Skilled and Semi Skilled Manpower Supply

24 Month PCIC

April-2013

24

E.mail:[email protected]  www.sksgroup.net Phone: +965 23912074 / 75    Fax: +965 23917767 P.O. Box: 46122, Fahaheel – 64012, Kuwait

25