Oracle Corporation Oracle Value Chain Planning - Planning Time Fence Profile Options Revised: 2015-05-20

description

ASCP Planning Time Fence Profiles

Transcript of VCPProfilePTF

Page 1: VCPProfilePTF

Oracle Corporation

Oracle Value Chain Planning - Planning Time Fence Profile

OptionsRevised: 2015-05-20

Page 2: VCPProfilePTF

For Oracle Internal and licensed customer use only.This report is compiled from the Profile Options Database created and maintained by theVCP Support Team and contains knowledge gathered from the Documentation, Notes,Bugs, and other internal sources. We do not guarantee this data to be without flaw andoffer no warranty to its fitness for use.

We will update and maintain this document when possible to present the best availableinformation.

(c) Oracle Corporation 2010

Page 3: VCPProfilePTF

Table of ContentsAdvanced Planning and Scheduling Profile Options......................................................................3

MRP: Firm Internal Req Transferred to OE.............................................................................4MRP: Net All Purchase Orders Prior To Requisitions.............................................................5MRP:Calculate Excess Exceptions on Time Fence................................................................6MRP:Create Time fence..........................................................................................................7MRP:Firm Planned Order Time Fence....................................................................................8MRP:Include Substitute Components.....................................................................................9MRP:Recommend action within PTF....................................................................................10MRP:Time Fence Warning....................................................................................................11MSC: Apply shortage and excess tolerance to planned orders............................................12MSC: Consume Forecast Inside Demand Time Fence.........................................................13MSC: Firm Internal Requisition Time Fence.........................................................................14MSC: Firm Intransit and PO in Receiving Supplies...............................................................15MSC: Ignore PTF during CTP...............................................................................................16MSC: MPS Auto-Firm Planned Orders.................................................................................17MSC: PS Adjust Post Horizon Demand Qty..........................................................................18MSO: Create Aggregate Supply for Unsatisfied Demands within Planning Time Fence......19MSO: Firm Requisitions Within Time Fence.........................................................................21MSO: Firm Supply Allocation Window (Backward days).......................................................22MSO: Generate Compression Days Exception.....................................................................23MSO: Lead Time Control......................................................................................................24MSO: Schedule All Firm Planned Orders First......................................................................26

Page 4: VCPProfilePTF

Advanced Planning and Scheduling Profile Options

MRP: Firm Internal Req Transferred to OE

Profile Code MRPProfile Option Name MRP_FIRM_OE_XFERRED_INTERNAL_REQDescription Valid values are:

• Yes - all internal requisitions transferred to Oracle Order Management are treated as firm supplies by Oracle Advanced Supply Chain Planning

• No - Oracle Advanced Supply Chain Planning may generate reschedule recommendations for these internal requisitions.

Rescheduled recommendations cannot be released to purchasing for internalrequisitions. To reschedule recommendations, cancel the internal requisition in the source instance and create a new requisition with the new date.

Default Value - Yes Note Reference(s)

Bug Reference(s)Document References(s) Oracle Advanced Supply Chain Planning Implementation and User's GuideDependent Profiles11.5.10 Profile Yes12.1.1 ProfileData Collections NoItem Mass Maintenance NoAdvanced Supply Chain Planning Yes

All Plan Types NoUnconstrained Plan NoConstrained – EDD No

Constrained – ECC NoDistribution Planning YesCollaborative Planning NoInventory Optimization NoService Parts Planning Yes

All Plan Types NoEnforce Constraints – Not Optimized No

Enforce Constraints – Optimized No

Disable Constraints – Not Optimized No

Disable Constraints – Optimized NoRapid Planning NoDemand Planning NoDemantra NoStrategic Network Optimization YesAdvanced Planning Command Center NoManufacturing Operations Center NoGlobal Order Promising No

Page 5: VCPProfilePTF

MRP: Net All Purchase Orders Prior To Requisitions

Profile Code MRPProfile Option Name MRP_FIRM_REQS_WITHIN_TFDescription Use this profile to specify whether or not the planning engine should net all

existing supplies prior to netting purchase requisitions.

• Yes - Net purchase orders, then net purchase requisitions. This may result in purchase requisitions with schedule dates earlier than purchase orders being canceled or rescheduled out.

• No - Net purchase orders and purchase requisitions together. Note: If the plan planning mode is Constrained (Without Detailed Scheduling), the planning engine does not use this profile option.

Default - NoNote Reference(s)

Bug Reference(s)Document References(s) Oracle Advanced Supply Chain Planning Implementation and User's GuideDependent Profiles11.5.10 Profile Yes12.1.1 ProfileData Collections NoItem Mass Maintenance NoAdvanced Supply Chain Planning Yes

All Plan Types NoUnconstrained Plan NoConstrained – EDD No

Constrained – ECC NoDistribution Planning NoCollaborative Planning NoInventory Optimization NoService Parts Planning NoRapid Planning NoDemand Planning NoDemantra NoStrategic Network Optimization NoAdvanced Planning Command Center NoManufacturing Operations Center NoGlobal Order Promising No

Page 6: VCPProfilePTF

MRP:Calculate Excess Exceptions on Time Fence

Profile Code MRPProfile Option Name MRP_CALC_EXCESS_EXCEPTDescription Indicates whether excess exceptions are calculated at the time fence or up to

the time fence• Yes: The planning engine issues exceptions only at the time

fence date. • No: The planning engine issues individual exception.

Valid values: yes/noDefault value: yes

Note Reference(s) Bug Reference(s)Document References(s)Dependent Profiles11.5.10 Profile Yes12.1.1 ProfileData Collections NoItem Mass Maintenance NoAdvanced Supply Chain Planning Yes

All Plan Types YesUnconstrained Plan NoConstrained – EDD No

Constrained – ECC NoDistribution Planning NoCollaborative Planning NoInventory Optimization NoService Parts Planning NoRapid Planning NoDemand Planning NoDemantra NoStrategic Network Optimization NoAdvanced Planning Command Center NoManufacturing Operations Center NoGlobal Order Promising No

Page 7: VCPProfilePTF

MRP:Create Time fence

Profile Code MRPProfile Option Name MRP_FIRM_ORDER_TFDescription Instructs the planning engine to create a natural time fence on firm work

orders, purchase orders, flow schedules and shipments. Valid values are:• Yes - create a natural time fence based on firm work orders,

purchase orders, flow schedules, and shipments

• No - the planning engine does not create a time fence

The planning engine honors the item attribute Planning Time Fence regardless of the value of this profile option.

Note Reference(s) 399888.1 422361.1

Bug Reference(s)Document References(s) -1

-1-1-1-1-1-1-1-1-1-1-1

Dependent Profiles11.5.10 Profile Yes12.1.1 ProfileData Collections NoItem Mass Maintenance NoAdvanced Supply Chain Planning Yes

All Plan Types NoUnconstrained Plan NoConstrained – EDD No

Constrained – ECC NoDistribution Planning NoCollaborative Planning NoInventory Optimization NoService Parts Planning NoRapid Planning NoDemand Planning NoDemantra NoStrategic Network Optimization NoAdvanced Planning Command Center NoManufacturing Operations Center NoGlobal Order Promising No

Page 8: VCPProfilePTF

MRP:Firm Planned Order Time Fence

Profile Code MRPProfile Option Name MRP_FIRM_PO_TFDescription Instructs the planning engine to create a natural time fence for an item at the

completion date of the latest firm planned order. Valid values are:• Yes - firm planned orders create a natural time fence.

• No - planning engine does not create a time fence at a firm

planned order

If the overwrite option in the plan is set to overwrite all, then all firm planned orders are deleted

Note Reference(s)

Bug Reference(s) 36420862553205

Document References(s) -1-1-1-1-1-1-1-1-1-1

Dependent Profiles11.5.10 Profile Yes12.1.1 ProfileData Collections NoItem Mass Maintenance NoAdvanced Supply Chain Planning Yes

All Plan Types NoUnconstrained Plan NoConstrained – EDD No

Constrained – ECC NoDistribution Planning NoCollaborative Planning NoInventory Optimization NoService Parts Planning NoRapid Planning NoDemand Planning NoDemantra NoStrategic Network Optimization NoAdvanced Planning Command Center NoManufacturing Operations Center NoGlobal Order Promising No

Page 9: VCPProfilePTF

MRP:Include Substitute Components

Profile Code MRPProfile Option Name MRP_ATP_SUB_COMPDescription Indicates whether to include substitute components in the Oracle Global

Order Promising calculation. Users can update at the site level. This setting is only applicable when ATP is based on Planning output.

Note Reference(s)

Bug Reference(s) 31623341555350

Document References(s) -1-1Oracle Global Order Promising Implementation and User's Guide

Dependent Profiles11.5.10 Profile Yes12.1.1 ProfileData Collections NoItem Mass Maintenance NoAdvanced Supply Chain Planning NoDistribution Planning NoCollaborative Planning NoInventory Optimization NoService Parts Planning NoRapid Planning NoDemand Planning NoDemantra NoStrategic Network Optimization NoAdvanced Planning Command Center NoManufacturing Operations Center NoGlobal Order Promising Yes

Page 10: VCPProfilePTF

MRP:Recommend action within PTF

Profile Code MRPProfile Option Name MRP_REC_ACTION_IN_PTFDescription Affects exceptions and recommendations. It instructs the planning engine, in

unconstrained plans, to generate recommendations for scheduled receipts earlier than Planning Time Fence Date.

This profile is not used for MSO (constrained planning), looks at planning time fence control.

Note Reference(s)

Bug Reference(s) 2980511Document References(s) -1

-1Dependent Profiles11.5.10 Profile Yes12.1.1 ProfileData Collections NoItem Mass Maintenance NoAdvanced Supply Chain Planning Yes

All Plan Types NoUnconstrained Plan YesConstrained – EDD No

Constrained – ECC NoDistribution Planning NoCollaborative Planning NoInventory Optimization NoService Parts Planning NoRapid Planning NoDemand Planning NoDemantra NoStrategic Network Optimization NoAdvanced Planning Command Center NoManufacturing Operations Center NoGlobal Order Promising No

Page 11: VCPProfilePTF

MRP:Time Fence Warning

Profile Code MRPProfile Option Name MRP_MPS_TIME_FENCE_WARNINGDescription Not used in Oracle Advanced Planning.Note Reference(s) Bug Reference(s)Document References(s)Dependent Profiles11.5.10 Profile Yes12.1.1 ProfileData Collections NoItem Mass Maintenance NoAdvanced Supply Chain Planning NoDistribution Planning NoCollaborative Planning NoInventory Optimization NoService Parts Planning NoRapid Planning NoDemand Planning NoDemantra NoStrategic Network Optimization NoAdvanced Planning Command Center NoManufacturing Operations Center NoGlobal Order Promising No

Page 12: VCPProfilePTF

MSC: Apply shortage and excess tolerance to planned orders

Profile Code MSCProfile Option Name MSC_APPLY_TOL_PLAN_ORDDescription Introduced in ASCP Egnine/UI rollup #33

Valid values are:

• Yes - The shortage tolerance and excess percentages are applied to all supplies including planned orders. This is the default value.

• No - The shortage tolerance and excess percentages are applied only to firm existing supplies (such as Onhand, WIP).

Introduced in ASCP Engine/UI rollup #33.

Default Value - YesNote Reference(s)

Bug Reference(s) 7461501Document References(s) -1Dependent Profiles11.5.10 Profile Yes12.1.1 ProfileData Collections NoItem Mass Maintenance NoAdvanced Supply Chain Planning Yes

All Plan Types NoUnconstrained Plan NoConstrained – EDD No

Constrained – ECC NoDistribution Planning NoCollaborative Planning NoInventory Optimization NoService Parts Planning NoRapid Planning NoDemand Planning NoDemantra NoStrategic Network Optimization NoAdvanced Planning Command Center NoManufacturing Operations Center NoGlobal Order Promising No

Page 13: VCPProfilePTF

MSC: Consume Forecast Inside Demand Time Fence

Profile Code MSCProfile Option Name MSC_CONSUME_FORECAST_DTFDescription Valid values are:

• No - demand time fence control is implemented prior to forecast consumption. Forecast entries in the demand time fence are dropped as demand statements and not used for consumption.

• Yes - forecast consumption occurs prior to enforcing demandtime fence control. The forecast entries within the demand time fence are used for consumption but not as demand. After consumption, demand quantity for all the forecast entries within the demand time fence is zero.

If you are using forecast spreading:

• For a periodic forecast entry that falls in weekly planning buckets within the demand time fence, the forecast spreading process spreads the entries into daily entries.

• If the daily entry is within the demand time fence, the processignores the value that you set and uses the value Yes in processing.

• If the daily entry is outside the demand time fence, the process ignores this profile option and consumes against theentry.

Note Reference(s) 565926.1

Bug Reference(s)Document References(s) -1Dependent Profiles11.5.10 Profile Yes12.1.1 ProfileData Collections NoItem Mass Maintenance NoAdvanced Supply Chain Planning Yes

All Plan Types NoUnconstrained Plan NoConstrained – EDD No

Constrained – ECC NoDistribution Planning NoCollaborative Planning NoInventory Optimization NoService Parts Planning NoRapid Planning NoDemand Planning NoDemantra NoStrategic Network Optimization NoAdvanced Planning Command Center NoManufacturing Operations Center NoGlobal Order Promising No

Page 14: VCPProfilePTF

MSC: Firm Internal Requisition Time Fence

Profile Code MSCProfile Option Name MSC_FIRM_PURCH_REQ_TFDescription This profile option creates a natural time fence for an item if a firm internal

requisition exists. The natural time fence is the date of the latest firm internal requisition. Valid values are:

• Yes: Use this to create a natural time fence for a firm internalrequisition.

• No: Use this if you do not want to create a natural time fence for a firm internal requisition.

Note Reference(s)

Bug Reference(s)Document References(s) Oracle Advanced Supply Chain Planning Implementation and User's GuideDependent Profiles11.5.10 Profile Yes12.1.1 ProfileData Collections NoItem Mass Maintenance NoAdvanced Supply Chain Planning Yes

All Plan Types YesUnconstrained Plan NoConstrained – EDD No

Constrained – ECC NoDistribution Planning YesCollaborative Planning NoInventory Optimization NoService Parts Planning NoRapid Planning NoDemand Planning NoDemantra NoStrategic Network Optimization NoAdvanced Planning Command Center NoManufacturing Operations Center NoGlobal Order Promising No

Page 15: VCPProfilePTF

MSC: Firm Intransit and PO in Receiving Supplies

Profile Code MSCProfile Option Name MSC_FIRM_INTRANSIT_PO_IN_RECEIVINGDescription This profile option applies to unconstrained plans only and instructs the

planning engine whether it should consider intransit and purchase order in receiving supplies as firm or it should issue reschedule recommendations for them. Valid values are:

• Yes - the planning engine considers intransit and purchase order in receiving supplies as firm.

• No - the planning engine generates reschedule recommendations for these types of supplies. Use this setting if you expedite shipments that are en route from a supplier to a receiving organization or if you want to expeditethe movement of materials in receiving to the shop floor. For example, you might offload a package from a ship at a port and then fly the package to the receiving organization.

These recommendations are informational only and cannot be released from the Planner Workbench.

This is a user level profile option.Note Reference(s)

Bug Reference(s) 4593891Document References(s) -1Dependent Profiles11.5.10 Profile Yes12.1.1 ProfileData Collections NoItem Mass Maintenance NoAdvanced Supply Chain Planning Yes

All Plan Types NoUnconstrained Plan YesConstrained – EDD No

Constrained – ECC NoDistribution Planning NoCollaborative Planning NoInventory Optimization NoService Parts Planning NoRapid Planning NoDemand Planning NoDemantra NoStrategic Network Optimization NoAdvanced Planning Command Center NoManufacturing Operations Center NoGlobal Order Promising No

Page 16: VCPProfilePTF

MSC: Ignore PTF during CTP

Profile Code MSCProfile Option Name MSC_CTP_IGNORE_PTFDescription Valid values are:

* Yes - set the Planning Time Fence to sysdate. So Planning Time Fence is not considered while doing ATP. * No

Default Value - NoIntroduced to help customers who are running UNconstrained plan and usingATP based on Planning output.

For GOP, for make order, the start date will respect Planning Time Fence . For transfer order, the ship date will respect Planning Time Fence. For buy order, the dock date will respect Planning Time Fence.This it is consistent with the constrained plan, and it is by design.However, for an unconstrained plan, due date will respect Planning Time Fence.So if GOP is done on a unconstrained plan, this could lead to confusion.

Available in 11.5.10 - Front port bug 6241549 on top of VCP 12.1.3.8 was done Jan 2014 via Patch18150049 but requires DEV Approval to apply.

Note Reference(s) 464095.1

Bug Reference(s) 61132156241549624154

Document References(s) -1-1-1-1

Dependent Profiles11.5.10 Profile Yes12.1.1 ProfileData Collections NoItem Mass Maintenance NoAdvanced Supply Chain Planning Yes

All Plan Types NoUnconstrained Plan NoConstrained – EDD No

Constrained – ECC NoDistribution Planning NoCollaborative Planning NoInventory Optimization NoService Parts Planning NoRapid Planning NoDemand Planning NoDemantra NoStrategic Network Optimization NoAdvanced Planning Command Center NoManufacturing Operations Center NoGlobal Order Promising Yes

Page 17: VCPProfilePTF

MSC: MPS Auto-Firm Planned Orders

Profile Code MSCProfile Option Name MSC_MPS_AUTO_FIRM_PODescription This profile option specifies how the planning engine deals with master

production schedule firm planned orders. You can use this profile option to specify whether or not the planning engine should treat all planned orders in the master production schedule as firm:

Valid values are:• Yes - When running batch replan using an MPS plan, all

planned orders are treated as firm without regard to planningtime fence

• No - When running batch replan, only planned orders inside the PTF are firm.

If an MPS is a demand schedule for another plan, this has no impact as planned orders from the MPSare always treated as firm.

This profile option applies only to master production schedule plans. You canset it at the site and user levels.

Note Reference(s) 259322.1

Bug Reference(s)Document References(s) -1Dependent Profiles11.5.10 Profile Yes12.1.1 ProfileData Collections NoItem Mass Maintenance NoAdvanced Supply Chain Planning Yes

All Plan Types NoUnconstrained Plan NoConstrained – EDD No

Constrained – ECC NoDistribution Planning NoCollaborative Planning NoInventory Optimization NoService Parts Planning NoRapid Planning NoDemand Planning NoDemantra NoStrategic Network Optimization NoAdvanced Planning Command Center NoManufacturing Operations Center NoGlobal Order Promising No

Page 18: VCPProfilePTF

MSC: PS Adjust Post Horizon Demand Qty

Profile Code MSCProfile Option Name MSC_SCP_PS_ADJUST_POST_HORIZON_DEM_QTYDescription MSC: PS Adjust Post Horizon Demand Qty

This profile allows PS solver to "net-out" demands that are not fulfilled until after the end of the scheduling horizon.

When profile "MSC: PS Adjust Post Horizon Demand Qty" to yes,

then PS uses the Work Orders that are on end of horizon to meet demand.

Note Reference(s) 1386168.1

Bug Reference(s) 12939774Document References(s) -1

-1Dependent Profiles11.5.10 Profile No12.1.1 ProfileData Collections NoItem Mass Maintenance NoAdvanced Supply Chain Planning Yes

All Plan Types NoUnconstrained Plan NoConstrained – EDD No

Constrained – ECC NoDistribution Planning NoCollaborative Planning NoInventory Optimization NoService Parts Planning NoRapid Planning NoDemand Planning NoDemantra NoStrategic Network Optimization NoAdvanced Planning Command Center NoManufacturing Operations Center NoGlobal Order Promising No

Page 19: VCPProfilePTF

MSO: Create Aggregate Supply for Unsatisfied Demands within Planning Time Fence

Profile Code MSOProfile Option Name MSO_AGG_SUP_FOR_DMD_IN_PTFDescription Introduced in ASCP Engine/UI rollup #33 for

11.5.10Front ported to R12 in CU5 patch 7270650Fixed in VCP Cum patch 12.1.3.1 and above

The Memory Based Planner (MBP) used to create supplies for unsatisfied demands inside PTF on respective dates after considering the FDS. Later on those supplies were moved to PTF date, resulting in more than one supply on PTF date. This would be wrong for some set up. So, we madethe code changes to create single supply for unsatisfied demands in PTF.

This is now controlled by this profile.

• Yes, then one supply is created for unsatisfied demands on the PTF date if all of the following conditions are satisfied:

• Plan is not constrained with Decision Rules

• Plan is not optimized.

• No, more than one supply may be created for unsatisfied demands on the PTF date. (Default if NULL)

Available in 12.1.3.1 and upwards

Note Reference(s)

Bug Reference(s) 7294117Document References(s) -1Dependent Profiles11.5.10 Profile Yes12.1.1 ProfileData Collections NoItem Mass Maintenance NoAdvanced Supply Chain Planning Yes

All Plan Types NoUnconstrained Plan YesConstrained – EDD No

Constrained – ECC NoDistribution Planning NoCollaborative Planning NoInventory Optimization No

Page 20: VCPProfilePTF

Service Parts Planning NoRapid Planning NoDemand Planning NoDemantra NoStrategic Network Optimization NoAdvanced Planning Command Center NoManufacturing Operations Center NoGlobal Order Promising No

Page 21: VCPProfilePTF

MSO: Firm Requisitions Within Time Fence

Profile Code MSOProfile Option Name MSO_FIRM_REQ_WITHIN_PTFDescription Indicates whether or not the planning engine should firm those requisitions

that are within the time fence. The valid values are:• Yes: Firms requisitions that are within the time fence.

• No: The planning engine does not reschedule the non-firm purchase requisitions that have dock dates within the Planning Time Fence.

The planning engine does not reschedule or cancel recommendations even ifthere are conditions for reschedules and cancellations.The planning engine uses the start date of the receiving organization as the reference for internal requisitions. Default : No

Note Reference(s) 555016.1 1079681.1 1068297.1 365112.1

Bug Reference(s) 8709703Document References(s) -1

-1-1-1-1

Dependent Profiles11.5.10 Profile Yes12.1.1 ProfileData Collections NoItem Mass Maintenance NoAdvanced Supply Chain Planning Yes

All Plan Types YesUnconstrained Plan NoConstrained – EDD No

Constrained – ECC NoDistribution Planning NoCollaborative Planning NoInventory Optimization NoService Parts Planning Yes

All Plan Types NoEnforce Constraints – Not Optimized No

Enforce Constraints – Optimized No

Disable Constraints – Not Optimized No

Disable Constraints – Optimized NoRapid Planning NoDemand Planning NoDemantra NoStrategic Network Optimization NoAdvanced Planning Command Center NoManufacturing Operations Center NoGlobal Order Promising No

Page 22: VCPProfilePTF

MSO: Firm Supply Allocation Window (Backward days)

Profile Code MSOProfile Option Name MSO_FIRM_SUPPLY_ALLOC_WINDescription The allocation of firm supplies to demands is based on demand priorities

within the Firm Supply Allocation window. Set this window using system level profile options. This window is derived dynamically for each demand; it starts with the demand due date and goes backwards to the window size. This is stated as the number of calendar days including non-workdays. Validvalues are:

• Integer > 0

Default Value - 1Note Reference(s)

Bug Reference(s) 4688250Document References(s) -1

Oracle Advanced Supply Chain Planning Implementation and User's GuideDependent Profiles11.5.10 Profile Yes12.1.1 ProfileData Collections NoItem Mass Maintenance NoAdvanced Supply Chain Planning Yes

All Plan Types NoUnconstrained Plan NoConstrained – EDD Yes

Constrained – ECC YesDistribution Planning NoCollaborative Planning NoInventory Optimization NoService Parts Planning NoRapid Planning NoDemand Planning NoDemantra NoStrategic Network Optimization NoAdvanced Planning Command Center NoManufacturing Operations Center NoGlobal Order Promising No

Page 23: VCPProfilePTF

MSO: Generate Compression Days Exception

Profile Code MSOProfile Option Name MSO_GENERATE_COMPRESSION_EXCEPTIONDescription Use this profile option to control issuance of exception message Orders with

compression days. Valid values are:

• Yes - Issue the exception message • No - Do not issue the exception message

The planning engine issues exception message Orders with insufficient lead-time when it schedules orders for less time than their assembly's lead-time. If the reason for that scheduling is that the planning engine would schedule the order in the past, it also issues exception message Orders with compression days.

To avoid seeing both these exceptions for the same order, select No for this profile option.

Note Reference(s)

Bug Reference(s)Document References(s) Oracle Advanced Supply Chain Planning Implementation and User's GuideDependent Profiles11.5.10 Profile Yes12.1.1 ProfileData Collections NoItem Mass Maintenance NoAdvanced Supply Chain Planning Yes

All Plan Types NoUnconstrained Plan NoConstrained – EDD No

Constrained – ECC NoDistribution Planning NoCollaborative Planning NoInventory Optimization NoService Parts Planning NoRapid Planning NoDemand Planning NoDemantra NoStrategic Network Optimization NoAdvanced Planning Command Center NoManufacturing Operations Center NoGlobal Order Promising No

Page 24: VCPProfilePTF

MSO: Lead Time Control

Profile Code MSOProfile Option Name MSO_LEAD_TIME_CONTROLDescription Violate Minimum Processing Times to Meet

Demand Due Date: The planning engine meets the demand due date even if it compresses operations and supplies beyond their minimum durations (from item lead-times and routing usages). -- This setting can violate the Planning Time Fence settings for an item. -- It can also violate a Natural Time Fence created by using profile MRP: Create Time Fence = Yes

Do Not Violate Minimum Processing Times: Theplanning engine respects the minimum durations ofoperations and supplies (from item lead-times and routing usages) even if it satisfies demands late.

Default Value: Violate minimum Processing Times to Meet Demand Due Date

This, sometimes, used with plan option - Enforce Purchasing Lead-times Constraint and can change planning engine behavior.

In 11.5.10, this profile is only for EDD - Enforce Demand Due Dates plan

In 12.0.4 and above, this profile works for BOTH EDD and ECC - Enforce Capacity Constraints plans.

Note Reference(s) 399888.1 850591.1 443357.1

Bug Reference(s)Document References(s) -1

-1-1Oracle Advanced Supply Chain Planning Implementation and User's Guide

Dependent Profiles11.5.10 Profile Yes12.1.1 ProfileData Collections NoItem Mass Maintenance NoAdvanced Supply Chain Planning Yes

Page 25: VCPProfilePTF

All Plan Types NoUnconstrained Plan NoConstrained – EDD Yes

Constrained – ECC YesDistribution Planning NoCollaborative Planning NoInventory Optimization NoService Parts Planning NoRapid Planning NoDemand Planning NoDemantra NoStrategic Network Optimization NoAdvanced Planning Command Center NoManufacturing Operations Center NoGlobal Order Promising No

Page 26: VCPProfilePTF

MSO: Schedule All Firm Planned Orders First

Profile Code MSOProfile Option Name MSO_SCHEDULE_FIRM_PLANNED_ORDERS_FIRSTDescription Determines if Firm Planned Orders are to be scheduled first before other

supplies. This can work in tandem with other Firm profiles to create a NaturalTime fence.

Valid values: Yes/No Default value: No

Note Reference(s) Bug Reference(s)Document References(s)Dependent Profiles11.5.10 Profile No12.1.1 ProfileData Collections NoItem Mass Maintenance NoAdvanced Supply Chain Planning Yes

All Plan Types YesUnconstrained Plan YesConstrained – EDD Yes

Constrained – ECC YesDistribution Planning NoCollaborative Planning NoInventory Optimization NoService Parts Planning NoRapid Planning NoDemand Planning NoDemantra NoStrategic Network Optimization NoAdvanced Planning Command Center NoManufacturing Operations Center NoGlobal Order Promising No